JP2515888B2 - Construction method of steel pipe pile for building offshore structure and its equipment - Google Patents

Construction method of steel pipe pile for building offshore structure and its equipment

Info

Publication number
JP2515888B2
JP2515888B2 JP1204790A JP20479089A JP2515888B2 JP 2515888 B2 JP2515888 B2 JP 2515888B2 JP 1204790 A JP1204790 A JP 1204790A JP 20479089 A JP20479089 A JP 20479089A JP 2515888 B2 JP2515888 B2 JP 2515888B2
Authority
JP
Japan
Prior art keywords
casing
steel pipe
casing pipe
layer
pipe pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1204790A
Other languages
Japanese (ja)
Other versions
JPH0369717A (en
Inventor
望 篠原
雄一 芳野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP1204790A priority Critical patent/JP2515888B2/en
Publication of JPH0369717A publication Critical patent/JPH0369717A/en
Application granted granted Critical
Publication of JP2515888B2 publication Critical patent/JP2515888B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は桟橋等の海上構造物を築造するための鋼管杭
の施工工法およびその装置に関する。
Description: TECHNICAL FIELD The present invention relates to a construction method of a steel pipe pile for constructing a marine structure such as a jetty and its apparatus.

[従来技術] 桟橋等の海上構造物を築造するに際し、海底の岩盤層
に鋼管杭を施工する。
[Prior Art] When constructing an offshore structure such as a jetty, steel pipe piles are constructed in a rock layer on the seabed.

この鋼管杭を施工するのち、従来の施工工法およびそ
の装置は、施工を連続的に行なうことができず、施工効
率が低かった。
After the construction of this steel pipe pile, the conventional construction method and its equipment could not be continuously constructed, and the construction efficiency was low.

[発明が解決しようとする問題点] 本発明は上記した問題点を解決するためになされたも
ので、その目的は連続的に施工効率が高い工法およびそ
の装置を提供するにある。
[Problems to be Solved by the Invention] The present invention has been made to solve the above-mentioned problems, and an object thereof is to provide a construction method and a device therefor which are continuously high in construction efficiency.

[問題点を解決するための手段] 本発明によれば海上構造物を築造する海底の岩盤層上
に捨石層を構築し、該捨石層の所定位置の捨石の一部を
除去し、作業船を所定位置に係留してレグを下ろし、該
作業船からケーシングパイプを建込んで前記捨石層の捨
石を一部除去した箇所に食い付かせ、ケーシングパイプ
を旋回してケーシング内を掘削しながらケーシングパイ
プを先端が岩盤層に達するまで下ろしたのち、ケーシン
グパイプ下の岩盤層を所定深さまで掘削し、掘削した削
孔内に鋼管杭をケーシングパイプを介して建込み、該鋼
管杭にモルタルを所定高さまで打設してモルタルを養生
したのち、鋼管杭とケーシングパイプとの間に玉砂利を
投入し、ケーシングパイプを引抜くことを特徴とする海
上構造物を築造するための鋼管杭の施工工法が提供され
ている。
[Means for Solving Problems] According to the present invention, a rubble layer is constructed on a bedrock layer on the seabed where an offshore structure is built, and a part of the rubble at a predetermined position of the rubble layer is removed, and a work boat Mooring at a predetermined position, lowering the leg, building a casing pipe from the work boat to bite into a portion of the rubble layer of the rubble layer, and turning the casing pipe to excavate the casing while casing. After lowering the pipe until the tip reaches the bedrock layer, the bedrock layer under the casing pipe is excavated to a predetermined depth, a steel pipe pile is installed in the excavated hole through the casing pipe, and mortar is specified in the steel pipe pile. A construction work for a steel pipe pile for constructing a marine structure characterized by inserting gravel between the steel pipe pile and the casing pipe and then pulling out the casing pipe after casting to a height to cure the mortar. The law is provided.

更に本発明によれば、作業船と、該作業船からケーシ
ングパイプおよび鋼管杭を建込む建込み装置と、前記作
業船上に移動自在に設けられ前記ケーシングパイプを旋
回昇降する旋回装置と、移動自在で前記ケーシング下の
岩盤層の表層を掘削する表層掘削機と、移動自在で前記
ケーシングパイプ下の岩盤層を掘削する掘削機とを備え
たことを特徴とする海上構造物を築造するための鋼管杭
の施工装置が提供されている。
Further, according to the present invention, a work boat, a building device for building a casing pipe and a steel pipe pile from the work boat, a swivel device movably provided on the work boat for swiveling and raising the casing pipe, and A steel pipe for constructing an offshore structure, comprising: a surface excavator for excavating a surface layer of a rock layer under the casing, and an excavator for freely excavating a rock layer under the casing pipe. Pile construction equipment is provided.

[発明の作用効果] 従って表層掘削機による掘削が終了したら該掘削を移
動するとともに、旋回装置を次の鋼管杭を施工すべき場
所に移動し、建込み装置により次のケーシングパイプの
建込から施工を連続的に行ない、施工効率を向上するこ
とができる。
[Advantageous effects of the invention] Therefore, when the excavation by the surface layer excavator is completed, the excavation is moved, the swivel device is moved to the place where the next steel pipe pile is to be constructed, and the next casing pipe is installed by the installation device. Construction can be performed continuously, and construction efficiency can be improved.

[好ましい実施の態様] 本発明の実施に際し、作業船の側壁にケーシングパイ
プを位置決めしガイドする案内部材を着脱自在に設ける
のが好ましい。本発明の実施に際し、案内部材の下方に
施工が終った鋼管杭を作業船を撤去するまで作業船に保
持しておく振れ止め部材を着脱自在に設けるのが好まし
い。
[Preferable Embodiments] When carrying out the present invention, it is preferable that a guide member for positioning and guiding the casing pipe is detachably provided on the side wall of the work boat. In carrying out the present invention, it is preferable to detachably install a steady rest below the guide member for holding the steel pipe pile which has been constructed on the work boat until the work boat is removed.

本発明の実施に関し、掘削機を本体と回転架台とから
構成し、本体は作業船の隣に係船した資材台船に積み、
回転架台は陸上に置き、必要時に両者を作業船上に移動
するのが好ましい。
Regarding the implementation of the present invention, the excavator is composed of a main body and a rotary gantry, and the main body is loaded on a material carrier moored next to the work boat,
It is preferable to place the rotary platform on land and move both to the work boat when necessary.

本発明の実施に際し、鋼管杭は作業船の隣に係船した
杭台船に積んでおくのが好ましい。
In practicing the present invention, steel pipe piles are preferably loaded on a pile barge moored next to the workboat.

[実施例] 以下図面を参照して本発明の実施例を説明する。Embodiment An embodiment of the present invention will be described below with reference to the drawings.

第1図および第2図は本発明を実施する装置を示して
おり、装置は作業船すなわちセップ1と、セップ1上の
建込み装置であるクローラクレーン12とセップ上に移動
自在に設けられた旋回装置である全旋回ケーシング掘削
機20と、移動自在な表層掘削機であるクラブハンマー
(第17図)44と、移動自在な掘削機である回転式掘削機
30とから概略構成されている。
1 and 2 show an apparatus for carrying out the present invention. The apparatus is movably provided on a work boat, ie, CEP 1, a crawler crane 12 which is an installation device on CEP 1, and CEP. Full-swivel casing excavator 20 which is a swivel device, club hammer (Fig. 17) 44 which is a movable surface layer excavator, and rotary excavator which is a movable excavator.
It is roughly composed of 30 and.

第1図ないし第3図において、セップ1は公知技術に
よるもので、長方形状の甲板2の4隅部に昇降自在なレ
グ4が設けられ、長手方向の一側に沿ってレール5、5
が敷設され、また、その側の側壁には後出のケーシング
パイプCの案内部材である下部導材7を取付ける複数の
ブラケット6が水平に突設されている。なお、図中符号
3はクローラクレーン12の作業区域、13はコンプレッ
サ、14は発電機である。
In FIGS. 1 to 3, a sep 1 is a known technique, and a leg 4 which is vertically movable is provided at four corners of a rectangular deck 2, and rails 5 and 5 are provided along one side in the longitudinal direction.
And a plurality of brackets 6 for horizontally mounting the lower conductive material 7 which is a guide member for the casing pipe C described later are horizontally provided on the side wall on the side. In the figure, reference numeral 3 is a work area of the crawler crane 12, 13 is a compressor, and 14 is a generator.

第1図ないし第4図において、全旋回ケーシング掘削
機20は、レール5、5上を走行用油圧ユニット21により
移動自在な移動台車22と、移動第22上をレール5と直交
方向に移動自在でかつ前部両側と後部とにアウトリガー
23、24を備えたクローラ台車25と、クローラ台車25の前
部に設けられケーシングパイプCを回転し昇降させる旋
回ヘッド26と、旋回ヘッド26を旋回させる旋回用ユニッ
ト27とからなっている。なお、図中符号28は作業足場で
ある。
1 to 4, a full swing casing excavator 20 is movable on a rail 5 or 5 by a traveling hydraulic unit 21 by a traveling carriage 22 and on a movable 22 on a rail 5 in a direction orthogonal to the rail 5. Outriggers on both front and rear
It comprises a crawler carriage 25 provided with 23, 24, a swivel head 26 provided in the front part of the crawler carriage 25 for rotating and raising and lowering the casing pipe C, and a swivel unit 27 for swiveling the swivel head 26. Reference numeral 28 in the figure is a work scaffold.

第1図、第2図、第5図および第6図において、回転
式掘削機30は公知技術によるもので、ケーシングパイプ
Cに取付けられた図示しないケーシング頭に回転装置を
備え、掘削機30の一部をなす回転架台31を介して取付け
られ、公知のドリルストリングス(第1図)32を回転し
て掘削を行なうようになっている。なお、図中符号33は
掘削用パワーユニット、34は給水用配管、35は排土用配
管である。
1, FIG. 2, FIG. 5, and FIG. 6, the rotary excavator 30 is of a known technique, and a casing head (not shown) attached to the casing pipe C is provided with a rotating device, and It is attached via a rotary mount 31 forming a part, and is adapted to rotate a known drill string (FIG. 1) 32 for excavation. In the figure, reference numeral 33 is a power unit for excavation, 34 is a water supply pipe, and 35 is a soil discharge pipe.

第7図ないし第10図において、前記ブラケット6上に
はケーシングパイプCを位置決め案内する下部導材7が
張設され。下部導材7にはストローク調整ハンドル8に
より移動量を調節してケーシングパイプCを位置決め案
内するガイドローラ9が円周4等配に設けられている。
In FIGS. 7 to 10, a lower conductive member 7 for positioning and guiding the casing pipe C is stretched on the bracket 6. Guide rollers 9 are provided on the lower conductive member 7 at equal intervals on the circumference 4 for adjusting the amount of movement by a stroke adjusting handle 8 and positioning and guiding the casing pipe C.

また、第11図および第12図に示すように、甲板2の側
壁のブラケット6の下方には梁10が水平に取付けられ、
この梁10には施工の終った鋼管杭Pをセップ1が移動す
るまで振れ止めするための振れ止め部材である振れ止め
ブラケット11が取付けられるようになっている。
Further, as shown in FIGS. 11 and 12, a beam 10 is horizontally attached below the bracket 6 on the side wall of the deck 2,
The beam 10 is provided with a steady rest bracket 11 which is a steady rest member for steadying the steel pipe pile P after the construction until the sep 1 moves.

第1図においてセップ1は岸壁Wに繁留されるように
なっており、回転式掘削機30は第2図に示すようにセッ
プ1上に移され、ケーシングパイプCに取付けられたケ
ーシング頭に回転架台31を介して取付けられるが、非運
転時はドリルリンクス32とともにセップ1の隣に係船さ
れた資材台船15上に保管され、回転架台31は陸上に保管
されるようになっている。なお、図中符号16、16は資材
台船15に設けられた泥水タンク、17は 18はマッドスクリーン、19は鋼管杭Pを積み、セップ1
の隣に係船された杭台船である。
As shown in FIG. 2, the rotary excavator 30 is moved onto the sep 1 as shown in FIG. 2, and the casing head attached to the casing pipe C is mounted on the casing head. It is mounted via the rotary mount 31, but when not in operation, it is stored together with the drill links 32 on the material carrier 15 moored next to the SEP 1, and the rotary mount 31 is stored on land. In the figure, reference numerals 16 and 16 are muddy water tanks provided on the material carrier 15, and 17 is 18 is a mud screen, 19 is a pile of steel pipes P, 1 sep
It is a pile barge moored next to.

次に第13図ないし第27図を参照して工法の実施態様を
説明する。
Next, an embodiment of the construction method will be described with reference to FIGS. 13 to 27.

第1工順(第13図):あらかじめ海上構造物を築造す
る海底の岩盤層A上に、公知任意の工法で捨石層Bを構
築し、隣接した岸壁Wの陸上部にアンカー40を打設して
おく。そして、セップ1を曵船39により陸上からの誘導
で位置決めし、アンカー40にワイヤ41で繁留し、岸壁W
との間に乗船桟橋(第1図)42を張設する。なお、この
際、岸壁Wのワイヤー41に当接する部分に、防護材41を
取付けるのが好ましい。次いで、レグ4〜4を下す。
1st order (Fig. 13): A rubble layer B is constructed by a publicly known arbitrary method on the bedrock layer A on the seabed where the offshore structure is built in advance, and the anchor 40 is placed on the land portion of the adjacent quay W. I'll do it. Then, the sep 1 is positioned by landing by a tugboat 39, and is anchored to the anchor 40 by the wire 41, and the quay W
An embarkation pier (Fig. 1) 42 will be stretched between and. At this time, it is preferable to attach the protective member 41 to the portion of the quay W that contacts the wire 41. Then, the legs 4 to 4 are lowered.

第2工順(第14図):セツプ1にプレロードをかけ、
セップ1が捨石層B上に安定に保持されたことを測量に
より確認する。次いで、クローラクレーン12等の搭載機
器のセップ1への固縛を解除し、クローラクレーン12に
よりブラケット6〜6に陸上に置いてあった下部導材7
を取付ける。
2nd route (Fig. 14): Preloading the set 1
It is confirmed by measurement that SEP 1 is stably retained on the rubble layer B. Next, the securing of the mounted equipment such as the crawler crane 12 to the SEPP 1 is released, and the lower conductive material 7 placed on the brackets 6 to 6 on the land by the crawler crane 12 is released.
Install.

他方、ダイバーSにより鋼管杭Pを施工すべき捨石層
Bの捨石B1の一部を除去し、また、セップ1に隣接して
回転式掘削機30、ケーシングパイプC等の積んだ資材台
船15を係船する。
On the other hand, a part of the rubble B1 of the rubble layer B on which the steel pipe pile P is to be constructed is removed by the diver S, and the material excavator 15 having the rotary excavator 30, the casing pipe C, and the like adjacent to the CEP 1 is loaded. Mooring.

第3工順(第15図):鋼管杭Pを施工すべき位置に全
旋回ケーシング掘削機20を移動し、クローラクレーン12
により資材台船15上のケーシングパイプCを掘削機20の
旋回ヘッド(第3図)26を介して建込み、下部導材7の
ガイドローラ(第10図)9の移動量を調節して位置決め
し、ケーシングパイプ建ちを調整する。
3rd route (Fig. 15): Move the full swing casing excavator 20 to the position where the steel pipe pile P should be installed, and move the crawler crane 12
The casing pipe C on the material carrier 15 is installed by the swivel head (Fig. 3) 26 of the excavator 20 by adjusting the movement amount of the guide roller (Fig. 10) 9 of the lower conductive material 7 and positioned. And adjust the casing pipe construction.

第4工順(第16図):次いで、ケーシングパイプCの
捨石層Bへの食い付きを確認し、ケーシングパイプCに
ケーシング頭(図示せず)を取付け、掘削機20の旋回ヘ
ッド26を旋回しケーシングパイプCの下端に形成された
図示しない刃先で掘削する。
Fourth route (Fig. 16): Next, confirm the biting of the casing pipe C to the rubble layer B, attach a casing head (not shown) to the casing pipe C, and turn the turning head 26 of the excavator 20. Then, excavation is performed with a cutting edge (not shown) formed at the lower end of the casing pipe C.

第5工順(第17図および第18図):そして、ケーシン
グパイプCの先端が岩盤層Aに到達したら、クラーラク
レーン12にクラブハンンマー44を調節してケーシングパ
イプC内の捨石を除き、岩盤層Aの表面を掘削する。こ
の際、クラブハンマー44で掘削不能の場合は、チゼル
(第18図)により岸壁を破砕する。そして、掘削長さが
所定量であることを確認したのち、ケーシング頭(図示
せず)を撤去する。
5th route (Figs. 17 and 18): When the tip of the casing pipe C reaches the bedrock layer A, the club hammer 12 is adjusted to the Clara crane 12 to remove the rubble in the casing pipe C, Excavate the surface of bedrock layer A. At this time, if the club hammer 44 cannot excavate, the quay is crushed by a chisel (Fig. 18). Then, after confirming that the excavation length is a predetermined amount, the casing head (not shown) is removed.

第6工順(第19図):次いで、全旋回ケーシング掘削
機20を次の鋼管杭Pを施工すべき場所に移動し次の鋼管
杭Pについて第3工順から施工を始める。他方、ケーシ
ングパイプCにケーシング頭を再取付けし、クローラク
レーン12により陸上から回転架台31を吊り挙げ、ケーシ
ング頭にセットする。
6th route (Fig. 19): Next, the full swing casing excavator 20 is moved to the place where the next steel pipe pile P should be constructed, and the next steel pipe pile P is begun to be constructed from the 3rd route. On the other hand, the casing head is reattached to the casing pipe C, and the rotary base 31 is lifted from the land by the crawler crane 12 and set on the casing head.

第7工順(第20図):次いで、クローラクレーン12に
より資材台船15から回転式掘削機30を吊り回転架台31上
にセットし、同様にしてドリルストリングス32をケーシ
ングパイプC内に建込み、また、給水用配管34を資材台
船15の水中ポンプ(第1図)46に接続し、排土用配管35
を資材台船15のマッドスクリーン18に接続し、エア配管
47を陸上のコンプレッサ48に接続する。
7th route (Fig. 20): Then, the crawler crane 12 is used to set the rotary excavator 30 from the material carrier 15 on the rotary platform 31, and the drill strings 32 are built in the casing pipe C in the same manner. In addition, the water supply pipe 34 is connected to the submersible pump (Fig. 1) 46 of the material carrier 15, and the soil discharge pipe 35 is connected.
Connected to the mud screen 18 of the material carrier 15 and air piping
Connect 47 to onshore compressor 48.

第8工順(第21図):次いで、回転架台31でドリルス
トリングス32を回転して岩盤層Aを所定深度まで掘削
し、コンプレッサ48、エア配管47、水中ポンプ46、給水
用配管34、排土用配管35、マッドスクリーン18、 泥水タンク16等により掘削スライムを処理する。そし
て、掘削長さをチェックしたのち、ドリルストリングス
32を撤去し、回転式掘削機30を撤去してともに資材台船
15上に仮置きする。次いで、岩盤層Aの削孔(第23図)
Dの孔壁を測定し、回転架台31を撤去する。
8th route (Fig. 21): Next, the drill strings 32 are rotated by the rotary mount 31 to excavate the bedrock layer A to a predetermined depth, and the compressor 48, the air pipe 47, the submersible pump 46, the water supply pipe 34, and the drainage pipe are discharged. Earth pipe 35, mud screen 18, The drilling slime is processed by the mud tank 16 or the like. And after checking the drilling length, drill strings
32 removed, rotary excavator 30 removed, and material carrier
15 Temporarily place on top. Next, drilling of rock layer A (Fig. 23)
Measure the hole wall of D and remove the rotary mount 31.

第9工順(第22図および第23図):次いで、セップ1
に隣接して鋼管杭Pを積んだ杭台船19を係船し、クロー
ラクレーン12により吊り金具49、玉掛けワイヤー50を介
して鋼管杭PをケーシングパイプCと削孔D内に建込
む。この際、削孔D鋼管杭Pとの間にスペーサ50を介装
して所要隙間を形成し、また、鋼管杭Pの下端にスリッ
ト52を設けて削孔Dの底面に食い付かせるようにするの
が好ましい。
Route 9 (Figs. 22 and 23): Next, Sep 1
Pile barge 19 having steel pipe piles P adjacent thereto is laid up, and steel pipe piles P are erected in casing pipe C and drilled hole D by crawler crane 12 via suspension metal fittings 49 and sling wires 50. At this time, a spacer 50 is provided between the drilled hole D and the steel pipe pile P to form a required gap, and a slit 52 is provided at the lower end of the steel pipe pile P so as to bite the bottom surface of the drilled hole D. Preferably.

第10工順(第24図および第25図):次いで、陸上に設
置したモルタルポンプ53にモルタルホース54を接続し、
水タンク55の水を送水してスライムを攪拌したのち、ト
ラックミキサ56のモルタルアジテータ57、モルタルポン
プ53、モルタルホース54を介して削工D内に打設する。
この際、削孔D内の所定高さに鋼管杭Pの内外に界面計
58、58をセットし、モルタル注入パイプ59からのモルタ
ルMの打設高さをチェックする。
Route 10 (Figs. 24 and 25): Next, connect the mortar hose 54 to the mortar pump 53 installed on land,
After the water in the water tank 55 is sent to stir the slime, it is placed in the machining D through the mortar agitator 57, the mortar pump 53 and the mortar hose 54 of the track mixer 56.
At this time, the interface gauges are installed inside and outside the steel pipe pile P at a predetermined height within the drilled hole D.
Set 58 and 58 and check the casting height of the mortar M from the mortar injection pipe 59.

第11工順(第26図および第27図):次いで打設したモ
ルタルMを養生したのち、鋼管杭Pの開口部を玉砂利投
入用シュート60で覆い、クローラクレーン12に玉砂利投
入れバケット61を吊り、バケット61の玉砂利B2をケーシ
ングパイプC鋼管杭Pとの間の隙間Eに投入充填する。
11th work order (Figs. 26 and 27): Next, after curing the mortar M that has been placed, the opening of the steel pipe pile P is covered with the chute 60 for throwing gravel, and the crawler crane 12 is loaded with the gravel throwing bucket 61. The gravel B2 of the hanging and bucket 61 is charged into the gap E between the casing pipe C and the steel pipe pile P.

第12工順(第28図および第29図):次いで、全旋回ケ
ーシング掘削機20を移動して旋回ヘッド26でチェック
し、ケーシングパイプCを旋回しながら引抜く。これに
より鋼管杭Pの下端部を削孔D内に固着し、捨石槽Bの
部分を玉砂利B2を介して捨石B1で囲み安定化し、鋼管杭
Pを岩盤層Aに確実に立設することができる。最後に、
下部導材7を撤去し、第11図に示すように、梁10に振れ
止めブラケット11を取付けて鋼管杭Pを保持する。
12th route (Figs. 28 and 29): Next, the full swing casing excavator 20 is moved and checked by the swing head 26, and the casing pipe C is pulled out while swinging. As a result, the lower end of the steel pipe pile P is fixed in the drilled hole D, the part of the rubble tank B is surrounded by the rubble B1 via the gravel B2 and stabilized, and the steel pipe pile P can be reliably erected on the rock layer A. it can. Finally,
The lower conductor 7 is removed, and as shown in FIG. 11, the steady rest bracket 11 is attached to the beam 10 to hold the steel pipe pile P.

このようにして第2図に示すように、例えば位置I、
II、IIIおよびIVの順序で鋼管杭Pを施工し、セップ1
を撤去したのち、鋼管杭Pの上に図示しない海上構造物
を築造する。
Thus, as shown in FIG. 2, for example, position I,
Steel pipe pile P was constructed in the order of II, III and IV, and Sep 1
After removing, the offshore structure (not shown) is built on the steel pipe pile P.

[まとめ] 以上説明したように本発明によれば、全旋回ケーシン
グ掘削機と回転式掘削機を工順に応じて移動し、工順を
並列に実施して鋼管杭を連続的に施工し、その結果、施
工効率を向上することできる。
[Summary] As described above, according to the present invention, the full-swivel casing excavator and the rotary excavator are moved according to the work order, the work steps are performed in parallel, and steel pipe piles are continuously constructed, As a result, the construction efficiency can be improved.

【図面の簡単な説明】[Brief description of drawings]

第1図はセップ回りを示す平面図、第2図はセップの側
面図、第3図は全旋回ケーシング掘削機を示す側面図、
第4図は第3図の上面図、第5図は回転式掘削機を示す
側面図、第6図は第5図の上面図、第7図は下部導材を
示す側面図、第8図は第7図の上面図、第9図は第8図
の要部の拡大図、第10図はガイドローラ回りを示す即断
面図、第11図は振れ止めブラケットを示す側面図、第12
図は第11図の上面図、第13図、第14図、第15図、第16
図、第17図および第18図、第19図、第20図、第21図、第
22図および第23図第、24図および第25図、第26図および
第27図、第28図および第29図はそれぞれ第1、第2、第
3、第4、第5、第6、第7、第8、第9、第10、第11
および第12工順を説明するための側面図である。 1……作業船、12……クローラクレーン、20……全旋回
ケーシング掘削機、22……移動台車、30……回転式掘削
機、44……クラブハンマー、C……ケーシングパイプ
FIG. 1 is a plan view showing the vicinity of a sep, FIG. 2 is a side view of the sep, FIG. 3 is a side view showing a full swing casing excavator,
4 is a top view of FIG. 3, FIG. 5 is a side view showing a rotary excavator, FIG. 6 is a top view of FIG. 5, FIG. 7 is a side view showing a lower conductor, and FIG. 7 is a top view of FIG. 7, FIG. 9 is an enlarged view of an essential part of FIG. 8, FIG. 10 is a sectional view showing around the guide roller, FIG. 11 is a side view showing a steady rest bracket, and FIG.
The figures are the top view of FIG. 11, FIG. 13, FIG. 14, FIG. 15, and FIG.
Figure 17, Figure 17 and Figure 18, Figure 19, Figure 20, Figure 21, Figure
FIG. 22 and FIG. 23, FIG. 24 and FIG. 25, FIG. 26 and FIG. 27, FIG. 28 and FIG. 29 are respectively the first, second, third, fourth, fifth and sixth, respectively. 7th, 8th, 9th, 10th, 11th
FIG. 16 is a side view for explaining a twelfth work order. 1 …… Work boat, 12 …… Crawler crane, 20 …… Full swing casing excavator, 22 …… Mobile cart, 30 …… Rotary excavator, 44 …… Club hammer, C …… Casing pipe

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】海上構造物を築造する海底の岩盤層上に捨
石層を構築し、該捨石層の所定位置の捨石の一部を除去
し、作業船を所定位置に係留してレグを下ろし、該作業
船からケーシングパイプを建込んで前記捨石層の捨石を
一部除去した箇所に食い付かせ、ケーシングパイプを旋
回してケーシング内を掘削しながらケーシングパイプを
先端が岩盤層に達するまで下ろしたのち、ケーシングパ
イプ下の岩盤層を所定深さまで掘削し、掘削した削孔内
に鋼管杭をケーシングパイプを介して建込み、該鋼管杭
にモルタルを所定高さまで打設してモルタルを養生した
のち、鋼管杭とケーシングパイプとの間に玉砂利を投入
し、ケーシングパイプを引抜くことを特徴とする海上構
造物を築造するための鋼管杭の施工工法。
1. A rubble layer is constructed on a bedrock layer on the seabed where an offshore structure is built, a part of the rubble stone at a predetermined position of the rubble layer is removed, and a work boat is moored at a predetermined position to lower a leg. , A casing pipe was built from the work boat to bite into a portion of the rubble layer of the rubble layer, and the casing pipe was swiveled to lower the casing pipe until the tip reached the bedrock layer while excavating the inside of the casing. After that, the rock layer under the casing pipe was excavated to a predetermined depth, a steel pipe pile was installed in the excavated hole through the casing pipe, and the mortar was cured by driving mortar to the steel pipe pile to a predetermined height. After that, a method for constructing a steel pipe pile for constructing an offshore structure, characterized by pouring pebbles between the steel pipe pile and the casing pipe and pulling out the casing pipe.
【請求項2】作業船と、該作業船からケーシングパイプ
および鋼管杭を建込む建込み装置と、前記作業船上に移
動自在に設けられ前記ケーシングパイプを旋回昇降する
旋回装置と、移動自在で前記ケーシング下の岩盤層の表
層を掘削する表層掘削機と、移動自在で前記ケーシング
パイプ下の岩盤層を掘削する掘削機とを備えたことを特
徴とする海上構造物を築造するための鋼管杭の施工装
置。
2. A work boat, an erection device for constructing a casing pipe and a steel pipe pile from the work boat, a slewing device movably provided on the work boat for slewing and lifting the casing pipe, and A surface layer excavator for excavating the surface layer of the rock layer under the casing, and an excavator for movably excavating the rock layer under the casing pipe, of a steel pipe pile for constructing an offshore structure. Construction equipment.
JP1204790A 1989-08-09 1989-08-09 Construction method of steel pipe pile for building offshore structure and its equipment Expired - Lifetime JP2515888B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1204790A JP2515888B2 (en) 1989-08-09 1989-08-09 Construction method of steel pipe pile for building offshore structure and its equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1204790A JP2515888B2 (en) 1989-08-09 1989-08-09 Construction method of steel pipe pile for building offshore structure and its equipment

Publications (2)

Publication Number Publication Date
JPH0369717A JPH0369717A (en) 1991-03-26
JP2515888B2 true JP2515888B2 (en) 1996-07-10

Family

ID=16496395

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1204790A Expired - Lifetime JP2515888B2 (en) 1989-08-09 1989-08-09 Construction method of steel pipe pile for building offshore structure and its equipment

Country Status (1)

Country Link
JP (1) JP2515888B2 (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL1025805C2 (en) * 2004-03-25 2005-09-27 Dsm Ip Assets Bv Process for the granulation of urea.
JP2008014107A (en) * 2006-07-10 2008-01-24 Misawa Homes Co Ltd Siding fastening member, mounting method and dismounting method of siding member
JP5306885B2 (en) * 2009-04-14 2013-10-02 鹿島建設株式会社 Construction method for underwater structures
JP6319935B2 (en) * 2011-12-21 2018-05-09 株式会社横山基礎工事 Tubing pile driving method
JP2014070469A (en) * 2012-10-01 2014-04-21 Yokoyama Kiso Koji:Kk Casing guide device and casing driving method
JP6034675B2 (en) * 2012-11-28 2016-11-30 株式会社高特 Glide surface weathering depth survey machine
CN104532795B (en) * 2014-12-29 2018-07-06 中国电建集团贵阳勘测设计研究院有限公司 A kind of the unpowered of power station blocks dirty method and device
FR3084380B1 (en) * 2018-07-30 2020-10-23 Saipem Sa PROCESS FOR INSTALLING A TUBULAR METAL PILE IN ROCKY SOIL

Also Published As

Publication number Publication date
JPH0369717A (en) 1991-03-26

Similar Documents

Publication Publication Date Title
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN109780325B (en) Installation method of underwater pipeline of water taking tunnel of water plant
CN103850249B (en) Long spire is squeezed into rock filling pile construction technology
CN102953341B (en) A kind of high-order trestle work structure be arranged in deep water torrent intectate steep bare rock
CN109797749B (en) Underwater foundation pit construction device and construction method
CN103924585B (en) The construction method of wind-powered electricity generation socketed pile
CN102979039B (en) Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN110629747A (en) Full-casing full-rotation construction process for pile foundation under complex geological conditions
JP5813109B2 (en) Surface-projecting reusable underwater template for installing one or more underwater struts or piles
CN110295648A (en) A kind of facility and its integral installation construction method for fetching water in torrent riverbed
JP2515888B2 (en) Construction method of steel pipe pile for building offshore structure and its equipment
CN110847185B (en) Stone throwing and tamping integrated ship
CN114197439B (en) Construction method and construction equipment for high-current deepwater underwater gravel pile
CN210263062U (en) Anti construction structures that floats of shallow earthing subway tunnel foundation ditch earthwork excavation in pit bottom
CN109707002B (en) Device and method for accurately positioning, sinking and installing large water intake head
CN106400807B (en) Extra large work barge grouting method and its equipment
WO2023207250A1 (en) Construction method for rapidly driving trestle steel pipe pile into sloped bare rock
CN113356179B (en) Treatment method of hydraulic structure foundation
CN215629910U (en) Steel upright pile with reinforced structure
CN206752413U (en) A kind of extra large work barge implement
CN114635450A (en) Construction method for permanent steel pipe structural column of covered and excavated station
JP3169911B2 (en) Heavy weight type steel pipe digging and driving method using the same
CN206328759U (en) Extra large work barge grouting equipment
WO2010104235A1 (en) Excavation method of underground plaza and submarine plaza using steel casing retaining wall
JP4504752B2 (en) Construction method and apparatus for tubular precast concrete member