JP2777542B2 - Excavation sediment unloading system - Google Patents

Excavation sediment unloading system

Info

Publication number
JP2777542B2
JP2777542B2 JP6095631A JP9563194A JP2777542B2 JP 2777542 B2 JP2777542 B2 JP 2777542B2 JP 6095631 A JP6095631 A JP 6095631A JP 9563194 A JP9563194 A JP 9563194A JP 2777542 B2 JP2777542 B2 JP 2777542B2
Authority
JP
Japan
Prior art keywords
excavated
sand
earth
hopper
excavated earth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP6095631A
Other languages
Japanese (ja)
Other versions
JPH07279587A (en
Inventor
守道 戸田
哲也 寺田
雄一 柴崎
浩彦 春山
邦彦 飯泉
貞夫 野口
義雄 岩井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toda Corp
Original Assignee
Toda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toda Corp filed Critical Toda Corp
Priority to JP6095631A priority Critical patent/JP2777542B2/en
Publication of JPH07279587A publication Critical patent/JPH07279587A/en
Application granted granted Critical
Publication of JP2777542B2 publication Critical patent/JP2777542B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、掘削土砂搬出システム
に関し、特に泥土圧シールド工法における掘削土砂搬出
システムに関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an excavated sediment transport system, and more particularly to an excavated sediment transport system in a mud pressure shield method.

【0002】[0002]

【従来の技術】一般に、トンネルの施工に際しては、切
羽の安定性、作業環境の向上、等数々の利点があること
から、泥水式シールド工法が採用されることが多い。
2. Description of the Related Art Generally, when a tunnel is constructed, a muddy water shield method is often employed because of its many advantages such as stability of a face and improvement of a working environment.

【0003】しかし、泥水式シールド工法においては、
隔壁と切羽との間のカッタチャンバを加圧した泥水で満
たし、切羽の安定を図ると共に、掘削した土砂を泥水中
に取り込み、排泥水として地上の泥水処理設備まで流体
輸送し、この泥水処理設備で土砂分を分級処理し、所定
の性状に調泥して、再び送泥水として循環使用されるよ
うになっており、この泥水処理設備に広大な作業基地が
必要になるものであった。
However, in the muddy water shield method,
Filling the cutter chamber between the partition wall and the face with pressurized muddy water, stabilizing the face, taking in the excavated earth and sand into the muddy water, and transporting it as muddy water to the ground muddy water treatment equipment. The sediment is subjected to a classification process, and the mud is adjusted to a predetermined property, and is again circulated as muddy water. This muddy water treatment facility requires a vast work base.

【0004】特に、都市部などにおいては、地上設備の
ために広大な作業基地を確保するのが困難な状態となっ
てきており、そのため都市部などでは、泥水式シールド
工法に代えて泥土圧シールド工法が採用されることもあ
る。
In particular, in urban areas, it has become difficult to secure a vast work base for ground equipment, so in urban areas, etc., instead of the muddy shield method, a mud pressure shield is used. Construction methods may be adopted.

【0005】この泥土圧シールド工法では、掘削土砂の
塑性流動化を促進する泥水等添加材を注入しながら施工
するもので、泥水式シールド工法のように調泥等を必要
としないため、泥水式シールド工法に比し、地上設備の
ためにそれほど広大な作業基地を必要とせずに済むもの
である。
[0005] In this mud pressure shield construction method, construction is performed while injecting an additive such as mud which promotes plastic fluidization of excavated earth and sand. Compared to the shield method, there is no need for a vast work base for ground equipment.

【0006】[0006]

【発明が解決しようとする課題】前述の泥土圧シールド
工法にあっては、泥水式シールド工法に比し、地上設備
のためにそれほど広大な作業基地を必要とせずに済むも
のであるが、掘削土砂の搬出にあたっては一般に、
トロを用いて搬出するようにしており、このようなずり
トロを用いて掘削土砂の搬出を行う場合には、立坑内に
ずりビンを設けたり、掘削土砂を収容するバケットの反
転スペースが必要となり、そのため立坑の面積を大きく
しなければならなかった。
The above-mentioned mud pressure shield method does not require a very large work base for ground equipment as compared with the muddy water shield method. generally when unloading, not a has to be carried out using a retro, when performing discharge of drilling soil with such shear Toro, or provided with a shear bottle into vertical shaft, to accommodate the drilling soil Space for reversing the bucket was required, and the area of the shaft had to be increased.

【0007】このように立坑の面積が大きくなると、地
上設備も大きくなってしまい、都市部などのように地上
設備のために充分な土地を確保することができない場合
には、トンネルの掘削が困難な状態となってしまうとい
う問題があった。
[0007] When the area of the shaft becomes large, the ground equipment becomes large, and it is difficult to dig a tunnel when sufficient land cannot be secured for the ground equipment such as in an urban area. There was a problem that would be in a state.

【0008】また、泥土圧シールド工法においては、特
に都市部においては、騒音上の問題から、ダンプカー等
を夜間に稼動させることができず、そのため少なくとも
夜間作業分の掘削土砂を貯留するスペースが必要とな
り、この貯留スペースを地上設備内に設けると、地上設
備が大きくなってしまい、地上設備のための広いスペー
スを確保することができないような場合には、トンネル
の掘削ができないような状態も生じるという問題があっ
た。
Further, in the mud pressure shield method, especially in an urban area, a dump truck or the like cannot be operated at night due to a problem of noise. Therefore, at least a space for storing excavated earth and sand for night work is required. When this storage space is provided in the ground equipment, the ground equipment becomes large, and when it is not possible to secure a wide space for the ground equipment, a state where the tunnel cannot be excavated also occurs. There was a problem.

【0009】本発明は、前述の問題点に着目してなされ
たもので、その目的は、地上設備を小さくして、都市部
などのような地上設備のために広いスペースを確保する
ことができないような場合にも、トンネルの施工を可能
とする掘削土砂搬出システムを提供することにある。
SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned problems, and an object of the present invention is to reduce the size of the ground equipment and to secure a large space for the ground equipment such as an urban area. In such a case, an object of the present invention is to provide an excavated sediment transport system that enables construction of a tunnel.

【0010】[0010]

【課題を解決するための手段】前記目的を達成するた
め、第1の発明は、カッターで切削した土砂を隔壁と切
羽との間のカッタチャンバに充満させ、掘削量に相応し
た土砂をカッタチャンバから排出しつつ、掘進を行う泥
土圧シールド工法の掘削土砂搬出システムにおいて、シ
ールド機発進用の立坑内に配設され、掘削土砂を貯留す
る掘削土砂ホッパーと、トンネル内に配設され、前記カ
ッタチャンバ内の掘削土砂を前記掘削土砂ホッパーに搬
送する第1の圧送管と前記立坑内に配設され、前記掘
削土砂を前記掘削土砂ホッパーから地上に搬出する第2
の圧送管とを含み前記第1の圧送管の管径が、前記
シールド機から前記シールド機に連結した後方台車後部
までの区間Aにおいて、前記後方台車後部から前記掘削
土砂ホッパーまでの区間Bにおける管径よりも小さく形
成されていることを特徴としている。
In order to achieve the above object, a first aspect of the present invention is to fill a cutter chamber between a partition wall and a face with earth and sand cut by a cutter, and to deposit earth and sand corresponding to the amount of excavation. In the excavated earth and sand transport system of the mud pressure shield method that excavates and excavates, it is installed in the shaft for starting the shield machine and stores the excavated earth and sand
And excavating sand hopper that is disposed within the tunnel, the mosquito
The excavated sediment in the pit chamber is transported to the excavated sediment hopper.
A first pumping tube feeding, is disposed within said vertical shaft, said drilling
The second to carry the excavated earth from the excavated earth and sand hopper to the ground
Includes a pumping tube, the tube diameter of the first pumping tube, the
Rear bogie rear connected to the shield machine from the shield machine
In the section A up to, the excavation from the rear of the rear bogie
Smaller than the pipe diameter in section B to the earth and sand hopper
It is characterized by being made .

【0011】第2の発明は、請求項1において、 前記掘
削土砂は、前記区間Aでは前記シールド機に配設された
スネークポンプにより搬送され、前記区間Bでは前記後
方台車後部に配設されたピストンポンプと前記トンネル
内の適宜位置に配設された中継ポンプとにより搬送され
ことを特徴としている。
According to a second aspect of the present invention, in the first aspect, the excavation
The excavated sand was disposed on the shield machine in the section A.
Transported by a snake pump,
Piston pump installed at the rear of the truck and the tunnel
Transported by a relay pump arranged at an appropriate position in the
It is characterized in that that.

【0012】第3の発明は、請求項1または2におい
て、 前記掘削土砂ホッパーは、少なくとも一晩の作業に
相当する掘削土砂量を貯留し得る容量を有することを特
徴としている。
A third aspect of the present invention is directed to claim 1 or 2.
The excavated earth and sand hopper can be used at least overnight
It is characterized by having a capacity to store a corresponding amount of excavated sediment .

【0013】請求項4の発明は、請求項1〜3のいずれ
かにおいて、 前記立坑を、前記掘削土砂ホッパーの高さ
分深く掘削して立坑の底部に掘削土砂ホッパーを収納す
ことを特徴としている。
According to a fourth aspect of the present invention, there is provided any one of the first to third aspects.
In the above, the shaft is set at the height of the excavated sediment hopper.
Drill deep and store excavated sediment hopper at bottom of shaft
It is characterized in that that.

【0014】請求項5の発明は、請求項1〜4のいずれ
かにおいて、 前記掘削土砂ホッパーに掘削土砂の貯留レ
ベルを計測するセンサーが配設されていることを特徴と
している。
According to a fifth aspect of the present invention, there is provided any one of the first to fourth aspects.
The excavated sediment hopper,
It is characterized by a sensor that measures the bell .

【0015】[0015]

【作用】前記構成の第1の発明にあっては、トンネル内
に配設された第1の圧送管にてカッタチャンバ内の掘削
土砂を搬送して立坑内に配設した掘削土砂ホッパーに一
時貯留し、この掘削土砂ホッパーから立坑内に配設され
た第2の圧送管にて地上に搬出することにより、地上設
備に掘削土砂の貯留用のスペースを設ける必要がなく、
立坑及び地上設備に要する占有面積を狭小化することが
できる。
According to the first aspect of the present invention, in the tunnel,
Excavation in the cutter chamber by the first pumping pipe installed in
The sediment is transported and temporarily stored in the excavated sediment hopper arranged in the shaft, and the excavated sediment hopper is disposed in the shaft.
It is not necessary to provide a space for storing excavated earth and sand in the ground equipment
The occupied area required for the shaft and ground facilities can be reduced.

【0016】また、掘削土砂を第1及び第2の圧送管に
て搬出することにより、従来のようにずりトロを用いる
場合に比し、立坑面積を小さくすることができ、その結
果地上設備を小さく抑えることが可能となる。また、坑
内の作業可能範囲を広くすることができるとともに、坑
内の作業環境を改善することができる。特に、第1の圧
送管は、シールド機から後方台車後部までの区間Aの管
径を、後方台車後部から掘削土砂ホッパーまでの区間B
の管径よりも小さくしているため、区間Aにおける作業
スペースを損なわないようにすることができる。
Further, by excavating the excavated earth and sand through the first and second pumping pipes, the shaft area can be reduced as compared with the conventional case where a shear toro is used. It is possible to keep it small. Further, the workable area in the mine can be widened, and the work environment in the mine can be improved. In particular, the first pressure
The transmission pipe is the pipe in the section A from the shield machine to the rear of the rear bogie.
Diameter of section B from the rear of the rear bogie to the excavated soil hopper
Work in section A because it is smaller than the pipe diameter of
Space can be prevented from being impaired.

【0017】第2の発明にあっては、スネークポンプ
は、ピストンポンプに比し、小型であるため、シールド
機内の作業スペースを損なうことなく、掘削土砂をピス
トンポンプまで搬送することができ、しかも、後方台車
のない区間Bでは比較的大型のピストンポンプや中継ポ
ンプを用いて十分な搬送を行うことができる。
According to the second invention, a snake pump is provided.
Is shielded because it is smaller than a piston pump.
Piping excavated soil without damaging the work space inside the machine
Can be transported to the pump
In section B, where there are no pistons, a relatively large piston pump or relay port
Sufficient conveyance can be performed using the pump.

【0018】第3の発明にあっては、掘削土砂ホッパー
を少なくとも一晩の掘削土砂量を貯留し得る容量にする
ことにより、夜間にダンプトラックを動かすことのでき
ない都市部などにおいても、掘削土砂ホッパー内に夜間
分の掘削土砂を一時貯留することができ、そのため、昼
夜連続したトンネルの掘削を行うことが可能となる
According to the third invention, an excavated earth and sand hopper is provided.
The capacity to store at least overnight excavated sediment
This makes it possible to move the dump truck at night
Even in urban areas where there is no
Minutes of excavated sediment can be temporarily stored,
Tunnel excavation can be performed continuously at night .

【0019】第4の発明にあっては、立坑を掘削土砂ホ
ッパーの高さ分深く掘削して、立坑の底部に掘削土砂ホ
ッパーを収納することにより、立坑面積を大きくするこ
となく、しかもトンネル内への資材への搬送にも支障な
く掘削土砂ホッパーを収納することが可能となる
According to the fourth aspect of the present invention, the shaft is excavated with earth and sand.
Drill deeper to the height of the
The pit area can be increased by storing
And there is no problem in transporting materials into the tunnel.
It becomes possible to store the excavated earth and sand hopper .

【0020】第5の発明にあっては、掘削土砂ホッパー
内の掘削土砂の貯留レベルをセンサにて計測すること
で、貯留レベルを一定に制御し、掘削土砂ホッパーの容
量を低減して小型化を図ることができる
According to a fifth aspect, an excavated earth and sand hopper is provided.
Measuring the storage level of excavated sediment in the building with a sensor
To control the storage level to a constant
The size can be reduced by reducing the amount .

【0021】[0021]

【実施例】以下、本発明の好適な実施例について、図面
を参照して詳細に説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Preferred embodiments of the present invention will be described below in detail with reference to the drawings.

【0022】図1〜図3は、本発明の一実施例に係る掘
削土砂搬出システムを示す図である。
FIGS. 1 to 3 are views showing an excavated earth and sand carrying system according to an embodiment of the present invention.

【0023】この実施例における掘削土砂搬出システム
は、泥土圧シールド工法に用いられるもので、この泥土
圧シールド工法では、シールド発進用の立坑10上に地
上設備12を配設し、前記立坑10よりシールド機14
を発進させ、シールド機14の先端に取付けたカッター
16により地山を掘削しながらシールド機14後部でセ
グメント18を組立てつつトンネル20を構築していく
ようになっている。なお、地上設備12には、加泥材注
入及び裏込め注入のための設備2,中央管理室3,濁水
処理装置4,受変電設備5,泥土固化装置52等の諸設
備が配設されるようになっている。
The system for carrying out excavated earth and sand in this embodiment is used in a mud pressure shield method. In this mud pressure shield method, a ground facility 12 is disposed on a shaft 10 for starting a shield. Shield machine 14
And the tunnel 20 is constructed while assembling the segment 18 at the rear of the shield machine 14 while excavating the ground with the cutter 16 attached to the tip of the shield machine 14. The ground facility 12 includes various facilities such as a facility 2 for injecting mud and a backfill, a central control room 3, a turbid water treatment device 4, a substation facility 5, and a mud solidification device 52. It has become.

【0024】シールド機14による掘削時には、カッタ
ー16により切削した土砂を隔壁22と切羽24との間
のカッタチャンバ26内に充満させ、カッタチャンバ2
6内に掘削土砂の塑性流動化を促進する加泥材等の添加
剤を注入しながら、掘削量に相応した土砂をカッタチャ
ンバ26から排出しつつ、掘進を行うようになってい
る。
At the time of excavation by the shield machine 14, earth and sand cut by the cutter 16 are filled in a cutter chamber 26 between the partition wall 22 and the face 24, and the cutter chamber 2
The excavation is carried out while pouring an additive such as a mud material that promotes the plastic fluidization of excavated soil into the inside 6 and discharging soil corresponding to the excavated amount from the cutter chamber 26.

【0025】掘削されたカッタチャンバ26内の掘削土
砂は、トンネル20内でシールド機14からシールド機
14に連結された後方台車32後部までの区間Aと後方
台車32後部から立坑10までの区間Bに配設された2
種類の圧送管36、38から構成される第1の圧送管3
5によって立坑10へと搬送される。すなわち、カッタ
チャンバ26内の掘削土砂は、シールド機14に配設し
たスクリューコンベア28によりシールド機14内に取
り込まれ、そこらからシールド機14内に配設したスネ
ークポンプ30により、シールド機14と連結した後方
台車32後部のピストンポンプ34間で圧送管36を介
して搬送されるようになっている。このスネークポンプ
30は、ピストンポンプ34に比し、小型であるため、
シールド機14内の作業スペースを損なうことなく、掘
削土砂をピストンポンプ34まで搬送することが可能で
ある。また、スネークポンプ30は、後方台車32の後
部まで、充分に掘削土砂を圧送し得る能力を有してい
る。
The excavated earth and sand in the cutter chamber 26 is removed from the shield machine 14 in the tunnel 20 by the shield machine 14.
Section A to the rear of the rear bogie 32 connected to 14 and the rear
2 provided in the section B from the rear of the bogie 32 to the shaft 10
First pumping tube 3 composed of different kinds of pumping tubes 36, 38
5 to the shaft 10. That is, the cutter
The excavated earth and sand in the chamber 26 is taken into the shield machine 14 by a screw conveyor 28 arranged in the shield machine 14, and the rear bogie connected to the shield machine 14 therefrom by a snake pump 30 arranged in the shield machine 14. It is configured to be conveyed via a pressure feed pipe 36 between piston pumps 34 at the rear of 32. Since the snake pump 30 is smaller than the piston pump 34,
The excavated earth and sand can be transported to the piston pump 34 without impairing the working space in the shield machine 14. Further, the snake pump 30 has a capability of sufficiently pumping excavated earth and sand to the rear part of the rear bogie 32.

【0026】さらに、圧送管36は、スネークポンプ3
0からピストンポンプ34までの区間をやや小径(例え
ば6インチ)のものを用いることによって、シールド機
14内の作業スペースを損なわないようにすることがで
きる。
Further, the pressure feed pipe 36 is connected to the snake pump 3
By using a section with a slightly smaller diameter (for example, 6 inches) in the section from 0 to the piston pump 34, the working space in the shield machine 14 can be prevented from being impaired.

【0027】後方台車32後部のピストンポンプ34か
らは、適宜中継ポンプを用いながら、圧送管38を介し
て、立坑10まで掘削土砂を搬出するようになってい
る。この後方台車32から立坑10までの間のトンネル
20は、後方台車28等がないため比較的大型のピスト
ンポンプ34や中継ポンプ及び大径(例えば8インチ)
の圧送管などを充分に設置することが可能である。
From the piston pump 34 at the rear of the rear bogie 32, excavated earth and sand is carried out to the shaft 10 via the pressure feed pipe 38, using a relay pump as appropriate. The tunnel 20 between the rear bogie 32 and the shaft 10 has a relatively large piston pump 34, a relay pump, and a large diameter (for example, 8 inches) because there is no rear bogie 28 or the like.
Can be sufficiently installed.

【0028】さらに、ピストンポンプ34の坑口側にミ
キシング装置35を設け、掘削土砂の圧送を容易にする
ための添加材を混入する。この場合、圧送管36内の土
砂性状を各種センサ(図示せず)によって計測してお
き、その計測結果に応じて添加材の種類、配合及び添加
量を設定するようにするとよい。
Further, a mixing device 35 is provided on the wellhead side of the piston pump 34, and an additive for facilitating the pumping of excavated earth and sand is mixed therein. In this case, the properties of the earth and sand in the pressure feed pipe 36 may be measured by various sensors (not shown), and the type, combination and amount of the additive may be set according to the measurement result.

【0029】このように、シールド機14から立坑10
までの掘削土砂の搬出を、ずりトロを用いずに、圧送管
36,38により行うことにより、立坑10内にずりビ
ンやバケット反転スペースなどを設ける必要がなく、し
たがって、立坑10を最小限の大きさとすることがで
き、それに伴って、地上設備12をも小さくすることが
可能である。
As described above, from the shield machine 14 to the shaft 10
By carrying out the excavated earth and sand up to the pumping pipes 36 and 38 without using a shearing torro, it is not necessary to provide a shearing bin or a bucket reversal space in the shaft 10, and therefore, the shaft 10 is minimized. The size of the ground equipment 12 can be reduced accordingly.

【0030】立坑10内では、底部に掘削土砂ホッパー
40を配設しており、この掘削土砂ホッパー40内に圧
送管38により搬出されてきた掘削土砂を貯留するよう
になっている。このように、立坑内に配設した掘削土砂
ホッパー40に掘削土砂を一時貯留しておくことによ
り、地上設備12内に掘削土砂貯留用のスペースを設け
る必要がなく、それだけ地上設備12を小さくして、狭
い工事敷地からのシールド発進を可能にしている。この
場合、掘削土砂ホッパー40内に超音波センサなどのレ
ベル測定器を配設し、その計測結果に応じて、掘削土砂
がほぼ同一レベルになるよう、圧送管38の先端位置を
制御することにより、掘削土砂ホッパー40の容量を低
減することが可能になる。
In the shaft 10, an excavated sediment hopper 40 is disposed at the bottom, and the excavated sediment carried out by the pressure pipe 38 is stored in the excavated sediment hopper 40. As described above, by temporarily storing the excavated sediment in the excavated sediment hopper 40 disposed in the shaft, there is no need to provide a space for excavated sediment storage in the ground equipment 12, and the ground equipment 12 is reduced accordingly. This makes it possible to launch a shield from a narrow construction site. In this case, a level measuring device such as an ultrasonic sensor is provided in the excavated sediment hopper 40, and according to the measurement result, the tip position of the pumping pipe 38 is controlled so that the excavated sediment is substantially at the same level. Thus, the capacity of the excavated earth hopper 40 can be reduced.

【0031】また、掘削土砂ホッパー40は、少なくと
も一晩の掘削土砂量を貯留し得る容量、例えば一晩で7
〜8リング分の掘進を行う場合、その7〜8リングの掘
進に相当する掘削土砂量を貯留し得る容量を有し、夜間
などダンプトラック等の稼動が制限されている都市部な
どにおいても、夜間掘削分の掘削土砂を掘削土砂ホッパ
ー40にて充分に貯留することが可能である。したがっ
て、ダンプトラック等の稼動が不可能な時間帯であって
もシールド機14による掘削を継続して行うことがで
き、昼夜連続した掘削を行うことが可能となる。
The excavated soil hopper 40 has a capacity capable of storing at least one night of excavated earth and sand, for example, 7 g / night.
When performing excavation for up to 8 rings, it has a capacity to store the amount of excavated sediment corresponding to the excavation of 7 to 8 rings, and even in an urban area where the operation of a dump truck or the like is restricted such as at night, Excavated earth and sand for night excavation can be sufficiently stored in the excavated earth and sand hopper 40. Therefore, excavation by the shield machine 14 can be continued even during a time period in which the operation of the dump truck or the like is impossible, and excavation can be performed continuously day and night.

【0032】さらに、掘削土砂ホッパー40は、掘削土
砂ホッパー40の高さ分立坑10を深く掘削して、その
立坑10の底部に配設されるようになっており、掘削土
砂ホッパー40の上端が少なくともトンネル内10内に
配設される搬送レール42の位置よりも下方に位置する
ようにされている。したがって、立坑10の面積を大き
くすることなく立坑10内に掘削土砂ホッパー40を収
納でき、しかも搬送台車44によるセグメント等の機材
搬送に支障がないようになっている。
Further, the excavated sediment hopper 40 excavates the shaft 10 at the height of the excavated sediment hopper 40 and is disposed at the bottom of the shaft. It is configured to be located at least below the position of the transport rail 42 disposed in the tunnel 10. Therefore, the excavated earth and sand hopper 40 can be stored in the shaft 10 without increasing the area of the shaft 10, and the conveyance of the equipment such as the segments by the carriage 44 is not hindered.

【0033】立坑10内の掘削土砂ホッパー40から
は、スクリューフィーダ46より取り出された掘削土砂
が、ピストンポンプ48により立坑10内に配設された
第2の圧送管50を介し地上設備12内に搬出されるよ
うになっている。
From the excavated sediment hopper 40 in the shaft 10, excavated earth and sand taken out from the screw feeder 46 is disposed in the shaft 10 by a piston pump 48.
It is carried out into the ground equipment 12 via the second pressure feed pipe 50.

【0034】地上設備12内には泥土固化装置52が配
設され、この泥土固化装置52により第2の圧送管50
より搬出された掘削土砂が固化されて、ダンプカー54
に積み込まれ、地上設備12より搬出されるようになっ
ている。この場合、第2の圧送管50内の掘削土砂の性
状(比重、含水量、粒度組成、鉱物組成など)を適宜手
段によって計測し、その結果に応じて自動的に固化材の
添加量を設定し、供給するようになっている。したがっ
て、掘削土砂を固化した状態で地上設備12より搬出で
きるため、地上設備12からの搬出が容易に行えること
となる。さらに、埋立て・埋戻し・盛土工事などへの材
料として有効利用することも可能となる。
A mud solidifying device 52 is provided in the ground equipment 12, and the second pumping pipe 50 is provided by the mud solidifying device 52 .
The excavated earth and sand carried out is solidified and the dump truck 54
And is carried out from the ground equipment 12. In this case, the properties (specific gravity, water content, particle size composition, mineral composition, etc.) of the excavated earth and sand in the second pumping pipe 50 are measured by appropriate means, and the amount of the solidified material is automatically set according to the result. And supply it. Therefore, since the excavated earth and sand can be carried out from the ground facility 12 in a solidified state, the carry-out from the ground facility 12 can be easily performed. Further, it can be effectively used as a material for landfilling, backfilling, embankment construction, and the like.

【0035】また、本実施例においては、地上設備12
からセグメントのストックスペースや作業のためのスペ
ースをなくして、地上設備12を極力小さく抑えるため
に、立坑10内に複数のセグメントを収納するセグメン
トストック装置56を配設し、昇降可能なスタッカ装置
58によりセグメントストック装置56に対するセグメ
ントの積込みおよび取出しを行い、このセグメントスト
ック装置56から搬送台車44によりトンネル20内に
搬送し、後方台車32中に設けたセグメント仮置台車6
0にストックしておけるようにしている。
In this embodiment, the ground equipment 12
In order to eliminate the stock space for the segments and the space for work, and to keep the ground equipment 12 as small as possible, a segment stock device 56 for accommodating a plurality of segments in the shaft 10 is provided, and a stacker device 58 that can move up and down. The loading and unloading of segments into and from the segment stock device 56 is carried out, and the segments are transported from the segment stock device 56 into the tunnel 20 by the transport vehicle 44, and the segment temporary storage vehicle 6
You can stock it at 0.

【0036】本発明は、前記実施例に限定されるもので
はなく、本発明の要旨の範囲内において種々の変形実施
例が可能である。例えば、前記実施例においては、セグ
メントを立坑内のセグメントストック装置に収納する場
合について説明したが、この例に限らず、地上設備12
内にセグメントをストックすることも可能である。
The present invention is not limited to the above embodiment, and various modified embodiments are possible within the scope of the present invention. For example, in the above-described embodiment, the case where the segments are stored in the segment stock device in the shaft has been described. However, the present invention is not limited to this example.
It is also possible to stock the segments within.

【0037】[0037]

【発明の効果】以上説明したように、前記構成の第1の
発明にあっては、トンネル内に配設された第1の圧送管
にてカッタチャンバ内の掘削土砂を搬送して立坑内に配
設した掘削土砂ホッパーに一時貯留し、この掘削土砂ホ
ッパーから立坑内に配設された第2の圧送管にて地上に
搬出することにより、地上設備に掘削土砂の貯留用のス
ペースを設ける必要がなく、地上設備を小さくして、作
業スペースを大きくとることができない都市部などにお
けるトンネルの施工を可能とすることができるという効
果がある。
As described above, according to the first aspect of the present invention, the first pumping pipe provided in the tunnel is provided.
Transports the excavated earth and sand in the cutter chamber and distributes it in the shaft.
It is necessary to provide a space for storing excavated sediment on the ground equipment by temporarily storing it in the excavated sediment hopper that has been set up and carrying it from the excavated sediment hopper to the ground using the second pumping pipe installed in the shaft. In addition, there is an effect that it is possible to reduce the size of the ground equipment and construct a tunnel in an urban area where a large work space cannot be taken.

【0038】また、掘削土砂を第1及び第2の圧送管に
て搬出することにより、従来のようにずりトロを用いる
場合に比し、立坑面積を小さくすることができ、その結
果地上設備を小さく抑えることが可能となる。また、坑
内の作業可能範囲を広くすることができるとともに、坑
内の作業環境を改善することができる。特に、第1の圧
送管は、シールド機から後方台車後部までの区間Aの管
径を、後方台車後部から掘削土砂ホッパーまでの区間B
の管径よりも小さくしているため、区間Aにおける作業
スペースを損なわないようにすることができるという効
果がある。
Further, by excavating the excavated earth and sand through the first and second pumping pipes, the area of the shaft can be reduced as compared with the conventional case where a shear toro is used. It is possible to keep it small. Further, the workable area in the mine can be widened, and the work environment in the mine can be improved . In particular, the first pressure
The transmission pipe is the pipe in the section A from the shield machine to the rear of the rear bogie.
Diameter of section B from the rear of the rear bogie to the excavated soil hopper
Work in section A because it is smaller than the pipe diameter of
There is an effect that the space can be prevented from being damaged .

【0039】第2の発明にあっては、スネークポンプ
は、ピストンポンプに比し、小型であるため、シールド
機内の作業スペースを損なうことなく、掘削土砂をピス
トンポンプまで搬送することができ、しかも、後方台車
のない区間Bでは比較的大型のピストンポンプや中継ポ
ンプを用いて十分な搬送を行うことができるという効果
がある。
According to the second invention, the snake pump
Is shielded because it is smaller than a piston pump.
Piping excavated soil without damaging the work space inside the machine
Can be transported to the pump
In section B, where there are no pistons, a relatively large piston pump or relay port
There is an effect that sufficient conveyance can be performed using the pump .

【0040】第3の発明にあっては、掘削土砂ホッパー
を少なくとも一晩の掘削土砂量を貯留し得る容量にする
ことにより、夜間にダンプトラックを動かすことのでき
ない都市部などにおいても、掘削土砂ホッパー内に夜間
分の掘削土砂を一時貯留することができ、そのため、昼
夜連続したトンネルの掘削を行うことが可能となるとい
う効果がある。
According to the third invention, an excavated earth and sand hopper is provided.
The capacity to store at least overnight excavated sediment
This makes it possible to move the dump truck at night
Even in urban areas where there is no
Minutes of excavated sediment can be temporarily stored,
There is an effect that it becomes possible to excavate a tunnel continuously at night .

【0041】第4の発明にあっては、立坑を掘削土砂ホ
ッパーの高さ分深く掘削して、立坑の底部に掘削土砂ホ
ッパーを収納することにより、立坑面積を大きくするこ
となく、しかもトンネル内への資材への搬送にも支障な
く掘削土砂ホッパーを収納することが可能となるという
効果がある。
According to the fourth aspect of the present invention, the shaft is excavated with earth and sand.
Drill deeper to the height of the
The pit area can be increased by storing
And there is no problem in transporting materials into the tunnel.
There is an effect that the excavated earth and sand hopper can be stored .

【0042】第5の発明にあっては、掘削土砂ホッパー
内の掘削土砂の貯留レベルをセンサにて計測すること
で、貯留レベルを一定に制御し、掘削土砂ホッパーの容
量を低減して小型化を図ることができるという効果があ
る。
According to the fifth invention, an excavated earth and sand hopper is provided.
Measuring the storage level of excavated sediment in the building with a sensor
To control the storage level to a constant
There is an effect that the size can be reduced by reducing the amount .

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施例に係る掘削土砂搬出システム
の地上設備および立坑の状態を示す断面図である。
FIG. 1 is a cross-sectional view showing a state of ground equipment and a shaft of an excavated earth and sand discharging system according to an embodiment of the present invention.

【図2】図1の立坑に続くトンネルの断面図である。FIG. 2 is a sectional view of a tunnel following the shaft of FIG.

【図3】地上設備の平面図である。FIG. 3 is a plan view of the ground equipment.

【符号の説明】[Explanation of symbols]

10 立坑 12 地上設備 14 シールド機 16 カッター 20 トンネル 22 隔壁 24 切羽 26 カッタチャンバ 30 スネークポンプ 32 後方台車 34 ピストンポンプ 36,38,50 圧送管 40 掘削土砂ホッパー 48 ピストンポンプ 52 泥土固化装置 DESCRIPTION OF SYMBOLS 10 Vertical shaft 12 Ground equipment 14 Shield machine 16 Cutter 20 Tunnel 22 Partition wall 24 Face 26 Cutter chamber 30 Snake pump 32 Back bogie 34 Piston pump 36,38,50 Pumping pipe 40 Drilling sand hopper 48 Piston pump 52 Mud solidifying device

───────────────────────────────────────────────────── フロントページの続き (72)発明者 柴崎 雄一 東京都中央区京橋1丁目7番1号 戸田 建設株式会社内 (72)発明者 春山 浩彦 東京都中央区京橋1丁目7番1号 戸田 建設株式会社内 (72)発明者 飯泉 邦彦 東京都中央区京橋1丁目7番1号 戸田 建設株式会社内 (72)発明者 野口 貞夫 東京都中央区京橋1丁目7番1号 戸田 建設株式会社内 (72)発明者 岩井 義雄 東京都中央区京橋1丁目7番1号 戸田 建設株式会社内 (56)参考文献 特開 昭60−164598(JP,A) 特開 昭60−199198(JP,A) (58)調査した分野(Int.Cl.6,DB名) E21D 9/12──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Yuichi Shibasaki 1-7-1 Kyobashi, Chuo-ku, Tokyo Toda Construction Co., Ltd. (72) Inventor Hirohiko Haruyama 1-7-1 Kyobashi, Chuo-ku, Tokyo Toda Construction (72) Inventor Kunihiko Iizumi 1-7-1 Kyobashi, Chuo-ku, Tokyo Toda Construction Co., Ltd. (72) Inventor Sadao Noguchi 1-7-1 Kyobashi, Chuo-ku, Tokyo Toda Construction Co., Ltd. 72) Inventor Yoshio Iwai 1-7-1 Kyobashi, Chuo-ku, Tokyo Toda Construction Co., Ltd. (56) References JP-A-60-164598 (JP, A) JP-A-60-199198 (JP, A) ( 58) Field surveyed (Int.Cl. 6 , DB name) E21D 9/12

Claims (5)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 カッターで切削した土砂を隔壁と切羽と
の間のカッタチャンバに充満させ、掘削量に相応した土
砂をカッタチャンバから排出しつつ、掘進を行う泥土圧
シールド工法の掘削土砂搬出システムにおいて、 シールド機発進用の立坑内に配設され、掘削土砂を貯留
する掘削土砂ホッパーと、トンネル内に配設され、前記カッタチャンバ内の掘削土
砂を前記掘削土砂ホッパーに搬送する第1の圧送管と前記立坑内に配設され、前記掘削土砂を前記掘削土砂ホ
ッパーから地上に搬出する第2の圧送管とを含み前記第1の圧送管の管径が、前記シールド機から前記シ
ールド機に連結した後方台車後部までの区間Aにおい
て、前記後方台車後部から前記掘削土砂ホッパーまでの
区間Bにおける管径よりも小さく形成されている ことを
特徴とする掘削土砂搬出システム。
An excavated earth and sand carrying system of a mud pressure shield construction method in which earth and sand cut by a cutter is filled in a cutter chamber between a partition wall and a face and excavation is performed while discharging earth and sand corresponding to an excavated amount from the cutter chamber. At the pit for launching shield machines , and store excavated sediment
Excavated earth and sand hopper, and excavated earth in the cutter chamber
A first pumping tube for transporting the sand to the excavated soil hopper, is disposed within said pit, the excavated soil Ho said excavated soil
Anda second pumping tube to be transferred out on the ground from the wrapper, the tube diameter of the first pumping tube, said from the shield machine Shi
In the section A to the rear of the rear bogie connected to the
From the rear of the rear bogie to the excavated soil hopper
An excavated earth and sand discharging system, wherein the excavated earth and sand is formed smaller than a pipe diameter in the section B.
【請求項2】 請求項1において、 前記掘削土砂は、前記区間Aでは前記シールド機に配設
されたスネークポンプにより搬送され、前記区間Bでは
前記後方台車後部に配設されたピストンポンプと前記ト
ンネル内の適宜位置に配設された中継ポンプとにより搬
送されることを特徴とする掘削土砂搬出システム。
2. The section according to claim 1, wherein the excavated earth and sand is conveyed in the section A by a snake pump arranged in the shield machine, and in the section B, the piston pump and the piston pump arranged in a rear portion of the rear bogie. An excavated earth and sand unloading system, which is transported by a relay pump disposed at an appropriate position in a tunnel.
【請求項3】 請求項1または2において、 前記掘削土砂ホッパーは、少なくとも一晩の作業に相当
する掘削土砂量を貯留し得る容量を有することを特徴と
する掘削土砂搬出システム。
3. An apparatus according to claim 1 or 2, wherein the excavated soil hopper, drilling soil unloading system characterized by having a capacity capable of storing the excavated earth and sand amount corresponding to the work of at least overnight.
【請求項4】 請求項1〜3のいずれかにおいて、 前記立坑を、前記掘削土砂ホッパーの高さ分深く掘削し
て立坑の底部に掘削土砂ホッパーを収納することを特徴
とする掘削土砂搬出システム。
4. The claim 1-3, drilling soil unloading system, characterized in that the vertical shaft houses the excavated earth and sand hopper and the height of deep drilling of the excavated earth and sand hopper at the bottom of the vertical shaft .
【請求項5】 請求項1〜4のいずれかにおいて、 前記掘削土砂ホッパーに掘削土砂の貯留レベルを計測す
るセンサーが配設されていることを特徴とする掘削土砂
搬出システム。
5. The claim 1, drilling soil unloading system characterized by a sensor for measuring the storage level of the excavation soil into the excavated earth and sand hopper is arranged.
JP6095631A 1994-04-07 1994-04-07 Excavation sediment unloading system Expired - Fee Related JP2777542B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6095631A JP2777542B2 (en) 1994-04-07 1994-04-07 Excavation sediment unloading system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6095631A JP2777542B2 (en) 1994-04-07 1994-04-07 Excavation sediment unloading system

Publications (2)

Publication Number Publication Date
JPH07279587A JPH07279587A (en) 1995-10-27
JP2777542B2 true JP2777542B2 (en) 1998-07-16

Family

ID=14142877

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6095631A Expired - Fee Related JP2777542B2 (en) 1994-04-07 1994-04-07 Excavation sediment unloading system

Country Status (1)

Country Link
JP (1) JP2777542B2 (en)

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60164598A (en) * 1984-02-03 1985-08-27 株式会社奥村組 Earth and sand discharge method in shield construction method
JPS60199198A (en) * 1984-03-22 1985-10-08 株式会社小松製作所 Sand and earth transport apparatus

Also Published As

Publication number Publication date
JPH07279587A (en) 1995-10-27

Similar Documents

Publication Publication Date Title
KR100902364B1 (en) Shield tunneling apparatus and constructing method thereof
JP2777542B2 (en) Excavation sediment unloading system
KR101796929B1 (en) The shield tunnel excavator and it's tunnel excavation method with reverse injection of underground water
JPH0258697A (en) Hydraulic balance type force feed earth discharging shield construction method and shield excavator
JPH09217589A (en) Tunnel excavator and its driving method
JPH04203093A (en) Sludge pressure type shield machine
JP5206363B2 (en) Sediment transport method and sediment transport system
US4900191A (en) Method for removal of broken ground
JPH02289792A (en) Earth pressure shield construction method
JP2757729B2 (en) Discharge system in pneumatic submersion method
JPH085134Y2 (en) Sediment carry-out device
JP2006249670A (en) Tunnelling machine
JP2817493B2 (en) Construction method of shield tunnel
JPH02289791A (en) Earth pressure shield construction method allowing shield construction at natural ground applied with high water pressure
JP2509494B2 (en) Rock cutting powder removal device for rock semi-shielding machine
JPH035592A (en) Shielding method
CA1307298C (en) Contamination reducing mining system for harmful ores
JP2744885B2 (en) Segment loading system
JPH09316921A (en) Earth and sand booster pump car
JP2699153B2 (en) Construction method of underground plate-like structure and girder material for plate-like structure construction
JPH02243899A (en) Ebullition preventing execution method for discharged soil by shield excavator machine
JPH05141189A (en) Semi-shield machine
JPH02157400A (en) Method and device for backfilling of tunnel
JPS6351596A (en) Method of muddy water shielding construction
JP2726764B2 (en) Underwater tunnel excavator

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19980407

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130501

Year of fee payment: 15

LAPS Cancellation because of no payment of annual fees