JP2545198B2 - Reservoir device - Google Patents

Reservoir device

Info

Publication number
JP2545198B2
JP2545198B2 JP6041493A JP4149394A JP2545198B2 JP 2545198 B2 JP2545198 B2 JP 2545198B2 JP 6041493 A JP6041493 A JP 6041493A JP 4149394 A JP4149394 A JP 4149394A JP 2545198 B2 JP2545198 B2 JP 2545198B2
Authority
JP
Japan
Prior art keywords
plate portion
ground
concrete pouring
lid
end body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP6041493A
Other languages
Japanese (ja)
Other versions
JPH07252871A (en
Inventor
順也 福室
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TSURUMI KONKURIITO KK
Original Assignee
TSURUMI KONKURIITO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TSURUMI KONKURIITO KK filed Critical TSURUMI KONKURIITO KK
Priority to JP6041493A priority Critical patent/JP2545198B2/en
Publication of JPH07252871A publication Critical patent/JPH07252871A/en
Application granted granted Critical
Publication of JP2545198B2 publication Critical patent/JP2545198B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Sewage (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、雨水を一時的に貯溜す
る遊水池装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a reservoir device for temporarily storing rainwater.

【0002】[0002]

【従来の技術】従来、遊水池を地下に配置し大量の雨水
を一時的に貯溜するとともに、遊水池に蓋体を設け、そ
の上部を人工基盤として利用する遊水池装置としては、
例えば図7ないし図10に示す構造が知られている。
2. Description of the Related Art Conventionally, as a reservoir device in which a reservoir is placed underground to temporarily store a large amount of rainwater, a lid is provided on the reservoir, and the upper portion of the reservoir is used as an artificial base,
For example, the structures shown in FIGS. 7 to 10 are known.

【0003】この図7ないし図10に示す遊水池装置
は、略箱状の外支柱体41a と中支柱体41b を配設してい
る。そして、外支柱体41a は、平面状の基板部44に地盤
に略垂直に平板状の外壁部45を略L字状に形成し、この
外壁部45の上端に上板部46を基板部44と同方向に設け、
この上板部46の先端と基板部44の先端間に外壁部45と平
行に雨水などの貯溜水の流通を確保する流通口47を開口
する壁部48を設けて箱状に形成している。また、中支柱
体41b は、外支柱体41a の外壁部45の代わりに流通口47
を開口する壁部48を設けた箱状に形成している。
The water reservoir device shown in FIGS. 7 to 10 has a substantially box-shaped outer strut body 41a and a middle strut body 41b. In the outer strut body 41a, a flat plate-shaped outer wall portion 45 is formed in a substantially L shape on the flat substrate portion 44 substantially perpendicular to the ground, and an upper plate portion 46 is formed on the upper end of the outer wall portion 45. Set in the same direction as
A wall portion 48 is provided between the tip of the upper plate portion 46 and the tip of the substrate portion 44 in parallel with the outer wall portion 45 to open a circulation port 47 for ensuring the circulation of stored water such as rainwater to form a box shape. . Further, the middle strut body 41b is provided with a flow port 47 instead of the outer wall portion 45 of the outer strut body 41a.
It is formed in a box shape having a wall portion 48 that opens.

【0004】そして、この外支柱体41a を外壁部45が直
線状になるように、壁部48を対向させて同方向に接合す
るとともに、中支柱体41b を壁部48が直線状となるよう
に、壁部48を所定の間隙でそれぞれ対向させて外支柱体
41a ,41a 間に複数列並設している。
Then, the outer strut body 41a is joined in the same direction with the wall portions 48 facing each other so that the outer wall portion 45 becomes linear, and the middle strut body 41b becomes linear in the wall portion 48. The wall parts 48 facing each other with a predetermined gap.
Multiple rows are arranged in parallel between 41a and 41a.

【0005】さらに、外支柱体41a と中支柱体41b との
基板部44,44間に面一に現場コンクリート打ちにより底
部49を形成し、外支柱体41a と中支柱体41b との上端部
間に平板状の蓋体52を架橋載置し、外支柱体41a 、中支
柱体41b および蓋体52の並列する両端側を現場コンクリ
ート打ちにて形成した端板部53にて閉塞し、この端板部
53に雨水などの貯溜する水を流入する流入口54および流
出させる流出口55を形成して、箱状に遊水池装置本体56
を形成している。
Further, a bottom 49 is formed between the base parts 44, 44 of the outer strut body 41a and the middle strut body 41b by in-situ concrete pouring so that the bottom 49 is formed between the outer strut body 41a and the middle strut body 41b. A flat plate-like lid body 52 is placed on the bridge, and both end sides of the outer strut body 41a, the middle strut body 41b and the lid body 52 which are arranged in parallel are closed by end plate portions 53 formed by on-site concrete pouring, and this end is closed. Board
An inflow port 54 for inflowing stored water such as rainwater and an outflow port 55 for outflowing water are formed in 53 to form a box-like main body 56 of the water reservoir device.
Is formed.

【0006】[0006]

【発明が解決しようとする課題】ところで、上記図7な
いし図10に示す構造の遊水池装置において、複数の外
支柱体41a 、中支柱体41b および蓋体52を並設するた
め、各部材の寸法誤差、各部材の接合部分の目地伸びに
よる誤差などにより、並設方向の端部が揃わない。この
ため、外支柱体41a 、中支柱体41b および蓋体52の並列
する両端側を、平板状のプレキャストブロックの端板部
53にて閉塞し、ボルトやインサートなどの組付手段によ
り接合すると、誤差による並設方向の端部のばらつきに
より隙間が形成されて漏水などが生じ、地盤を損傷した
り、遊水池装置本体56の接合部分を損傷するなどの問題
がある。さらに、誤差が大きいと、端板部53にて閉塞で
きなくなる。
By the way, in the water reservoir device having the structure shown in FIGS. 7 to 10, a plurality of outer strut bodies 41a, middle strut bodies 41b, and lid bodies 52 are arranged side by side. Due to dimensional errors, errors due to joint expansion of the joints of the members, etc., the ends in the arranging direction are not aligned. For this reason, the outer strut body 41a, the middle strut body 41b, and the lid body 52 in parallel with each other are provided at the end plate portions of the flat precast block.
If it is closed at 53 and joined by an assembly means such as bolts or inserts, gaps are formed due to variations in the ends in the parallel installation direction due to errors, resulting in water leaks, damage to the ground, and the main body of the water reservoir device 56 There is a problem such as damage to the joint part of. Further, if the error is large, the end plate portion 53 cannot be closed.

【0007】このため、誤差が生じるような場合には、
従来は、外支柱体41a 、中支柱体41b および蓋体52の並
列する両端側の全面を、現場コンクリート打ちにて平板
状に端板部53を形成して閉塞し、箱状に遊水池装置本体
56を形成している。しかしながら、この現場コンクリー
ト打ち作業は煩雑で時間が掛かるとともに、遊水池装置
本体56の高さ寸法が比較的高い場合には、型枠工や配筋
工に足場が必要となり、さらには、遊水池装置本体56は
箱状に閉塞されて形成されるため、現場コンクリート打
ち作業後に内側に設置された足場や型枠などを撤去する
作業が非常に煩雑となり、遊水池装置本体56の施行性が
低下する。
Therefore, when an error occurs,
Conventionally, the outer strut body 41a, the middle strut body 41b, and the lid body 52 are closed in parallel with each other by forming end plate portions 53 in a flat plate shape by in-situ concrete pouring to form a box-like water reservoir device. Body
Forming 56. However, this on-site concrete pouring work is complicated and time-consuming, and if the height of the main body 56 of the water reservoir is relatively high, scaffolding is required for the formwork and rebar work. Since the device body 56 is closed and formed in a box shape, the work of removing the scaffolding, formwork, etc. installed inside after the site concrete pouring work becomes very complicated, and the effectiveness of the water reservoir device body 56 is reduced. To do.

【0008】そして、施工性が煩雑であるため、現場コ
ンクリート打ちにて端板部53を形成して遊水池装置本体
56の端部を閉塞する際には、この端部を面積が小さくな
るように、外支柱体41a 、中支柱体41b および蓋体52を
配置しなければならず、汎用性が限られ、施工性も低下
する。
Since the workability is complicated, the end plate portion 53 is formed by concrete pouring on site to form the main body of the water reservoir device.
When closing the end portion of 56, the outer strut body 41a, the middle strut body 41b, and the lid body 52 must be arranged so that the area of this end portion becomes small, which limits versatility and construction. Sex is also reduced.

【0009】また、蓋体52を載置するための外支柱体41
a および中支柱体41b は、遊水池装置本体56の構造強度
などのため、外支柱体41a および中支柱体41b の壁部48
が流入した雨水などの貯溜水を流出する流出口55の両側
を囲むように配置せざるおえない。なお、この遊水池装
置本体56は、貯溜水を流出口55から流出させるために若
干流出口55に向けて若干傾斜するように形成されてい
る。
Further, an outer support body 41 for mounting the lid body 52.
Because of the structural strength of the main body 56 of the water reservoir, the a and the middle pillar body 41b are not covered by the wall 48
There is no choice but to arrange it so as to surround both sides of the outflow port 55 through which the stored water such as rainwater that flows in flows out. The main body 56 of the water reservoir is formed so as to be slightly inclined toward the outflow port 55 in order to let the stored water flow out from the outflow port 55.

【0010】このため、貯溜水の流出口55に向けて流下
する流下方向と交差する方向に板面を有する外支柱体41
a および中支柱体41b の端板部53と連続する壁部48によ
り、土砂やごみなどを混入する貯溜水の一部が流出口55
から流出されずに滞留してしまい、しいては土砂やごみ
などが滞積し、貯溜容積が減少するなどの問題がある。
For this reason, the outer strut body 41 having a plate surface in a direction intersecting with the flow-down direction of the stored water flowing out toward the outlet 55.
Due to the wall portion 48 that is continuous with the end plate portion 53 of the a and the middle strut body 41b, a part of the stored water that mixes dirt and dust is discharged from the outlet 55.
There is a problem that it accumulates without being discharged from the outlet, eventually depositing dirt and dust, and reducing the storage volume.

【0011】本発明は、上記問題点に鑑みなされたもの
で、貯溜水を滞留させず施行性が向上する遊水池装置を
提供することを目的とする。
The present invention has been made in view of the above problems, and it is an object of the present invention to provide a retaining basin device in which stored water is not retained and the workability is improved.

【0012】[0012]

【課題を解決するための手段】本発明の遊水池装置は、
地盤上に載置される基板部、この基板部に前記地盤に対
して略垂直に形成された平板状の壁部およびこの壁部の
上端に形成された載置部を有し、この載置部を間隔を介
して対向させて前記壁部を直線状にして並設する複数の
支柱体と、前記対向する載置部間に載置される蓋体と、
前記複数並設された支柱体の並設方向の両端側に位置し
て配設される端部体とを備え、流入口および流出口を設
けた遊水池装置において、前記端部体は、前記地盤上に
載置され上面が前記流出口に向けて傾斜するテーパ面を
設けた板状で前記支柱体の基板部と現場コンクリート打
ち用の間隙を介して対向して配設される底板部と、この
底板部の一縁に前記地盤に対して略垂直で前記支柱体の
壁部に流通路を介して略垂直に形成された端板部と、こ
の端板部の上端縁に前記底板部に対して略平行に設けら
れ前記蓋体と現場コンクリート打ち用の間隙を介して対
向する天板部とを備え、前記端部体およびこの端部体に
対向する前記支柱体および前記蓋体は、現場コンクリー
ト打ち用の間隙の相対する面にそれぞれ対向して突出す
る骨組金具を備え、これら骨組金具を覆って前記現場コ
ンクリート打ち用の間隙に現場コンクリート打ちするこ
とにより前記端部体と前記支柱体および蓋体とを一連に
接続したものである。
The reservoir device of the present invention comprises:
The base part is placed on the ground, a flat plate-shaped wall part is formed on the base part substantially perpendicular to the ground, and a mounting part is formed on the upper end of the wall part. A plurality of pillar bodies that are arranged in parallel so that the wall portions are linearly arranged with the portions facing each other with a gap, and a lid body mounted between the facing mounting portions,
An end body arranged at both ends in the direction of juxtaposition of the plurality of column bodies arranged side by side, wherein the end body is a water reservoir device provided with an inflow port and an outflow port. A bottom plate portion which is placed on the ground and has an upper surface provided with a taper surface which is inclined toward the outflow port, and which is arranged so as to face the substrate portion of the pillar body with a gap for in-situ concrete pouring. An end plate portion formed at one edge of the bottom plate portion substantially perpendicular to the ground and substantially perpendicular to the wall portion of the support body through a flow passage, and the bottom plate portion at an upper end edge of the end plate portion. A top plate portion that is provided substantially parallel to the lid body and is opposed to the end body through a gap for in-situ concrete pouring, and the end body and the pillar body and the lid body that face the end body are , Equipped with skeleton metal fittings that project to face the opposite surfaces of the gap for concrete pouring on site It is obtained by connecting the strut and the lid and said end member to a series by situ concrete hitting the gap for said site concrete strike over these scaffold bracket.

【0013】[0013]

【作用】本発明の遊水池装置は、支柱体の並設方向の両
端側に配設する端部体を、底板部、端板部および天板部
にて略コ字状に形成する。そして、端部体およびこの端
部体に対向する支柱体および蓋体に現場コンクリート打
ち用の間隙に突設した骨組金具を覆って現場コンクリー
ト打ちして端部体と支柱体および蓋体とを一連に接続し
て形成する。このため、並設方向の誤差を現場コンクリ
ート打ち用の間隙で吸収され、間隙に骨組金具を覆って
現場コンクリート打ちするのみで、現場コンクリート打
ち部分が少なくなり、施行性が向上する。また、支柱体
の壁部に流通路を介して端板部を形成した端部体の底板
部に、流出口に向けて傾斜するテーパ面を設けたため、
貯溜水は滞留することなく流出する。
In the water reservoir device according to the present invention, the end bodies arranged at both ends of the support body in the juxtaposed direction are formed in a substantially U shape by the bottom plate portion, the end plate portion and the top plate portion. Then, the end body and the pillar body and the lid body facing the end body are covered with the frame fitting projecting in the gap for the concrete pouring on site to perform the concrete pouring on site, and the end body, the pillar body and the lid body are attached. It is formed by connecting in series. For this reason, the error in the parallel installation direction is absorbed by the gap for in-situ concrete pouring, and the in-situ concrete pouring portion is reduced only by covering the skeleton metal fittings in the gap and in-situ concrete pouring, and the workability is improved. Further, since the bottom plate portion of the end body in which the end plate portion is formed on the wall portion of the strut body via the flow passage is provided with the tapered surface inclined toward the outflow port,
The stored water flows out without staying.

【0014】[0014]

【実施例】以下、本発明の遊水池装置の一実施例の構成
を図面を参照して説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The construction of an embodiment of the reservoir device according to the present invention will be described below with reference to the drawings.

【0015】また、図1ないし図5において、1は遊水
池装置本体で、この遊水池装置本体1は、図示しない鉄
筋などの鋼材を内部に埋設したコンクリートにてそれぞ
れ一体的にプレキャストによりブロック状に形成され
た、支柱体としてのボックスカルバート2、蓋体3、低
端部体4aおよび高端部体4bにて箱状に形成されている。
Further, in FIGS. 1 to 5, reference numeral 1 is a main body of the water reservoir device, and the main body 1 of the water reservoir device is a block shape integrally made of concrete in which a steel material such as a reinforcing bar (not shown) is embedded inside by precasting. The box culvert 2 serving as a column body, the lid body 3, the low-end body 4a, and the high-end body 4b, which are formed in the above, are formed in a box shape.

【0016】そして、ボックスカルバート2は、平面が
図示しない地盤上に接触して載置される平板状の基板部
6を設けている。なお、地盤は、表面が平面状となるよ
うに形成されている。
The box culvert 2 is provided with a flat plate-shaped substrate portion 6 whose flat surface is placed in contact with the ground (not shown). The ground is formed so that the surface is flat.

【0017】さらに、ボックスカルバート2は、基板部
6の一端縁から地盤に対して略垂直に設けられた平板状
の外壁部7と、基板部6の他端縁から外壁部7と同方向
に略平行に設けられた壁部8とを有し、外壁部7および
壁部8の上端には、基板部6と略平行に平板状の上板部
9が設けられ、略角筒状に形成されている。
Further, the box culvert 2 has a flat plate-like outer wall portion 7 which is provided substantially perpendicular to the ground from one end edge of the base plate portion 6, and the same direction as the outer wall portion 7 from the other end edge of the base plate portion 6. The outer wall 7 and the wall 8 are provided substantially parallel to each other, and a flat plate-shaped upper plate 9 is provided substantially parallel to the substrate 6 at the upper ends of the outer wall 7 and the wall 8 to form a substantially rectangular tube. Has been done.

【0018】そして、基板部6の壁部8が設けられた側
の端面には、図3に示すように、ボックスカルバート2
を構成するコンクリートにて内部に埋設された鉄筋など
の鋼材の一部が、補強金具10として突出形成されてい
る。
Then, as shown in FIG. 3, the box culvert 2 is provided on the end surface of the substrate portion 6 on the side where the wall portion 8 is provided.
A part of a steel material such as a reinforcing bar embedded in the concrete forming the above is formed as a reinforcing metal fitting 10 in a protruding manner.

【0019】また、壁部8は上下方向の一側縁には、図
1、図3および図4に示すように、略台形状に切り欠か
れた切欠部12が形成され、この切欠部12により、壁部8
の基板部6側の基端は基板部6の幅寸法より短い幅寸法
の幅狭部13が形成され、壁部8の上部は上板部9の幅寸
法と略同寸法の幅広部14が形成されている。
As shown in FIGS. 1, 3 and 4, the wall portion 8 has a notch 12 formed in a substantially trapezoidal shape at one side edge in the vertical direction. The wall 8
A narrow portion 13 having a width dimension shorter than the width dimension of the substrate portion 6 is formed at the base end of the substrate portion 6 side, and a wide portion 14 having substantially the same dimension as the width dimension of the upper plate portion 9 is formed on the upper portion of the wall portion 8. Has been formed.

【0020】さらに、壁部8の上端には、図3に示すよ
うに、上端縁に沿ってL字状に切れ欠かれた載置部15が
形成されている。
Further, at the upper end of the wall portion 8, as shown in FIG. 3, a mounting portion 15 is formed which is cut out in an L shape along the upper edge.

【0021】一方、蓋体3は、長方形の平板状に形成さ
れている。
On the other hand, the lid 3 is formed in a rectangular flat plate shape.

【0022】また、低端部体4aおよび高端部体4bは、平
面が地盤上に接触して載置される平板状の底板部17と、
この底板部17の一縁に地盤に対して略垂直に設けられた
端板部18a ,18b と、この端板部18a ,18b の上端縁に
底板部17と同方向に略平行に設けられた天板部19とを有
し、断面略コ字状に形成されている。
The low-end body 4a and the high-end body 4b are flat plate-like bottom plates 17 that are placed with their flat surfaces in contact with the ground.
The end plate portions 18a and 18b are provided on one edge of the bottom plate portion 17 substantially perpendicular to the ground, and the upper end edges of the end plate portions 18a and 18b are provided substantially parallel to the bottom plate portion 17 in the same direction. It has a top plate portion 19 and is formed into a substantially U-shaped cross section.

【0023】そして、低端部体4aは、上下方向の高さ寸
法が、ボックスカルバート2の壁部8の高さ寸法と略同
寸法に形成され、高端部体4bは、上下方向の高さ寸法
が、ボックスカルバート2の壁部8の高さ寸法より高い
寸法に形成されている。
The height of the lower end body 4a in the vertical direction is approximately the same as the height of the wall portion 8 of the box culvert 2, and the height of the high end body 4b is in the vertical direction. The dimension is formed to be higher than the height dimension of the wall portion 8 of the box culvert 2.

【0024】また、低端部体4aおよび高端部体4bは、底
板部17と天板部19との突出側の先端面に、低端部体4aお
よび高端部体4bを構成するコンクリートに内部に埋設さ
れた鉄筋などの鋼材の一部が、骨組金具20として外方に
突出形成されている。
Further, the low-end body 4a and the high-end body 4b are formed in the concrete forming the low-end body 4a and the high-end body 4b at the tip end surfaces of the bottom plate portion 17 and the top plate portion 19 on the protruding side. A part of a steel material such as a reinforcing bar buried in is formed as a frame fitting 20 so as to project outward.

【0025】そして、ボックスカルバート2は、内側に
壁部8,8が所定の距離を介して対向するように、幅方
向に連続して基板部6の下面が地盤上に接地されて並列
に設置されている。さらに、対向するボックスカルバー
ト2の載置部15,15間には、蓋体3が長手方向の両端部
を載置されて配設されている。
The box culvert 2 is installed in parallel so that the lower surface of the substrate portion 6 is grounded continuously in the width direction so that the wall portions 8 face each other with a predetermined distance inside. Has been done. Further, between the mounting portions 15 and 15 of the box culvert 2 facing each other, the lid body 3 is disposed with both longitudinal end portions mounted thereon.

【0026】なお、並設されたボックスカルバート2お
よび蓋体3の並設方向の両端側に位置するボックスカル
バート2および蓋体3は、並設方向の端面に、ボックス
カルバート2および蓋体3を構成するコンクリートに埋
設された鉄筋などの鋼材の一部が、骨組金具20として外
方に突出形成されている。
The box culverts 2 and the lids 3 located at both ends of the box culverts 2 and the lids 3 juxtaposed in the juxtaposed direction have the box culverts 2 and the lids 3 on the end faces in the juxtaposed direction. A part of a steel material such as a reinforcing bar embedded in the constituent concrete is formed as a frame fitting 20 so as to project outward.

【0027】また、ボックスカルバート2は、隣接する
ボックスカルバート2,2の幅広部14,14の幅方向の端
部が当接され、幅狭部13,13間には切欠部12,12により
貯溜水が流通可能な流通口22が形成されて並設されてい
る。
Further, in the box culvert 2, the ends of the wide portions 14, 14 of the adjacent box culverts 2, 2 in the width direction are brought into contact with each other, and the narrow portions 13, 13 are stored by the notches 12, 12. A circulation port 22 through which water can flow is formed and arranged side by side.

【0028】さらに、並設されたボックスカルバート2
および蓋体3の並設方向の一端側に、所定の間隙、例え
ば15〜20cm程度の間隔を介して、骨組金具20が突出
する端面を対向させて、低端部体4aおよび高端部体4bが
複数並列に配設され、箱状に遊水池装置本体1が形成さ
れている。
Further, box culverts 2 arranged side by side
And, one end side in the juxtaposed direction of the lid body 3 is faced with the end faces from which the frame fittings 20 project through a predetermined gap, for example, a gap of about 15 to 20 cm, and the low end body 4a and the high end body 4b. Are arranged in parallel, and the water reservoir device main body 1 is formed in a box shape.

【0029】なお、遊水池装置本体1の四隅に位置する
低端部体4aおよび高端部体4bは、端板部18a ,18b が側
面にも連続してL字状に形成されている。さらに、高端
部体4bは、上端面が面一となるように、底板部17をボッ
クスカルバート2の基板部6より低い位置となるように
配設されている。
The low-end body 4a and the high-end body 4b located at the four corners of the main body 1 of the water reservoir have end plate portions 18a, 18b formed continuously in L-shape on their side surfaces. Further, the high end body 4b is arranged such that the bottom plate portion 17 is located at a position lower than the base plate portion 6 of the box culvert 2 so that the upper end surface is flush.

【0030】また、低端部体4aおよび高端部体4bの配設
により、対向するボックスカルバート2の壁部8との間
に、貯溜水が流通可能な流通路23が形成されている。
By disposing the low end body 4a and the high end body 4b, a flow passage 23 through which the stored water can flow is formed between the wall portion 8 of the box culvert 2 facing each other.

【0031】そして、並設されたボックスカルバート
2,2の基板部6,6間には、上面が面一となるように
現場コンクリート打ちにて底部24が形成されている。さ
らに、ボックスカルバート2および蓋体3と低端部体4a
および高端部体4bとの骨組金具20が位置する間隙に、図
6に示すように、骨組金具20を覆うように埋設させて現
場コンクリート打ちにてコンクリート25を形成し、この
現場打ちコンクリート25にてボックスカルバート2およ
び蓋体3と低端部体4aおよび高端部体4bとが接続され
て、遊水池装置本体1が箱状に形成されている。
Then, a bottom portion 24 is formed between the base plate portions 6 and 6 of the box culverts 2 and 2 arranged side by side by concrete pouring on site so that the top surfaces are flush with each other. Further, the box culvert 2 and the lid 3 and the lower end body 4a
As shown in FIG. 6, it is embedded so as to cover the skeleton metal fittings 20 in the gap where the skeleton metal fittings 20 are located with the high end body 4b, and concrete 25 is formed by on-site concrete pouring. The box culvert 2 and the lid body 3 are connected to the low-end body 4a and the high-end body 4b to form the reservoir body 1 in the shape of a box.

【0032】また、遊水池装置本体1の低端部体4aの一
側に位置する低端部体4aの1つには、端板部18a の上部
に位置して雨水などが流入する流入口27が開口形成さ
れ、この流入口27には雨水などを遊水池装置本体1に流
入させる導入管28が接続されている。
Further, one of the lower end bodies 4a located on one side of the lower end body 4a of the main body 1 of the water reservoir is provided with an inflow port which is located above the end plate portion 18a and through which rainwater or the like flows in. An opening 27 is formed, and an inlet pipe 28 for introducing rainwater or the like into the water reservoir device body 1 is connected to the inlet 27.

【0033】さらに、遊水池装置本体1の高端部体4bの
うちの略中央に位置する高端部体4bには、端板部4bの基
端部に、遊水池装置本体1内に流入し貯溜する貯溜水を
遊水池装置本体1外に流出する流出口29が開口形成さ
れ、この流出口29には、流出口29を介して流出する貯溜
水を放水する流出路30が接続されている。
Further, in the high end body 4b of the high end body 4b of the main body 1 of the water reservoir, which is located substantially at the center, the base end of the end plate 4b flows into the main body 1 of the water reservoir, and is stored. An outlet 29 for discharging the stored water out of the main body 1 of the reservoir is formed with an opening, and an outlet 30 for discharging the stored water flowing out through the outlet 29 is connected to the outlet 29.

【0034】また、遊水池装置本体1の下流側である流
出口29の近傍には、流出口29を囲むように囲い壁31にて
貯溜部32が区画形成されている。なお、この囲い壁31の
高さは、ボックスカルバート2の並設にて形成される流
通口22の上端より若干低くなるように形成されている。
さらに、この貯溜部32の外側には、貯溜部32を囲むよう
に底面が貯溜部32の底面と略同じ深さの樋部33が形成さ
れている。
In the vicinity of the outlet 29 on the downstream side of the main body 1 of the water reservoir, a storage portion 32 is defined by an enclosure wall 31 so as to surround the outlet 29. The height of the surrounding wall 31 is formed to be slightly lower than the upper end of the flow port 22 formed by the box culverts 2 arranged side by side.
Further, on the outside of the storage portion 32, a gutter portion 33 is formed so that the bottom surface is substantially the same depth as the bottom surface of the storage portion 32 so as to surround the storage portion 32.

【0035】そして、流通路23の底部を構成する高端部
体4bの底板部17の上面には、流出口29を囲む貯溜部32に
向けて下方に傾斜するテーパ面35を設けた集水部36が、
並設された両端側に位置する高端部体4bが高く、次第に
樋部33に向けて連通するように低くなるように傾斜し
て、現場コンクリート打ちにて形成されている。
Then, on the upper surface of the bottom plate portion 17 of the high end body 4b constituting the bottom portion of the flow passage 23, there is provided a water collecting portion provided with a tapered surface 35 which is inclined downward toward the reservoir portion 32 surrounding the outlet 29. 36 is
The high end bodies 4b located on both ends side by side are high, and are formed by in-situ concrete pouring to incline so that they gradually become lower so as to communicate with the gutter portion 33.

【0036】また、貯溜部32の囲い壁31の下部には、遊
水池装置本体1の底部24の上面に対応する位置に貯溜水
の一部を貯溜部32内に流入させるリーク孔37が開口形成
されている。
A leak hole 37 is formed in the lower portion of the enclosing wall 31 of the storage section 32 at a position corresponding to the upper surface of the bottom section 24 of the main body 1 of the water reservoir device to allow a part of the stored water to flow into the storage section 32. Has been formed.

【0037】さらに、流出口29を開口する高端部体4bの
天板部19には、作業者が貯溜部32内に立ち入ることがで
きるように、点検口38が開口形成されている。また、上
板部9に点検口38が開口形成されたボックスカルバート
2を、適宜の位置に配設して、遊水池装置本体1が形成
されている。なお、点検口38の下方には、はしご39が設
けられ、常時は、点検口38は図示しないマンホールカバ
ーなどにて閉塞されている。
Further, an inspection port 38 is formed in the top plate portion 19 of the high end body 4b which opens the outflow port 29 so that an operator can enter the storage portion 32. Further, the box culvert 2 having the inspection port 38 formed in the upper plate portion 9 is arranged at an appropriate position to form the water reservoir device body 1. A ladder 39 is provided below the inspection port 38, and the inspection port 38 is normally closed by a manhole cover or the like (not shown).

【0038】なお、この遊水池装置本体1は、底面が下
流側である流出口29側に若干傾斜するように配置形成さ
れている。
The main body 1 of the water reservoir is arranged and formed such that its bottom surface is slightly inclined toward the outlet 29 which is the downstream side.

【0039】次に、上記実施例の組立動作を示す。Next, the assembling operation of the above embodiment will be described.

【0040】まず、遊水池装置本体1を設置する場所を
掘削して平滑に図示しない基盤面を形成し、この基盤面
の上面に所定の厚さで礫や砂利などを敷き詰め、表面を
平面状に平滑にして地盤を形成する。なお、遊水池装置
本体1の下流側となる位置は、所定の深さにさらに掘削
して、貯溜部32および樋部33が位置する部分が上流側に
向けて平面凸字状に掘り下げられて平滑に形成してお
く。
First, the place where the main body 1 of the water reservoir is installed is excavated to form a smooth base surface (not shown), and gravel, gravel or the like is spread over the upper surface of the base surface to a flat surface. To form a ground. In addition, the position on the downstream side of the main body 1 of the basin is further excavated to a predetermined depth, and the portion where the storage part 32 and the gutter part 33 are located is dug in a plane convex shape toward the upstream side. Form smoothly.

【0041】一方、あらかじめ、鉄筋などの鋼材を埋設
したコンクリートにて、ボックスカルバート2、蓋体3
および端部体4を、それぞれ一体的にプレキャストによ
りブロック状に形成する。
On the other hand, the box culvert 2 and the lid 3 are made of concrete in which a steel material such as a reinforcing bar is embedded in advance.
The end body 4 and the end body 4 are integrally formed in a block shape by precasting.

【0042】そして、図示しない地盤上に、ボックスカ
ルバート2を、内側に壁部8を所定の距離を介して対向
させ、外壁部7を面一となるように幅方向に連続して基
板部6の下面を地盤上に接触させ、隣接するボックスカ
ルバート2,2の幅広部14,14の幅方向の端部間を当接
させ、幅狭部13,13間に切欠部12,12により貯溜水が流
通可能な流通口22を形成して並列に設置する。なお、下
流側の端部に並設されたボックスカルバート2は、一段
低く凸字状に掘削された部分を介して対向するように並
設する。
Then, on the ground not shown, the box culvert 2 is made to face the inside with the wall portion 8 at a predetermined distance, and the outer wall portion 7 is continuous in the width direction so as to be flush with the substrate portion 6. The bottom surface of the box is brought into contact with the ground, the widthwise ends of the wide portions 14, 14 of the adjacent box culverts 2, 2 are brought into contact with each other, and the cutouts 12, 12 are provided between the narrow portions 13, 13 to store water. A distribution port 22 through which the liquid can be distributed is formed and installed in parallel. The box culverts 2 arranged side by side at the downstream end are arranged side by side so as to face each other through the portion excavated in a convex shape that is one step lower.

【0043】さらに、対向するボックスカルバート2,
2の載置部15,15間に、蓋体3を長手方向の両端部を載
置して配設する。
Furthermore, the opposing box culverts 2,
Between the two mounting portions 15 and 15, the lid body 3 is disposed with both ends in the longitudinal direction mounted.

【0044】なお、並設されたボックスカルバート2お
よび蓋体3の並設方向の両端側には、幅方向の一端面に
骨組金具20を突出形成するボックスカルバート2および
蓋体3を、骨組金具20が並設方向の両端方向に突出する
ように配設する。また、ボックスカルバート2の上板部
9に点検口38が開口形成され、外壁部7の壁部8に対向
する側の内面に点検口38の下方に位置してはしご39が設
けられたボックスカルバート2を、適宜の間隔で配設す
る。なお、各点検口38は、図示しないマンホールカバー
などにて閉塞しておく。
At both ends of the box culvert 2 and the lid 3 arranged side by side in the juxtaposed direction, the box culvert 2 and the lid 3 having the frame fittings 20 projectingly formed on one end face in the width direction are provided. 20 are arranged so as to project toward both ends in the arranging direction. Further, a box culvert having an inspection port 38 formed in the upper plate portion 9 of the box culvert 2 and a ladder 39 provided below the inspection port 38 on the inner surface of the outer wall portion 7 facing the wall portion 8 is provided. 2 are arranged at appropriate intervals. Each inspection port 38 is closed by a manhole cover or the like (not shown).

【0045】次に、並設されたボックスカルバート2お
よび蓋体3の並設方向の上流側となる位置に、低端部体
4aの突出する骨組金具20をボックスカルバート2および
蓋体3の骨組金具20に向け、かつ、ボックスカルバート
2および蓋体3の端面と低端部体4aの端面間に、例えば
15〜20cm程度の現場コンクリート打ち用の間隔を介
して、ボックスカルバート2および蓋体3の並設方向と
垂直方向である幅方向に低端部体4aを複数並設する。な
お、端板部18a に流入口27が開口する低端部体4aを、複
数並列する低端部体4aの端部に位置させて配設する。
Next, at the position on the upstream side of the juxtaposed box culvert 2 and lid 3 in the juxtaposed direction, the low end body is placed.
The protruding frame fitting 20 of 4a is directed toward the frame bracket 20 of the box culvert 2 and the lid 3, and between the end faces of the box culvert 2 and the cover 3 and the end face of the low end part 4a, for example, about 15 to 20 cm. A plurality of low-end parts 4a are arranged side by side in the width direction which is a direction perpendicular to the direction in which the box culverts 2 and the lid 3 are arranged side by side with an interval for on-site concrete pouring. In addition, the low end body 4a having the inflow port 27 opened in the end plate portion 18a is arranged at the end portion of the plurality of parallel low end bodies 4a.

【0046】さらに、並設されたボックスカルバート2
および蓋体3の並設方向の下流側となる位置で、一段深
く掘削された地盤上に、高端部体4bを、低端部体4aと同
様に骨組金具20を対向させて現場コンクリート打ち用の
間隔を介して、ボックスカルバート2および蓋体3の並
設方向と幅方向に複数並設する。なお、この高端部体4b
の並設に際しては、高端部体4bの上端面がボックスカル
バート2の上端面と面一となり、高端部体4bの底板部17
がボックスカルバート2の基板部6より低い位置となる
ように配設する。また、天板部19に点検口38を開口形成
し、端板部18bに流出口29を開口形成する高端部体4b
は、一段低く掘削された部分で、並列される複数の高端
部体4bの略中央に位置させて配設する。
Further, the box culverts 2 arranged side by side
And at the position on the downstream side in the direction in which the lids 3 are arranged side by side, on the ground excavated one step deep, the high end body 4b is made to face the frame metal fitting 20 in the same manner as the low end body 4a, and for concrete pouring on site. A plurality of box culverts 2 and lids 3 are arranged side by side in the width direction and the box culverts 2 with a space of. In addition, this high end body 4b
In parallel installation, the upper end surface of the high end body 4b becomes flush with the upper end surface of the box culvert 2 and the bottom plate portion 17 of the high end body 4b is formed.
Is arranged at a position lower than the substrate portion 6 of the box culvert 2. Further, a high end body 4b having an inspection opening 38 formed in the top plate portion 19 and an outlet 29 formed in the end plate portion 18b.
Is a portion excavated one step lower, and is arranged at a position approximately at the center of the plurality of high end bodies 4b arranged in parallel.

【0047】次に、並設したボックスカルバート2,2
の基板部6,6間に、基板部6,6の対向する端面から
突出する補強金具10,10を埋設して、基板部6の上面と
面一となるように現場コンクリート打ちにて底部24を形
成する。この際、一段低く凸字状に掘削された部分の地
盤上も連続して、高端部体4bの底板部17に突出する骨組
金具20を埋設するように形成する。さらに、ボックスカ
ルバート2および蓋体3と低端部体4aおよび高端部体4b
との骨組金具20が位置する現場コンクリート打ち用の間
隙に、骨組金具20を覆うように埋設して現場コンクリー
ト打ちして現場打ちコンクリート25を形成し、この現場
打ちコンクリート25により、ボックスカルバート2、蓋
体3、低端部体4aおよび高端部体4bを一体的に接続し
て、遊水池装置本体1を内部に貯溜空間を形成して箱状
に形成する。
Next, box culverts 2 and 2 arranged in parallel
Reinforcing metal fittings 10, 10 projecting from the opposite end surfaces of the board parts 6, 6 are embedded between the board parts 6, 6 of the board parts 6, 6 and the bottom part 24 is made by concrete pouring so as to be flush with the upper surface of the board part 24. To form. At this time, the skeleton metal fittings 20 projecting from the bottom plate portion 17 of the high end body 4b are formed so as to be embedded continuously on the ground where the portion is excavated in a convex shape that is one step lower. Further, the box culvert 2 and the lid 3, the low end body 4a and the high end body 4b.
In the space for in-situ concrete pouring where the skeleton metal fitting 20 is located, it is embedded so as to cover the skeleton metal fitting 20 and struck in-situ concrete to form the in-situ concrete 25. With this in-situ concrete 25, the box culvert 2, The lid body 3, the low-end body 4a, and the high-end body 4b are integrally connected to each other to form a reservoir space inside the water reservoir device body 1 and form a box shape.

【0048】なお、遊水池装置本体1は、底面が下流側
の流出口29側に若干傾斜するように形成する。
The main body 1 of the water reservoir is formed so that its bottom surface is slightly inclined toward the outlet 29 on the downstream side.

【0049】そして、一段低くなっている底部24の上面
に、外側に樋部33を、内側に貯溜部32を区画するよう
に、コ字状に囲い壁31を高端部体4bの端板部18b に連続
させて現場コンクリート打ちにて形成する。
Then, on the upper surface of the bottom portion 24 which is lower by one step, the trough portion 33 is defined on the outer side and the storage portion 32 is defined on the inner side. It is formed by continuous concrete pouring on 18b.

【0050】さらに、流入口27および流出口29にそれぞ
れ導入管28および流出路30を接続する。
Further, an inlet pipe 28 and an outlet passage 30 are connected to the inlet 27 and the outlet 29, respectively.

【0051】また、雨水などの貯溜に際しては、雨水な
どが、導入管28から流入口27を介して遊水池装置本体1
内の貯溜空間に流入して、この流入した雨水を、一時貯
溜して、順次下流側に流下し、一部は樋部33からリーク
孔37を介して貯溜部32に流入し、一部は、囲い壁31を乗
り越えて貯溜部32に流入し、貯溜水を貯溜部32内に向け
て開口する流出口29から流出路30に流出して放流する。
When storing rainwater or the like, rainwater or the like is introduced from the introduction pipe 28 through the inflow port 27 into the main body 1 of the water reservoir device.
The rainwater that has flowed into the inside of the storage space is temporarily stored and then flows down to the downstream side, part of which flows into the storage part 32 through the leak hole 37 and part of which flows into the storage part 32. , Overcoming the surrounding wall (31) and flowing into the reservoir (32), and the stored water is discharged from the outlet (29) opening toward the inside of the reservoir (32) to the outflow passage (30).

【0052】次に、上記実施例の作用を説明する。Next, the operation of the above embodiment will be described.

【0053】地盤上に載置される平板状の底板部17と、
この底板部17に地盤に対して略垂直に設けた端板部18a
,18b と、この端板部18a ,18b に底板部17と同方向
に略垂直に設けた天板部19とにて略コ字状に低端部体4a
および高端部体4bを形成する。
A flat plate-shaped bottom plate portion 17 placed on the ground,
An end plate portion 18a provided on the bottom plate portion 17 substantially perpendicular to the ground
, 18b and a top plate portion 19 provided on the end plate portions 18a, 18b in a direction substantially perpendicular to the bottom plate portion 17 in a substantially U-shape.
And the high end body 4b is formed.

【0054】そして、これら低端部体4aおよび高端部体
4bを、複数並設されたボックスカルバート2およびこれ
らボックスカルバート2の載置部15,15間に載置された
蓋体3の並設方向の両端側に、底板部17およびをボック
スカルバート2の基板部6と現場コンクリート打ち用の
間隙を介して対向させるとともに、天板部19を蓋体3と
現場コンクリート打ち用の間隙を介して対向させ、端板
部18a ,18b の内面側とボックスカルバート2の壁部8
の端部とに流通路23を形成して並設する。さらに、現場
コンクリート打ち用の間隙に相対する骨組金具20を覆っ
て現場コンクリート打ちし、低端部体4aおよび高端部体
4bとボックスカルバート2および蓋体3とを一連に接続
して形成する。
And, these low end body 4a and high end body
4b, a plurality of box culverts 2 arranged in parallel, and a bottom plate portion 17 and a box culvert 2 of the box culvert 2 on both end sides in the juxtaposed direction of the lid 3 mounted between the mounting portions 15 and 15 of these box culverts 2. The top plate portion 19 is opposed to the base plate portion 6 through a gap for in-situ concrete pouring, and the top plate portion 19 is opposed to the lid body 3 through a gap for in-situ concrete pouring, and the inner surface side of the end plate portions 18a and 18b and the box culvert. Wall part 2
A flow passage 23 is formed in parallel with the end portion of the. Further, on-site concrete driving is performed by covering the frame metal fittings 20 facing the gap for on-site concrete driving, and the low end body 4a and the high end body are
4b and the box culvert 2 and the lid 3 are connected in series to form.

【0055】このため、目地伸びなどの誤差や各構成物
品の寸法誤差などによる並設方向の誤差を、現場コンク
リート打ち用の間隙で吸収でき、間隙に骨組金具20を覆
って現場コンクリート打ちするのみでよく、現場コンク
リート打ち部分が少なくなり、施行性が向上する。ま
た、低端部体4aおよび高端部体4bが略コ字状であるた
め、低端部体4aおよび高端部体4bの端板部18a ,18b と
ボックスカルバート2の壁部8との間に貯溜水が流通可
能な流通路23を開口形成でき、低端部体4aおよび高端部
体4bの底板部17に流出口29に向けて傾斜するテーパ面35
を有する集水部36を設けたため、従来のように貯溜水が
低端部体4aおよび高端部体4bとボックスカルバート2の
壁部8とにて滞留することを防止でき、貯溜水全量を流
出口29に誘導でき、確実に流出できる。
Therefore, an error in joint direction due to an error such as joint extension and a dimensional error of each component can be absorbed in the space for concrete pouring on site, and only the frame metal fitting 20 is covered in the space and concrete pouring on site is performed. The workability of the concrete is improved by reducing the number of concrete pouring parts on site. Moreover, since the low-end body 4a and the high-end body 4b are substantially U-shaped, between the end plate portions 18a and 18b of the low-end body 4a and the high-end body 4b and the wall portion 8 of the box culvert 2. A flow passage (23) through which stored water can flow can be formed as an opening, and a tapered surface (35) inclined toward the outflow port (29) at the bottom plate portion (17) of the low end body (4a) and the high end body (4b).
Since the water collecting portion 36 having the above is provided, it is possible to prevent the stored water from accumulating in the low end body 4a and the high end body 4b and the wall portion 8 of the box culvert 2 as in the conventional case, and the total amount of stored water flows. It can be guided to the outlet 29 and can surely flow out.

【0056】さらに、低端部体4aおよび高端部体4bが略
コ字状であるため、従来のように、低端部体4aおよび高
端部体4bを平板状のプレキャストブロックに形成したも
のは、施工の際、低端部体4aおよび高端部体4bを立位状
態に保持具などにて保持して連結接続する必要がなく、
保持具なしでも地盤上に載置でき、施工性を向上でき
る。
Further, since the low end body 4a and the high end body 4b are substantially U-shaped, the one in which the low end body 4a and the high end body 4b are formed in a flat plate-shaped precast block as in the conventional case is During construction, it is not necessary to hold the low-end body 4a and the high-end body 4b in a standing position with a holder or the like to connect and connect them.
It can be placed on the ground without a retainer, improving workability.

【0057】また、地盤状態や設置条件などにより、例
えば遊水池装置本体1を細長状に形成する必要がある場
合、従来は、低端部体4aおよび高端部体4bを現場コンク
リート打ちにて形成する場合には、その施工が煩雑とな
ることから、面積が小さい側面である遊水池装置本体1
の長手方向の両端部に低端部体4aおよび高端部体4bを現
場コンクリート打ちにて形成しなければならないが、上
記実施例は施工性の向上に伴い、遊水池装置本体1の側
面のいずれを端面として形成でき、地盤状態や設置条件
などにかかわらず、遊水池装置本体1を容易に形成でき
る。
Further, when it is necessary to form the main body 1 of the basin in an elongated shape depending on the ground condition and installation conditions, conventionally, the low-end body 4a and the high-end body 4b are formed by in-situ concrete pouring. If this is the case, the construction will be complicated, so the main body 1
The low-end body 4a and the high-end body 4b must be formed on site by concrete pouring at both ends in the longitudinal direction of the above. Can be formed as an end face, and the water reservoir device body 1 can be easily formed regardless of the ground condition, installation conditions, and the like.

【0058】なお、上記実施例において、支柱体として
のボックスカルバート2を略角筒状に形成して説明した
が、基板部6を2つに分割した状態で、基板部6に略L
字状に外壁部7を設けた側部体と、基板部6に略T字状
に壁部8を設けた支柱部とを対向して並設し、側部体お
よび支柱部と、支柱部間とにそれぞれ蓋体3を載置する
構成の遊水池装置本体1や、各部分を分割して、平板状
の外壁部7、蓋体3および別途流通口22を有する平板状
に形成した支柱体となる壁部8とを組み立て遊水池装置
本体1を形成する構成などでも同様の効果が得られる。
In the above embodiment, the box culvert 2 serving as the support pillar is formed in a substantially rectangular tube shape. However, the substrate portion 6 is divided into two and the substrate portion 6 is substantially L-shaped.
A side body having a character-shaped outer wall portion 7 and a support portion having a substantially T-shaped wall portion 8 provided on the substrate portion 6 are arranged in parallel to face each other. The main body 1 of the water reservoir having a configuration in which the lid 3 is placed in the space, and the pillars formed by dividing each part into the flat outer wall portion 7, the lid 3, and the separate flow port 22. The same effect can be obtained by a configuration in which the body wall portion 8 is assembled to form the water retention device body 1.

【0059】また、ボックスカルバート2の壁部8に設
けた切欠部12の形状は、貯溜水が流通可能に流通口22を
形成するいずれの形状でもよい。さらに、ボックスカル
バート2,2間に現場コンクリート打ちにて底部24を形
成して説明したが、ボックスカルバート2の基板部6や
底部24の一部を開口し、この開口から貯溜水の一部を地
盤に浸透させる浸透式としてもよい。また、囲い壁31に
て貯溜部32を区画形成せず、流出口29が貯溜空間に向け
て直接開口するようにしてできる。
The shape of the notch 12 provided in the wall portion 8 of the box culvert 2 may be any shape that forms the flow port 22 so that the stored water can flow. Furthermore, although the bottom 24 was formed between the box culverts 2 and 2 by in-situ concrete pouring, a part of the base 6 or the bottom 24 of the box culvert 2 was opened, and a part of the stored water was opened from this opening. It may be an infiltration type that penetrates into the ground. Further, the storage part 32 may not be defined by the surrounding wall 31, and the outlet 29 may be opened directly toward the storage space.

【0060】そして、ボックスカルバート2、蓋体3、
低端部体4aおよび高端部体4bなど各部材の組み立てに際
しては、ボルトや網材などにて緊結したり、接着剤など
にて一体的に形成したり、互いにせり合わせて一体的に
形成したり、係合などにより一体的に組み立て形成する
などいずれの方法を用いてもよい。
Then, the box culvert 2, the lid body 3,
When assembling each member such as the low-end body 4a and the high-end body 4b, they are tightly connected with each other by bolts, nets, etc., integrally formed with an adhesive, etc. Alternatively, any method such as integrally assembling by engagement or the like may be used.

【0061】また、骨組金具20として各構成部品を構成
する鉄筋などの鋼材の一部を突出して形成させて説明し
たが、各構成部品の形成の際に別途専用の骨組金具20の
一端側を埋設させて形成したり、別途骨組金具20を現場
コンクリート打ち用の間隔の端面に打ち込み形成するな
ど、現場打ちされるコンクリート25の硬化前の保持、硬
化後の補強、低端部体4aおよび高端部体4bと支柱体およ
び蓋体3との連結強度の向上などが図れる構成であれば
いずれの形状および形成方法でもよい。
Further, the frame fitting 20 has been described by forming a part of the steel material such as the reinforcing bar forming each component so as to project. However, when forming each component, one end side of the dedicated frame fitting 20 is separately attached. It is formed by embedding, or by separately forming the frame metal fitting 20 on the end surface of the space for concrete pouring on site, holding concrete 25 that is cast on site before hardening, reinforcing after hardening, low end part 4a and high end Any shape and formation method may be used as long as the connection strength between the body 4b and the support body and the lid 3 can be improved.

【0062】[0062]

【発明の効果】本発明の遊水池装置によれば、支柱体の
並設方向の両端側に配設する端部体を略コ字状に形成
し、端部体と支柱体および蓋体に対向して突出する骨組
金具を覆って現場コンクリート打ち用の間隙に現場コン
クリート打ちして一連に接続するため、並設方向の誤差
を現場コンクリート打ち用の間隙で吸収できるととも
に、骨組金具を覆って現場コンクリート打ちするのみ
で、現場コンクリート打ち部分を少なくでき、施行性を
向上できる。さらに、端部体が略コ字状であるため、地
盤状に載置するのみで容易に施工できるとともに、端部
体の底板部に流出口に向けて傾斜するテーパ面を設けた
ため、貯溜水を滞留させずに流出でき、貯溜空間を有効
的に利用できる。
EFFECTS OF THE INVENTION According to the water retention device of the present invention, the end bodies disposed on both ends of the support body in the juxtaposed direction are formed in a substantially U shape, and the end body, the support body and the lid body are formed. By covering the frame fittings projecting oppositely and connecting them in series in the space for concrete pouring on site, the error in the parallel installation direction can be absorbed by the space for concrete pouring, and the frame fittings can be covered. Only by pouring concrete on site, it is possible to reduce the portion of concrete pouring on site and improve the workability. Furthermore, since the end body is approximately U-shaped, it can be easily installed by placing it on the ground, and the bottom plate of the end body is provided with a tapered surface that slopes toward the outflow port. Can flow out without staying, and the storage space can be effectively used.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の遊水池装置の一実施例を示す一部を切
り欠いた図5のA−A断面図である。
FIG. 1 is a cross-sectional view taken along the line AA of FIG. 5 in which an embodiment of a water retention device of the present invention is partially cut away.

【図2】同上図5のB−B断面図である。FIG. 2 is a sectional view taken along line BB of FIG. 5 above.

【図3】同上図5のC−C断面図である。3 is a sectional view taken along line CC of FIG.

【図4】同上図5のD−D断面図である。FIG. 4 is a sectional view taken along line DD of FIG.

【図5】同上遊水池装置本体を示す一部を切り欠いた平
面図である。
FIG. 5 is a partially cutaway plan view showing the same water reservoir device body as above.

【図6】同上現場コンクリート打ち間隙の部分を示す断
面図である。
FIG. 6 is a cross-sectional view showing a portion of the above-mentioned site concrete pouring gap.

【図7】従来の遊水池装置の一実施例を示す一部を切り
欠いた平面図である。
FIG. 7 is a partially cutaway plan view showing an example of a conventional reservoir device.

【図8】同上図7のE−E断面図である。8 is a sectional view taken along line EE of FIG.

【図9】同上図7のF−F断面図である。FIG. 9 is a sectional view taken along line FF of FIG.

【図10】同上図7のG−G断面図である。10 is a sectional view taken along line GG of FIG. 7 above.

【符号の説明】[Explanation of symbols]

1 遊水池装置本体 2 支柱体としてのボックスカルバート 3 蓋体 4a 低端部体 4b 高端部体 6 基板部 8 壁部 15 載置部 17 底板部 18a ,18b 端板部 19 天板部 20 骨組金具 23 流通路 25 現場打ちコンクリート 27 流入口 29 流出口 35 テーパ面 1 Reservoir device main body 2 Box culvert as pillar body 3 Lid body 4a Low end body 4b High end body 6 Board part 8 Wall part 15 Mounting part 17 Bottom plate part 18a, 18b End plate part 19 Top plate part 20 Frame bracket 23 Inlet 25 In-situ concrete 27 Inlet 29 Outlet 35 Tapered surface

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 地盤上に載置される基板部、この基板部
に前記地盤に対して略垂直に形成された平板状の壁部お
よびこの壁部の上端に形成された載置部を有し、この載
置部を間隔を介して対向させて前記壁部を直線状にして
並設する複数の支柱体と、前記対向する載置部間に載置
される蓋体と、前記複数並設された支柱体の並設方向の
両端側に位置して配設される端部体とを備え、流入口お
よび流出口を設けた遊水池装置において、 前記端部体は、 前記地盤上に載置され上面が前記流出口に向けて傾斜す
るテーパ面を設けた板状で前記支柱体の基板部と現場コ
ンクリート打ち用の間隙を介して対向して配設される底
板部と、 この底板部の一縁に前記地盤に対して略垂直で前記支柱
体の壁部に流通路を介して略垂直に形成された端板部
と、 この端板部の上端縁に前記底板部に対して略平行に設け
られ前記蓋体と現場コンクリート打ち用の間隙を介して
対向する天板部とを備え、 前記端部体およびこの端部体に対向する前記支柱体およ
び前記蓋体は、 現場コンクリート打ち用の間隙の相対する面にそれぞれ
対向して突出する骨組金具を備え、 これら骨組金具を覆って前記現場コンクリート打ち用の
間隙に現場コンクリート打ちすることにより前記端部体
と前記支柱体および蓋体とを一連に接続したことを特徴
とした遊水池装置。
1. A substrate portion mounted on the ground, a flat plate-shaped wall portion formed on the substrate portion substantially perpendicular to the ground, and a mounting portion formed at an upper end of the wall portion. Then, a plurality of pillar bodies in which the mounting portions are opposed to each other with a space therebetween and the wall portions are linearly arranged side by side, a lid body mounted between the opposing mounting portions, and An end body arranged at both ends of the installed support body in the direction of juxtaposition, and a water reservoir device provided with an inflow port and an outflow port, wherein the end body is on the ground. A bottom plate portion that is placed and has a tapered surface whose upper surface is inclined toward the outlet, and that is disposed so as to face the base plate portion of the pillar body with a gap for in-situ concrete pouring; An end plate portion that is formed substantially perpendicular to the ground on one edge of the portion and that is formed substantially perpendicular to the wall portion of the pillar body through a flow passage; The top plate portion provided substantially parallel to the bottom plate portion at the upper end edge of the end plate portion and facing the top plate portion with a gap for in-situ concrete pouring, the end body and this end body The column body and the lid body facing each other are provided with frame fittings projecting so as to oppose to the opposite surfaces of the gap for in-situ concrete pouring. By doing this, the end body, the pillar body, and the lid body are connected in series.
JP6041493A 1994-03-11 1994-03-11 Reservoir device Expired - Lifetime JP2545198B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6041493A JP2545198B2 (en) 1994-03-11 1994-03-11 Reservoir device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP6041493A JP2545198B2 (en) 1994-03-11 1994-03-11 Reservoir device

Publications (2)

Publication Number Publication Date
JPH07252871A JPH07252871A (en) 1995-10-03
JP2545198B2 true JP2545198B2 (en) 1996-10-16

Family

ID=12609887

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6041493A Expired - Lifetime JP2545198B2 (en) 1994-03-11 1994-03-11 Reservoir device

Country Status (1)

Country Link
JP (1) JP2545198B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100462517C (en) * 2006-06-28 2009-02-18 贵阳铝镁设计研究院 Building method of pulp placed rockfill ash dyke

Also Published As

Publication number Publication date
JPH07252871A (en) 1995-10-03

Similar Documents

Publication Publication Date Title
JP5594629B2 (en) Construction method of tunnel bottom structure with drainage equipment
US6332303B1 (en) Method of building underground structure
KR100988806B1 (en) The water-storage tank of assembly type and method for constructing thereof
JP5610632B2 (en) Inspection port structure in rainwater storage facilities
KR100731773B1 (en) The water-storage tank worthy an undercurrent a block of loss in weight structure
JP2545198B2 (en) Reservoir device
JP2002327600A (en) Retaining wall structure of tunnel watchman's passage and member for forming retaining wall
JP4092284B2 (en) Rainwater underground seepage structure and its construction method
KR101224380B1 (en) Prefab water-storage tank
DE19728799C1 (en) Paving for areas subject to spillages of liquids
JP2884495B2 (en) Rainwater storage tank
JPH0826573B2 (en) Rainwater storage tank
JP2859130B2 (en) Reservoir equipment implementation method
KR102598717B1 (en) Member for forming a waterproofing curb and method of constructing an underground structure
JP3721526B2 (en) Precast concrete culvert side gutter
JP3072964B2 (en) Fire protection fence and its installation method
JP2632661B2 (en) Underground Reservoir Structure
CN214362568U (en) Ballastless track structure
JPH0841842A (en) Built-up channel
JP2752313B2 (en) Reservoir equipment
JPS6332164Y2 (en)
JP2791274B2 (en) Reservoir equipment
JP2571398Y2 (en) Reservoir equipment
JP3635249B2 (en) Fence repair method and fence repair block
JPH06272289A (en) Rain-water storage tank

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080725

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090725

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090725

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100725

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100725

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110725

Year of fee payment: 15

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120725

Year of fee payment: 16

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120725

Year of fee payment: 16

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130725

Year of fee payment: 17

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130725

Year of fee payment: 17

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term