JP2584127B2 - Tunnel connection method - Google Patents

Tunnel connection method

Info

Publication number
JP2584127B2
JP2584127B2 JP2325477A JP32547790A JP2584127B2 JP 2584127 B2 JP2584127 B2 JP 2584127B2 JP 2325477 A JP2325477 A JP 2325477A JP 32547790 A JP32547790 A JP 32547790A JP 2584127 B2 JP2584127 B2 JP 2584127B2
Authority
JP
Japan
Prior art keywords
tunnel
ground
wire saw
divided
block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2325477A
Other languages
Japanese (ja)
Other versions
JPH04198583A (en
Inventor
正信 高木
知平 登坂
昭雄 玉井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2325477A priority Critical patent/JP2584127B2/en
Publication of JPH04198583A publication Critical patent/JPH04198583A/en
Application granted granted Critical
Publication of JP2584127B2 publication Critical patent/JP2584127B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28DWORKING STONE OR STONE-LIKE MATERIALS
    • B28D1/00Working stone or stone-like materials, e.g. brick, concrete or glass, not provided for elsewhere; Machines, devices, tools therefor
    • B28D1/02Working stone or stone-like materials, e.g. brick, concrete or glass, not provided for elsewhere; Machines, devices, tools therefor by sawing
    • B28D1/08Working stone or stone-like materials, e.g. brick, concrete or glass, not provided for elsewhere; Machines, devices, tools therefor by sawing with saw-blades of endless cutter-type, e.g. chain saws, i.e. saw chains, strap saws
    • B28D1/088Sawing in situ, e.g. stones from rocks, grooves in walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】 〈産業上の利用分野〉 この発明は、既存トンネルに新トンネルの先端を開通
させる最終工程において、周囲地盤や既存トンネル構造
物の破壊などを伴うことなく、また既存トンネル内の交
通に対する影響を極力少なくした状態で確実に貫通させ
ることの出来るトンネル接続工法に関する。
DETAILED DESCRIPTION OF THE INVENTION <Industrial application field> The present invention relates to a final step of opening the tip of a new tunnel to an existing tunnel without destruction of the surrounding ground or existing tunnel structure, and the present invention. The present invention relates to a tunnel connection method capable of assuredly penetrating a building while minimizing the effect on traffic inside the building.

〈従来の技術〉 使用中の既存トンネルに交差させて、新たに退避用,
連絡用あるいは換気用などのトンネルを新設する場合が
ある。
<Conventional technology> Crossing the existing tunnel in use and newly evacuating,
There may be new tunnels for communication or ventilation.

既存トンネルが山岳トンネルなど比較的堅い岩盤を掘
削することによって形成されたものの場合、新トンネル
を掘削するにあたっては、前記既存トンネルの接続位置
付近まで発破工法などにより岩盤を破砕しつつ掘り進む
ことができる。
When the existing tunnel is formed by excavating a relatively hard rock such as a mountain tunnel, when excavating a new tunnel, it is possible to excavate while crushing the rock by a blasting method or the like to a position near the connection position of the existing tunnel. .

しかしながら、その最終工程、すなわち既存トンネル
との交差位置近傍まで新トンネルの掘削が進行した状態
で、発破を仕掛けた場合にはその振動や騒音,岩石など
の飛散により既存トンネルの構造物に与える影響が大き
い。
However, if the blasting is performed in the final step, that is, when the excavation of the new tunnel has progressed to the vicinity of the intersection with the existing tunnel, the impact on the existing tunnel structure due to the vibration, noise, and scattering of rock etc. Is big.

また既存トンネルでは工事中といえどもある程度交通
量が確保されていることから、発破時においてここを通
行している第3者に与える万が一の影響を考えると極め
て危険である。
In addition, since the existing tunnel has a certain amount of traffic even during construction, it is extremely dangerous considering the potential impact on third parties who pass through the tunnel during blasting.

したがって、この接続位置近傍では前記発破工法に代
わるものとして以下の(イ)〜(ニ)に述べる各種掘削
工法があるが、いずれも問題があった。
Therefore, in the vicinity of the connection position, there are various excavation methods described in the following (a) to (d) as alternatives to the blasting method, but all have problems.

〈発明が解決しようとする課題〉 (イ)静的破砕剤による破砕工法…時間がかかり、破砕
効果が一定でない。また鉄筋入りの構造物は破砕できな
いほか、安全面での問題がある。
<Problems to be solved by the invention> (A) Crushing method using a static crushing agent: It takes time and the crushing effect is not constant. Reinforced structures cannot be crushed and have safety problems.

(ロ)ウオータージェット工法…削岩深度に限界があ
り、非能率的である。
(B) Water jet method: The rock drilling depth is limited and inefficient.

(ハ)スロット削孔…機械が大型化し、使用断面に制約
があるほか、振動騒音を伴う。
(C) Slot drilling: In addition to the large size of the machine, there are restrictions on the section used, and vibration and noise are involved.

(ニ)割岩機…小型機械では割岩能力に限界があるほ
か、作業中に騒音,振動を伴う。
(D) Breaker: Small machines have limited rock breaking capacity, and are accompanied by noise and vibration during work.

この発明は以上の問題を解決するもので、小形の装置
を使用でき、周囲地盤や既存トンネルの構造,交通など
に対して大きな影響を与えることなく両トンネルの接続
位置の掘削作業を行えるトンネル接続工法を提供するも
のである。
SUMMARY OF THE INVENTION The present invention solves the above-mentioned problems, and enables the use of a small-sized device, and a tunnel connection for excavating a connection position between the two tunnels without significantly affecting the surrounding ground, the structure of the existing tunnel, and traffic. It provides a construction method.

〈課題を解決するための手段〉 前記目的を達成するため、この発明工法は、既存トン
ネルに向けて掘り進まれた新トンネルの掘削最終工程に
おいて、両トンネル間の接続部を隔離する地盤を穿孔し
て前記トンネル間に複数の導孔を貫通形成し、前記既存
トンネルを経て隣接する導孔間にワイヤソーをループ状
に挿通し、前記ワイヤソーにテンションをかけつつ無端
状に回転駆動しながら前記新トンネル内で前記ワイヤソ
ーを牽引することにより、前記導孔間を結ぶ線分に沿っ
た切削作業を行ない、かかる切削作業を繰返すことによ
って、前記隔離地盤を周縁地盤から切り離すものであ
る。
<Means for Solving the Problems> In order to achieve the above-mentioned object, this invention method involves drilling a ground for isolating a connection between the two tunnels in the final excavation step of a new tunnel dug toward an existing tunnel. A plurality of holes are formed between the tunnels, and a wire saw is inserted in a loop between adjacent holes through the existing tunnel. The tension is applied to the wire saw, and the wire saw is driven endlessly to rotate the wire saw. By pulling the wire saw in a tunnel, a cutting operation is performed along a line connecting the conductive holes, and the cutting operation is repeated to separate the isolated ground from the peripheral ground.

またこの発明工法では、前記隔離地盤を周囲地盤から
切り離した後に、対向する縦また横方向の前記導孔間に
前記ワイヤソーを挿通し、前記導孔間を結ぶ線分に沿っ
て切削することにより、前記隔離地盤を縦横複数のブロ
ックに分断する。
Further, in the method of the present invention, after the isolation ground is separated from the surrounding ground, the wire saw is inserted between the opposed vertical or horizontal conductive holes, and cut along a line connecting the conductive holes. The isolation ground is divided into a plurality of vertical and horizontal blocks.

さらに前記ブロックに分断する際に、このブロックの
少なくとも一辺が接続された状態で、該ブロックの底辺
部を分断し、分断された底辺部内に搬送台を挿入した後
に前記接続された辺を分断する。
Further, at the time of dividing the block, at least one side of the block is connected, the bottom of the block is divided, and the connected side is divided after inserting the carrier into the divided bottom. .

〈作用〉 以上の構成によれば、ワイヤソーによる切削作業が完
了すると、隔離地盤は周囲地盤より切り離されので、周
囲地盤や既存トンネルに影響を与えることなく破砕,搬
出などの処理を行うことができる。
<Operation> According to the above configuration, when the cutting operation by the wire saw is completed, the isolated ground is separated from the surrounding ground, so that the processing such as crushing and unloading can be performed without affecting the surrounding ground or the existing tunnel. .

また、隔離地盤をさらに各ブロックに切り分ける場合
には、順次各ブロックを引き抜いて搬出することで、両
トンネル間が開通する。
When the isolated ground is further divided into blocks, the tunnels are opened by sequentially pulling out and carrying out each block.

この際各ブロックの下に予め搬送台を敷設しておくこ
とによって、搬送台を引き出せば、分離されたブロック
が容易に引き出される。
At this time, by laying the carrier in advance under each block, if the carrier is pulled out, the separated block can be easily pulled out.

〈実施例〉 以下、この発明の実施例を図面を用いて詳細に説明す
る。
<Example> Hereinafter, an example of the present invention will be described in detail with reference to the drawings.

第1図において、1は堅岩などの地盤Eを掘削して得
られた既存トンネル、2はこの既存トンネル1に交差し
て開口すべく発破工法により既存トンネル1に向けて掘
進された新トンネルである。
In FIG. 1, reference numeral 1 denotes an existing tunnel obtained by excavating a ground E such as a hard rock, and 2 denotes a new tunnel dug into the existing tunnel 1 by a blasting method so as to cross and open the existing tunnel 1. It is.

この新トンネル2の先端と既存トンネル1の交差位置
には工事最終時点で発破工法による限界距離に相当する
距離Lの未掘削の堅岩などからなる地盤(以下隔離地盤
と称する)E1および前記既存トンネル1の外殻を構成す
る構造物であるRCコンクリート1aによって隔離されてい
る。
At the intersection of the tip of the new tunnel 2 and the existing tunnel 1, a ground (hereinafter referred to as an isolated ground) E1 made of unexcavated hard rock or the like having a distance L corresponding to the limit distance by the blasting method at the end of the construction and the existing ground The tunnel 1 is isolated by RC concrete 1a, which is a structure constituting the outer shell.

本発明は、特に、この部分の掘削を行うための工法で
ある。
The invention is, in particular, a construction method for excavating this part.

第2図〜第5図はその第一実施例を示している。 2 to 5 show the first embodiment.

まず、前記新トンネル2の断面形状に沿って、その前
面に位置する隔離地盤E1の表面に、第2図に鎖線で示す
ように、線分を描写して、掘削すべき部分を縦横複数に
区画する。
First, along the cross-sectional shape of the new tunnel 2, a line segment is drawn on the surface of the isolated ground E1 located in front of the new tunnel 2 as shown by a chain line in FIG. Partition.

次に、描かれた線分と新トンネル2の周縁との交点を
穿孔することにより、同第2図,第3図に示すように、
前記地盤E1およびRCコンクリート1aを突き抜けて既存ト
ンネル1に到達する複数の導孔3を縦横に貫通形成す
る。
Next, by drilling the intersection between the drawn line segment and the periphery of the new tunnel 2, as shown in FIGS.
A plurality of conducting holes 3 penetrating the ground E1 and the RC concrete 1a and reaching the existing tunnel 1 are formed vertically and horizontally.

次に、ダイヤモンドワイヤソー4を各導孔3のうちの
一番近い隣合う一対の導孔3間に挿通し、前記既存トン
ネル1側を経てループ状に引き回す。
Next, the diamond wire saw 4 is inserted between a pair of nearest neighboring conductive holes 3 among the conductive holes 3, and is routed in a loop shape through the existing tunnel 1 side.

このワイヤソー4およびこれを含む切削装置は無振
動,無騒音で堅岩などを切削するための公知の装置であ
り、新トンネル1の内部でワイヤソー4をガイドプーリ
5によりガイドした状態で一方のループ端をテンション
プーリ6に懸架する。
The wire saw 4 and a cutting device including the wire saw 4 are known devices for cutting hard rock and the like without vibration and without noise. One of the loops is formed in a state where the wire saw 4 is guided by the guide pulley 5 inside the new tunnel 1. The end is suspended on the tension pulley 6.

この準備作業後、テンションプーリ6を配置した回転
および牽引装置7を駆動すると、前記ワイヤソー4はテ
ンションをかけられた状態で無端状に回転駆動しつつ矢
印方向に牽引され、他方のループ端は隔離地盤E1を切削
しつつ新トンネル2側に向けて接近する。
After this preparatory work, when the rotation and traction device 7 on which the tension pulley 6 is disposed is driven, the wire saw 4 is pulled in the direction of the arrow while being driven endlessly while being tensioned, and the other loop end is isolated. Approach the new tunnel 2 while cutting the ground E1.

最終的にワイヤソー4の他方ループ端が隔離地盤E1の
表面に到達すると、前記隣り合う導孔3を結ぶ線分に沿
った切削作業を終了する。
When the other loop end of the wire saw 4 finally reaches the surface of the isolated ground E1, the cutting operation along the line connecting the adjacent conductive holes 3 is completed.

以上の切削作業を新トンネル1の周囲に沿って順次繰
返すことで、隔離地盤E1は第4図に示すように、導孔3
同士を結んで新トンネル2の内周形状にほぼ沿った立体
形状で周囲地盤Eから切り離される(既存トンネル1側
でもRCコンクリートは1aは、新トンネル2の断面形状に
ほぼ沿って周囲から切り離される)。
By repeating the above-mentioned cutting operation sequentially along the periphery of the new tunnel 1, the isolated ground E1 becomes as shown in FIG.
It is separated from the surrounding ground E in a three-dimensional shape almost along the inner peripheral shape of the new tunnel 2 by connecting each other (RC concrete 1a is also cut off from the surroundings along the cross-sectional shape of the new tunnel 2 even on the existing tunnel 1 side) ).

したがって、その後の処理は、この切り離された隔離
地盤E1の内部を、例えば、静的破砕剤や割岩機による粉
砕工法によって粉砕し、細分化しても周囲地盤Eに対す
る影響や、既存トンネル1の構造に対する影響を未然に
防止できる。
Therefore, in the subsequent processing, the inside of the separated ground E1 is crushed by, for example, a crushing method using a static crushing agent or a rock crusher, and even if the crushing is performed on the ground, the influence on the surrounding ground E, the structure of the existing tunnel 1, and Can be prevented beforehand.

この場合、さらに好ましくは、縦方向および横方向に
対向する導孔3間にそれぞれ前記ワイヤソー4を挿通
し、上記と同じ切削作業を繰返すと、最終的には第5図
に示すように隔離地盤E1の内部は各導孔3間の縦横の線
分に囲われた断面積×L(隔離地盤E1の距離)の長方形
のブロックE1−1に分断され(RCコンクリート側も同様
である)、分割搬出が可能となる。
In this case, more preferably, the wire saw 4 is inserted between the conductive holes 3 facing each other in the vertical direction and the horizontal direction, and when the same cutting operation as described above is repeated, finally, as shown in FIG. The inside of E1 is divided into rectangular blocks E1-1 having a cross-sectional area × L (distance of the isolated ground E1) surrounded by vertical and horizontal lines between the conductive holes 3 (the same applies to the RC concrete side) and divided. Unloading is possible.

その後は搬出用重機などの利用によって上から順に各
ブロックE1−1を引き抜きつつ搬出作業を行うことによ
って、新トンネル2の断面形状に沿った空洞が前記既存
トンネル1側に開口し、両トンネル1,2間が開通するの
である。
Thereafter, by carrying out the unloading operation while pulling out each block E1-1 in order from the top by using a heavy equipment for unloading, a cavity along the cross-sectional shape of the new tunnel 2 opens to the existing tunnel 1 side, and both tunnels 1 , 2 is opened.

以上の各工程において、既存トンネル1内の交通が規
制されるのは、主に導孔3の穿孔時とワイヤソー4を既
存トンネル1側に引き回す時および切削初期時点であ
り、それ以外は交通に与える大きな影響はない。
In each of the above steps, the traffic in the existing tunnel 1 is regulated mainly at the time of drilling the guide hole 3, when the wire saw 4 is routed to the existing tunnel 1 and at the initial cutting time, and otherwise at the time of traffic. There is no significant effect.

なお、新トンネル2の断面が大きい場合や隔離地盤E1
の距離Lが長い場合には、第6図に示すように縦横の線
分同士の交点にも導孔3aを穿設し、上下左右に隣合う導
孔3a間にワイヤソー4を挿通して、切削作業を行っても
良い。
When the cross section of the new tunnel 2 is large or when the isolated ground E1
In the case where the distance L is long, as shown in FIG. 6, a conducting hole 3a is formed at the intersection of the vertical and horizontal line segments, and the wire saw 4 is inserted between the conducting holes 3a adjacent vertically and horizontally. A cutting operation may be performed.

第7図,第8図は、分割される各ブロックE1−1の引
き抜き作業性を考慮してなされた第二実施例を示してい
る。
FIGS. 7 and 8 show a second embodiment in which the workability of pulling out each of the divided blocks E1-1 is taken into consideration.

図において、各ブロックE1−1の底辺部に相当する箇
所は、前記ワイヤソー4によって予め分断され、この分
断された部位E1−2には、ブロック搬送台8が挿入され
る。
In the figure, a portion corresponding to the bottom of each block E1-1 is divided in advance by the wire saw 4, and a block carrier 8 is inserted into the divided portion E1-2.

この搬送台8は鉄板などからなる載荷荷重に耐え、か
つ下面を滑りやすくした構造物であり、その引出し端側
には手掛かり用の把手部8aが設けてある。
The transfer table 8 is a structure made of an iron plate or the like that withstands a load and has a slippery lower surface, and has a handle 8a for a cue at a drawer end side.

この搬送台8を挿入した状態で、上部側を含む他の片
を前記導孔3a(または3)間を結ぶ線分に沿って縦横に
切削すれば、残りの上部および側部の3辺が分断されブ
ロックE1−1は、前記搬送台8上に載置される。
In the state where the transfer table 8 is inserted, another piece including the upper side is cut lengthwise and crosswise along a line connecting the conductive holes 3a (or 3), so that the remaining three sides of the upper part and the side part are cut. The divided block E1-1 is placed on the transfer table 8.

したがって、把手部8aを手掛かりとして搬送台8を引
き出すことによりブロックE1−1は搬送台8上に載置さ
れた状態で隔離地盤E1の壁面より抜き取られる。
Therefore, the block E1-1 is pulled out from the wall surface of the isolation ground E1 while being placed on the carrier 8 by pulling out the carrier 8 using the handle 8a as a clue.

この実施例では、切削作業とこれによって切り分けら
れたブロックE1−1の引き抜き作業を交互に繰返すこと
によって、順次新トンネル2の先端が既存トンネル1側
に開口する。
In this embodiment, the cutting operation and the extraction operation of the block E1-1 cut out by the cutting operation are alternately repeated, so that the tip end of the new tunnel 2 is sequentially opened to the existing tunnel 1 side.

なお、第7,8図に示す実施例では、ブロックE1−1の
上部および側部のいずれか一辺が接続された状態で底辺
部を分断して搬送台8を挿入することができる。
In the embodiment shown in FIGS. 7 and 8, it is possible to insert the carrier 8 by cutting off the bottom portion while any one of the upper and side portions of the block E1-1 is connected.

《発明の効果》 以上各実施例によって詳細に説明したように、この発
明によるトンネル接続工法にあっては、既存トンネルに
新トンネルを接続する際に、簡易な装置を使用しつつワ
イヤソーによる切削作業を行うことができるとともに、
周囲の地盤や既存トンネルの構造、交通などに対して大
きな影響を与えることなく、両トンネル間の接続部を隔
離する地盤の掘削作業を容易に行うことができる。
<< Effects of the Invention >> As described in detail in the above embodiments, in the tunnel connection method according to the present invention, when connecting a new tunnel to an existing tunnel, a cutting operation using a wire saw is performed while using a simple device. Along with
The excavation work for the ground that isolates the connection between the two tunnels can be easily performed without significantly affecting the surrounding ground, the structure of the existing tunnel, and traffic.

また、周囲地盤から切り離された隔離地盤をさらに各
ブロックに切り分けることによって、これら各ブロック
を分割して搬出することができ、搬出作業を完了すると
新トンネルは既存トンネルに開通する。
Further, by separating the isolated ground separated from the surrounding ground into blocks, each of these blocks can be divided and carried out. When the carrying out work is completed, the new tunnel is opened to the existing tunnel.

また切り分けられたブロックの引抜き作業に際して
は、ブロックの底辺側に予め設置された搬送台を引き出
すことにより、ブロックを引き出すことができるため、
ブロックの搬出作業がさらに簡単となる。
In addition, at the time of the work of pulling out the cut block, since the block can be pulled out by pulling out the carrier that is previously set on the bottom side of the block,
The work of unloading the blocks is further simplified.

【図面の簡単な説明】[Brief description of the drawings]

第1図はこの発明を適用する既存トンネルと新トンネル
の交差位置の状態を示す説明図、第2図ないし第5図は
この発明の第一実施例を示す説明図、第6図は第一実施
例における変形例を示す説明図、第7図,第8図はこの
発明の第二実施例を示す説明図である。 1……既存トンネル 1a……RCコンクリート 2……新トンネル 3、3a……導孔 4……ワイヤソー 8……搬送台 E……地盤 E1……隔離地盤 E1−1……ブロック E1−2……切り分け部位
FIG. 1 is an explanatory view showing the state of the intersection of an existing tunnel and a new tunnel to which the present invention is applied, FIGS. 2 to 5 are explanatory views showing a first embodiment of the present invention, and FIG. FIGS. 7 and 8 are explanatory views showing a modification of the embodiment, and FIGS. 7 and 8 are explanatory views showing a second embodiment of the present invention. 1 ... Existing tunnel 1a ... RC concrete 2 ... New tunnel 3,3a ... Hole 4 ... Wire saw 8 ... Carrier E ... Soil E1 ... Isolated ground E1-1 ... Block E1-2 ... … Segmentation site

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】既存トンネルに向けて掘り進まれた新トン
ネルの掘削最終工程において:両トンネル間の接続部を
隔離する地盤を穿孔して前記トンネル間に複数の導孔を
貫通形成し、前記既存トンネルを経て隣接する導孔間に
ワイヤソーをループ状に挿通し、前記ワイヤソーにテン
ションをかけつつ無端状に回転駆動しながら前記新トン
ネル内で前記ワイヤソーを牽引することにより、前記導
孔間を結ぶ線分に沿った切削作業を行ない、かかる切削
作業を繰返すことによって前記隔離地盤を周囲地盤から
切り離すことを特徴とするトンネル接続工法。
In a final step of excavating a new tunnel dug into an existing tunnel: drilling a ground for isolating a connection between the two tunnels and forming a plurality of through holes between the tunnels; A wire saw is inserted in a loop between adjacent holes through an existing tunnel, and the wire saw is pulled in the new tunnel while being endlessly rotated while applying tension to the wire saw, so that the gap between the holes is reduced. A tunnel connection method comprising performing a cutting operation along a connecting line segment and separating the isolated ground from a surrounding ground by repeating the cutting operation.
【請求項2】前記隔離地盤を周囲地盤から切り離した後
に、対向する縦または横方向の前記導孔間に前記ワイヤ
ソーを挿通し、前記導孔間を結ぶ線分に沿って切削する
ことにより、前記隔離地盤を縦横複数のブロックに分断
することを特徴とする請求項1記載のトンネル接続工
法。
2. After separating the isolated ground from the surrounding ground, insert the wire saw between the opposed vertical or horizontal conductive holes, and cut along the line connecting the conductive holes, 2. The tunnel connection method according to claim 1, wherein the isolation ground is divided into a plurality of blocks vertically and horizontally.
【請求項3】前記ブロックに分断する際に、このブロッ
クの少なくとも一辺が接続された状態で、該ブロックの
底辺部を分断し、分断された底辺部内に搬送台を挿入し
た後に前記接続された辺を分断することを特徴とする請
求項2記載のトンネル接続工法。
3. When the block is divided into blocks, at least one side of the block is connected, the bottom of the block is divided, and after the carrier is inserted into the divided bottom, the connection is established. 3. The tunnel connection method according to claim 2, wherein the side is divided.
JP2325477A 1990-11-29 1990-11-29 Tunnel connection method Expired - Fee Related JP2584127B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2325477A JP2584127B2 (en) 1990-11-29 1990-11-29 Tunnel connection method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2325477A JP2584127B2 (en) 1990-11-29 1990-11-29 Tunnel connection method

Publications (2)

Publication Number Publication Date
JPH04198583A JPH04198583A (en) 1992-07-17
JP2584127B2 true JP2584127B2 (en) 1997-02-19

Family

ID=18177322

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2325477A Expired - Fee Related JP2584127B2 (en) 1990-11-29 1990-11-29 Tunnel connection method

Country Status (1)

Country Link
JP (1) JP2584127B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2521256C1 (en) * 2013-03-18 2014-06-27 Общество с ограниченной ответственностью "НПП СК МОСТ" Method of tunnelling
JP2016102369A (en) * 2014-11-28 2016-06-02 株式会社奥村組 Construction method for invert in existing tunnel
CN107587879A (en) * 2017-09-15 2018-01-16 袁奥 Method for tunnel construction

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109366770A (en) * 2018-12-06 2019-02-22 中铁隧道集团二处有限公司 It is a kind of to receive the rope saw cut construction method that portal is abolished for shield
KR20200091786A (en) * 2019-01-23 2020-07-31 최인환 Wire-saw excavation apparatus that can change the cutting line according to the cutting section tunnel excavation method using the same
GB2582713B (en) * 2020-04-17 2021-05-26 Kingston William Method of shoreline wave energy capture
CN112360478B (en) * 2020-11-27 2022-06-14 中铁工程装备集团有限公司 Special-shaped hard rock tunneling machine for sawing and shearing combined rock breaking and construction method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01223294A (en) * 1988-03-02 1989-09-06 Komatsu Ltd Ring cutting machine

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2521256C1 (en) * 2013-03-18 2014-06-27 Общество с ограниченной ответственностью "НПП СК МОСТ" Method of tunnelling
JP2016102369A (en) * 2014-11-28 2016-06-02 株式会社奥村組 Construction method for invert in existing tunnel
CN107587879A (en) * 2017-09-15 2018-01-16 袁奥 Method for tunnel construction

Also Published As

Publication number Publication date
JPH04198583A (en) 1992-07-17

Similar Documents

Publication Publication Date Title
JP2584127B2 (en) Tunnel connection method
KR102154862B1 (en) Non-vibration excavating methods for tunnel or rock slope by cutting and splitting
KR100923328B1 (en) Rock Excavation Method Using the Free Surface of Large Diameter
JPH10205272A (en) Construction method of tunnel and widening method thereof
WO2011107818A1 (en) Method of cutting foundation elements in the ground
JPS5894598A (en) Level drilling method and drill guide used therein
JP2940402B2 (en) Rock tunnel excavation method using arch machine
KR100537064B1 (en) lower part bench excavation method of a tunnel
JP3486103B2 (en) How to blast rock
KR102656665B1 (en) Vibration-free excavation construction method
KR102228560B1 (en) Method for rock cutting and tunnel excavation using shaped charge and wire saw
KR100445098B1 (en) method for blasting center-cut of tunnel
JP2587309B2 (en) Protective structure of concrete underground structure and its construction method
RU2058464C1 (en) Method for making foundation
JP2812366B2 (en) Destruction and removal of walls of concrete structures
JPH02164996A (en) Excavating method for hard rock bed
JP2650539B2 (en) Construction method of underground diaphragm wall
JP6808255B1 (en) Obstacle crushing method and obstacle removal method
JPH08120670A (en) Removing method for underground pile
JPS5988598A (en) Widening of underground construction
JPH07301005A (en) Demolition method of foundation
WO2022241540A1 (en) Vehicle for excavating and excavation method using the same
JP2003041882A (en) Tunnel section widening method
JPH10292767A (en) Excavating method of tunnel
JP2000204574A (en) Reconstruction method for underground structure

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees