JP2928903B2 - Embankment retaining wall - Google Patents

Embankment retaining wall

Info

Publication number
JP2928903B2
JP2928903B2 JP23962193A JP23962193A JP2928903B2 JP 2928903 B2 JP2928903 B2 JP 2928903B2 JP 23962193 A JP23962193 A JP 23962193A JP 23962193 A JP23962193 A JP 23962193A JP 2928903 B2 JP2928903 B2 JP 2928903B2
Authority
JP
Japan
Prior art keywords
embankment
wall
steel
reinforcing material
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP23962193A
Other languages
Japanese (ja)
Other versions
JPH0790863A (en
Inventor
洋司 菊地
光俊 尾形
文 平田
忠夫 川原
勝 岡山
幸司 杉山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NIPPON KONKURIITO KOGYO KK
NITSUTOKU KENSETSU KK
Original Assignee
NIPPON KONKURIITO KOGYO KK
NITSUTOKU KENSETSU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NIPPON KONKURIITO KOGYO KK, NITSUTOKU KENSETSU KK filed Critical NIPPON KONKURIITO KOGYO KK
Priority to JP23962193A priority Critical patent/JP2928903B2/en
Publication of JPH0790863A publication Critical patent/JPH0790863A/en
Application granted granted Critical
Publication of JP2928903B2 publication Critical patent/JP2928903B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Retaining Walls (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、急勾配の斜面において
道路築造や宅地造成などで、必要とする用地の確保や地
滑り地における地滑りを抑止するための補強土としての
盛土用土留壁に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an embankment for embankment as a reinforcing soil for securing necessary land and suppressing landslides on landslides, for example, in road construction and residential land development on steep slopes. It is.

【0002】[0002]

【従来の技術】急勾配の斜面において道路築造や宅地造
成などで必要とする用地の確保をなす補強土(土留構造
物)としては、従来、図10に示すように基礎地盤1上に
コンクリート基礎2を設け、このコンクリート基礎2に
コンクリートパネルでの壁体3を積み重ね、この壁体3
の裏側に盛土4を施すのに該盛土4内に盛土内補強材5
を配設するようにしている。図示の例は急峻地形におけ
る通路拡幅の場合で、αは既道路幅員、βは新道路幅員
である。図中6は切土のり面、7は施工前ののり面、8
は表層土である。
2. Description of the Related Art Conventionally, as a reinforcing soil (earth retaining structure) for securing land required for road construction or residential land development on a steep slope, as shown in FIG. 2 is provided, and a wall 3 of concrete panel is stacked on the concrete foundation 2, and the wall 3
The embankment 4 is applied to the back side of the embankment.
Is arranged. The illustrated example is a case of widening a passage on a steep terrain, where α is the width of an existing road and β is the width of a new road. In the figure, 6 is a cut slope, 7 is a slope before construction, 8
Is surface soil.

【0003】この図10に示す補強土の場合、盛土4内の
補強材5の長さは最小でも 5.0m程度は必要となるの
で、急峻な地形では山側への切土が必要である。そし
て、この切土によって新たな切土のり面6ができ、その
保護が必要となる。また、既設道路幅員αをさらに狭く
することになり、場合によっては工事期間中、通路を使
用することができなくなる。これでは、一般車両の不通
とともに壁体3の設置作業を行うクレーン車の乗入れが
不可能となり、施工に支障をきたす。
In the case of the reinforced soil shown in FIG. 10, the length of the reinforcing material 5 in the embankment 4 is required to be at least about 5.0 m. Therefore, in a steep terrain, it is necessary to cut the mountain side. Then, a new cut slope 6 is formed by this cut, and its protection is required. Further, the existing road width α is further reduced, and in some cases, the passage cannot be used during the construction period. This makes it impossible for a general vehicle to be blocked and a crane truck for performing the installation work of the wall 3 to enter, thereby hindering construction.

【0004】また、壁体3は不連続なコンクリートパネ
ルのために、使用した盛土の経時沈下や変形によって積
み重ねた壁体3の倒れやはらみ出しが発生することがあ
り、工事中から工事後も壁体3の垂直性の確保が難し
い。
Further, since the wall 3 is a discontinuous concrete panel, the stacked wall 3 may fall or protrude due to the sedimentation or deformation of the used embankment with time, and the wall 3 may be used during and after construction. It is difficult to secure the verticality of the wall 3.

【0005】基礎地盤1は、軟岩以上の安定した地盤が
必要であるので基礎地盤1が深い場合には大きな掘削が
必要であり、斜面上の基礎は上載した荷重によって崩壊
する危険が多い。
[0005] The foundation ground 1 needs a stable ground more than soft rock, so when the foundation ground 1 is deep, a large excavation is required, and the foundation on the slope has a high risk of collapse due to the loaded load.

【0006】これに対して、特公平4-2733号公報の補強
土用壁面構造には図11、図12に示すように基礎地盤1を
掘孔し、根入してH鋼による杭9を適宜間隔で立設し、
コンクリートパネルによる壁体3は両端に係合溝10を形
成し、これをH鋼による杭9の前側フランジに係合させ
て、杭9間に壁体3を嵌込むようにしている。
On the other hand, as shown in FIGS. 11 and 12, the foundation ground 1 is dug into the wall surface structure for reinforcing soil disclosed in Japanese Patent Publication No. Stand at appropriate intervals,
The wall 3 made of a concrete panel has engagement grooves 10 formed at both ends, and these are engaged with front flanges of the pile 9 made of H steel so that the wall 3 is fitted between the piles 9.

【0007】また、盛土内補強材5はこれは棒鋼や帯鋼
からなるが、一端が杭9間に上下に移動自在に嵌め込ま
れた係合杆11に連結した。
[0007] The reinforcing material 5 in the embankment is made of bar steel or strip steel, and has one end connected to an engaging rod 11 fitted between the piles 9 so as to be vertically movable.

【0008】この特公平4-2733号公報の補強土用壁面構
造によれば、壁体3は杭9による支持が得られるので、
盛土内補強材5の長さも短くでき、また、コンクリート
パネルである壁体3も連続性のあるものとなって倒れや
はらみ出しの発生が防止でき、垂直性も確保できる。
[0008] According to the wall structure for reinforced soil disclosed in Japanese Patent Publication No. 4-2733, the wall 3 can be supported by the pile 9,
The length of the reinforcing material 5 in the embankment can be shortened, and the wall 3 which is a concrete panel has continuity, so that it can be prevented from falling down or protruding and verticality can be secured.

【0009】[0009]

【発明が解決しようとする課題】しかし、前記特公平4-
2733号公報の補強土用壁面構造は壁体3と盛土内補強材
5との結合は杭9を介して行われるものであり、杭9と
コンクリートパネルである壁体3と盛土内補強材5がそ
れぞれ一体化していない。
[Problems to be Solved by the Invention]
In the wall structure for reinforced soil disclosed in Japanese Patent No. 2733, the connection between the wall 3 and the reinforcing material 5 in the embankment is performed via a pile 9, and the pile 9, the wall 3, which is a concrete panel, and the reinforcing material 5 in the embankment Are not integrated.

【0010】さらに、H鋼による杭9は盛土材中にあ
り、腐食し易く、この杭9が腐食すると盛土内補強材5
の支持にも悪影響がでる。
Furthermore, the pile 9 made of H steel is in the embankment material and is easily corroded.
Support is also adversely affected.

【0011】本発明は前記従来例の不都合を解消し、壁
体とこれを支持する杭と盛土内補強材とが一体化して土
圧等を有効に杭や盛土内補強材に伝達することができる
とともに、鋼材による杭の錆を防止でき、しかも、施工
中における盛土転圧の沈下に盛土内補強材を追従させて
応力の集中も防止できる盛土用土留壁を提供することに
ある。
The present invention solves the inconvenience of the prior art, and the wall, the pile supporting the wall and the reinforcing material in the embankment are integrated to effectively transmit the earth pressure and the like to the pile and the reinforcing material in the embankment. An object of the present invention is to provide an embankment embankment wall capable of preventing the pile from being rusted by a steel material, and capable of preventing the concentration of stress by making the reinforcing material in the embankment follow the collapse of the embankment rolling pressure during construction.

【0012】[0012]

【課題を解決するための手段】本発明は前記目的を達成
するため、地盤上に積み重ねた壁体を所定間隔で立設し
た杭で固定し、また、この壁体裏側の盛土内に配設する
盛土内補強材で該壁体を支持する盛土用土留壁におい
て、壁体には杭を挿通する孔を形成して杭に壁体を挿入
して積み重ねてからこの孔内に間詰めモルタルを充填し
て固定し、また、壁体の接続端面に形成した切欠部同士
を組合わせて狭間、およびこの狭間から外方へ連通する
スリットを形成し、この狭間内に前記盛土内補強材の膨
大端部を差し入れ、前記スリットを介してこの盛土内補
強材を壁体に対して上下動自在に配設したこと、およ
び、狭間内に間詰めモルタルを充填して、盛土内補強材
の膨大端部を固定すること、さらに、盛土内補強材は、
鋼棒や帯鋼などの鋼材であること、もしくは、膨大端部
と反対側に鋼管を横向きに設け、この鋼管に鋼材を芯材
として配設したモルタル充填の袋体を挿通させ、該鋼管
間でこの袋体に敷設ネットの一端を巻回して結合させた
ことを要旨とするものである。
According to the present invention, in order to achieve the above object, the walls stacked on the ground are fixed by piles erected at predetermined intervals, and are disposed in the embankment on the back side of the wall. In the embankment retaining wall for supporting the wall with a reinforcing material in the embankment, a hole for inserting a pile is formed in the wall, the wall is inserted into the pile, and the mortar is filled in the hole. It is filled and fixed, and a slit is formed by combining notches formed in the connection end face of the wall with each other, and a slit communicating from the gap to the outside is formed. Inserting the end portion, the reinforcing material in the embankment is disposed so as to be movable up and down with respect to the wall through the slit, and filling the mortar in the narrow space, the enormous end of the reinforcing material in the embankment Fixing the part, furthermore, the reinforcing material in the embankment,
A steel material such as a steel rod or a steel strip, or a steel tube is provided sideways on the side opposite to the enlarged end, and a mortar-filled bag provided with the steel material as a core material is inserted through the steel tube, and The gist of the invention is that one end of the laying net is wound around the bag body and joined.

【0013】[0013]

【作用】請求項1記載の本発明によれば、杭と壁体は間
詰めモルタルを介して一体化しており、土圧等を有効に
杭や盛土内補強材に伝達することができるとともに、倒
れや局部変形がしにくく、垂直度が管理しやすい。
According to the first aspect of the present invention, the pile and the wall are integrated via the filling mortar, so that earth pressure and the like can be effectively transmitted to the pile and the reinforcing material in the embankment. It is hard to fall and local deformation, and the verticality is easy to manage.

【0014】さらに、杭に鋼材を使用してもこれが間詰
めモルタル内に埋設されるので錆等の発生はなく、ま
た、盛土内補強材はその膨大端部が壁体間の狭間に設置
し、施工当初はこの狭間の長手方向に沿ってスリットを
介してスライドでき、盛土転圧によって圧密度の最も大
きい初期沈下に追従でき転圧が均等に行われる。
Further, even if a steel material is used for the pile, it is buried in the filling mortar, so that no rust or the like is generated. At the beginning of construction, it is possible to slide through the slit along the longitudinal direction of the narrow space, and to follow the initial settlement with the highest compaction density by the embankment rolling, so that the rolling can be performed uniformly.

【0015】請求項2記載の本発明によれば、さらに、
天端まで転圧完了後は前記狭間である孔内を間詰めモル
タルを充填してこの盛土内補強材の膨大端部を固定する
ことができる。
According to the second aspect of the present invention,
After the completion of the rolling to the top end, the inside of the narrow hole is filled with mortar and the expanded end portion of the reinforcing material in the embankment can be fixed.

【0016】請求項3記載の本発明によれば、前記作用
に加えて、工費が安価で、地盤に対する追随性のよい盛
土内補強材とすることができる。
According to the third aspect of the present invention, in addition to the above-mentioned effects, a reinforcing material in the embankment which is inexpensive and has good followability to the ground can be obtained.

【0017】[0017]

【実施例】以下、図面について本発明の実施例を詳細に
説明する。図1は本発明の盛土用土留壁の第1実施例を
示す平面図、図2は同上縦断側面図で、前記従来例を示
す図10〜図12と同一構成要素には同一参照符号を付した
ものである。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 is a plan view showing a first embodiment of an embankment retaining wall for embankment of the present invention, and FIG. 2 is a vertical sectional side view of the same, and the same components as those of FIGS. It was done.

【0018】図中3はコンクリートパネルである壁体で
あるが、中央部に上下方向にH鋼等の鋼材による杭9が
挿通する孔12を形成し、また、接続端面にこれら壁体3
相互が組み合わさった時に狭間14をなす切欠部13を形成
した。
In the figure, reference numeral 3 denotes a wall which is a concrete panel. A hole 12 through which a pile 9 made of a steel material such as H-steel is inserted is formed in a central portion in a vertical direction.
When combined with each other, a notch 13 forming a gap 14 was formed.

【0019】図7〜図9はこの壁体3の例を示すもので
あるが、図7、図8に示すように孔12は側方開口面を蓋
板15で閉塞して形成するようにしたものや、図9に示す
ように一対の2つ割りのパネルの組合せからなり、相互
に埋め込みインサート16で結合するようにしてもよい。
FIGS. 7 to 9 show an example of the wall body 3. As shown in FIGS. 7 and 8, the hole 12 is formed by closing the side opening surface with the cover plate 15. As shown in FIG. 9 or a combination of a pair of halved panels as shown in FIG.

【0020】前記杭9は基礎地盤1を掘孔し、根入して
適宜間隔で立設する。そして、前記壁体3をその孔12に
この杭9を挿通するように地盤1上に積み重ねる。その
際、該杭9は孔12の中心に位置するように調整し、孔12
内に間詰めコンクリートモルタル17を充填して固定す
る。
The piles 9 are formed by digging holes in the foundation ground 1 and piercing the foundations 1 at appropriate intervals. Then, the wall body 3 is stacked on the ground 1 so that the pile 9 is inserted into the hole 12. At this time, the pile 9 is adjusted so as to be located at the center of the hole 12, and the hole 12 is adjusted.
The inside is filled with fixed concrete mortar 17 and fixed.

【0021】このようにして1段もしくは所定段壁体3
を積み重ねたなら、壁体3の内側に盛土4を施し、ま
た、壁体3の接続端面に形成されている切欠部13同士で
狭間14が形成され、さらに、壁体3の接続端同士でこの
狭間14から外方へ連通するスリット25が形成されるの
で、この狭間14内にその上方開口から盛土内補強材5の
膨大端部18を差し入れ、スリット25を介してこの盛土内
補強材5を外側に導き、そのまま下降させて盛土4に配
設する。
In this manner, the one-step or predetermined-step wall 3
Are piled up, the embankment 4 is applied to the inside of the wall 3, a gap 14 is formed between the notches 13 formed on the connection end faces of the wall 3, and furthermore, the connection ends of the wall 3 are connected with each other. Since a slit 25 communicating outward from the gap 14 is formed, the enlarged end portion 18 of the reinforcing material 5 in the embankment is inserted into the gap 14 from its upper opening, and the reinforcing material 5 in the embankment is inserted through the slit 25. To the outside, lower it as it is, and place it on the embankment 4.

【0022】前記杭9にはH鋼の他に鋼管や鉄筋カゴの
利用も考えられる。また、盛土内補強材5には支圧プレ
ート付鉄筋、波形プレート、グリット鉄筋などの鋼棒や
帯鋼などの鋼材によるスプリットバーもしくはネットな
どの使用が考えられるが、前記膨大端部18は湾曲板など
による定着板体を取り付けて膨大部として、狭間14から
抜け出ないようにしておく。
The pile 9 may be made of a steel pipe or a steel cage in addition to the H steel. The reinforcing material 5 in the embankment may be a reinforcing bar with a supporting plate, a corrugated plate, a steel bar such as a grit reinforcing bar, or a split bar or a net made of a steel material such as a strip steel. A fixing plate body made of a plate or the like is attached to form a huge portion so that the fixing plate body does not fall out of the narrow space 14.

【0023】このようにした壁体3の積み上げ、盛土4
の配設、および盛土内補強材5の設置を適宜繰り返す
が、施工当初は盛土内補強材5はその膨大端部18が狭間
14内をスライドでき、盛土転圧によって圧密度の最も大
きい初期沈下に追従できるので、転圧が均等に行われ
る。
The stacking of the walls 3 and the embankment 4
Of the embankment and the installation of the reinforcing material 5 in the embankment are repeated as appropriate, but at the beginning of the construction, the reinforcing material 5 in the embankment
14 can be slid and the embankment can follow the initial settlement with the highest compaction density by the compaction, so that compaction is performed evenly.

【0024】天端まで転圧完了後は、狭間14にも間詰め
コンクリートモルタル17を充填して膨大端部18を固定す
る。
After the rolling is completed to the top end, the narrow space 14 is filled with the filling concrete mortar 17 and the enlarged end portion 18 is fixed.

【0025】なお、杭9の根入れについては、地山掘孔
を行わずに図3に示すように基礎地盤1上にコンクリー
ト基礎2を設け、これに行うようにしてもよい。
The pile 9 may be inserted into the concrete foundation 2 on the foundation ground 1 as shown in FIG.

【0026】図4〜図6は本発明の第2実施例を示すも
ので、盛土内補強材5は敷設ネット24を利用するもので
あり、その係止部材20としては膨大端部18と反対側に鋼
管19を横向きに設けたものとする。
FIGS. 4 to 6 show a second embodiment of the present invention. The reinforcing material 5 in the embankment uses a laying net 24, and its locking member 20 is opposite to the enlarged end portion 18. FIG. It is assumed that a steel pipe 19 is provided sideways on the side.

【0027】この鋼管19に、鉄筋、PC鋼より線などの
鋼材を芯材21として配設し、かつ、モルタル22を内部に
充填した布袋23を挿通させ、さらに、この布袋23の外周
で前記鋼管19間には敷設ネット24の一端を巻回して結合
させた。
A steel material such as a reinforcing steel bar or a PC steel wire is disposed as a core material 21 in the steel pipe 19, and a cloth bag 23 filled with a mortar 22 is inserted through the steel tube 19. One end of the laying net 24 was wound and connected between the steel pipes 19.

【0028】このように盛土内補強材5を敷設ネット24
を主体のものとすることにより、盛土4との結合性を広
範囲で確保でき、しかも、連結杆的な部材としてモルタ
ル22詰めの布袋23を土嚢のようなものとして利用できる
ので、これも盛土4と馴染み、盛土転圧によって圧密度
の最も大きい初期沈下に追従できる。
The reinforcing material 5 in the embankment is laid on the net 24
Is mainly used, the bonding property with the embankment 4 can be ensured in a wide range, and the cloth bag 23 filled with the mortar 22 can be used as a connecting rod-like member as a sandbag. It is possible to follow the initial settlement with the highest compaction density by embankment compaction.

【0029】[0029]

【発明の効果】以上述べたように本発明の盛土用土留壁
は、壁体とこれを支持する杭と盛土内補強材とが一体化
して土圧等を有効に杭や盛土内補強材に伝達することが
できるとともに、鋼材による杭の錆を防止でき、しか
も、施工中における盛土転圧の沈下に盛土内補強材を追
従させて応力の集中も防止できるものである。
As described above, the embankment retaining wall for embankment of the present invention integrates a wall body, a pile supporting the same, and a reinforcing material in the embankment so that the earth pressure and the like can be effectively used as a reinforcing material in the pile and the embankment. In addition to the transmission, the pile can be prevented from rusting due to the steel material, and the concentration of stress can be prevented by making the reinforcing material in the embankment follow the settlement of the embankment rolling pressure during construction.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の盛土用土留壁の第1実施例を示す平面
図である。
FIG. 1 is a plan view showing a first embodiment of an embankment retaining wall according to the present invention.

【図2】本発明の盛土用土留壁の第1実施例を示す縦断
側面図である。
FIG. 2 is a longitudinal sectional side view showing a first embodiment of an embankment retaining wall according to the present invention.

【図3】本発明の盛土用土留壁の第1実施例の応用例を
示す縦断側面図である。
FIG. 3 is a longitudinal sectional side view showing an application example of the first embodiment of the embankment retaining wall of the present invention.

【図4】本発明の盛土用土留壁の第2実施例を示す平面
図である。
FIG. 4 is a plan view showing a second embodiment of the embankment retaining wall of the present invention.

【図5】図4のA−A線断面図である。FIG. 5 is a sectional view taken along line AA of FIG. 4;

【図6】図4のB−B線断面図である。FIG. 6 is a sectional view taken along line BB of FIG. 4;

【図7】壁体の第1例を示す平面図である。FIG. 7 is a plan view showing a first example of a wall body.

【図8】壁体の第2例を示す平面図である。FIG. 8 is a plan view showing a second example of the wall body.

【図9】壁体の第3例を示す平面図である。FIG. 9 is a plan view showing a third example of the wall body.

【図10】従来例を示す縦断側面図である。FIG. 10 is a vertical sectional side view showing a conventional example.

【図11】他の従来例を示す横断平面図である。FIG. 11 is a cross-sectional plan view showing another conventional example.

【図12】他の従来例を示す縦断側面図である。FIG. 12 is a vertical sectional side view showing another conventional example.

【符号の説明】[Explanation of symbols]

1…基礎地盤 2…コンクリー
ト基礎 3…壁体 4…盛土 5…盛土内補強材 6…切土のり面 7…施工前ののり面 8…表層土 9…杭 10…係合溝 11…係合杆 12…孔 13…切欠部 14…狭間 15…蓋板 16…埋め込みイ
ンサート 17…間詰めコンクリートモルタル 18…膨大端部 19…鋼管 20…係止部材 21…芯材 22…モルタル 23…布袋 24…敷設ネット 25…スリット
DESCRIPTION OF SYMBOLS 1 ... Foundation ground 2 ... Concrete foundation 3 ... Wall 4 ... Embankment 5 ... Reinforcement material in embankment 6 ... Cut slope 7 ... Slope before construction 8 ... Surface soil 9 ... Pile 10 ... Engagement groove 11 ... Engagement Rod 12 ... Hole 13 ... Notch 14 ... Narrow 15 ... Cover plate 16 ... Embedded insert 17 ... Filled concrete mortar 18 ... Extended end 19 ... Steel pipe 20 ... Locking member 21 ... Core material 22 ... Mortar 23 ... Clothing bag 24 ... Laying net 25 ... Slit

───────────────────────────────────────────────────── フロントページの続き (72)発明者 平田 文 東京都中央区銀座8丁目14番14号 日特 建設株式会社内 (72)発明者 川原 忠夫 東京都港区新橋1丁目8番3号 日本コ ンクリート工業株式会社内 (72)発明者 岡山 勝 東京都港区新橋1丁目8番3号 日本コ ンクリート工業株式会社内 (72)発明者 杉山 幸司 東京都港区新橋1丁目8番3号 日本コ ンクリート工業株式会社内 (56)参考文献 特開 平7−90865(JP,A) 特開 平4−254614(JP,A) 特開 平5−295748(JP,A) 特開 平2−213523(JP,A) 特公 平4−49607(JP,B2) 特公 平4−9889(JP,B2) (58)調査した分野(Int.Cl.6,DB名) E02D 29/02 303 E02D 17/18 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Fumi Hirata, Inventor Nippon Construction Co., Ltd. 8-14-14 Ginza, Chuo-ku, Tokyo (72) Tadao Kawahara 1-8-3, Shimbashi, Minato-ku, Tokyo Japan Inside Concrete Industry Co., Ltd. (72) Inventor Masaru Okayama 1-8-3 Shimbashi, Minato-ku, Tokyo Japan Inside Concrete Industry Co., Ltd. (72) Koji Sugiyama 1-8-3 Shimbashi, Minato-ku, Tokyo Japan (56) References JP-A-7-90865 (JP, A) JP-A-4-254614 (JP, A) JP-A-5-295748 (JP, A) JP-A-2-213523 (JP, A) JP 4-49607 (JP, B2) JP 4-9889 (JP, B2) (58) Fields investigated (Int. Cl. 6 , DB name) E02D 29/02 303 E02D 17 / 18

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 地盤上に積み重ねた壁体を所定間隔で立
設した杭で固定し、また、この壁体裏側の盛土内に配設
する盛土内補強材で該壁体を支持する盛土用土留壁にお
いて、壁体には杭を挿通する孔を形成して杭に壁体を挿
入して積み重ねてからこの孔内に間詰めモルタルを充填
して固定し、また、壁体の接続端面に形成した切欠部同
士を組合わせて狭間、およびこの狭間から外方へ連通す
るスリットを形成し、この狭間内に前記盛土内補強材の
膨大端部を差し入れ、前記スリットを介してこの盛土内
補強材を壁体に対して上下動自在に配設したことを特徴
とする盛土用土留壁。
1. An embankment for fixing a wall stacked on the ground with piles erected at predetermined intervals and supporting the wall with a reinforcing material in the embankment disposed in the embankment on the back side of the wall. In the earth retaining wall, a hole is formed in the wall body through which the pile is inserted, the wall body is inserted into the pile, the pile is stacked, and then the filling mortar is filled in the hole and fixed, and the connection end face of the wall body is formed. The cutouts thus formed are combined with each other to form a gap, and a slit communicating with the gap outwardly. A huge end portion of the reinforcing material in the embankment is inserted into the gap, and the reinforcing in the embankment is performed through the slit. An earth retaining wall for embankment, in which a material is disposed vertically movable with respect to a wall body.
【請求項2】 狭間内に間詰めモルタルを充填して、盛
土内補強材の膨大端部を固定する請求項1記載の盛土用
土留壁。
2. The embankment retaining wall according to claim 1, wherein the narrowing mortar is filled in the narrow space to fix the enlarged end portion of the reinforcing material in the embankment.
【請求項3】 盛土内補強材は、鋼棒や帯鋼などの鋼材
である請求項1記載の盛土用土留壁。
3. The embankment retaining wall according to claim 1, wherein the reinforcing material in the embankment is a steel material such as a steel bar or a steel strip.
【請求項4】 盛土内補強材は、膨大端部と反対側に鋼
管を横向きに設け、この鋼管に鋼材を芯材として配設し
たモルタル充填の袋体を挿通させ、該鋼管間でこの袋体
に敷設ネットの一端を巻回して結合させた請求項1記載
の盛土用土留壁。
4. The reinforcing material in the embankment is provided with a steel pipe provided sideways on the side opposite to the enormous end, and a mortar-filled bag provided with steel as a core material is inserted through the steel pipe, and the bag is inserted between the steel pipes. The earth retaining wall for embankment according to claim 1, wherein one end of the laying net is wound around and joined to the body.
JP23962193A 1993-09-27 1993-09-27 Embankment retaining wall Expired - Lifetime JP2928903B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP23962193A JP2928903B2 (en) 1993-09-27 1993-09-27 Embankment retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP23962193A JP2928903B2 (en) 1993-09-27 1993-09-27 Embankment retaining wall

Publications (2)

Publication Number Publication Date
JPH0790863A JPH0790863A (en) 1995-04-04
JP2928903B2 true JP2928903B2 (en) 1999-08-03

Family

ID=17047459

Family Applications (1)

Application Number Title Priority Date Filing Date
JP23962193A Expired - Lifetime JP2928903B2 (en) 1993-09-27 1993-09-27 Embankment retaining wall

Country Status (1)

Country Link
JP (1) JP2928903B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6318934B1 (en) * 1999-06-24 2001-11-20 Anchor Wall Systems, Inc. Segmental retaining wall system
WO2002038872A1 (en) * 2000-11-08 2002-05-16 Jeung Su Lee Placementing method of reinforcing strips for constructing precast concrete facing panel and pulling-up device of reinforcing strips
JP4684953B2 (en) * 2006-06-19 2011-05-18 財団法人鉄道総合技術研究所 Embankment reinforcement structure
CN109183811B (en) * 2018-10-27 2020-10-23 江苏中煤地质工程研究院有限公司 Deformation-resistant foundation pit supporting structure and construction method thereof

Also Published As

Publication number Publication date
JPH0790863A (en) 1995-04-04

Similar Documents

Publication Publication Date Title
US6371699B1 (en) Anchored retaining wall system
JPH1150457A (en) Earth retaining construction used for earth anchor
JPH111926A (en) Countermeasure against liquefaction of embankment structure
JP2928903B2 (en) Embankment retaining wall
KR102490872B1 (en) Reinforced earth retaining wall and construction method using tensile force of steel rod piles
JPS58120924A (en) Block for assembling retaining wall
JP2743264B2 (en) Retaining wall construction
JP3120103B2 (en) Road widening structure
JP2868651B2 (en) Earth retaining method above existing underground structure
JP3470576B2 (en) Construction method of retaining wall and retaining wall structure
JP3270433B2 (en) Rooted retaining wall
JP3063673B2 (en) Foundation structure of building with soil cement pillar row retaining wall tied to frame
KR102610495B1 (en) Construction method of self-supporting retaining wall
JPS6117696A (en) Construction of underground head
JP3681883B2 (en) Long-cut soil slope reduction method
KR102272494B1 (en) Slope reinforcement structure using support and tension and Its Construction method
JPH1082055A (en) Method of earthquake-resisting pile foundation construction
JPS6016535B2 (en) How to form retaining walls and underground walls
JP2658692B2 (en) Earth retaining method for deep excavation
JP2565071B2 (en) Column-type underground continuous wall
KR200295956Y1 (en) Grid fixing device for constructing of mechanically stabilized earth walls and reinforced soil slopes
JP3357631B2 (en) Construction method of slope protection work
JP2918420B2 (en) Wall used for earth retaining method
JP2918421B2 (en) Wall used for earth retaining method
JPH05295748A (en) Sheathing method

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080521

Year of fee payment: 9

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 10

Free format text: PAYMENT UNTIL: 20090521

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 11

Free format text: PAYMENT UNTIL: 20100521

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 11

Free format text: PAYMENT UNTIL: 20100521

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 12

Free format text: PAYMENT UNTIL: 20110521

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120521

Year of fee payment: 13

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 13

Free format text: PAYMENT UNTIL: 20120521

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 14

Free format text: PAYMENT UNTIL: 20130521

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 14

Free format text: PAYMENT UNTIL: 20130521

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 15

Free format text: PAYMENT UNTIL: 20140521

EXPY Cancellation because of completion of term