JP3047817B2 - Method of placing concrete so that it can be separated - Google Patents
Method of placing concrete so that it can be separatedInfo
- Publication number
- JP3047817B2 JP3047817B2 JP8204617A JP20461796A JP3047817B2 JP 3047817 B2 JP3047817 B2 JP 3047817B2 JP 8204617 A JP8204617 A JP 8204617A JP 20461796 A JP20461796 A JP 20461796A JP 3047817 B2 JP3047817 B2 JP 3047817B2
- Authority
- JP
- Japan
- Prior art keywords
- slab
- concrete
- punching
- formwork
- cast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Description
【0001】[0001]
【発明の属する技術分野】この発明は、建物の構築時に
おいて、柱や梁の部分とスラブの部分との各部分へ、そ
れぞれ別種類のコンクリートを打設できるようにしたコ
ンクリートの打設方法に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of placing concrete in which different types of concrete can be poured into columns and beams and slabs when building a building. Things.
【0002】[0002]
【従来の技術】近年、超高層鉄筋コンクリート集合住宅
等の大きな躯体強度を必要とする建物には、Fc=600Kg/c
m2という高強度コンクリートが用いられるようになって
きている。ちなみに、従来ではFc=360Kg/cm2からFc=420
Kg/cm2までである。この高強度コンクリートは、建物に
おいて特に強度を必要とする柱にのみ、多く見ても、柱
と大梁とにのみ必要なものであり、スラブには必要ない
ものであった。ちなみに、スラブに必要な強度はFc=240
Kg/cm2程度である。また、この高強度コンクリートは、
非常に高価なものであると共に、粘度が高く施工性が悪
いという欠点もある。2. Description of the Related Art In recent years, for buildings requiring large frame strength, such as high-rise reinforced concrete condominiums, Fc = 600Kg / c
has come to high strength concrete is used as m 2. Incidentally, in the conventional Fc from Fc = 360Kg / cm 2 = 420
Up to Kg / cm 2 . This high-strength concrete is necessary only for columns that require particularly high strength in a building, and at best, only for columns and girder beams, not for slabs. By the way, the strength required for the slab is Fc = 240
It is about Kg / cm 2 . In addition, this high-strength concrete
It is very expensive and has the disadvantage of high viscosity and poor workability.
【0003】これらのことから、前述したように大きな
躯体強度を必要とする建物においては、柱および梁との
部分に高強度コンクリートを打設し、スラブの部分に普
通コンクリートを打設するというように、別種類のコン
クリートを打分けることが、理想的な打設方法となって
いる。[0003] From these facts, as described above, in a building requiring a large skeleton strength, high-strength concrete is poured into columns and beams, and ordinary concrete is poured into slabs. Separating different types of concrete is an ideal casting method.
【0004】しかし、このように別種類のコンクリート
を打分けて打設することは非常に難しい作業であると共
に、打分けるための打設方法が確立されていないことも
あり、これまでは、打分けることをあまり実施せずに、
高強度コンクリートのみを建物全体へ打設していた。そ
のため、大きな躯体強度が必要な建物を構築するに際し
て、前述した高強度コンクリートの欠点から起因する、
施工費用が高価になると共に、施工能率も悪くなるとい
う問題に悩まされることとなる。[0004] However, it is very difficult to separate and lay out different types of concrete, and a method for laying out concrete has not been established. Without doing much of the splitting,
Only high-strength concrete was cast throughout the building. Therefore, when constructing a building that requires large frame strength, it is caused by the above-mentioned disadvantage of high-strength concrete,
The construction cost becomes expensive and the construction efficiency becomes poor.
【0005】従って、従来から、柱および梁等の特に強
度を必要とする部分に高強度コンクリートを打設し、ま
た、スラブ等の部分に普通コンクリートを打設するとい
うように、別種類のコンクリートを打分ける打設方法を
採用したいというニーズは非常に高いものであり、容易
かつ確実に打分けることのできる打設方法の確立が望ま
れていた。[0005] Therefore, conventionally, high-strength concrete is poured into portions requiring particularly high strength such as columns and beams, and ordinary concrete is poured into portions such as slabs. There is an extremely high need to employ a casting method that separates pieces, and it has been desired to establish a casting method that can easily and reliably separate pieces.
【0006】なお、従来では、この柱および梁とスラブ
とに別種類のコンクリートを打分けるということに関し
ての明確な打設方法を確立してはいないが、打ち止め型
枠を利用することによって、コンクリートの打分けに対
処できるようにすることも考えられていた。この打ち止
め型枠は、目的を多少異なるものとして使用されるもの
で、施工ブロックの分割によって生じる、壁や梁および
スラブの鉛直打ち継ぎ部において、コンクリートの流出
を仕切るためのものである。[0006] In the past, no clear casting method has been established for punching different types of concrete into columns and beams, and slabs. It was conceived to be able to deal with the bats. The striking formwork is used for a slightly different purpose, and is used to partition the outflow of concrete at the vertical joints of walls, beams and slabs caused by the division of construction blocks.
【0007】そして、この打ち止め型枠を用いた具体例
を、図13〜図15に示す。ここで、図13は、通常良く見ら
れるものであり、仕切り用のばら板40と、押さえ用の桟
木41とを用いた方法である。また、図14は、壁施工時に
用いるものであるがスラブにも応用可能であり、仕切り
用のエキスパンドメタル42またはラス網と、押さえ用の
桟木41とを用いた方法である。図15は、仕切り用の発泡
ゴム43と、押さえ用の締付け用定規44とを用いた方法で
ある。[0007] Figs. 13 to 15 show specific examples using the perforated formwork. Here, FIG. 13 is a method which is often seen, and is a method using a bulky plate 40 for partitioning and a pier 41 for holding. FIG. 14 shows a method used at the time of wall construction, but is also applicable to a slab, and is a method using an expanded metal 42 or a lath net for partition and a pier 41 for holding. FIG. 15 shows a method using a foam rubber 43 for partitioning and a tightening ruler 44 for holding.
【0008】[0008]
【発明が解決しようとする課題】前述した従来の打ち止
め型枠を、コンクリートを打分ける目的で使用する場合
の最大の問題点は、後打ち側のコンクリートを打つ前に
おいて、仕切り用の各部材(ばら板や発砲ゴム)と押さ
え用の各部材(桟木)とを、いかに迅速に手間をかけず
に取り除くかである。なお、図14におけるエキスパンド
メタルやラス網は取り除かなくてよい。The biggest problem in using the above-mentioned conventional perforated formwork for the purpose of punching concrete is that each member for partitioning (before the perforated concrete is hit) is used. It is how to quickly and easily remove the bulkhead (rubber plate and rubber foam) and each member (pier) for holding. The expanded metal and the lath net in FIG. 14 do not need to be removed.
【0009】このことは、後打ちコンクリートが翌日以
降になるような、本来の目的として使用する打ち止め型
枠の場合には、あまり問題にならない。しかし、その日
の内に引続き後打ちコンクリートを打設しなくてはいけ
ない、柱,梁とスラブというようなコンクリート打分け
施工の場合には、非常に大きな問題となる。特に、この
コンクリート打分けの場合には、後打ち側のスラブ配筋
が完了しているので、特に下側の押さえ用部材(桟木)
や仕切り用部材(発砲ゴム等)を取り除く作業が面倒な
ものとなる。そして、このことが、その日の内に引続き
後打ちコンクリートを打設するという、コンクリート打
分け施工に支障をきたすこととなる。[0009] This is not a serious problem in the case of a hitting formwork used for the original purpose such that the post-casting concrete will be on the next day or later. However, in the case of concrete splitting work such as columns, beams and slabs, where post-cast concrete must be continuously cast within the day, a very serious problem arises. In particular, in the case of this concrete splitting, since the slab reinforcement on the rear striking side is completed, the lower holding member (pier) is particularly used.
The operation of removing the partition member (foam rubber or the like) becomes troublesome. And this will hinder the concrete splitting work of continuously placing the post-cast concrete within the day.
【0010】この発明は前述した事情に鑑みて創案され
たもので、その目的は柱や梁の部分への先打ちコンクリ
ート(高強度コンクリート)と、スラブの部分への後打
ちコンクリート(普通コンクリート)との打分けを容易
かつ確実に行えると共に、コンクリート打分けのために
設置した打分け用部材(従来での仕切り用部材や押さえ
用部材)の取り除き作業も容易に短時間で行えて、後打
ちコンクリートを先打ちコンクリートに引続き素早く打
設することのできる打設方法を提供することにある。The present invention has been made in view of the above-mentioned circumstances, and has an object of pre-cast concrete (high-strength concrete) for columns and beams, and post-cast concrete (normal concrete) for slabs. In addition to being able to easily and reliably perform the punching, the work of removing the punching members (conventional partitioning members and holding members) installed for concrete punching can be performed easily and in a short time. It is an object of the present invention to provide a method for placing concrete in which concrete can be poured quickly into cast-in-place concrete.
【0011】[0011]
【課題を解決するための手段】この発明では、先ず、上
面に鉄筋トラスが複数列突出しており、スラブ下部を構
成するハーフPC床版と、前記各鉄筋トラスの上端にス
ラブ上端筋を架け渡し配筋した後において、ハーフPC
床版の上面に打設するスラブコンクリートとからなる合
成床板によってスラブを構成する。According to the present invention, first, a plurality of rows of reinforcing trusses protrude from the upper surface, and a half PC slab constituting a lower portion of the slab and a slab upper reinforcing bar are bridged over the upper end of each reinforcing truss. After arranging, half PC
The slab is constituted by a composite floorboard made of slab concrete cast on the upper surface of the floor slab.
【0012】また、柱および梁の部分へ打設する先打ち
コンクリートとスラブの部分へ打設する後打ちコンクリ
ートとを仕切るために、ハーフPC床版の上面からスラ
ブ上端筋の下端までの間をラス網で塞ぐことができるよ
うに構成されており、除去せずにスラブコンクリートの
中に埋め込んでしまう下部打分け型枠と、この下部打分
け型枠の上部に載置することで、スラブ上端筋の下端か
らスラブコンクリート天端までの間を塞ぐことができる
ように構成されており、スラブ用の後打ちコンクリート
の打設前に取り除く上部打分け型枠とからなる打分け型
枠を、柱および梁とスラブとの境界部分(打分け位置)
であるハーフPC床版の上面に設置することとする。さ
らに、打分け型枠における下部打分け型枠は、スラブに
おけるハーフPC床版上面の梁側端部に梁延設方向へ延
びる状態で設けられており、上弦材の上端でスラブ上端
筋を支持できるように構成されている打分け用鉄筋トラ
スと、この打分け用鉄筋トラスの梁側に取付けて、ハー
フPC床版の上面からスラブ上端筋の下端までの間を塞
いで、コンクリート打ち止め用としているラス網とから
構成する。また、打分け型枠における上部打分け型枠
は、梁の延設方向へ延びる桟木と、この桟木の下面に張
り付けられているクッション材とからなっており、下部
打分け型枠の上部に取付けた時に、クッション材が圧縮
して、スラブ上端筋の周表面および打分け用鉄筋トラス
における上弦材の上面へ密接できるように構成すること
とする。 Further, in order to separate the precast concrete cast into the column and the beam and the postcast concrete cast into the slab, the space between the upper surface of the half PC floor slab and the lower end of the upper slab upper bar is separated. It is constructed so that it can be closed with a lath net, and it is embedded in slab concrete without being removed, and by placing it on the upper part of this lower parting form, the upper end of the slab A punching formwork consisting of an upper punching formwork removed before placing the postcast concrete for the slab is constructed so as to be able to close the space between the lower end of the streak and the top of the slab concrete. And the boundary between the beam and the slab (striking position)
Is installed on the upper surface of the half PC floor slab. Sa
In addition, the lower punching formwork in the punching formwork is
Extend in the beam extension direction at the beam side end of the half PC floor slab
Slab at the top of the upper chord
Reinforcing bar truss configured to support the bars
To the beam side of this reinforced truss truss.
Close the space between the upper surface of the PC floor slab and the lower end of the upper slab muscle.
And the lath net used for concrete
Constitute. Also, the upper punching formwork in the punching formwork
Is a pier that extends in the direction in which the beams extend,
It is made of cushion material attached to the bottom
Cushion material compresses when installed on top of punching formwork
And the reinforced steel truss
So that it can be in close contact with the upper surface of the upper chord at
And
【0013】そして、柱および梁の部分におけるスラブ
コンクリート天端レベルまでに、先打ちコンクリートを
打設すると共に、打分け型枠によって柱および梁とスラ
ブとの境界部分で打ち止められた先打ちコンクリートの
硬化後、上部打分け型枠を取り除き、ハーフPC床版の
上面に後打ちコンクリートをスラブコンクリート天端ま
で打設することにより、柱および梁の部分とスラブの部
分との各部分へ、それぞれ別種類のコンクリートを打分
けられるようにしている。[0013] Then, pre-cast concrete is poured to the top of the slab concrete at the column and the beam, and the pre-cast concrete is stopped at the boundary between the column and the beam and the slab by the punching formwork. After hardening, remove the upper parting formwork and place the post-cast concrete on the upper surface of the half-PC slab to the top of the slab concrete to separate the column and beam parts and the slab part respectively. We can make different types of concrete.
【0014】このような本発明のコンクリートの打設方
法によれば、ハーフPC床版の上面に打分け型枠を設置
するという簡単な作業で、コンクリートを打分けること
ができるので、スラブに高価な高強度コンクリートを無
駄に打設しなくてもよい。そのため、材料費の大きなコ
ストダウン効果が期待できる。また、柱や梁に高強度コ
ンクリートを用いても、スラブへの打設コンクリートに
普通コンクリートを用いることができる。そのため、こ
の普通コンクリートが高強度コンクリートに比べて施工
性が良いことから、省力化や施工費のコストダウンの効
果が付加されることとなる。さらに、打分け型枠におけ
る上部打分け型枠のクッション材によって、交差するス
ラブのスラブ上端筋と打分け用鉄筋トラスの上弦材との
交差部分も確実に塞ぐことができる。そのため、打分け
時における打設コンクリートの漏れを確実に防ぐことが
できる。 According to the concrete casting method of the present invention, concrete can be separated by a simple operation of installing a separate formwork on the upper surface of the half-PC floor slab. It is not necessary to use unnecessary high-strength concrete. Therefore, a large cost reduction effect of material costs can be expected. Further, even if high-strength concrete is used for columns and beams, ordinary concrete can be used for placing concrete on the slab. For this reason, since the ordinary concrete has a better workability than the high-strength concrete, the effect of labor saving and cost reduction of the construction cost is added. Furthermore, in the punching formwork
The crossing of the upper and lower
Between the upper slab of the slab and the upper chord of the truss truss
Intersections can be reliably closed. Because of that,
To prevent concrete leakage during casting
it can.
【0015】[0015]
【発明の実施の形態】以下、本発明の打分けられるよう
にしたコンクリートの打設方法を図示する実施形態によ
って説明する。BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a perspective view of a concrete casting method according to the present invention.
【0016】本発明のコンクリートの打設方法(図1参
照)は、建物(図示せず)の構築時において、柱1およ
び梁2の部分とスラブ3の部分との各部分へ、それぞれ
別種類のコンクリートを打設できるように、即ち、打分
けられるようにしたものである。The concrete casting method according to the present invention (see FIG. 1) is a method for constructing a building (not shown) in which each of the pillar 1 and the beam 2 and the slab 3 are separated from each other. In which concrete can be poured, that is, the concrete can be separated.
【0017】本発明の打設方法では、先ず、上面に鉄筋
トラス4が複数列突出しており、スラブ下部を構成する
ハーフPC床版5(図6参照)と、各鉄筋トラス4の上
端(上弦材6)にスラブ上端筋7を架け渡し配筋した後
において、ハーフPC床版5の上面に打設するスラブコ
ンクリート8(図5参照)とからなる合成床板により、
スラブ3を構成することとする。In the casting method according to the present invention, first, a plurality of rows of reinforcing trusses 4 protrude from the upper surface, and a half PC floor slab 5 (see FIG. 6) constituting the lower part of the slab and the upper end (upper chord) of each reinforcing truss 4. After the upper slab 7 of the slab is bridged over the material 6), the composite slab composed of the slab concrete 8 (see FIG. 5) cast on the upper surface of the half PC slab 5
The slab 3 is configured.
【0018】また、柱1および梁2の部分へ打設する先
打ちコンクリート9とスラブ3の部分へ打設する後打ち
コンクリート10とを仕切るために、ハーフPC床版5の
上面からスラブ上端筋7の下端までの間をラス網11で塞
ぐことができるように構成されており、除去せずにスラ
ブコンクリートの中に埋め込んでしまう下部打分け型枠
12と、この下部打分け型枠12の上部に載置することで、
スラブ上端筋7の下端からスラブコンクリート天端まで
の間を塞ぐことができるように構成されており、スラブ
用の後打ちコンクリート10の打設前に取り除く上部打分
け型枠13とから打分け型枠14を構成すると共に、この打
分け型枠14を柱1および梁2とスラブ3との境界部分
(打分け位置)であるハーフPC床版5の上面に設置す
ることとする。Further, in order to separate the precast concrete 9 to be cast into the column 1 and the beam 2 and the post-cast concrete 10 to be cast into the slab 3, the upper end of the slab from the upper surface of the half PC floor slab 5. The lower punching formwork is constructed so that the space up to the lower end of 7 can be closed by the lath net 11, and is embedded in the slab concrete without being removed.
12 and by placing it on the upper part of this lower punching formwork 12,
It is constructed so as to be able to close the space between the lower end of the upper slab upper end bar 7 and the top end of the slab concrete, and is separated from the upper punching formwork 13 which is removed before placing the post-cast concrete 10 for the slab. In addition to forming the frame 14, the punching formwork 14 is installed on the upper surface of the half PC floor slab 5, which is the boundary portion (the punching position) between the column 1 and the beam 2 and the slab 3.
【0019】そして、柱1および梁2の部分におけるス
ラブコンクリート天端レベルまでに、先打ちコンクリー
ト9を打設すると共に、打分け型枠14によって柱1およ
び梁2とスラブ3との境界部分で打ち止められた先打ち
コンクリート9の硬化後、上部打分け型枠13を取り除
き、ハーフPC床版5の上面に後打ちコンクリート10を
スラブコンクリート天端まで打設することにより、柱1
および梁2の部分とスラブ3の部分との各部分へ、それ
ぞれ別種類のコンクリートを打分けられるようにしてい
る。Then, pre-cast concrete 9 is poured to the top of the slab concrete at the column 1 and the beam 2 at the boundary between the column 1 and the beam 2 and the slab 3 by the punching formwork 14. After the hardened pre-cast concrete 9 is hardened, the upper parting formwork 13 is removed, and the post-cast concrete 10 is cast on the upper surface of the half-PC floor slab 5 to the top of the slab concrete, whereby the column 1
Also, different types of concrete can be punched into the beam 2 and the slab 3 respectively.
【0020】なお、柱1および梁2は、ハーフPCでも
現場打ちどちらでも良いが、この実施形態では梁現場打
ちとして説明する。また、この実施形態では、梁2とス
ラブ3との打分け状態について述べる。The column 1 and the beam 2 may be either half-PC or cast-in-place, but in this embodiment, the beam will be described as cast-in-place. Further, in this embodiment, a state in which the beam 2 and the slab 3 are separated from each other will be described.
【0021】この実施形態での打分け型枠14における下
部打分け型枠12(図7参照)は、スラブ3におけるハー
フPC床版5上面の梁2側端部に梁2延設方向へ延びる
状態で設けられており、上弦材15aの上端でスラブ上端
筋7を支持できる(図3参照)ように構成されている打
分け用鉄筋トラス15と、この打分け用鉄筋トラス15の一
方側(梁2側)において、ハーフPC床版5の上面から
スラブ上端筋7の下端(打分け用鉄筋トラス15の上弦材
15a)まで間に、コンクリート打ち止め用として取付け
られているラス網11とからなっている。The lower punching formwork 12 (see FIG. 7) of the punching formwork 14 in this embodiment extends in the beam 2 extension direction at the beam 2 side end of the upper surface of the half PC floor slab 5 in the slab 3. A reinforced truss 15 for punching, which is provided in a state and can support the upper slab reinforcement 7 at the upper end of the upper chord material 15a (see FIG. 3), and one side ( On the beam 2 side), from the upper surface of the half PC floor slab 5 to the lower end of the upper slab reinforcement 7 (the upper chord material of the reinforcing truss 15 for splitting)
Up to 15a), a lath net 11 is attached for concrete driving.
【0022】この下部打分け型枠12での打分け用鉄筋ト
ラス15は、図8に示すように、ハーフPC床板5に用い
られる鉄筋トラス4と同様の鉄筋トラスを用いたもので
ある。そして、図7に示したように、この鉄筋トラスの
一方側(梁2側)の斜側面(上弦材15aおよび下弦材15
bや斜材15c)に、ラス網11が点溶接されており、この
ラス網11がコンクリートの打ち止めの役を果たしてい
る。なお、このラス網11は、図7に示したように、その
上部が上弦材15aより高くならないようにすると共に、
その下部を下弦材15bの下端より数センチ長くしてお
き、ハーフPC床版5に馴染ませる。このハーフPC床
版5に馴染ませることは、ハーフPC床版5と下弦材15
bとの隙間からコンクリートが漏れるのを防ぐためであ
る。As shown in FIG. 8, the reinforcing bar truss 15 used in the lower punching formwork 12 uses the same reinforcing bar truss as the reinforcing bar truss 4 used for the half-PC floorboard 5. Then, as shown in FIG. 7, one side (the side of the beam 2) of the reinforcing bar truss (upper chord material 15a and lower chord material 15a).
The lath net 11 is spot-welded to the b and the diagonal members 15c), and the lath net 11 plays a role in stopping concrete. In addition, as shown in FIG. 7, the upper part of the lath net 11 does not become higher than the upper chord material 15a.
The lower part is made several centimeters longer than the lower end of the lower chord material 15b, and is adapted to the half PC floor slab 5. The half PC floor slab 5 and lower chord material 15
This is to prevent concrete from leaking from the gap with b.
【0023】このように、図示した実施形態での下部打
分け型枠12は、材質が全て鉄で出来ており、かつコンク
リートのかぶり厚さも確保されているので、スラブ3内
に打ちこまれてもスラブ3の性能上なんら問題はない。
この下部打分け型枠12は、現在市場にある材料を用いて
最も簡単に構成できる例である。なお、ここでの打分け
用鉄筋トラス15における上弦材15aの高さは、スラブ上
端筋7のスペーサーとなる高さである。また、この打分
け用鉄筋トラス15の別形態としては、鉄筋トラス4の斜
材を、図9に示すように、タイバー16に置き換えたもの
でも良い。即ち、この下部打分け型枠12としては、機能
的にコンクリートを止めるラス網11を点溶接等で固定で
き、ラス網11にかかるコンクリートの圧を受け止めるこ
とができる安定した状態で、かつ上部打分け型枠13を重
ねるための上弦材15aがあれば良い。As described above, since the lower punching formwork 12 in the illustrated embodiment is entirely made of iron and has a sufficient cover thickness of concrete, it is driven into the slab 3. There is no problem on the performance of the slab 3.
The lower punching formwork 12 is an example which can be most easily formed by using a material currently on the market. Here, the height of the upper chord material 15a in the perforated reinforcing bar truss 15 is a height serving as a spacer for the upper slab reinforcement 7. Further, as another form of the reinforcing bar truss 15 for punching, as shown in FIG. 9, a tie bar 16 may be used in place of the diagonal member of the reinforcing bar truss 4. That is, as the lower punching formwork 12, a lath net 11 for functionally stopping the concrete can be fixed by spot welding or the like, and the pressure of the concrete applied to the lath net 11 can be received in a stable state, and the upper die What is necessary is just to have the upper chord material 15a for stacking the divided formwork 13.
【0024】また、この実施形態での打分け型枠14にお
ける上部打分け型枠13は、図10および図11に示すよう
に、梁2の延設方向へ延びる桟木17と、この桟木17の下
面に張り付けられているクッション材18とからなってお
り、図4に示すように、下部打分け型枠12の上部に取付
けた時に、クッション材18が、スラブ上端筋7の周表面
および打分け用鉄筋トラス15における上弦材15aの上面
へ密接できるように構成されている。ここでの桟木17の
下面に張付けられているクッション材18は、非常に柔ら
かいスポンジ状の、例えば、高発砲ポリエチレンフォー
ム等から構成されている。なお、この桟木17の高さH
(図10参照)はスラブ上端筋7のかぶり厚さL(図4参
照)以上であると共に、クッション材18の厚さD(図10
参照)はおよそスラブ上端筋7の径の二倍強である。こ
のクッション材18の厚さDは、図12に示すように、桟木
17と打分け用鉄筋トラス15の上弦材15aとの間である程
度圧縮されても、スラブ上端筋7の部分からコンクリー
トが漏れない厚さである。Further, as shown in FIGS. 10 and 11, an upper punching formwork 13 of the punching formwork 14 in this embodiment includes a crosspiece 17 extending in the direction in which the beam 2 extends, and a crosspiece 17 of this crosspiece 17. As shown in FIG. 4, when the cushioning member 18 is attached to the upper portion of the lower punching formwork 12, the cushioning member 18 is attached to the peripheral surface of the upper slab 7 and punching out. It is configured so that it can be in close contact with the upper surface of the upper chord material 15a of the reinforcing steel truss 15. The cushion material 18 attached to the lower surface of the crosspiece 17 here is formed of a very soft sponge-like, for example, polyethylene foam having a high foaming property. In addition, the height H of this pier 17
10 (see FIG. 10) is equal to or greater than the cover thickness L (see FIG. 4) of the upper slab 7 and the thickness D of the cushion material 18 (see FIG. 10).
) Is about twice the diameter of the upper slab muscle 7. As shown in FIG. 12, the thickness D of the cushion
Even if it is compressed to some extent between the chord member 17 and the upper chord material 15a of the reinforcing steel truss 15, the thickness is such that the concrete does not leak from the slab upper end bar 7.
【0025】このようなに下部打分け型枠12および上部
打分け型枠13を打分け型枠14として用いれば、クッショ
ン材18が打分け用鉄筋トラス15における上弦材15aの上
面へ密接することにより、桟木17やラス網11と共に、柱
1および梁2の部分とスラブ3の部分とを確実に仕切る
ことができる。また、打分け用鉄筋トラス15とラス網11
および桟木17とクッション材18というように比較的安価
な材料を使って打分け型枠14を構成することができる。When the lower punching formwork 12 and the upper punching formwork 13 are used as the punching formwork 14 as described above, the cushion member 18 can be brought into close contact with the upper surface of the upper chord material 15a in the punching reinforcing truss 15. Thereby, together with the crosspiece 17 and the lath net 11, the column 1 and the beam 2 and the slab 3 can be reliably partitioned. In addition, rebar truss 15 and lath net 11
In addition, the punching formwork 14 can be formed by using relatively inexpensive materials such as the crosspiece 17 and the cushion material 18.
【0026】このような構成からなる本発明の打設方法
を用いて、柱1および梁2の部分とスラブ3の部分へコ
ンクリートを打設するには、次に述べるようにして行
う。Using the casting method of the present invention having such a configuration, concrete is poured into the column 1 and the beam 2 and the slab 3 as follows.
【0027】先ず、図2に示すように、梁型枠19にハー
フPC床版5を設置後、スラブ上端筋7の配筋に先立
ち、梁2とスラブ3との境目位置であるハーフPC床版
5の端部上面に、下部打分け型枠12を設置する。この下
部打分け型枠12の設置は、数メーターの長さの打分け用
鉄筋トラス15をスラブ3の幅方向(梁2の長手方向)へ
複数個並べて(図示せず)行うが、梁2と平行でかつ隣
接するラス網11に隙間ができないように並べると共に、
必要に応じて隣接するラス網11または鉄筋同志(上弦材
15aおよび下弦材15bや斜材15c)を結束する。そし
て、その後、図3に示すように、この下部打分け型枠12
をもスペーサーとして利用し、スラブ上端筋7を配筋す
ると共に、スラブ上端筋7と下部打分け型枠12の上弦材
15aと結束する。First, as shown in FIG. 2, after the half-PC floor slab 5 is installed on the beam formwork 19, prior to the arrangement of the upper slab 7 of the slab, the half-PC floor, which is the boundary position between the beam 2 and the slab 3, is provided. On the upper surface of the end of the plate 5, a lower punching formwork 12 is installed. The lower punching formwork 12 is installed (not shown) by arranging a plurality of punching reinforcing trusses 15 having a length of several meters in the width direction of the slab 3 (longitudinal direction of the beam 2). And in parallel so that there is no gap in the adjacent lath net 11,
Adjacent lath net 11 or rebars (upper chord if necessary)
15a and the lower chord material 15b and the diagonal material 15c) are bound. Then, as shown in FIG.
Is also used as a spacer, and the upper slab upper muscle 7 is arranged, and the upper chord material of the slab upper muscle 7 and the lower punching formwork 12 are arranged.
Unite with 15a.
【0028】次に、下部打分け型枠12の上に、図3およ
び図1に示すように、上部打分け型枠13をそのクッショ
ン材18が下になるようにして重ねる。ただし、下部打分
け型枠12の上にはこれに直交するスラブ上端筋7がある
ので、上部打分け型枠13の重量はスラブ上端筋7で支え
られる。また、クッション材18は、図1および図12に示
すように、桟木17の自重によりスラブ上端筋7で大きく
圧縮されると共に、打分け用鉄筋トラス15の上弦材15a
では少し圧縮される。そして、その後、この上部打分け
型枠13とスラブ上端筋7とを、図1に示すように、結束
線20で互いに結束することで、打分け型枠14が完成す
る。その後、柱1まわりについても同様のことを行う。
なお、前述した梁2と直交する方向の梁2まわりではス
ラブ上端筋7のレベルが異なるので、下部打分け型枠12
の高さおよび上部打分け型枠13の桟木17の高さHは異な
ってくる。即ち、二種類必要となる。Next, as shown in FIGS. 3 and 1, an upper punching mold 13 is placed on the lower punching mold 12 with the cushion material 18 facing down. However, since the upper punching slab 7 is perpendicular to the lower punching mold 12, the weight of the upper punching rim 13 is supported by the upper slab reinforcing bar 7. Also, as shown in FIGS. 1 and 12, the cushion material 18 is greatly compressed by the upper end muscle 7 of the slab due to the weight of the crosspiece 17, and the upper chord material 15a of the reinforcing steel truss 15 for punching is used.
Then it is compressed a little. Then, the upper punching formwork 13 and the upper slab upper end liner 7 are bound together by a binding wire 20, as shown in FIG. After that, the same is performed for the column 1.
Since the level of the upper slab 7 is different around the beam 2 in a direction orthogonal to the beam 2 described above, the lower punching form 12
And the height H of the pier 17 of the upper blanking formwork 13 differ. That is, two types are required.
【0029】次に、図4に示すように、柱1および梁2
の部分へ高強度コンクリートを打設すると共に、この先
打ちコンクリート9がある程度硬化した(柱1および梁
2を形成した)時点で、上部打分け型枠13とスラブ上端
筋7とを結束している結束線20を切り、上部打分け型枠
13を取外す(図5参照)。その後、図5に示すように、
ハーフPC床版5の上面に、後打ちコンクリート10(ス
ラブコンクリート8)を打設して、スラブ3を形成す
る。そして、このような非常に簡単である上部打分け型
枠13の取外し作業によって、後打ちコンクリート、即
ち、スラブ用の普通コンクリートの打設にかかる事がて
きる。即ち、簡単な打分け型枠14の設置作業や打分け型
枠14における上部打分け型枠13の短時間でかつ簡単な取
外し作業によって、後打ちコンクリート10(普通コンク
リート)を先打ちコンクリート9(高強度コンクリー
ト)の打設に続き連続して打てることとなる。Next, as shown in FIG.
The high-strength concrete is poured into the above-mentioned portion, and when the pre-cast concrete 9 has hardened to some extent (the columns 1 and the beams 2 have been formed), the upper-parting formwork 13 and the slab upper-end reinforcement 7 are bound. Cut the binding wire 20 and form the upper part
Remove 13 (see Fig. 5). Then, as shown in FIG.
A slab 3 is formed by placing a post-cast concrete 10 (slab concrete 8) on the upper surface of the half PC floor slab 5. Then, by such a very simple operation of removing the upper punching formwork 13, it is possible to start placing of post-cast concrete, that is, ordinary concrete for slabs. That is, the short and simple detaching of the top casting divided mold 13 in installation work and punch divided formwork 14 simple punch divided formwork 14, post-deposited concrete 10 (usually concrete) ahead hit concrete 9 ( High-strength concrete) can be continuously cast after casting.
【0030】このような本発明におけるコンクリートの
打設方法によれば、打分け型枠14を使用することによ
り、柱1および梁2の部分とスラブ3の部分とにそれぞ
れ別種類のコンクリートを打設することができる。しか
も、比較的安価な材料を使い、下部打分け型枠12および
上部打分け型枠13からなる打分け型枠14を製作できると
共に、打分け型枠14を設置後に上部打分け型枠13を取外
すという簡単な作業でコンクリートを打分けることがで
きる。そのため、スラブ3に高価な高強度コンクリート
を無駄に打たなくてもよいので、材料費の大きなコスト
ダウン効果が期待できる。また、スラブ3のコンクリー
トとしては普通コンクリートを打設することができるの
で、高強度コンクリートに比べて、施工性が良くなると
共に、省力化や施工費のコストダウンの効果が付加され
ることとなる。さらに、打分け型枠14における上部打分
け型枠13のクッション材18によって、交差するスラブ3
のスラブ上端筋7と打分け用鉄筋トラス15の上弦材15a
との交差部分も確実に塞ぐことが出来て、打分け時にお
ける打設コンクリートの漏れを確実に防ぐことができ
る。 According to the concrete casting method of the present invention, different types of concrete are respectively cast on the column 1 and the beam 2 and the slab 3 by using the split formwork 14. Can be set up. Moreover, using a relatively inexpensive material, a punching formwork 14 comprising a lower punching formwork 12 and an upper punching formwork 13 can be manufactured. The concrete can be separated by the simple task of removal. For this reason, it is not necessary to waste expensive high-strength concrete on the slab 3, and a large cost reduction in material costs can be expected. Moreover , since concrete can be cast as the concrete of the slab 3, the workability is improved as compared with high-strength concrete, and the effect of labor saving and cost reduction of construction cost is added. . Furthermore, the upper batting in the batting formwork 14
The slab 3 that intersects with the cushioning material 18 of the
Upper chord material 15a of truss 15 for slab and truss 15 for punching
Can be securely closed at the intersection with
Can reliably prevent the concrete from leaking.
You.
【0031】[0031]
【発明の効果】この発明によれば、ハーフPC床版の上
面に打分け型枠を設置すると共に、その上部打分け型枠
を取外すという簡単な作業で、柱および梁の部分とスラ
ブの部分とに別種類のコンクリートを打分けることがで
きるので、スラブにまでも高価な高強度コンクリートを
打設しなくてもよくなる。そのため、大きな応力が加わ
る部分だけに必要な高強度コンクリートを、全ての部分
に打設してしまうというような無駄を無くすことができ
て、材料費の大きなコストダウン効果を期待することが
できる。According to the present invention, the punching formwork is installed on the upper surface of the half PC floor slab, and the upper punching formwork is removed. Since it is possible to separate different types of concrete, it is not necessary to cast expensive high-strength concrete even on the slab. Therefore, it is possible to eliminate waste such as casting high-strength concrete necessary only for a portion to which a large stress is applied to all portions, and to expect a large cost reduction effect on material costs.
【0032】また、この発明によれば、打分け型枠で打
分けられることにより、柱や梁に高強度コンクリートを
用いても、スラブへの打設コンクリートに普通コンクリ
ートを用いることができる。そのため、この普通コンク
リートが高強度コンクリートに比べて施工性が良いこと
から、省力化や施工費のコストダウンの効果も付加され
ることとなる。さらに、この発明によれば、打分け型枠
における上部打分け型枠のクッション材によって、交差
するスラブのスラブ上端筋と打分け用鉄筋トラスの上弦
材との交差部分も確実に塞ぐことができる。そのため、
打分け時における打設コンクリートの漏れを確実に防ぐ
ことができる。 Further, according to the present invention, the concrete can be cast in the slab, even if high-strength concrete is used for the columns and beams, by being punched by the punching formwork. Therefore, the workability of the ordinary concrete is higher than that of the high-strength concrete, so that the effects of labor saving and reduction of construction cost are also added. Furthermore, according to the present invention, the punching formwork
By the cushioning material of the top punching formwork in
Upper slab and upper chord of truss truss
The intersection with the material can be reliably closed. for that reason,
Prevents concrete concrete leakage during casting
be able to.
【図1】この発明の打分けられるようにしたコンクリー
トの打設方法を示す概略図である。FIG. 1 is a schematic view showing a method for placing concrete according to the present invention so that it can be separated.
【図2】この発明の打設方法を用いて行う、コンクリー
トの打分け工程を示す概略図である。FIG. 2 is a schematic diagram showing a concrete separating process performed using the casting method of the present invention.
【図3】この発明の打設方法を用いて行う、コンクリー
トの打分け工程を示す概略図である。FIG. 3 is a schematic view showing a concrete separating process performed using the casting method of the present invention.
【図4】この発明の打設方法を用いて行う、コンクリー
トの打分け工程を示す概略図である。FIG. 4 is a schematic view showing a concrete separating process performed using the casting method of the present invention.
【図5】この発明の打設方法を用いて行う、コンクリー
トの打分け工程を示す概略図である。FIG. 5 is a schematic view showing a concrete separating process performed using the casting method of the present invention.
【図6】この発明の打設方法で用いるハーフPC床版を
示す概略図である。FIG. 6 is a schematic view showing a half PC floor slab used in the casting method of the present invention.
【図7】この発明の打設方法で用いる打分け型枠の下部
打分け型枠を示す概略拡大図である。FIG. 7 is a schematic enlarged view showing a lower punching formwork of the punching formwork used in the casting method of the present invention.
【図8】この発明の打設方法で用いる打分け型枠の下部
打分け型枠における打分け用鉄筋トラスを示す斜視図で
ある。FIG. 8 is a perspective view showing a rebar truss for punching in the lower punching formwork of the punching formwork used in the casting method of the present invention.
【図9】この発明の打設方法で用いる打分け型枠の下部
打分け型枠における打分け用鉄筋トラスの別形態を示す
斜視図である。FIG. 9 is a perspective view showing another form of the reinforcing truss for punching in the lower punching formwork of the punching formwork used in the casting method of the present invention.
【図10】この発明の打設方法で用いる打分け型枠の上
部打分け型枠を、下部打分け型枠上へ設置する状態を示
す概略拡大図である。FIG. 10 is a schematic enlarged view showing a state where an upper punching formwork of the punching formwork used in the casting method of the present invention is set on a lower punching formwork.
【図11】図10のA−A線矢視図である。FIG. 11 is a view taken in the direction of arrows AA in FIG. 10;
【図12】この発明の打設方法で用いる打分け型枠の上
部打分け型枠を、下部打分け型枠上へ押し付けた状態を
示す概略図である。FIG. 12 is a schematic diagram showing a state in which an upper punching formwork of the punching formwork used in the casting method of the present invention is pressed onto a lower punching formwork.
【図13】従来の打分け型枠を示すす概略図である。FIG. 13 is a schematic diagram showing a conventional punching formwork.
【図14】従来の打分け型枠を示す概略図である。FIG. 14 is a schematic view showing a conventional punching formwork.
【図15】従来の打分け型枠を示す概略図である。FIG. 15 is a schematic view showing a conventional punching formwork.
1…柱、2…梁、3…スラブ、4…鉄筋トラス、5…ハ
ーフPC床版、6…上弦材、7…スラブ上端筋、8…ス
ラブコンクリート、9…先打ちコンクリート、10…後打
ちコンクリート、11…ラス網、12…下部打分け型枠、13
…上部打分け型枠、14…打分け型枠、15…打分け用鉄筋
トラス、15a…上弦材、15b…下弦材、15c…斜材、16
…タイバー、17…桟木、18…クッション材、19…梁型
枠、20…結束線。DESCRIPTION OF SYMBOLS 1 ... pillar, 2 ... beam, 3 ... slab, 4 ... steel truss, 5 ... half PC floor slab, 6 ... upper chord material, 7 ... upper slab reinforcement, 8 ... slab concrete, 9 ... pre-cast concrete, 10 ... post-cast Concrete, 11 ... lath net, 12 ... lower formwork, 13
... upper punching formwork, 14 ... punching formwork, 15 ... punching rebar truss, 15a ... upper chord material, 15b ... lower chord material, 15c ... diagonal material, 16
... tie bars, 17 ... piers, 18 ... cushioning materials, 19 ... beam forms, 20 ... binding wires.
Claims (1)
分とスラブの部分との各部分へ、それぞれ別種類のコン
クリートを打設できるようにしたコンクリートの打設方
法であり、 先ず、前記スラブは、上面に鉄筋トラスが複数列突出し
ており、スラブ下部を構成するハーフPC床版と、前記
各鉄筋トラスの上端にスラブ上端筋を架け渡し配筋した
後において、ハーフPC床版の上面に打設するスラブコ
ンクリートとからなる合成床板とし、 また、前記柱および梁の部分へ打設する先打ちコンクリ
ートと前記スラブの部分へ打設する後打ちコンクリート
である前記スラブコンクリートとを仕切るために、前記
ハーフPC床版の上面から前記スラブ上端筋の下端まで
の間をラス網で塞ぐことができるように構成されてお
り、除去せずに前記スラブコンクリートの中に埋め込ん
でしまう下部打分け型枠と、この下部打分け型枠の上部
に載置することで、スラブ上端筋の下端からスラブコン
クリート天端までの間を塞ぐことができるように構成さ
れており、前記スラブ用の後打ちコンクリートの打設前
に取り除く上部打分け型枠とからなる打分け型枠を、柱
および梁とスラブとの境界部分の打分け位置であるハー
フPC床版の上面に設置することとし、さらに、前記打分け型枠における下部打分け型枠は、前
記スラブにおけるハーフPC床版上面の前記梁側端部に
前記梁延設方向へ延びる状態で設けられており、上弦材
の上端で前記スラブ上端筋を支持できるように構成され
ている打分け用鉄筋トラスと、この打分け用鉄筋トラス
の前記梁側に取付けて、前記ハーフPC床版の上面から
前記スラブ上端筋の下端までの間を塞いで、コンクリー
ト打ち止め用としているラス網とからなり、 前記打分け型枠における上部打分け型枠は、前記梁の延
設方向へ延びる桟木と、この桟木の下面に張り付けられ
ているクッション材とからなっており、前記下部打分け
型枠の上部に取付けた時に、前記クッション材が圧縮し
て、前記スラブ上端筋の周表面および前記打分け用鉄筋
トラスにおける上弦材の上面へ密接できるように構成す
ることとし、 そして、前記柱および梁の部分における前記スラブコン
クリート天端レベルまでに、前記先打ちコンクリートを
打設すると共に、前記打分け型枠によって柱および梁と
スラブとの境界部分で打ち止められた先打ちコンクリー
トの硬化後、前記上部打分け型枠を取り除き、前記ハー
フPC床版の上面に後打ちコンクリートをスラブコンク
リート天端まで打設することにより、柱および梁の部分
とスラブの部分との各部分へ、それぞれ別種類のコンク
リートを打分けられるようにしたことを特徴とする打分
けられるようにしたコンクリートの打設方法。1. A method of placing concrete in which different types of concrete can be poured into each of a column and a beam and a slab during construction of a building. In the upper surface of the half-PC floor slab, a plurality of rows of reinforced trusses protrude from the upper surface, and after arranging a half-PC slab constituting the lower part of the slab and the upper-end slab over the upper end of each of the reinforced trusses. A composite floorboard made of slab concrete to be cast, and a pre-cast concrete to be cast into the column and the beam and a post-cast concrete to be cast into the slab
To partition the said slab concrete is, the are from the top surface of the half PC slab is constructed to be able to close the until the lower end of the slab upper muscles lath, the slab without removing A lower parting form that is embedded in concrete and a structure that can be closed from the lower end of the upper slab top to the top of the slab concrete by placing it on top of this lower parting form. are half PC floor top casting divided mold consisting of a punch divided mold to remove the striking設前the post-deposited concrete for the slabs, a droplet split position location of a boundary portion between the pillars and beams and slabs It is to be installed on the upper surface of the plate, and further, the lower punching formwork in the punching formwork is
At the beam side end of the half PC floor slab in the slab
The upper chord material is provided so as to extend in the beam extending direction.
The upper end of the slab is configured to support the upper muscle
Punching reinforcing truss and the punching reinforcing truss
From the upper surface of the half PC floor slab
Cover the space between the upper slab upper muscle and the lower
And the upper punching formwork in the punching formwork is an extension of the beam.
A pier that extends in the direction of installation, and
The cushioning material is made of
When mounted on top of the formwork, the cushioning material compresses
A peripheral surface of the upper end bar of the slab and the reinforcing bar for punching;
The truss should be configured so that it can be in close contact with the upper surface of the upper chord.
The pre-cast concrete is poured into the slab concrete top level at the column and beam portions, and is stopped at the boundary between the column and beam and the slab by the punching formwork. After the hardening of the precast concrete, the upper punching formwork is removed, and the postcast concrete is cast on the upper surface of the half PC floor slab to the top of the slab concrete, so that the column and beam portions and the slab portion are formed. A method of placing concrete in which different types of concrete can be driven into the respective parts.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP8204617A JP3047817B2 (en) | 1996-08-02 | 1996-08-02 | Method of placing concrete so that it can be separated |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP8204617A JP3047817B2 (en) | 1996-08-02 | 1996-08-02 | Method of placing concrete so that it can be separated |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH1046814A JPH1046814A (en) | 1998-02-17 |
JP3047817B2 true JP3047817B2 (en) | 2000-06-05 |
Family
ID=16493451
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP8204617A Expired - Lifetime JP3047817B2 (en) | 1996-08-02 | 1996-08-02 | Method of placing concrete so that it can be separated |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3047817B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2016087175A (en) * | 2014-11-06 | 2016-05-23 | 株式会社Naテック | Bedding, manufacturing method of bedding, and band |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100408483B1 (en) * | 2001-02-16 | 2003-12-06 | 삼성중공업 주식회사 | Construction method for apartment's ceiling slab |
CN102587655B (en) * | 2012-02-29 | 2015-01-21 | 福建名成集团有限公司 | Floor slab mounting equipment for high-rise building and method for pouring and mounting floor slabs |
-
1996
- 1996-08-02 JP JP8204617A patent/JP3047817B2/en not_active Expired - Lifetime
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2016087175A (en) * | 2014-11-06 | 2016-05-23 | 株式会社Naテック | Bedding, manufacturing method of bedding, and band |
Also Published As
Publication number | Publication date |
---|---|
JPH1046814A (en) | 1998-02-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP1347121A3 (en) | Construction method and system | |
JP3047817B2 (en) | Method of placing concrete so that it can be separated | |
JP2915897B1 (en) | Building construction method | |
JPH0579049A (en) | Constructing method for beam and slab in underground body construction work | |
JP3707006B2 (en) | New method for opening openings in existing masonry walls | |
KR100694824B1 (en) | Deck plate for reinforced concrete structure and structure construction method thereof | |
JP4404263B2 (en) | Concrete jointing method | |
JPH09221706A (en) | Floor slab for road surface and layout method thereof | |
JP3299596B2 (en) | Construction method of reinforced concrete retaining wall using large precast plate. | |
JP2000356041A (en) | Method for placing concrete | |
JP3406502B2 (en) | Glue construction method and formwork | |
CN215406927U (en) | Assembled concrete column | |
JPH06299718A (en) | Construction of wall, floor in atomic power plant and wall slab thereof | |
JP2707966B2 (en) | Floor construction method using prestressed concrete plate as beam-side formwork | |
JP2001090226A (en) | Reinforced concrete earthquake-resistant construction | |
JPH08253909A (en) | Ferroconcrete floor slab for bridge and form therefor | |
JPS59114313A (en) | Construction of prestressed concrete floor panel in road bridge | |
JP2904648B2 (en) | Construction method of earthquake-resistant wall using PC version | |
JP2643760B2 (en) | How to build foundation beams | |
JPH111983A (en) | Construction method for construction slab and bridge floor plate, and construction plate for concrete placement | |
JPH06228916A (en) | Strut of elevated bridge, etc., and construction method thereof | |
CN117403778A (en) | Assembled hollow sandwich plate structure and construction method thereof | |
JPH0634494Y2 (en) | Flat slab pillar structure | |
JP2651506B2 (en) | How to apply underground beams | |
JPH01223248A (en) | Folded plate unit slab construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20000222 |