CN110295648A - A kind of facility and its integral installation construction method for fetching water in torrent riverbed - Google Patents

A kind of facility and its integral installation construction method for fetching water in torrent riverbed Download PDF

Info

Publication number
CN110295648A
CN110295648A CN201910685711.XA CN201910685711A CN110295648A CN 110295648 A CN110295648 A CN 110295648A CN 201910685711 A CN201910685711 A CN 201910685711A CN 110295648 A CN110295648 A CN 110295648A
Authority
CN
China
Prior art keywords
water
water intake
aqueduct
steel
platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910685711.XA
Other languages
Chinese (zh)
Inventor
陈慧
梁文
蒋武华
宋作栋
李新
李佳丽
刘银华
曾斌
陈磊
朱春林
唐传辉
左川
胡天明
伍志光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd
Second Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
Second Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd filed Critical Second Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd
Priority to CN201910685711.XA priority Critical patent/CN110295648A/en
Publication of CN110295648A publication Critical patent/CN110295648A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/06Placing concrete under water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03BINSTALLATIONS OR METHODS FOR OBTAINING, COLLECTING, OR DISTRIBUTING WATER
    • E03B3/00Methods or installations for obtaining or collecting drinking water or tap water
    • E03B3/04Methods or installations for obtaining or collecting drinking water or tap water from surface water

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Earth Drilling (AREA)

Abstract

The facility and its integral installation construction method that the present invention provides a kind of for fetching water in torrent riverbed, facility include aqueduct, positioning steel tube stake, the connection beam parallel with aqueduct axis, pile cover, I-shaped gooseneck, distribution beam, steel facing, column, spandrel girder, water intake, water intake flower stand, water blocking facility, cross beam frame pipe, railing, side walk slab, hanging ring weldment, chain block, canvas hoisting hook band, roller, aqueduct flower stand, the connection beam vertical with aqueduct axis;The aqueduct includes horn mouth and straightway, and the water intake facilities are to draw rivers center river for life industrial water by pipeline of fetching water, and is composed of water intake and aqueduct;Using positioning steel tube stake position as support system, aqueduct truss work platform and horn mouth assembly workbench are established, is hung using pool, chain block will connect integral water intake facilities and integrally transfer low water, the dry operation that realization water intake assembly is connect with aqueduct.

Description

A kind of facility and its integral installation construction method for fetching water in torrent riverbed
Technical field
The present invention relates to waterworks or draw water pump house construction phase water intake facilities field more particularly to a kind of invigorated rivers Water intake facilities and its integral installation construction method in bed.
Background technique
Water intake facilities refer generally to water intake, aqueduct and dock facility with the horn mouth of water intake, aqueduct joint, Construction and installation are always interim one of the most critical processes of waterworks construction.With construction safety risk big, environmental protection be difficult to it is up to standard, apply The problem that the work period is long and operating expenses is high.In the prior art, those skilled in the art are used to solve above-mentioned technical problem Scheme be to be generally divided into fording operation and land and water to convert two kinds of dry operation method, the installation for water intake facilities.It paddles work Pipeline transportation by driving to set waters, water filling are sunk down into commitment positions, adopted by the method that transportation by driving sinking installation is generallyd use when industry, segmentation Implemented with ship, raft plate ship auxiliary.Land and water converts that dry operation is relatively easy to be illustrated, be exactly using the modes such as pipe laying, drainage into The guidance of row water flow forms dry ground condition and carries out operation after then the modes such as cofferdam, caisson are drawn water.But land and water conversion dry method is made Industry is suitable for that water is shallow, flow velocity is slower, innavigable operating condition, transportation by driving when fording operation sink installation premise be must point Section, stream are slow, navigation requires under low operating condition.
As (belonging to Drainage Area of Jinsha River korneforos heart cruising ground in Jinsha jiang River away from bank 20m~80m, depth of water 9m, flow velocity 6m/s Domain, level-one water source, mandarin sturgeon protection zone) in installation water intake facilities (specifically: the aqueduct of 1420 × 14mm of double joint φ (wherein underwater portion mileage is K0+000~K0+055) and long 12.4m, the ship type steel construction water intake of wide 3.6m, high 5.9m (36.9 tons of its total weight)), and the operating condition of navigation condition must be reserved, using the method safety risk of segmentation floating clouds sinking installation It is huge, thus research and develop it is a kind of suitable in torrent riverbed water intake facilities install new process, new method, taken in torrent riverbed Effective measure solves the installation question of water intake facilities in terms of duration, cost-effectiveness, safe mass control, is one It is worth the project of exploratory development.
Summary of the invention
The purpose of the present invention takes effective measure in torrent riverbed, reduces the water flow reduction of speed in construction area, Diving under water powder charge is avoided, the installation question of water intake facilities is solved.
The present invention is in order to solve the above technical problems, provide the following technical solutions:
Invent a kind of facility for fetching water in torrent riverbed, which is characterized in that including aqueduct, positioning steel tube stake and diversion The parallel connection beam of pipe axis, pile cover, I-shaped gooseneck, distribution beam, steel facing, column, spandrel girder, water intake, water intaking headdress flower Frame, water blocking facility, cross beam frame pipe, railing, side walk slab, hanging ring weldment, chain block, canvas hoisting hook band, roller, aqueduct Flower stand, the connection beam vertical with aqueduct axis;The aqueduct includes horn mouth and straightway, and the water intake facilities are to pass through Water intaking pipeline draws rivers center river for life industrial water, is composed of water intake and aqueduct;With positioning steel tube Stake position is support system, establishes aqueduct truss work platform and horn mouth assembly workbench, and in the downstream of truss platform Setting construction channel for personnel above and below, install I-shaped gooseneck in the vertical positioning steel tube stake top of every three row, every place's I-steel is horizontal Arrange that two 10T chain blocks will be used for binding type lifting pipeline on beam;Using positioning steel tube stake position as support system, 14m is established The steel girder platform of × 5m welds as water intake steel member, slinging work platform, along water intake facilities water (flow) direction on platform Longitudinally disposed two Pin door shaped stent, two Pin door shaped stents are connected by spandrel girder, flower stand, make frame structure, every place is held Arrange that two 20T chain blocks will be used for hanging-ring type lifting water intake on weight beam;Hung using pool, chain block will connect it is integral Water intake facilities integrally transfer low water, realize the dry operation that water intake assembly is connect with aqueduct.
A kind of facility integral installation construction method for fetching water in torrent riverbed, which comprises the steps of:
(1): double-row steel pipe truss single wall water blocking is applied in such a way that steel truss and steel facing are implemented step by step by barge, the quick-fried ship of brill Plate reduces the water flow reduction of speed in construction area;
(2): using quick-fried ship is bored with blasthole diameter 90mm, hole depth is greater than 5m, short-delay blasting between row, the water for controlling single hop explosive quantity The mode of lower deep hole blasting carries out water intake facilities and intends falling channel excavation;
(3): utilizing the pile driving barge with drilling machine with " three pipes two bore method " pipe-following drilling, apply minor-diameter steel-tube guide pile, water intake Arrange that 5 column 6 are ranked a steel-pipe pile, column pitch is respectively 2.4m, 4.2m, 4.2m, 2.4m, arranges spacing 0.9m;Aqueduct horn mouth Place arranges that 3 column 3 are ranked a steel-pipe pile altogether with water intake in conjunction with, column pitch 4.2m, arranges spacing 2.0m;Straightway aqueduct arrangement 5 column, 24 row, column pitch are respectively 1.2m, 2.1m, 0.6m, 1.2m, arrange spacing 2.0m;
(4): the temporary wharf at interim truss downstream waterborne bank setting one ties up 500 horsepower power ships and landing stage one Driving is acted as, steel girder platform component is transported using landing stage, crane barge as water transportation platform, lifting, with steel pipe guide pile Position is support system, establish the steel girder platform of 14m × 5m welded as water intake steel member, slinging work platform, on platform Along the longitudinally disposed two Pin door shaped stent of water intake facilities water (flow) direction, and configures 6 20 tons of chain blocks and be used for lifting operation;
(5): using landing stage, crane barge using steel pipe guide pile position as support system, establishing aqueduct truss work platform and horn mouth Assembled workbench, and above and below the downstream installation of truss platform construction channel is for personnel, truss is set on bank and operation is flat Platform installs I-shaped gooseneck in two rows of every place's vertical steel pipe positioning stake tops, and two 10T chain blocks of arrangement will on every place's crossbeam Pipeline is lifted for binding type;
(6): being sling aqueduct using chain block, successively Congjiang bank water intake direction into river conveys, and configures two volumes Machine cooperation transport is raised to designated position;
(7): making shipping platform using landing stage and water intaking head component is transported, hanging piece is numbered before lifting, uses 50T truck crane on the bank Water intake steel member is grouped by number and is hung on the cargo ship for resting in temporary wharf, transport foot to water intake work waterborne Near industry platform, is hung using barge or water intake steel member is hung to water intake aquatic work platform and is assembled, splices by crane barge, After component conveying to platform, finely lifted using the 20T chain block of configuration;
(8): being hung using barge, aqueduct, horn mouth, water-fetching head are integrally transferred from aquatic work flat surface by chain block, so The roller and lateral connection component for removing diversion tubular truss afterwards also remove the workbench steel plate in water intaking portion and vertically and horizontally connect structure Part, so that will connect integral water intake facilities entirety average rate after not having barrier under water intake steel case and transfer low water, every decentralization A distance just removes the cross bar for hindering aqueduct decentralization, and the cross bar that connection aqueduct top has been removed immediately, it is ensured that branch The structural stability of frame is repeated up to sinking low water in place, completes water intake facilities installation.
Wherein: in the step (1), double-row steel pipe truss single wall water fender is arranged in the water intake facilities upstream position 8~10m Go deep into water, length, which is arranged, in end to be not less than 10m beyond water intake, to reduce water intake over-water construction regional water flow velocity and disappear Except the security risk that water fender reflux constructs to water intake, and ship anchor is set, the water fender is carried out by drawing anchor by wirerope, Water flow impact pressure is shared, lower part converts moment of flexure torsion for the horizontal impact power of water flow by the support stake of steel truss and is transferred to ground Base.
Wherein: in the step (2) further include: powder charge steel pipe and drill bit of drilling machine are followed up using " three pipes two bore method ", Make powder charge process by extraditing the water surface under water, only charging work need to can be completed from steel pipe top sequence powder charge on ship, avoid Diving under water powder charge, waits 15 minutes after detonation, after being checked by security official, dynamiter to quick-fried area and handled blind big gun, using digging Mud ship and overlength arm digging machine carry out underwater scarfing cinder, then examine foundation trench using underwater photography instrument, topography scanners cooperation, realize deep water Foundation trench is checked and accepted in river.
Wherein: in the step (3): steel pipe guide pile is higher by construction ordinary water level not less than 2.2m, using two bench drill machine drills Head is the hydraulic drill rig construction steel pipe guide pile used for geological prospecting of eccentric bit, and the steel pipe specifications and models are D168mm, wall thickness is The seamless T40 steel pipe of 8mm carries out spreading using thread casing in standard type, and socket length is 2.5m~3m, and steel pipe internal pressure fills C30 pea gravel concreten forms steel tube concrete pile.
Wherein: in the step (5): install detachable moved cross beam on every row's steel pipe guide pile, pipeline transportation, Play the role of bearing pipeline weight offer job platform when docking;Pipeline plays security protection safety effect when transferring, and every Decentralization 50cm needs to carry out accurate adjustment and measurement calibration, and in centre from roller is arranged on the crossbeam at water surface 0.5m, it is defeated to be used for pipeline It send, between two section aqueducts, to prevent steel pipe from plastic deformation occurs, is embraced to preceding added in two section steel pipe junctions of korneforos conveying Hoop or welding H-bar are fixed.
Wherein: in the step (8): before integral hoisting, making sinking witness marker and scale, implement to prevent hitting overboard rescue Measure, the counterweight for preventing water intake facilities from floating and setting limiting device, suspension centre reasonable Arrangement and examination is helped to hang, to lifting equipment performance Check, diver to hilllock in place.
Wherein: further including step (9): water intake and aqueduct being observed by diver to the bottom after sinking in place and connect with foundation trench Touch situation, if any larger gap under pipe, should be spread by diver with C30 concrete block fill and lead up it is whole after code build mould-bag concrete, pour C30 and mix under water Solidifying soil is assured.
Wherein: the concrete incorporation non-dispersible underwater concrete wadding in the step (9), in Placement of Underwater Concrete for Casting Solidifying agent.
Wherein: further include step (10): after underwater concrete reaches design strength, remove steel girder platform, water fender and Steel pipe guide pile is cut away, river is restored.
The invention has the benefit that inventing a kind of facility and its integral installation construction party for fetching water in torrent riverbed Method takes effective measure in torrent riverbed, reduces the water flow reduction of speed in construction area, avoids diving under water powder charge, It easily solves the problems, such as the integral installation of water intake facilities and checks and accepts, and be able to achieve and recycle.
Detailed description of the invention
Fig. 1 is foundation plan of the invention
Fig. 2 is the sectional view of water intake position of the present invention
Fig. 3 is the sectional view of aqueduct position of the present invention
Fig. 4 is elevation of the invention
Fig. 5 is positioning steel tube stanchion of the present invention top mode of connection figure
Fig. 6 is the flow chart of construction operation method of the invention
In figure: 1. positioning steel tube stakes, 2. parallel connection beams, 3. pile covers, 4. I-shaped goosenecks, 5. distribution beams, 6, steel facings, 7, Column, 8. spandrel girders, 9. water intake flower stands, 10. water intakes, 11. aqueducts, 12 riverbanks, 13. water blocking facilities, 14, crossbeams Frame pipe, 15, railings, 16, side walk slabs, 17. hanging ring weldments, 18. chain blocks, 19. canvas hoisting hook bands, 20. rollers, 21. aqueduct flower stand, 22. vertical linkage beams.
Specific embodiment
Technical solution of the present invention will be clearly and completely described below, it is clear that described embodiment is only A part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art Every other embodiment obtained without creative efforts, shall fall within the protection scope of the present invention.
A kind of facility for fetching water in torrent riverbed, which is characterized in that including aqueduct, positioning steel tube stake 1 and diversion The parallel parallel connection beam 2 of pipe axis, pile cover 3, I-shaped gooseneck 4, distribution beam 5, steel facing 6, column 7, spandrel girder 8, water intaking First 10, water intake flower stand 9, water blocking facility 13, cross beam frame pipe 14, railing 15, side walk slab 16, hanging ring weldment 17, chain block 18, canvas hoisting hook band 19, roller 20, aqueduct flower stand 21, the vertical linkage beam 22 vertical with aqueduct axis;The diversion Pipe includes horn mouth and straightway, and the water intake facilities are to draw rivers center river by pipeline of fetching water to use for producing Water is composed of water intake 10 with aqueduct;With positioning steel tube stake 1 for support system, it is flat to establish aqueduct truss work Platform and horn mouth assembly workbench, and above and below the downstream of truss platform setting construction channel is for personnel, it is vertical in every three row I-shaped gooseneck 4 is installed on the top of positioning steel tube stake 1, two 10T chain blocks of arrangement will be used to tie and embrace on every place's I-shaped gooseneck Formula lifts pipeline;Using positioning steel tube stake position as support system, the steel girder platform for establishing 14m × 5m is welded as water intake steel member It connects, slinging work platform, along the longitudinally disposed two Pin door shaped stent of water intake facilities water (flow) direction on platform, two Pin door shaped stents are logical Spandrel girder 8, flower stand connection are crossed, makes frame structure, two 20T chain blocks of arrangement will be used for hanging ring on every place's spandrel girder Formula lifts water intake;It is hung using pool, chain block will connect integral water intake facilities and integrally transfer low water, realization water intake spelling Fill the dry operation connecting with aqueduct.
Using the pile driving barge with drilling machine with " three pipes two bore method " pipe-following drilling, apply minor-diameter steel-tube guide pile, water intake Arrange that 5 column 6 are ranked a steel-pipe pile, column pitch is respectively 2.4m, 4.2m, 4.2m, 2.4m, arranges spacing 0.9m;Aqueduct horn mouth Place arranges that 3 column 3 are ranked a steel-pipe pile altogether with water intake in conjunction with, column pitch 4.2m, arranges spacing 2.0m;Straightway aqueduct arrangement 5 column, 24 row, column pitch are respectively 1.2m, 2.1m, 0.6m, 1.2m, arrange spacing 2.0m;Its steel pipe specifications and models is D168mm, wall Thickness is the seamless T40 steel pipe of 8mm, carries out spreading using thread casing in standard type, socket length is 2.5m~3m, steel pipe internal pressure C30 pea gravel concreten is filled, steel tube concrete pile is formed.
Wherein, the pile cover 3 is weldingly fixed on positioning steel tube stake top portion, provides and is welded and fixed and stress support for girder Face;
Wherein, the distribution beam 5 is weldingly fixed on I-shaped gooseneck top and is put down by the work that steel facing group builds up water intake Platform;
Wherein, the column 7 is combined into water intake lifting frame by welding manner with spandrel girder 8, flower stand (water intake part) Frame structure;
Wherein, the spandrel girder 8 is weldingly fixed on the top of positioning steel tube stake 1, forms door type structure with positioning steel tube stake, as rising Hang the load-carrying construction of aqueduct (horn mouth and straightway).
Wherein, the positioning steel tube stake (is hung down by connection beam (parallel with aqueduct axis), connection beam with aqueduct axis Directly), flower stand (diversion tube portion) connects, and makes frame structure, enhancing structure stability;
Wherein, the aqueduct (horn mouth and straightway) is used by canvas hoisting hook band and reveals all the details cluster by chain block It hangs.Rising to the bait for chain block is hooked on hanging ring weldment, and suffered load is transferred to ground by gate truss.
Wherein, the hanging ring weldment 17 is weldingly fixed on 8 lower edge of spandrel girder.
Wherein, the steel member welding, lifting of the water intake 10 are sling by chain block, pool.
Wherein, using railing, side walk slab above and below the downstream installation construction channel of truss platform is for personnel.
Further include installing detachable moved cross beam on every row's steel pipe guide pile, plays and hold in pipeline transportation, docking The effect of job platform is provided by pipeline weight;Pipeline plays security protection safety effect when transferring, and every decentralization 50cm needs Accurate adjustment and measurement calibration are carried out, in centre from roller is arranged on the crossbeam at water surface 0.5m, is used for pipeline, two section aqueducts Between, to prevent steel pipe from plastic deformation occurs, anchor ear or welding I-shaped are being added in two section steel pipe junctions to korneforos conveying is preceding Steel is fixed.
It further include being sling aqueduct using chain block, successively Congjiang bank water intake direction into river conveys, configuration Two hoist engine cooperations are transported to designated position.The dry operation that large size water intake assembly is connect with aqueduct can be achieved, and Water intake and the whole of aqueduct work compound are transferred, and can be accelerated to realize constructing aims and be reduced security risk.
" three pipes two brill " genealogy of law boring method, including guide pipe, casing and drilling rod, pipe-following drilling, drill bit of drilling machine are bias It bores.Operating process is: guide pipe is first descended in ship's fix, then puts down casing → according to rock surface situation, if relatively more broken, Then first to casing carry out alloy drilling (off-balance bit will slightly be expanded by pressure-bearing rotary drilling-head, in favor of casing follow-up) → Alloy is crept into complete basement rock, is lifted related drilling tool → lower drilling rod progress mace bit and is proceeded to design bottom absolute altitude → metering-orifice It is deep, it is such as not deep enough, then it repeats the above steps.
A kind of facility integral installation construction method for fetching water in torrent riverbed, which comprises the steps of:
(1): double-row steel pipe truss single wall water blocking is applied in such a way that steel truss and steel facing are implemented step by step by barge, the quick-fried ship of brill Plate reduces the water flow reduction of speed in construction area;
(2): using quick-fried ship is bored with blasthole diameter 90mm, hole depth is greater than 5m, short-delay blasting between row, the water for controlling single hop explosive quantity The mode of lower deep hole blasting carries out water intake facilities and intends falling channel excavation;
(3): utilizing the pile driving barge with drilling machine with " three pipes two bore method " pipe-following drilling, apply minor-diameter steel-tube guide pile, water intake Arrange that 5 column 6 are ranked a steel-pipe pile, column pitch is respectively 2.4m, 4.2m, 4.2m, 2.4m, arranges spacing 0.9m;Aqueduct horn mouth Place arranges that 3 column 3 are ranked a steel-pipe pile altogether with water intake in conjunction with, column pitch 4.2m, arranges spacing 2.0m;Straightway aqueduct arrangement 5 column, 24 row, column pitch are respectively 1.2m, 2.1m, 0.6m, 1.2m, arrange spacing 2.0m;
(4): the temporary wharf at interim truss downstream waterborne bank setting one ties up 500 horsepower power ships and landing stage one Driving is acted as, steel girder platform component is transported using landing stage, crane barge as water transportation platform, lifting, with steel pipe guide pile Position is support system, establish the steel girder platform of 14m × 5m welded as water intake steel member, slinging work platform, on platform Along the longitudinally disposed two Pin door shaped stent of water intake facilities water (flow) direction, and configures 6 20 tons of chain blocks and be used for lifting operation;
(5): using landing stage, crane barge using steel pipe guide pile position as support system, establishing aqueduct truss work platform and horn mouth Assembled workbench, and above and below the downstream installation of truss platform construction channel is for personnel, truss is set on bank and operation is flat Platform installs I-shaped gooseneck in two rows of every place's vertical steel pipe positioning stake tops, and two 10T chain blocks of arrangement will on every place's crossbeam Pipeline is lifted for binding type;
(6): being sling aqueduct using chain block, successively Congjiang bank water intake direction into river conveys, and configures two volumes Machine cooperation transport is raised to designated position;
(7): making shipping platform using landing stage and water intaking head component is transported, hanging piece is numbered before lifting, uses 50T truck crane on the bank Water intake steel member is grouped by number and is hung on the cargo ship for resting in temporary wharf, transport foot to water intake work waterborne Near industry platform, is hung using barge or water intake steel member is hung to water intake aquatic work platform and is assembled, splices by crane barge, After component conveying to platform, finely lifted using the 20T chain block of configuration;
(8): being hung using barge, aqueduct, horn mouth, water-fetching head are integrally transferred from aquatic work flat surface by chain block, so The roller and lateral connection component for removing diversion tubular truss afterwards also remove the workbench steel plate in water intaking portion and vertically and horizontally connect structure Part, so that will connect integral water intake facilities entirety average rate after not having barrier under water intake steel case and transfer low water, every decentralization A distance just removes the cross bar for hindering aqueduct decentralization, and the cross bar that connection aqueduct top has been removed immediately, it is ensured that branch The structural stability of frame is repeated up to sinking low water in place, completes water intake facilities installation.
Wherein: in the step (1), double-row steel pipe truss single wall water fender is arranged in the water intake facilities upstream position 8~10m Go deep into water, length, which is arranged, in end to be not less than 10m beyond water intake, to reduce water intake over-water construction regional water flow velocity and disappear Except the security risk that water fender reflux constructs to water intake, and ship anchor is set, the water fender is carried out by drawing anchor by wirerope, Water flow impact pressure is shared, lower part converts moment of flexure torsion for the horizontal impact power of water flow by the support stake of steel truss and is transferred to ground Base.
Wherein: in the step (2) further include: powder charge steel pipe and drill bit of drilling machine are followed up using " three pipes two bore method ", Make powder charge process by extraditing the water surface under water, only charging work need to can be completed from steel pipe top sequence powder charge on ship, avoid Diving under water powder charge, waits 15 minutes after detonation, after being checked by security official, dynamiter to quick-fried area and handled blind big gun, using digging Mud ship and overlength arm digging machine carry out underwater scarfing cinder, then examine foundation trench using underwater photography instrument, topography scanners cooperation, realize deep water Foundation trench is checked and accepted in river.
Wherein: in the step (3): steel pipe guide pile is higher by construction ordinary water level not less than 2.2m, using two bench drill machine drills Head is the hydraulic drill rig construction steel pipe guide pile used for geological prospecting of eccentric bit, and the steel pipe specifications and models are D168mm, wall thickness is The seamless T40 steel pipe of 8mm carries out spreading using thread casing in standard type, and socket length is 2.5m~3m, and steel pipe internal pressure fills C30 pea gravel concreten forms steel tube concrete pile.
Wherein: in the step (5): install detachable moved cross beam on every row's steel pipe guide pile, pipeline transportation, Play the role of bearing pipeline weight offer job platform when docking;Pipeline plays security protection safety effect when transferring, and every Decentralization 50cm needs to carry out accurate adjustment and measurement calibration, and in centre from roller is arranged on the crossbeam at water surface 0.5m, it is defeated to be used for pipeline It send, between two section aqueducts, to prevent steel pipe from plastic deformation occurs, is embraced to preceding added in two section steel pipe junctions of korneforos conveying Hoop or welding H-bar are fixed.
Wherein: in the step (8): before integral hoisting, making sinking witness marker and scale, implement to prevent hitting overboard rescue Measure, the counterweight for preventing water intake facilities from floating and setting limiting device, suspension centre reasonable Arrangement and examination is helped to hang, to lifting equipment performance Check, diver to hilllock in place.
Wherein: further including step (9): water intake and aqueduct being observed by diver to the bottom after sinking in place and connect with foundation trench Touch situation, if any larger gap under pipe, should be spread by diver with C30 concrete block fill and lead up it is whole after code build mould-bag concrete, pour C30 and mix under water Solidifying soil is assured.
Wherein: the concrete incorporation non-dispersible underwater concrete wadding in the step (9), in Placement of Underwater Concrete for Casting Solidifying agent.
Wherein: further include step (10): after underwater concrete reaches design strength, remove steel girder platform, water fender and Steel pipe guide pile is cut away, river is restored.
Wherein, in the step (10), the above truss platform of the water surface provides job platform using barge, carries out gas cutting, water Lower steel pipe guide pile is cut by diver using dedicated electrode for underwater cutting.
Wherein, further include the steps that the steel truss frame member recycling and reusing.
Water intake facilities integral installation construction method in a kind of torrent riverbed of the present invention, takes effective in torrent riverbed Measure, reduce the water flow reduction of speed in construction area, avoid diving under water powder charge, the convenient integral installation for solving water intake facilities With the problem of examination, and it is able to achieve and recycles.
The above description is merely a specific embodiment, but that scope of protection of the present invention is not limited thereto is above-mentioned Technical solution only embodies the optimal technical scheme of technical solution of the present invention, the art, any to be familiar with the art Technical staff in the technical scope disclosed by the present invention, can easily think of the change or the replacement, should all cover in guarantor of the invention It protects in range.Therefore, protection scope of the present invention should be based on the protection scope of the described claims.

Claims (10)

1. a kind of facility for fetching water in torrent riverbed, which is characterized in that including aqueduct, positioning steel tube stake and aqueduct The parallel connection beam of axis, pile cover, I-shaped gooseneck, distribution beam, steel facing, column, spandrel girder, water intake, water intake flower stand, Water blocking facility, cross beam frame pipe, railing, side walk slab, hanging ring weldment, chain block, canvas hoisting hook band, roller, aqueduct flower Frame, the connection beam vertical with aqueduct axis;The aqueduct includes horn mouth and straightway, and the water intake facilities are by taking Water lines draw rivers center river for life industrial water, are composed of water intake and aqueduct;With positioning steel tube stake Position is support system, establishes aqueduct truss work platform and horn mouth assembly workbench, and set in the downstream of truss platform Set construction channel for personnel above and below, I-shaped gooseneck, every place's I-shaped gooseneck are installed in the vertical positioning steel tube stake top of every three row Two 10T chain blocks of upper arrangement will be used for binding type lifting pipeline;Using positioning steel tube stake position as support system, establish 14m × The steel girder platform of 5m welds as water intake steel member, slinging work platform, along the vertical of water intake facilities water (flow) direction on platform To two Pin door shaped stents of setting, two Pin door shaped stents are connected by spandrel girder, flower stand, make frame structure, every place's load-bearing Arrange that two 20T chain blocks will be used for hanging-ring type lifting water intake on beam;Using pool hang, chain block will connect it is integral Water intake facilities integrally transfer low water, realize the dry operation that water intake assembly is connect with aqueduct.
2. a kind of facility integral installation construction method for fetching water in torrent riverbed, which comprises the steps of:
(1): double-row steel pipe truss single wall water blocking is applied in such a way that steel truss and steel facing are implemented step by step by barge, the quick-fried ship of brill Plate reduces the water flow reduction of speed in construction area;
(2): using quick-fried ship is bored with blasthole diameter 90mm, hole depth is greater than 5m, short-delay blasting between row, the water for controlling single hop explosive quantity The mode of lower deep hole blasting carries out water intake facilities and intends falling channel excavation;
(3): utilizing the pile driving barge with drilling machine with " three pipes two bore method " pipe-following drilling, apply minor-diameter steel-tube guide pile, water intake Arrange that 5 column 6 are ranked a steel-pipe pile, column pitch is respectively 2.4m, 4.2m, 4.2m, 2.4m, arranges spacing 0.9m;Aqueduct horn mouth Place arranges that 3 column 3 are ranked a steel-pipe pile altogether with water intake in conjunction with, column pitch 4.2m, arranges spacing 2.0m;Straightway aqueduct arrangement 5 column, 24 row, column pitch are respectively 1.2m, 2.1m, 0.6m, 1.2m, arrange spacing 2.0m;
(4): the temporary wharf at interim truss downstream waterborne bank setting one ties up 500 horsepower power ships and landing stage one Driving is acted as, steel girder platform component is transported using landing stage, crane barge as water transportation platform, lifting, with steel pipe guide pile Position is support system, establish the steel girder platform of 14m × 5m welded as water intake steel member, slinging work platform, on platform Along the longitudinally disposed two Pin door shaped stent of water intake facilities water (flow) direction, and configures 6 20 tons of chain blocks and be used for lifting operation;
(5): using landing stage, crane barge using steel pipe guide pile position as support system, establishing aqueduct truss work platform and horn mouth Assembled workbench, and above and below the downstream installation of truss platform construction channel is for personnel, truss is set on bank and operation is flat Platform installs I-shaped gooseneck in two rows of every place's vertical steel pipe positioning stake tops, and two 10T chain blocks of arrangement will on every place's crossbeam Pipeline is lifted for binding type;
(6): being sling aqueduct using chain block, successively Congjiang bank water intake direction into river conveys, and configures two volumes Machine cooperation transport is raised to designated position;
(7): making shipping platform using landing stage and water intaking head component is transported, hanging piece is numbered before lifting, uses 50T truck crane on the bank Water intake steel member is grouped by number and is hung on the cargo ship for resting in temporary wharf, transport foot to water intake work waterborne Near industry platform, is hung using barge or water intake steel member is hung to water intake aquatic work platform and is assembled, splices by crane barge, After component conveying to platform, finely lifted using the 20T chain block of configuration;
(8): being hung using barge, aqueduct, horn mouth, water-fetching head are integrally transferred from aquatic work flat surface by chain block, so The roller and lateral connection component for removing diversion tubular truss afterwards also remove the workbench steel plate in water intaking portion and vertically and horizontally connect structure Part, so that will connect integral water intake facilities entirety average rate after not having barrier under water intake steel case and transfer low water, every decentralization A distance just removes the cross bar for hindering aqueduct decentralization, and the cross bar that connection aqueduct top has been removed immediately, it is ensured that branch The structural stability of frame is repeated up to sinking low water in place, completes water intake facilities installation.
3. a kind of facility integral installation construction method for fetching water in torrent riverbed according to claim 2, feature Be: in the step (1), double-row steel pipe truss single wall water fender gos deep into water in the setting of the water intake facilities upstream position 8~10m In, length, which is arranged, in end to be not less than 10m beyond water intake, to reduce water intake over-water construction regional water flow velocity and eliminate water blocking The security risk that plate reflux constructs to water intake, and ship anchor is set, the water fender is carried out by drawing anchor by wirerope, share water Impact force is flowed, lower part converts moment of flexure torsion for the horizontal impact power of water flow by the support stake of steel truss and is transferred to ground.
4. a kind of facility integral installation construction method for fetching water in torrent riverbed according to claim 2, feature It is: in the step (2) further include: powder charge steel pipe and drill bit of drilling machine are followed up using " three pipes two bore method ", make chargehand By extraditing the water surface under water only charging work need to can be completed from steel pipe top sequence powder charge on ship in sequence, avoid underwater latent Water powder charge waits 15 minutes after detonation, after being checked by security official, dynamiter to quick-fried area and handled blind big gun, using dredger and surpasses Long-armed digging machine carries out underwater scarfing cinder, then examines foundation trench using underwater photography instrument, topography scanners cooperation, realizes foundation trench in deep water river It checks and accepts.
5. a kind of facility integral installation construction method for fetching water in torrent riverbed according to claim 2, feature Be: in the step (3): steel pipe guide pile is higher by construction ordinary water level not less than 2.2m, uses two drill bit of drilling machine for bias The hydraulic drill rig construction steel pipe guide pile used for geological prospecting bored, the steel pipe specifications and models are D168mm, wall thickness is the seamless of 8mm T40 steel pipe carries out spreading using thread casing in standard type, and socket length is 2.5m~3m, and steel pipe internal pressure fills C30 microlith coagulation Soil forms steel tube concrete pile.
6. a kind of facility integral installation construction method for fetching water in torrent riverbed according to claim 2, feature Be: in the step (5): install detachable moved cross beam on every row's steel pipe guide pile, pipeline transportation, docking when from The effect of job platform is provided to pipeline weight is born;Pipeline plays security protection safety effect, and every decentralization 50cm when transferring It needs to carry out accurate adjustment and measurement calibration, in centre from roller is arranged on the crossbeam at water surface 0.5m, is used for pipeline, two sections draw Between water pipe, to prevent steel pipe from plastic deformation occurs, anchor ear or welding are being added in two section steel pipe junctions to korneforos conveying is preceding I-steel is fixed.
7. a kind of facility integral installation construction method for fetching water in torrent riverbed according to claim 2, feature Be: in the step (8): before integral hoisting, make sinking witness marker and scale, implement it is anti-hit overboard urgent measure, The counterweight and setting limiting device, suspension centre reasonable Arrangement and examination for preventing water intake facilities from floating hang, to lifting equipment performance checking, latent The hilllock Shui Yuandao is in place.
8. a kind of facility integral installation construction method for fetching water in torrent riverbed according to claim 2, feature It is: further includes step (9): water intake and aqueduct is observed by diver to the bottom after sinking in place and foundation trench contacts situation, If any larger gap under pipe, it should be spread by diver with C30 concrete block and fill and lead up whole rear code block mould-bag concrete, pour C30 underwater concrete packet Pipe.
9. a kind of facility integral installation construction method for fetching water in torrent riverbed according to claim 8, feature Be: in the step (9), the concrete in Placement of Underwater Concrete for Casting mixes non-dispersible underwater concrete flocculant.
10. a kind of facility integral installation construction method for fetching water in torrent riverbed according to claim 2, feature It is: further includes step (10): after underwater concrete reaches design strength, removes steel girder platform, water fender and cut away steel Pipe guide pile restores river.
CN201910685711.XA 2019-07-28 2019-07-28 A kind of facility and its integral installation construction method for fetching water in torrent riverbed Pending CN110295648A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910685711.XA CN110295648A (en) 2019-07-28 2019-07-28 A kind of facility and its integral installation construction method for fetching water in torrent riverbed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910685711.XA CN110295648A (en) 2019-07-28 2019-07-28 A kind of facility and its integral installation construction method for fetching water in torrent riverbed

Publications (1)

Publication Number Publication Date
CN110295648A true CN110295648A (en) 2019-10-01

Family

ID=68032031

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910685711.XA Pending CN110295648A (en) 2019-07-28 2019-07-28 A kind of facility and its integral installation construction method for fetching water in torrent riverbed

Country Status (1)

Country Link
CN (1) CN110295648A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111022764A (en) * 2019-12-29 2020-04-17 中铁五局集团第二工程有限责任公司 Dry construction method for water diversion pipe water-land adapter
CN113774988A (en) * 2021-09-13 2021-12-10 中建安装集团南京建设有限公司 Deep water taking head device and construction method
CN114525828A (en) * 2022-02-23 2022-05-24 郭锐朋 Box culvert type large seawater taking structure
CN115616592A (en) * 2022-12-20 2023-01-17 山东省煤田地质局第四勘探队 River channel surveying equipment based on mobile ship

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111022764A (en) * 2019-12-29 2020-04-17 中铁五局集团第二工程有限责任公司 Dry construction method for water diversion pipe water-land adapter
CN113774988A (en) * 2021-09-13 2021-12-10 中建安装集团南京建设有限公司 Deep water taking head device and construction method
CN113774988B (en) * 2021-09-13 2023-03-07 中建安装集团南京建设有限公司 Deep water taking head device and construction method
CN114525828A (en) * 2022-02-23 2022-05-24 郭锐朋 Box culvert type large seawater taking structure
CN115616592A (en) * 2022-12-20 2023-01-17 山东省煤田地质局第四勘探队 River channel surveying equipment based on mobile ship
CN115616592B (en) * 2022-12-20 2023-03-07 山东省煤田地质局第四勘探队 River channel surveying equipment based on mobile ship

Similar Documents

Publication Publication Date Title
CN102720140B (en) Large-span prestress concrete continuous beam deepwater pier construction process
CN105386408B (en) Deep-water bridge pile foundation construction method
CN110295648A (en) A kind of facility and its integral installation construction method for fetching water in torrent riverbed
CN109780325B (en) Installation method of underwater pipeline of water taking tunnel of water plant
CN102953341B (en) A kind of high-order trestle work structure be arranged in deep water torrent intectate steep bare rock
CN106120839B (en) A kind of construction technology of off-lying sea blower foundation embedded rock pile
CN104234079B (en) A kind of subway station Y type cast steel combines steel pipe column construction method
CN102537517A (en) Construction technology for jacking pipe in river or lake
CN101538833B (en) Vertical subsection double-wall steel cofferdam water stopping construction method
CN109797749B (en) Underwater foundation pit construction device and construction method
CN102979039B (en) Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN105350526B (en) Method for setting up steel platform
CN113550340A (en) Construction method of deepwater foundation of double-wall steel cofferdam without sealing bottom under deepwater rock entering condition
CN111058458A (en) Construction method and structure based on cutter suction type ground connecting wall local replacement row pile support
CN102268871A (en) Construction method of turnover platform for underwater pile foundation of bridge
CN106812144A (en) Double-wall steel cofferdam construction method
CN102561371A (en) Steel caisson enclosure structure at island-tunnel combination part
CN104164881A (en) Piling wall overlapping cantilever foundation pit support construction method and structure
CN109707002B (en) Device and method for accurately positioning, sinking and installing large water intake head
CN112538852A (en) Construction method of deepwater bored pile for thin covering layer
WO2023207250A1 (en) Construction method for rapidly driving trestle steel pipe pile into sloped bare rock
JP2515888B2 (en) Construction method of steel pipe pile for building offshore structure and its equipment
CN115387207A (en) Shallow covering layer steel-concrete composite pile pier structure and construction method
CN110984003B (en) Method for removing pier and bearing platform at lower part of river-crossing bridge
CN104047276B (en) The on-the-spot joining method of a kind of lattice steel sheet pile large cylinder nominative sheet pile 1/4 cylinder

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination