JP2749388B2 - Retaining method for soft ground - Google Patents

Retaining method for soft ground

Info

Publication number
JP2749388B2
JP2749388B2 JP22368189A JP22368189A JP2749388B2 JP 2749388 B2 JP2749388 B2 JP 2749388B2 JP 22368189 A JP22368189 A JP 22368189A JP 22368189 A JP22368189 A JP 22368189A JP 2749388 B2 JP2749388 B2 JP 2749388B2
Authority
JP
Japan
Prior art keywords
ground
fixing
area
anchor
soft ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP22368189A
Other languages
Japanese (ja)
Other versions
JPH0387416A (en
Inventor
秀則 小寺
邦洋 小笠原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP22368189A priority Critical patent/JP2749388B2/en
Publication of JPH0387416A publication Critical patent/JPH0387416A/en
Application granted granted Critical
Publication of JP2749388B2 publication Critical patent/JP2749388B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、アンカーを軟弱地盤に定着させることに
より、前記軟弱地盤の山留めをする工法に関する。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention relates to a method of fixing a soft ground by anchoring an anchor to the soft ground.

〔従来の技術〕[Conventional technology]

地下構造物を構築する際には、周辺地盤の山留めとし
て山留め壁が施工され、これにより周辺地盤の崩壊を防
止することが行われている。この山留め壁としては、現
位置混合固化壁,コンクリート連続壁、親杭横矢板等の
壁を使用することが公知であり、周囲の地盤の強度が充
分な場合には、地下構造物の構築のために囲まれた区域
を掘削するに際しては、土圧や水圧に基づく山留め壁の
変形防止のために、地盤に植設したアンカーにより前記
壁を支持することが行われている。このアンカーによる
山留め壁の支持は、山留め壁に囲まれた地下構造物の構
築領域に、邪魔になる梁等が存在しないために地下構造
物の構築作業性に優れている。
When constructing an underground structure, a retaining wall is constructed as a retaining ground for the surrounding ground, thereby preventing the collapse of the surrounding ground. As this retaining wall, it is known to use a wall such as a mixed solidified wall at the current position, a continuous wall of concrete, a parent pile horizontal sheet pile, or the like, if the strength of the surrounding ground is sufficient, the construction of an underground structure is required. When excavating the enclosed area, the wall is supported by an anchor planted on the ground to prevent deformation of the retaining wall due to earth pressure or water pressure. The support of the retaining wall by the anchor is excellent in the workability of constructing the underground structure because there are no obstacles or the like in the construction area of the underground structure surrounded by the retaining wall.

一方、前記周辺地盤が軟弱である場合には、地盤にア
ンカーの定着力を期待することができないから、山留め
壁に囲まれている地下構造物の構築領域において、対向
する山留め壁間に切梁を掛け渡して、この切梁によって
山留め壁を支持することが行われている。
On the other hand, if the surrounding ground is soft, it is not possible to expect anchoring power of the ground, so in the construction area of the underground structure surrounded by the retaining wall, the beam is cut between the opposed retaining walls. To support the retaining wall with this cutting beam.

〔発明が解決しようとする課題〕[Problems to be solved by the invention]

しかしながら、周辺地盤が前記軟弱な場合には、地下
構造物の構築領域内に、山留め壁を支持するための切梁
が掛け渡されているために、これが邪魔になって地下構
造物の構築作業性がよくないという問題点があった。
However, in the case where the surrounding ground is soft, since a cutting beam for supporting the retaining wall is hung in the construction area of the underground structure, this is a hindrance to the construction work of the underground structure. There was a problem that it was not good.

そこでこの発明は、地下構造物を構築領域の周辺の地
盤が軟弱な場合にも、アンカーによって山留め壁を支持
することを目的としてなされたものである。
Therefore, the present invention has been made to support the retaining wall with an anchor even when the ground around the construction area for the underground structure is soft.

〔課題を解決するための手段〕[Means for solving the problem]

この発明の軟弱地盤の山留め工法は、軟弱地盤中に、
当該地盤を固化処理して定着域を形成し、前記軟弱地盤
に山留め壁を配し、前記山留め壁を支持するアンカーを
前記定着域に定着させるものである。
The method of retaining the soft ground according to the present invention includes:
A fixing area is formed by solidifying the ground, a mountain retaining wall is disposed on the soft ground, and an anchor supporting the mountain retaining wall is anchored in the fixing area.

前記定着域の形成は、拡幅できる翼とこの翼の周辺に
固化剤の供給口とを持つ深層混合機により、前記翼を地
盤中で拡幅して回転するとともに固化剤を注入して現地
軟弱土と固化剤とを攪拌した後、前記攪拌域を固化させ
て行うことができる。また、従来の深層混合機,噴射攪
拌混合機を用いることも可能である。
The fixing zone is formed by widening and rotating the wings in the ground while injecting the solidifying agent by using a deep mixer having a wing that can be widened and a supply port of a solidifying agent around the wings, and injecting the solidifying agent into the soft soil. After the agitation with the solidifying agent, the agitation zone can be solidified. It is also possible to use a conventional deep-layer mixer or a jet-stirring mixer.

前記定着域は地盤の深さ方向に複数形成して各定着域
を個別にブロック状とすること及び深さ方向に連続形成
して壁状とすることが可能である。
The fixing area may be formed in a plurality in the depth direction of the ground, and each fixing area may be individually formed in a block shape, or may be formed continuously in the depth direction to form a wall shape.

〔作用〕[Action]

軟弱地盤の一部が固化処理されてアンカーの定着域が
形成されるために、このアンカーの定着力が増大し、ま
た、定着域前面に発生する受働土圧を利用することによ
り、アンカーを介しての山留め壁の支持力を充分にする
ことができ、切梁による山留め壁の支持を不要にし又は
切梁の数を減少することができる。
Since a part of the soft ground is solidified to form an anchoring area for the anchor, the anchoring force of the anchor increases, and the passive earth pressure generated in front of the anchoring area is used, so that the anchoring area can be increased. The supporting force of all the retaining walls can be made sufficient, and the supporting of the retaining walls by the cutting beams can be eliminated or the number of the cutting beams can be reduced.

定着域の形成を深層混合機等により行うと、地盤の固
化作業が簡単になり、またこの作業を地盤の深さ方向に
複数回行うことにより、前記定着域を地盤の深さ方向に
複数形成することができる。これによって、各定着域は
個別にブロック状になるから、周辺地盤を利用するに際
しては、前記定着域を破壊又は取り出すことが容易にな
る。
When the fixing area is formed by a deep mixer or the like, the work of solidifying the ground is simplified, and this work is performed a plurality of times in the depth direction of the ground to form a plurality of the fixing areas in the depth direction of the ground. can do. Thus, since each fixing area is individually formed in a block shape, it is easy to destroy or remove the fixing area when using the surrounding ground.

〔実施例〕〔Example〕

第1〜3図は実施例を示す図であり、まず第1,2図に
基づいて説明する。
1 to 3 are views showing an embodiment, and will be described first with reference to FIGS.

記号1で示したのが建物の地下階等の地下構造物を構
築するための構築領域であって地盤を掘削して形成され
たものであり、2がその周辺の軟弱地盤である。前記構
築領域1の掘削に先立って、先ず軟弱地盤2中に、この
地盤2の所定位置を固化処理して定着域3を形成する。
固化処理は、軟弱地盤2を形成する土砂にセメントミル
ク等の固化剤を混入し攪拌して固化させることにより行
い、この固化した部分が前記定着域3である。
Reference numeral 1 denotes a construction area for constructing an underground structure such as a basement floor of a building, which is formed by excavating the ground, and reference numeral 2 denotes a soft ground around the ground. Prior to the excavation of the construction area 1, first, a predetermined position of the ground 2 is solidified in the soft ground 2 to form a fixing area 3.
The solidification process is performed by mixing a solidifying agent such as cement milk into the earth and sand forming the soft ground 2 and stirring and solidifying the mixture. The solidified portion is the fixing area 3.

この状態で構築領域1を掘削して次第に掘り下げ、こ
の掘削に伴い軟弱地盤2の端面に山留め壁4を配置す
る。次いで山留め壁4から軟弱地盤2を経て定着域3に
至るアンカー孔5を形成し、このアンカー孔5に公知の
アンカー6を挿入して、アンカー6先端を定着域3に定
着させ、且つその基端を横バタ7等を用いて山留め壁4
に固定する。前記アンカー孔5の形成とアンカー6の挿
入とは慣用の手段により行うものとする。
In this state, the construction area 1 is excavated and gradually excavated, and the excavation places the retaining wall 4 on the end face of the soft ground 2. Next, an anchor hole 5 extending from the retaining wall 4 to the fixing area 3 through the soft ground 2 is formed, and a known anchor 6 is inserted into the anchor hole 5 so that the tip of the anchor 6 is fixed to the fixing area 3. Edge retaining wall 4 using horizontal flap 7 etc.
Fixed to The formation of the anchor holes 5 and the insertion of the anchors 6 are performed by conventional means.

前記山留め壁4の建て込み,アンカー孔5の形成,ア
ンカー6の挿入定着は、構築領域1の掘削の進行に伴っ
て順次下方へと繰り返し施工するが、軟弱地盤2の崩落
の危険がない範囲において、構築領域1を或る程度の深
度まで一気に掘削した後に、山留め壁4の建て込み,ア
ンカー孔5の形成,アンカー6の挿入定着を、複数段に
わたって一度に施工することも可能である。これらの手
順も慣用されている通りに行う。
The embedding of the retaining wall 4, the formation of the anchor hole 5, and the insertion and fixing of the anchor 6 are repeatedly performed sequentially downward as the excavation of the construction area 1 progresses, but in a range where there is no danger of the soft ground 2 collapsing. In the above, after excavating the construction area 1 to a certain depth at a stretch, it is also possible to construct the retaining wall 4, form the anchor hole 5, and insert and fix the anchor 6 at a time in a plurality of steps. These procedures are also performed as usual.

ところで、前記定着域3は、軟弱地盤2の深さ方向に
複数形成されて、各定着域3がブロック状にされてい
る。
Incidentally, a plurality of fixing areas 3 are formed in the depth direction of the soft ground 2, and each fixing area 3 is formed in a block shape.

かかる定着域3の形成方法を第3図に基づいて説明す
る。この定着域3の形成は深層混合機8を用いて行うも
のであり、この深層混合機8は、垂直なブーム9に沿っ
て昇降可能な回転軸10の下端に取付けられた拡幅できる
翼11と、この翼11の周辺に固化剤の図示しない供給口
と、同様に図示しないが軟弱地盤2の所定位置に液状に
するための注水口とを持つものであって、次の手順で施
工される。
A method for forming the fixing area 3 will be described with reference to FIG. The formation of the fixing zone 3 is performed by using a deep-layer mixer 8, which comprises a wide-width wing 11 attached to the lower end of a rotating shaft 10 that can move up and down along a vertical boom 9. It has a supply port (not shown) of the solidifying agent around the wing 11 and a water supply port (not shown) for making it liquid at a predetermined position on the soft ground 2, and is constructed in the following procedure. .

まず、第3図(a)に示すように、軟弱地盤2の所定
深度まで注水しながら削孔し、次に同図(b)に示され
るように拡幅装置を回転させながら軟弱地盤2中で翼11
を開く。さらに同図(c)に示すように、開翼終了後に
も注水を継続しながら拡幅削孔し、その後に、同図
(d)に示すように翼を回転させながらセメントミルク
等の固化剤を注入して、現位置の土砂と攪拌し、さらに
回転軸10とともに翼11を適宜昇降させて充分な攪拌を行
う。終わりに同図(e)に示すように翼を閉じて引き上
げる。
First, as shown in FIG. 3 (a), a hole is drilled while pouring water to a predetermined depth of the soft ground 2, and then, as shown in FIG. Wing 11
open. Further, as shown in FIG. 3 (c), widening and drilling are performed while continuing water injection even after the completion of the blade opening, and then a solidifying agent such as cement milk is added while rotating the blades as shown in FIG. 4 (d). Inject, mix with the earth and sand at the current position, and further raise and lower the blades 11 together with the rotating shaft 10 to perform sufficient stirring. At the end, the wing is closed and pulled up as shown in FIG.

前記第3図(a)〜(e)の工程は1つの定着域3を
形成するためのものであるが、前記の工程を軟弱地盤2
中の複数の深さにおいて繰り返し行うことにより、前記
第1,2図のような複数の定着域3を形成することができ
る。この場合は最下段の定着域3から施工し、順次その
上の定着域3を施工するとよい。
3 (a) to 3 (e) are for forming one fixing area 3, but the above-mentioned steps are performed on the soft ground 2
By repeatedly performing the fixing at a plurality of inner depths, a plurality of fixing areas 3 as shown in FIGS. 1 and 2 can be formed. In this case, it is preferable to perform the fixing from the lowermost fixing area 3 and to sequentially form the fixing area 3 thereabove.

このように、軟弱地盤2には定着域3が形成されて、
これにアンカー6が定着されるために、アンカー6の定
着力は、強度が充分な地盤に定着すると同様に大なもの
となる。このため、構築領域1の両側に対向して配置さ
れる山留め壁4間に、切梁を掛け渡してこれにより山留
め壁4を支持して土圧や水圧に対向させる必要がなくな
るし、仮にその必要があったとしても、その数は少なく
て足りる。したがって、構築領域1の空間を広く確保す
ることができるから、地下構造物の構築作業性がよい。
Thus, the fixing area 3 is formed on the soft ground 2,
Since the anchor 6 is fixed to this, the anchoring force of the anchor 6 becomes large similarly when the anchor 6 is fixed on the ground having sufficient strength. For this reason, it is not necessary to hang a cutting beam between the retaining walls 4 arranged on both sides of the construction area 1 so as to support the retaining walls 4 and to oppose the earth pressure or the water pressure. Even if needed, the number is small enough. Therefore, since the space of the construction area 1 can be widely secured, construction workability of the underground structure is good.

また、軟弱地盤2の状態が第1,2図に示した定着域3
では、アンカー6の定着のために強度が充分でないこと
が予想される場合には、上下に連続する定着域3の中央
連続部3aに補強材12を建込んでもよい。この補強材12と
しては、H形鋼等の鋼材が適当であり、特に定着域3が
固化する以前に建込むことが望ましい。この場合に、補
強材12の外周には剥離剤や滑り膜等を塗布しておくこと
により、構築領域1に地下構造物が完成した後にその撤
去が容易になる。この撤去の後に、定着域3を撤去又は
破砕する必要がある場合には、前記定着域3は複数がブ
ロック化されているために撤去が容易であり、また破砕
も容易である。このため、軟弱地盤2の再利用時に障害
が残らないという効果がある。
Also, the condition of the soft ground 2 is the fixing area 3 shown in FIGS.
In this case, when it is expected that the strength is not sufficient for anchoring the anchor 6, the reinforcing member 12 may be built in the central continuous portion 3a of the anchoring area 3 which is vertically continuous. As the reinforcing member 12, a steel material such as an H-section steel or the like is appropriate, and it is particularly preferable that the reinforcing member 12 be built before the fixing region 3 is solidified. In this case, by applying a release agent, a sliding film, or the like to the outer periphery of the reinforcing member 12, it is easy to remove the underground structure after the completion of the underground structure in the construction area 1. When it is necessary to remove or crush the fixing area 3 after the removal, the fixing area 3 is easy to remove and crush easily because a plurality of the fixing areas 3 are blocked. Therefore, there is an effect that no obstacle remains when the soft ground 2 is reused.

なお、前記実施例における山留め壁4は上下に渡って
一体に図示してあるが、複数の材料を多段状に積んで構
成するものが、構築領域1の掘削深度の増大とともに下
方に継ぎ足しできるから好適である。また前記実施例で
は横バタ7を使用したが、アンカー6を固定できるもの
であれば他の部材でもよいし、またこれらを使用せずア
ンカー6を山留め壁4に直接固定してもよい。
Although the retaining wall 4 in the above embodiment is shown integrally over the upper and lower sides, it is possible to add a plurality of materials in a multi-tiered configuration, because the material can be added downward as the excavation depth of the construction area 1 increases. It is suitable. Further, in the above-described embodiment, the horizontal butter 7 is used, but other members may be used as long as the anchor 6 can be fixed, or the anchor 6 may be directly fixed to the retaining wall 4 without using these members.

〔発明の効果〕〔The invention's effect〕

以上説明したように、この発明にあっては、軟弱地盤
の一部が固化処理されてアンカーの定着域が形成される
ために、このアンカーの定着力が増大するから、軟弱地
盤においてもアンカーを介しての山留め壁の支持力を充
分にすることができる。このため切梁による山留め壁の
支持を不要にし又は切梁の数を減少することができるか
ら、山留め壁の前面において掘削される地下構造物の構
築領域での空間が広くなり作業性が向上する。
As described above, according to the present invention, the anchoring force of the anchor increases because a part of the soft ground is solidified and the anchoring area of the anchor is formed. Thus, the supporting force of the retaining wall can be sufficient. For this reason, it is not necessary to support the retaining wall by the girder or the number of the girder can be reduced, so that the space in the construction area of the underground structure excavated at the front of the girder wall is widened and workability is improved. .

また、前記定着域の形成を深層混合機により行うと、
地盤の固化作業が簡単になって作業効率が高くなる。
Further, when the fixing area is formed by a deep mixer,
The work of solidifying the ground is simplified and the working efficiency is increased.

さらに前記定着域の形成を地盤の深さ方向に複数回行
うことにより、前記定着域を地盤の深さ方向に複数形成
することができる。これによって、各定着域は個別にブ
ロック状になるから、爾後に周辺地盤を利用するに際し
ては、前記定着域を破壊又は取り出すことが容易になる
という効果がある。
Further, by forming the fixing area a plurality of times in the depth direction of the ground, a plurality of the fixing areas can be formed in the depth direction of the ground. Thus, since each fixing area is individually formed in a block shape, when the surrounding ground is used later, there is an effect that the fixing area can be easily broken or taken out.

【図面の簡単な説明】[Brief description of the drawings]

第1図〜第3図は実施例を示すものであって、第1図は
軟弱地盤とこれに形成した定着域にアンカー孔を形成し
た状態の断面図、第2図はアンカーを定着させた状態の
断面図、第3図(a)〜(e)は夫々定着域の形成順序
を示す断面図である。 1……構築領域、2……軟弱地盤、3……定着域、4…
…山留め壁、5……アンカー孔、6……アンカー、8…
…深層混合機、9……ブーム、10……回転軸、11……翼
1 to 3 show an embodiment. FIG. 1 is a sectional view showing a state in which an anchor hole is formed in a soft ground and a fixing area formed in the soft ground, and FIG. 2 shows a state where an anchor is fixed. 3 (a) to 3 (e) are sectional views showing the order of forming the fixing areas. 1 ... construction area, 2 ... soft ground, 3 ... fixing area, 4 ...
... Mounting wall, 5 ... Anchor hole, 6 ... Anchor, 8 ...
… Deep mixer, 9… Boom, 10… Rotary axis, 11… Wings

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】軟弱地盤中に、当該地盤を固化処理して定
着域を形成するとともに、前記軟弱地盤に山留め壁を配
し、さらに前記山留め壁を支持するアンカーを前記定着
域に定着させることを特徴とする軟弱地盤の山留め工
法。
1. A method of solidifying a ground in a soft ground to form a fixing area, arranging a retaining wall on the soft ground, and fixing an anchor supporting the retaining wall to the fixing area. The method of retaining the soft ground characterized by the following characteristics.
【請求項2】拡幅できる翼とこの翼の周辺に固化剤の供
給口とを持つ深層混合機により、前記翼を地盤中で拡幅
して回転するとともに固化剤を注入して現地軟弱土と固
化剤とを攪拌した後、前記攪拌域を固化させて定着域を
形成することを特徴とする第1請求項記載の軟弱地盤の
山留め工法。
2. A deep mixing machine having a wing that can be widened and a supply port of a solidifying agent around the wing, the wing is widened and rotated in the ground, and a solidifying agent is injected to solidify the soft soil at the site. 2. The method of claim 1, wherein the stirring area is solidified to form a fixing area after the agent is stirred.
【請求項3】定着域を地盤の深さ方向に複数形成して各
定着域を壁状とすることを特徴とすることを特徴とする
第1又は第2請求項記載の軟弱地盤の山留め工法。
3. The method according to claim 1, wherein a plurality of fixing areas are formed in the depth direction of the ground, and each fixing area is formed in a wall shape. .
JP22368189A 1989-08-30 1989-08-30 Retaining method for soft ground Expired - Fee Related JP2749388B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP22368189A JP2749388B2 (en) 1989-08-30 1989-08-30 Retaining method for soft ground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP22368189A JP2749388B2 (en) 1989-08-30 1989-08-30 Retaining method for soft ground

Publications (2)

Publication Number Publication Date
JPH0387416A JPH0387416A (en) 1991-04-12
JP2749388B2 true JP2749388B2 (en) 1998-05-13

Family

ID=16801981

Family Applications (1)

Application Number Title Priority Date Filing Date
JP22368189A Expired - Fee Related JP2749388B2 (en) 1989-08-30 1989-08-30 Retaining method for soft ground

Country Status (1)

Country Link
JP (1) JP2749388B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04336117A (en) * 1991-05-10 1992-11-24 Ebine Gisuke Landslide protection stabilizing construction method
JP4745842B2 (en) * 2006-01-30 2011-08-10 株式会社ガスター Cloudy bubble / jet jet bubble jetting device and cloudy bubble / jet jet bubble jetting system using the cloudy bubble / jet jet bubble jetting device
JP6606909B2 (en) * 2015-08-04 2019-11-20 株式会社大林組 Deformation prevention structure of retaining wall and deformation prevention method of retaining wall

Also Published As

Publication number Publication date
JPH0387416A (en) 1991-04-12

Similar Documents

Publication Publication Date Title
JP2002155530A (en) Embedding method and tip metal fitting of existing pile
JP2003119775A (en) Construction of foundation pile
JP2749388B2 (en) Retaining method for soft ground
JPH0960028A (en) Method for increasing strength of existing steel pipe pile
JP2003147782A (en) Foundation structure for constructing new building on existing basement and its construction method
JPH0460022A (en) Sheathing method and sheathing pile therefor
JP4485006B2 (en) Construction method for underground structures
JP2832508B2 (en) Retaining wall structure and retaining method
JP2868651B2 (en) Earth retaining method above existing underground structure
JP3948655B2 (en) Construction method of retaining wall and underground structure
JPH03447B2 (en)
JPS59195925A (en) Construction of on-site concrete pile
JPH03257215A (en) Pile constructing method
JP7511926B1 (en) Earth retaining wall and earth retaining wall construction method
JP3101762B2 (en) Simple mountain retaining method
JPH04115024A (en) Sheathing method
JPS6018769B2 (en) Construction method of underground structure
JP3012896B2 (en) Reverse cutting method combined with advance cutting
JP3012895B2 (en) Simple underground construction method
JPS62178620A (en) Formation of improved angular ground
JPH06287951A (en) Setting method of box pile
JP2002371550A (en) Construction method of soil cement composite precast pile
JPS6272817A (en) Construction of retaining wall concurrently serving as sheathing
JP2742709B2 (en) How to build a ground reinforcement support in the ground
JP3146375B2 (en) Existing structure retention method

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees