JP2845338B2 - Simple infiltration pavement method - Google Patents

Simple infiltration pavement method

Info

Publication number
JP2845338B2
JP2845338B2 JP3162890A JP3162890A JP2845338B2 JP 2845338 B2 JP2845338 B2 JP 2845338B2 JP 3162890 A JP3162890 A JP 3162890A JP 3162890 A JP3162890 A JP 3162890A JP 2845338 B2 JP2845338 B2 JP 2845338B2
Authority
JP
Japan
Prior art keywords
aggregate
cement
setting
asphalt
quick
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP3162890A
Other languages
Japanese (ja)
Other versions
JPH03235801A (en
Inventor
厚一 名方
仁 緒形
正樹 広瀬
康成 前嶋
邦彦 西川
明洋 緒方
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Materials Corp
Kotobuki Kogyo KK
Original Assignee
Mitsubishi Materials Corp
Kotobuki Kogyo KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Materials Corp, Kotobuki Kogyo KK filed Critical Mitsubishi Materials Corp
Priority to JP3162890A priority Critical patent/JP2845338B2/en
Publication of JPH03235801A publication Critical patent/JPH03235801A/en
Application granted granted Critical
Publication of JP2845338B2 publication Critical patent/JP2845338B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は、道路をコンクリート等の水硬性材料で剛性
舗装する際に、短時間で工事が完成され、道路の開放が
短時間で可能で然も施工が簡単な舗装方法に関する。
[Detailed Description of the Invention] [Industrial application field] According to the present invention, when a road is rigidly paved with a hydraulic material such as concrete, construction is completed in a short time, and the road can be opened in a short time. Naturally, it relates to a pavement method that is easy to construct.

[従来の技術及び発明が解決しようとする問題点] 従来の舗装方法には、コンクリート舗装とアルファル
ト舗装とがあり、コンクリート舗装方法は、路床上に切
り込み採石並びに粒度調整採石等をあらかじめ定められ
た交通量に従ってコンクリート舗装要綱等で規定されて
いる所定厚に敷き均し、不陸調整、転圧により造成した
路盤上にコンクリートを所定厚敷き均し、所定の精度に
表面を仕上げ、所定期間養生した後、開放していた。
[Problems to be Solved by Conventional Techniques and Inventions] Conventional pavement methods include concrete pavement and asphalt pavement. In the concrete pavement method, cut quarry, grain size adjustment quarry, and the like are previously determined on a roadbed. According to the traffic volume, spread the concrete to the specified thickness specified by the concrete pavement outline, etc., spread the concrete to the specified thickness on the roadbed created by unevenness adjustment and compaction, finish the surface to the specified accuracy, and After curing, she was open.

このようなコンクリート舗装の場合は、コンクリート
供試体の現場養生強度で、35Kg/cm2以上か、普通ポルト
ランドセメントの場合、2週間程度の養生期間を要する
と定められている。更に、コンクリート舗装の場合、ス
ランプで2.5cmを標準としたコンシステンシーが悪いコ
ンクリートを使用するため、通常施行時には、スプレッ
タ、フィニシャ、表面仕上機、目地切り機の施行機械を
使用する必要があり、更に小規模の舗装を施行する場合
にも、振動機を使用する締め固め、所定の精度に表面を
仕上げる道具を使用する技術者並びに作業員が必要であ
るばかりでなく、施行にも時間を要していた。従って、
使用中の道路の補修工事等には不向きで、施行単価も高
くなる等の欠点があった。
In the case of such a concrete pavement, the curing strength in the field of the concrete specimen is 35 kg / cm 2 or more, and in the case of ordinary Portland cement, a curing period of about two weeks is required. Furthermore, in the case of concrete pavement, it is necessary to use a spreader, a finisher, a surface finishing machine, a jointing machine, etc. during normal operation, because concrete with poor consistency with a standard of 2.5 cm slump is used. In addition, when performing small-scale pavement, not only technicians and workers who use tools to compact the surface using a vibrator and finish the surface to a predetermined accuracy are required, but also require time to perform the pavement. Was. Therefore,
It is unsuitable for repairing roads in use and has other drawbacks such as higher unit prices.

所定の空隙率に粒度を調整された砕石骨材を、所定の
厚さに敷き均し、転圧した後、ポルトランドセメント又
は混合セメントと、速硬性剤化材と凝結調整剤とを所定
量配合したグラウト材を混練し、該骨材層上に散布し
て、浸透される舗装方法では、簡易で安価であり、施行
後早期に開放できる等の効果があるが、スラリーを砕石
骨材層上に散布する際に、衝撃並びにレーキ等で表面を
かき均すために、表面の砕石粒が剥がれて、不陸を生じ
るため、浸透後、再度表層の仕上工程が必要であった。
After the crushed stone aggregate whose particle size has been adjusted to a predetermined porosity is spread to a predetermined thickness and rolled, a predetermined amount of Portland cement or mixed cement, a quick-curing agent-forming material and a setting modifier is blended. In the pavement method in which the grout material is kneaded, sprayed on the aggregate layer and permeated, the pavement method is simple and inexpensive, and has an effect that it can be opened early after the application, but the slurry is applied to the crushed aggregate layer. When spraying on the surface, crushed stones on the surface are peeled off and unevenness is generated in order to smooth the surface with an impact and a rake, etc., so that after the infiltration, a surface finishing step is required again.

本発明は、以上述べたような従来の問題点を解決すべ
く、施行が簡単で、施行能率並びに耐久性がよく、且つ
施工単価も安価で、早期に開放可能な簡易舗装方法を提
供することを目的にする。
An object of the present invention is to provide a simple pavement method that can be easily opened at an early stage with a simple execution, good execution efficiency and good durability, and a low construction unit price, in order to solve the above-mentioned conventional problems. For the purpose.

[問題点を解決するための手段] 本発明は、ポルトランドセメント又は混合セメント10
0重量部に対して、速硬性硬化材3〜300重量部混合した
混合物を速硬性セメント材とし、該速硬性セメント材10
0重量部に対して凝結調整剤0.1〜2.0重量部を配合した
混合物をグラウト材とし、水を前記速硬性セメント材に
対して重量比(以後W/Cと称する)で、20〜200%の範囲
で混練して、スラリー状とし、空隙率が5〜50%の砕石
骨材を敷き均し転圧した舗装骨材層表面に、散布し、浸
透充填させる浸透簡易舗装方法において、 A.前記砕石骨材層を接着する接着剤、アスファルト、又
は速硬性を有する水硬性物質より選択された1種又は2
種以上の混合物のスラリーを散布して、舗装骨剤層表面
の粒子を固定する工程及び B.工程Aの後、前記配合のグラウト材のスラリーを散
布、浸透させ、間隙部分を充填する工程を含むことを特
等とする浸透舗装方法である。そして、前記工程Aの
後、前記工程Bの前に、前記骨材層の表面に、該砕石骨
材より粒径が小さく且つ骨材の空隙率が5〜40%である
砕石骨材を敷き均し、再度、前記接着剤、アスファルト
又は速硬性を有する水硬性物質より選択された1種又は
2種以上の物質の混合物のスラリーを散布し、その後に
工程Bを行なうことを特徴とする浸透簡易舗装方法であ
る。また、本発明は、工程Aの前に、前記骨材層の表面
部に該砕石骨材より粒径が小さく且つ該骨材の空隙率が
5〜40%である骨材を層厚50mm以下に、敷き均し、転圧
し、工程Aを行ない、その後工程Bを行なうことを特徴
とする浸透簡易舗装方法である。また、そのグラウト材
は、前記配合のグラウト材を、水を前記速硬性セメント
材に対して(即ちW/Cで)、20〜200重量%の範囲で混練
して、その際に、該速硬性セメント材に対して、減水剤
0.05〜5重量%及び/又は流動化剤0.05〜10重量%を添
加して混練することが好適である。また、その接着剤
は、天然ゴム及び合成高分子(樹脂、プラスチック、ゴ
ム、繊維等)を原料として、溶剤又は水に溶解したもの
と、天然ゴム及び合成高分子の微粉末を水に分散したエ
マルジョンから選択されたものを用いることが好適であ
る。そして、そのアスファルトは、ストレートアスファ
ルト、アスファルト乳剤又はカットバックアスファルト
のいずれか1種であり、ストレートアスファルトは、13
0〜180℃、アスファルト乳剤は、5〜60℃、カットバッ
クアスファルトは、40〜140℃に加熱し、液状化させた
ものを用いることが好適である。そして、その速硬性硬
化材は、ジェットセメント、ジェットセメントとポルト
ランドセメント又は混合セメントとの混合物に凝結調整
剤を配合したもの、及びポルトランドセメント又は混合
セメントと速硬性硬化材と凝結調整剤とを配合したもの
とからなる群から選択されたものであり、水と前記速硬
性セメントを重量比で、30〜300%で混練して、ペース
ト状にしたものをグラウト材とすることが好適である。
また、舗装すべき路盤上に、前記グラウト材、接着剤、
アスファルト又は速硬性を有する水硬性物質を散布し、
路盤を固め、その後に、舗装のための骨材を敷き均し
て、転圧して、その後、工程Aを行ない、その後、工程
Bを行なうことが好適である。また、その凝結調整剤が
クエン酸、酒石酸、グルコン酸或いはこれらの塩のう
ち、1種或いは2種以上の混合物である有機酸系凝結遅
延剤と炭酸アルカリよりなるものから選択されるものが
好適である。
[Means for Solving the Problems] The present invention relates to Portland cement or mixed cement.
A mixture obtained by mixing 3 to 300 parts by weight of the quick-setting hardening material with respect to 0 parts by weight was used as a quick-setting cement material.
A mixture obtained by mixing 0.1 to 2.0 parts by weight of the setting modifier with respect to 0 parts by weight was used as a grout material, and water was used in an amount of 20 to 200% by weight (hereinafter referred to as W / C) with respect to the quick-setting cement material. A simple infiltration pavement method in which a crushed aggregate having a porosity of 5 to 50% is kneaded to form a slurry, and the crushed aggregate having a porosity of 5 to 50% is spread and spread on the surface of the rolled pavement aggregate layer to penetrate and fill. One or two selected from an adhesive for adhering the crushed aggregate layer, asphalt, or a hydraulic material having quick-setting properties
A step of spraying a slurry of the mixture of the above-mentioned kinds to fix particles on the surface of the pavement aggregate layer, and B. After the step A, a step of spraying and infiltrating the slurry of the grout material having the above composition to fill the gap portion. This is an infiltration pavement method characterized by including Then, after the step A and before the step B, a crushed stone aggregate having a particle diameter smaller than that of the crushed stone aggregate and a porosity of the aggregate of 5 to 40% is laid on the surface of the aggregate layer. Leveling, again applying a slurry of a mixture of one or two or more substances selected from the adhesive, asphalt or a hydraulic substance having quick-setting properties, and thereafter performing step B. This is a simple pavement method. Further, the present invention provides, before the step A, an aggregate having a particle size smaller than that of the crushed aggregate and a porosity of the aggregate of 5 to 40% on a surface portion of the aggregate layer having a thickness of 50 mm or less. And then performing rolling step A, and then performing step B. Further, the grout material is obtained by kneading the grout material having the above-mentioned composition with water in the range of 20 to 200% by weight with respect to the quick-hardening cement material (that is, in W / C). Water reducing agent for hard cement materials
It is preferable to add and knead 0.05 to 5% by weight and / or 0.05 to 10% by weight of a fluidizing agent. The adhesive is made of natural rubber and synthetic polymers (resins, plastics, rubber, fibers, etc.) as raw materials, and one obtained by dissolving in a solvent or water and dispersing fine powder of natural rubber and synthetic polymers in water. It is preferred to use one selected from emulsions. The asphalt is any one of straight asphalt, asphalt emulsion and cutback asphalt, and the straight asphalt is 13
It is preferable to use a liquid which has been heated and liquefied at 0 to 180 ° C, asphalt emulsion at 5 to 60 ° C, and cutback asphalt at 40 to 140 ° C. The quick-setting hardening material is a mixture of jet cement, a mixture of jet cement and Portland cement or mixed cement with a setting modifier, and a mixture of Portland cement or mixed cement with a quick-setting hardening material and a setting modifier. It is preferable that the grout material is obtained by kneading water and the quick-setting cement at a weight ratio of 30 to 300% to form a paste.
Also, on the roadbed to be paved, the grout material, adhesive,
Spray asphalt or hydraulic material with quick-setting,
It is preferable to harden the roadbed, then spread and aggregate aggregates for pavement, perform rolling, and then perform step A, and then perform step B. In addition, it is preferable that the setting regulator is selected from citric acid, tartaric acid, gluconic acid, and salts thereof, which are one or a mixture of two or more organic acid-based setting retarders and alkali carbonates. It is.

本発明の簡易舗装方法において、表層散布に使用する
接着剤、アスファルト又は水硬性物質の混練物は、スプ
レイ等で散布する際に、表層の砕石骨材を乱さない程度
の粘性を有し、且つ硬化後レーキ等で表面を仕上げる際
に、砕石骨材が剥がれない程度の接着力と、その際、散
布するグラウト材スラリーの浸透を妨げないような性状
が必要である。
In the simple pavement method of the present invention, the adhesive used for surface spraying, the kneaded material of asphalt or a hydraulic substance, when sprayed with a spray or the like, has a viscosity that does not disturb the crushed aggregate of the surface layer, and When the surface is finished with a rake or the like after hardening, it is necessary that the adhesive strength be such that the crushed stone aggregate does not peel off, and that it does not impede the penetration of the grout material slurry to be sprayed.

また、前もって、グラウト材、接着剤、アスファルト
或いは速硬性を有する水硬性物質又はその混合物を、路
盤上、又は必要に応じて、石粉を路盤上に敷き均した上
に、表面が十分に濡れるまで散布した後、砕石骨材を敷
き均し、転圧して、舗装骨材層を造成するようにすれ
ば、充填時に該スラリーの水分が路盤に奪われ、充填不
良又は水分不足による硬化不良、或いはスラリーが路盤
内に浸透し、材料の消費量が多くなる等の事故を防止す
ることができる 更に前記グラウト材を混練する際に、該速硬性セメン
ト材100重量部に対して、減水剤を0.5〜5重量部及び/
又は流動化剤を0.05〜10重量部添加すれば、水の添加量
を減ずることができる。使用する接着剤のタイプとして
は、例えば、エポキシ系、アクリル系、ゴム系等の溶液
型、水溶液型、エマルジョン(ラテックス)型等があ
り、特に、エマルジョンタイプは、ポリマーセメント用
として市販されており、好適であるが、接着時間に注意
する必要がある。また、接着剤単独で使用せずに、セメ
ント及びセメントと速硬性硬化材との混合物に添加する
ようにすれば費用が安くなり、経済的である。
Also, in advance, grout material, adhesive, asphalt or a hydraulic material having a quick setting or a mixture thereof, on the roadbed, or, if necessary, spread the stone powder on the roadbed, until the surface is sufficiently wet. After spraying, spread crushed aggregate, roll and roll, to create a pavement aggregate layer, if filling, the moisture of the slurry is taken away by the roadbed, poor filling or insufficient curing due to insufficient water, or Slurry penetrates into the roadbed, and it is possible to prevent accidents such as an increase in the consumption of the material.Furthermore, when kneading the grout material, a water reducing agent is added to the quick-setting cement material by 100 parts by weight. ~ 5 parts by weight and / or
Alternatively, if 0.05 to 10 parts by weight of a fluidizing agent is added, the amount of water added can be reduced. As the type of adhesive used, for example, there are an epoxy type, an acrylic type, a rubber type, etc., a solution type, an aqueous type, an emulsion (latex) type and the like. In particular, the emulsion type is commercially available for polymer cement. However, attention must be paid to the bonding time. In addition, if the adhesive is not used alone but is added to the cement or a mixture of the cement and the quick-setting hardening material, the cost is reduced and it is economical.

また、本発明の簡易舗装方法において、使用するアス
ファルトとしては、ストレートアスファルト、アスファ
ルト乳剤又はカットバックアスファルトの何れか1種で
あり、ストレートアスファルトは、130〜180℃、アスフ
ァルト乳剤は、5〜60℃、カットバックアスファルト
は、40〜140℃に加熱し、液状化させたものであり、そ
の品質は、日本道路協会規格 アスファルト乳剤規格
及び日本工業規格(JIS K2208)に定める規格に合格し
たものを用いれば良い。
Further, in the simple pavement method of the present invention, asphalt to be used is any one of straight asphalt, asphalt emulsion or cutback asphalt, straight asphalt is 130 to 180 ° C, and asphalt emulsion is 5 to 60 ° C. , Cutback asphalt is heated to 40-140 ° C and liquefied, and its quality conforms to Japan Road Association standard asphalt emulsion standard
And those that have passed the standards specified in Japanese Industrial Standards (JIS K2208) may be used.

更に、本発明の簡易舗装方法において、使用する速硬
性を有する水硬性物質としては、ジェットセメント、ジ
ェットセメントとポルトランドセメント又は混合セメン
トの混合物に凝結調整剤を配合したもの、ポルトランド
セメント又は混合セメントと速硬性硬化剤と凝結調整剤
とを配合したものから選択された1種類を用いる。
Further, in the simple pavement method of the present invention, the hydraulic material having a quick-setting property used is jet cement, a mixture of jet cement and portland cement or a mixture of cement and a setting modifier, a mixture of portland cement or mixed cement. One selected from a combination of a fast-setting hardener and a setting modifier is used.

水と水硬性物質との重量比即ちW/Cは、好適には、使
用する水硬性セメント材と同配合のものを、W/C=30〜3
00%と大きくとり、充填するスラリーより粘性を小さく
したものを使用すれば、散布が容易である。また、混練
する際に、凝結調整剤の添加量を調整することにより、
硬化時間を調節できるばかりでなく、材料の別に手配す
る必要がないので、好適である。
The weight ratio of water to hydraulic substance, that is, W / C, is preferably the same as the hydraulic cement material to be used, W / C = 30 to 3
Spreading is easy if the slurry is as large as 00% and has a lower viscosity than the slurry to be filled. Also, when kneading, by adjusting the addition amount of the setting regulator,
This is preferable because not only can the curing time be adjusted, but it is not necessary to arrange for each material separately.

更に、本発明の簡易舗装方法における、砕石骨材の空
隙率は、JIS A1104の規定により、砕石骨材の単位容積
重量試験方法により、実績率を求め、これより空隙率を
算出した値である。本発明にると、前記配合で混練した
スラリーを使用することにより、混練した後、一定時間
の間は、混練した直後の流動性を維持することができ、
その後は、急激に硬化し、早期に、道路を開放すること
が可能である強度が得られる。
Furthermore, in the simple pavement method of the present invention, the porosity of the crushed stone aggregate is a value obtained by calculating the porosity by the unit volume weight test method of the crushed stone aggregate according to the provisions of JIS A1104. . According to the present invention, by using the slurry kneaded in the above-mentioned composition, after kneading, for a certain period of time, it is possible to maintain the fluidity immediately after kneading,
After that, it hardens rapidly, and the strength that can open the road early is obtained.

[作用] 本発明は、舗装要項等に定められた方法に従って造成
した路盤上に道路用砕石骨材(JIS A5001)を所定の厚
に敷き均し、転圧、レベル調整を行なった後、接着剤、
アスファルト或いは速硬性を有する水硬性物質からの混
合スラリーを、散布して、砕石骨材を固定し、しかる
後、前記配合で混練したスラリーを砕石骨材層の表面に
散布し、必要に応じて、振動ローラ等を使用しながら、
空隙部分に浸透充填させる簡易舗装方法である。
[Operation] The present invention provides a crushed aggregate for roads (JIS A5001) on a roadbed formed according to the method specified in the pavement requirements and the like, lays down to a predetermined thickness, performs rolling compaction, adjusts the level, and then adheres. Agent,
A mixed slurry from asphalt or a hydraulic substance having fast-setting properties is sprayed to fix the crushed stone aggregate, and thereafter, the slurry kneaded with the above composition is sprayed on the surface of the crushed stone aggregate layer, and if necessary, , While using vibration rollers, etc.
This is a simple pavement method in which voids are infiltrated and filled.

舗装骨材の表面の粒子を固定することにより、前記の
配合のスラリーを散布する際に、衝撃並びにレーキ等に
より、表面を仕上げる際に、表面が荒れることがなくな
り、仕上げ工程を簡素化できるばかりでなく、工事時間
を短縮することができる。
By fixing the particles on the surface of the pavement aggregate, when spraying the slurry having the above-mentioned composition, impact and rake, etc., when finishing the surface, the surface is not roughened, and the finishing process can be simplified only. In addition, the construction time can be reduced.

上記の方法では、使用する骨材の粒径が大きいため、
表面の凹凸が大きくなり、仕上げ時の平坦性を良くする
ためには、表面部のグラウト材スラリーの量を多くして
おく必要があるが、路面の摩擦係数が小さくなり問題で
ある。従って、表面に粒径が小さく、ある程度空隙率が
大きい砕石骨材をまけば、表面の凹凸が少なくなり、同
時に、路面の摩擦係数が大きくなり、好都合である。表
面層に使用する骨材としては、JIS A5001[道路用砕石
に関する規定]に規定する6号又は7号砕石の単品か或
いはこれらの混合物が使用可能であり、特に、7号砕石
が好適である。
In the above method, the particle size of the aggregate used is large,
In order to increase the unevenness of the surface and improve the flatness at the time of finishing, it is necessary to increase the amount of the grout material slurry on the surface portion, but this causes a problem that the friction coefficient of the road surface becomes small. Therefore, if a crushed stone aggregate having a small particle size and a large porosity is applied to the surface, the unevenness of the surface is reduced, and at the same time, the coefficient of friction of the road surface is increased. As the aggregate to be used for the surface layer, a single piece of No. 6 or No. 7 crushed stone specified in JIS A5001 [Rules on Road Crushed Stone] or a mixture thereof can be used, and especially No. 7 crushed stone is suitable. .

更に、路盤上に骨材を敷き均す以前に、路盤に、接着
剤、アスファルト或いは速硬性を有する水硬性物質のス
ラリーを散布しておけば、前記スラリーを充填する際
に、スラリー中の水分が路盤に移動し、水分不足による
硬化不良或いは充填不良を起こす恐れがない。この際
に、接着剤、アスファルト及び水硬性物質のミルク中に
石粉を混合するか、湿らせた石粉を敷き均した後に、散
布すれば、事前に散布する量を節約することができる。
Furthermore, if a slurry of an adhesive, asphalt, or a hydraulic substance having quick-setting properties is sprayed on the roadbed before the aggregates are spread on the roadbed, the moisture in the slurry can be reduced when the slurry is filled. Does not move to the roadbed, and there is no danger of insufficient curing or insufficient filling due to insufficient moisture. At this time, if the stone powder is mixed with the adhesive, the asphalt and the hydraulic substance milk, or the wet stone powder is spread and then sprayed, the amount to be sprayed in advance can be saved.

本発明の簡易舗装方法に用いる速硬性硬化材として
は、アルミン酸カルシウム化合物を50重量%以上含有す
る微粉末にII型無水石膏を添加したものを用いると、前
記配合で混練した場合、セメント中の酸化カルシウムと
アルミン酸カルシウム化合物が、水和反応して、カルシ
ウムアルミネートハイドレートが生成し、更に、このカ
ルシウムアルミネートハイドレートとII型無水石膏と
の、水和反応によって、針状結晶のエトリンガイト(3C
aO・Al2O3・CaSO412H2O)が生成し、急速に硬化して初
期強度の発現となる。更に長期的には、ポルトランドセ
メント及び混合セメント中のカルシウムシリケート系水
和物が強度の発現に寄与する。
As the fast-curing hardening material used in the simple pavement method of the present invention, when a type obtained by adding a type II anhydrous gypsum to a fine powder containing a calcium aluminate compound in an amount of 50% by weight or more is used, when kneaded with the above-mentioned composition, the cement The calcium oxide and the calcium aluminate compound undergo a hydration reaction to form calcium aluminate hydrate. Further, the calcium aluminate hydrate and the type II anhydrous gypsum form a needle crystal by a hydration reaction. Ettringite (3C
aO.Al 2 O 3 .CaSO 4 12H 2 O) is formed and hardens rapidly to develop the initial strength. In the long term, calcium silicate hydrate in Portland cement and mixed cement contributes to the development of strength.

更に、速硬性の水硬性物質には、その他に、CaOの存
在下で、初期にエトリンガイトを生成し、以後、前記と
同様に水和反応をするものであれば、使用可能である。
In addition, any other fast-setting hydraulic substance may be used as long as it produces ettringite in the initial stage in the presence of CaO and then undergoes a hydration reaction in the same manner as described above.

ポルトランドセメントと速硬性硬化材の配合について
は、速硬性硬化材を多く使用すれば、初期強度が高く、
初期強度に対する長期強度の伸び率が、小さくなり、少
ないと初期強度が低くなる傾向を示す。
Regarding the combination of Portland cement and quick-setting hardening material, if a large amount of quick-setting hardening material is used, the initial strength is high,
The elongation percentage of the long-term strength with respect to the initial strength is small, and if it is small, the initial strength tends to be low.

凝結調整剤の添加量は、少なくすれば、混練した後、
所定の流動性を維持する時間が短くなり、多くすると長
くなる傾向を示す。然し乍ら、凝結調整作用は、化学反
応によるために、作業時の温度によって配合比を調整す
る必要がある。
If the addition amount of the setting regulator is small, after kneading,
There is a tendency that the time for maintaining the predetermined fluidity becomes shorter, and that the longer the time, the longer the time. However, since the setting adjustment effect is due to a chemical reaction, it is necessary to adjust the compounding ratio depending on the temperature during operation.

減水剤並びに流動化剤を使用すれば、所定の流動性を
得るためのW/Cを小さくすることができる。
If a water reducing agent and a fluidizing agent are used, W / C for obtaining a predetermined fluidity can be reduced.

W/Cを大きくすれば、前記スラリーの流動性は大きく
なるが、逆に強度は低下する傾向がある。
Increasing W / C increases the fluidity of the slurry, but tends to decrease strength.

減水剤のみを使用した状態で、水を5〜20重量%程
度、流動化剤のみで、5〜20程度の重量%で、両者を併
用した場合でも、同様の効果を有する。
The same effect can be obtained even when both are used in a state where only about 5 to 20% by weight of water is used in the state of using only the water reducing agent, and about 5 to 20% by weight in the case of using only the fluidizing agent.

尚、減水剤並びに流動化剤は、混和剤のJIS規格に合
格したもの及び同等品であれば、使用可能である。
The water reducing agent and the fluidizing agent can be used as long as they have passed the JIS standard of the admixture or are equivalent.

更に、前記スラリーを浸透させる骨材層の空隙率は、
10%より小さいと浸透性悪くなり、50%より大きいと、
該グラウト材スラリーの使用量が、増加し、単価が高く
なり、不経済であるばかりでなく、耐摩耗性等の耐久性
が悪くなり、不都合である。また、表層部に使用する骨
材の最大粒径は、13mmより大きいと、表面の凹凸が大き
くなり、1.2mmより小さいと、該グラウト材スラリーの
浸透が、悪くなり、好ましくない。
Furthermore, the porosity of the aggregate layer in which the slurry is infiltrated is
If it is less than 10%, permeability will be poor, if it is more than 50%,
The use amount of the grout material slurry increases, the unit price increases, and it is not only uneconomical but also inferior in durability such as abrasion resistance, which is inconvenient. If the maximum particle size of the aggregate used for the surface layer is larger than 13 mm, the irregularities on the surface become large, and if smaller than 1.2 mm, the penetration of the grout material slurry becomes poor, which is not preferable.

次に、本発明の浸透簡易舗装方法について具体例によ
り説明するが、本発明は、次の実施例に限定されるもの
ではない。
Next, the simple infiltration pavement method of the present invention will be described with reference to specific examples, but the present invention is not limited to the following examples.

[実施例] 本実施例に用いた材料は、以下に示すものである。[Examples] Materials used in the present examples are shown below.

セメント 三菱鉱業セメント社製 普通ポルトランドセメント 速硬性硬化材 三菱鉱業セメント社製 コーカエース(登録商標) アルミン酸カルシウム系硬化材 凝結調整剤 コーカセッター(登録商標) (三菱鉱業セメント社製) 減水剤 ポゾリス物産社製 ポゾリス#70(減水剤) 第1表に示すA粒度と空隙率の骨材を3×10mに厚さ1
5cmに敷き均した後、転圧し、第1図に示す1×1mを12
区画として、30区画に分け、次のような舗装試験を行な
った。
Cement Ordinary Portland cement made by Mitsubishi Mining Cement Co., Ltd. Fast-curing hardener Made by Mitsubishi Mining Cement Coca Ace (registered trademark) Calcium aluminate hardening agent Coagulation setter Cauca Setter (registered trademark) (Mitsubishi Mining Cement Co.) Water reducer Pozzolith Bussan Pozzolith # 70 (water reducing agent) Aggregate with A particle size and porosity shown in Table 1
After laying down 5cm and rolling, roll 1x1m shown in Fig. 12
The sections were divided into 30 sections, and the following pavement tests were performed.

先ず、各散布のときに、骨材層表面粒子の接着状況を
観察するために、日本舗装社製ニッポゾルPK−3と称す
るアスファルト乳剤を、区画1〜3に各々1.8/m2、3.
6/m2、0.9/m2(アスファルト乳剤を水で2倍に希釈
した)と、第2表に示すA配合のグラウト材をスラリー
にしたものを、骨材表面層の粒子を接着するためスラリ
ーとして、各々1.8/m2、3.6/m2、5.4/m2、敷き均
し、転圧した砕石骨材表面に散布し、30分経過後、ゴム
製レーキで骨材の表面をこすり、砕石骨材粒子の接着状
況を観察した結果、アスファルト乳剤で、2.5〜3.6/m
2程度、接着用スラリーで、1.8〜3.6/m2程度、散布す
れば、表面骨材粒子の固定が、可能であることが、判明
した。
First, at the time of each spraying, in order to observe the state of adhesion of the aggregate layer surface particles, asphalt emulsion called Nipposol PK-3 manufactured by Nippon Pavement Co., Ltd., 1.8 / m 2 , 3.
6 / m 2 , 0.9 / m 2 (asphalt emulsion was diluted 2 times with water) and grout material of A composition shown in Table 2 as a slurry were used to adhere the particles of the aggregate surface layer. As a slurry, 1.8 / m 2 , 3.6 / m 2 , 5.4 / m 2 , respectively, spread and spread on the surface of the crushed crushed aggregate, after 30 minutes, rub the surface of the aggregate with a rubber rake, As a result of observing the adhesion of crushed aggregate particles, asphalt emulsion, 2.5 to 3.6 / m
About 2, an adhesive slurry, 1.8 to 3.6 / m 2 or so, if sprayed, be fixed on the surface aggregate particles are possible, it has been found.

次に、速硬性セメントと、グラウト材を施工して、施
工結果を観察した。
Next, a quick-setting cement and a grout material were applied, and the application results were observed.

[実施例1] 普通セメント100重量部に対して、上記の速硬性硬化
材コーカエース(三菱鉱業セメント社製)25重量部とを
W/C=80%で、混合して、速硬性セメント材とし、得ら
れた速硬性セメント材100重量部に対して、コーカセッ
ターを0.2重量部、添加し、骨材を接着するためのスラ
リーとした。
[Example 1] 25 parts by weight of the above-mentioned quick-curing hardener Coke Ace (Mitsubishi Mining Cement Co.) was added to 100 parts by weight of ordinary cement.
Mix at 80% W / C to form a fast-setting cement material, add 0.2 parts by weight of Caucasian to 100 parts by weight of the obtained quick-setting cement material, and add a slurry to bond the aggregate. And

更に、このスラリーをグラウト材として、W/C=50或
いは55%で、混練し、更に、同じ配合したグラウト材
に、該速硬性セメント材に対して、市販のポゾリス#70
減水剤を、0.5重量%、W/C=45%で混練し、充填用グラ
ウト材スラリーとした。
Further, this slurry was used as a grout material, kneaded at a W / C of 50 or 55%, and further mixed with the same blended grout material and commercially available pozzolith # 70 with respect to the quick-setting cement material.
The water reducing agent was kneaded at 0.5% by weight and W / C = 45% to obtain a grout material slurry for filling.

区画7〜9には、アスファルト乳剤を、3.6/m2に、
区画10〜12には接着剤をスラリーにしたものを1.8/m2
散布し、硬化後に、区画7、10には、第2表の配合Cの
グラウト材をスラリーにしたものを、散布、浸透せし
め、区画8、11には、第2表の配合Bのグラウト材スラ
リーを散布し、区画9、12には、第2表の配合Aのグラ
ウト材スラリーを散布、浸透せしめ、間隙部に充填させ
た。
In sections 7-9, asphalt emulsion was added to 3.6 / m 2 ,
1.8 / m 2 of slurry of adhesive in sections 10 to 12
After being scattered and cured, the slurries of the grout material of Formula C in Table 2 were sprayed and impregnated in the sections 7 and 10, and the grout material of Formula B in Table 2 was spread in the sections 8 and 11. The slurry was sprayed, and the grout material slurry of Formulation A shown in Table 2 was sprayed and infiltrated into the sections 9 and 12, and the gap was filled.

表面の平坦性にやや難点が見られたが、ほぼ満足すべ
き結果が得られた。
Although there were some difficulties in the flatness of the surface, almost satisfactory results were obtained.

[実施例2] 実施例1と同じ配合のグラウト材によるスラリーとア
スファルト乳剤を用いて、更に、次のような試験を行な
った。
Example 2 The following test was further performed using a grout slurry and an asphalt emulsion having the same composition as in Example 1.

第1図の区画13〜15には、アスファルト乳剤を2.5/
m2散布した後、第1表の粒度分布及び空隙率を有するB
骨材を表面の凹凸がなくなる程度に敷き均し、再度、ア
スファルト乳剤を0.9/m2散布した。更に、区画16〜18
に、第2表の配合Aのグラウト材をスラリーにしたもの
を、1.8/m2散布した後、同様に、第1表のB骨材を敷
き均し、同じ接着剤スラリーを、更に、0.9/m2散布し
て、表面を固定した。しかる後に、区画13、16に第2表
の配合Cのグラウト材によるスラリーを、区画14、17
に、第2表の配合Bによるスラリーを、区画15、18に第
2表の配合Aによるスラリーを散布し、浸透させ、間隙
部に充填した。
In blocks 13 to 15 of FIG.
After spraying m 2, B having the particle size distribution and porosity shown in Table 1
The aggregate was spread to such an extent that surface irregularities disappeared, and asphalt emulsion was sprayed again at 0.9 / m 2 . In addition, sections 16-18
Then, 1.8 g of the grout material of the mixture A in Table 2 was slurried, and after spraying 1.8 / m 2 , the aggregate B in Table 1 was similarly spread and spread. / m 2 was sprayed to fix the surface. Thereafter, the slurries of the grout material having the composition C shown in Table 2 were applied to the compartments 13 and 16, respectively.
Then, the slurry according to the formulation B in Table 2 was sprayed on the sections 15 and 18 with the slurry according to the formulation A in Table 2 to permeate and fill the gap.

次いで、第1図の区画19〜24には、更に、第1表のB
骨材を厚さ1〜2cm程度敷き均し、転圧した上に、区画1
9〜21には、アスファルト乳剤を3.6/m2散布し、区画2
2〜24には、第2表の配合Aのグラウト材をスラリーに
したものを1.8/m2散布して、表面の砕石骨材を固定
し、しかる後、区画19、22に.第2表の配合Cのグラウ
ト材によるスラリーを散布し、区画20、23には、第2表
の配合Bのスラリーを散布し、区画21、24には、第2表
の配合Aのグラウト材によるスラリーを散布し、浸透さ
せ、間隙部に充填させた。所定期間養生させた後、各試
験区間より、3箇所コアを抜き取り、充填状況を調査し
た結果、いずれの箇所のコアでも、充填状況は良好であ
った。
Next, in the sections 19 to 24 in FIG.
Spread the aggregate about 1-2cm in thickness and roll it.
For 9 to 21, spray 3.6 / m 2 of asphalt emulsion and
In 2 to 24, the grouted material of the composition A in Table 2 was slurried and sprayed at 1.8 / m 2 to fix the crushed aggregate on the surface. The slurry of the grout material of the composition C in Table 2 is sprayed, and the slurries of the composition B in Table 2 are sprayed in the sections 20 and 23, and the grout materials of the composition A in Table 2 are sprayed in the sections 21 and 24. Was sprayed, permeated, and filled in the gap. After curing for a predetermined period, cores were extracted from each of the test sections at three locations, and the state of filling was examined. As a result, the state of filling was good in any of the cores.

同時に、第1表のA砕石骨材を、10cmΦ×20cmのコン
クリート試験用の円筒形型枠に詰めた後、アンスラー耐
圧試験機を用いて、2トンの加重を掛け、その後、上記
のニッポゾルPK−3のアスファルト乳剤を、3.6/m2
第2表の配合Aのグラウト材をスラリーにしたもの1.8
/m2とを散布した後、第2表の配合A、B、Cによる
スラリーを、テーブルバイブレータ上で振動しながら、
充填し、強度試験用の供試体を作成した。
At the same time, the A crushed stone aggregate shown in Table 1 was packed in a cylindrical form for a concrete test of 10 cmΦ × 20 cm, and then a 2 ton load was applied thereto using an Ansler pressure tester. -3 asphalt emulsion obtained by slurrying 3.6 / m 2 and grout material of formulation A in Table 2 1.8
/ m 2 and then slurries the blends A, B, and C in Table 2 while vibrating on a table vibrator.
The specimen was filled to prepare a test specimen for a strength test.

その際の舗装された骨材の空隙率は、37%であり、充
填状況も良好であった。
At that time, the porosity of the paved aggregate was 37%, and the filling condition was good.

また、30×30×5cmの型枠に、前記の第1表のAの砕
石骨材を詰め、前記と同様の手順で、第2表の配合によ
るスラリーを充填した。養生完了後、30×5×5cmの供
試体を切り出し、曲げスパン20cmの1点載荷による曲げ
試験を行なった。
In addition, a 30 × 30 × 5 cm formwork was filled with the crushed aggregate of A in Table 1 described above, and the slurry having the composition shown in Table 2 was filled in the same procedure as described above. After curing was completed, a test specimen of 30 × 5 × 5 cm was cut out, and a bending test was performed by loading a single point with a bending span of 20 cm.

以上による圧縮強度試験及び曲げ強度試験の結果を、
第2図A、Bに示す。
The results of the compression strength test and bending strength test
2A and 2B.

[実施例3] JIS A5001の規定にする粒度調整砕石骨材M−25を、
広さ1×2m、厚さ10cmに敷き均し、転圧して、路盤を造
成し、石灰石粉末を水との重量比で80重量%で練り混ぜ
たものを、前記骨材による層の1×1mの区画に均一に散
布し、更に第2表の配合Aによるグラウト剤をW/C=45
%で混練して得られたスラリーを1×1mの区画に散布し
た後、第1表のA骨材を、15cm厚に敷き均し、転圧した
後、メタコートGSと称するアクリル樹脂溶液(接着剤)
(重量比3%)と第2表の配合Aのグラウト材との混合
物を、W/C=50%に混練して得られたスラリーを、0.9
/m2散布し、その後、更に、第1表のB骨材を、1cm厚に
敷き均し、転圧した。その後、更に、同じ接着剤と速硬
性硬化材との混合物を、1.8/m2散布し、表面の骨材を
固定し、更に、第2表の配合Bによるスラリーを散布
し、その後、振動転圧機を用いて充填した。その結果を
観察すると、材料の食い込みは、ほとんどなく、コアを
抜き取って、充填状況を調査した結果も、良好であっ
た。
[Example 3] Particle size-adjusted crushed stone aggregate M-25 specified in JIS A5001 was used.
1x2m wide, 10cm thick, flattened and rolled to form a roadbed, kneaded with limestone powder at a weight ratio of 80% by weight with water, 1x of the layer made of the aggregate Sprinkle evenly over a 1m section, and further apply the grouting agent of Formula A in Table 2 to W / C = 45.
%, The slurry obtained by kneading the mixture was sprayed over a 1 × 1 m section, the A-aggregate in Table 1 was spread to a thickness of 15 cm, rolled, and then pressed with an acrylic resin solution called Metacoat GS (adhesive Agent)
(Weight ratio 3%) and a mixture of the grout material of formulation A in Table 2 were kneaded to a W / C = 50%, and the resulting slurry was mixed with 0.9%.
/ m 2 , and then the B aggregate in Table 1 was spread evenly to a thickness of 1 cm and compacted. Thereafter, the mixture of the same adhesive and the quick-curing hardener was further sprayed at 1.8 / m 2 to fix the aggregate on the surface, and further, the slurry according to Formulation B in Table 2 was sprayed. It was filled using a pressure machine. Observation of the results showed that there was almost no bite of the material, and that the core was extracted and the state of filling was examined.

[発明の効果] 本発明の浸透簡易舗装方法は、砕石骨材に対して、樹
脂系速硬性硬化材を前に、散布する工程と、その後に、
グラウト材のスラリーを散布する工程を行なうことによ
り、砕石骨材を固定する舗装工法によるものであり、 第1に、路盤造成後、砕石骨材を敷き均し転圧するの
みで、直ちに、表層舗装に掛かることができ、工期を大
幅に短縮できる舗装工法を提供すること、 第2に、路盤造成後、砕石骨材を敷き均す前に、その
路盤上に、前記の材料を散布するので、路盤と舗装の骨
材層との境界部において、水分不足による硬化不足又は
粘性が増加し、充填不足を起こす恐れが少ない舗装工法
を提供すること、 第3に、路盤の表面を固定材料で覆っているために、
砕石骨材を敷き均した後、前記固定のためのスラリーを
充填する際に、材料の食い込みがなく、材料の購入計画
を立て易い簡易舗装方法を提供すること、 第4に、砕石骨材層に固定スラリーを散布、充填する
際に、表面の骨材粒子が固定されているので、散布並び
に散布後の表面仕上げ時に、骨材層の表面が荒れること
がなく、散布後の表面仕上げ工程を簡略化することがで
きる舗装方法を提供すること、 第5に、混練後、一定時間経過後に、早期に強度の発
現するため、短い養生期間で早期に開放可能な強度を得
るので、交通量の多い幹線道路等の補修等にも十分利用
できる舗装方法を提供すること、 第6に、表層舗装にも、大型の施行機械を必要しない
ばかりか、特別な技能を必要せずに、施行費用を安くす
ることができる舗装方法を提供すること、 第7に、アスファルト並びにセメントコンクリート舗
装のように、材料を混練する特別のプラントを必要とし
ないため、場所的、時間的な制約がなく、従って、プラ
ントより遠く離れた僻地でも舗装工事を容易に実施出来
る舗装方法を提供すること、 第8に、舗装表面部に粒径の小さい砕石骨材を使用す
ることにより、表面の耐摩耗性能う下げずに、表面の平
滑性をある程度確保できる舗装方法を提供すること、 などの技術的効果が得られた。
[Effect of the Invention] The infiltration simple pavement method of the present invention is a step of spraying a resin-based quick-curing hardening material on crushed stone aggregate, and thereafter,
It is a pavement method that fixes the crushed stone aggregate by performing a step of spraying a grout material slurry. First, after the roadbed is formed, the crushed stone aggregate is spread and rolled, and the surface layer is immediately paved. Second, to provide a pavement method that can significantly shorten the construction period, after the roadbed construction, before spreading the crushed aggregate, the above-mentioned material is sprayed on the roadbed, At the boundary between the roadbed and the pavement aggregate layer, there is provided a pavement method that is less likely to cause insufficient filling or insufficient curing due to insufficient moisture or insufficient filling. Third, the surface of the roadbed is covered with a fixed material. To be
When the crushed aggregate is spread and leveled, when filling with the slurry for fixing, there is provided a simple pavement method that does not bite the material and makes it easy to make a purchase plan of the material. Since the aggregate particles on the surface are fixed when the fixed slurry is sprayed and filled, the surface of the aggregate layer is not roughened at the time of spraying and surface finishing after spraying, and the surface finishing step after spraying is performed. Fifth, to provide a pavement method that can be simplified. Fifth, after kneading, a certain time elapses, so that the strength develops early. To provide a pavement method that can be sufficiently used for repairing many main roads, etc. Sixth, the surface pavement does not require large-scale construction machinery, and does not require special skills. Paving methods that can be cheaper Seventh, since there is no need for a special plant for kneading materials as in the case of asphalt and cement concrete pavement, there is no place and time restriction, and therefore paving work is possible even in a remote place far from the plant. Eighth, the use of crushed stone having a small particle size on the surface of the pavement ensures the smoothness of the surface to some extent without lowering the abrasion resistance of the surface. Technical effects such as providing a pavement method that can be used were obtained.

【図面の簡単な説明】[Brief description of the drawings]

第1図は、本発明の舗装方法により試験区間を示す平面
図である。 第2図A、Bは、本発明による舗装材料の強度につい
て、圧縮強度試験及び曲げ強度試験をした結果を示すグ
ラフである。
FIG. 1 is a plan view showing a test section by the pavement method of the present invention. 2A and 2B are graphs showing the results of a compression strength test and a bending strength test on the strength of the pavement material according to the present invention.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 緒形 仁 福岡県北九州市八幡西区洞南町1番地1 三菱鉱業セメント株式会社九州事業所 開発研究部内 (72)発明者 広瀬 正樹 福岡県北九州市八幡西区洞南町1番地1 三菱鉱業セメント株式会社九州事業所 開発研究部内 (72)発明者 前嶋 康成 福岡県北九州市八幡西区洞南町1番地1 三菱鉱業セメント株式会社九州事業所 開発研究部内 (72)発明者 西川 邦彦 福岡県北九州市八幡西区洞南町1番地1 三菱鉱業セメント株式会社九州事業所 開発研究部内 (72)発明者 緒方 明洋 福岡県北九州市八幡西区洞南町1番地1 三菱鉱業セメント株式会社九州事業所 開発研究部内 (56)参考文献 特開 昭63−247467(JP,A) 特開 平2−145469(JP,A) (58)調査した分野(Int.Cl.6,DB名) E01C 7/08 E01C 7/32──────────────────────────────────────────────────続 き Continued on the front page (72) Inventor Jin Ogata 1 Minami-cho, Yawata-nishi-ku, Kitakyushu-shi, Fukuoka Prefecture 1 In the Research and Development Department, Kyushu Works, Mitsubishi Mining Cement Co., Ltd. 1 Minamicho 1 Mitsubishi Mining & Cement Co., Ltd. Kyushu Plant Development Research Department (72) Inventor Yasunari Maejima 1 Minami-cho, Yawata-nishi-ku, Kitakyushu-shi, Fukuoka 1 Mitsubishi Mining Cement Co., Ltd. Kyushu Plant Development Research Department (72) Inventor Nishikawa Kunihiko 1 Minamicho, Yawatanishi-ku, Kitakyushu-shi, Fukuoka Prefecture 1 Minamicho, Kyushu Office, Development Research Department, Mitsubishi Mining Cement Co., Ltd. (56) References JP-A-63-247467 ( P, A) JP flat 2-145469 (JP, A) (58 ) investigated the field (Int.Cl. 6, DB name) E01C 7/08 E01C 7/32

Claims (9)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】ポルトランドセメント又は混合セメント10
0重量部に対して、速硬性硬化材3〜300重量部混合した
混合物を速硬性セメント材とし、 該速硬性セメント材100重量部に対して凝結調整剤0.1〜
2.0重量部を配合した混合物をグラウト材とし、 水を前記速硬性セメント材に対して重量比で、20〜200
%の範囲で混練して、スラリー状とし、空隙率が5〜50
%の砕石骨材を敷き均し転圧した舗装骨材層表面に、散
布し、浸透充填させる浸透舗装方法において、 A.前記骨材層を接着する接着剤、アスファルト、又は、
速硬性を有する水硬性物質より選択された1種又は2種
以上の混合物のスラリーを散布し、表面を固定する工程
及び B.工程Aの後、前記配合のグラウト材のスラリーを散
布、浸透させ、間隙部分を充填する工程を含むことを特
徴とする浸透簡易舗装方法。
1. Portland cement or mixed cement
A mixture obtained by mixing 3 to 300 parts by weight of the quick-setting hardening material with respect to 0 parts by weight is used as a quick-setting cement material.
The mixture containing 2.0 parts by weight was used as a grout material, and water was added in a weight ratio of 20 to 200 with respect to the quick-setting cement material.
% In a range of 5% to 50% to form a slurry.
% Of the crushed stone aggregate and spread on the surface of the rolled pavement aggregate layer, and infiltration and filling, the following: A. An adhesive, asphalt, or asphalt for bonding the aggregate layer
A step of spraying a slurry of one or more mixtures selected from hydraulic substances having quick-setting properties and fixing the surface; and B. After the step A, spray and infiltrate the slurry of the grout material having the above composition. And a step of filling a gap portion.
【請求項2】前記工程Aの後、前記工程Bの前に、前記
砕石骨材層の表面に、該砕石骨材より粒径が小さく且つ
砕石骨材の空隙率が5〜40%である砕石骨材を敷き均
し、再度、前記接着剤、アスファルト又は速硬性を有す
る水硬性物質より選択された1種又は2種以上の物質の
混合物のスラリーを散布する工程を行ない、次に、工程
Bを行なうことを特徴とする請求項1に記載の浸透簡易
舗装方法。
2. After the step A and before the step B, on the surface of the crushed aggregate layer, the particle size is smaller than that of the crushed aggregate and the porosity of the crushed aggregate is 5 to 40%. Laying crushed stone aggregates, again performing a step of spraying a slurry of a mixture of one or more substances selected from the above-mentioned adhesive, asphalt or a hydraulic substance having quick-setting property, 2. The simple infiltration pavement method according to claim 1, wherein B is performed.
【請求項3】工程Aの前に、前記骨材層の表面部に該骨
材より粒径が小さく且つ該骨材の空隙率が5〜40%であ
る骨材を層厚50mm以下に、敷き均し、転圧し、 工程Aを行ない、その後工程Bを行なうことを特徴とす
る請求項1に記載の浸透簡易舗装方法。
3. Prior to the step A, an aggregate having a particle size smaller than that of the aggregate and a porosity of the aggregate of 5 to 40% is reduced to a layer thickness of 50 mm or less on the surface portion of the aggregate layer. The method of claim 1, wherein the step (A) is carried out, the step (A) is carried out, and the step (B) is carried out thereafter.
【請求項4】前記のグラウト材は、前記配合のグラウト
材を、水を前記速硬性セメント材に対して、20〜200重
量%の範囲で混練して、その際に、該速硬性セメント材
に対して、減水剤0.05〜5重量%及び/又は流動化剤0.
05〜10重量%を添加して混練することを特徴とする請求
項1〜3のいずれかに記載の浸透簡易舗装方法。
4. The grout material according to claim 1, wherein said grout material is kneaded with water in a range of 20 to 200% by weight with respect to said fast-hardening cement material. The water reducing agent is 0.05 to 5% by weight and / or the fluidizing agent is 0.
4. The simple infiltration pavement method according to any one of claims 1 to 3, wherein the kneading is carried out by adding 05 to 10% by weight.
【請求項5】前記の接着剤は、天然ゴム及び合成高分子
(樹脂、プラスチック、ゴム、繊維等)を原料として、
溶剤又は水に溶解したものと、天然ゴム及び合成高分子
の微粉末を水に分散したエマルジョンから選択されるこ
とを特徴とする請求項1〜4のいずれかに記載の浸透簡
易舗装方法。
5. The adhesive is made of natural rubber and synthetic polymer (resin, plastic, rubber, fiber, etc.) as raw materials.
The method according to any one of claims 1 to 4, wherein the method is selected from a solution dissolved in a solvent or water and an emulsion in which fine powders of natural rubber and synthetic polymer are dispersed in water.
【請求項6】前記のアスファルトは、ストレートアスフ
ァルト、アスファルト乳剤又はカットバックアスファル
トのいずれか1種であり、ストレートアスファルトは、
130〜180℃、アスファルト乳剤は、5〜60℃、カットバ
ックアスファルトは、40〜140℃に加熱し、液状化させ
たものを用いることを特徴とする請求項1〜4のいずれ
かに記載の浸透簡易舗装方法。
6. The asphalt is any one of straight asphalt, asphalt emulsion and cutback asphalt.
130 to 180 ° C, asphalt emulsion is heated to 5 to 60 ° C, cutback asphalt is heated to 40 to 140 ° C, and liquefied one is used. Simple infiltration pavement method.
【請求項7】前記の速硬性を有する水硬性物質が、ジェ
ットセメント、ジェットセメントとポルトランドセメン
ト又は混合セメントの混合物に凝結調整剤を配合したも
の、及びポルトランドセメント又は混合セメントと速硬
性硬化材と凝結調整剤とを配合したものから選択された
ものであり、 水と前記速硬性セメントを重量比で、30〜300%混練し
て、ペースト状にしたものであることを特徴とする請求
項1〜4のいずれかに記載の浸透簡易舗装方法。
7. A hydraulic material having a quick-setting property, comprising: a jet cement, a mixture of a jet cement and a portland cement or a mixed cement with a setting modifier, and a mixture of a portland cement or a mixed cement and a quick-setting hardening material. 2. A paste selected from a mixture of a setting modifier and water, wherein the water and the quick-setting cement are kneaded at a weight ratio of 30 to 300% to form a paste. 5. The simple infiltration pavement method according to any one of items 1 to 4.
【請求項8】前記のグラウト材、接着剤、アスファルト
及び速硬性を有する水硬性物質を舗装すべき路盤上に散
布した後、骨材を敷き均し、転圧して、舗装骨材層を造
成し、その後に、工程Aを行ない、その後、工程Bを行
なうことを特徴とする請求項1〜7のいずれかに記載の
浸透簡易舗装方法。
8. A pavement aggregate layer is formed by spraying said grout material, adhesive, asphalt, and hydraulic material having quick-curing property on the roadbed to be paved, and then laying and flattening the aggregate and rolling it. The method according to any one of claims 1 to 7, wherein the step A is performed, and then the step B is performed.
【請求項9】該凝結調整剤がクエン酸、酒石酸、グルコ
ン酸或いはこれらの塩のうち、1種或いは2種以上の混
合物である有機酸系凝結遅延剤と炭酸アルカリよりなる
ものから選択されることを特徴とする請求項1〜8のい
ずれかに記載の浸透簡易舗装方法。
9. The setting regulator is selected from citric acid, tartaric acid, gluconic acid or salts thereof, which are one or a mixture of two or more of an organic acid-based retarder and an alkali carbonate. The infiltration simple pavement method according to any one of claims 1 to 8, characterized in that:
JP3162890A 1990-02-14 1990-02-14 Simple infiltration pavement method Expired - Lifetime JP2845338B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3162890A JP2845338B2 (en) 1990-02-14 1990-02-14 Simple infiltration pavement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3162890A JP2845338B2 (en) 1990-02-14 1990-02-14 Simple infiltration pavement method

Publications (2)

Publication Number Publication Date
JPH03235801A JPH03235801A (en) 1991-10-21
JP2845338B2 true JP2845338B2 (en) 1999-01-13

Family

ID=12336478

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3162890A Expired - Lifetime JP2845338B2 (en) 1990-02-14 1990-02-14 Simple infiltration pavement method

Country Status (1)

Country Link
JP (1) JP2845338B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102817299A (en) * 2012-09-05 2012-12-12 华中科技大学 Structure for repairing urban bituminous pavements and construction method thereof

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4995634B2 (en) * 2007-05-16 2012-08-08 太平洋マテリアル株式会社 Asphalt emulsion curing additive and asphalt emulsion curing method
CN104294731A (en) * 2014-10-31 2015-01-21 北京建筑大学 Filter material-included permeable cement concrete sand-based brick paving system
CN105002800B (en) * 2015-07-27 2017-04-12 福州市规划设计研究院 Pavement overhaul method and structure for treating different lane road surfaces with large road condition differences
JP7285560B2 (en) * 2019-12-27 2023-06-02 株式会社セリタ建設 Construction method of roadbed, roadbed and artificial turf pavement
CN115353344B (en) * 2022-08-10 2023-04-07 聊城市交通发展有限公司 Cement-based bonding slurry, preparation process thereof and splicing construction method of new and old pavements

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102817299A (en) * 2012-09-05 2012-12-12 华中科技大学 Structure for repairing urban bituminous pavements and construction method thereof
CN102817299B (en) * 2012-09-05 2015-04-01 华中科技大学 Structure for repairing urban bituminous pavements and construction method thereof

Also Published As

Publication number Publication date
JPH03235801A (en) 1991-10-21

Similar Documents

Publication Publication Date Title
RU2410486C2 (en) Asphalt of ultrahigh strength
US4915539A (en) Wear resistant pavement structure
ITUB20152750A1 (en) PROCEDURE FOR THE PRODUCTION OF A MIXTURE FOR THE REALIZATION OF ROAD AND SIMILAR FLOORS AND MIXTURE SO OBTAINED
JP2845338B2 (en) Simple infiltration pavement method
US5288439A (en) Method of installing a post
JP2008196145A (en) Material and method for repairing surface of pavement
JPH07300358A (en) Hydraulic grout material for paving and grout
JP4476859B2 (en) Dry mortar spraying method
JP4617084B2 (en) Construction method of porous concrete pavement
US4747878A (en) Compositions and methods of making no mix cements
EP0936311A2 (en) Road refurbishment method and mortar composition
FI3914570T3 (en) Additive for concrete and method for producing said concrete
JP7116433B2 (en) Filler for block pavement
JP7014556B2 (en) How to make concrete pavement
JP2688774B2 (en) Semi-rigid pavement method
JP3378226B2 (en) Cosmetic functionally graded water-permeable composition and method for producing the same
RU2232841C1 (en) Method of regenerating layers of road coating (variants)
FI74758B (en) FOERFARANDE FOER FRAMSTAELLNING AV BELAEGGNING FOER IDROTTSPLANER, ISYNNERHET TENNISPLANER.
JPH1018567A (en) Slide preventive durable floor material
JP2845337B2 (en) Infiltration pavement method
JP4086969B2 (en) Super fast non-shrink grout mortar
JP7356648B2 (en) Method for improving slip resistance and hardened cement
JPH0210109B2 (en)
KR100632207B1 (en) Manufacturing method of wet pavement material with crack prevention property
JP2006096627A (en) Injection material for open-graded mixture, and method of constructing semi-flexible structure using the injection material

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071030

Year of fee payment: 9

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 10

Free format text: PAYMENT UNTIL: 20081030

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081030

Year of fee payment: 10

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091030

Year of fee payment: 11

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 11

Free format text: PAYMENT UNTIL: 20091030

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091030

Year of fee payment: 11

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101030

Year of fee payment: 12

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101030

Year of fee payment: 12