JP2812590B2 - How to modify the elevator - Google Patents

How to modify the elevator

Info

Publication number
JP2812590B2
JP2812590B2 JP29201391A JP29201391A JP2812590B2 JP 2812590 B2 JP2812590 B2 JP 2812590B2 JP 29201391 A JP29201391 A JP 29201391A JP 29201391 A JP29201391 A JP 29201391A JP 2812590 B2 JP2812590 B2 JP 2812590B2
Authority
JP
Japan
Prior art keywords
car
work
elevator
existing
machine room
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP29201391A
Other languages
Japanese (ja)
Other versions
JPH05105357A (en
Inventor
敏博 中川
秀登 松沢
洋 郷古
茂信 木村
金久 横山
文則 菊地
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Building Systems Co Ltd
Original Assignee
Hitachi Building Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Building Systems Co Ltd filed Critical Hitachi Building Systems Co Ltd
Priority to JP29201391A priority Critical patent/JP2812590B2/en
Publication of JPH05105357A publication Critical patent/JPH05105357A/en
Application granted granted Critical
Publication of JP2812590B2 publication Critical patent/JP2812590B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は既設エレベータを新設エ
レベータに改造するエレベータの改造方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an elevator remodeling method for remodeling an existing elevator into a new elevator.

【0002】[0002]

【従来の技術】過去に納入された既設エレベータを新設
エレベータに改造する場合、例えば特開昭61−550
79号公報に示されたように、先ず、取替える部品およ
び追加になる部品を既設エレベータで最上階まで運び、
釣合おもりをピツトの緩衝器上に載置させる。次に乗か
ごを分解して昇降路外へ撤去し、かご枠から外した主ロ
ープを巻上機およびそらせ車から外してピツトへ下ろ
し、更に主ロープの他端を釣合おもりから外して撤去す
る。その後、巻上機および制御盤も機械室から撤去す
る。
2. Description of the Related Art When an existing elevator delivered in the past is converted into a new elevator, for example, Japanese Patent Application Laid-Open No. 61-550 / 1986
As shown in JP-A-79, first, the parts to be replaced and the parts to be added are carried to the top floor by the existing elevator,
The counterweight is placed on the pit buffer. Next, disassemble the car and remove it out of the hoistway, remove the main rope removed from the car frame from the hoisting machine and deflector car and lower it to the pit, and remove the other end of the main rope from the counterweight and remove it I do. Thereafter, the hoist and the control panel are also removed from the machine room.

【0003】次に、予め最上階に運んで置いた新設エレ
ベータの部品を取付けることになるが、先ず、新設巻上
機を設置し、新設制御盤を設置し、所定の配線を行な
う。次に昇降路に足場を組み、最初の据付作業と同じよ
うに新設エレベータの組立を行ない、主ロープを巻上機
に巻きかけ、その一端を乗かご枠に、また他端を釣合お
もりに連結し、このようにして乗かごを稼働状態にし、
その後、撤去した部品を新設エレベータで下ろして改造
作業を終えていた。
Next, parts of the newly installed elevator which has been transported to the top floor in advance are to be mounted. First, a newly installed hoist, a new control panel are installed, and predetermined wiring is performed. Next, build a scaffold on the hoistway, assemble the new elevator in the same way as the initial installation work, wind the main rope around the hoisting machine, one end on the car frame, and the other end on the counterweight. Connected, thus putting the car in operation,
After that, the removed parts were lowered by the new elevator and the remodeling work was completed.

【0004】[0004]

【発明が解決しようとする課題】このような従来の改造
方法では、作業を始めて再び新設エレベータによる稼働
状態にするには約2週間を要し、その間、サービス運転
は中止され、ビル内の交通は階段に頼らざるを得ず、関
係者に多大な迷惑をかけていた。また同公報には、この
改造作業中、仮設エレベータを設け、この仮設エレベー
タによるサービスを行なうようにすることが示されてい
るが、一時的な仮設エレベータを準備したり、またその
設置、解体のために多大な労力を費やさなければなら
ず、無駄が生じていた。
In such a conventional remodeling method, it takes about two weeks to start work and return to the operation state by the newly installed elevator, during which service operation is stopped and traffic in the building is stopped. Had to rely on the stairs, causing great inconvenience to those involved. In addition, the official gazette states that a temporary elevator will be provided during this remodeling work and that the service will be performed by the temporary elevator. Therefore, a great deal of labor has to be spent, and waste has occurred.

【0005】本発明の目的は、仮設エレベータを必要と
することなく、短時間で作業を終えることができるエレ
ベータの改造方法を提供することにある。
An object of the present invention is to provide a method for remodeling an elevator, which can complete work in a short time without requiring a temporary elevator.

【0006】[0006]

【課題を解決するための手段】本発明は上記目的を達成
するために、既設乗かごを機械室に設けた揚重装置によ
り吊り上げた状態でガイドレールに固定した受台に支持
し、上記既設乗かごの上下いずれか一方の昇降路に中間
作業床を構成し、この中間作業床の上記既設乗かごと反
対側のガイドレールに他の受台を構成し、少なくとも上
記他の受台上への新設乗かごの組立作業と、上記既設乗
かごの解体および乗り場側への撤去作業と、上記機械室
の制御盤、巻上機およびそらせ車の交換作業とを並行し
て行なう工程を含むことを特徴とする。
According to the present invention, in order to achieve the above object, an existing car is supported by a receiving stand fixed to a guide rail while being lifted by a lifting device provided in a machine room. An intermediate work floor is formed in one of the upper and lower hoistways of the car, and another cradle is formed on the guide rail on the opposite side of the existing cab of the intermediate work floor, and at least on the other cradle. Assembling the new car, dismantling the existing car and removing it to the landing side, and replacing the control panel, hoist and deflector car in the machine room in parallel. It is characterized by.

【0007】[0007]

【作用】本発明によるエレベータの改造方法は上述のよ
うに、中間作業床の一方側における新設乗かごの組立作
業と、他方側における既設乗かごの解体撤去作業と、機
械室内の交換作業とを並行して行なうようにしたため、
従来のように仮設エレベータを必要とすることなく、ま
た三個所での同時進行によつて改造作業時間を大幅に短
縮することができる。
As described above, the method for remodeling an elevator according to the present invention comprises the steps of assembling a new car on one side of the intermediate work floor, dismantling and removing the existing car on the other side, and replacing work in the machine room. Because it was done in parallel,
The remodeling work time can be greatly reduced without the need for a temporary elevator as in the prior art, and by simultaneously proceeding in three places.

【0008】[0008]

【実施例】以下、本発明の実施例を図面によつて説明す
る。図1は本発明の一実施例によるエレベータの改造方
法を示すフローチヤートである。先ず第一段階として事
前作業1が行なわれ、この事前作業1は、後に機械室に
設置される制御盤に一端を接続され、他端を各階床へ導
出される信号線の付設作業を少なくとも含んでおり、既
設エレベータのサービス運転に支障を与えることなく行
なうことができる作業あるいは夜間等の停止中に行なう
ことができる作業が選ばれている。次に行なわれる第二
段階は、詳細を後述する作業3から作業10までに示す
ようにエレベータのサービス運転を連続的に止めて行な
う本工事2である。その後、第三段階として事後作業1
2が行なわれるが、この事後作業12としては標準でな
い作業や、新設エレベータのサービス運転中あるいは短
期間の停止中に行なえるものが選ばれる。次に、これら
の各作業1,2および12の詳細について図2乃至図1
2を併用しながら説明する。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is a flowchart showing a method of modifying an elevator according to an embodiment of the present invention. First, a preparatory operation 1 is performed as a first step, and this preparatory operation 1 includes at least an operation of attaching a signal line that is connected at one end to a control panel installed in a machine room and the other end is led to each floor. Therefore, a work that can be performed without hindering the service operation of the existing elevator or a work that can be performed during stoppage at night or the like is selected. The second stage to be performed next is the main construction 2 in which the service operation of the elevator is continuously stopped as shown in operations 3 to 10 described in detail below. Then, as the third stage, post-operation 1
2, the post-operation 12 is selected to be a non-standard operation or a task that can be performed during service operation of the new elevator or during a short stop. Next, details of these operations 1, 2, and 12 will be described with reference to FIGS.
2 will be described together.

【0009】図2は事前作業1を説明するエレベータの
縦断面図であり、エレベータの乗かご20が稼働中ある
いは夜間等の停止中を示している。機械室21内には既
設制御盤22、巻上機23およびそらせ車24等が配置
され、これらに巻きかけられた主ロープ25の一端には
乗かご20が連結され、その他端には釣合おもり26が
連結されている。事前作業1は、この状態で、機械室2
1に後で納入される新設制御盤に一端を接続される図示
を省略した信号線を、昇降路の内壁に固定しながら各階
床へ導出する作業を少なくとも含んでおり、その他に既
設エレベータの運転に影響を与えずに行なえる作業や、
夜間等の停止期間中に行なえる作業を加えても良い。
FIG. 2 is a longitudinal sectional view of the elevator for explaining the preparatory work 1, and shows a state in which the elevator car 20 is operating or stopped at night or the like. An existing control panel 22, a hoisting machine 23, a deflecting wheel 24, and the like are arranged in the machine room 21, a car 20 is connected to one end of a main rope 25 wound around these, and a balance is connected to the other end. A weight 26 is connected. In the preparatory work 1, the machine room 2
1. Includes at least the work of leading out to each floor while fixing the unillustrated signal line, one end of which is connected to the newly installed control panel to be delivered later, to the inner floor of the hoistway. Work that can be done without affecting
Operations that can be performed during a suspension period such as nighttime may be added.

【0010】その後、エレベータのサービス運転を停止
して本工事2を行なう。この本工事2は、先ず養生と主
ロープ外し作業3から行なわれる。つまり図3に示すよ
うに、乗かご20を最上階からかご上に乗れるような位
置に停止させ、後述する中間作業床32を設ける近傍の
階床乗り場を養生手段27でそれぞれ養生すると共に、
機械室21においてチエーンブロツク等から成る揚重装
置28を構成し、この揚重装置28によつて吊りロープ
29を介して乗かご20を吊り下げ、更にこれと同時に
釣合おもり26を支持材30で支持する。その後、揚重
装置28によつて乗かご20を少し吊り上げた状態に
し、既設主ロープ25を取り外す。
After that, the service operation of the elevator is stopped, and the main construction 2 is performed. The main construction 2 is first performed from the curing and the main rope removal work 3. That is, as shown in FIG. 3, the car 20 is stopped at a position where the car can be put on the car from the top floor, and the floor platform near the intermediate work floor 32 described later is cured by the curing means 27, respectively.
In the machine room 21, a lifting device 28 composed of a chain block or the like is constructed, and the lifting device 28 suspends the car 20 via a suspension rope 29, and at the same time, simultaneously mounts the counterweight 26 on the supporting material 30. Support with. Thereafter, the car 20 is slightly lifted by the lifting device 28, and the existing main rope 25 is removed.

【0011】その後、図4に示すように揚重装置28に
よつて乗かご20を昇降路31の下部、つまり最下階近
傍まで吊り下げ、図示を省略したガイドレールに固定し
た受台35上に支持させ、このようにして乗かご20の
降ろし支持作業4を行なう。次いで、機械室21の揚重
装置28および吊りロープ29を撤去し、図5に示すよ
うに中間作業床の構成作業5を行なう。つまり昇降路3
1における既設乗かご20の上部近傍に中間作業床32
を構成する。次に、この組立られた中間作業床32から
新設乗かごを支持させるための受台34を中間作業床3
2の上部に位置するガイドレールに固定する。
Thereafter, as shown in FIG. 4, the car 20 is suspended by the lifting device 28 to a lower portion of the hoistway 31, that is, to the vicinity of the lowest floor. , And the support operation 4 for lowering the car 20 is performed in this manner. Next, the lifting device 28 and the hanging rope 29 in the machine room 21 are removed, and the construction work 5 of the intermediate work floor is performed as shown in FIG. That is, hoistway 3
In the vicinity of the upper part of the existing car 20 in FIG.
Is configured. Next, a pedestal 34 for supporting the newly installed car from the assembled intermediate work floor 32 is moved to the intermediate work floor 3.
2 fixed to the guide rail located at the top.

【0012】この中間作業床の構成作業5が終了する
と、今度は、解体組立作業6である。図6に示すように
中間作業床32からガイドレールへ固定した受台34上
に新設乗かご36を組立てると同時に、既設乗かご20
を解体しながら乗り場側へ撤去させる作業を同時に進め
る。しかも図6に示すように、これらの作業に並行して
機械室21では、既設制御盤22、既設巻上機23およ
び既設そらせ車24の解体撤去作業と、新設制御盤3
7、新設巻上機38および新設そらせ車39の組立付設
作業から成る交換作業を行なつている。従つて、中間作
業床32の上方部、下方部および機械室21という三個
所での作業が並行することになり、作業時間の短縮が一
層図られている。なお、上記した構成作業5の中で各階
床ごとの信号線の接続作業等をおこなう。
When the construction work 5 of the intermediate work floor is completed, the disassembly and assembly work 6 is now performed. As shown in FIG. 6, a new car 36 is assembled on a receiving stand 34 fixed to the guide rail from the intermediate work floor 32, and at the same time, the existing car 20 is assembled.
At the same time, dismantling and removing to the platform side. Further, as shown in FIG. 6, in parallel with these operations, in the machine room 21, the dismantling and removal of the existing control panel 22, the existing hoisting machine 23 and the existing deflecting vehicle 24, and the new control panel 3
7. The replacement work including the work of assembling and installing the new hoisting machine 38 and the new deflecting wheel 39 is performed. Accordingly, the work in three places, the upper part, the lower part, and the machine room 21 of the intermediate work floor 32 is performed in parallel, and the working time is further reduced. In addition, in the above-mentioned configuration work 5, connection work of signal lines for each floor is performed.

【0013】その後、図7に示すように乗かご吊り作業
7を行なうが、機械室21に再び揚重装置28を組立
て、吊りロープ29を介して新設乗かご36と連結し、
この揚重装置28によつて新設乗かご36を最上階付近
まで吊り上げると共に、受台34,35の解体撤去を行
なう。その状態で新設主ロープ40を新設巻上機38お
よび新設そらせ車39に掛け、その一端を新設乗かご3
6に連結すると共に、昇降路下部に枠組足場33を構成
し、この枠組足場33を利用して中間作業床32を解体
し、またこの枠組足場33を利用して新設主ロープ40
の他端と釣合おもり26との連結を行なう。その後、図
8に示すように揚重装置の撤去作業8を行なう。つまり
機械室21の揚重装置28を解体撤去し、また各階床に
設けていた養生手段27を撤去する。次いで、図9に示
すように試運転および調整作業9として、乗かご36を
下降させ、釣合おもり26を支持していた支持材30を
撤去し、新設乗かご36の試運転と調整を行なう。
Thereafter, as shown in FIG. 7, the car hanging operation 7 is performed. The lifting device 28 is assembled again in the machine room 21 and connected to the newly installed car 36 via the hanging rope 29.
With the lifting device 28, the newly-installed car 36 is lifted to the vicinity of the top floor, and the cradles 34 and 35 are dismantled and removed. In this state, the new main rope 40 is hung on the new hoisting machine 38 and the new deflecting car 39, and one end thereof is connected to the new car 3
6, a frame scaffold 33 is formed at the lower part of the hoistway, the intermediate work floor 32 is dismantled by using the frame scaffold 33, and a new main rope 40 is constructed by using the frame scaffold 33.
And the counterweight 26 are connected. Then, as shown in FIG. 8, the lifting operation 8 of the lifting device is performed. That is, the lifting device 28 of the machine room 21 is dismantled and removed, and the curing means 27 provided on each floor is removed. Next, as shown in FIG. 9, as the test run and adjustment work 9, the car 36 is lowered, the support member 30 supporting the counterweight 26 is removed, and the test run and adjustment of the new car 36 are performed.

【0014】その後、図10および図11に示すように
出入口改造作業10を行なうわけであるが、乗かご36
の上部に作業床41を設け、乗かご36を下降させなが
ら各階床の出入口の改造、例えば既設階床扉を新設階床
扉に取替えたりする。最下階については、図11に示す
ように乗り場を養生手段27で養生して昇降路31内に
枠組足場33を再び構成し、この枠組足場33を利用し
ながら行ない、その後、枠組足場33を撤去する。
Thereafter, as shown in FIGS. 10 and 11, the entrance remodeling work 10 is performed.
A work floor 41 is provided in the upper part of the car, and the entrance of each floor is modified while the car 36 is lowered, for example, an existing floor door is replaced with a new floor door. As for the lowest floor, as shown in FIG. 11, the platform is cured by the curing means 27 to reconstruct the framed scaffold 33 in the hoistway 31, and the frame scaffold 33 is used while using the framed scaffold 33. Remove it.

【0015】これら一連の作業の終了後、図12に示す
ように事後作業12を行なう。この事後作業12は、新
設エレベータによる稼働中あるいはその後の適当な時期
を見つけて新設エレベータを短時間停止させて行なう
が、例えば釣合おもり26を新設品に変えるなどの標準
でない作業あるいは短時間停止中に行なえる他の簡単な
作業である。
After the end of these series of operations, a post operation 12 is performed as shown in FIG. This post-operation 12 is performed while the new elevator is in operation or at an appropriate time thereafter, and the new elevator is stopped for a short time. For example, non-standard work such as changing the counterweight 26 to a new product or a short stoppage is performed. Other simple tasks that can be done inside.

【0016】尚、上述の実施例においては、中間作業床
32の上方に設けた受台34へ新設乗かご36を構成
し、下方の受台35に既設乗かご20を支持させて解体
撤去するようにしたが、受台34、35への支持を逆に
し、つまり図5に示す上方の受台34へ既設乗かご20
を支持し、また下方の受台35へ新設乗かご36を組立
てるようにしても良い。更に、中間作業床32は昇降路
31の図示の位置に限らず、より上方に構成しても良
い。また上述の実施例における養生手段27の撤去時期
は図示の場合に限らず、適当な時期に行なうことができ
るし、また図11に示すように後に再度設ける養生手段
27は、状況が許すなら図7に示す時期から解体せずに
構成しておくこともできる。
In the above-described embodiment, a new car 36 is constructed on the cradle 34 provided above the intermediate work floor 32, and the existing cab 20 is supported on the lower cradle 35 for disassembly and removal. However, the support on the cradle 34, 35 is reversed, that is, the existing car 20 is placed on the upper cradle 34 shown in FIG.
, And a new car 36 may be assembled to the lower cradle 35. Further, the intermediate work floor 32 is not limited to the illustrated position of the hoistway 31, and may be configured to be higher. In addition, the time for removing the curing means 27 in the above-described embodiment is not limited to the case shown in the figure, and can be performed at an appropriate time. Further, as shown in FIG. It is also possible to configure without dismantling from the time shown in FIG.

【0017】[0017]

【発明の効果】以上説明したように本発明は、昇降路に
中間作業床を構成し、この中間作業床の上下の一方側で
行なう新設乗かごの組立て作業と、他方側で行なう既設
乗かごの解体撤去作業と、機械室での交換作業を並行し
て行なう工程を含むようにしたため、仮設エレベータを
設ける必要がなく、また並行して行なう上述の作業によ
つて改造時間を大幅に短縮することができる。
As described above, according to the present invention, an intermediate work floor is formed in a hoistway, and an assembling operation of a new car performed on one of the upper and lower sides of the intermediate work floor and an existing car performed on the other side. The step of performing dismantling and removal work in parallel with the replacement work in the machine room eliminates the need for provision of a temporary elevator, and greatly reduces the time required for remodeling due to the work performed in parallel. be able to.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施例によるエレベータの改造方法
を示すフローチヤートである。
FIG. 1 is a flowchart illustrating a method for retrofitting an elevator according to an embodiment of the present invention.

【図2】図1の事前作業を示す昇降路の縦断面図であ
る。
FIG. 2 is a vertical sectional view of a hoistway showing a preparatory operation of FIG.

【図3】図1の本工事の養生と主ロープ外し作業を示す
昇降路の縦断面図である。
FIG. 3 is a vertical sectional view of a hoistway showing a curing operation and a main rope removing operation of the main construction of FIG.

【図4】図1の乗かご降ろし支持作業を示す昇降路の縦
断面図である。
FIG. 4 is a longitudinal sectional view of a hoistway showing a car-unloading support operation of FIG. 1;

【図5】図1の中間作業床の構成作業を示す昇降路の縦
断面図である。
FIG. 5 is a vertical sectional view of a hoistway showing a construction work of the intermediate work floor of FIG. 1;

【図6】図1の解体組立作業を示す昇降路の縦断面図で
ある。
6 is a vertical sectional view of the hoistway showing the disassembly and assembly work of FIG.

【図7】図1の乗かご吊り作業を示す昇降路の縦断面図
である。
7 is a longitudinal sectional view of the hoistway showing the car hanging operation of FIG.

【図8】図1の揚重装置の撤去作業を示す昇降路の縦断
面図である。
FIG. 8 is a vertical sectional view of a hoistway showing a removal operation of the lifting device of FIG. 1;

【図9】図1の試運転および調整作業を示す昇降路の縦
断面図である。
FIG. 9 is a longitudinal sectional view of the hoistway showing the test operation and the adjustment work of FIG. 1;

【図10】図1の出入口改造作業を示す昇降路の縦断面
図である。
FIG. 10 is a vertical sectional view of a hoistway showing the entrance remodeling work of FIG.

【図11】図1の出入口改造作業を示す昇降路の縦断面
図である。
FIG. 11 is a vertical sectional view of a hoistway showing an entrance remodeling operation of FIG.

【図12】図1の事後作業を示す昇降路の縦断面図であ
る。
FIG. 12 is a longitudinal sectional view of the hoistway showing the post-operation of FIG. 1;

【符号の説明】[Explanation of symbols]

1 事前作業 2 本工事 3 養生と主ロープ外し作業 4 乗かご降ろし支持作業 5 中間作業床の構成作業 6 解体組立作業 7 乗かご吊り作業 8 揚重装置の撤去作業 9 試運転および調整作業 10 出入口改造作業 12 事後作業 20 既設乗かご 21 機械室 25 既設主ロープ 27 受台 28 揚重装置 31 昇降路 32 中間作業床 33 枠組足場 36 新設乗かご 37 新設制御盤 40 新設主ロープ Reference Signs List 1 Preliminary work 2 Main work 3 Curing and removal of main ropes 4 Support for unloading and supporting the car 5 Construction work for the intermediate work floor 6 Dismantling and assembling work 7 Hanging the car 8 Work for removing the lifting device 9 Trial run and adjustment work 10 Remodeling the entrance Work 12 Post-work 20 Existing car 21 Machine room 25 Existing main rope 27 Cradle 28 Lifting device 31 Hoistway 32 Intermediate work floor 33 Frame scaffold 36 New car 37 New control panel 40 New main rope

───────────────────────────────────────────────────── フロントページの続き (72)発明者 郷古 洋 東京都千代田区神田錦町1丁目6番地 株式会社日立ビルシステムサービス内 (72)発明者 木村 茂信 茨城県勝田市堀口832番地の2 日立エ レベータエンジニアリング株式会社内 (72)発明者 横山 金久 東京都千代田区神田錦町1丁目6番地 株式会社日立ビルシステムサービス内 (72)発明者 菊地 文則 東京都千代田区神田錦町1丁目6番地 株式会社日立ビルシステムサービス内 (56)参考文献 特開 昭63−218493(JP,A) 特開 平5−105356(JP,A) (58)調査した分野(Int.Cl.6,DB名) B66B 7/00──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Hiroshi Goko 1-6-6 Kandanishikicho, Chiyoda-ku, Tokyo Within Hitachi Building System Service Co., Ltd. (72) Inventor Shigenobu Kimura 832-2 Horiguchi, Katsuta-shi, Ibaraki 2 Hitachi, Ltd. Within the Beta Engineering Co., Ltd. (72) Inventor Kanehisa 1-6-6 Kandanishikicho, Chiyoda-ku, Tokyo Within Hitachi Building System Services (72) Inventor Fuminori Kikuchi 1-6-6 Kandanishikicho, Chiyoda-ku, Tokyo Hitachi Building, Ltd. (56) References JP-A-63-218493 (JP, A) JP-A-5-105356 (JP, A) (58) Fields investigated (Int. Cl. 6 , DB name) B66B 7/00

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 機械室の巻上機およびそらせ車を介して
設けた主ロープの一端に乗かごを連結し、また他端に釣
合おもりを連結して成り、少なくとも上記機械室の制御
盤、巻上機およびそらせ車と、上記乗かごを新設品に交
換するエレベータの改造方法において、既設乗かごを上
記機械室に設けた揚重装置により吊り上げた状態でガイ
ドレールに固定した受台に支持し、上記既設乗かごの上
下いずれか一方の昇降路に中間作業床を構成し、この中
間作業床の上記既設乗かごと反対側のガイドレールに他
の受台を構成し、少なくとも上記他の受台上への新設乗
かごの組立作業と、上記既設乗かごの解体および乗り場
側への撤去作業と、上記機械室の制御盤、巻上機および
そらせ車の交換作業とを並行して行なう工程を含むこと
を特徴とするエレベータの改造方法。
1. A control panel for at least a control panel of the machine room, wherein a car is connected to one end of a main rope provided via a hoisting machine and a deflector wheel in a machine room, and a counterweight is connected to the other end. In the method of remodeling an elevator for exchanging the car with a hoisting machine and a deflecting car and the above-mentioned car, the existing car is lifted by a lifting device provided in the machine room, and is fixed to a guide rail fixed to a guide rail. Supporting, forming an intermediate work floor on one of the upper and lower hoistways of the existing car, and configuring another receiving stand on the guide rail on the opposite side of the existing work cage on the intermediate work floor, In parallel with the work of assembling the new car on the cradle, dismantling the existing car and removing it to the landing side, and replacing the control panel, hoist and deflector car in the machine room Elevating, comprising the step of performing How to modify the data.
【請求項2】 上記請求項1記載のものにおいて、上記
工程の後、上記新設乗かごを用いての運転と共に出入り
口改造作業を行なうことを特徴とするエレベータの改造
方法。
2. The method for remodeling an elevator according to claim 1, wherein after the above-mentioned steps, the doorway is remodeled together with the operation using the new car.
JP29201391A 1991-10-14 1991-10-14 How to modify the elevator Expired - Lifetime JP2812590B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP29201391A JP2812590B2 (en) 1991-10-14 1991-10-14 How to modify the elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP29201391A JP2812590B2 (en) 1991-10-14 1991-10-14 How to modify the elevator

Publications (2)

Publication Number Publication Date
JPH05105357A JPH05105357A (en) 1993-04-27
JP2812590B2 true JP2812590B2 (en) 1998-10-22

Family

ID=17776399

Family Applications (1)

Application Number Title Priority Date Filing Date
JP29201391A Expired - Lifetime JP2812590B2 (en) 1991-10-14 1991-10-14 How to modify the elevator

Country Status (1)

Country Link
JP (1) JP2812590B2 (en)

Also Published As

Publication number Publication date
JPH05105357A (en) 1993-04-27

Similar Documents

Publication Publication Date Title
JP2812590B2 (en) How to modify the elevator
JP2812591B2 (en) How to modify the elevator
JP3844944B2 (en) Demolition method of construction elevator
JP2620123B2 (en) Temporary lifting equipment for construction work
JP2812592B2 (en) How to modify the elevator
JP2812589B2 (en) How to modify the elevator
JP2612393B2 (en) How to modify the elevator
EP3907170A1 (en) Jumping elevator system and jumping method used in construction process of building
JP3195124B2 (en) How to modify the elevator
JP3193609B2 (en) Elevator installation method
JPH0597345A (en) Modification of elevator
JP2001335255A (en) Elevator installation construction method, and elevator installation unit
JPH05105354A (en) Elevator modifying method
JP3872833B2 (en) Elevator repair method
JP3920527B2 (en) Elevator for construction
JPH05262475A (en) Installation method of elevator
JPH04213581A (en) Installation method for linear motor type elevator
JPH10218527A (en) Temporary elevator and installing method thereof
JP2000095456A (en) Temporary operation device for elevator
JP2003292268A (en) Load receiving bracket
CN116812719A (en) Application method of construction lifter and construction lifter
JPH05201648A (en) Installation of elevator
JPH0747453B2 (en) Elevator installation method
JPH10218529A (en) Replacement method of elevator main rope
JP3035099B2 (en) Elevator main cable replacement method