JP5206363B2 - Sediment transport method and sediment transport system - Google Patents

Sediment transport method and sediment transport system Download PDF

Info

Publication number
JP5206363B2
JP5206363B2 JP2008301288A JP2008301288A JP5206363B2 JP 5206363 B2 JP5206363 B2 JP 5206363B2 JP 2008301288 A JP2008301288 A JP 2008301288A JP 2008301288 A JP2008301288 A JP 2008301288A JP 5206363 B2 JP5206363 B2 JP 5206363B2
Authority
JP
Japan
Prior art keywords
earth
sand
excavation
period
excavated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2008301288A
Other languages
Japanese (ja)
Other versions
JP2010126947A (en
Inventor
秀一 熊谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2008301288A priority Critical patent/JP5206363B2/en
Publication of JP2010126947A publication Critical patent/JP2010126947A/en
Application granted granted Critical
Publication of JP5206363B2 publication Critical patent/JP5206363B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、トンネルを掘削する掘削手段(例えば、シールドマシン)と、掘削手段により掘削された土砂を掘削現場から搬出する搬出手段(例えば、ベルトコンベアや排泥ポンプ)とを用いてトンネルを施工するにあたり、特に、単位時間当たりの、掘削手段による土砂の掘削量より、搬出手段による土砂の搬出量が少ない場合において、掘削現場から土砂を効率的に搬出する土砂搬出方法及びそれを用いた土砂搬出システムに関する。   The present invention constructs a tunnel using excavation means (for example, a shield machine) for excavating the tunnel and unloading means (for example, a belt conveyor or a mud pump) for carrying out the earth and sand excavated by the excavation means from the excavation site. In particular, in the case where the amount of earth and sand transported by the unloading means is less than the amount of sand and sand excavated by the means of excavation per unit time, the method for transporting earth and sand efficiently from the excavation site and the earth and sand using the method It relates to an unloading system.

シールドマシンを使用して地盤を掘削しトンネルを構築するシールド工法の一つに、シールドマシン内の土圧室に掘削した土砂を充満させて、この土圧によって切羽土圧及び地下水圧等に対抗させて切羽を安定させる泥土圧式シールド工法がある。   One of the shield methods for excavating the ground using a shield machine to construct a tunnel is to fill the earth pressure chamber in the shield machine with the excavated earth and sand, and counteract the face pressure and groundwater pressure, etc. There is a mud pressure shield method that stabilizes the face.

かかる泥土圧式シールド工法では、掘削された土砂を掘削現場から搬出する際に、掘削現場で掘削した土砂に泥水を混合してスラリーを作製し、当該スラリーを排泥ポンプによりパイプを介してトンネル2の外部まで圧送して搬出する方式を採ることがある。   In such a mud pressure shield method, when carrying out excavated earth and sand from the excavation site, slurry is prepared by mixing mud water with the excavated earth and sand, and the slurry is tunneled through a pipe by a mud pump. A method of pumping out to the outside of the machine and taking it out may be employed.

例えば、特許文献1には、シールド工法によるトンネル施工において、掘削された土砂に泥水を加えてスラリー化させ、トンネルから搬出するとともに、トンネルから搬出したスラリー化した土砂から泥水を分離し、分離された泥水を掘削現場に再度供給して掘削された土砂に加える泥水の循環システムが開示されている。
特開2003−41884号公報
For example, Patent Document 1 discloses that in tunnel construction by a shield method, mud water is added to the excavated earth and sand to be slurried, and the mud is separated from the slurried earth and sand that has been carried out from the tunnel. A muddy water circulation system is disclosed in which the muddy water is supplied again to the excavation site and added to the excavated soil.
JP 2003-41884 A

上記のように掘削した土砂を排泥ポンプにより搬出すべくスラリー化するためには、通常、土砂の量に対して数倍の泥水を加える必要がある。すなわち、排泥ポンプは、シールドマシンにより掘削される土砂の量の何倍もの容量のスラリーを搬送する必要がある。   In order to slurry the excavated earth and sand so as to be carried out by the mud pump, it is usually necessary to add mud water several times the amount of earth and sand. In other words, the mud pump needs to transport a slurry having a volume many times larger than the amount of earth and sand excavated by the shield machine.

さらに、トンネル施工途中にシールドマシンの掘進速度を当初の施工計画よりも速めたい場合、それによって掘削される土砂の量が増加し、その土砂の増加分に対してさらに数倍の泥水が加えられるので、スラリーの容量が増大してしまい、当初の施工計画によりスラリーの排出量を見積もって採用された排泥ポンプでは、スラリーを搬出できないことがある。   Furthermore, if you want to increase the shield machine digging speed during tunnel construction faster than the original construction plan, the amount of earth and sand excavated will increase, and several times more mud will be added to the increase in the earth and sand. Therefore, the capacity of the slurry is increased, and the slurry cannot be carried out by the wastewater pump adopted by estimating the discharged amount of the slurry according to the initial construction plan.

かかる対策として、例えば、排出能力を向上させた排泥ポンプに変更することが考えられるが、大型の排泥ポンプは、小断面のトンネルでは寸法制限により設置できないおそれがある。
また、トンネル内に大型の排泥ポンプを設置できたとしても、排泥ポンプの大型化によって施工コストが増大するとともに、坑内の作業スペースが狭小になり安全性を確保する点で不利になるおそれもある。
As such a countermeasure, for example, it is conceivable to change to a sludge pump with improved discharge capacity, but a large sludge pump may not be installed in a tunnel with a small cross section due to dimensional restrictions.
Moreover, even if a large drainage pump can be installed in the tunnel, the construction cost will increase due to the increase in the size of the drainage pump, and the work space in the mine will be reduced, which may be disadvantageous in terms of ensuring safety. There is also.

一方、特許文献1に記載の泥水の循環システムの技術には、特に、このような問題に対する対策が講じられていない。   On the other hand, in the technique of the mud circulation system described in Patent Document 1, no countermeasure is particularly taken against such a problem.

本発明は上記の点に鑑みてなされたものであり、トンネルを掘削する掘削手段(例えば、シールドマシン)と、掘削手段により掘削された土砂を掘削現場から搬出する搬出手段(例えば、ベルトコンベアや排泥ポンプ)とを用いてトンネルを施工するにあたり、特に、単位時間当たりの、掘削手段による土砂の掘削量より、搬出手段による土砂の搬出量が少ない場合において、掘削現場から土砂を効率的に搬出する土砂搬出方法及びそれを用いた土砂搬出システムを提供することを目的とする。   The present invention has been made in view of the above points. Excavation means (for example, a shield machine) for excavating a tunnel and unloading means (for example, a belt conveyor or the like) for unloading earth and sand excavated by the excavation means from the excavation site. When constructing a tunnel using a sludge pump), especially when the amount of sediment transported by the transporting means is less than the amount of sediment transported by the drilling means per unit time, the sediment is efficiently removed from the excavation site. An object is to provide a method for carrying out sediment and a sediment carrying system using the method.

上記の目的を達成するため、本発明は、トンネルを掘削する掘削手段と、前記掘削手段により掘削された土砂を掘削現場から搬出する搬出手段とを用いてトンネルを施工するにあたり、単位時間当たりの、前記掘削手段によって掘削される土砂の掘削量より、前記搬出手段による土砂の搬出量が少ない場合における、土砂搬出方法であって、
前記搬出手段の前段に、前記掘削手段により掘削された土砂を一時的に貯蔵し、当該貯蔵した土砂を前記搬出手段に導入する土砂貯蔵手段を設け、
前記搬出手段により前記土砂貯蔵手段に貯蔵された土砂を搬出させ
前記搬出手段として、前記土砂貯蔵手段から土砂を導入するとともに、前記導入した土砂に泥水を混合してスラリーを作製する土砂スラリー化装置と、前記土砂スラリー化装置で作製されたスラリーを掘削現場から搬出する排泥ポンプとを用いることを特徴とする。
In order to achieve the above-mentioned object, the present invention provides a method for constructing a tunnel using excavation means for excavating a tunnel and unloading means for unloading earth and sand excavated by the excavation means from a drilling site. In the case where the amount of earth and sand carried out by the carrying-out means is less than the amount of earth and sand excavated by the excavating means,
In the previous stage of the unloading means, the earth and sand excavated by the excavating means is temporarily stored, and earth and sand storage means for introducing the stored earth and sand into the unloading means,
The earth and sand stored in the earth and sand storage means are carried out by the carry-out means ,
As the unloading means, the earth and sand is introduced from the earth and sand storage means, and the earth and sand slurrying apparatus for preparing slurry by mixing muddy water into the introduced earth and sand, and the slurry produced by the earth and sand slurrying apparatus from the excavation site It is characterized by using a discharge mud pump .

本発明の土砂搬出方法によれば、単位時間当たりの、掘削手段によって掘削される土砂の掘削量より、搬出手段による土砂の搬出量が少ない場合であっても、掘削期間内に搬出手段によって搬出できない土砂を土砂貯蔵手段に一時的に貯蔵することができ、掘削休止期間に、掘削期間に搬出手段によって搬出できなかった土砂を、搬出手段によって搬出することができるので、搬出手段の搬出量を増大させることなく、土砂を効率的に掘削現場から搬出することができる。
また、シールド工法で掘削された土砂を搬出するためによく用いられるズリトロ(土砂を運搬して運び出すトロッコ)を使用した方法と比べて、軌道設備を簡素化することができるので、狭小な坑内において安全性を確保することができる。
According to the earth and sand carrying-out method of the present invention, even if the amount of earth and sand carried out by the carrying-out means is smaller than the amount of earth and sand excavated by the excavating means per unit time, the carrying-out means carries out during the excavation period. The earth and sand that cannot be stored can be temporarily stored in the earth and sand storage means, and the earth and sand that cannot be carried out by the carrying means during the excavation period can be carried out by the carrying means during the excavation suspension period. Sediment can be efficiently carried out from the excavation site without increasing.
In addition, compared to the method using Zuritro (a truck that transports and transports earth and sand) often used to carry out sediment excavated by the shield method, the track facilities can be simplified, so in a narrow mine Safety can be ensured.

また、本発明において、前記搬出手段は、前記トンネルの施工工程において、前記掘削手段によりトンネルを掘削する掘削期間のうち少なくとも一部の期間と、前記掘削手段によりトンネルを掘削しない掘削休止期間のうち少なくとも一部の期間とに、前記土砂貯蔵手段に貯蔵された土砂を搬出することとしてもよい。   In the present invention, the unloading means includes at least a part of a digging period in which the tunnel is excavated by the excavating means and an excavation suspension period in which the excavating means does not excavate the tunnel in the tunnel construction process. The earth and sand stored in the earth and sand storage means may be carried out at least during a part of the period.

また、本発明において、前記掘削休止期間内に前記搬出手段が前記土砂貯蔵手段に貯蔵された土砂のすべてを搬出できるように、前記掘削休止期間を設定することとしてもよい。この構成によれば、土砂が土砂貯蔵手段から溢れないようにするための掘削休止期間を効率的に設定できる。   Moreover, in this invention, it is good also as setting the said excavation stop period so that the said carrying-out means can carry out all the earth and sand stored in the said sediment storage means within the said excavation stop period. According to this configuration, it is possible to efficiently set the excavation suspension period for preventing the earth and sand from overflowing the earth and sand storage means.

また、本発明において、前記掘削期間終了時に前記掘削手段により掘削された土砂を貯蔵できるように、前記土砂貯蔵手段の容量を設定することとしてもよい。この構成によれば、土砂が土砂貯蔵手段から溢れないようにするための土砂貯蔵手段の容量を効率的に設定することができる。   Moreover, in this invention, it is good also as setting the capacity | capacitance of the said earth and sand storage means so that the earth and sand excavated by the said excavation means at the end of the said excavation period can be stored. According to this configuration, the capacity of the earth and sand storage means for preventing the earth and sand from overflowing from the earth and sand storage means can be set efficiently.

また、本発明において、前記掘削手段として、シールドマシンを用い、前記掘削期間として、前記シールドマシンによるセグメントの1リング分の幅を掘削する期間を設定し、前記掘削休止期間として、前記シールドマシンによって掘削されたトンネルの内壁に前記セグメントを1リング組み立てる期間を設定することとしてもよい。この構成によれば、シールドマシンにより掘削され、土砂貯蔵手段に貯蔵された土砂を、セグメント組み立て期間を有効に利用して搬出手段により搬出することができる。   Further, in the present invention, a shield machine is used as the excavation means, a period for excavating a width corresponding to one ring of the segment by the shield machine is set as the excavation period, and the excavation pause period is set by the shield machine. A period for assembling one ring of the segments on the inner wall of the excavated tunnel may be set. According to this configuration, the earth and sand excavated by the shield machine and stored in the earth and sand storage means can be carried out by the carry-out means by effectively using the segment assembly period.

また、本発明は、トンネルを掘削する掘削手段と、前記掘削手段により掘削された土砂を掘削現場から搬出する搬出手段とを備え、トンネルを施工するにあたり、単位時間当たりの、前記掘削手段によって掘削される土砂の掘削量より、前記搬出手段による土砂の搬出量が少ない場合において使用される、土砂搬出システムであって、前記搬出手段は、前記土砂貯蔵手段から土砂を導入するとともに、前記導入した土砂に泥水を混合してスラリーを作製する土砂スラリー化装置と、前記土砂スラリー化装置で作製されたスラリーを掘削現場から搬出する排泥ポンプとを有し、前記搬出手段の前段に、前記掘削手段により掘削された土砂を一時的に貯蔵し、当該貯蔵した土砂を前記搬出手段に導入する土砂貯蔵手段を備え、前記搬出手段が、前記トンネルの施工工程において、前記掘削手段によりトンネルを掘削する掘削期間と、前記掘削手段によりトンネルを掘削しない掘削休止期間との両期間において、前記土砂貯蔵手段に貯蔵された土砂を搬出することを特徴とする。 Further, the present invention comprises a drilling means for excavating a tunnel and an unloading means for carrying out the earth and sand excavated by the excavating means from the excavation site, and excavated by the excavating means per unit time when constructing the tunnel. The earth and sand carrying system is used when the amount of earth and sand carried by the carrying means is smaller than the amount of excavated earth and sand. The carrying means introduces the earth and sand from the earth and sand storage means and the introduced It has a soil and sand slurrying device that mixes mud water with the soil and makes a slurry, and a mud discharge pump that transports the slurry made by the soil and sand slurrying device from an excavation site. Means for temporarily storing the earth and sand excavated by the means and introducing the stored earth and sand into the carrying-out means; In the tunnel construction process, the earth and sand stored in the earth and sand storage means are carried out in both the excavation period in which the excavation means excavates the tunnel and the excavation suspension period in which the excavation means does not excavate the tunnel. And

本発明によれば、トンネルを掘削する掘削手段(例えば、シールドマシン)と、掘削手段により掘削された土砂を掘削現場から搬出する搬出手段とを用いてトンネルを施工するにあたり、特に、単位時間当たりの、掘削手段による土砂の掘削量より、搬出手段による土砂の搬出量が少ない場合において、掘削現場から土砂を効率的に搬出する土砂搬出方法及びそれを用いた土砂搬出システムを提供できる。 According to the present invention, the drilling means for drilling a tunnel (e.g., shield machine) and, upon applying a tunnel using an unloading means to unload the sediment excavated by drilling means from the drilling site, in particular, the unit time When the amount of sediment transported by the unloading means is smaller than the amount of soil sedimented by the drilling means, it is possible to provide a sediment transporting method for efficiently transporting sediment from the excavation site and a sediment transport system using the same.

以下、本発明の好ましい一実施形態について図面に基づき詳細に説明する。
図1は、本実施形態に係る、シールド工法における土砂搬出方法に使用する設備を示す図である。
Hereinafter, a preferred embodiment of the present invention will be described in detail with reference to the drawings.
FIG. 1 is a diagram showing equipment used in the sediment transport method in the shield method according to the present embodiment.

図1では、シールド工法のうち、泥土圧式シールド工法を用いた場合の掘削された土砂の搬出方法を示している。泥土圧式シールド工法とは、シールドマシン内の土圧室に掘削土砂を充満させ、この土圧によって切羽土圧及び地下水圧等に対抗させて切羽を安定させる工法である。   FIG. 1 shows a method for carrying out excavated earth and sand when the mud pressure shield method is used among the shield methods. The mud pressure type shield construction method is a construction method in which the earth pressure chamber in the shield machine is filled with excavated earth and sand, and the earth pressure is counteracted by the earth pressure and groundwater pressure to stabilize the face.

図1に示すように、本実施形態に係る土砂搬出方法では、シールドマシン10により掘削された土砂を切羽後方に搬送するためのベルトコンベア12と、ベルトコンベア12により移送された土砂を一時的に貯蔵する土砂ストック装置14と、土砂ストック装置14に貯蔵された土砂を導入し、土砂に加泥材を混合してスラリーを作製する土砂スラリー化装置16と、土砂スラリー化装置16で作製されたスラリーをトンネル2の内部から搬出する排泥ポンプ18とを用いる。   As shown in FIG. 1, in the earth and sand carrying-out method according to this embodiment, the belt conveyor 12 for conveying the earth and sand excavated by the shield machine 10 to the rear of the face and the earth and sand transferred by the belt conveyor 12 are temporarily stored. The earth and sand stocking device 14 to be stored, the earth and sand stored in the earth and sand stocking device 14 were introduced, and the earth and sand slurrying device 16 for mixing slurry with the mud to prepare slurry, and the earth and sand slurrying device 16 were used. A sludge pump 18 that carries the slurry out of the tunnel 2 is used.

なお、これらの設備のうち、土砂ストック装置14と、土砂スラリー化装置16と、排泥ポンプ18とは、例えば、トンネル施工中に掘削されたトンネル2の内部に敷設される軌道レール20に載置され、軌道レール20に沿って走行可能な台車22が下部に設けられている。   Of these facilities, the earth and sand stocking device 14, the earth and sand slurrying device 16, and the mud pump 18 are mounted on, for example, a track rail 20 laid inside the tunnel 2 excavated during tunnel construction. A carriage 22 that is placed and can travel along the track rail 20 is provided in the lower part.

ベルトコンベア12は、シールドマシン10により掘削された土砂を、切羽後方の軌道レール20上に配備された土砂ストック装置14まで搬送するためのものである。
なお、ここで用いる土砂を搬送する設備には、ベルトコンベア12に限らず、スクリューコンベアを用いてもよく、また、土砂が流動性を有している場合には圧送方式のポンプを用いてもよい。すなわち、シールドマシン10から掘削される土砂を土砂ストック装置14まで搬送できるものであればよい。
The belt conveyor 12 is for conveying the earth and sand excavated by the shield machine 10 to the earth and sand stock apparatus 14 provided on the track rail 20 behind the face.
The facility for transporting the earth and sand used here is not limited to the belt conveyor 12, and a screw conveyor may be used. In addition, when the earth and sand have fluidity, a pump of a pumping system may be used. Good. That is, any material can be used as long as it can transport the earth and sand excavated from the shield machine 10 to the earth and sand stocking device 14.

土砂ストック装置14としては、シールドマシン10により掘削された土砂を一時的に貯蔵するできる容器であればどのようなものでもよいが、例えば、同図に示すようなアジテータホッパーを用いることができる。
ここで、土砂ストック装置14は、シールドマシン10による掘削期間終了時に掘削された土砂を少なくとも収納できるような容量を備えている。この土砂ストック装置14の容量は、掘削期間と、掘削期間中に掘削される土砂の量と、土砂ストック装置14から搬出される土砂の搬出量速度とによって設定される。
The earth and sand stocking device 14 may be any container that can temporarily store the earth and sand excavated by the shield machine 10. For example, an agitator hopper as shown in the figure can be used.
Here, the earth and sand stock apparatus 14 has a capacity capable of storing at least the earth and sand excavated at the end of the excavation period by the shield machine 10. The capacity of the earth and sand stocking device 14 is set by the excavation period, the amount of earth and sand excavated during the excavation period, and the amount of earth and sand carried out from the earth and sand stocking device 14.

土砂ストック装置14と土砂スラリー化装置16との間には、フィーダーコンベア15が設けられ、土砂ストック装置14に貯蔵された土砂が土砂スラリー化装置16に導入されるようになっている。   A feeder conveyor 15 is provided between the earth and sand stocking device 14 and the earth and sand slurrying device 16, and the earth and sand stored in the earth and sand stocking device 14 is introduced into the earth and sand slurrying device 16.

また、トンネル2の内部には、トンネル2の外部から土砂スラリー化装置16に加泥材を移送するための送泥管24が配管されている。
かかる加泥材には、例えば、泥水又は清水が用いられる。そして、フィーダーコンベア15から土砂スラリー化装置16に導入される土砂の量に対して所定倍率(例えば、約5〜6倍)の量の加泥材が、送泥管24を介して土砂スラリー化装置16に混入されるようになっている。
Further, inside the tunnel 2, a mud feeding pipe 24 for transferring the mud material from the outside of the tunnel 2 to the earth and sand slurrying device 16 is provided.
For example, muddy water or fresh water is used as the muddy material. Then, the amount of mud added at a predetermined magnification (for example, about 5 to 6 times) with respect to the amount of earth and sand introduced from the feeder conveyor 15 to the earth and sand slurrying device 16 is sludged into the earth and sand via the mud pipe 24. The device 16 is mixed.

また、土砂スラリー化装置16内には攪拌機17が備えられており、土砂スラリー化装置16に導入された土砂と加泥材は、混合攪拌されてスラリーになる。   Further, the earth and sand slurrying device 16 is provided with a stirrer 17, and the earth and sand and the mud material introduced into the earth and sand slurrying device 16 are mixed and stirred into a slurry.

排泥ポンプ18としては、例えば、コンクリートやモルタルを圧送するためのポンプを用いることができる。排泥ポンプ18には、トンネル2の外部から配管される排泥管26が接続され、排泥ポンプ18により圧送されたスラリーは排泥管26を介してトンネル2の外部に搬出される。   As the mud pump 18, for example, a pump for pumping concrete or mortar can be used. The mud pump 18 is connected to a mud pipe 26 piped from the outside of the tunnel 2, and the slurry pumped by the mud pump 18 is carried out of the tunnel 2 through the mud pipe 26.

トンネル2の外部に搬出されたスラリーは、例えば、トンネル2の外部に設置される泥水処理プラント28に移送され、泥水と土砂とに分離される。そして、分離された土砂は一般残土として処分される。一方、分離された泥水は、送泥ポンプ30により送泥管24を介して再びトンネル2の内部の土砂スラリー装置まで移送され、土砂に混入されて利用される。   The slurry carried out of the tunnel 2 is transferred to, for example, a muddy water treatment plant 28 installed outside the tunnel 2 and separated into muddy water and earth and sand. The separated earth and sand are disposed of as general residual soil. On the other hand, the separated muddy water is transferred again by the mud pump 30 through the mud pipe 24 to the earth and sand slurry device inside the tunnel 2 and mixed with the earth and sand for use.

本実施形態に係る土砂搬出方法は、特に、シールドマシン10によって掘削される土砂が、上記設備のうち、土砂スラリー化装置16と排泥ポンプ18とを用いるだけでは搬出できない場合に有効である。
すなわち、シールドマシン10の掘削期間中に掘削される土砂の量が大きいため、シールドマシン10が掘削した土砂を、直接土砂スラリー化装置16に投入すると、その土砂に加泥材が追加されることにより増量したスラリーの量が、同掘削期間中に排泥ポンプ18により搬出可能な量を超えるような場合である。この場合、土砂スラリー化装置16で作製されるスラリーが、土砂スラリー化装置16からオーバーフローしてしまう。
The earth and sand carrying-out method according to the present embodiment is particularly effective when the earth and sand excavated by the shield machine 10 cannot be carried out only by using the earth and sand slurrying device 16 and the mud pump 18 among the above facilities.
That is, since the amount of earth and sand excavated during the excavation period of the shield machine 10 is large, when the earth and sand excavated by the shield machine 10 is directly input to the earth and sand slurrying device 16, a mud is added to the earth and sand. This is a case where the amount of the slurry increased by the amount exceeds the amount that can be carried out by the mud pump 18 during the excavation period. In this case, the slurry produced by the earth and sand slurrying apparatus 16 overflows from the earth and sand slurrying apparatus 16.

そこで、本実施形態では、土砂を搬出するのに、土砂スラリー化装置16及び排泥ポンプ18とともに、土砂ストック装置14を用いている。   Therefore, in the present embodiment, the earth and sand stocking device 14 is used together with the earth and sand slurrying device 16 and the mud pump 18 to carry out the earth and sand.

図2は、本実施形態に係る土砂搬出方法を説明するための図であり、同図(a)は掘削期間中、同図(b)は掘削休止期間中を示す。
なお、ここでいう掘削期間とは、例えば、トンネル覆工体としてシールドマシン10により掘削されたトンネル2の内壁に設置されるセグメント4の1リング分の幅を掘削する期間をいい、掘削休止期間とは、セグメント4を1リング分の幅を掘削した後に、セグメント4を組み立てる期間をいう。
2A and 2B are diagrams for explaining the sediment transport method according to the present embodiment, in which FIG. 2A shows the excavation period and FIG. 2B shows the excavation suspension period.
The excavation period here refers to, for example, a period in which the width of one ring of the segment 4 installed on the inner wall of the tunnel 2 excavated by the shield machine 10 as a tunnel lining body is excavated, and the excavation pause period Means a period for assembling the segment 4 after excavating the width of the segment 4 for one ring.

図2(a)に示すように、本実施形態に係る土砂搬出方法では、掘削期間中にシールドマシン10によって掘削された土砂を、一旦、ベルトコンベア12により土砂ストック装置14にすべて移送し、その後、フィーダーコンベア15により土砂ストック装置14から土砂スラリー化装置16へ土砂を搬送する。このとき、フィーダーコンベア15による土砂の搬送量を、土砂スラリー化装置16で作製されるスラリーが土砂スラリー化装置16からオーバーフローすることなく排泥ポンプ18により搬出されるように調節する。   As shown in FIG. 2 (a), in the sediment transport method according to the present embodiment, all the sediment excavated by the shield machine 10 during the excavation period is once transferred to the sediment stock apparatus 14 by the belt conveyor 12, and thereafter The earth and sand are conveyed from the earth and sand stocking device 14 to the earth and sand slurrying device 16 by the feeder conveyor 15. At this time, the amount of earth and sand transported by the feeder conveyor 15 is adjusted so that the slurry produced by the earth and sand slurrying device 16 is carried out by the mud pump 18 without overflowing from the earth and sand slurrying device 16.

ここで、掘削期間中は、土砂ストック装置14から土砂スラリー化装置16への土砂の搬送量よりも、シールドマシン10による掘削される土砂量の方が多いので、土砂ストック装置14には、掘削土砂の量が増加していく。   Here, during the excavation period, the amount of earth and sand to be excavated by the shield machine 10 is larger than the amount of earth and sand transported from the earth and sand stock device 14 to the earth and sand slurrying device 16. The amount of earth and sand increases.

また、図2(b)に示すように、掘削休止期間中には、掘削期間中と同様にフィーダーコンベア15により土砂ストック装置14から土砂スラリー化装置16へ土砂を搬送するとともに、土砂スラリー化装置16で作製されるスラリーを排泥ポンプ18により搬出する。
これにより、掘削期間中に土砂ストック装置14に貯蔵された土砂量が減少していく。
In addition, as shown in FIG. 2B, during the excavation suspension period, as in the excavation period, the earth and sand are conveyed from the earth and sand stock device 14 to the earth and sand slurrying device 16 by the feeder conveyor 15, and the earth and sand slurrying device. The slurry produced in 16 is carried out by the mud pump 18.
As a result, the amount of earth and sand stored in the earth and sand stocking device 14 during the excavation period decreases.

ここで、掘削休止期間を、その期間内に土砂ストック装置14に貯蔵された土砂がすべて搬送されるように設定する。このようにすることで、土砂ストック装置14に貯蔵された土砂が残存した状態で掘削を再開した場合、土砂ストック装置14内の土砂の量が、掘削期間と掘削休止期間とを繰り返すうちに増加することはなく、土砂が土砂ストック装置14からオーバーフローするのを防止できる。   Here, the excavation suspension period is set so that all of the earth and sand stored in the earth and sand stocking device 14 is conveyed within that period. By doing in this way, when excavation is restarted in the state where the earth and sand stored in the earth and sand stocking device 14 remains, the amount of earth and sand in the earth and sand stocking device 14 increases while repeating the excavation period and the excavation pause period. The earth and sand can be prevented from overflowing from the earth and sand stocking apparatus 14.

また、土砂ストック装置14として、少なくとも掘削期間終了時における掘削された土砂を収納できるような容積を確保することに留意する。すなわち、シールドマシン10により掘削期間中に掘削された土砂の量から、同掘削期間中に土砂ストック装置14から土砂スラリー化装置16へ搬送された量を差引いた量を収納できる容積を、土砂ストック装置14が有していればよい。   In addition, it should be noted that the earth and sand stock device 14 has a capacity to store at least the excavated earth and sand at the end of the excavation period. That is, the volume that can store the amount of earth and sand excavated by the shield machine 10 during the excavation period minus the amount conveyed from the earth and sand stock device 14 to the earth and sand slurrying device 16 during the excavation period, What is necessary is just to have the apparatus 14. FIG.

以上のようにシールドマシン10により掘削された土砂を搬送することにより、掘削土砂をトンネル2の外部に効率よく円滑に搬出することができる。   By transporting the earth and sand excavated by the shield machine 10 as described above, the excavated earth and sand can be efficiently and smoothly carried out of the tunnel 2.

次に、シールドマシン10によって掘削される土砂を、土砂ストック装置14を用いずに搬出する場合(ケース1)と、本実施形態のように土砂ストック装置14を用いて搬出する場合(ケース2)とについて、具体的な数値を設定して、掘進速度、掘削期間、及び掘削休止期間を求め、比較検討する数値実験を行ったので、以下にその詳細について説明する。
なお、その他の比較例として、土砂ストック装置14を用いずに土砂を搬出する場合において、排出能力を向上させた排泥ポンプ18を用いたとき(ケース3)の数値実験も行った。
Next, the case where the earth and sand excavated by the shield machine 10 is carried out without using the earth and sand stock apparatus 14 (case 1), and the case where the earth and sand stock apparatus 14 is carried out as in the present embodiment (case 2). As for numerical values, a specific numerical value is set, and the numerical value of the excavation speed, the excavation period, and the excavation suspension period is obtained and compared. The details will be described below.
In addition, as another comparative example, when carrying out the earth and sand without using the earth and sand stocking device 14, a numerical experiment was performed when the mud pump 18 with improved discharge capacity was used (case 3).

図3は、数値実験に使用した条件を説明するための図である。   FIG. 3 is a diagram for explaining the conditions used in the numerical experiment.

図3に示すように、シールドマシン10により直径4mのトンネル2を、セグメント4の1リングの幅である1m掘削し、当該掘削した土砂に土砂スラリー化装置16で約5倍(土砂:泥水=16.5:83.5)の容積の泥水を混合してスラリーを作製し、当該スラリーを排泥ポンプ18で搬出する場合において、上記ケース1〜3について数値実験を行った。   As shown in FIG. 3, the tunnel 2 having a diameter of 4 m is excavated by 1 m which is the width of one ring of the segment 4 by the shield machine 10, and the excavated earth and sand is about five times (sand: mud water = 16.5: 83.5) The volume of muddy water was mixed to produce a slurry, and when the slurry was carried out by the mud pump 18, numerical experiments were conducted for cases 1 to 3 above.

ケース1では、掘削した土砂を、土砂ストック装置14を用いず、土砂スラリー化装置16に直接移送し、土砂スラリー化装置16でスラリー化させて、2m/分の搬出量を備える排泥ポンプ18を用いて土砂スラリー化装置16内のスラリーを搬出することとした。 In case 1, the excavated earth and sand is directly transferred to the earth and sand slurrying apparatus 16 without using the earth and sand stocking apparatus 14, and is slurried by the earth and sand slurrying apparatus 16 and is provided with a discharge amount of 2 m 3 / min. 18 was used to carry out the slurry in the sediment slurrying apparatus 16.

ケース2では、掘削した土砂を、先ず、土砂ストック装置14に移送し、その後、フィーダーコンベア15により土砂ストック装置14から土砂スラリー化装置16に徐々に移送し、土砂スラリー化装置16でスラリー化させて、2m/分の搬出量を備える排泥ポンプ18を用いて土砂スラリー化装置16内のスラリーを搬出することとした。 In case 2, the excavated earth and sand are first transferred to the earth and sand stocking device 14, and then gradually transferred from the earth and sand stocking device 14 to the earth and sand slurrying device 16 by the feeder conveyor 15 and slurried by the earth and sand slurrying device 16. Thus, the slurry in the earth and sand slurrying device 16 is carried out by using the mud pump 18 having a carry-out amount of 2 m 3 / min.

ケース3では、掘削した土砂を、土砂ストック装置14を用いず、土砂スラリー化装置16に直接移送し、土砂スラリー化装置16でスラリー化させて、4m/分の搬出量を備える排泥ポンプ18を用いて土砂スラリー化装置16内のスラリーを搬出することとした。 In case 3, the excavated earth and sand are directly transferred to the earth and sand slurrying apparatus 16 without using the earth and sand stocking apparatus 14, and are slurried by the earth and sand slurrying apparatus 16 to provide a discharge mud pump having a discharge amount of 4 m 3 / min. 18 was used to carry out the slurry in the sediment slurrying apparatus 16.

なお、各ケースとも、シールドマシン10による掘削後のセグメント4の組み立てに35分かかることとし、この時間を掘削休止期間とした。   In each case, it took 35 minutes to assemble the segment 4 after excavation by the shield machine 10, and this time was set as the excavation suspension period.

このような条件の下、まず、シールドマシン10により掘削される土砂の量は、直径4m(=半径2m)のトンネル2をセグメント4の1リング分である1m掘進した量に相当するので、数式1のように約13m発生する。
π×(2(m))×1m≒13(m) ・・・ (数式1)
Under such conditions, first, the amount of earth and sand excavated by the shield machine 10 corresponds to the amount of tunnel 1 having a diameter of 4 m (= 2 m radius) that has been excavated by 1 m, which is one ring of the segment 4. As shown in Fig. 1, approximately 13 m 3 is generated.
π × (2 (m)) 2 × 1 m≈13 (m 3 ) (Formula 1)

また、スラリーは土砂に対し約5倍(土砂:泥水=16.5:83.5)の容積の泥水を混合するので、数式2のように約80m発生する。
13(m)/16.5×100≒80(m) ・・・ (数式2)
Further, the slurry is mixed with muddy water having a volume about 5 times that of the earth (sand: mud water = 16.5: 83.5), so that about 80 m 3 is generated as shown in Equation 2.
13 (m 3 ) /16.5×100≈80 (m 3 ) (Formula 2)

図4は、各ケースについての、掘進速度、掘削期間、掘削休止期間、掘削とセグメント組み立てとに要する時間等をまとめて表にしたものである。   FIG. 4 is a table summarizing the excavation speed, excavation period, excavation suspension period, time required for excavation and segment assembly, and the like for each case.

図4に示すように、ケース1の場合では、上記約80m発生したスラリーを、2m/分の搬出量を備える排泥ポンプ18で搬出するのに、数式3のように40分かかる。
80(m)/2(m/分)=40(分) ・・・ (数式3)
したがって、ケース1では、掘削した土砂を、土砂ストック装置14を用いず、土砂スラリー化装置16に直接移送するので、土砂スラリー化装置16からスラリーをオーバーフローさせないようにするために、シールドマシン10の掘進速度を、数式4のように2.5cm/分に制限する必要がある。
1(m)/40(分)=2.5(cm/分) ・・・ (数式4)
As shown in FIG. 4, in case 1, it takes 40 minutes as shown in Equation 3 to carry out the slurry generated in about 80 m 3 by the mud pump 18 having a carry-out amount of 2 m 3 / min.
80 (m 3 ) / 2 (m 3 / min) = 40 (min) (Formula 3)
Therefore, in case 1, since the excavated earth and sand are directly transferred to the earth and sand slurrying apparatus 16 without using the earth and sand stocking apparatus 14, in order to prevent the slurry from overflowing from the earth and sand slurrying apparatus 16, the shield machine 10 It is necessary to limit the excavation speed to 2.5 cm / min as shown in Equation 4.
1 (m) / 40 (min) = 2.5 (cm / min) (Formula 4)

また掘削後、セグメント組み立て時間に35分要するので、掘削とセグメント組み立てとの1サイクルに要する時間は75分(掘削時間40分+セグメント組み立て時間35分)となる。   In addition, since the segment assembly time is 35 minutes after excavation, the time required for one cycle of excavation and segment assembly is 75 minutes (excavation time 40 minutes + segment assembly time 35 minutes).

一方、ケース2の場合(本実施形態に係る土砂搬出方法)では、上記約80m発生したスラリーに対し、ケース1と同様に、2m/分の搬出量を備える排泥ポンプ18で搬出するので、スラリーをすべてトンネル2の内部から搬出するのにケース1と同じく40分かかる。
しかしながら、ケース2では、掘削期間に搬出できない土砂を土砂ストック装置14に貯蔵することができる。これにより、シールドマシン10の掘進速度をケース1と比べて速めることができる。
例えば、シールドマシン10の掘進速度を5.0cm/分とした場合、掘削期間はケース1の半分に短縮され20分となるが、その後のセグメント組み立て時間が35分あるので、次の掘削再開まで合計55分間、排泥ポンプ18が土砂スラリー化装置16からスラリーを搬出する期間にあてることができる。これに対し、ケース2では、スラリーをすべてトンネル2の内部から搬出するのにケース1と同じく40分しか要しないので、搬出に必要な期間が足りる。
On the other hand, in the case 2 (the earth and sand carrying-out method according to the present embodiment), the slurry generated about 80 m 3 is carried out by the mud pump 18 having a carrying-out amount of 2 m 3 / min as in the case 1. Therefore, it takes 40 minutes to carry out all the slurry from the inside of the tunnel 2 as in the case 1.
However, in case 2, the earth and sand that cannot be carried out during the excavation period can be stored in the earth and sand stocking device 14. Thereby, the excavation speed of the shield machine 10 can be increased compared to the case 1.
For example, when the excavation speed of the shield machine 10 is 5.0 cm / min, the excavation period is shortened to half that of Case 1 to 20 minutes, but since the subsequent segment assembly time is 35 minutes, the next excavation resumes. A total of 55 minutes can be applied to the period during which the sludge pump 18 carries the slurry out of the sediment slurrying device 16. On the other hand, in case 2, it takes only 40 minutes to carry out all the slurry from the inside of the tunnel 2 as in the case 1, so that a period necessary for carrying out is sufficient.

なお、掘進速度を5.0cm/分に設定した場合、掘削期間終了時点では掘削が始まってから20分経過しているので、排泥ポンプ18から、80mの半分の量である40mのスラリーが既に排出されている。すわなち、土砂量に換算すると13mの半分の量である6.5mが搬出され、残りの6.5mが土砂ストック装置14に貯蔵されていることになる。
したがって、土砂ストック装置14の土砂を収納する容積を、少なくとも6.5m確保すればよい。
In addition, when the excavation speed is set to 5.0 cm / min, since 20 minutes have passed since the excavation started at the end of the excavation period, 40 m 3 , which is half of 80 m 3 , from the mud pump 18. The slurry has already been discharged. Nachi Suwa, is 6.5m 3 is the amount of half of 13m 3 in terms of sediment volume is unloaded, so that the remaining 6.5m 3 are stored in the sediment collecting assembly 14.
Therefore, what is necessary is just to ensure the volume which accommodates the earth and sand of the earth and sand stock apparatus 14 at least 6.5 m < 3 >.

また、ケース3の場合では、数式2で求めた約80mのスラリーを4m/分の搬出量を備える排泥ポンプ18で搬出するので、排出に要する時間は、数式5のように20分かかる。
80(m)/4(m/分)=20(分) ・・・ (数式5)
したがって、この時のシールドマシン10の掘進速度を、数式6のように5.0cm/分に速めることができる。
1(m)/40(分)=5.0(cm/分) ・・・ (数式6)
Further, in case 3, since about 80 m 3 of the slurry obtained by Equation 2 is carried out by the mud pump 18 having a carry-out amount of 4 m 3 / min, the time required for discharging is 20 minutes as shown in Equation 5. Take it.
80 (m 3 ) / 4 (m 3 / min) = 20 (min) (Formula 5)
Therefore, the excavation speed of the shield machine 10 at this time can be increased to 5.0 cm / min as shown in Equation 6.
1 (m) / 40 (min) = 5.0 (cm / min) (Formula 6)

ケース3でも、掘削後のセグメント組み立て時間に35分要するので、掘削とセグメント組み立てとの1サイクルに要する時間は、ケース2と同じ55分(掘削時間20分+セグメント組み立て時間35分)となる。   Even in case 3, since the segment assembly time after excavation takes 35 minutes, the time required for one cycle of excavation and segment assembly is 55 minutes (excavation time 20 minutes + segment assembly time 35 minutes).

しかしながら、ケース3の場合、排泥ポンプ18の排出能力を向上させると大型化するので、小断面のトンネル2では坑内に設置可能な設備の寸法が制限されることにより設置できないおそれがある。
また、トンネル2の内部に大型の排泥ポンプ18を設置できたとしても、大型の排泥ポンプ18の使用よる施工コストが増大するとともに、坑内の作業スペースが狭小になり安全性を確保する点で不利になるおそれもある。
However, in the case 3, if the discharge capacity of the mud pump 18 is improved, the size of the tunnel 2 is increased. Therefore, the tunnel 2 having a small cross section may be unable to be installed because the size of equipment that can be installed in the mine is limited.
Moreover, even if the large-scale mud pump 18 can be installed inside the tunnel 2, the construction cost due to the use of the large-scale mud pump 18 increases, and the working space in the mine is narrowed to ensure safety. Can be disadvantageous.

以上説明したように、本実施形態に係る土砂搬出方法では、土砂ストック装置14の前段に、シールドマシン10により掘削された土砂を一時的に貯蔵し、当該貯蔵した土砂を土砂スラリー化装置16に導入する土砂ストック装置14を設け、土砂ストック装置14において土砂に泥水を混合することにより作製されたスラリーを、排泥ポンプ18により搬出させる。
ここで、排泥ポンプ18は、トンネル2の施工工程において、シールドマシン10によりトンネル2を掘削する掘削期間のうち少なくとも一部の期間と、シールドマシン10によりトンネル2を掘削しない掘削休止期間のうち少なくとも一部の期間とに、スラリーを搬出する。
As described above, in the sediment transport method according to the present embodiment, the sediment excavated by the shield machine 10 is temporarily stored in the previous stage of the sediment stock device 14, and the stored sediment is stored in the sediment slurrying device 16. The sediment stock apparatus 14 to be introduced is provided, and the slurry produced by mixing mud water with the sediment in the sediment stock apparatus 14 is carried out by the mud pump 18.
Here, in the construction process of the tunnel 2, the mud pump 18 includes at least a part of the excavation period during which the tunnel 2 is excavated by the shield machine 10 and the excavation suspension period during which the tunnel 2 is not excavated by the shield machine 10. The slurry is unloaded at least during some period.

これにより、シールドマシン10によって掘削される土砂の掘削量より、土砂スラリー化装置16及び排泥ポンプ18による土砂の搬出量が少ない場合であっても、掘削期間内に排泥ポンプ18によって搬出できないスラリーの量に相当する土砂を土砂ストック装置14に貯蔵することができ、また、掘削休止期間内に、掘削期間に排泥ポンプ18によって搬出できなかったスラリーの量に相当する土砂を、土砂スラリー化装置16や排泥ポンプ18によって搬出することができるので、排泥ポンプ18の搬出量を増大させることなく、土砂を効率的にトンネル2の内部から外部に搬出することができる。   Thereby, even if the amount of earth and sand carried out by the earth and sand slurrying device 16 and the mud pump 18 is smaller than the amount of earth and sand excavated by the shield machine 10, it cannot be carried out by the mud pump 18 within the excavation period. The earth and sand corresponding to the amount of the slurry can be stored in the earth and sand stocking device 14, and the earth and sand corresponding to the amount of the slurry that could not be carried out by the mud pump 18 during the excavation period can be stored in the earth and sand slurry. Therefore, the sediment can be efficiently carried out from the inside of the tunnel 2 without increasing the carry-out amount of the mud pump 18.

また、本実施形態に係る土砂搬出方法によれば、掘削休止期間内に、排泥ポンプ18が、土砂ストック装置14に貯蔵された土砂のすべてをスラリー化したときに該スラリーを搬出できるように、掘削休止期間を設定することにより、土砂ストック装置14から土砂が溢れないようにするための掘削休止期間を効率的に設定することができる。   Moreover, according to the earth and sand carrying-out method which concerns on this embodiment, it is possible to carry out this slurry, when the mud pump 18 slurries all the earth and sand stored in the earth and sand stock apparatus 14 within the excavation suspension period. By setting the excavation suspension period, it is possible to efficiently set the excavation suspension period for preventing sediment from overflowing from the sediment storage device 14.

また、本実施形態に係る土砂搬出方法によれば、掘削期間終了時にシールドマシン10により掘削された土砂を貯蔵できるように、土砂ストック装置14の容量を設定することにより、土砂ストック装置14から土砂が溢れないようにするための容量を効率的に設定することができる。   Moreover, according to the earth and sand carrying-out method which concerns on this embodiment, by setting the capacity | capacitance of the earth and sand stock apparatus 14 so that the earth and sand excavated by the shield machine 10 can be stored at the end of the excavation period, It is possible to efficiently set a capacity for preventing overflow.

本実施形態に係る、シールド工法における土砂搬出方法に使用する設備を示す図である。It is a figure which shows the equipment used for the earth and sand carrying-out method in the shield construction method based on this embodiment. 本実施形態に係る土砂搬出方法を説明するための図であり、同図(a)は掘削期間中、同図(b)は掘削休止期間中を示す。It is a figure for demonstrating the earth and sand carrying-out method which concerns on this embodiment, the figure (a) shows during a digging period, and the figure (b) shows during a digging suspension period. 数値実験に使用した条件を示す図である。It is a figure which shows the conditions used for the numerical experiment. 各ケースについての、掘進速度、掘削期間、掘削休止期間、掘削とセグメント組み立てとに要する時間等をまとめて表にしたものである。For each case, the excavation speed, excavation period, excavation suspension period, time required for excavation and segment assembly, etc. are summarized in a table.

符号の説明Explanation of symbols

2 トンネル
4 セグメント
10 シールドマシン
12 ベルトコンベア
14 土砂ストック装置
15 フィーダーコンベア
16 土砂スラリー化装置
17 攪拌機
18 排泥ポンプ
20 軌道レール
22 台車
24 送泥管
26 排泥管
28 泥水処理プラント
30 送泥ポンプ
2 Tunnel 4 Segment 10 Shield Machine 12 Belt Conveyor 14 Sediment Stock Equipment 15 Feeder Conveyor 16 Sediment Slurry 17 Stirrer 18 Mud Pump 20 Track Rail 22 Dolly 24 Mud Pipe 26 Mud Pipe 28 Mud Treatment Plant 30 Mud Pump

Claims (6)

トンネルを掘削する掘削手段と、前記掘削手段により掘削された土砂を掘削現場から搬出する搬出手段とを用いてトンネルを施工するにあたり、単位時間当たりの、前記掘削手段によって掘削される土砂の掘削量より、前記搬出手段による土砂の搬出量が少ない場合における、土砂搬出方法であって、
前記搬出手段の前段に、前記掘削手段により掘削された土砂を一時的に貯蔵し、当該貯蔵した土砂を前記搬出手段に導入する土砂貯蔵手段を設け、
前記搬出手段により前記土砂貯蔵手段に貯蔵された土砂を搬出させ
前記搬出手段として、前記土砂貯蔵手段から土砂を導入するとともに、前記導入した土砂に泥水を混合してスラリーを作製する土砂スラリー化装置と、前記土砂スラリー化装置で作製されたスラリーを掘削現場から搬出する排泥ポンプとを用いることを特徴とする土砂搬出方法。
Excavation amount of earth and sand excavated by the excavating means per unit time when constructing the tunnel using excavating means for excavating the tunnel and unloading means for carrying out the earth and sand excavated by the excavating means from the excavation site More, a method for carrying out earth and sand when the amount of earth and sand carried out by the carrying-out means is small,
In the previous stage of the unloading means, the earth and sand excavated by the excavating means is temporarily stored, and earth and sand storage means for introducing the stored earth and sand into the unloading means,
The earth and sand stored in the earth and sand storage means are carried out by the carry-out means ,
As the unloading means, the earth and sand is introduced from the earth and sand storage means, and the earth and sand slurrying apparatus for preparing slurry by mixing muddy water into the introduced earth and sand, and the slurry produced by the earth and sand slurrying apparatus from the excavation site A method for carrying out earth and sand, characterized by using an unloading mud pump .
前記搬出手段は、前記トンネルの施工工程において、前記掘削手段によりトンネルを掘削する掘削期間のうち少なくとも一部の期間と、前記掘削手段によりトンネルを掘削しない掘削休止期間のうち少なくとも一部の期間とに、前記土砂貯蔵手段に貯蔵された土砂を搬出することを特徴とする請求項1に記載の土砂搬出方法。   In the tunnel construction process, the unloading means includes at least a part of a digging period in which the digging means digs a tunnel, and at least a part of a digging suspension period in which the digging means does not dig a tunnel; The method according to claim 1, wherein the earth and sand stored in the earth and sand storage means are carried out. 前記掘削休止期間内に前記搬出手段が前記土砂貯蔵手段に貯蔵された土砂のすべてを搬出できるように、前記掘削休止期間を設定することを特徴とする請求項2に記載の土砂搬出方法。   The sediment excavation period according to claim 2, wherein the excavation suspension period is set so that the unloading means can carry out all of the sediment stored in the sediment storage means within the excavation suspension period. 前記掘削期間終了時に前記掘削手段により掘削された土砂を貯蔵できるように、前記土砂貯蔵手段の容量を設定することを特徴とする請求項2又は3に記載の土砂搬出方法。   4. The sediment transport method according to claim 2, wherein a capacity of the sediment storage means is set so that sediment excavated by the excavation means can be stored at the end of the excavation period. 前記掘削手段として、シールドマシンを用い、
前記掘削期間として、前記シールドマシンによるセグメントの1リング分の幅を掘削する期間を設定し、
前記掘削休止期間として、前記シールドマシンによって掘削されたトンネルの内壁に前記セグメントを1リング組み立てる期間を設定することを特徴とする請求項2〜4の何れか1項に記載の土砂搬出方法。
As the excavation means, using a shield machine,
As the excavation period, set a period for excavating the width of one ring of the segment by the shield machine,
The earth and sand carrying-out method according to any one of claims 2 to 4, wherein a period for assembling one ring of the segments on the inner wall of the tunnel excavated by the shield machine is set as the excavation suspension period.
トンネルを掘削する掘削手段と、前記掘削手段により掘削された土砂を掘削現場から搬出する搬出手段とを備え、トンネルを施工するにあたり、単位時間当たりの、前記掘削手段によって掘削される土砂の掘削量より、前記搬出手段による土砂の搬出量が少ない場合において使用される、土砂搬出システムであって、
前記搬出手段は、前記土砂貯蔵手段から土砂を導入するとともに、前記導入した土砂に泥水を混合してスラリーを作製する土砂スラリー化装置と、前記土砂スラリー化装置で作製されたスラリーを掘削現場から搬出する排泥ポンプとを有し、
前記搬出手段の前段に、前記掘削手段により掘削された土砂を一時的に貯蔵し、当該貯蔵した土砂を前記搬出手段に導入する土砂貯蔵手段を備え、
前記搬出手段が、前記土砂貯蔵手段に貯蔵された土砂を搬出することを特徴とする土砂搬出システム。
An excavation means for excavating a tunnel, and an unloading means for carrying out the earth and sand excavated by the excavation means from an excavation site. More, a sediment transport system used when the transport amount of sediment by the transport means is small,
The unloading means introduces the earth and sand from the earth and sand storage means, and mixes the introduced earth and sand with muddy water to produce a slurry, and the slurry produced by the earth and sand slurrying apparatus from the excavation site. A mud pump to carry out,
In the front stage of the unloading means, the earth and sand excavated by the excavation means is temporarily stored, and the earth and sand storage means for introducing the stored earth and sand into the unloading means,
The earth and sand carrying-out system, wherein the carrying-out means carries out the earth and sand stored in the earth and sand storage means.
JP2008301288A 2008-11-26 2008-11-26 Sediment transport method and sediment transport system Expired - Fee Related JP5206363B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008301288A JP5206363B2 (en) 2008-11-26 2008-11-26 Sediment transport method and sediment transport system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008301288A JP5206363B2 (en) 2008-11-26 2008-11-26 Sediment transport method and sediment transport system

Publications (2)

Publication Number Publication Date
JP2010126947A JP2010126947A (en) 2010-06-10
JP5206363B2 true JP5206363B2 (en) 2013-06-12

Family

ID=42327526

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008301288A Expired - Fee Related JP5206363B2 (en) 2008-11-26 2008-11-26 Sediment transport method and sediment transport system

Country Status (1)

Country Link
JP (1) JP5206363B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106150509A (en) * 2016-08-05 2016-11-23 中铁工程装备集团有限公司 A kind of double track tunnel is non-bores quick-fried mechanized construction method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62174498A (en) * 1986-01-24 1987-07-31 三菱重工業株式会社 Method of measuring quantity of earth removed in shielding type tunnel excavator
JP2002180790A (en) * 2000-12-14 2002-06-26 Toda Constr Co Ltd Slurry transporting system and slurry transporting method
JP2002250197A (en) * 2001-02-23 2002-09-06 Ohbayashi Corp Shield machine

Also Published As

Publication number Publication date
JP2010126947A (en) 2010-06-10

Similar Documents

Publication Publication Date Title
JP5462761B2 (en) Tunnel construction method
KR101381566B1 (en) super slurry type shield tunneling machine and super slurry type propulsion method using it
JP6463222B2 (en) Processing method and processing system of excavated soil
KR100902364B1 (en) Shield tunneling apparatus and constructing method thereof
JP5206363B2 (en) Sediment transport method and sediment transport system
JP2012120987A (en) Method for purifying excavated soil when shield construction is performed in contaminated soil and shield excavator
JP2011038344A (en) Treatment method of slime-containing muddy water and treatment system therefor
KR20170093024A (en) The shield tunnel excavator and it&#39;s tunnel excavation method with reverse injection of underground water
JP3253931B2 (en) Tunnel construction method
JP5010998B2 (en) Processing equipment, processing method of excavated sediment
JP5826347B2 (en) Fluid transport method of excavated soil using foam suppressor in bubble shield method
JP6536633B2 (en) Method and system for purifying contaminated soil in shield method
JP4273031B2 (en) Stabilization method of ground in shield method
JPH08105290A (en) Excavated sediment recycling system in mud type shield construction method
JP2017071957A (en) Propulsion device
JP5670683B2 (en) Backfill injection system and method
JPH0366898A (en) Soil and sand carryout method in shield method and soil modifying device
JP2004169455A (en) Mud type pipe jacking method and boring machine
JP2817493B2 (en) Construction method of shield tunnel
JP5366652B2 (en) Soil reforming equipment and soil reforming method
JP2003138883A (en) Tunnel boring machine
JP4172021B2 (en) Shield excavator
JP2003071825A (en) Agitator tank for mud mixed with cement
JP2824041B2 (en) Earth removal method and device in earth pressure shield method
JPH02217595A (en) Improvement of soil quality

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20111020

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20121024

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20121030

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20121221

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20130122

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130204

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20160301

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees