JP2743961B2 - Concrete foundation method - Google Patents

Concrete foundation method

Info

Publication number
JP2743961B2
JP2743961B2 JP62197570A JP19757087A JP2743961B2 JP 2743961 B2 JP2743961 B2 JP 2743961B2 JP 62197570 A JP62197570 A JP 62197570A JP 19757087 A JP19757087 A JP 19757087A JP 2743961 B2 JP2743961 B2 JP 2743961B2
Authority
JP
Japan
Prior art keywords
concrete
foundation
formwork
stabilizer
ready
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP62197570A
Other languages
Japanese (ja)
Other versions
JPS6443622A (en
Inventor
努 本間
Original Assignee
努 本間
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 努 本間 filed Critical 努 本間
Priority to JP62197570A priority Critical patent/JP2743961B2/en
Publication of JPS6443622A publication Critical patent/JPS6443622A/en
Application granted granted Critical
Publication of JP2743961B2 publication Critical patent/JP2743961B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Description

【発明の詳細な説明】 産業上の利用分野 この発明は、コンクリート製基礎を構築する方法に関
するものである。 従来技術とその欠点 従来、コンクリート製基礎を構築するには、設置位置
の地均しを行った後、コンクリートで安定板を打設し、
その養生後、木板製又は金属板製の型枠を組み立て、そ
の型枠内に鉄筋などを組み入れて、コンクリートを型枠
内に投入して基礎を形成し、その養生固化後に型枠の取
外しを行い、安定板の埋め戻しをしていた。 上記のように、従来方法は、順序性が濃い工程数が多
く、安定板製造時と基礎本体製造時の二度においてコン
クリート養生期間を必要とするので工期が非常に長くな
り、また、少なくとも、最初の地均しから安定板打設ま
での工程と、型枠組み立てからコンクリート投入までの
工程と、型枠取外し及び埋め戻しの工程とにおいて、現
場と資材倉庫などとの間を往復する必要があるので、運
賃及び工賃が非常に嵩む欠点があった。 とくに、山岳地帯など、地理的気候的条件の厳しい場
所に建造物の基礎を構築する場合は、可及的短期間の施
工が要請され、資材運搬の簡便化、現場作業の簡略化、
軽減化が要望されているが、上記従来方法ではこれらの
要望に応えることはできない。 上記に鑑み、工期の短縮を図った基礎工法が、幾つか
提案された。その一つは、特開昭48−58609号公報に記
載されたものである。この公報は、L型の隅角ブロッ
クと、その隅角ブロックの端部同志を結合するための板
状ブロックと、中空の角柱ブロックとを工場で形成して
おき、設置現場の根切り底に割栗地業又は砂利地業を
した後、その上に、前記隅角ブロック及び板状ブロッ
クを型状に組立て、必要に応じて配筋して、その中に生
コンクリートを流し込んで基盤部を形成し、次いで、
基盤部の上に前記角柱ブロックを載せ、その角柱ブロッ
クの中空部の中に再び生コンクリートを流し込んで、固
化により台部を形成すると同時に、基盤部と台部とを一
体に有する独立基礎を形成するものである。 もう一つは、特開昭61−126222号公報に記載されたも
のである。この工法は、基礎設置位置に捨てコンクリ
ートを打設し、その硬化時の接着力により固定され
た、又は硬化後に単に載置された下部支持部材により型
枠用板を離間して立設するとともに、上部支持部材によ
り型枠用板を固定して、型枠を形成した後、上部支持
部材にはアンカーボルトを挿入固定し、その後に、型
枠内側に生コンクリートを打ち込み、養生固化させて、
基礎を構築するものである。 さらに、もう一つは、実願昭54−83056号のマイクロ
フィルムに開示されたものであり、捨てコンクリート
を形成、硬化後、その捨てコンクリートの上に、金属
板を溶接して形成されたタイプレート(結合板)を基礎
延長方向に離間配設して、ねじなどで固定するととも
に、必要に応じて配筋した後、前記タイプレートの両
側に型枠であるパネル材の下端部を嵌合するとともに、
そのパネル材の上端部にセパレータを取付けてパネル材
を固定し、パネル材の間に生コンクリートを充填し、
硬化させて、基礎を構築するものである。 上記いずれの従来方法も、安定板又は基盤形成のため
の捨てコンクリート打設作業及びそのコンクリートの養
生固化の工程と、固化した安定板上への型枠立設固定後
の生コンクリート打込み作業及び養生固化の工程とから
なる点において、共通している。従って、基礎施工期間
は、少なくとも、地業開始時点から安定板形成のための
捨てコンクリート打設作業の終了時点までの期間、捨て
コンクリートの養生固化に要する期間、及びその後の型
枠間への生コンクリート打込み作業を終了するまでの所
要期間を積算した期間となるので、工期短縮効果は、上
記の要望の背景を考慮した場合は、未だ満足できる程度
に到達していなかった。 解決しようとする技術課題 この発明は、上記の事情を背景になされたものであ
り、その目的は、既製の鉄筋コンクリート型枠を基礎設
置位置に立設固定し、その型枠内に生コンクリートを打
込んで、その型枠と基礎とを一体に接合して、型枠自体
を基礎の一部とする施工方法において、一層の工期短縮
効果が得られる基礎工法を提供することにある。 課題解決手段 上記の目的を達成するため、本発明は、基礎設置位置
に、安定板形成用鉄筋と、その鉄筋を囲む安定板形成用
型枠を設置するとともに、前記安定板形成用型枠の内側
に、型枠載置部と、その型枠載置部から下方に延びる脚
部とを有して、上下方向及び側方に連通する型枠位置決
め枠を、方向とレベルを取って設置し、前記型枠位置決
め枠に筒状の既製鉄筋コンクリート型枠を載置し、前記
既製鉄筋コンクリート型枠内に鉄筋を配設した後、前記
安定板形成用型枠内及び前記既製鉄筋コンクリート型枠
内に生コンクリートを投入して安定板を打設するととも
に、その生コンクリートの養生固化により前記安定板と
前記既製鉄筋コンクリート型枠と基礎とを一体に接合す
ることを特徴としている。 この発明の実施例 次に、この発明の実施例を工程順に沿って、図面に基
いて説明する。 [第一工程](型枠製作) この発明による方法では、まず、予め工場において、
鉄筋コンクリート型枠Aを製作しておく。この型枠Aの
製作方法は従来方法と同様であり、第1図に示すよう
に、内外の金属板又は木板製の型枠1,2を用いて、その
型枠1,2の間に形成される空間に格子状に接合した補強
用鉄筋3を型枠間空間内の中央に位置するようにセット
したのち、型枠間空間内にコンクリートを流入充填させ
て養生し、固化後に型枠1,2を取外して、第3図に示す
ようなコンクリート型枠Aを製造する。 型枠Aは基礎の外見に対する要望により、あるいは、
基礎の上に設けられる建造物の形状により、多角筒状又
は円筒状に成形される。鉄筋3のコーナー部付近又は円
筒形の型枠の場合は、円筒中心に関して対称位置に、上
方に延びる吊り輪4を予め接合しておき、コンクリート
型枠製作後にその吊り輪4を型枠Aから突出させること
により、製作したコンクリート型枠Aを貯蔵位置に移動
する際に、又は後述するように基礎構築現場へ搬送する
際及び現場での所定位置に設置する際に、型枠Aを容易
に吊り上げ得るようにしてある。 また、コンクリート型枠Aには、第2図に示すよう
に、その内壁面から突出し、上記鉄筋3の一部である横
筋が埋設されたリブ5が、型枠の高さ方向に適宜の間隔
をもって設けられている。このリブ5は、後述されるよ
うに、第一には、型枠A自体の壁面に対して直角な方向
の力に対する強度を補強して、この型枠内に流入される
コンクリートに対する耐圧力を確保すること、第二に、
この型枠内に設けられる基礎の鉄筋及びアンカーなどの
被り厚さ(型枠内に投入されるコンクリートが鉄筋など
を覆う厚さ)を決定すること、の二つの機能を果たすた
めに設けられる。 [第二工程](型枠搬送・現場設置) コンクリート基礎を構築するときは、上記コンクリー
ト型枠Aを搬送装置により基礎建設現場まで搬送して、
所定位置に設置する。 コンクリート型枠Aは上記のように吊り輪4を有する
ので、第3図に示すように、各吊り輪4にワイヤロープ
6などの先端に固着したフック7を引っ掛け、そのロー
プを固定クレーン、車上クレーン、ヘリコプターなどで
上げ下ろしして、型枠Aを容易にトラックその他の搬送
装置に積み卸しして現場まで移送することができる。ま
た、現場でも簡単に所定位置に設置することができる。 基礎建設現場の所定位置に基礎を設置するには、第4
図に示すように、設置位置に慣用技術により、地業を形
成し、その上面に、型枠位置決め枠8を正確な方向とレ
ベルを取って立設し、固定する。型枠位置決め枠8は、
前記型枠Aの下端面と合致し、これを載置するための載
置部と、その載置部から下方に延びる脚部とを有し、上
下方向と脚部の間において側方に連通しており、骨組み
状に軽量に製作されているので、方向とレベル設定が容
易かつ正確に行うことができる。その型枠位置決め枠に
コンクリート型枠Aを載せる。従って、型枠Aの方向と
レベルも正確に設定される。そして、型枠位置決め枠8
の周囲に安定板用鉄筋9及び安定板形成用型枠10を配設
することとなる。 [第三工程](配筋・アンカー設置) 上記のようにして型枠Aの設置を終了した後は、第4
図及び第5図に示すように、この型枠A内に基礎補強用
鉄筋11及び建造物固定用アンカーボルト12を配設する。
コンクリート型枠Aは成形後の変形率が少ないので、鉄
筋11と型枠Aの内面に突設してあるリブ5に当接するこ
とによりその被り厚さを容易に確保することができ、ま
た、型枠Aの上端面に横架したアンカー支持部材13を介
してアンカーボルト12の型枠Aの上端部内面からの距離
を設定して、所要位置において固定することにより、ア
ンカー設置位置を容易にかつ、正確に決めることができ
る。 上記のように、型枠位置決め枠8は、正確に方向とレ
ベルが取られているので、型枠Aの上端面も正確な水平
面となっているから、アンカー支持部材13はどの位置に
横架しても正確なレベルが保証され、従って、アンカー
ボルト12を容易に垂直に設けることができる。吊り輪4
はアンカー支持部材の位置決めにも利用することができ
る。 [第四工程](コンクリート投入・養生) 上記のようにして、型枠A内への鉄筋11及びアンカー
ボルト12の設置を終了したならば、次に、生コンクリー
トを型枠Aの周囲の安定板形成用型枠10内に投入して安
定板14を打設して、その表面を均し、続いて、型枠A内
にコンクリートを投入してその底部から安定板形成用空
間に流下充填し、これに続いて投入される生コンクリー
トを型枠A内に充填する。この場合、型枠Aの内壁面
に、流動するコンクリートの圧力が加わるが、型枠Aは
上記リブ5を有してコンクリート壁の弱点を排除され、
十分な耐圧力性を備えているので、型枠Aの壁部分の厚
みを比較的薄くしても強度的には問題がない。上記のよ
うなスペーサを兼ねるリブ5を設けて強度を高めた場合
は、必要な耐圧力を確保し、しかも、型枠Aの壁を薄く
して型枠Aの総重量を軽くして、搬送負荷の軽減を図る
ことが可能である。 型枠A内に投入したコンクリートが固化すれば、アン
カー支持部材13を除去することにより、第6図に示すよ
うに、所望の基礎Bが完成する。必要ならば養生固化後
に安定板形成用型枠10を取外したのち、基礎の周囲を埋
め戻して安定板14を土砂で覆う。安定板形成用型枠を取
外す必要がない場合あるいはその時間的余裕がない場合
は、型枠Aへの生コンクリート投入を終了した時点で、
原則として基礎建設の施工は完了である。 第6図は安定板14を同時に形成した基礎Bの完成状態
を示す斜視図であり、基礎の外周には型枠Aが一体に接
合され、基礎の上面にはアンカーボルト12が突出してい
る。従って、この基礎の上に、第7図に例示するよう
に、アンカーボルトとナットを用いて建造物Cを固定す
ることができる。 吊り輪4は、基礎完成後も、建造物のボルトナットに
よる締結終了時まで、建造物を直立状態に保つワイヤー
などを通すために利用することもできる。 第8図は、型枠Aの上記吊り輪4を型枠Aの角部至近
において内壁面に沿って上方に突出させることにより、
背の高い基礎柱を建設する必要がある場合、複数の型枠
A1,A2を積み重ねたときに、その吊り輪により上下の型
枠A1,A2の相対移動を阻止して、安定した状態でこの型
枠内に生コンクリートを投入することができる利点があ
る。 この発明の効果 上述のように、この発明によれば、安定板形成用型枠
内と既製鉄筋コンクリート型枠内に生コンクリートを投
入するだけで、安定板打設と基礎本体打設とを一挙に行
うことができるため、安定板打設と基礎本体打設とを工
期的に2回に分けて行っていた従来と異なり、現場作業
が著しく省略され、工期は従来の三分の一と、大幅に短
縮される。 従って、至急に建設することが要請される防災設備な
どの基礎構築や、山岳地帯など建設が季節的に制限され
る建造物の基礎構築に適切有効な工法であり、災害の拡
大防止にも効果を発揮し、厳しい気象条件などの影響を
受けないことができる。 また、上下方向及び側方に連通している型枠位置決め
枠を用いるので、安定板と基礎本体とが一体に接合され
易く、全体として非常に堅固な基礎を構築することがで
きる。
Description: TECHNICAL FIELD The present invention relates to a method for constructing a concrete foundation. Conventional technology and its disadvantages Conventionally, in order to construct a concrete foundation, after leveling the installation position, a stabilizer is cast with concrete,
After curing, assemble a wooden or metal plate formwork, incorporate rebar etc. into the formwork, put concrete in the formwork, form a foundation, remove the formwork after curing and solidification. It was backfilling the stabilizer. As described above, in the conventional method, the number of steps having a high order is large, and the concrete curing period is required twice during the production of the stable plate and the production of the base body, so the construction period becomes extremely long, and at least, It is necessary to go back and forth between the site and the material warehouse etc. in the process from the initial leveling to the installation of the stabilizer, the process from the formwork assembly to the concrete input, and the process of removing and backfilling the formwork. There was a disadvantage that the fare and labor cost were very high. In particular, when constructing the foundation of a building in a location with severe geographical and climatic conditions, such as a mountainous area, construction is required in as short a time as possible, simplifying material transportation, simplifying site work,
Although there is a demand for reduction, these conventional methods cannot meet these demands. In view of the above, several basic construction methods have been proposed to shorten the construction period. One of them is described in JP-A-48-58609. This publication discloses that an L-shaped corner block, a plate-like block for connecting the ends of the corner block, and a hollow prism block are formed in a factory, and formed at the root of the installation site. After doing the splittering or gravel work, assemble the corner block and plate-like block into a shape on top of it, arrange them as necessary, pour ready-mixed concrete into it, Forming, then
Place the prism block on the base part, pour ready-mixed concrete again into the hollow part of the prism block, form the base part by solidification, and at the same time, form an independent foundation integrally with the base part and the base part Is what you do. The other is described in JP-A-61-126222. In this method, concrete is thrown away at the foundation installation position, and the mold plate is separated and erected by the lower support member fixed by the adhesive force at the time of curing or simply placed after curing. After fixing the form plate by the upper support member and forming the form, the anchor bolt is inserted and fixed to the upper support member, and then, the ready-mixed concrete is driven into the inside of the form and cured,
It builds the foundation. The other is disclosed in the microfilm of Japanese Utility Model Application No. 54-83056, in which a discarded concrete is formed, hardened, and then a metal plate is formed on the discarded concrete by welding. A plate (coupling plate) is spaced apart in the direction of extension of the foundation, fixed with screws, etc., and after arranging as necessary, the lower ends of the panel material as a formwork are fitted on both sides of the tie plate. Along with
Attach a separator to the upper end of the panel material and fix the panel material, fill the fresh concrete between the panel materials,
It cures and builds the foundation. In any of the above-mentioned conventional methods, the steps of placing discarded concrete for forming a stabilizer or a base and curing and solidifying the concrete, and placing and curing the fresh concrete after erecting and fixing the formwork on the solidified stabilizer are performed. It is common in that it comprises a solidification process. Therefore, the foundation work period should be at least the period from the start of the ground work to the end of the work to cast the discarded concrete for the formation of stabilizers, the period required for the curing and solidification of the discarded concrete, and the subsequent production between the forms. Since this is a period obtained by integrating the required period until the concrete pouring work is completed, the effect of shortening the construction period has not yet reached a satisfactory level in view of the background of the above-mentioned demands. SUMMARY OF THE INVENTION The present invention has been made in view of the above circumstances, and has as its object to erect and fix a ready-made reinforced concrete formwork at a foundation installation position and cast ready-mixed concrete into the formwork. In addition, it is an object of the present invention to provide a foundation method in which the formwork and the foundation are integrally joined and the formwork itself is used as a part of the foundation, whereby a further effect of shortening the construction period can be obtained. Means for Solving the Problems In order to achieve the above object, the present invention provides, at a foundation installation position, a stabilizing plate forming reinforcing bar, and a stabilizing plate forming form surrounding the reinforcing bar. On the inner side, a formwork positioning frame having a formwork mounting portion and legs extending downward from the formwork mounting portion, and communicating vertically and sideways, is installed taking the direction and level. After placing a tubular ready-made reinforced concrete formwork on the formwork positioning frame and arranging the reinforcing steel in the ready-made reinforced concrete formwork, the rebar is formed in the stabilizer plate forming form and the ready-made reinforced concrete formwork. The method is characterized in that concrete is put in, a stabilizer is poured, and the stabilizer, the ready-made reinforced concrete formwork and the foundation are integrally joined by curing and solidifying the raw concrete. Next, an embodiment of the present invention will be described with reference to the drawings in the order of steps. [First Step] (Form Forming) In the method according to the present invention, first, in a factory,
A reinforced concrete form A is manufactured in advance. The method of manufacturing the mold A is the same as the conventional method. As shown in FIG. 1, the mold A is formed between the molds 1 and 2 using metal molds 1 and 2 made of inner and outer metal plates or wooden boards. After the reinforcing reinforcing bar 3 joined in a lattice shape to the space to be formed is set so as to be located at the center of the space between the formwork, concrete is poured into the space between the formwork and cured, and after solidification, the form 1 , 2 are removed to produce a concrete form A as shown in FIG. Formwork A is based on the demand for the appearance of the foundation, or
Depending on the shape of the building provided on the foundation, it is formed into a polygonal cylindrical or cylindrical shape. In the case of the corner of the reinforcing bar 3 or in the case of a cylindrical form, an upwardly extending suspension ring 4 is previously joined at a symmetric position with respect to the center of the cylinder, and after the concrete form is manufactured, the suspension ring 4 is removed from the form A. By projecting, when moving the produced concrete form A to the storage position, or when transporting it to the foundation construction site and setting it at a predetermined position on the site as described later, the form A It can be lifted. As shown in FIG. 2, the concrete form A is provided with ribs 5 protruding from the inner wall surface and having embedded therein horizontal bars which are a part of the reinforcing bars 3 at appropriate intervals in the height direction of the form. It is provided with. As will be described later, the rib 5 firstly reinforces the strength against a force in a direction perpendicular to the wall surface of the form A itself, and increases the pressure resistance to the concrete flowing into the form. Second, to secure
It is provided to fulfill the two functions of determining the covering thickness of the reinforcing bars and anchors of the foundation provided in the formwork (thickness in which the concrete put into the form covers the reinforcing bars). [Second step] (Form transport / site installation) When constructing a concrete foundation, the above concrete form A is transported to the foundation construction site by a transport device.
Install in place. Since the concrete form A has the suspension rings 4 as described above, as shown in FIG. 3, hooks 7 fixed to the tip of a wire rope 6 or the like are hooked on each suspension ring 4, and the ropes are fixed to a fixed crane or a vehicle. The form A can be easily unloaded on a truck or other transport device and transferred to the site by being lifted and lowered by an upper crane, helicopter or the like. In addition, it can be easily installed at a predetermined position even on site. To install a foundation at a given location on a foundation construction site, a fourth
As shown in the figure, a ground operation is formed at the installation position by a conventional technique, and a formwork positioning frame 8 is erected and fixed on the upper surface thereof in an accurate direction and level. Formwork positioning frame 8
It has a mounting portion that matches with the lower end surface of the formwork A, and a mounting portion for mounting the mounting portion, and a leg portion extending downward from the mounting portion, and communicates laterally between the vertical direction and the leg portion. Since it is made lightweight in a frame shape, the direction and level can be set easily and accurately. The concrete formwork A is placed on the formwork positioning frame. Therefore, the direction and level of the mold A are also set accurately. And the formwork positioning frame 8
Is provided around the stabilizing plate reinforcing bar 9 and the stabilizing plate forming formwork 10. [Third Step] (Reinforcement / Anchor Installation) After the installation of the formwork A is completed as described above, the fourth step is performed.
As shown in FIG. 5 and FIG. 5, a reinforcing steel bar 11 for foundation and an anchor bolt 12 for fixing a building are arranged in the formwork A.
Since the concrete form A has a low deformation rate after molding, the covering thickness can be easily secured by contacting the reinforcing bar 11 with the rib 5 protruding from the inner surface of the form A. By setting the distance between the anchor bolt 12 and the inner surface of the upper end of the form A via the anchor support member 13 laid on the upper end of the form A, and fixing the anchor bolt 12 at a required position, the anchor installation position can be easily adjusted. And it can be determined accurately. As described above, since the form positioning frame 8 is accurately oriented and leveled, the upper end surface of the form A is also an accurate horizontal plane. However, an accurate level is assured, so that the anchor bolt 12 can be easily provided vertically. Hanging ring 4
Can also be used for positioning the anchor support member. [Fourth Step] (Concrete Injection and Curing) After the installation of the reinforcing bars 11 and the anchor bolts 12 in the form A is completed as described above, the ready-mixed concrete is then stabilized around the form A. It is poured into the plate forming mold 10 and the stabilizer 14 is cast therein, and its surface is leveled. Then, concrete is charged into the mold A and the bottom is filled into the stabilizer forming space from the bottom. Then, the ready-mixed concrete to be charged subsequently is filled into the formwork A. In this case, the pressure of the flowing concrete is applied to the inner wall surface of the form A, but the form A has the ribs 5 to eliminate the weak points of the concrete wall,
Since it has sufficient pressure resistance, there is no problem in strength even if the wall portion of the formwork A is relatively thin. When the strength is increased by providing the ribs 5 also serving as spacers as described above, the necessary pressure resistance is ensured, and the wall of the mold A is made thinner to reduce the total weight of the mold A, and the transport is performed. It is possible to reduce the load. When the concrete put into the formwork A solidifies, the desired foundation B is completed by removing the anchor support members 13 as shown in FIG. If necessary, after the curing and solidification, the mold 10 for forming the stabilizer is removed, and then the periphery of the foundation is backfilled and the stabilizer 14 is covered with earth and sand. If it is not necessary to remove the stabilizer-forming form or if there is not enough time, at the time when the ready-mixed concrete has been put into the form A,
In principle, the construction of the foundation is completed. FIG. 6 is a perspective view showing a completed state of the foundation B on which the stabilizer 14 is formed at the same time. The form A is integrally joined to the outer periphery of the foundation, and the anchor bolts 12 protrude from the upper surface of the foundation. Therefore, the building C can be fixed on this foundation by using anchor bolts and nuts as illustrated in FIG. The suspension ring 4 can also be used to pass a wire or the like that keeps the building in an upright state after the foundation is completed until the fastening of the building with the bolt and nut is completed. FIG. 8 shows that the suspension ring 4 of the form A is projected upward along the inner wall surface near the corner of the form A,
If you need to build tall foundation columns, use multiple formwork
When A 1 and A 2 are stacked, the suspension ring prevents the upper and lower forms A 1 and A 2 from moving relative to each other, so that ready-mixed concrete can be put into this form in a stable state. There is. Advantageous Effects of the Invention As described above, according to the present invention, the casting of the stabilizer and the casting of the base body can be performed at once by simply putting ready-mixed concrete into the mold for forming the stabilizer and the ready-made reinforced concrete form. Since the work can be performed, the work on the stable plate and the work on the foundation body are divided into two works in the construction period. Is shortened to Therefore, it is an effective and effective method for building foundations such as disaster prevention facilities that require urgent construction, and for buildings where construction is restricted seasonally, such as mountainous areas, and is also effective in preventing the spread of disasters. And can be unaffected by severe weather conditions. In addition, since the mold positioning frame communicating with the vertical direction and the side is used, the stabilizer and the base body are easily joined together integrally, so that a very solid foundation can be constructed as a whole.

【図面の簡単な説明】 図面は、この発明の実施例を説明するものであり、第1
図は鉄筋コンクリート型枠を製造する工程の一例を示す
斜視図、第2図はコンクリート型枠の一部の縦断面図、
第3図は完成したコンクリート型枠を移動する状態を示
す斜視図、第4図はコンクリート型枠を現場に設置する
様子を示す斜視図、第5図はコンクリート型枠を利用し
て基礎中に埋設する鉄筋及びアンカーの取付けをする状
態を示す斜視図、第6図は完成した基礎の斜視図、第7
図は基礎に建造物を取付けた例を示す要部斜視図、第8
図は複数の型枠を縦に連結する場合の例を示す一部正面
断面図である。 ……鉄筋、 4……吊り輪、 A……鉄筋コンクリート型枠、 5……リブ 8……型枠位置決め枠、 9……安定板形成用鉄筋、 10……安定板形成用型枠、 11……鉄筋、 12……アンカーボルトなど、 13……アンカー支持部材、 14……安定板。
BRIEF DESCRIPTION OF THE DRAWINGS The drawings explain embodiments of the present invention.
The figure is a perspective view showing an example of a process for manufacturing a reinforced concrete form, FIG. 2 is a longitudinal sectional view of a part of the concrete form,
FIG. 3 is a perspective view showing a state in which the completed concrete form is moved, FIG. 4 is a perspective view showing a state where the concrete form is installed on the site, and FIG. FIG. 6 is a perspective view showing a state in which a reinforcing bar and an anchor to be buried are attached, FIG. 6 is a perspective view of a completed foundation, and FIG.
The figure is a perspective view of an essential part showing an example in which a building is attached to a foundation, and FIG.
The figure is a partial front sectional view showing an example in which a plurality of molds are vertically connected. 3 ... reinforcing bar, 4 ... hanging ring, A ... reinforced concrete formwork, 5 ... rib 8 ... formwork positioning frame, 9 ... rebar for forming stable plate, 10 ... formwork for forming stable plate, 11 …… Reinforcing bar, 12 …… Anchor bolt, etc. 13 …… Anchor support member, 14 …… Stabilizer.

フロントページの続き (56)参考文献 特開 昭48−58609(JP,A) 特開 昭61−126222(JP,A) 特開 昭54−137809(JP,A) 実願 昭54−83056号(実開 昭56− 865号)の願書に添付した明細書及び図 面の内容を撮影したマイクロフィルム (JP,U)Continuation of front page    (56) References JP-A-48-58609 (JP, A)                 JP-A-61-126222 (JP, A)                 JP-A-54-137809 (JP, A)                 Japanese Utility Model Application No. 54-83056 (Japanese Utility Model Application Showa 56-               No. 865) and the specification attached to the application               Microfilm of the contents of the surface               (JP, U)

Claims (1)

(57)【特許請求の範囲】 1.(イ)基礎設置位置に、安定板形成用鉄筋と、その
鉄筋を囲む安定板形成用型枠を設置するとともに、前記
安定板形成用型枠の内側に、型枠載置部と、その型枠載
置部から下方に延びる脚部とを有して、上下方向及び側
方に連通する型枠位置決め枠を、方向とレベルを取って
設置し、 (ロ)前記型枠位置決め枠に、筒状の既製鉄筋コンクリ
ート型枠を載置し、 (ハ)前記既製鉄筋コンクリート型枠内に鉄筋を配設し
た後、 (ニ)前記安定板形成用型枠内及び前記既製鉄筋コンク
リート型枠内に生コンクリートを投入して安定板を打設
するとともに、その生コンクリートを養生固化させて、
前記安定板と前記既製鉄筋コンクリート型枠と基礎とを
一体に接合すること、 を特徴とするコンクリート基礎工法。
(57) [Claims] (B) A reinforcing plate forming reinforcing bar and a stabilizer forming frame surrounding the reinforcing bar are installed at the foundation setting position, and a form placing portion and a mold are provided inside the stabilizer forming form. A frame positioning frame having legs extending downward from the frame mounting portion and communicating vertically and laterally is installed in a direction and at a level, and (b) a cylinder is mounted on the frame positioning frame. (C) After arranging a reinforcing bar in the ready-made reinforced concrete form, (d) ready-mixed concrete in the stabilizer-forming form and the ready-made reinforced concrete form. Injecting and setting a stabilizer, curing the ready-mixed concrete,
A concrete foundation method, wherein the stabilizer, the ready-made reinforced concrete formwork and the foundation are integrally joined.
JP62197570A 1987-08-07 1987-08-07 Concrete foundation method Expired - Fee Related JP2743961B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62197570A JP2743961B2 (en) 1987-08-07 1987-08-07 Concrete foundation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62197570A JP2743961B2 (en) 1987-08-07 1987-08-07 Concrete foundation method

Publications (2)

Publication Number Publication Date
JPS6443622A JPS6443622A (en) 1989-02-15
JP2743961B2 true JP2743961B2 (en) 1998-04-28

Family

ID=16376699

Family Applications (1)

Application Number Title Priority Date Filing Date
JP62197570A Expired - Fee Related JP2743961B2 (en) 1987-08-07 1987-08-07 Concrete foundation method

Country Status (1)

Country Link
JP (1) JP2743961B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62156949A (en) * 1985-12-28 1987-07-11 電気化学工業株式会社 Heat-resistant composite polypropylene sheet
JP6871723B2 (en) * 2016-11-18 2021-05-12 鹿島建設株式会社 How to build precast formwork and foundation structure

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4858609A (en) * 1971-11-20 1973-08-17

Also Published As

Publication number Publication date
JPS6443622A (en) 1989-02-15

Similar Documents

Publication Publication Date Title
JP2002256573A (en) Foundation for existing foundation reinforcing steel tower and construction method for it
WO1984004768A1 (en) Prestressed component retaining wall system
US5224313A (en) Apparatus for constructing isolation pockets
RU2082853C1 (en) Method of construction of foundation
CN108487290B (en) Cast-in-place and prefabricated combined portable communication tower floor foundation and construction method
US20170241088A1 (en) Fully adjustable suspended post and panel modules and installation methods
US20070212172A1 (en) Telescoping pier foundation
JP2743961B2 (en) Concrete foundation method
JP3519378B2 (en) Retaining wall structure and members for retaining wall construction in the observer passage in the tunnel
KR101036177B1 (en) Method for constructing building using PRC integrating method
JPH063881Y2 (en) Concrete formwork for concrete foundation construction
EP0151626B1 (en) Procedure for making foundations for a structure, and intermediate piece for use in the procedure
JP3191951B2 (en) Foundation construction method
JP3778392B2 (en) Basic block
JP2709346B2 (en) Block for legal framework
JP2981009B2 (en) Foundation structure
JP3110341B2 (en) Construction formwork and method of fabric foundation or fence for housing
JP3629684B2 (en) Sound insulation wall foundation block
JP2554382B2 (en) Dwelling
JP3242160B2 (en) Concrete formwork and its construction method
JP3002026B2 (en) Structure of residential continuous foundation
JPH01315525A (en) Snowslide preventing and slope stabilizing structure
JPH06306874A (en) Concrete block for footing
JP2723418B2 (en) Formwork for foundation construction
JPH06146307A (en) Construction method of construction structure

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees