JP2640928B2 - A crane that can assemble and disassemble small towers - Google Patents
A crane that can assemble and disassemble small towersInfo
- Publication number
- JP2640928B2 JP2640928B2 JP18228295A JP18228295A JP2640928B2 JP 2640928 B2 JP2640928 B2 JP 2640928B2 JP 18228295 A JP18228295 A JP 18228295A JP 18228295 A JP18228295 A JP 18228295A JP 2640928 B2 JP2640928 B2 JP 2640928B2
- Authority
- JP
- Japan
- Prior art keywords
- tower
- boom
- crane
- mast
- tip
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Jib Cranes (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は、鉄塔建設をクレーンに
て行う装置に関するものである。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an apparatus for constructing a steel tower with a crane.
【0002】[0002]
【従来の技術】従来の鉄塔建設用タワーマストにおいて
は、鉄塔頂部を構築し、又は鉄塔頂部を解体する場合、
鉄塔の外側に押上げ式リフトアップ装置(クライミング
装置)を配設し、タワーマストの上方支持部にブームの
基部を軸着し、ブームの先端部に吊り下げたタワー部材
をタワーマストの回りにおいて組立、又は組立てられた
タワー部材を解体することができる(特開5−2866
94号公報)。しかし乍ら、鉄塔の頂部の三角錐形塔部
を組立てようとしてもブームが邪魔をして鉄塔の中心部
に三角錐形塔部の中心部を移動して積み重ねることがで
きない。又、地上で組立てられた鉄塔の三角錐形塔部を
解体しないで取外すことが困難であって、三角錐形の鉄
塔頂部を解体して組立てたり、解体するのにブームの先
端部の吊り下げにボルトナット等を緩めて三角錐形塔部
を鉄塔より分解し、分解した部材をそれぞれ処理して加
工しなければならず、その組立及び分解作業に長時間と
多人数の人手を要し、作業能率が悪い欠点があった。2. Description of the Related Art In a conventional tower mast for construction of a tower, when a tower top is constructed or dismantled,
A push-up type lift-up device (climbing device) is installed outside the tower, and the base of the boom is pivotally mounted on the upper support of the tower mast, and the tower member suspended at the tip of the boom is placed around the tower mast. The assembled or assembled tower member can be disassembled (Japanese Patent Laid-Open No. 5-2866).
No. 94). However, even when attempting to assemble the triangular pyramid tower at the top of the tower, the boom hinders the movement of the center of the triangular pyramid tower to the center of the tower and cannot be stacked. In addition, it is difficult to remove the triangular pyramid tower section of the tower assembled on the ground without dismantling it, and it is necessary to suspend the top of the boom to disassemble and assemble or dismantle the top of the triangular pyramid tower. The bolts and nuts must be loosened to dismantle the triangular pyramid tower from the steel tower, and the disassembled members must be processed and processed, and the assembly and disassembly work requires a long time and a large number of people, There was a drawback that work efficiency was poor.
【0003】[0003]
【発明が解決しようとする課題】本発明は前記従来の欠
点を無くすために、鉄塔の頂部の三角錐形塔部をブーム
をタワーの中心より後方に倒すことができるように構成
すると共に、ブームの先端部に回動するように軸着し、
その軸着部を中心として前方に倒せるように補助ブーム
を配設する。SUMMARY OF THE INVENTION In order to obviate the above-mentioned drawbacks, the present invention comprises a triangular pyramid tower at the top of a steel tower so that the boom can be tilted backward from the center of the tower. Pivotally attached to the tip of the
An auxiliary boom is provided so that the auxiliary boom can be tilted forward around the shaft attachment portion.
【0004】[0004]
【課題を解決するための手段】タワーマストの上方支持
部に基部を軸着されたブームは、軸着部を中心としてタ
ワーマストの縦軸よりも後方に倒すことができ、且つこ
のブームの先端部に垂直に立て、及び前方に倒せるよう
に基部を軸止した補助ブームを具備することにより、鉄
塔の中心部にタワーマストを配設して、補助ブームにて
鉄塔の三角錐形塔部材を鉄塔の上端部に載置固定し、又
は鉄塔の上端部に載置固定された鉄塔の三角錐形塔部材
を補助ブームにて鉄塔の上端部より引き降し、鉄塔より
分解することができるように構成したものである。A boom whose base is pivotally mounted on the upper support portion of the tower mast can be tilted rearward of the vertical axis of the tower mast with the shaft mounting portion as the center, and the tip of the boom can be tilted. By installing an auxiliary boom that has its base fixed to the part vertically and can be tilted forward, a tower mast is arranged at the center of the tower, and the triangular pyramid tower member of the tower is installed with the auxiliary boom. The triangular pyramid-shaped tower member placed and fixed on the upper end of the tower or fixed on the upper end of the tower can be pulled down from the upper end of the tower with the auxiliary boom and disassembled from the tower. It is what was constituted.
【0005】[0005]
【作用】ブームを直立状態にした時、平面寸法がタワー
マストと同一以下であるために、降下時の寸法がタワー
マスト分の鉄塔に空隙があるから降下後ブームを解体が
でき、小さな鉄塔の内部にクレーン駆動装置を設けて嵩
上げ、せり上げして、鉄塔の組立が可能であり、クレー
ンの駆動装置をタワーマスト内に収納して、小さな鉄塔
内においてタワーマストの組立てを行い、且つ分解を行
い、鉄塔の組立てを同時に行うことができる。[Function] When the boom is in the upright state, the plane dimensions are the same as or smaller than the tower mast, so the dimensions at the time of descent have a gap in the tower for the tower mast. It is possible to assemble a steel tower by raising and raising a crane drive device inside, storing the drive device of the crane in the tower mast, assembling the tower mast in a small steel tower, and disassembling. The tower can be assembled at the same time.
【0006】[0006]
【実施例】図面を参照しながら、本発明を説明する。図
1は一部を欠如して示す正面図、図2はブームを直立し
た状態の側面図、図3は図1の横断面図である。Aは送
電線路方向の強度とこれに直角方向の強度とが等しいよ
うに設計された四面同形の鉄塔である。Bは、この鉄塔
Aの頂部に載架固定した三角錐形の鉄塔頂部である。C
1 ,C2 ,C3 は鉄塔Aの上部、中央部及び下部に横架
した送電線支持部材である。1は鉄塔Aの中心部に下部
から上部に亘って嵩上げ又はせり上げして配設したタワ
ーマストである。2は上部の鉄塔構成部材aに軸3にて
基部5を軸着したブームであって、タワーマストの構成
部材10とブーム2との間に油圧シリンダ12を介在さ
せ、油圧シリンダ11をクレーン駆動装置4にて往動又
は復動してブーム2を立ち上げ又は倒伏する(図1、図
2)。ブーム2を垂直に立ち上げ、更に後方に倒す(図
1)と、ブーム2の中間部は三角錐形の鉄塔頂部Bを越
えて停止する(図1の鎖線の位置)。DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described with reference to the drawings. 1 is a front view showing a part of the boom, FIG. 2 is a side view of the boom in an upright state, and FIG. 3 is a cross-sectional view of FIG. A is a four-sided steel tower designed so that the strength in the direction of the transmission line and the strength in the direction perpendicular thereto are equal. B is a triangular pyramid-shaped tower top mounted and fixed on the top of the tower A. C
Reference numerals 1 , C 2 , and C 3 denote transmission line support members that lie on the upper, central, and lower portions of the tower A. Reference numeral 1 denotes a tower mast which is disposed at the center of the tower A from the lower part to the upper part by raising or raising the tower. Reference numeral 2 denotes a boom in which a base 5 is axially mounted on an upper steel tower component a with a shaft 3. A hydraulic cylinder 12 is interposed between the tower mast component 10 and the boom 2, and the hydraulic cylinder 11 is driven by a crane. The device 4 moves forward or backward to raise or lower the boom 2 (FIGS. 1 and 2). When the boom 2 is raised vertically and tilted further backward (FIG. 1), the middle part of the boom 2 stops beyond the top B of the triangular pyramid tower (the position of the chain line in FIG. 1).
【0007】ブーム2の先端部には補助ブーム6が第2
軸7にて軸着されており、ブーム2と補助ブーム6の間
に第2油圧シリンダ12が配設されており、補助ブーム
6の先端部には三角錐形の鉄塔頂部Bを吊り下げるフッ
ク8がワイヤ9にて吊り下げてある。An auxiliary boom 6 is provided at the tip of the boom 2
A second hydraulic cylinder 12 is disposed between the boom 2 and the auxiliary boom 6, and a hook for suspending the top B of the triangular pyramid-shaped tower is provided at the tip of the auxiliary boom 6. 8 is suspended by a wire 9.
【0008】ブーム2を垂直位置から更に後方に倒し
て、補助ブーム6を前方に屈伏して補助ブーム6の先端
部を鉄塔Aの中心部に配設して、ブーム2と補助ブーム
6とにて懐形空間部13をつくる。ここで補助ブーム6
の先端部にフック8を設けたワイヤロープ9にて三角錐
形の鉄塔頂部Bを図1に示すように吊り下げて、三角錐
形の鉄塔頂部Bを鉄塔Aの上端部に載置固定する。前記
と反対に三角錐形の鉄塔頂部Bを鉄塔Aから取り外す時
は、図1においてブーム2の上端部において補助ブーム
6とブーム2とがく字形に屈曲して形成され、懐形空間
部13を形成しているから、三角錐形の鉄塔頂部Bはブ
ーム2にて邪魔されることなく、ワイヤロープ9にて吊
り上げることができる。The boom 2 is tilted further backward from the vertical position, the auxiliary boom 6 is bent forward, and the tip of the auxiliary boom 6 is disposed at the center of the tower A. To create a pocket-shaped space 13. Here the auxiliary boom 6
The top portion B of the triangular pyramid is hung as shown in FIG. 1 by a wire rope 9 provided with a hook 8 at the end of the tower, and the top B of the triangular pyramid is placed and fixed on the upper end of the tower A. . When the top B of the triangular pyramid is removed from the tower A, the auxiliary boom 6 and the boom 2 are bent at the upper end of the boom 2 in FIG. Since it is formed, the triangular pyramid-shaped tower top B can be lifted by the wire rope 9 without being disturbed by the boom 2.
【0009】三角錐形の鉄塔頂部Bを鉄塔Aの上端部よ
り取り外した後、ブーム2を油圧シリンダ11にて垂直
に直し補助ブーム6を第2油圧シリンダ12を作動して
垂直に直して、タワーマスト1の下段のブロックより鉄
塔Aの外方に順次取り出し、最後にブーム2及び補助ブ
ーム6を鉄塔Aより外方に取り出す。14はタワーマス
トの基部に設けた押上げ式リフトアップ装置(クライミ
ング装置)であって、鉄塔Aの組立及び分解を行うもの
である。After the top B of the triangular pyramid-shaped tower is removed from the upper end of the tower A, the boom 2 is straightened vertically by the hydraulic cylinder 11, and the auxiliary boom 6 is straightened vertically by operating the second hydraulic cylinder 12. The boom 2 and the auxiliary boom 6 are finally taken out of the tower A from the lower block of the tower mast 1 to the outside of the tower A. Reference numeral 14 denotes a lifting type lift-up device (climbing device) provided at the base of the tower mast, which assembles and disassembles the steel tower A.
【0010】[0010]
【発明の効果】本発明は前記したように、鉄塔の内部に
タワーマストを装置したことにより、鉄塔とタワーマス
トを同時に又は時を変えて組立て建設することができ、
タワーマストの上端部に軸着したブームを鉄塔の中心軸
線より後方に倒し、ブームの先端部に軸着した補助ブー
ムを前方に倒してその先端部に吊下げたワイヤロープの
フックを鉄塔の中心軸線方向に誘導して三角錐形の鉄塔
頂部に係止し、クレーン駆動装置にてワイヤロープを引
き下ろし又は引き上げて三角錐形の鉄塔頂部を鉄塔の上
端部に係止し、又は鉄塔の上端部より取外す際ブーム2
が邪魔とならず作業工程を簡素化し、鉄塔と三角錐形の
鉄塔頂部との組立及び分解を迅速に行うことができる。
又ブームを直立状態にした時平面寸法がタワーマストと
同一以下にしてあるため、降下時の寸法がタワーマスト
分の鉄塔に空隙があれば降下解体ができる。従って小さ
な鉄塔の組付、解体が可能であり、クレーンの駆動装置
をタワーマスト内に収納したため小さな鉄塔内を通過で
きる。As described above, according to the present invention, by installing a tower mast inside a tower, the tower and the tower mast can be assembled or constructed simultaneously or at different times.
The boom attached to the upper end of the tower mast is tilted backward from the center axis of the tower, and the auxiliary boom attached to the tip of the boom is tilted forward and the hook of the wire rope suspended from the tip is attached to the center of the tower. It is guided in the axial direction and locked at the top of the triangular pyramid-shaped tower, and the wire rope is pulled down or pulled up by a crane drive to lock the top of the triangular pyramid at the top of the tower, or the top of the tower. Boom 2 when removing from
However, the work process can be simplified without disturbing, and the assembling and disassembling of the tower and the top of the triangular pyramid tower can be performed quickly.
Also, when the boom is in the upright state, the plane dimensions are equal to or smaller than the tower mast, so if there is a gap in the tower at the time of the descent, the tower can be dismantled. Therefore, it is possible to assemble and disassemble a small tower, and it is possible to pass through the small tower because the driving device of the crane is housed in the tower mast.
【図1】図1は本発明の正面図である。FIG. 1 is a front view of the present invention.
【図2】図2は本発明の要部の側面図である。FIG. 2 is a side view of a main part of the present invention.
【図3】図3は鉄塔とタワーマストの組立状態の横断面
図である。FIG. 3 is a cross-sectional view of an assembled state of a steel tower and a tower mast.
A 鉄塔 a 鉄塔の構成部材 B 三角錐形の鉄塔頂部 C1 ,C2 ,C3 送電線支持部材 1 タワーマスト 2 ブーム 3 軸 4 クレーン駆動装置 5 ブームの基部 6 補助ブーム 7 第2軸 8 フック 9 ワイヤ 10 タワーマストの上方支持部 11 油圧シリンダ 12 第2油圧シリンダ 13 懐形空間部 14 押上げ式リフトアップ装置Reference Signs List A steel tower a steel tower component B triangular pyramid steel tower top C 1 , C 2 , C 3 transmission line support member 1 tower mast 2 boom 3 shaft 4 crane driving device 5 boom base 6 auxiliary boom 7 second shaft 8 hook Reference Signs List 9 wire 10 tower mast upper support part 11 hydraulic cylinder 12 second hydraulic cylinder 13 pocket-shaped space part 14 push-up type lift-up device
Claims (3)
いて、組立、分解される鉄塔の内側にクレーンのタワー
マストを装置し、タワーマストの上方支持部に基部を軸
止したブームの先端部に補助ブームを軸着してなり、ブ
ームの先端部をタワーマストの軸着部を軸として鉄塔の
中心軸線よりも後方に倒し、ブームの先端部に軸止した
補助ブームの先端部をブームに対して前方にく字形に折
りたたみ、補助ブームの先端部に吊り下げたワイヤーロ
ープのフックにて鉄塔に組立又は解体される三角錐形の
鉄塔頂部を吊り上げ又は吊り降ろしするようにしたこと
を特徴とする小規模鉄塔の組立、解体ができるクレー
ン。In a crane for assembling and dismantling a tower, a tower mast of a crane is installed inside a tower to be assembled and disassembled, and an auxiliary part is provided for a tip end of a boom whose base is fixed to an upper support portion of the tower mast. The boom is pivoted, and the tip of the boom is tilted backward from the center axis of the tower with the pivoting part of the tower mast as the axis, and the tip of the auxiliary boom, which is fixed to the tip of the boom, against the boom It is folded in the shape of a square forward, and the top of a triangular pyramid-shaped steel tower assembled or disassembled into a steel tower is lifted or lowered by hooks of a wire rope suspended from the tip of an auxiliary boom. A crane that can assemble and dismantle large-scale towers.
ワーマスト内にクレーンの駆動装置を収納した請求項1
記載の小規模鉄塔の組立、解体ができるクレーン。2. A tower mast is installed inside a steel tower, and a driving device of a crane is housed in the tower mast.
A crane that can assemble and disassemble the small-scale tower described.
タワーマストと同一寸法以下にして置き、ブーム降下時
の寸法がタワーマスト分の鉄塔に空隙を作り、ブームを
降下して解体可能としたことを特徴とする請求項1又は
請求項2記載の小規模鉄塔の組立、解体ができるクレー
ン。3. The plane dimension when the boom is in the upright state is set to be equal to or smaller than the tower mast, and the dimension when the boom is lowered creates an air gap in the tower for the tower mast, and the boom can be lowered and dismantled. 3. A crane capable of assembling and disassembling a small-scale tower according to claim 1 or 2.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18228295A JP2640928B2 (en) | 1995-06-27 | 1995-06-27 | A crane that can assemble and disassemble small towers |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP18228295A JP2640928B2 (en) | 1995-06-27 | 1995-06-27 | A crane that can assemble and disassemble small towers |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH0912274A JPH0912274A (en) | 1997-01-14 |
JP2640928B2 true JP2640928B2 (en) | 1997-08-13 |
Family
ID=16115555
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP18228295A Expired - Fee Related JP2640928B2 (en) | 1995-06-27 | 1995-06-27 | A crane that can assemble and disassemble small towers |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2640928B2 (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102583163A (en) * | 2012-03-20 | 2012-07-18 | 西安市第四建筑工程公司 | Steel wire rope symmetrically disassembling process flow for tower crane attachment device |
JP6159197B2 (en) * | 2013-04-22 | 2017-07-05 | 松島工業株式会社 | Steel tower dismantling method and dismantling apparatus |
CN103832933B (en) * | 2013-09-29 | 2015-11-25 | 国家电网公司 | A kind of group tower tower crane with auxiliary |
JP6318076B2 (en) * | 2014-11-13 | 2018-04-25 | 鹿島建設株式会社 | Steel tower dismantling method and steel tower dismantling apparatus |
CN106245984B (en) * | 2016-09-26 | 2018-09-18 | 吉林安装集团股份有限公司 | Jack up Multifunctional creeping gin pole |
CN114084817B (en) * | 2021-11-12 | 2024-02-09 | 北京紫竹慧建设服务股份有限公司 | Tower arm dismantling device and dismantling process for long and narrow field |
CN115385239B (en) * | 2022-09-02 | 2024-08-23 | 江苏南通二建集团有限公司 | Complementary dismantling construction method for tower crane under unconventional working condition |
-
1995
- 1995-06-27 JP JP18228295A patent/JP2640928B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH0912274A (en) | 1997-01-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2640928B2 (en) | A crane that can assemble and disassemble small towers | |
CN107226422B (en) | A kind of single arm support is fixed to be hung and cantilever crane hinge installation method | |
JP2010242429A (en) | Demolition method for steel tower | |
JP2007162639A (en) | Windmill assembling apparatus and windmill assembling method | |
JP2000204792A (en) | Frame for assembly and/or maintenance for tower-shaped building, and assembly and/or maintenance method for tower-shaped building | |
JP4064935B2 (en) | Temporary arm and assembly method of arm bracket in transmission line tower using this temporary arm | |
JP5654280B2 (en) | Jib crane and its dismantling method | |
CN107044305B (en) | Lifting device for a turbine casing and method of lifting a casing | |
JP2010064867A (en) | Method for demolishing tower crane | |
JP7044393B2 (en) | Tower-shaped structure dismantling method and tower-shaped structure dismantling device | |
JPH10205429A (en) | Construction method for wind power generator | |
JP7555840B2 (en) | Tower crane transport unit and tower crane transport method | |
JP2004036235A (en) | Construction method for heightening steel tower | |
JP3939819B2 (en) | Jib crane for crane demolition | |
JP2009286531A (en) | Dismantling method of tower crane | |
CN211415003U (en) | Damage-free bearing dismounting device | |
JP2000145126A (en) | Demolishing unit for tower body and its demolishing method | |
KR100310991B1 (en) | assembly type tower crane for power transmission tower | |
CN219471646U (en) | Explosion-free chimney dismantling equipment | |
CN215974684U (en) | High-altitude portable tower dismantling derrick mast | |
CN110697585A (en) | Self-detaching attachment mechanism | |
CN111661771B (en) | Arm support for offshore wind power crane | |
JP2019027046A (en) | Pile driving machine | |
JP2000272876A (en) | Folding jib crane | |
CN217867700U (en) | Hoisting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090502 Year of fee payment: 12 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100502 Year of fee payment: 13 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110502 Year of fee payment: 14 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120502 Year of fee payment: 15 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130502 Year of fee payment: 16 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |