JP2670732B2 - Floor concrete placement method - Google Patents

Floor concrete placement method

Info

Publication number
JP2670732B2
JP2670732B2 JP4300320A JP30032092A JP2670732B2 JP 2670732 B2 JP2670732 B2 JP 2670732B2 JP 4300320 A JP4300320 A JP 4300320A JP 30032092 A JP30032092 A JP 30032092A JP 2670732 B2 JP2670732 B2 JP 2670732B2
Authority
JP
Japan
Prior art keywords
concrete
floor
slab
bar
splicing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP4300320A
Other languages
Japanese (ja)
Other versions
JPH06129100A (en
Inventor
行正 荻原
宏恭 藤井
寛人 田口
隆司 伊藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP4300320A priority Critical patent/JP2670732B2/en
Publication of JPH06129100A publication Critical patent/JPH06129100A/en
Application granted granted Critical
Publication of JP2670732B2 publication Critical patent/JP2670732B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、鉄筋コンクリート構造
の建築において、床コンクリートと梁等のコンクリート
を打分けることができる床コンクリートの打分け工法に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a floor concrete separating method capable of separately separating floor concrete and concrete such as beams in the construction of a reinforced concrete structure.

【0002】[0002]

【従来の技術】鉄筋コンクリート造の建築において、コ
ンクリートは一般的には1階分をまとめて打設するの
で、柱・梁・壁・床のコンクリートは同種(同強度)と
なる。
2. Description of the Related Art In reinforced concrete construction, since concrete is generally placed on one floor at a time, concrete of columns, beams, walls and floors is of the same type (same strength).

【0003】また、水平・垂直部材を分割打設する場合
でも、梁成分のかかる垂直部材の部分(パネルゾーン)
を水平材と打ち分けるのは難しいので、結局、1階分は
同一強度とならざるを得ない。
Even when the horizontal and vertical members are separately cast, the vertical member portion (panel zone) to which the beam component is applied.
Since it is difficult to separate the timber with the horizontal timber, it is inevitable that the first floor will have the same strength.

【0004】しかし、コンクリート強度が飛躍的に高ま
ると、そのコンクリートの施工性状は従来のものとは異
なり、一般的に粘性が高くなり、特に床部材のコンクリ
ートとしては好ましくない施工性状を呈することにな
る。
However, when the strength of concrete is dramatically increased, the workability of the concrete is different from the conventional one, and the viscosity is generally high, and the workability is unfavorable as concrete for floor members. Become.

【0005】一方、床部材はその階数分だけの荷重を負
担するのであるから建物の階数に強度を左右されること
はない。このことは従来においても、ハーフPCa板を
床板に用いる場合ハーフPCa板のコンクリート強度が
必ずしも柱や梁のコンクリートと同じでなくてもよいこ
とからも分かる通りである。
On the other hand, since the floor member bears the load corresponding to the number of floors, the strength does not depend on the number of floors of the building. This can be understood from the fact that, even when the half PCa plate is used as the floor plate, the concrete strength of the half PCa plate does not necessarily have to be the same as that of the concrete of the pillar or the beam.

【0006】このような床部材を梁・柱部材のコンクリ
ートと打分ける方法は従来実施されたことがないが、こ
れを行おうとすると、従来、他の部分でコンクリートの
仮打ち止めに用いる資材を使用することになる。これら
の資材としては、リブラス等の金網やエアーバック(空
気圧による棒状の袋)がある。
Although a method of driving such a floor member into concrete of a beam / column member has never been carried out, when attempting to do this, conventionally, a material used for temporarily fixing concrete to another portion is used. Will be done. As these materials, there are a wire mesh such as rib lath and an air bag (a bar-shaped bag by air pressure).

【0007】[0007]

【発明が解決しようとする課題】しかし、リブラスの場
合はこれを張設すること自体が面倒であり、しかも、床
スラブ筋を貫通させることに非常な手間を要する。ま
た、エアーバックの場合は、これを取り除いた後にコン
クリート破片が大量に生じ、このコンクリート破片の掃
除に非常な手間を要する。よって、いずれの場合も実現
性に難がある。
However, in the case of a rib lath, it is troublesome to stretch the rib lath, and it takes a lot of time and labor to penetrate the floor slab muscle. Further, in the case of an air bag, a large amount of concrete debris is produced after the air bag is removed, and cleaning of the concrete debris requires a great deal of labor. Therefore, there is a difficulty in realization in any case.

【0008】本発明の目的は前記従来例の不都合を解消
し、打継用のせき板が簡単に設置でき、しかも、このせ
き板にスラブ定着筋を容易に挿通させてこれにより床ス
ラブ筋の貫通状態が得られるとともに、この打継用のせ
き板の天端を梁・床コンリートのレベル定規とすること
もでき、一方、せき板を境に性状の異なるコンクリート
を打設することが可能であり、例えば梁部分に打設する
コンクリートのみ高強度のものを用い、これよりも容積
が大きい床部分には普通コンクリートを用いることで大
幅なコストダウンを図ることができ、しかもこのように
性状の異なるコンクリートを用いても一体性の高いもの
となる床コンクリートの打分け工法を提供することにあ
る。
The object of the present invention is to eliminate the disadvantages of the above-mentioned conventional example, to easily install a weir plate for splicing, and to easily insert the slab anchoring muscle into this weir plate, thereby making it possible to remove the floor slab muscle. A penetration state can be obtained, and the top end of the damping board can be used as a level ruler for beam / floor concrete.On the other hand, concrete with different properties can be cast at the damping board. Yes, for example, use only high-strength concrete to be cast on the beam, and use ordinary concrete for the floor with a larger volume than this, so that significant cost reduction can be achieved. An object of the present invention is to provide a method for placing floor concrete, which is highly integrated even if different concretes are used.

【0009】[0009]

【課題を解決するための手段】本発明は前記目的を達成
するため、梁型枠と床型枠を接合してこれら梁型枠内お
よび床型枠上にコンクリートを打設する場合において、
床型枠上で梁型枠との境界線上に下端に釘止め用の水平
フランジを有し、鉄筋貫通孔を形成した打継用のせき板
を左右の梁型枠の上方に立上げ、該鉄筋貫通孔を介して
梁部分を跨ぐような長さからなるスラブ定着筋を対向す
るせき板相互に掛け渡すようにして貫通させ、かつ該ス
ラブ定着筋の端部をスラブ上筋にラップさせて配筋し、
前記せき板を境に性状の異なるコンクリートを打設する
こと、または、この構成に加えて、打継用のせき板は、
反対側を凹部とするコッター用の膨出部を形成したこと
を要旨とするものである。
Means for Solving the Problems In order to achieve the above object, the present invention provides a method of joining a beam form and a floor form, and placing concrete in the beam form and on the floor form.
On the floor formwork, a horizontal flange for nailing is provided at the lower end on the boundary line with the beam formwork, and a damming plate for joining having reinforcing bar through holes is raised above the left and right beam formworks, A slab anchoring bar having a length that straddles the beam part through the reinforcing bar through-hole is passed through so as to extend between the opposing cuffs, and the end of the slab anchoring bar is wrapped around the upper slab bar. Arrange the
Placing concrete with different properties on the border of the weir, or, in addition to this configuration, a weir for jointing,
The gist is that a bulge portion for a cotter having a concave portion on the opposite side is formed.

【0010】[0010]

【作用】請求項1記載の本発明によれば、打継用のせき
板は下端の水平フランジを床型枠上に釘止めするだけで
床型枠上で梁型枠との境界線上に簡単に設置でき、この
ようにしてせき板を左右の梁型枠の上方に立上げた後、
該鉄筋貫通孔を介して梁部分を跨ぐような長さからなる
スラブ定着筋を対向するせき板相互に掛け渡すようにし
て貫通させ、かつ該スラブ定着筋の端部をスラブ上筋に
ラップさせて配筋するので、このスラブ定着筋により床
スラブ筋は床コンリート部分と梁コンクリート部分の双
方に連続性を発揮できる。また、せき板の天端を梁・床
コンリートのレベル定規とすることもできる。
According to the first aspect of the present invention, the damping plate for the joint can be easily formed on the boundary between the beam form and the floor form only by nailing the lower horizontal flange to the floor form. Can be installed in this way, after raising the cough plate above the left and right beam formwork in this way,
A slab anchorage having a length that straddles the beam portion through the reinforcing bar through-hole is pierced so as to hang it over the opposing dams, and the end of the slab anchorage is wrapped around the slab upper bar. Since the slab anchoring bars allow the floor slab reinforcing bars to exhibit continuity in both the floor concrete portion and the beam concrete portion. In addition, the top end of the weir board can be used as a level ruler for the beam / floor concrete.

【0011】一方、せき板を境に性状の異なるコンクリ
ートを打設することが可能となり、例えば梁部分に打設
するコンクリートのみ高強度のものを用い、これよりも
容積が大きい床部分には普通コンクリートを用いること
で大幅なコストダウンを図ることができる。このように
性状の異なるコンクリートを用いても、前記スラブ定着
筋により連続性が発揮されていることから、床部分に打
設されるコンリートと梁部分に打設するコンクリートと
の一体性を高くできる。
On the other hand, it is possible to cast concrete having different properties at the boundary of the weir. For example, only high-strength concrete to be cast at the beam portion is used, and a floor portion having a larger volume is usually used. The cost can be reduced significantly by using concrete. Even if concrete with different properties is used, since the continuity is exhibited by the slab anchoring streak, the integrity of the concrete cast on the floor and the concrete cast on the beam can be increased. .

【0012】なお、スラブ定着筋とせき板とを予め組み
合わせた梯子状のユニットを作製しておき、これを型枠
上にセットするようにすれば、配筋作業の合理化が図れ
る。
If a ladder-shaped unit in which the slab anchoring streak and the dam are combined in advance is prepared and set on the formwork, the reinforcing work can be rationalized.

【0013】請求項2記載の本発明によれば、前記作用
に加えて、コッター用の膨出部によりせき板とコンクリ
ートの接合度が強化され、また、コッター用の膨出部の
反対側は凹部なので、この反対側についても同様にせき
板とコンクリートの接合度が強化され、床コンクリート
部分と梁コンクリート部分の結合性が増す。
According to the second aspect of the present invention, in addition to the above action, the joint between the dam and the concrete is strengthened by the bulging portion for the cotter, and the opposite side of the bulging portion for the cotter is provided. Since it is a recess, the joint between the dam and the concrete is similarly strengthened on the opposite side, and the bondability between the floor concrete portion and the beam concrete portion is increased.

【0014】[0014]

【実施例】以下、図面について本発明の実施例を詳細に
説明する。図1は本発明の床コンクリートの打分け工法
の1実施例を示す縦断側面図である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments of the present invention will be described below in detail with reference to the drawings. FIG. 1 is a longitudinal sectional side view showing one embodiment of the method for separating floor concrete according to the present invention.

【0015】先に本発明工法で使用する打継用のせき板
1について説明すると、図2、図3に示すように、鋼製
などの金属製もしくは硬質合成樹脂製のもので、垂直板
1aの下端に水平フランジ1bを形成し、この水平フラ
ンジ1bに釘穴2を穿設して釘止め用のフランジとし、
また、上端にも水平フランジ1cを設けた。この水平フ
ランジ1cはコンクリートの充填性をよくするため水平
フランジ1bよりも幅の狭いものとする。
First, the weir plate 1 for splicing used in the method of the present invention will be described. As shown in FIGS. 2 and 3, the vertical plate 1a is made of metal such as steel or hard synthetic resin. Forming a horizontal flange 1b at the lower end of the, and forming a nail hole 2 in the horizontal flange 1b to form a nail fastening flange,
A horizontal flange 1c is also provided on the upper end. The horizontal flange 1c is narrower than the horizontal flange 1b in order to improve the filling property of concrete.

【0016】さらに、垂直板1aの上部位置には適宜間
隔で鉄筋貫通孔3を形成し、また、プレスその他の手段
でコッター用の膨出部4をこの垂直板1aに形成した。
該膨出部4は鉄筋貫通孔3の間に位置させることが望ま
しく、反対側は凹部となっている。
Further, reinforcing bar through holes 3 are formed at appropriate positions at the upper position of the vertical plate 1a, and swelling portions 4 for a cotter are formed on the vertical plate 1a by pressing or other means.
The bulging portion 4 is preferably located between the reinforcing bar through holes 3, and a concave portion is formed on the opposite side.

【0017】図1中、5は梁型枠、6は床型枠、7は梁
主筋、8は梁スターラップ筋、9はスラブ上筋、10はス
ラブ下筋であるが、梁型枠5の上端に床型枠6の端部を
載せ、これらを結合して型枠を組むことは従来と同じで
ある。
In FIG. 1, 5 is a beam form, 6 is a floor form, 7 is a beam main bar, 8 is a beam stirrup bar, 9 is a slab upper bar, and 10 is a slab lower bar, but the beam frame 5 It is the same as the conventional method that the end of the floor formwork 6 is placed on the upper end of the, and these are combined to form a formwork.

【0018】本発明は床型枠6上の端で梁型枠5との境
界線上に、水平フランジ1bを釘止めして打継用のせき
板1を立上げる。図中12は梁型枠5と床型枠6との結合
部に配置する桟木であるが、前記釘止めはこの桟木12を
介在させる。
According to the present invention, the horizontal flange 1b is nailed at the edge of the floor formwork 6 on the boundary line between the beam formwork 5 and the weir plate 1 for splicing is raised. In the figure, reference numeral 12 is a pier arranged at the joint between the beam form 5 and the floor form 6, and the pier 12 is interposed for the nailing.

【0019】さらに、鉄筋貫通孔3を介してせき板1に
スラブ定着筋11を貫通させた。このスラブ定着筋11は左
右の梁型枠5の上方に立ち上がる対向するせき板1相互
を貫通するものとして、梁部分を跨ぐような長さのもの
とする。
Further, the slab anchoring muscle 11 was penetrated through the dam 1 through the reinforcing-bar through-hole 3. The slab fixing streak 11 penetrates through the opposing weir plates 1 rising above the left and right beam form frames 5, and has a length that straddles the beam portion.

【0020】なお、スラブ定着筋11は端部をスラブ上筋
9にラップさせるが、これがあることにより、床筋が増
えるようなことはない。
Although the end portion of the slab anchoring muscle 11 is wrapped around the upper slab muscle 9, the presence of this prevents the floor muscle from increasing.

【0021】このようにして、せき板1により床コンリ
ート打設部分と梁コンクリート打設部分は上方まで仕切
られるので、せき板1を境に性状のことなるコンクリー
トを打設することが可能となる。その際、水平フランジ
1cがあるせき板1の天端を梁・床コンリートのレベル
定規とすることもできる。床型枠がハーフPC板等でレ
ベル精度が悪い場合は水平フランジ1bにレベル調整用
ボルト等を介在させることにより水平フランジ1Cをレ
ベル定規とすることができる。
In this way, since the floor concrete placing portion and the beam concrete placing portion are partitioned to the upper side by the weir board 1, it becomes possible to place concrete having different properties with the weir board 1 as a boundary. . At that time, the top end of the weir plate 1 having the horizontal flange 1c can be used as a level ruler for the beam / floor concrete. When the floor formwork is a half PC plate or the like and the level accuracy is poor, the horizontal flange 1C can be used as a level ruler by interposing a level adjusting bolt or the like in the horizontal flange 1b.

【0022】また、図4に示すようにスラブ定着筋11と
せき板1とを予め組み合わせた梯子状のユニットを作製
しておき、これを型枠上にセットするようにしてもよ
い。
Further, as shown in FIG. 4, a ladder-shaped unit in which the slab fixing streak 11 and the dam 1 are combined in advance may be prepared and set on the mold.

【0023】図5は本発明の第2実施例を示すもので、
前記打継用のせき板1は図6、図7に示すように、垂直
板1aの上部位置の鉄筋貫通孔3の他に下部位置にも鉄
筋貫通孔13を形成した。この鉄筋貫通孔13は水平フラン
ジ1bまで達する切欠き孔としてもよい。
FIG. 5 shows a second embodiment of the present invention.
As shown in FIGS. 6 and 7, in the weir plate 1 for splicing, reinforcing bar through holes 13 are formed in the lower position in addition to the reinforcing bar through holes 3 in the upper position of the vertical plate 1a. The reinforcing bar through hole 13 may be a cutout hole reaching the horizontal flange 1b.

【0024】このようにして、鉄筋貫通孔13を介してス
ラブ下筋10もせき板1を貫通させ、梁部分に端部を突出
させるようにした。
In this way, the lower slab reinforcing bar 10 was made to penetrate through the reinforcing bar through hole 13 so that the end portion was projected to the beam portion.

【0025】[0025]

【発明の効果】以上述べたように本発明の床コンクリー
トの打分け工法は、梁型枠と床型枠を接合してこれら梁
型枠内および床型枠上にコンクリートを打設する場合に
おいて、床コンクリートと梁等のコンクリートを打分け
ることができるため、打継用のせき板が簡単に設置で
き、しかも、このせき板にスラブ定着筋を容易に挿通さ
せてこれにより床スラブ筋の貫通状態が得られるととも
に、この打継用のせき板の天端を梁・床コンクリートの
レベル定規とすることもできるものである。なお、スラ
ブ定着筋とせき板とを予め組み合わせた梯子状のユニッ
トを作製しておき、これを型枠上にセットするようにす
れば、配筋作業の合理化が図れる。
As described above, the method for splitting floor concrete according to the present invention can be applied to a case where a beam form and a floor form are joined and concrete is cast in the beam form and on the floor form. Since floor concrete and concrete such as beams can be separately punched, a splint for splicing can be easily installed, and the slab anchoring streak can be easily inserted through this splint to penetrate the floor slab streak. In addition to the condition being obtained, the top end of this splint for splicing can be used as a level ruler for beams and floor concrete. In addition, if a ladder-shaped unit in which the slab anchoring streak and the dam are combined in advance is prepared and set on the formwork, the work of arranging can be rationalized.

【0026】一方、せき板を境に性状の異なるコンクリ
ートを打設することが可能となり、例えば梁部分に打設
するコンクリートのみ高強度のものを用い、これよりも
容積が大きい床部分には普通コンクリートを用いること
で大幅なコストダウンを図ることができる。このように
性状の異なるコンクリートを用いても、スラブ定着筋を
対向するせき板相互に掛け渡すようにして貫通させ、か
つ該スラブ定着筋の端部をスラブ上筋にラップさせて配
筋するので、このスラブ定着筋により床スラブ筋は床コ
ンリート部分と梁コンクリート部分の双方に連続性を発
揮できるので、床部分に打設されるコンリートと梁部分
に打設するコンクリートとの一体性を高くすることがで
きるものである。
On the other hand, it becomes possible to place concrete having different properties on the basis of a weir board. For example, only concrete having a high strength is used for placing a beam portion, and a floor portion having a larger volume than this is generally used. The cost can be reduced significantly by using concrete. Even if concrete with different properties is used in this manner, the slab anchorage bars are pierced so as to hang between the opposing dams, and the ends of the slab anchorage bars are laid on the upper slab muscles for reinforcement. , The floor slab reinforcement can show continuity in both the floor concrete part and the beam concrete part by this slab anchorage bar, so that the integrity of the concrete poured into the floor part and the concrete poured into the beam part is increased. Is something that can be done.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の床コンクリートの打分け工法の第1実
施例を示す縦断側面図である。
FIG. 1 is a vertical cross-sectional side view showing a first embodiment of a floor concrete placing method according to the present invention.

【図2】本発明工法で使用する打継用のせき板の1例を
示す表側の斜視図である。
FIG. 2 is a front perspective view showing an example of a splicing plate for splicing used in the method of the present invention.

【図3】本発明工法で使用する打継用のせき板の1例を
示す裏側の斜視図である。
FIG. 3 is a back side perspective view showing an example of a splicing plate for splicing used in the method of the present invention.

【図4】本発明工法の応用例を示すユニットの斜視図で
ある。
FIG. 4 is a perspective view of a unit showing an application example of the method of the present invention.

【図5】本発明の床コンクリートの打分け工法の第2実
施例を示す縦断側面図である。
FIG. 5 is a vertical cross-sectional side view showing a second embodiment of the floor concrete placing method according to the present invention.

【図6】本発明工法で使用する打継用のせき板の他例を
示す表側の斜視図である。
FIG. 6 is a front side perspective view showing another example of a splice plate for splicing used in the method of the present invention.

【図7】本発明工法で使用する打継用のせき板の他例を
示す裏側の斜視図である。
FIG. 7 is a back side perspective view showing another example of a splicing board for splicing used in the method of the present invention.

【符号の説明】[Explanation of symbols]

1…せき板 1a…垂直板 1b…水平フランジ 1c…水平フランジ 2…釘穴 3…鉄筋貫通孔 4…膨出部 5…梁型枠 6…床型枠 7…梁主筋 8…梁スターラップ筋 9…スラブ上筋 10…スラブ下筋 11…スラブ定着筋 12…桟木 DESCRIPTION OF SYMBOLS 1 ... Cushion board 1a ... Vertical board 1b ... Horizontal flange 1c ... Horizontal flange 2 ... Nail hole 3 ... Reinforcing bar through hole 4 ... Bulging part 5 ... Beam form frame 6 ... Floor form frame 7 ... Beam main bar 8 ... Beam stirrup bar 9 ... Slab upper muscle 10 ... Slab lower muscle 11 ... Slab anchor muscle 12 ... Pier

───────────────────────────────────────────────────── フロントページの続き (72)発明者 伊藤 隆司 愛知県名古屋市中区新栄町二丁目14番地 鹿島建設株式会社 名古屋支店内 (56)参考文献 特開 昭62−37465(JP,A) 特開 平4−155058(JP,A) 特開 平2−101259(JP,A) 特公 平2−44974(JP,B2) ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Takashi Ito 2-14, Shin-eicho, Naka-ku, Nagoya-shi, Aichi Kashima Construction Co., Ltd., Nagoya Branch (56) Reference JP-A-62-37465 (JP, A) Kaihei 4-155058 (JP, A) JP-A-2-101259 (JP, A) JP-B 2-44974 (JP, B2)

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 梁型枠と床型枠を接合してこれら梁型枠
内および床型枠上にコンクリートを打設する場合におい
て、床型枠上で梁型枠との境界線上に下端に釘止め用の
水平フランジを有し、鉄筋貫通孔を形成した打継用のせ
き板を左右の梁型枠の上方に立上げ、該鉄筋貫通孔を介
して梁部分を跨ぐような長さからなるスラブ定着筋を対
向するせき板相互に掛け渡すようにして貫通させ、かつ
該スラブ定着筋の端部をスラブ上筋にラップさせて配筋
し、前記せき板を境に性状の異なるコンクリートを打設
することを特徴とする床コンクリートの打分け工法。
When a beam form and a floor form are joined and concrete is cast in the beam form and on the floor form, a lower end is provided on a boundary between the beam form and the beam form on the floor form. It has a horizontal flange for nailing, raises a damming plate for joining with reinforcing bar through holes above the left and right beam formwork, and spans the beam part through the reinforcing bar through holes. The slab anchoring streak is pierced so as to span the opposing dams, and the end of the slab anchoring bar is wrapped around the slab upper bar to arrange the reinforcement, and concrete having different properties with the dam as the boundary is used. A method for placing floor concrete, which is characterized by placing it.
【請求項2】 打継用のせき板は、反対側を凹部とする
コッター用の膨出部を形成した請求項1記載の床コンク
リートの打分け工法。
2. The method for striking a floor concrete according to claim 1, wherein the weir for splicing is formed with a bulge for a cotter having a recess on the opposite side.
JP4300320A 1992-10-13 1992-10-13 Floor concrete placement method Expired - Lifetime JP2670732B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4300320A JP2670732B2 (en) 1992-10-13 1992-10-13 Floor concrete placement method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4300320A JP2670732B2 (en) 1992-10-13 1992-10-13 Floor concrete placement method

Publications (2)

Publication Number Publication Date
JPH06129100A JPH06129100A (en) 1994-05-10
JP2670732B2 true JP2670732B2 (en) 1997-10-29

Family

ID=17883368

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4300320A Expired - Lifetime JP2670732B2 (en) 1992-10-13 1992-10-13 Floor concrete placement method

Country Status (1)

Country Link
JP (1) JP2670732B2 (en)

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6237465A (en) * 1985-08-12 1987-02-18 三井建設株式会社 Method for casting concrete
JPH0244974A (en) * 1988-08-05 1990-02-14 Fujitsu Ltd Object tracking device for television camera
JPH02101259A (en) * 1988-10-08 1990-04-13 Fujita Corp Jointing stop material for slab concrete and construction method
JP2622621B2 (en) * 1990-10-18 1997-06-18 晃 室星 Joining frame and joining method of concrete floor

Also Published As

Publication number Publication date
JPH06129100A (en) 1994-05-10

Similar Documents

Publication Publication Date Title
KR100690198B1 (en) Steel beam with U-shaped connector and Steel composite beam using the steel beam
JP2781155B2 (en) Precast concrete board
JPH0754428A (en) Method of constructing wall by truss reinforcing bar embedded form
JP3999114B2 (en) Reinforcing method and structure of notched corner of bridge main girder
JP2522714B2 (en) Construction method of building frame
JP2670732B2 (en) Floor concrete placement method
JP2003129676A (en) Method of reinforcing concrete frame
JPH08302619A (en) Joint structure for composite members
JPH04254646A (en) Steel framed reinforced concrete beam
JPH03281855A (en) Floor framing construction for building
JP3047817B2 (en) Method of placing concrete so that it can be separated
JP4083913B2 (en) Seismic reinforcement structure of building
JPH01290853A (en) Composite floor board using deck plate
JPH04306303A (en) Jointing structure
JPH0932311A (en) Reinforcement structure of existing building
JP7546445B2 (en) Synthetic flooring
JPS60133146A (en) Construction of synthetic large beam using u-shaped precast beam material
JPH08326197A (en) Joint structure of precast concrete floor board
KR200364220Y1 (en) Joint panel for mold
JPH0566462B2 (en)
JPH07139054A (en) Joining method for precast concrete wall plate
JP2942370B2 (en) Formwork method for vertical joints such as reinforced concrete beams and walls and guide metal fittings used in this method
JP2004107961A (en) Flexural reinforcement construction method for junction of existing pillar and beam or slab
JP2612977B2 (en) Prevention method of crack of post-cast concrete in composite slab.
JPH05230837A (en) Concrete expendable form construction method