JP2780571B2 - Reinforcing cage construction equipment - Google Patents

Reinforcing cage construction equipment

Info

Publication number
JP2780571B2
JP2780571B2 JP15974192A JP15974192A JP2780571B2 JP 2780571 B2 JP2780571 B2 JP 2780571B2 JP 15974192 A JP15974192 A JP 15974192A JP 15974192 A JP15974192 A JP 15974192A JP 2780571 B2 JP2780571 B2 JP 2780571B2
Authority
JP
Japan
Prior art keywords
cage
main frame
reinforcing
frame
vertical hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP15974192A
Other languages
Japanese (ja)
Other versions
JPH062437A (en
Inventor
斎藤  博
登美男 加藤
仁 渋谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP15974192A priority Critical patent/JP2780571B2/en
Publication of JPH062437A publication Critical patent/JPH062437A/en
Application granted granted Critical
Publication of JP2780571B2 publication Critical patent/JP2780571B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は鉄筋籠の建込み装置に
関し、特に、高さ制限のある場所や狭い作業現場におい
て鉄筋籠を縦穴に建込む場合に好適な鉄筋籠の建込み装
置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an apparatus for building a reinforced cage, and more particularly to a reinforced basket building apparatus suitable for setting a reinforced cage in a vertical hole in a place having a limited height or a narrow work site.

【0002】[0002]

【従来の技術】例えば高架道路等の路面下の作業空間か
らさらにその下方の地盤を掘り下げて地下連続壁を構築
する場合、高さに制限が生ずるため、クローラクレーン
等の吊り込み用の重機を使用して鉄筋籠を縦穴に一度に
建込むことが出来ないという不都合が生じる。このた
め、鉄筋籠を長手方向に複数分割し、縦孔に既に挿入し
た鉄筋籠を、これの上端部を貫通する仮受けバーによっ
て支持しつつ、これの上端に次の分割した鉄筋籠を継足
しながら順次鉄筋籠を挿入して行く工法が採用されてい
るが、以下のような問題点があった。
2. Description of the Related Art For example, when constructing an underground continuous wall by digging a ground below a working space below a road surface such as an elevated road or the like, since a height is limited, a heavy machine for hanging such as a crawler crane is used. There is an inconvenience that the steel cage cannot be installed in the vertical hole at one time. For this reason, the rebar cage is divided into a plurality of pieces in the longitudinal direction, and the rebar basket already inserted in the vertical hole is supported by the temporary receiving bar penetrating the upper end thereof, and the next divided rebar cage is connected to the upper end thereof. The construction method in which reinforced cages are sequentially inserted while being added has been adopted, but has the following problems.

【0003】[0003]

【発明が解決しようとする課題】すなわち、この種の高
さ制限のある場所での鉄筋籠の建込みに用いられる装置
としては、従来は電気ホイストやチェンブロック等が用
いられていたが、これらの装置にあっては、鉄筋籠を継
ぎ足す毎にこれの重量が増すため、大深度の鉄筋籠を建
込む場合その総重量が装置の能力の限界を上回る惧れが
あるほか、鉄筋籠同士を継足すときの鉛直度の調整が困
難で、かつその継足し作業に時間かかり、施工性に劣る
という問題点があった。
That is, electric hoists, chain blocks and the like have conventionally been used as a device used for building a reinforcing bar cage in a place having a height restriction of this kind. The weight of this equipment increases each time a reinforcing cage is added.Therefore, when building a reinforcing steel basket at a large depth, the total weight may exceed the limit of the capacity of the equipment. There is a problem that it is difficult to adjust the verticality at the time of refilling, and it takes a long time to perform the reloading operation, resulting in poor workability.

【0004】そこで、この発明は以上の問題点を解決す
るものであって、その目的は、分割した鉄筋籠の吊り込
み及び継足し作業を容易にして、高さ制限のある場所や
狭い作用現場においても迅速かつ容易に建込み作業を行
なうことができるとともに、鉄筋籠を鉛直方向に精度良
く継足して行くことのできる鉄筋籠の建込み装置を提供
することにある。
Accordingly, the present invention has been made to solve the above problems, and an object of the present invention is to make it easy to suspend and reinforce a divided reinforced cage, and to restrict the height of a place having a limited height or a narrow working site. It is also an object of the present invention to provide a reinforcing cage building apparatus capable of quickly and easily performing a setting work and also capable of accurately adding a reinforcing cage in a vertical direction.

【0005】[0005]

【課題を解決するための手段】前記目的を達成するた
め、この発明の鉄筋籠の建込み装置は、地中に設けた縦
穴に鉄筋籠を建込むための装置であって、箱状に枠組み
され、前記縦穴の開口部を跨いで設置されるメインフレ
ームと、該メインフレームのベース部から立設する少な
くとも4本の伸縮ジャッキと、該伸縮ジャッキの上端に
架設され、前記メインフレームの内側において昇降する
とともに、滑車を有する昇降フレームと、一端を前記メ
インフレームに取付けるとともに、前記滑車に巻装され
て下方に懸吊し、他端には鉄筋籠を吊持するための係止
部材を備えたチェーン、ワイヤー等の吊り部材とからな
ることを特徴とするものである。
In order to achieve the above-mentioned object, the present invention provides an apparatus for installing a reinforcing cage in a vertical hole provided in the ground, comprising a box-shaped framework. And a main frame installed across the opening of the vertical hole, at least four telescopic jacks erected from the base of the main frame, and installed at the upper end of the telescopic jack, inside the main frame. Elevating frame having a pulley while raising and lowering, and a locking member for attaching one end to the main frame, being wound around the pulley and hanging down, and having the other end hanging a reinforcing bar cage. And a hanging member such as a chain or a wire.

【0006】なお、本発明は、鉄筋籠の建込みの際に用
いる場合が多く、また利用価値が高いため、象徴的に鉄
筋籠の建込み装置としているが、他の鋼材、例えばH鋼
等の建込みの際にも適宜使用することができる。
[0006] The present invention is often used for the construction of a steel cage, and has high utility value. Therefore, the present invention is symbolically used as a device for building a steel cage, but other steel materials, such as H steel, etc. Can also be used as appropriate when erected.

【0007】[0007]

【作用】上記構成を有するこの発明の鉄筋籠の建込み装
置では、メインフレームによって鉄筋籠の吊り代が常に
確保されるとともに、鉄筋籠の建込み、継足し作業はメ
インフレームにより画定された作業領域内で行われるた
め、狭い作用現場においての周囲の既設構造物等に障害
を及ぼすことなく安全に作業を行なうことができる。
In the rebar cage setting device of the present invention having the above-described structure, the hanging margin of the rebar basket is always ensured by the main frame, and the rebar basket setting and extending work is performed by the work defined by the main frame. Since the work is performed in the area, the work can be performed safely without impeding surrounding existing structures and the like at the narrow working site.

【0008】また、建込み、あるいは継足すべき鉄筋籠
は、昇降フレームを介して少なくとも4本の伸縮ジヤッ
キによって支持されるので、これらの伸縮ジヤッキの伸
縮量を調整することにより、鉄筋籠の鉛直方向へ建込
み、あるいは継足しを精度良く管理することができる。
Further, since the reinforcing cage to be built or extended is supported by at least four extendable jacks via the lifting frame, the amount of expansion and contraction of these extendable jacks is adjusted so that the vertical position of the reinforcing cage is adjusted. The building in the direction or the extension can be managed accurately.

【0009】[0009]

【実施例】以下、本発明の一実施例を図面を用いて詳細
に説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS One embodiment of the present invention will be described below in detail with reference to the drawings.

【0010】図1(a),(b),(c)はこの発明に
係る鉄筋籠の建込み装置を示すものである。図における
建込み装置は、連続地中壁を構築するための縦穴1の上
部を跨いで設置されるメインフレーム2と、メインフレ
ーム2のベース2aから立設する4本の油圧ジャッキ3
と、メインフレーム2の内側にあって、前記油圧ジャッ
キ3の上端に架設されてるとともに、ガイド用スプロケ
ット7を有する昇降フレーム4と、一端をメインフレー
ムに取り付けるとともに、前記ガイド用スプロケット7
を介して他端が下方に懸吊する、先端に係止部材9を備
えたチェーン8とによって構成されている。
FIGS. 1 (a), 1 (b) and 1 (c) show a reinforced basket setting device according to the present invention. The construction device in the figure includes a main frame 2 installed over a vertical hole 1 for constructing a continuous underground wall, and four hydraulic jacks 3 erected from a base 2a of the main frame 2.
And an elevating frame 4 which is provided inside the main frame 2 and at the upper end of the hydraulic jack 3 and has a guide sprocket 7, and one end attached to the main frame and the guide sprocket 7
, The other end of which is suspended downward, and a chain 8 having a locking member 9 at the tip.

【0011】メインフレーム2は、連続地中壁を構成す
る1ガット分の縦穴1の平面長さ及び幅に応じて鉄骨を
矩形状に枠組みしたベース2a上に前後門型に立設さ
れ、かつ上端を矩形に連接することにより箱状に枠組み
された支持フレーム2bと、支持フレーム2bの上部及
び外側3面にx字形をなして一体化された補強ブレース
2cとからなり、残りの1面を鉄筋籠6の受入用開口と
している。
The main frame 2 is vertically erected on a base 2a in which a steel frame is framed in a rectangular shape in accordance with the plane length and width of the vertical hole 1 for one gut constituting the continuous underground wall, and A support frame 2b framed in a box shape by connecting its upper end to a rectangle, and a reinforcing brace 2c integrated in an x-shape on the upper and outer three surfaces of the support frame 2b, and the remaining one surface is It is an opening for receiving the reinforcing bar 6.

【0012】昇降フレーム4は前記油圧ジャッキ3の頂
部に突出するプランジャ3aの上端に連結されたもので
あり、プランジャ3aの突出ストロークに応じて支持フ
レーム2bのほぼ中間位置から最上部の間を昇降する。
また、この昇降フレーム4の内、図1(a)において左
右方向に延長する一対のフレームには、これと平行にス
リット4aが各々形成され、この各スリット4aには一
対のガイド用スプロケット7が合計4か所軸受けされて
いる。
The lifting frame 4 is connected to the upper end of a plunger 3a projecting from the top of the hydraulic jack 3. The lifting frame 4 moves up and down between a substantially middle position and an uppermost position of the support frame 2b in accordance with the projecting stroke of the plunger 3a. I do.
1A, slits 4a are formed in parallel with the pair of frames extending in the left-right direction in FIG. 1A, and a pair of guide sprockets 7 is provided in each slit 4a. There are a total of four bearings.

【0013】そして、各スプロケット7には、一端を前
記ベース2aに固定具8aを介して固定されたチェーン
8が巻装している。すなわち、このチェーン8はスプロ
ケット7を通じて昇降フレーム4に掛け回され、その他
端はカウンターウエイト5によりたるみを生じることな
く下方に懸吊している。
A chain 8 having one end fixed to the base 2a via a fixture 8a is wound around each sprocket 7. That is, the chain 8 is hung around the lifting frame 4 through the sprocket 7, and the other end is suspended downward by the counterweight 5 without sagging.

【0014】したがって、昇降フレーム4の最上昇位置
においてはチェーン8が引かれる結果、カウンターウエ
イト5は昇降フレーム4の直下に接して位置する。ま
た、昇降フレーム4が最低位置、すなわち支持フレーム
2bの中間位置まで下降すると、チェーン8が繰り出さ
れる結果、カウンターウエイト5はその二倍のストロー
ク量である支持フレーム2bの下部まで下降し、その結
果鉄筋籠6を図1(b),(c)の想像線位置まで下降
させることが出来る。
Therefore, as a result of the chain 8 being pulled at the highest position of the lifting frame 4, the counterweight 5 is located immediately below the lifting frame 4. When the elevating frame 4 is lowered to the lowest position, that is, the intermediate position of the support frame 2b, the chain 8 is extended, and as a result, the counterweight 5 is lowered to the lower part of the support frame 2b, which is twice the stroke amount. The rebar basket 6 can be lowered to the imaginary line positions in FIGS. 1 (b) and 1 (c).

【0015】また、カウンターウエイト5には、その下
部4箇所にシャックル等からなる係止部材9が設けら
れ、これによって前記鉄筋籠6の上部に設けた水平の連
結バー6aを係止して鉄筋籠6を吊り下げるようににな
っている。
The counterweight 5 is provided with a locking member 9 made of a shackle or the like at four locations below the counterweight 5, whereby a horizontal connecting bar 6a provided on the upper part of the reinforcing bar cage 6 is locked to rebar. The basket 6 is suspended.

【0016】次に以上の構成からなる鉄筋の建込み装置
を用いた鉄筋籠の建込み手順を図2を用いて説明する。
まず、掘削された縦穴1の上部にメインフレーム2を位
置決め設置する。これの移動はベース2aをジャッキア
ップし、コロをはさみこみ滑らせることによって移動さ
せ、目的位置に位置決めされたなら、再度ジャッキアッ
プし、コロを取り外すことによって容易に行うことがで
きる。
Next, a procedure for building a reinforcing bar cage using the reinforcing bar building apparatus having the above configuration will be described with reference to FIG.
First, the main frame 2 is positioned and installed above the excavated vertical hole 1. This movement can be easily performed by jacking up the base 2a and moving it by inserting and sliding the rollers, and when it is positioned at the target position, jacking up again and removing the rollers.

【0017】次いで油圧ジャッキ3のプランジャ3aを
伸ばし昇降フレーム4を最上昇位置に位置させる。この
状態ではカウンターウェイト5は昇降フレーム4の下面
に接し、この状態で支持フレーム2bの開口を通じてメ
インフレーム2の内部に最初の鉄筋籠6を供給し、その
上端を係止部材9に引っ掛け係止すれば、図2(a)に
示すように支持フレーム2aの内側に鉄筋籠6を吊り下
げることができる。なお、鉄筋籠の供給にはフォークリ
フトなどを用いれば、吊り下げの際の上下位置の位置決
めなどの微調整を簡単に行なうことができる。
Next, the plunger 3a of the hydraulic jack 3 is extended and the lifting frame 4 is positioned at the highest position. In this state, the counterweight 5 is in contact with the lower surface of the elevating frame 4, and in this state, the first rebar cage 6 is supplied into the main frame 2 through the opening of the support frame 2b, and the upper end thereof is hooked on the locking member 9 and locked. Then, as shown in FIG. 2A, the reinforcing cage 6 can be hung inside the support frame 2a. If a forklift or the like is used to supply the reinforcing bar, fine adjustment such as positioning of the vertical position during suspension can be easily performed.

【0018】鉄筋籠6を吊り下げたら昇降フレーム4を
下降する。そして、油圧ジャッキ3の下降動作により、
昇降フレーム4が支持フレーム2bの中間位置まで下降
するに従い、チェーン8が繰り出され、昇降フレーム4
の下降位置ではそのストロークの二倍量のストロークの
位置まで下降し、図2(b)に示すように上端部を縦穴
1の開口の上方にやや露出させた状態で、鉄筋籠6を縦
穴1の内部に挿入することができる。そして、この状態
で一対の仮受け梁10を連結バー6aの直下に交差して
差し込んで縦穴1の開口面に掛け渡し、この仮受け梁1
0に鉄筋籠6の荷重を支持させた後に、係止部材9を連
結バー6aから取り外す。
When the reinforcing cage 6 is suspended, the lifting frame 4 is lowered. And, by the lowering operation of the hydraulic jack 3,
As the lifting frame 4 descends to the intermediate position of the support frame 2b, the chain 8 is extended, and the lifting frame 4
Is lowered to the position of the stroke twice as much as that stroke, and the reinforcing bar 6 is inserted into the vertical hole 1 with the upper end slightly exposed above the opening of the vertical hole 1 as shown in FIG. Can be inserted inside. Then, in this state, a pair of temporary receiving beams 10 are inserted across the connection bar 6a just across the connecting bar 6a, and bridged over the opening surface of the vertical hole 1.
After the load of the reinforcing bar 6 is supported at 0, the locking member 9 is removed from the connecting bar 6a.

【0019】次いで、再度昇降フレーム4を上昇させれ
ば次の鉄筋籠6の受入待機状態となり、図2(c)に示
すように、次の鉄筋籠6を吊り下げ、下降動作させるこ
とが出来る。ある程度下降動作させた状態では図2
(d)に示すように次の鉄筋籠6の下端が既に仮受けさ
れている最初の鉄筋籠6の上端に重複する。この時点で
一端下降動作を停止し、重複部分を溶接またはカップラ
ーなどにより連結するのであるが、かかる鉄筋籠6の接
合の前に、前記4本の油圧ジャッキ3の伸縮量を調整す
ることにより、左右及び前後方向の傾きを修正して鉄筋
籠6を垂直方向に精度良く接合することができる。
Next, when the lifting frame 4 is raised again, the next rebar cage 6 is in a standby state for receiving the next rebar cage 6, and as shown in FIG. 2C, the next rebar basket 6 can be suspended and lowered. . Fig. 2
As shown in (d), the lower end of the next rebar basket 6 overlaps the upper end of the first rebar basket 6 that has already been provisionally received. At this point, the lowering operation is temporarily stopped, and the overlapped portion is connected by welding or a coupler, etc. Before the joining of the rebar cage 6, by adjusting the amount of expansion and contraction of the four hydraulic jacks 3, The reinforcing bars 6 can be joined in the vertical direction with high accuracy by correcting the inclination in the left-right and front-back directions.

【0020】鉄筋籠6の接合が完了したら、後仮受け梁
10を外し、昇降フレーム4を下降動作すれば、図2
(e)に示すように鉄筋籠6は連結状態のままさらに下
降して、縦穴1内に挿入されて行く。この際にも前記油
圧ジャッキ3の伸縮量を調整して、鉄筋籠6を垂直方向
に精度良く建込んで行くことができる。そして、上端部
が縦穴1の開口の上方にやや露出する状態まで鉄筋籠6
を挿入したら、再び昇降フレーム4を下降動作を停止す
る。
When the joining of the reinforcing cage 6 is completed, the temporary provisional receiving beam 10 is removed, and the lifting frame 4 is moved downward, as shown in FIG.
As shown in (e), the rebar cage 6 is further lowered while being connected, and is inserted into the vertical hole 1. Also in this case, by adjusting the amount of expansion and contraction of the hydraulic jack 3, the rebar cage 6 can be accurately built in the vertical direction. Then, the reinforcing rod cage 6 is set until the upper end is slightly exposed above the opening of the vertical hole 1.
Is inserted, the operation of lowering the elevating frame 4 is stopped again.

【0021】そして、以上の作業サイクルを3番目,4
番目…の鉄筋籠6について繰り返すことで目的とする深
度まで鉄筋籠6を順次継足しながら建込むことができる
のである。
The above-mentioned work cycle is the third, fourth
By repeating the reinforcing cage 6, the reinforcing cage 6 can be built while sequentially adding up to the target depth.

【0022】なお、本実施例では、鉄筋籠を建込む場合
について記載したが、H鋼等の他の鋼材を建込む場合に
も同様に用いることができる。
In this embodiment, the case where the steel cage is built is described. However, the present invention can be similarly used when other steel materials such as H steel are built.

【0023】[0023]

【発明の効果】以上実施例によって詳細に説明したよう
に、この発明の鉄筋籠の建込み装置によれば、メインフ
レームによって鉄筋籠の吊り代が常に確保されるととも
に、鉄筋籠の建込み、継足し作業をメインフレームによ
り画定された作業領域内で行なうことができるので、高
さ制限のある場所や狭い作用現場においても迅速かつ安
全に鉄筋籠の建込み作業を行なうことができる。
As described in detail in the above embodiments, according to the reinforcing cage building apparatus of the present invention, the hanging margin of the reinforcing cage is always secured by the main frame, Since the extension work can be performed in the work area defined by the main frame, the work of laying the rebar basket can be quickly and safely performed even in a place where the height is limited or in a narrow working site.

【0024】また、少なくとも4本の伸縮ジヤッキの伸
縮量を調整することにより、鉛直方向に容易かつ高精度
で鉄筋籠を建込んで行くことができる。
Further, by adjusting the amount of expansion and contraction of at least four elastic jacks, it is possible to easily and accurately build a reinforcing cage in the vertical direction.

【図面の簡単な説明】[Brief description of the drawings]

【図1】図1はこの発明に係る鉄筋籠の建込み装置を示
し、(a)は半断面平面図である。 (b)は半断面正面図である。 (c)は半断面側面図である。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 shows a reinforcing device for a reinforcing cage according to the present invention, and FIG. 1 (a) is a half sectional plan view. (B) is a half sectional front view. (C) is a half sectional side view.

【図2】(a)〜(e)は同建込み装置を用いた作業手
順を示す説明図である。
FIGS. 2A to 2E are explanatory views showing work procedures using the built-in device.

【符号の説明】[Explanation of symbols]

1 縦穴 2 メインフレーム 3 油圧ジャッキ 4 昇降フレーム 5 カウンターウェイト 6 鉄筋籠 7 スプロケット(滑車) 8 チェーン 9 係止部材 DESCRIPTION OF SYMBOLS 1 Vertical hole 2 Main frame 3 Hydraulic jack 4 Elevating frame 5 Counter weight 6 Steel cage 7 Sprocket (pulley) 8 Chain 9 Locking member

フロントページの続き (56)参考文献 特開 平4−140315(JP,A) 特開 平5−214813(JP,A) (58)調査した分野(Int.Cl.6,DB名) E04G 21/16 E04G 21/12Continuation of front page (56) References JP-A-4-140315 (JP, A) JP-A-5-214813 (JP, A) (58) Fields investigated (Int. Cl. 6 , DB name) E04G 21 / 16 E04G 21/12

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 地中に設けた縦穴に鉄筋籠を建込むため
の装置であって、箱状に枠組みされ、前記縦穴の開口部
を跨いで設置されるメインフレームと、該メインフレー
ムのベース部から立設する少なくとも4本の伸縮ジャッ
キと、該伸縮ジャッキの上端に架設され、前記メインフ
レームの内側において昇降するとともに、滑車を有する
昇降フレームと、一端を前記メインフレームに取付ける
とともに、前記滑車に巻装されて下方に懸吊し、他端に
は鉄筋籠を吊持するための係止部材を備えたチェーン、
ワイヤー等の吊り部材とからなることを特徴とする鉄筋
籠の建込み装置。
1. An apparatus for laying a rebar cage in a vertical hole provided in the ground, comprising a main frame which is framed in a box shape and is installed across the opening of the vertical hole, and a base of the main frame. At least four telescopic jacks erected from the portion, an elevating frame erected at the upper end of the telescopic jack, ascending and descending inside the main frame, having a pulley, and attaching one end to the main frame, A chain with a locking member for hanging a reinforcing rod cage at the other end,
An installation device for a reinforcing rod cage, comprising a hanging member such as a wire.
JP15974192A 1992-06-18 1992-06-18 Reinforcing cage construction equipment Expired - Lifetime JP2780571B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15974192A JP2780571B2 (en) 1992-06-18 1992-06-18 Reinforcing cage construction equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15974192A JP2780571B2 (en) 1992-06-18 1992-06-18 Reinforcing cage construction equipment

Publications (2)

Publication Number Publication Date
JPH062437A JPH062437A (en) 1994-01-11
JP2780571B2 true JP2780571B2 (en) 1998-07-30

Family

ID=15700260

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15974192A Expired - Lifetime JP2780571B2 (en) 1992-06-18 1992-06-18 Reinforcing cage construction equipment

Country Status (1)

Country Link
JP (1) JP2780571B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007530574A (en) 2004-03-23 2007-11-01 ライフライン・ニュートラシューティカルズ・コーポレーション Compositions and methods for reducing inflammation and oxidative stress in mammals
US9265808B2 (en) 2004-03-23 2016-02-23 Lifeline Nutraceuticals Corporation Compositions for alleviating inflammation and oxidative stress in a mammal
CN103174303B (en) * 2011-12-23 2016-03-30 五冶集团上海有限公司 Movable overhanging unloading platform and making thereof and mounting method
JP6531504B2 (en) * 2015-06-11 2019-06-19 株式会社大林組 Ground drilling machine
CN110526153A (en) * 2019-09-16 2019-12-03 中国建筑土木建设有限公司 A kind of jack auxiliary pile foundation steel bar cage hangs structure and its construction method

Also Published As

Publication number Publication date
JPH062437A (en) 1994-01-11

Similar Documents

Publication Publication Date Title
US4809814A (en) Scaffolding
JP2684155B2 (en) Excavation method used for construction of underground structures
JP2780571B2 (en) Reinforcing cage construction equipment
JP6893188B2 (en) Demolition system and demolition method of existing structures
JP6668676B2 (en) Heavy equipment
JPH11293679A (en) Slope frame lifting device, slope frame lifting type drilling machine, protection frame for slide used in them, and drilling method in slope frame crossing point part using them
JPH11147690A (en) Low head space reinforcing bar building-in device
NZ242874A (en) Cantilevered and adjustably suspended worker's staging or platform with jack devices exteriorly of structure's wall
JP6059176B2 (en) Mobile lifting scaffold for assembling temporary elevated jetty
JP7463766B2 (en) Lifting device and reinforcing cage installation method
JPH0849235A (en) Inclination adjusting device in construction method for building up permanent substractural column
JP3230104B2 (en) Tower crane
JP6967383B2 (en) How to dismantle an existing structure
JP2801520B2 (en) Excavation method and equipment for steep slope
CN108301765A (en) Be easily installed drilling tool from hoisting type horizontal boring machine
JP3532161B2 (en) Tower construction machine and tower construction method
JP3111854B2 (en) Elevating guide mechanism of jumping scaffold for building construction
CN218231682U (en) Swinging arm hoisting frame for gallery
JP2019157532A (en) Building construction method
CN215101591U (en) A shield constructs quick-witted hoisting structure for secretly dig construction
JPH0957661A (en) Scaffold device for wall surface work
JP7275793B2 (en) Position adjusting device and method for adjusting position of structural column
JPH11287040A (en) Hanging stairs
JPH01312119A (en) Erecting method for reinforced cage and its erecting device
CN117963677A (en) Aerial in-situ underpinning platform structure of super high-rise construction elevator and construction method thereof