JP2676205B2 - Construction method of water collecting pipe on underground wall - Google Patents

Construction method of water collecting pipe on underground wall

Info

Publication number
JP2676205B2
JP2676205B2 JP29345087A JP29345087A JP2676205B2 JP 2676205 B2 JP2676205 B2 JP 2676205B2 JP 29345087 A JP29345087 A JP 29345087A JP 29345087 A JP29345087 A JP 29345087A JP 2676205 B2 JP2676205 B2 JP 2676205B2
Authority
JP
Japan
Prior art keywords
water collecting
continuous wall
sleeve
underground continuous
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP29345087A
Other languages
Japanese (ja)
Other versions
JPH01137013A (en
Inventor
孝二 峯岸
徹 小松原
茂巳 若山
統一 児島
泰秀 桑原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyo Gas Co Ltd
Shimizu Corp
Original Assignee
Tokyo Gas Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Gas Co Ltd, Shimizu Corp filed Critical Tokyo Gas Co Ltd
Priority to JP29345087A priority Critical patent/JP2676205B2/en
Publication of JPH01137013A publication Critical patent/JPH01137013A/en
Application granted granted Critical
Publication of JP2676205B2 publication Critical patent/JP2676205B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 「産業上の利用分野」 この発明は、地中連続壁の内側に浸透してくる水を、
地中連続壁の外側に設けられた集水ピットに導くための
集水管の施工方法に関するものである。 「従来の技術」 地中連続壁(以下では単に連続壁という)を利用した
地下タンク等の地中構造物では、完成後の構造形式によ
っては、周辺地盤から連続壁の内側に浸透してくる水を
排出する必要が生じる。このため、従来一般には、第2
図に示すように連続壁1の外側に集水ピット2を設ける
とともに、その集水ピット2の下部と連続壁1の内側と
を連通する集水管3を連続壁1を貫通させて設けること
により、連続壁1内側に浸透してきた水を集水管3を通
して集水ピット2に導き、その集水ピット2内に設置し
た水中ポンプ4によって汲み上げて排水するようにして
いる。 上記の集水ピット2および集水管3を施工するにあた
っては、第3図あるいは第4図に示す方法によることが
従来一般的である。 第3図に示す方法は、集水ピット2を構成する大径長
尺の竪管5(一般には鋼管が用いられる)の下部に予め
集水管3を接続しておき、これらを(イ)に示すように
連続壁1を構成する鉄筋篭6に一体に組み込んで鉄筋篭
6とともに所定位置に建て込むものである。そして、鉄
筋篭6の周囲および竪管5の周囲にコンクリートを打設
し、連続壁1の施工が完了してその内側を掘削した後、
(ロ)に示すように連続壁1表面のコンクリートを斫っ
て集水管3を露出させるものである。 また、第4図に示す方法は、鉄筋篭6を建て込んだ後
に(イ)に示すように竪管5のみを所定位置に建て込
み、連続壁1の施工が完了してその内側を掘削した後
に、(ロ)に示すように集水管3を取り付けるべき位置
にコアボーリングを行って集水管3より大径の連通孔7
を形成し、続いて(ハ)に示すようにその連通孔7内に
集水管3を配設するとともに、連通孔7と集水管3との
間の隙間にモルタル等のグラウト8を充填するものであ
る。 「発明が解決しようとする問題点」 しかしながら、第3図に示す方法では、竪管5および
集水管3を鉄筋篭6に組み込むことから、連続壁1の壁
厚が大きい場合や鉄筋篭6が長い場合には鉄筋篭6の重
量が過大となり、したがって鉄筋篭6の建て込み作業の
ために超大型のクレーンが必要となったり、また、現有
のクレーンでは吊り下げ不可能であるなどの問題があっ
た。 また、第4図に示す方法では、特に連続壁1の壁厚が
大きい場合やその配筋が複雑な場合あるいは集水管3の
径が大きい場合には、コアボーリングに長時間を要して
作業性が良くないばかりでなく、連続壁の鉄筋を切断し
たり、コアボーリング位置がズレて竪管との接合がうま
くいかなかったりの問題があった。 この発明は上記の事情に鑑みてなされたもので、施工
性に優れた集水管の施工方法を提供することを目的とし
ている。 「問題点を解決するための手段」 この発明は、地中連続壁を貫通して取り付けられて、
竪管の周囲にコンクリートが打設されることによって前
記地中連続壁と一体となってその外側に設けられた集水
ピットと前記地中連続壁の内側とを連通する集水管の施
工方法において、前記地中連続壁の鉄筋篭の所定位置に
その地中連続壁の厚さと同等またはやや短いスリーブを
前記集水ピットを構成する竪管の下部に対向する位置に
配設しておくとともに、該スリーブの両端を閉塞してお
き、その鉄筋篭を建て込んでコンクリートを打設し、コ
ンクリートが硬化して地中連続壁の施工が完了したらそ
の地中連続壁の内側を掘削し、その後、前記地中連続壁
の内側から前記スリーブを通してそのスリーブと前記竪
管との間のコンクリートに対してコアボーリングを行う
ことによって連通孔を形成し、そのスリーブおよび連通
孔内に前記集水管を配設することを特徴としている。 「実施例」 以下、この発明の施工方法の一実施例を第1図を参照
して説明する。第1図(イ)〜(ハ)はこの実施例の施
工方法を工程順に示すものであるが、上述した従来の方
法の場合と同一部分については図面に同一符号を付して
説明は省略する。 この実施例の施工方法においては、まず、第4図に示
した従来の施工方法の場合と同様に、連続壁1内に埋設
される鉄筋篭6を建て込み、次いで、その外側に集水ピ
ット2を構成する竪管5を建て込むが、その鉄筋篭6に
は予めスリーブ(さや管)10を取り付けておく。そのス
リーブ10は、たとえば鋼管を用い、その径を集水管3よ
りやや大きくしておくとともにその長さを連続壁1の壁
厚よりやや短くしておき、内部にコンクリートが流れ込
まないようにその両端を閉塞しておく。そして、このス
リーブ10を、(イ)に示すように鉄筋篭6および竪管5
がそれぞれ建て込まれたときに竪管5の下端部に対向す
る位置に取り付けておく。 上記のスリーブ10を取り付けた鉄筋篭6、および竪管
5を(イ)に示すように建て込んだ後、コンクリートを
打設して鉄筋篭6および竪管5をコンクリート内に埋設
し、コンクリートが硬化して連続壁1、集水ピット2の
施工が完了したら、連続壁1の内側の地盤を掘削する。
そして、コンクリートの表層部を斫ってスリーブ10の先
端部を露出させ、そのスリーブ10内にコアボーリング機
の先端を挿入し、スリーブ10の後端と竪管5との間のコ
ンクリートに対してコアボーリングを行って、(ロ)に
示すようにスリーブ10よりやや小径かつ集水管3よりや
や大径の連通孔11を形成する。 続いて、(ハ)に示すように、スリーブ10および連通
孔11内に集水管3を配設するとともに、その集水管3の
外面とスリーブ10および連通孔11の内面との間の隙間に
グラウト12を充填し、そのグラウト12が硬化すれば施工
が完了する。 以上の方法によれば、鉄筋篭6にはスリーブ10を取り
付けるのみであって、竪管5と鉄筋篭6とを各別に建て
込むようにしたので、第3図に示した竪管5を鉄筋篭6
に組み込んで建て込む従来の方法のように、鉄筋篭6の
重量が過大になってその建て込みが困難になることがな
い。 また、コアボーリングはスリーブ10と竪管5との間の
わずかな距離に対して行うのみで済むから、第4図に示
した連続壁1の壁厚全体に対してコアボーリングを行う
従来の方法のように、コアボーリングに長時間を要する
ことなく、また容易に正確な連通孔11を形成することが
できる。 なお、スリーブ10の長さは連続壁1の壁厚と同等であ
っても良い。また、スリーブ10の先端がコンクリート表
面に露出するようにすれば、スリーブ10の斫り出しに際
してその位置が自ずと明らかになるし、斫り出しも容易
となる。 「発明の効果」 以上で詳細に説明したように、この発明の施工方法に
よれば、両端を閉塞したスリーブを予め鉄筋篭に取り付
けておき、このスリーブと竪管との間のコンクリートに
対してコアボーリングを行うようにしたから、鉄筋篭の
重量が過大になってその建て込みが困難になるようなこ
とがなく、また、コアボーリングに長時間を要すること
もなく、しかも容易に正確な連通孔を形成することがで
き、したがって施工性が極めて良いという効果を奏す
る。
[Detailed Description of the Invention] [Industrial field of application] The present invention is designed to remove water that permeates inside a continuous underground wall,
