JP2608336B2 - Slab construction method - Google Patents

Slab construction method

Info

Publication number
JP2608336B2
JP2608336B2 JP1266295A JP26629589A JP2608336B2 JP 2608336 B2 JP2608336 B2 JP 2608336B2 JP 1266295 A JP1266295 A JP 1266295A JP 26629589 A JP26629589 A JP 26629589A JP 2608336 B2 JP2608336 B2 JP 2608336B2
Authority
JP
Japan
Prior art keywords
slab
slate
vertical
corrugated slate
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1266295A
Other languages
Japanese (ja)
Other versions
JPH03132546A (en
Inventor
昌宏 浅田
満 西村
宗男 加藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP1266295A priority Critical patent/JP2608336B2/en
Publication of JPH03132546A publication Critical patent/JPH03132546A/en
Application granted granted Critical
Publication of JP2608336B2 publication Critical patent/JP2608336B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】 《産業上の利用分野》 本発明はスラブ施工工程に適用するスラブの施工方法
とに関する。
The present invention relates to a slab construction method applied to a slab construction process.

《従来の技術》 住宅等の構造物の床スラブを構築する場合には、木製
枠板を型枠の主材とし、根太や大引を狭い間隔で多数配
して補強後、コンクリートを打設養生したならば脱型し
ていた。
<< Conventional technology >> When constructing floor slabs for structures such as houses, wooden frame plates are used as the main material of the formwork, and a large number of joists and pulling bars are arranged at narrow intervals. If he had cured, he had been removed.

上記木製枠板の代りに鉄板を用いたときには根太や大
引を使用せず、広い間隔で軽量ビームを配し、これによ
って補強していた。
When an iron plate was used in place of the wooden frame plate, joists and pulling were not used, and light beams were arranged at wide intervals to reinforce the beam.

鉄板を用いたときには脱型せず、軽量ビームのみを取
り外していた。
When using an iron plate, it was not removed, and only the lightweight beam was removed.

《発明が解決しようとする課題》 しかし、木製枠板を用いた場合は、これの解体除去や
コンクリートの脱型両側表面を仕上げるために、多大な
労力と時間とを要するとともに、使用後の枠板や端太材
などの支保材搬出を要していた。
《Problems to be solved by the invention》 However, when a wooden frame plate is used, it takes a great deal of labor and time to dismantle and remove the concrete and remove both sides of the concrete. It was necessary to carry out supporting materials such as boards and edge materials.

また、鉄板を用いた型枠では支保材となる軽量ビーム
を外すだけでよいが、型枠代りに使用した鉄板に対して
塗装ができないような箇所では腐食を生じるのである。
Further, in a formwork using an iron plate, it suffices to remove the lightweight beam which serves as a supporting material, but corrosion occurs in a place where the iron plate used as a substitute for the formwork cannot be painted.

本発明は上記事情に鑑みてなされたものであって、そ
の目的は脱型を要せず、しかも少ない支保材で充分な強
度を得ることができ、腐食の問題も残さないスラブの施
工方法を提供するにある。
The present invention has been made in view of the above circumstances, and an object of the present invention is to provide a slab construction method that does not require demolding, can obtain sufficient strength with a small amount of support material, and does not leave a problem of corrosion. To offer.

《課題を解決するための手段》 上記目的を達成するために本発明に係るスラブの施工
方法は、布基礎、壁、若しくは耐力壁等の立て向き躯体
部分を構築するための縦型枠を、波型スレート、モルタ
ル、コンクリート等の版で構築し、隣り合う一方の上記
躯体部分の上記縦型枠と、他方の該躯体部分の該縦型枠
との間に波型スレートを水平に渡設し、該波型スレート
の下面に、該波型スレートの山・谷に並行した方向と直
交するように支保材を当て渡し、上記躯体部分の上記縦
型枠間と上記波型スレートの表面とにコンクリートを連
続一体的に打設し、養生した後、上記波型スレートの下
面の上記支保材のみを除去することで、上記躯体部分と
床スラブとを同時に施工することを特徴とする。
<< Means for Solving the Problems >> In order to achieve the above object, the method of constructing a slab according to the present invention comprises a vertical frame for constructing a vertical foundation such as a cloth foundation, a wall, or a load-bearing wall, A slate, a mortar, a slab made of concrete or the like, and a corrugated slate is horizontally provided between the vertical frame of the adjacent one of the frame portions and the vertical frame of the other frame portion. Then, on the lower surface of the corrugated slate, a support material is applied so as to be orthogonal to the direction parallel to the peaks and valleys of the corrugated slate, between the vertical frames of the skeleton portion and the surface of the corrugated slate. After the concrete is continuously and integrally cast into and cured, and only the supporting material on the lower surface of the corrugated slate is removed, the skeleton part and the floor slab are simultaneously constructed.

《作 用》 スラブ用の型枠として、軽量かつ高い強度の波型スレ
ートを採用しているので、この波型スレートを、隣り合
う一方の躯体部分の縦型枠と、他方の躯体部分の縦型枠
との間に渡設して設置することで、波型スレートの山・
谷に並行した方向と直交するように支保材を当て渡すの
みで、縦型枠をも含めて、全体として安定でかつ高い強
度の一体的な型枠を構築することができ、このような構
成のために、布基礎等の立て向き躯体部分から横広がり
の床スラブにわたって連続一体的にコンクリートを打設
して、構造的な連続性を持たせて当該構造部分を構築す
ることができる。そして、コンクリート養生後は、波型
スレートの山・谷に並行した方向と直交する一方向にの
み当て渡した支保材のみを撤去することで施工作業を完
了できる。
<Operation> Since a lightweight and high-strength corrugated slate is used as the slab formwork, the corrugated slate is divided into a vertical form of one adjacent skeleton and a vertical form of the other skeleton. By installing it between the mold and the formwork,
By simply passing the support material perpendicular to the direction parallel to the valley, it is possible to construct a stable and high-strength integrated formwork as a whole, including the vertical formwork. For this purpose, concrete can be cast continuously and integrally from the upright skeleton portion such as a cloth foundation to the horizontally extending floor slab, and the structural portion can be constructed with structural continuity. Then, after the concrete is cured, the construction work can be completed by removing only the supporting material that is applied only in one direction orthogonal to the direction parallel to the peaks and valleys of the corrugated slate.

《実 施 例》 以下本発明の好適な実施例について、図面を参照して
詳細に説明する。
<< Examples >> Hereinafter, preferred examples of the present invention will be described in detail with reference to the drawings.

第1図は波型スレート1を床スラブの型枠として使用
している様子を示すもので、布基礎用の捨型枠としての
縦型枠2の上端にL型状の金物3を配置し、次にラチス
梁状の軽量ビーム4を支保材として、一方の布基礎用の
片側の縦型枠2の頂部と、図示しない他方の布基礎用の
片側の縦型枠の頂部との間に渡している。
Fig. 1 shows how the corrugated slate 1 is used as a formwork for a floor slab. An L-shaped metal fitting 3 is arranged at the upper end of a vertical formwork 2 as a scrap formwork for a cloth foundation. Next, using the lattice beam-shaped lightweight beam 4 as a support material, between the top of one vertical formwork 2 for one cloth foundation and the top of the other vertical formwork for one cloth foundation (not shown). Have passed.

軽量ビーム4の端部には、逆L字形の金属製ファスナ
ー5が着脱自在に嵌着してあって、このファスナー5を
縦型枠2の上端に係止させて軽量ビーム4を支持してい
る。また、縦型枠2は波型スレート,モルタル又はコン
クリート製の薄板で、波型スレートおよび軽量ビーム、
打設コンクリートの鉛直荷重に耐えられる強度を具え
る。
An inverted L-shaped metal fastener 5 is detachably fitted to the end of the lightweight beam 4, and the fastener 5 is locked to the upper end of the vertical frame 2 to support the lightweight beam 4. There is. The vertical frame 2 is a thin plate made of a corrugated slate, mortar or concrete, and has a corrugated slate and a light beam.
It has the strength to withstand the vertical load of cast concrete.

次いで、波型スレート1の山・谷に並行した方向と軽
量ビーム4とが直交するように波型スレート1の端部を
金物3の内側に合せて縦型枠2の頂部に載置する。
Then, the end of the corrugated slate 1 is placed on the top of the vertical formwork 2 so that the end of the corrugated slate 1 is aligned with the inside of the metal 3 so that the direction parallel to the peaks and valleys of the corrugated slate 1 and the light beam 4 are orthogonal to each other.

その際、波型スレート1とこの波型スレート1の山・
谷に並行した方向に向かって直列的に並んで隣接する他
のスレート1aとは、付き合せ,重ね合せいずれの場合に
も、それらの端部間に防水テープ6を貼着して打設コン
クリートのノロが漏れないようにしている。また、山・
谷に並行した方向と直交する方向おけるスレート端部の
接合については、重ね合せ、ずれないようにタッピング
ネジ7でスレート同士を縫い合わせ、一体化している。
At that time, the corrugated slate 1 and the peak of the corrugated slate 1
The other slate 1a that is arranged in series in the direction parallel to the valley and is adjacent to the other slate 1a is attached with waterproof tape 6 between its ends in both cases of laying and overlapping. I'm trying to prevent the leak of this. In addition, mountain
Regarding the joining of the slate ends in a direction perpendicular to the direction parallel to the valley, the slate is sewn together with a tapping screw 7 so as not to overlap or shift, and integrated.

然る後、第2図に示す如く、波型スレート1の上に床
スラブ用の鉄筋(図示せず)を配し、スラブ8のコンク
リートを打設する。
After that, as shown in FIG. 2, a reinforcing bar (not shown) for the floor slab is arranged on the corrugated slate 1, and concrete of the slab 8 is poured.

縦型枠2は基盤9の上に間隔を隔てて対向立設されて
おり、スラブ8のコンクリートは、縦型枠2の内部に打
ち込むコンクリートと連続一体的に打設されている。
The vertical formwork 2 is erected on the base 9 so as to face each other with a space therebetween, and the concrete of the slab 8 is continuously and integrally cast with the concrete to be poured into the vertical formwork 2.

また、基盤9とスラブ9との間隔が狭く、スラブ8の
床下から機材を搬出し難い場合には、予めスラブ8の一
部に2尺角程度の開口を設けてコンクリートを打設する
ようにしても良い。
If the space between the base 9 and the slab 9 is narrow and it is difficult to carry out the equipment from under the floor of the slab 8, the slab 8 should be preliminarily provided with an opening of about 2 sq. May be.

スラブ8のコンクリートの養生が終了したならば、フ
ァスナー5,縦型枠2及び波型スレート1をそのまま残し
て軽量ビーム4のみを取り外す。そして、上述した2尺
角程度のスラブ8の開口から軽量ビーム4を搬出し、こ
の開口には吊型枠を当ててコンクリートを打ち、これに
よりスラブ8の施工が終了する。
When the curing of the concrete of the slab 8 is completed, only the lightweight beam 4 is removed while leaving the fastener 5, the vertical frame 2 and the corrugated slate 1 as they are. Then, the lightweight beam 4 is carried out from the opening of the slab 8 having a size of about two square meters, and concrete is applied to the opening by applying a hanging form, whereby the construction of the slab 8 is completed.

なお、基盤9が下の階のスラブであって、縦型枠2が
耐力壁用の堰板であっても同様である。
The same applies to the case where the base 9 is a slab on the lower floor and the vertical formwork 2 is a weir plate for a load-bearing wall.

《効 果》 以上詳細に説明したように、本発明はスラブ用の型枠
として波型スレートを使用しているので、少なくともス
レートの山・谷に並行した方向に沿っては支保材を要せ
ず、端太材の設置や搬出は勿論のこと、取外し作業等が
著しく少なくなって工期を短縮できる効果がある。
<Effects> As described in detail above, since the present invention uses a corrugated slate as a mold for a slab, a support material is required at least along a direction parallel to the peaks and valleys of the slate. In addition, there is an effect that not only the installation and unloading of the timber, but also the removal work and the like are significantly reduced, and the construction period can be shortened.

また、本発明のスラブの施工方法によれば、スレート
は錆びるおそれがないので、スラブの型枠であるスレー
トを取り外す必要はなく、脱型・除去作業が不要である
ことから、省力化並びに工期短縮の点で極めて効果が大
きい。また、スラブ用の型枠として、軽量かつ高い強度
の波型スレートを採用しているので、この波型スレート
を、隣り合う一方の躯体部分の縦型枠と、他方の躯体部
分の縦型枠との間に渡設して設置することで、波型スレ
ートの山・谷に並行した方向と直交するように支保材を
当て渡すのみで、縦型枠をも含めて、全体として安定で
かつ高い強度の一体的な型枠を構築することができ、こ
のような構成のために、布基礎等の立て向き躯体部分か
ら横広がりの床スラブにわたって連続一体的にコンクリ
ートを打設して、構造的な連続性を持たせて当該構造部
分を構築することができる。そして、コンクリート養生
後は、波型スレートの山・谷に並行した方向と直交する
一方向のみ当て渡した支保材のみを撤去することで施工
作業を完了でき、工期短縮・作業の省力化に優れた効果
を発揮する。
Further, according to the slab construction method of the present invention, since the slate does not have the possibility of rusting, it is not necessary to remove the slate which is the formwork of the slab. This is extremely effective in terms of shortening. In addition, since a lightweight and high-strength corrugated slate is used as the form for the slab, this corrugated slate can be used as a vertical form for one of the adjacent skeletons and a vertical form for the other skeleton. By installing it across the space between and, the supporting material is only handed over so that it is orthogonal to the direction parallel to the peaks and valleys of the corrugated slate, and the overall vertical structure is stable and It is possible to construct a high-strength integrated formwork, and for such a structure, concrete is continuously and integrally cast from a vertical slab part such as a cloth foundation to a horizontally spread floor slab. The structural part can be constructed so as to have an appropriate continuity. After concrete curing, the construction work can be completed by removing only the support material that has been applied in only one direction perpendicular to the direction parallel to the peaks and valleys of the corrugated slate, which is excellent in shortening the construction period and saving labor. It has the effect.

【図面の簡単な説明】 第1図は本発明の実施例を示す斜視図、第2図はスラブ
用コンクリートの打設が終った状態を示す断面図であ
る。 1……波型スレート、2……縦型枠 3……金物、4……軽量ビーム 5……ファスナー、6……防水テープ 7……タッピングネジ、8……スラブ 9……基盤
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a perspective view showing an embodiment of the present invention, and FIG. 2 is a cross-sectional view showing a state in which concrete for slab has been poured. DESCRIPTION OF SYMBOLS 1 ... Corrugated slate, 2 ... Vertical frame 3 ... Hardware, 4 ... Light beam 5 ... Fastener, 6 ... Waterproof tape 7 ... Tapping screw, 8 ... Slab 9 ... Base

フロントページの続き (72)発明者 加藤 宗男 東京都港区芝大門2丁目12番10号 浅野 スレート株式会社内 (56)参考文献 特開 昭48−59618(JP,A) 特開 昭51−26724(JP,A) 特開 昭62−202151(JP,A) 特開 昭63−201222(JP,A) 実開 昭63−143613(JP,U) 特公 昭29−3875(JP,B1) 実公 昭30−16221(JP,Y1) 実公 昭35−6258(JP,Y1)Front page continuation (72) Inventor Muneo Kato 2-12-10 Shibadaimon, Minato-ku, Tokyo Asano Slate Co., Ltd. (56) Reference JP 48-59618 (JP, A) JP 51-26724 ( JP, A) JP-A-62-202151 (JP, A) JP-A-63-201222 (JP, A) JP-A-63-143613 (JP, U) JP-N-29-3875 (JP, B1) JP Showa 30-16221 (JP, Y1) Showa 35-6258 (JP, Y1)

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】布基礎、壁、若しくは耐力壁等の立て向き
躯体部分を構築するための縦型枠を、波型スレート、モ
ルタル、コンクリート等の版で構築し、隣り合う一方の
上記躯体部分の上記縦型枠と、他方の該躯体部分の該縦
型枠との間に波型スレートを水平に渡設し、該波型スレ
ートの下面に、該波型スレートの山・谷に並行した方向
と直交するように支保材を当て渡し、上記躯体部分の上
記縦型枠間と上記波型スレートの表面とにコンクリート
を連続一体的に打設し、養生した後、上記波型スレート
の下面の上記支保材のみを除去することで、上記躯体部
分と床スラブとを同時に施工することを特徴とするスラ
ブの施工方法。
1. A vertical frame for constructing a vertical skeleton such as a cloth foundation, a wall or a load-bearing wall is constructed of a slate, a mortar, a concrete plate or the like, and one of the adjacent skeletons. A corrugated slate is horizontally provided between the vertical formwork of the above and the other vertical formwork of the body part, and the lower surface of the corrugated slate is parallel to the peaks and valleys of the corrugated slate. The support material is applied so as to be orthogonal to the direction, concrete is continuously and integrally cast between the vertical frames of the skeleton portion and the surface of the corrugated slate, and after curing, the lower surface of the corrugated slate The method for constructing a slab, wherein the skeleton portion and the floor slab are simultaneously constructed by removing only the supporting material.
JP1266295A 1989-10-16 1989-10-16 Slab construction method Expired - Lifetime JP2608336B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1266295A JP2608336B2 (en) 1989-10-16 1989-10-16 Slab construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1266295A JP2608336B2 (en) 1989-10-16 1989-10-16 Slab construction method

Publications (2)

Publication Number Publication Date
JPH03132546A JPH03132546A (en) 1991-06-05
JP2608336B2 true JP2608336B2 (en) 1997-05-07

Family

ID=17428959

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1266295A Expired - Lifetime JP2608336B2 (en) 1989-10-16 1989-10-16 Slab construction method

Country Status (1)

Country Link
JP (1) JP2608336B2 (en)

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS604350B2 (en) * 1974-08-30 1985-02-02 株式会社構建設計研究所 Floor plate method

Also Published As

Publication number Publication date
JPH03132546A (en) 1991-06-05

Similar Documents

Publication Publication Date Title
US3394523A (en) Building enclosure of panels
US3818083A (en) Building method
US7219474B2 (en) Load bearing building panel
US3819143A (en) Formwork for concrete walls
US5676874A (en) Floor form assembly and apparatus used therewith
US4294052A (en) Prefabricated load bearing structure
JP2608336B2 (en) Slab construction method
JP2000234410A (en) Driven form and slab construction method making use thereof
JP3014918B2 (en) Construction method of slab formwork
JPH02248529A (en) Structural block body and constructing method thereof
JPH04108921A (en) Mat foundation panel
JP2545095B2 (en) Structure of the foundation of the building
JPH082260Y2 (en) Thermal insulation floor structural material
JPH0429821B2 (en)
AU750020B3 (en) A load bearing building panel
AU2002234421B2 (en) A load bearing building panel
JP2600411Y2 (en) Column-beam joint structure
JPH0319539Y2 (en)
JPS63206569A (en) Mold frame timbering of slab concrete and timbering construction method
JPS6013158A (en) Construction of metal plate/concrete synthetic wall
JPS58178745A (en) Mold frame material for use with finishing foundation
JP3001210U (en) Insulation board that also serves as a formwork for floor slab construction
JP3001078U (en) Architectural monocoque panel
JP3312945B2 (en) Construction method of concrete structure
JPS634146A (en) Slab execution method

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090213

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090213

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100213

Year of fee payment: 13

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100213

Year of fee payment: 13