JP2619214B2 - Hardware for lifting concrete pavement slab and method of assembling the same - Google Patents

Hardware for lifting concrete pavement slab and method of assembling the same

Info

Publication number
JP2619214B2
JP2619214B2 JP61594A JP61594A JP2619214B2 JP 2619214 B2 JP2619214 B2 JP 2619214B2 JP 61594 A JP61594 A JP 61594A JP 61594 A JP61594 A JP 61594A JP 2619214 B2 JP2619214 B2 JP 2619214B2
Authority
JP
Japan
Prior art keywords
concrete
flange
lifting
slab
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP61594A
Other languages
Japanese (ja)
Other versions
JPH07197417A (en
Inventor
専市 兼板
政之 広岡
弘紀 時葉
Original Assignee
株式会社ピー・エス
株式会社秦野製作所
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社ピー・エス, 株式会社秦野製作所 filed Critical 株式会社ピー・エス
Priority to JP61594A priority Critical patent/JP2619214B2/en
Publication of JPH07197417A publication Critical patent/JPH07197417A/en
Application granted granted Critical
Publication of JP2619214B2 publication Critical patent/JP2619214B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は不等沈下したコンクリー
ト舗装版を持上げるコンクリート舗装版持上用金具及び
その組立方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a metal fitting for lifting a concrete pavement slab, which lifts a concrete pavement sunk unevenly, and a method of assembling the same.

【0002】[0002]

【従来の技術】近時空港の舗装版としてプレストレスト
コンクリート版が賞用されている。一方、空港は海上の
埋立地等に造成されることが多くなっており、従前に比
べて地盤沈下による不等沈下の対策が大きな技術問題と
なっている。コンクリート舗装版の不等沈下対策として
予め舗装版の下面にコンクリート舗装版持上用の反力装
置等を埋設しておくことも考えられるが、予想に反して
金具埋設個所に沈下が生じなかったり、あるいは、また
予想外の個所に沈下が生じることがあるため、必要以上
に広範囲に設置しておかざるを得ず、高コストとなると
いう問題がある。さらに、予め埋設しておくコンクリー
ト版持上用金具では銹が発生したり、路面使用によって
内部に異物が詰まったりして実際に必要な時に使用不能
なものが出てくる可能性があるという問題があった。
2. Description of the Related Art Recently, prestressed concrete slabs have been used as pavement slabs at airports. On the other hand, airports are often built in landfills at sea, and measures for uneven settlement due to land subsidence have become a major technical problem compared to before. As a countermeasure against uneven settlement of the concrete paving slab, it is conceivable to bury a reaction force device for lifting the concrete paving slab in advance on the underside of the paving slab. Alternatively, the settlement may occur at an unexpected location, so that it has to be installed in an unnecessarily wide area, resulting in a high cost. Furthermore, there is a possibility that rust may occur on the concrete slab lifting hardware that is buried in advance, and foreign materials may be clogged inside due to the use of the road surface, making it impossible to use it when it is actually needed. was there.

【0003】このような観点から、沈下が生じた時、沈
下区域に適切な位置及び数の作業孔をコンクリート舗装
版の上下に貫通させ、この作業孔を用いてコンクリート
舗装版の持上を行う技術が開発されている。(特開平1
−318605号公報、特開平2−289703号公
報)。この場合、作業孔として大きな孔を開けると空港
の舗装版として不適切となることから、大きな孔を開け
ることはできず、引上用ジャッキを使用できる最小限の
口径の孔に限定される。
[0003] From such a viewpoint, when subsidence occurs, an appropriate position and number of working holes are penetrated in the subsidence area above and below the concrete paving slab, and the concrete paving slab is lifted using the working holes. Technology is being developed. (Japanese Unexamined Patent Publication No.
-318605, JP-A-2-289703). In this case, if a large hole is made as a working hole, it becomes inappropriate as a pavement plate at an airport. Therefore, a large hole cannot be made, and the hole is limited to a hole having a minimum diameter that allows use of a jack for pulling.

【0004】従来のコンクリート版持上用金具は、コン
クリート版の必要な個所に作業孔をあけ、その作業孔下
の周辺部分を掘削して空間を形成し、その空間内に複数
に分割したコンクリート版支承板を挿入し、その空間内
で補助筒のフランジ上に組み付け、補助筒のねじ部に筒
本体を螺嵌させ、その筒本体の下端とフランジ上面とで
コンクリート版支承板を挟み込み全体を一体化させる。
これによって、筒本体がコンクリート版の作業孔内に装
着され、コンクリート版支承板が作業孔下周縁に張り出
される。そして筒本体にジャッキを力学的に連絡させ、
路盤に反力を取らせて筒本体を持ち上げると、コンクリ
ート版支承板がコンクリート版下面に押し当てられて持
ち上げられる。
[0004] A conventional concrete slab lifting fixture is to form a space by drilling a work hole in a necessary place of the concrete slab, excavating a peripheral portion under the work hole, and dividing the space into a plurality of concrete pieces. Insert the plate support plate, assemble it on the flange of the auxiliary cylinder in the space, screw the cylinder body into the screw part of the auxiliary cylinder, sandwich the concrete plate support plate between the lower end of the cylinder body and the upper surface of the flange, and Integrate.
As a result, the cylinder main body is mounted in the working hole of the concrete slab, and the concrete slab support plate projects to the lower peripheral edge of the working hole. And let the jack contact the cylinder body dynamically,
When the base body is lifted by causing the roadbed to take a reaction force, the concrete slab support plate is pressed against the lower surface of the concrete slab and lifted.

【0005】次に、コンクリート舗装版持上用金具を使
用したコンクリート版の持上修復工程を図6、7を参照
して説明する。図6(a)に示すように、コンクリート
舗装版1の沈下量を測定し、次いで図6(b)に示すよ
うに沈下域に作業孔2を形成する。次いで図6(c)に
示すように、作業孔2の下方の周辺の路盤を掘削して作
業孔下空間3を形成し、図6(d)に示すようにその底
部にコンクリートを打設して反力版4を形成する。図7
(e)に示すように、この反力版4上の作業孔下空間3
及び作業孔2内に、コンクリート舗装版持上用金具10
をセットする。コンクリート舗装版持上用金具10は、
従来、図5に示すように、スリーブ17、コンクリート
版支承板15、引上筒11とから構成されている。引上
筒11は雄ねじ12を備え、その下端にフランジ13を
備えている。この雄ねじ12はスリーブ17の雌ねじ1
8に螺合する。フランジ13は作業孔2よりわずかに外
径が小さく、作業孔を挿通することができる。フランジ
13の上面にはピン14が植設してある。コンクリート
版支承板15は、コンクリート舗装版の下面に当接し、
ジャッキでコンクリート舗装版持上用金具10を引き上
げるとき、コンクリート舗装版を持上げるものである。
このコンクリート版支承板15は、作業孔2を通ってコ
ンクリート舗装版下の作業孔下空間3に装入することが
できるように、円形の板を多数の扇形に分割してあるも
のである。このコンクリート版支承板15は内径が引上
筒11のねじ部に外嵌し、ピン孔16にピン14が入る
ようになっている。そして、引上筒11の雄ねじにスリ
ーブ17の雌ねじ18を螺合すると、コンクリート版支
承板15は、フランジ13の上面とスリーブ17の下面
との間に挟持される。このコンクリート版支承板15を
コンクリート舗装版の下面に当接させ、スリーブ17を
ジャッキで引き上げる。図7(e)に示すように、コン
クリート舗装版持上用金具10を作業孔下空間3内にコ
ンクリート舗装版の下端にコンクリート版支承板15が
当接する位置に位置決めし、図7(f)に示すようにコ
ンクリート舗装版持上用金具10にジャッキ40のラム
チェアをスリーブ17の上端部の雌ねじ18に螺嵌す
る。
Next, a concrete plate lifting process using a concrete pavement plate lifting fixture will be described with reference to FIGS. As shown in FIG. 6 (a), the amount of settlement of the concrete paving slab 1 is measured, and then, as shown in FIG. 6 (b), working holes 2 are formed in the settlement area. Next, as shown in FIG. 6 (c), the roadbed under the working hole 2 is excavated to form a space 3 under the working hole, and concrete is poured into the bottom as shown in FIG. 6 (d). To form a reaction plate 4. FIG.
As shown in (e), the space 3 below the working hole on the reaction plate 4
And in the working hole 2, a metal fitting 10 for lifting a concrete pavement slab.
Is set. The concrete pavement lifting hardware 10 is
Conventionally, as shown in FIG. 5, it is composed of a sleeve 17, a concrete plate support plate 15, and a pull-up cylinder 11. The pulling cylinder 11 has a male screw 12 and a flange 13 at a lower end thereof. The male screw 12 is the female screw 1 of the sleeve 17
8 The outer diameter of the flange 13 is slightly smaller than that of the working hole 2 so that the working hole can be inserted. A pin 14 is implanted on the upper surface of the flange 13. The concrete slab support plate 15 contacts the lower surface of the concrete pavement slab,
When the concrete paving slab lifting metal fitting 10 is pulled up with a jack, the concrete paving slab is lifted.
The concrete plate support plate 15 is formed by dividing a circular plate into a large number of sectors so that the concrete plate support plate 15 can be inserted into the work hole space 3 below the concrete paving slab through the work hole 2. The concrete slab support plate 15 has an inner diameter fitted to the screw portion of the pull-up cylinder 11 so that the pin 14 can be inserted into the pin hole 16. When the female screw 18 of the sleeve 17 is screwed into the male screw of the pull-up cylinder 11, the concrete plate support plate 15 is sandwiched between the upper surface of the flange 13 and the lower surface of the sleeve 17. The concrete plate support plate 15 is brought into contact with the lower surface of the concrete paving slab, and the sleeve 17 is jacked up. As shown in FIG. 7 (e), the concrete paving slab lifting metal fitting 10 is positioned in the working hole space 3 at a position where the concrete slab support plate 15 contacts the lower end of the concrete paving slab. The ram chair of the jack 40 is screwed into the female screw 18 at the upper end of the sleeve 17 on the concrete pavement lifting hardware 10 as shown in FIG.

【0006】反力版4の上に反力支持板45をおく。図
7(g)に示すように、この反力支持板45にジャッキ
40のラムを当接させ、ジャッキ40のラムを押し出す
と、反力支持板45の反力によってラムチェアが引き上
げられ、コンクリート舗装版持上用金具10を介してコ
ンクリート舗装版1が持ち上げられる。そして所望の高
さまで持ち上げた後、スリーブ17内にあらかじめ挿入
しておいたロックナットを反力支持板45に当接させ、
コンクリート舗装版持上用金具10、ロックナット及び
反力支持板45を残してジャッキを取り外す。然る後、
図7(h)に示すように、持ち上げられたコンクリート
舗装版1下の空隙に裏込材50を充填し、コンクリート
舗装版持上作業を終了する。
A reaction force support plate 45 is placed on the reaction force plate 4. As shown in FIG. 7 (g), when the ram of the jack 40 is brought into contact with the reaction force support plate 45 and the ram of the jack 40 is pushed out, the ram chair is raised by the reaction force of the reaction force support plate 45, and the concrete pavement is formed. The concrete paving slab 1 is lifted via the plate lifting hardware 10. Then, after lifting to the desired height, the lock nut previously inserted into the sleeve 17 is brought into contact with the reaction force support plate 45,
The jack is removed leaving the concrete paving slab lifting hardware 10, the lock nut and the reaction force support plate 45. After that,
As shown in FIG. 7 (h), the backing material 50 is filled in the space below the lifted concrete paving slab 1, and the concrete paving slab lifting operation is completed.

【0007】[0007]

【発明が解決しようとする課題】上記技術では、引上筒
11のフランジ13の上面の面積が制限されている。す
なわちフランジ13の外径は作業孔2の内径より小さ
く、雄ねじ12の外径はスリーブの内径に規制され、従
ってフランジ13の内径もこれに規制される。従って、
コンクリート版支承板15を支持する支持力は、設計計
算上、ぎりぎりの数値とならざるを得ないという事情に
ある。このため、コンクリート版支承板15が支持でき
る荷重を負担することは次の事情から無理な場合がある
ことが判明した。 (イ)ジャッキがスリーブ17を引上げるとき、スリー
ブ17のねじは引上方向に作用する。従って、スリーブ
17の下端面がコンクリート版支承板15を支承する挾
持力が減殺される。このことは雄ねじと雌ねじ間に微少
ギャップが存在するねじ機構の宿命である。 (ロ)このため、コンクリート版支承板15とフランジ
13の上面との当り面が斜に傾き、局部集中荷重が生
じ、その集中荷重部分が部分的にへたりを生じ変形す
る。 (ハ)一旦上記変形が起こると、フランジ13の上面の
支持面積が小さく、コンクリート版支承版15は外径が
大きいので、大きなモーメントが生じ上記変形部の変形
が進行する。 (ニ)この変形は元に戻らないので、ジャッキ引上力が
減殺され、それより上昇しない。
In the above technique, the area of the upper surface of the flange 13 of the pulling cylinder 11 is limited. That is, the outer diameter of the flange 13 is smaller than the inner diameter of the working hole 2, and the outer diameter of the male screw 12 is restricted by the inner diameter of the sleeve. Therefore,
The supporting force for supporting the concrete slab support plate 15 is inevitably a barely numerical value in the design calculation. For this reason, it became clear that it might not be possible to bear the load that the concrete slab support plate 15 can support for the following reasons. (A) When the jack pulls up the sleeve 17, the screw of the sleeve 17 acts in the pulling-up direction. Therefore, the clamping force with which the lower end surface of the sleeve 17 supports the concrete plate support plate 15 is reduced. This is the fate of the screw mechanism where there is a small gap between the male and female threads. (B) For this reason, the contact surface between the concrete slab support plate 15 and the upper surface of the flange 13 is inclined, causing a localized concentrated load, and the concentrated load portion is partially sagged and deformed. (C) Once the deformation occurs, the supporting area of the upper surface of the flange 13 is small, and the concrete plate support plate 15 has a large outer diameter, so that a large moment is generated and the deformation of the deformed portion proceeds. (D) Since this deformation does not return, the jack pulling force is reduced and does not rise further.

【0008】以上の事情により、25トンジャッキで引
上げられる引上力は、7トン程度より上昇せず、スリー
ブ17がコンクリート舗装版1の上面より上方に抜け出
す現象が生じた。本発明はこのような問題点を解決した
コンクリート舗装版持上用金具及びその組立方法を提供
するものである。
Under the circumstances described above, the pulling force pulled up by the 25-ton jack does not rise more than about 7 tons, and the sleeve 17 comes off from the upper surface of the concrete paving slab 1. The present invention provides a concrete paving slab lifting bracket and a method for assembling the same, which solves such problems.

【0009】[0009]

【課題を解決するための手段】本発明は、上記問題点を
解決したコンクリート舗装版持上用金具であって、
(a)持上用ジャッキを取付ける雌ねじを有しコンクリ
ート舗装版の作業孔に内嵌するスリーブと、(b)この
スリーブに螺合しその下端に作業孔より小さい径の下部
フランジを有する引上筒と、(c)この引上筒の下部フ
ランジに外嵌し、円周を複数分割されたフランジ外周継
足部材と、(d)前記引上筒下部フランジ上面と前記ス
リーブ間に挾持され、コンクリート舗装版下面を支持す
る扇形に分割されたコンクリート版支承板とから構成さ
れたことを特徴とするコンクリート舗装版持上用金具で
ある。この発明の従来技術と異なる点は、上記(c)の
点にあり、このフランジ外周継足部材を次に示すような
方法によりフランジの外径に取付けるところにある。
SUMMARY OF THE INVENTION The present invention is directed to a concrete paving slab lifting hardware which solves the above problems,
(A) A sleeve having a female screw for mounting a lifting jack and fitted inside a working hole of a concrete paving slab, and (b) a pull-up screwed into the sleeve and having a lower flange having a smaller diameter than the working hole at the lower end thereof. A tube, (c) a flange outer peripheral connecting member which is fitted to the lower flange of the pull-up tube and has a plurality of divided circumferences, and (d) is sandwiched between the upper surface of the pull-up tube lower flange and the sleeve; A concrete paving slab lifting bracket comprising a fan-shaped divided concrete slab support plate for supporting a lower surface of the concrete paving slab. The point different from the prior art of the present invention is the above point (c), in that the flange outer peripheral connecting member is attached to the outer diameter of the flange by the following method.

【0010】すなわち本発明方法は、上記本発明のコン
クリート舗装版持上用金具をコンクリート舗装版に穿設
した作業孔内で組み立てるに当り、引上筒を天地倒立さ
せて作業孔下空間に装入し、フランジ外周継足部材を順
次作業孔下空間内に装入して引上筒のフランジ外周に取
付整列させ、仮取り付けし、フランジとフランジ継足部
材とを溶接接合し、ついで引上筒を天地転倒して正位置
とし、コンクリート版支承板を作業孔下空間内に装入し
て前記フランジ上面に位置決めし、次いでスリーブを作
業孔に挿入して引上筒に螺合し支承板を締付挾持するこ
とを特徴とするコンクリート舗装版持上用金具の組立方
法である。
That is, in the method of the present invention, when assembling the metal fitting for lifting the concrete paving slab of the present invention in the working hole formed in the concrete paving slab, the lifting cylinder is turned upside down and mounted in the space below the working hole. Then, insert the flange outer peripheral member sequentially into the space below the working hole, mount and align it on the outer periphery of the flange of the pull-up cylinder, temporarily attach it, weld the flange and the flange additional member, and then pull up The cylinder is turned upside down to the normal position, the concrete plate support plate is inserted into the space below the work hole and positioned on the upper surface of the flange, and then the sleeve is inserted into the work hole and screwed into the pull-up tube to screw the support plate. The method for assembling a metal fitting for lifting a concrete pavement slab, comprising:

【0011】[0011]

【作用】本発明のコンクリート舗装版持上用金具は引上
筒の下部フランジを拡大したので、支承板が十分に支持
され舗装版にジャッキの引上力を伝達する。コンクリー
ト舗装版持上用金具は本発明の組立工程によって、作業
孔下空間内で引上筒フランジに取り付けることができ
る。
With the metal fitting for lifting a concrete paving slab of the present invention, the lower flange of the pulling cylinder is enlarged, so that the support plate is sufficiently supported and the jack pulling force is transmitted to the paving slab. The concrete pavement lifting hardware can be attached to the lifting cylinder flange in the space below the working hole by the assembling process of the present invention.

【0012】[0012]

【実施例】図1に実施例のコンクリート舗装版持上用金
具の分解図を示した。実施例のコンクリート舗装版持上
用金具は、従来のスリーブ17、コンクリート版支承板
15、引上筒11のほかに、フランジ外周継足部材10
0を備えている。このフランジ外周継足部材100は、
引上筒11のフランジ13の外周に一体に溶接取付けさ
れるものである。このフランジ外周継足部材100は、
作業孔からコンクリート舗装版の下の作業孔下空間3に
装入できるように、複数分割されており、その内径10
1の寸法はフランジ13の外径と一致している。また、
その上面にはピン14が植設してあり、コンクリート版
支承板15にはこのピンが貫入する孔16が設けられて
いる。
FIG. 1 is an exploded view of a concrete paving slab lifting hardware according to an embodiment. The metal fitting for lifting a concrete pavement slab of the embodiment includes a conventional sleeve 17, a concrete slab support plate 15, a pull-up cylinder 11, and a flange outer peripheral connecting member 10.
0 is provided. This flange outer peripheral connecting member 100 is
It is integrally attached to the outer periphery of the flange 13 of the pulling cylinder 11 by welding. This flange outer peripheral connecting member 100 is
It is divided into a plurality of pieces so that the work hole can be inserted into the space 3 below the concrete paving slab from the work hole.
The dimension 1 corresponds to the outer diameter of the flange 13. Also,
A pin 14 is implanted on the upper surface thereof, and a concrete plate support plate 15 is provided with a hole 16 through which the pin penetrates.

【0013】図2は本発明の実施例のコンクリート舗装
版持上用金具の組立方法を示す説明図である。引上筒1
1を天地倒立させて作業孔2から作業孔下空間3に装入
する。ついで、分割されているフランジ外周継足部材1
00を作業孔2を通って作業孔下空間3内に装入する。
そして分割されているフランジ外周継足部材100を引
上筒11のフランジ13の外周に仮取付けする。この仮
取付けは、マグネット111を用いてフランジ13の外
径にフランジ外周継足部材100を合わせ、フランジと
フランジ外周継足部材とを点溶接し、その後、フランジ
13の外周とフランジ外周継足部材100の内周とを溶
接棒110を作業孔2から挿入して溶接結合する。あら
かじめ、フランジ13外周とフランジ外周継足部材10
0の内周に溶接用の開先を設けておく。
FIG. 2 is an explanatory view showing a method for assembling the metal fitting for lifting a concrete pavement slab according to an embodiment of the present invention. Pull cylinder 1
1 is turned upside down and inserted into the space 3 below the working hole 2 through the working hole 2. Then, the divided flange outer peripheral connecting member 1
00 is inserted through the work hole 2 into the space 3 below the work hole.
Then, the divided flange outer peripheral connecting member 100 is temporarily attached to the outer periphery of the flange 13 of the pulling cylinder 11. In this temporary mounting, the outer peripheral flange member 100 is fitted to the outer diameter of the flange 13 using the magnet 111, and the flange and the outer peripheral flange member are spot-welded. The welding rod 110 is inserted from the working hole 2 and welded to the inner periphery of 100. In advance, the outer circumference of the flange 13 and the outer circumference of the flange
A groove for welding is provided on the inner periphery of 0.

【0014】ついで引上筒11を天地転倒して正位置と
し、以下、図7に示す従来と同様にコンクリート版支承
板15を作業孔内に装入し、これをフランジ13上面に
位置決めし、スリーブ17を作業孔に挿入し、引上筒1
1に螺合してコンクリート版支承板15を締付け挾持す
る。フランジ13はその外周にフランジ外周継足部材1
00を取付けて、その上面の面積が広いので、大きな支
持力で支持する。従って、従来のように、ジャッキ引上
力が減殺されることなく、コンクリート舗装版1を引き
上げることができる。
Then, the pulling cylinder 11 is turned upside down to the normal position, and the concrete slab support plate 15 is inserted into the working hole in the same manner as in the prior art shown in FIG. Insert the sleeve 17 into the working hole,
1 and fasten and clamp the concrete plate support plate 15. The flange 13 is provided on the outer periphery of the flange
00 is attached, and since the area of the upper surface is large, it is supported with a large supporting force. Therefore, the concrete paving slab 1 can be pulled up without reducing the jack pulling force as in the related art.

【0015】図3はコンクリート舗装版1の引き上げ工
程を示し、ジャッキ40のラムチェア41がスリーブ1
7に螺合し、ラム42が反力支持板45に反力を取って
スリーブ17を引き上げる工程を示している。スリーブ
17は、その下端に引上筒11を螺合し、スリーブ17
と引上筒11がコンクリート舗装版支承板15を強固に
締め付けて挟持し、これらがと一体になっており、コン
クリート舗装版支承板15がコンクリート舗装版1の下
面に当接して、コンクリート舗装版1を引き上げる。舗
装板1が引き上げられると、ハンドル43によりナット
44を下方にねじ込み、このナット44を反力支持板4
5に当接させ、ジャッキを取り除くことができる。
FIG. 3 shows a process of lifting the concrete paving slab 1 and the ram chair 41 of the jack 40 is
7 shows a process in which the ram 42 takes up a reaction force on the reaction force support plate 45 and pulls up the sleeve 17. The pull-up cylinder 11 is screwed onto the lower end of the sleeve 17 and the sleeve 17
And the pulling cylinder 11 firmly clamp and hold the concrete paving plate support plate 15, and these are integrated with each other. The concrete paving plate support plate 15 abuts on the lower surface of the concrete paving plate 1, and the concrete paving plate Raise 1 When the paving board 1 is pulled up, the nut 44 is screwed downward by the handle 43, and the nut 44 is
5 to remove the jack.

【0016】図4はこの作業を完了し、コンクリート舗
装版1を引き上げて生じた下部空間にセメントグラウト
を充填した後、スリーブ17に蓋60を施した状態を示
している。ナット44は支持板45に支持されている。
このコンクリート舗装版持上用金具10は必要があれば
蓋60を外して再使用することができる。
FIG. 4 shows a state in which this operation is completed, the concrete paving slab 1 is pulled up, and the lower space created by filling the cement grout and then the sleeve 17 is covered with a lid 60. The nut 44 is supported by a support plate 45.
The concrete pavement lifting hardware 10 can be reused by removing the lid 60 if necessary.

【0017】[0017]

【発明の効果】本発明によれば、コンクリート版支承板
の中央部の固定部がへたることなく、ジャッキの引上力
を舗装版下面に加えることができ、コンクリート舗装版
の不等沈下を容易に修正することができるようになっ
た。また、コンクリート舗装版持上用金具の支持力を簡
易な組立方法によって確保することができるという優れ
た効果を奏する。
According to the present invention, the jack pulling force can be applied to the lower surface of the pavement slab without causing the fixed portion at the center of the concrete slab support plate to be flat, and uneven sunk of the concrete pavement slab can be prevented. It can be easily modified. Also, there is an excellent effect that the supporting force of the concrete paving slab lifting hardware can be secured by a simple assembling method.

【図面の簡単な説明】[Brief description of the drawings]

【図1】実施例のコンクリート舗装版持上用金具を示す
分解斜視図である。
FIG. 1 is an exploded perspective view showing a concrete paving slab lifting hardware of an embodiment.

【図2】実施例のコンクリート舗装版持上用金具の組立
方法の説明図である。
FIG. 2 is an explanatory view of a method of assembling a metal fitting for lifting a concrete pavement slab according to an embodiment.

【図3】実施例のコンクリート舗装版持上用金具の使用
説明図である。
FIG. 3 is an explanatory view of the use of a metal fitting for lifting a concrete pavement slab according to an embodiment.

【図4】実施例のコンクリート舗装版持上用金具の縦断
面図である。
FIG. 4 is a vertical sectional view of a metal fitting for lifting a concrete pavement slab according to an embodiment.

【図5】従来のコンクリート舗装版持上用金具の分解斜
視図である。
FIG. 5 is an exploded perspective view of a conventional concrete paving slab lifting hardware.

【図6】舗装版持上作業を説明する工程図である。FIG. 6 is a process diagram illustrating a paving slab lifting operation.

【図7】舗装版持上作業を説明する工程図である。FIG. 7 is a process diagram illustrating a paving slab lifting operation.

【符号の説明】[Explanation of symbols]

1 コンクリート舗装版 2 作業孔 3 作業孔下空間 4 反力版 10 コンクリート舗装版持上用金具 11 引上筒 12 雄ねじ 13 フランジ 14 ピン 15 コンクリート版支承板 16 孔 17 スリーブ 18 雌ねじ 40 ジャッキ 41 ラムチェア 42 ラム 43 ハンドル 44 ナット 45 反力支持板 50 裏込め材 60 蓋 100 フランジ継足部材 101 内径 110 溶接棒 111 マグネッ
REFERENCE SIGNS LIST 1 concrete paving plate 2 working hole 3 working hole lower space 4 reaction plate 10 concrete paving plate lifting bracket 11 pulling cylinder 12 male screw 13 flange 14 pin 15 concrete plate support plate 16 hole 17 sleeve 18 female screw 40 jack 41 ram chair 42 Ram 43 Handle 44 Nut 45 Reaction force support plate 50 Backing material 60 Cover 100 Flange extension member 101 Inner diameter 110 Welding rod 111 Magnet

───────────────────────────────────────────────────── フロントページの続き (56)参考文献 特開 平1−318605(JP,A) 特開 平2−289703(JP,A) 特公 平5−57362(JP,B2) ──────────────────────────────────────────────────続 き Continuation of front page (56) References JP-A-1-318605 (JP, A) JP-A-2-289703 (JP, A) JP-B 5-57362 (JP, B2)

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 持上用ジャッキを取付ける雌ねじを有し
コンクリート舗装版の作業孔に内嵌するスリーブと、該
スリーブに螺合する雄ねじを有しその下端に作業孔より
小径の下部フランジを有する引上筒と、該下部フランジ
外周に取付けたフランジ外周継足部材と、前記引上筒下
部フランジ上面と前記スリーブ下端面間に挾持され、コ
ンクリート舗装版下面に当接する多数の扇形支承板とか
らなることを特徴とするコンクリート舗装版持上用金
具。
1. A sleeve having a female screw for mounting a lifting jack, which is internally fitted in a working hole of a concrete paving slab, a male screw which is screwed into the sleeve, and a lower flange having a smaller diameter at the lower end than the working hole. A lifting cylinder, a flange outer peripheral connecting member attached to an outer periphery of the lower flange, and a plurality of fan-shaped support plates sandwiched between an upper surface of the lower flange of the lifting cylinder and a lower surface of the sleeve and abutting on a lower surface of the concrete paving slab. A metal fitting for lifting a concrete pavement slab.
【請求項2】 請求項1記載のコンクリート舗装版持上
用金具をコンクリート舗装版に穿設した作業孔内で組み
立てるに当り、引上筒を天地倒立させて作業孔下空間に
装入し、フランジ外周継足部材を作業孔下空間内に装入
して引上筒のフランジ外周に仮取付し、フランジとフラ
ンジ外周継足部材とを溶接接合し、次いで引上筒を天地
転倒して正位置とし、扇形支承板を作業孔下空間内に装
入して前記フランジ上面に位置決めし、次いでスリーブ
を作業孔に挿入し引上筒に螺合して支承板を締付挾持す
ることを特徴とするコンクリート舗装版持上用金具の組
立方法。
2. When assembling the metal fitting for lifting a concrete paving slab according to claim 1 in a working hole formed in the concrete paving slab, the lifting cylinder is turned upside down and inserted into a space below the working hole. The flange outer peripheral member is inserted into the space below the working hole and temporarily attached to the outer periphery of the flange of the pull-up tube, the flange and the flange outer peripheral member are welded to each other, and then the pull-up tube is turned over to correct Position, the fan-shaped support plate is inserted into the space below the work hole and positioned on the upper surface of the flange, then the sleeve is inserted into the work hole, screwed into the pull-up cylinder, and the support plate is clamped and clamped. Method of assembling a metal fitting for lifting a concrete pavement slab.
JP61594A 1994-01-07 1994-01-07 Hardware for lifting concrete pavement slab and method of assembling the same Expired - Fee Related JP2619214B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61594A JP2619214B2 (en) 1994-01-07 1994-01-07 Hardware for lifting concrete pavement slab and method of assembling the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61594A JP2619214B2 (en) 1994-01-07 1994-01-07 Hardware for lifting concrete pavement slab and method of assembling the same

Publications (2)

Publication Number Publication Date
JPH07197417A JPH07197417A (en) 1995-08-01
JP2619214B2 true JP2619214B2 (en) 1997-06-11

Family

ID=11478644

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61594A Expired - Fee Related JP2619214B2 (en) 1994-01-07 1994-01-07 Hardware for lifting concrete pavement slab and method of assembling the same

Country Status (1)

Country Link
JP (1) JP2619214B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4924968B2 (en) * 2006-06-09 2012-04-25 株式会社ピーエス三菱 Concrete plate height adjusting device and height adjusting method

Also Published As

Publication number Publication date
JPH07197417A (en) 1995-08-01

Similar Documents

Publication Publication Date Title
JP2619214B2 (en) Hardware for lifting concrete pavement slab and method of assembling the same
KR102116934B1 (en) Pressurized type Pre-embedded Anchor by Pressurized for Bridge Inspection Facility and Method for constructing this same
US5899629A (en) Manhole
JP2716422B2 (en) Method and apparatus for refilling top of tunnel support material
JP3362809B2 (en) Pillar support device
JPH01290803A (en) Device for lifting up concrete pavement slab
JPH06146213A (en) Height restoration method of sunk concrete pavement slab
JP3061593B2 (en) Concrete block connection method and connection metal fittings
JP4911823B2 (en) Anchor frame anchoring structure
JPH071466Y2 (en) Temporary columns for formwork support
CN219569698U (en) Supporting device for girder under heavy object action
JPH02289703A (en) Fitting for lifting concrete plate
JPH0721908U (en) PC board erection jig
JPH0978580A (en) Foundation pile pressing-in method and pressing-in device
JPH05247957A (en) Level corrector for structure
JPH0715853Y2 (en) Bridge support fixing device
JP3433007B2 (en) Reinforced concrete containment vessel and its construction method
KR200249533Y1 (en) A man hole cover case being able to adjusting its height
JPH1025759A (en) Level adjustable stud
JP3000954U (en) Basic structure of elevator
JPH086374B2 (en) Foundation bolt fixing structure
JP2990412B2 (en) Concrete paving plate lifting equipment
JP2760776B2 (en) Column base structure and column base construction method
JP4312907B2 (en) Direct foundation structure with non-settlement correction function
JP2526356Y2 (en) Pile connection device

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19970128

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120311

Year of fee payment: 15

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120311

Year of fee payment: 15

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120311

Year of fee payment: 15

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

LAPS Cancellation because of no payment of annual fees