The present invention relates to a method of constructing a water collecting pipe for guiding to a water collecting pit provided outside the underground wall. “Prior art” Underground structures such as underground tanks that use underground continuous walls (hereinafter simply referred to as continuous walls) will penetrate from the surrounding ground to the inside of the continuous walls depending on the structural type after completion. It is necessary to drain the water. Therefore, in the past, in general, the second
As shown in the figure, the water collecting pit 2 is provided outside the continuous wall 1, and the water collecting pipe 3 that connects the lower part of the water collecting pit 2 and the inside of the continuous wall 1 is provided through the continuous wall 1. The water that has permeated into the inside of the continuous wall 1 is guided to the water collecting pit 2 through the water collecting pipe 3, and is pumped up by the submersible pump 4 installed in the water collecting pit 2 to be drained. When constructing the water collecting pit 2 and the water collecting pipe 3, the method generally shown in FIG. 3 or 4 is conventionally used. In the method shown in FIG. 3, the water collecting pipe 3 is preliminarily connected to the lower part of the large-diameter and long vertical pipe 5 (generally a steel pipe is used) which constitutes the water collecting pit 2, and these are connected to (a). As shown in the figure, it is integrally incorporated into a reinforcing bar cage 6 which constitutes the continuous wall 1 and is built in a predetermined position together with the reinforcing bar cage 6. Then, after placing concrete around the reinforcing bar cage 6 and around the vertical pipe 5 and completing the construction of the continuous wall 1 and excavating the inside,
As shown in (b), the concrete on the surface of the continuous wall 1 is removed to expose the water collecting pipe 3. Further, in the method shown in FIG. 4, after the rebar cage 6 has been installed, only the vertical pipe 5 is installed at a predetermined position as shown in (a), the construction of the continuous wall 1 is completed, and the inside thereof is excavated. After that, as shown in (b), core boring is performed at a position where the water collecting pipe 3 should be attached, and a communication hole 7 having a diameter larger than that of the water collecting pipe 3 is formed.
Then, the water collecting pipe 3 is arranged in the communication hole 7 as shown in (c), and the gap between the communication hole 7 and the water collecting pipe 3 is filled with grout 8 such as mortar. Is. [Problems to be Solved by the Invention] However, in the method shown in FIG. 3, since the vertical pipe 5 and the water collecting pipe 3 are incorporated into the reinforcing bar basket 6, when the wall thickness of the continuous wall 1 is large or the reinforcing bar basket 6 is If it is long, the weight of the rebar cage 6 becomes too large, so that a super-large crane is required for the work to build the rebar cage 6, and it is impossible to hang it with the existing crane. there were. Moreover, in the method shown in FIG. 4, especially when the wall thickness of the continuous wall 1 is large, the bar arrangement is complicated, or the diameter of the water collection pipe 3 is large, it takes a long time to perform core boring. Not only was the property poor, but there were also problems such as cutting the reinforcing bars of the continuous wall, and the core boring position was misaligned, making it difficult to join the vertical pipe. The present invention has been made in view of the above circumstances, and an object of the present invention is to provide a method of constructing a water collecting pipe having excellent workability. "Means for Solving the Problems" The present invention is installed by penetrating an underground continuous wall,
In a method of constructing a water collecting pipe that connects a water collecting pit provided integrally with the underground continuous wall by being placed around the vertical pipe to the inside of the underground continuous wall and the inside of the underground continuous wall In addition, a sleeve having a thickness equal to or slightly shorter than the thickness of the underground continuous wall at a predetermined position of the reinforcing bar cage of the underground continuous wall is arranged at a position facing the lower part of the vertical pipe forming the water collecting pit, Both ends of the sleeve are closed, the reinforced cage is built and concrete is placed, and when the concrete hardens and the construction of the underground continuous wall is completed, the inside of the underground continuous wall is excavated, and thereafter, A through hole is formed by core boring through the sleeve from the inside of the underground wall to the concrete between the sleeve and the vertical pipe, and the water collecting pipe is formed in the sleeve and the through hole. It is characterized by disposing. "Embodiment" An embodiment of the construction method of the present invention will be described below with reference to FIG. 1 (a) to 1 (c) show the construction method of this embodiment in the order of steps, the same parts as in the case of the conventional method described above are designated by the same reference numerals and the description thereof will be omitted. . In the construction method of this embodiment, first, as in the case of the conventional construction method shown in FIG. 4, a reinforcing bar cage 6 to be buried in the continuous wall 1 is built, and then a water collecting pit is provided outside thereof. The vertical pipe 5 which constitutes 2 is built up, but the sleeve (sheath pipe) 10 is attached to the rebar cage 6 in advance. The sleeve 10 is made of, for example, a steel pipe, its diameter is made slightly larger than that of the water collecting pipe 3, and its length is made slightly shorter than the wall thickness of the continuous wall 1, so that concrete does not flow into the inside of the sleeve 10. Block it. Then, as shown in (a), the sleeve 10 is provided with a rebar cage 6 and a vertical pipe 5.
Are installed at positions facing the lower end of the vertical pipe 5 when they are respectively installed. After the rebar cage 6 with the sleeve 10 attached and the vertical pipe 5 are built as shown in (a), concrete is poured to embed the reinforcing bar cage 6 and the vertical pipe 5 in the concrete. After hardening and construction of the continuous wall 1 and the water collecting pit 2 is completed, the ground inside the continuous wall 1 is excavated.
Then, the surface layer of the concrete is scraped off to expose the tip of the sleeve 10, and the tip of the core boring machine is inserted into the sleeve 10, and with respect to the concrete between the rear end of the sleeve 10 and the vertical pipe 5. Core boring is performed to form a communication hole 11 having a diameter slightly smaller than that of the sleeve 10 and slightly larger than that of the water collection pipe 3 as shown in (b). Subsequently, as shown in (c), the water collecting pipe 3 is arranged in the sleeve 10 and the communication hole 11, and the grout is provided in the gap between the outer surface of the water collecting pipe 3 and the inner surface of the sleeve 10 and the communication hole 11. The construction is completed when 12 is filled and the grout 12 is hardened. According to the above method, only the sleeve 10 is attached to the rebar cage 6, and the vertical pipe 5 and the rebar cage 6 are separately built. Therefore, the vertical pipe 5 shown in FIG. Basket 6
Unlike the conventional method of incorporating and building in, the reinforcing bar cage 6 does not become too heavy and difficult to build. Further, since core boring is performed only for a short distance between the sleeve 10 and the vertical pipe 5, the conventional method of performing core boring on the entire wall thickness of the continuous wall 1 shown in FIG. As described above, the accurate communication hole 11 can be easily formed without requiring a long time for core boring. The length of the sleeve 10 may be equal to the wall thickness of the continuous wall 1. Further, if the tip of the sleeve 10 is exposed on the concrete surface, the position of the sleeve 10 becomes clear when the sleeve 10 is squeezed out, and the squeezing out is also easy. [Effect of the Invention] As described in detail above, according to the construction method of the present invention, the sleeve with both ends closed is attached to the rebar cage in advance, and the concrete between the sleeve and the vertical pipe is Since core boring is performed, the rebar cage will not become too heavy and difficult to assemble, and core drilling will not take a long time, and accurate communication will be easy. The hole can be formed, and therefore the workability is extremely good.

【図面の簡単な説明】 第1図(イ)〜(ハ)はこの発明の施工方法の実施例を
工程順に示す立断面図である。 第2図は地中連続壁の外側に設けられた集水ピットおよ
び集水管の概略構成を示すもので、このうち(イ)は立
断面図、(ロ)は平面図である。 第3図(イ),(ロ)、および第4図(イ)〜(ハ)
は、それぞれ従来の施工方法を工程順に示す立断面図で
ある。 1……地中連続壁、2……集水ピット、3……集水管、
5……竪管、6……鉄筋篭、10……スリーブ、11……連
通孔。
BRIEF DESCRIPTION OF THE DRAWINGS FIGS. 1 (a) to 1 (c) are vertical sectional views showing an embodiment of a construction method of the present invention in the order of steps. FIG. 2 shows a schematic structure of a water collecting pit and a water collecting pipe provided on the outer side of the underground wall, of which (a) is a vertical sectional view and (b) is a plan view. 3 (a), (b), and FIGS. 4 (a)-(c).
[Fig. 3] is an elevation sectional view showing a conventional construction method in the order of steps. 1 ... Underground wall, 2 ... collection pit, 3 ... collection pipe,
5 ... Vertical pipe, 6 ... Rebar cage, 10 ... Sleeve, 11 ... Communication hole.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 若山 茂巳 東京都中央区京橋2丁目16番1号 清水 建設株式会社内 (72)発明者 児島 統一 東京都中央区京橋2丁目16番1号 清水 建設株式会社内 (72)発明者 桑原 泰秀 東京都中央区京橋2丁目16番1号 清水 建設株式会社内   ────────────────────────────────────────────────── ─── Continuation of front page    (72) Inventor Shigemi Wakayama               Shimizu, 2-6-1 Kyobashi, Chuo-ku, Tokyo               Construction Co., Ltd. (72) Inventor Kojima Unification               Shimizu, 2-6-1 Kyobashi, Chuo-ku, Tokyo               Construction Co., Ltd. (72) Inventor Yasuhide Kuwahara               Shimizu, 2-6-1 Kyobashi, Chuo-ku, Tokyo               Construction Co., Ltd.

Claims (1)

(57)【特許請求の範囲】 1.地中連続壁を貫通して取り付けられて、竪管の周囲
にコンクリートが打設されることによって前記地中連続
壁と一体となってその外側に設けられた集水ピットと前
記地中連続壁の内側とを連通する集水管の施工方法にお
いて、前記地中連続壁の鉄筋篭の所定位置にその地中連
続壁の厚さと同等またはやや短いスリーブを前記集水ピ
ットを構成する竪管の下部に対向する位置に配設してお
くとともに、該スリーブの両端を閉塞しておき、その鉄
筋篭を建て込んでコンクリートを打設し、コンクリート
が硬化して地中連続壁の施工が完了したらその地中連続
壁の内側を掘削し、その後、前記地中連続壁の内側から
前記スリーブを通してそのスリーブと前記竪管との間の
コンクリートに対してコアボーリングを行うことによっ
て連通孔を形成し、そのスリーブおよび連通孔内に前記
集水管を配設することを特徴とする地中連続壁における
集水管の施工方法。
(57) [Claims] The water collecting pit and the underground continuous wall, which are integrally attached to the underground continuous wall by being installed by penetrating the underground continuous wall and placing concrete around the vertical pipe, and the outside of which are provided. In the method of constructing the water collecting pipe communicating with the inside of the bottom of the vertical pipe constituting the water collecting pit, a sleeve having a thickness equal to or slightly shorter than the thickness of the underground continuous wall is provided at a predetermined position of the rebar cage of the underground continuous wall. It is placed at a position opposite to, and both ends of the sleeve are closed, the reinforced basket is installed and concrete is poured, and when the concrete is hardened and construction of the underground wall is completed, The inside of the underground continuous wall is excavated, and thereafter, the communication hole is formed by core boring through the sleeve from the inside of the underground continuous wall to the concrete between the sleeve and the vertical pipe. Construction method of water collecting pipes in underground continuous wall, characterized by disposing the water collecting pipe to the sleeve and communicating hole.
JP29345087A 1987-11-20 1987-11-20 Construction method of water collecting pipe on underground wall Expired - Fee Related JP2676205B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP29345087A JP2676205B2 (en) 1987-11-20 1987-11-20 Construction method of water collecting pipe on underground wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP29345087A JP2676205B2 (en) 1987-11-20 1987-11-20 Construction method of water collecting pipe on underground wall

Publications (2)

Publication Number Publication Date
JPH01137013A JPH01137013A (en) 1989-05-30
JP2676205B2 true JP2676205B2 (en) 1997-11-12

Family

ID=17794920

Family Applications (1)

Application Number Title Priority Date Filing Date
JP29345087A Expired - Fee Related JP2676205B2 (en) 1987-11-20 1987-11-20 Construction method of water collecting pipe on underground wall

Country Status (1)

Country Link
JP (1) JP2676205B2 (en)

Also Published As

Publication number Publication date
JPH01137013A (en) 1989-05-30

Similar Documents

Publication Publication Date Title
CN109898669B (en) Construction method for underground first-layer beam column joint by reverse construction method
JP4440497B2 (en) Construction method of underground continuous wall and construction method of underground structure
JP2676205B2 (en) Construction method of water collecting pipe on underground wall
JP2848212B2 (en) Cast-in-place concrete pile method
JPH09111758A (en) Cast-in-place concrete pile and construction method thereof
JP2001234531A (en) Steel pipe pile filled with soil cement and method for building the same
JP2001164569A (en) All-casing cast-in-place pile construction method
KR200296444Y1 (en) Underaround continued wall structure using a large diameter cast-in-place pile installed by Benoto method
JPH09324422A (en) Cast-in-place compound pile and building method therefor
RU2026922C1 (en) Pile foundation and a method to erect it
JP2001173135A (en) Underground exterior wall of structure and method of construction thereof
JPH06108476A (en) Construction of stud in steel frame structure
JP3082054B2 (en) Large-scale, deep steel continuous basement wall and method of constructing the same
JPS60141919A (en) Method of building continuous pillar-shaped landslide protection wall
CN216446925U (en) Reinforcing construction device for entrance and exit of heavy-caliber jacking pipe in silt stratum
JPS6128774B2 (en)
JP2693027B2 (en) Pile head treatment method for cast-in-place concrete pile
JP2693028B2 (en) Construction method of human hole in middle of pipeline
JPS6136418A (en) Method of forming cast-in-place steel pipe concrete pile
JP2555796B2 (en) Underground construction method using hollow PC columns
JPH0314998B2 (en)
JPH0641956A (en) Execution method for high proof stress cast-in-place concrete pile, etc.
JPS61257529A (en) Underground continuous wall construction work
JPS61179918A (en) Reinforcing bar cage for cast-in-place concrete pile
JP2000130070A (en) Construction method for vertical shaft for shield

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees