JP2023036518A - Construction method for ultra-long pre-stressed steel bundle - Google Patents

Construction method for ultra-long pre-stressed steel bundle Download PDF

Info

Publication number
JP2023036518A
JP2023036518A JP2022094762A JP2022094762A JP2023036518A JP 2023036518 A JP2023036518 A JP 2023036518A JP 2022094762 A JP2022094762 A JP 2022094762A JP 2022094762 A JP2022094762 A JP 2022094762A JP 2023036518 A JP2023036518 A JP 2023036518A
Authority
JP
Japan
Prior art keywords
steel
ultra
anchor
bundle
wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2022094762A
Other languages
Japanese (ja)
Inventor
劉文生
Wensheng Liu
張治国
zhi guo Zhang
李鳳成
Fengcheng Li
馮超
Chao Feng
王高平
Gao Ping Wang
陳兆波
zhao bo Chen
尚亜新
Yaxin Shang
蘇力
Li Su
閔坤
Kun Min
謝磊
Lei Xie
陳雲明
Yunming Chen
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Engineering Co Ltd of China Railway Beijing Engineering Group Co Ltd
Original Assignee
Second Engineering Co Ltd of China Railway Beijing Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Engineering Co Ltd of China Railway Beijing Engineering Group Co Ltd filed Critical Second Engineering Co Ltd of China Railway Beijing Engineering Group Co Ltd
Publication of JP2023036518A publication Critical patent/JP2023036518A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Reinforcement Elements For Buildings (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

To solve the problem that although a large part of a pre-stressed steel twist yarn in an existing construction method is provided in a vertical surface and a bottom surface, an artificial beam is usually adopted, a maximum length of the artificial beam is generally within 70 m, it is a large technique difficulty how to save time and labor and realize ultra-long pre-stressed bundle, tension, slurry and anchor sealing for an ultra-long pre-stressed steel bundle having a top face thin layer structure.SOLUTION: A construction method for an ultra-long pre-stressed steel bundle includes the steps of: positioning and assembling a pre-stressed tube; inserting an upper face pre-stressed steel bundle; pre-stressing and tensing the upper face; mortar-pressing an upper face pre-stressed bundle tube; and pre-stressing and anchor-embedding the upper face. Mechanical means can be adopted in place of artificial means. Power is provided by an insertion machine, a steel drawn line is penetrated, and efficiency is improved.SELECTED DRAWING: Figure 1

Description

本発明は橋工事の施工分野に関し、具体的には、超長予応力鋼製束の施工方法に関する。 The present invention relates to the construction field of bridge construction, and in particular to a method for construction of ultra-long prestressed steel bundles.

大スパンコンクリート構造の安全と安定を保証するために、プレストレストコンクリート
の施工技術を採用するのが一般的です。プレストレストコンクリート施工技術におけるパ
イプラインの埋設、ケーブル貫通、引張、スラリー圧造、アンカー封止にとって、プレス
トレスト施工全体を貫く全過程である。
To ensure the safety and stability of large-span concrete structures, it is common to adopt prestressed concrete construction technology. For pipeline burying, cable penetration, tensioning, slurry heading and anchor sealing in prestressed concrete construction technology, it is a whole process that goes through the whole prestressed construction.

既存の施工法におけるプレストレスト鋼撚糸の大部分は立面と底面に配置され、通常は人
工ビームを採用し、人工ビームの最大長は一般的に70m以内である。しかし、頂面薄層構
造の超長プレストレスト鋼束に対して、どのように時間と省力を節約して超長プレストレ
スト束、張力、スラリー、アンカー封じの実現を確保するかは大きな技術難点である。薄
層構造の頂面は箱梁天板の製限によって操作空間が限られ、人工操作に時間がかかり、ベ
ローズ内の鋼撚線の数が多ければ多いほど完成しにくく、一般的な施工はセグメント牽引
方式を採用することが多く、ベローズに牽引孔を開き、品質に隠れた危険性がある。
Most of the prestressed steel strands in the existing construction methods are placed on the vertical and bottom surfaces, and usually adopt artificial beams, and the maximum length of the artificial beams is generally within 70m. However, how to save time and labor to ensure the realization of ultra-long prestressed bundles, tension, slurry, and anchor sealing for the super-long prestressed steel bundles with thin top layer structure is a big technical difficulty. . On the top surface of the thin layer structure, the operation space is limited due to the manufacturing limit of the box beam top plate, and it takes time to manually operate it. Segment traction method is often used, which opens a traction hole in the bellows, creating a hidden danger in quality.

現在、プレストレスト束機は超長プレストレスト束の施工に応用されているが、束を通す
過程では一本のみの駆動しか実現できず、多対鋼撚線の鋼束に対しては繰り返ししか行う
ことができない。束を通す過程で特に最後の数本の鋼撚糸の時に管壁と衝突しやすく、押
し込むと管路が破損し、コンクリート、管路の破片が落ちて管路が塞がる可能性がある。
同時に予応力の後続のスラリー圧造とアンカー封止も空間製限による施工困難である。そ
のため、従来技術は超長プレストレストの束を通すのに時間がかかり、プレストレストの
施工品質を保証することが困難である。
At present, the prestressing bundling machine is applied to the construction of ultra-long prestressed bundles, but in the process of threading the bundles, only one drive can be realized, and the steel bundles of multi-pair steel strands can only be operated repeatedly. can't In the process of passing the bundle, especially the last few steel strands, it is easy to collide with the pipe wall.
At the same time, the subsequent slurry heading and anchor sealing of prestressing is also difficult due to space limitations. Therefore, the prior art takes a long time to pass the super-long prestressed bundle, and it is difficult to guarantee the prestressed construction quality.

また、従来の大スパン連続梁の施工時には、頂面縦方向プレストレスト鋼束が最長200 m
を超え、箱室は横隔梁によって室内空間が製限されていた。どのように有限空間で頂面鋼
撚糸の束通し、張力、スラリー圧着、アンカー封じを実現するかは解決すべき技術難題と
なっている。
In addition, when constructing conventional large-span continuous beams, the maximum vertical prestressed steel bundle on the top surface is 200 m.
In Hakomuro, the interior space was limited by diaphragm beams. How to achieve bundling, tensioning, slurry crimping and anchor sealing of the top steel strand in a limited space is a technical problem to be solved.

関連技術の問題に対して、現在でも有効な解決策はない。 There are currently no effective solutions to problems in the related art.

関連技術における問題に対して、本発明は超長予応力鋼製束の施工方法を提案し、従来の
関連技術に存在する上述の技術問題を克服する。
そのため、本発明が採用する具体的な技術方案は以下の通りである。
In view of the problems in the related art, the present invention proposes a construction method for ultra-long prestressed steel bundles to overcome the above-mentioned technical problems existing in the prior art.
Therefore, the specific technical solutions adopted by the present invention are as follows.

超長予応力鋼製束の施工方法は、
予応力管道18のポジショニングと組立するステップと、
上面予応力鋼製束を挿通させるステップと、
上面予応力緊張させるステップと、
上面予応力束管道18のモルタルプレスするステップと、
上面予応力アンカー埋込みするステップと、を含む。
好ましくは、前記予応力管道18のポジショニングと組立するステップは、
プラスチック材波紋管による縦方向予応力穴の形成をするステップと、
管道組立と鋼筋拘束とモジュール組立の交互操作するステップと、
井字状のポジショニング鋼筋と鋼筋骨により確実的に半田づけするステップと、
波紋管における断裂の検査により、波紋管のモルタルリークによる管道の塞ぎを防止する
ステップと、
套管の引き押しにより管内のコンクリート凝固を防止するステップと、を含む。
好ましくは、前記上面予応力鋼製束を挿通させるステップは、
施工穴の位置に対応する延長線上において斜長予備穴を予備することにより引張ロープ9
を組するステップと、
予応力鋼製束2の全体穴貫設するステップと、を含む。
好ましくは、引張ロープ9は1本の鋼絞線を用い、そして機械的に挿通機により貫設する

好ましくは、前記上面予応力鋼製束を挿通させるステップは、
鋼絞線のズレ鋼線編製及び鋼製束の端部処理するステップと、
深埋めアンカー技術により、アンカー受板11は構成外廓辺線からの0.2m距離の構成
内部の凹溝に埋め込むと共に、緊張際にアンカー受板11と緊張オイルキャップ17の間
に延長筒を設置して移変させるするステップと、
ティースブロックの前端でリービング穴道を予備し、人工により機械を補助する形で全体
束の鋼絞線の引くことを行うと共に、鋼製束を他端まで張引すると、十分な工作長度を残
って、ホイールにより鋼絞線を切断するするステップと、を含む。
好ましくは、前記鋼絞線のズレ鋼線編製及び鋼製束の端部処理するステップは、
鋼絞線からズレ編製によって前端で錐状体を形成するするステップと、
細鋼線により張引ロープの一端と全体束挿通がすべき鋼絞線とを円錐状に編み合わせるこ
とにより円錐状を形成するするステップと、
挿通してから未編製部位における鋼絞線をホイールにより切除するするステップと、を含
む。
好ましくは、前記上面予応力緊張させるステップは、
ビーム面により2つのオイルキャップ工作予備小穴を予備し、鋼線ケーブルを貫通させて
、ビーム上面に吊上げ手段を逆さ掛けとするチェーンホイストを設置するステップと、
ビーム上面のチェーンホイストによりビーム内の緊張オイルキャップ17を吊り上げ、ビ
ーム内に操作台を載設し、または検査トラックを設置するステップと、
止め板、アンカー具、挟み片移変環を取り付けること、及び緊張工作を完成するステップ
と、を含む。
好ましくは、前記上面予応力束管道18のモルタルプレスするステップは、
緊張施工してから48h以内にモルタルプレスを行うステップと、
露出した鋼絞線を切除して、アンカー埋込みを行うステップと、
アンカー受板11上のモルタル注入穴を整理するステップと、を含む。
好ましくは、前記モルタルプレスの方法は、
真空抽出し、真空ポンプを起動して、システム負圧を0.07~0.1Mpaにさせるこ
と、
穴道の真空度が一定になると、ポンプを1min停止させること、
圧力低降が0.02Mpaより小さいと、穴道が真空になると判定し、圧力低降が0.0
2Mpaより大きいと、穴道が未完全密閉であり、モルタル注入前で検査および修正が必
要であると判定すること、を含む。
好ましくは、前記上面予応力アンカー埋込みするステップは、
鉄線により緊張端のアンカー埋込みモジュール22を上面から直接にビーム上面に固定し
て、操作空間の狭小問題を減少させるさせるステップと、
深埋めアンカー口の上面に予備穴15を設置するステップと、
アンカー埋込みコンクリートをビーム上面から注入して、振着するステップと、を含む。
The construction method of ultra-long prestressed steel bundles is
positioning and assembling the prestress conduit 18;
inserting a top prestressed steel bundle;
tensioning the upper surface prestress;
mortar pressing the top prestress flux duct 18;
and embedding a top surface prestress anchor.
Preferably, the positioning and assembling of the prestress conduit 18 comprises:
forming a longitudinal prestress hole with a corrugated tube of plastic material;
alternately operating pipe assembly, steel bar restraint, and module assembly;
a step of reliably soldering with a well-shaped positioning steel bar and a steel bar;
inspecting for ruptures in the ripple tube to prevent blockage of the conduit due to mortar leaks in the ripple tube;
and c. preventing solidification of concrete in the tube by pulling on the bushing.
Preferably, the step of inserting said top surface prestressed steel bundle comprises:
By preparing an oblique preliminary hole on the extension line corresponding to the position of the construction hole, the tension rope 9
a step of combining
and d.
Preferably, the pull rope 9 uses a single steel wire and is mechanically threaded by a threader.
Preferably, the step of inserting said top surface prestressed steel bundle comprises:
a step of braiding a steel wire with a deviation of the steel drawn wire and processing the end of the steel bundle;
With the deep-buried anchor technology, the anchor receiving plate 11 is embedded in the groove inside the structure at a distance of 0.2 m from the outer circumference of the structure, and an extension cylinder is inserted between the anchor receiving plate 11 and the tensioning oil cap 17 during tensioning. placing and translating;
A reeving hole path is prepared at the front end of the tooth block, and the steel drawing wire of the entire bundle is drawn manually by assisting the machine. , cutting the steel wire with the wheel.
Preferably, the steps of forming a misaligned steel wire of the drawn steel wire and treating the end of the steel bundle include:
forming a cone at the front end by offset knitting from a steel wire;
forming a conical shape by conically weaving one end of the tension rope with a fine steel wire and a steel draw wire through which the entire bundle should be inserted;
cutting the steel draw wire in the unwoven portion after threading with the wheel.
Preferably, said top surface prestressing step comprises:
Preparing two oil cap spare eyelets on the beam face, passing steel wire cables through it, and installing a chain hoist with a lifting means upside down on the beam face;
lifting the taut oil cap 17 in the beam by means of a chain hoist on top of the beam and mounting a control platform or an inspection truck in the beam;
Attaching stop plates, anchors, clip transition rings, and completing the tensioning.
Preferably, the step of mortar pressing the top prestress flux duct 18 comprises:
a step of performing mortar pressing within 48 hours after tension construction;
cutting the exposed steel wire and embedding the anchor;
and arranging the mortar injection holes on the anchor receiving plate 11 .
Preferably, the method of mortar pressing comprises:
vacuum extraction, starting the vacuum pump to make the system negative pressure 0.07~0.1Mpa;
Stop the pump for 1 minute when the degree of vacuum in the tunnel becomes constant,
If the pressure drop is less than 0.02Mpa, it is determined that the hole is vacuum, and the pressure drop is 0.0
If greater than 2Mpa, determine that the hole passage is not fully sealed and needs inspection and correction before mortar injection.
Preferably, the top surface prestress anchor embedding step comprises:
fixing the taut end anchor embedding module 22 directly from the top surface to the top surface of the beam by iron wire to reduce the problem of narrow operating space;
installing a preliminary hole 15 in the upper surface of the deep-buried anchor mouth;
and pouring anchor-embedded concrete from the upper surface of the beam and shaking.

上記本発明の技術案によれば、「引く+備える+張る」といった施工方法を用いて、上面
超長予応力鋼製束の施工際における空間制限、手間がかかること、鋼絞線による穴壁の容
易破壊、モルタルプレスの不飽満、アンカー埋込み施工困難という課題を解決している。
また、以下の技術的効果を有する。
1 人工に代えて機械手段を採用できる。挿通機により動力を提供して鋼絞線の貫設を実
現し、効率を向上する。
2 「バラバラ→全体」にする。引張ロープを案内とすることにより、予応力束の全体整
穴貫設を実現し、1本鋼絞線による繰り返し挿通施工であれば周期が長いといった問題を
解決する。さらに、全体穴貫設により鋼絞線間の相対順方向と緩和度を保証できる。
3 ビーム面においてリービング穴道を予備する。鋼絞線と挿通機はいずれもビーム面に
配置される。挿通過程全体は基本的にビーム面で行われる。このため、有効的に下方空間
の制限による悪影響を回避できる。
4 鋼線ズレ編製により予応力接続端を錐状端にすることができる。また、前端に保護カ
バーを備えるので、鋼製束と穴壁を効果的に隔離させる
5 アンカー定着端にアンカーを深埋めるという設計により、「移変環」を支持とする。
穴口隙間を利用してアンカー具のズレを調整することによりアンカー受板への応力集中を
防止する。深埋めアンカー凹溝設計によりアンカー埋込みの施工操作を簡単化させ、施工
質量を保証できる。
6 本施工技術の応用はプレストレストが室内空間の限られた状況の下で高効率、迅速、
高品質のプレストレスト施工の完成を実現し、しかもこの技術は横展開することができ、
鋼混合梁などの下方の施工条件のないプレストレスト構造施工に応用され、広範な応用場
面を持っている。
According to the above technical solution of the present invention, using the construction method of "pull + prepare + stretch", there are space restrictions and labor in constructing the upper surface ultra-long prestress steel bundle, and the hole wall by the steel drawn wire It solves the problems of easy destruction of the mortar, lack of mortar press, and difficulty of embedding anchors.
Moreover, it has the following technical effects.
1 Mechanical means may be employed in place of manual labor. The insertion machine provides power to realize the penetration of the steel drawing wire and improve the efficiency.
2 Make it "discrete → whole". By using a tension rope as a guide, it is possible to align the prestress bundle through the whole hole, and solve the problem that the cycle is long if repeated insertion work is performed using a single steel drawn wire. In addition, the full hole penetration can ensure the relative forward direction and relaxation between the steel drawn wires.
3 Prepare a reeving hole path in the beam plane. Both the steel draw wire and the threader are placed in the plane of the beam. The entire threading process basically takes place in the plane of the beam. Therefore, it is possible to effectively avoid adverse effects due to the limitation of the lower space.
4 The prestress connection end can be made into a conical end by steel wire slip knitting. It also has a protective cover on the front end, which effectively isolates the steel bundle and the hole wall.
To prevent stress concentration on an anchor receiving plate by adjusting the displacement of an anchor tool using a hole opening. The deep-buried anchor groove design simplifies the operation of embedding the anchor and guarantees the construction weight.
6. The application of this construction technology is highly efficient, rapid, and prestressed under the limited indoor space.
We have achieved the completion of high-quality prestressed construction, and this technology can be expanded horizontally.
It is applied to the construction of prestressed structures without construction conditions below, such as steel mixed beams, and has a wide range of applications.

本発明の実施形態または従来技術における技術的態様をより明確に説明するために、以下
に実施形態において使用する必要がある図面を簡単に紹介する。明らかに、以下の説明に
おける図面は本発明のいくつかの実施形態にすぎず、当業者にとっては、創造的な労働を
払わずに、これらの図面に基づいて他の図面を得ることもできる。
In order to describe the embodiments of the present invention or the technical aspects in the prior art more clearly, the following briefly introduces the drawings that need to be used in the embodiments. Obviously, the drawings in the following description are just some embodiments of the present invention, and those skilled in the art can also derive other drawings based on these drawings without creative effort.

本発明の実施例に係る超長予応力鋼製束の施工方法のフローチャートである。1 is a flow chart of a method for constructing an ultra-long prestressed steel bundle according to an embodiment of the present invention; 本発明の実施例に係るボックスビーム上面予応力の配置図である。FIG. 4 is a layout diagram of a box beam upper surface prestress according to an embodiment of the present invention; 本発明の実施例に係る引張ロープ貫設を示す模式図である。FIG. 4 is a schematic diagram showing a tension rope penetration according to an embodiment of the present invention; 本発明の実施例に係る予応力鋼製束編製を示す模式図である。1 is a schematic diagram showing prestressed steel bundle knitting according to an embodiment of the present invention; FIG. 本発明の実施例に係る深埋めアンカーを示す模式図である。1 is a schematic diagram showing a deep-buried anchor according to an embodiment of the present invention; FIG. 本発明の実施例に係る引張リービングを示す模式図である。FIG. 3 is a schematic diagram showing tension reeving according to an embodiment of the present invention; 本発明の実施例に係る上面緊張を示す模式図である。FIG. 4 is a schematic diagram showing upper surface tension according to an embodiment of the present invention; 本発明の実施例に係るアンカー埋込みを示す模式図である。FIG. 3 is a schematic diagram showing anchor embedding according to an embodiment of the present invention;

[符号の説明]
1 ボックスビーム上板
2 予応力鋼製束
3 アンカー定着ティースブロック
4 緊張オイルキャップ
5 ダイヤフラムビーム
6 ボックスビーム底板
7 挿通機
8 予備穴道
9 引張ロープ
10 穴道中心線
11 アンカー受板
12 大アンカー予備穴
13 チェーンホイスト
14 吊り枠
15 予備穴
16 鋼線ケーブル
17 緊張オイルキャップ
18 予応力管道
19 移変環
20 コンクリート注入穴
21 ビーム本体
22 アンカー埋込みモジュール
23 アンカー埋込みコンクリート
24 管道中線
[Description of symbols]
1 Box beam upper plate 2 Prestressed steel bundle 3 Anchor fixing tooth block 4 Tension oil cap 5 Diaphragm beam 6 Box beam bottom plate 7 Insertion machine 8 Preliminary hole path 9 Pulling rope 10 Hole path center line 11 Anchor receiving plate 12 Large anchor preliminary hole 13 Chain hoist 14 Suspension frame 15 Spare hole 16 Steel wire cable 17 Tensioning oil cap 18 Prestress pipe 19 Transition ring 20 Concrete injection hole 21 Beam body 22 Anchor embedding module 23 Anchor embedding concrete 24 Pipe center line

各実施形態をさらに説明するために、図面は本発明の開示内容の一部であり、主に実施形
態を説明するために使用され、明細書の関連説明と合わせて実施形態の動作原理を説明す
ることができ、これらの内容を参照するために、当業者は、他の可能な実施形態および本
発明の利点を理解することができるはずであり、図中のコンポーネントは比例して描かれ
ていない。類似したコンポーネントの符号は、通常、類似したコンポーネントを表すため
に使用されます。
In order to further describe each embodiment, the drawings are part of the disclosure of the present invention and are mainly used to describe the embodiments, and together with related descriptions in the specification, explain the principle of operation of the embodiments. and, upon reference to these contents, those skilled in the art should be able to appreciate other possible embodiments and advantages of the present invention, the components in the figures being drawn in proportion. do not have. Similar component codes are commonly used to represent similar components.

本発明は、超長予応力鋼製束の施工方法を提供する。
本施工方法の主要な手順は、管道のポジショニングおよび組立、上面予応力鋼製束2の挿
通、上面予応力緊張、上面予応力束への管道モルタルプレス、上面予応力アンカー埋込み
等を含む。上面予応力鋼製束2の全体施工手順に対して最適化および創新が行われてなる
ものである。「引き(張引ロープの機械的動きによる全体穴貫設)+備え(リービング、
緊張、モルタルプレスにおける予備穴の採用)+張り(緊張の端口における緊張増加、溝
口へのアンカー埋込み)」といった施工手順により有効的に工作効率を向上し、上面予応
力施工の空間不都合による制限を減少させ、上面鋼製束の全体手順施工を順調にさせる。
この手法の主要な思想は、(1)「引くこと」:「人工的でありながら機械的に張引ロープ
の全体穴への貫設を完成すること」により効果を上げること、(2)「備えること」:上面
予応力施工における総合考慮、すなわち、予備穴位置の数量上、正確度上、操作可能性上
の総合考慮を踏みあえて、各工程のリービング、緊張、モルタルプレス、アンカー埋込み
の最適化とロフティングを工夫すること、(3)「張ること」:上面超長ロープの緊張、ア
ンカー埋込みの過程における上面空間の制限、端部モジュールのポジショニング、定着、
コンクリート注入等の素因を考えて、「端部破壊」を避けるように工夫して施工質を向上
することを含む。
The present invention provides a method for constructing ultra-long prestressed steel bundles.
The main steps of this construction method include pipe positioning and assembly, insertion of top prestressed steel bundle 2, top prestress tensioning, pipe mortar press into top prestress bundle, top prestress anchor embedding, and so on. Optimization and innovation are made to the overall construction procedure of the top prestressed steel bundle 2 . "Pulling (piercing the entire hole by mechanical movement of the pulling rope) + preparation (reeving,
Tensioning, use of spare holes in mortar press) + Tensioning (increased tension at the end of tensioning, embedding anchors in grooves) effectively improves work efficiency and eliminates limitations due to spatial inconvenience in top surface prestress construction. reduce and smooth the overall procedure construction of the upper surface steel bundle.
The main ideas of this method are: (1) "pulling": increasing the effect by "manually but mechanically completing the penetration of the pulling rope into the entire hole", (2) " Preparedness: Comprehensive consideration in top surface prestress construction, that is, comprehensive consideration of the number of preliminary hole positions, accuracy, and operability, reeving, tensioning, mortar pressing, and anchor embedding in each process (3) "Tensioning": tensioning of the upper surface ultra-long rope, limitation of the upper surface space in the process of embedding the anchor, positioning and anchoring of the end module,
Considering factors such as concrete pouring, it includes devising ways to avoid "edge failure" and improve construction quality.

図面と実施例を参考しながら本発明を説明する。図1は、本願実施例にかかる超長予応力
鋼製束の施工方法を示す。該方法は、以下の工程を含む。
S1:予応力管道18のポジショニングと組立。
工程S1は、以下の工程を含む。
S11:プラスチック材波紋管による縦方向予応力穴の形成。
S12:管道組立と鋼筋拘束とモジュール組立の交互操作。
S13:井字状のポジショニング鋼筋と鋼筋骨により確実的に半田づける。
なお、1mの直線段ごとに一道、0.5mの曲線段ごとに一道といった原則に従うことに
より、予応力波紋管の配置過程では、穴道ポジショニングの正確確実性及び浮上、横曲げ
の防止を保証する。
S14:波紋管における断裂の検査により、波紋管のモルタルリークによる管道の塞ぎを
防止する。
S15:套管の引き押しにより管内のコンクリート凝固を防止する。
The present invention will be described with reference to the drawings and examples. FIG. 1 shows a method of constructing an ultra-long prestressed steel bundle according to an embodiment of the present application. The method includes the following steps.
S1: Positioning and assembly of the prestress conduit 18;
Step S1 includes the following steps.
S11: Formation of longitudinal prestress holes with plastic corrugated tubes.
S12: Alternate operation of pipe assembly, steel bar restraint and module assembly.
S13: Reliably soldering with the U-shaped positioning steel bar and the steel bar.
In addition, according to the principle of one path for each 1m straight step and one path for each 0.5m curved step, in the process of arranging the pre-stress rippled pipe, it is possible to ensure the accuracy and reliability of the positioning of the hole and the prevention of floating and lateral bending. .
S14: Check for rupture in the rippled tube to prevent clogging of the rippled tube due to mortar leak.
S15: Prevent solidification of concrete in the pipe by pulling and pushing the cannula.

S2:上面予応力鋼製束の挿通。
図2~3に示すように、工程S2は、以下の工程を含む。
S21:施工穴の位置に対応する延長線上において斜長予備穴を予備することにより引張
ロープ9を組立る(2人で操作可能となり、大幅に労働強度を軽減させ、生産効率を向上
する)。
なお、引張ロープ9は1本の鋼絞線を用い、そして機械的に挿通機により貫設する。1本の
鋼絞線が穴道より小体積なので、鋼絞線の貫設が容易に実現できる。
S22:予応力鋼製束2の全体穴貫設。
図4~6に示すように、工程S22は以下の工程を含む。
S221:鋼絞線のズレ鋼線編製及び鋼製束の端部処理。
工程S221は以下の工程を含む。
S2211:鋼絞線からズレ編製によって前端で錐状体を形成する。
S2211:細鋼線により張引ロープの一端と全体束挿通がすべき鋼絞線とを円錐状に編
み合わせることにより円錐状を形成する。
S2211:挿通してから未編製部位における鋼絞線をホイールにより切除する。
S222:深埋めアンカー技術により、アンカー受板11は構成外廓辺線からの0.2m
距離の構成内部の凹溝に埋め込む(開口型の設計とすることにより管道と全体鋼製束との
摩擦を減少させる)と共に、緊張際にアンカー受板11と緊張オイルキャップ17の間に
延長筒を設置して移変させることにより、移変環と溝壁の隙間によりアンカー具の位置ず
れを調整することによって、アンカーのアンカー受板11凹溝内に位置することを保証し
、応力集中を防止する。
S223:ティースブロックの前端でリービング穴道を予備し、人工により機械を補助す
る形で全体束の鋼絞線の引くことを行うと共に、鋼製束を他端まで張引すると、十分な工
作長度を残って、ホイールにより鋼絞線を切断する。
なお、鋼絞線及び挿通機は共にビーム面に配置される。挿通過程はほとんどビーム面にお
いて完成するので、有効的に下方空間の制限による影響を回避することができる。
S2: Insertion of top prestressed steel bundle.
As shown in FIGS. 2-3, step S2 includes the following steps.
S21: Assemble the pulling rope 9 by preparing oblique spare holes on the extension line corresponding to the position of the construction hole (it can be operated by two people, greatly reducing labor intensity and improving production efficiency).
The pulling rope 9 is made of a single drawn steel wire and is mechanically inserted by a threading machine. Since one steel drawn wire has a smaller volume than the hole, the steel drawn wire can be easily installed through.
S22: Pierce the prestressed steel bundle 2 through the entire hole.
As shown in FIGS. 4-6, step S22 includes the following steps.
S221: Displaced steel wire knitting of steel drawn wire and end treatment of steel bundle.
Step S221 includes the following steps.
S2211: A cone is formed at the front end by slip knitting from a steel drawing wire.
S2211: A conical shape is formed by weaving one end of the tension rope and the steel draw wire through which the entire bundle should be inserted by a fine steel wire into a conical shape.
S2211: After inserting, cut off the drawn steel wire in the non-knitted portion with the wheel.
S222: With the deep-buried anchor technology, the anchor receiving plate 11 is 0.2m from the configuration outer edge line.
embedded in the recessed groove inside the distance structure (the open design reduces the friction between the pipe and the entire steel bundle), and an extension tube is inserted between the anchor receiving plate 11 and the tensioning oil cap 17 during tensioning. By installing and displacing the anchor, the gap between the displacement ring and the groove wall adjusts the positional deviation of the anchor, thereby ensuring that the anchor is positioned in the recessed groove of the anchor receiving plate 11, and stress concentration is reduced. To prevent.
S223: A reeving hole path is prepared at the front end of the tooth block, and the steel drawing wire of the entire bundle is manually drawn with the aid of the machine. The remaining steel wire is cut by the wheel.
In addition, both the steel drawing wire and the inserter are arranged in the beam plane. The insertion process is almost completed in the plane of the beam, effectively avoiding the influence of the lower space limitation.

S3:上面予応力緊張。
図7に示すように、工程S3は、以下の工程を含む。
S31:ビーム面により2つのオイルキャップ工作予備小穴を予備し、鋼線ケーブルを貫
通させて、ビーム上面に吊上げ手段を逆さ掛けとするチェーンホイストを設置する。
S32:ビーム上面のチェーンホイストによりビーム内の緊張オイルキャップ17を吊り
上げ、ビーム内に操作台を載設し、または検査トラックを設置する(緊張過程中でダブル
コントロールを用い、緊張応力のコントロールを主とし、緊張延長量をチェック用とする
)。
S33:止め板、アンカー具、挟み片移変環を取り付けること、及び緊張工作を完成する
こと。
これにより、緊張過程中で、上面予応力鋼製束の順調な緊張を保証することができる。緊
張オイルキャップ17は、端部の鋼絞線を貫通させて緊張鋼絞線の断面と垂直することが
できる。
S3: top surface prestress tension.
As shown in FIG. 7, step S3 includes the following steps.
S31: Prepare two oil cap spare holes on the beam surface, pass the steel wire cable through it, and install the chain hoist with the lifting means upside down on the beam surface.
S32: Lift the tension oil cap 17 in the beam with the chain hoist on the upper surface of the beam, place the operation table in the beam, or install the inspection truck (using double control during the tensioning process, mainly to control the tension stress). and use it to check the amount of tension extension).
S33: Install stop plate, anchoring device, clamping piece displacement ring, and complete tension work.
This makes it possible to ensure a smooth tensioning of the top-prestressed steel bundle during the tensioning process. The tension oil cap 17 can be passed through the end steel draw wire and perpendicular to the cross-section of the tension steel draw wire.

S4:上面予応力束管道18のモルタルプレス。
工程S4は、以下の工程を含む。
S41:緊張施工してから48h以内にモルタルプレスを行う。
前記モルタルプレスの方法は、以下のことである。
S411:真空抽出する。真空ポンプを起動して、システム負圧を0.07~0.1Mp
aにさせる。
S412:穴道の真空度が一定になると、ポンプを1min停止させる。
S413:圧力低降が0.02Mpaより小さいと、穴道が真空になると判定し、圧力低
降が0.02Mpaより大きいと、穴道が未完全密閉であり、モルタル注入前で検査およ
び修正が必要であると判定する。
S42:露出した鋼絞線を切除して、アンカー埋込みを行う。
S43:アンカー受板11上のモルタル注入穴を整理する。
S4: Mortar pressing of the top prestress bundle duct 18 .
Step S4 includes the following steps.
S41: Mortar press is performed within 48 hours after tension construction.
The method of the mortar press is as follows.
S411: Vacuum extraction. Start the vacuum pump and set the system negative pressure to 0.07 to 0.1Mp
Let a.
S412: When the degree of vacuum in the tunnel becomes constant, the pump is stopped for 1 minute.
S413: If the pressure drop is less than 0.02Mpa, it is determined that the hole passage is vacuum; if the pressure drop is greater than 0.02Mpa, the hole passage is not completely sealed and needs to be inspected and corrected before mortar injection. Determine that there is.
S42: Cut off the exposed steel wire and embed the anchor.
S43: Arrange the mortar injection holes on the anchor receiving plate 11 .

S5:上面予応力アンカー埋込み。
図8に示すように、工程S5は、以下の工程を含む。
S51:鉄線により緊張端のアンカー埋込みモジュール22を上面から直接にビーム上面
に固定して、操作空間の狭小問題を減少させる。
S52:深埋めアンカー口の上面に予備穴15を設置する。
S53:アンカー埋込みコンクリートをビーム上面から注入して、みっしりと振着する。
なお、上面予応力緊張が終わると、現場の操作空間が狭くなってしまい、モジュールの組
立及びモジュールの固定ができなくなるが、工程S5により予応力鋼製束のアンカー埋込
みを順調に実施させることを保証する。
S5: Top surface prestress anchor embedding.
As shown in FIG. 8, step S5 includes the following steps.
S51: The tension end anchor embedding module 22 is directly fixed on the upper surface of the beam by iron wire from the upper surface to reduce the problem of narrow operation space.
S52: Install a preliminary hole 15 on the upper surface of the deep-buried anchor port.
S53: Anchor-embedded concrete is injected from the upper surface of the beam and shaken tightly.
After the upper surface prestress tensioning is completed, the operation space at the site becomes narrow, and it becomes impossible to assemble the module and fix the module. Guarantee.

本発明の上記法案を容易に理解させるため、以下、本発明の実際実施過程における動作原
理や操作方式を詳しく説明する。
実際の応用では、まず、挿通条件が満たされると、予備穴15を利用してビーム上面で挿
通機7により引張ロープ9の組立を行う。引張ロープ9は1本鋼絞線を用いるので、一定
の硬度を持ち、そして1本鋼絞線が予備管道より小体積であり、容易に挿通が可能となる
。正式的挿通の前、管道の長度と予備工作長度によって挿通量を決定する。該鋼製束の全
ての被挿鋼絞線を円錐状に沿ってネットバッグにより一緒に編製する。前端と引張ロープ
を接続して機械により引張して反方向に引き取ることにより、全体穴の鋼絞線を一度に所
定位置に引き取ることを実現する。それにより、鋼絞線の順調挿通、人工低効率、1本鋼
絞線の繰り返し挿通施工による長周期といった問題を解決する。また、全体穴貫設によっ
て、鋼絞線間の相対順方向と緩和度を保証できる。さらに、管道内における鋼製束の穴壁
との衝突による管道の塞ぎを回避するので、鋼製束の順調挿通を確保できる。被挿全体束
の鋼製束の端部で、鋼線ネットにより、円錐状に編製すると共に、引張ロープ9と鋼製束
の間に錐状の保護カバーを形成することにより鋼製束と穴壁の接触を防止する(即ち、管
道内で引張ロープは常に断面中心に位置し、かつ管壁と鋼製束の間に隔離層が存在するよ
うに保証する)ので、全体穴の鋼製束の穴内順調挿通を保証することができる。次に、ボ
ックスビーム上板1に穴洞を予備することにより、鋼絞線の緊張とモルタルプレス作業を
行うので、ボックス内の操作空間が狭くて、オイルキャップのポジショニングと緊張が困
難であるといった問題を解決する。最後は、上板に穴洞を予備すると共にティースブロッ
クの前端に凹溝を増設することにより、。ティースブロックのアンカー端のモジュール強
固とコンクリート注入の操作困難といった問題を解決する。「引く+備える+張る」とい
った施工方法の応用により、ボックスビームの各部位に予備穴を設置し、凹溝を増設する
等の手段により、超長予応力鋼製束はボックスビーム内の挿通、緊張、モルタルプレス、
アンカー埋込みが空間制限により操作され難いといった問題を解決する。施工過程では大
幅に施工難度を低減させ、施工コストの減少と施工期限の短縮を図る。
In order to facilitate the understanding of the above-mentioned scheme of the present invention, the working principle and operation method in the actual implementation process of the present invention will be described in detail below.
In practical application, first, when the insertion conditions are satisfied, the tension rope 9 is assembled by the insertion machine 7 on the upper surface of the beam using the preliminary hole 15 . Since the pulling rope 9 uses a single steel drawn wire, it has a certain hardness, and the single steel drawn wire has a smaller volume than the spare conduit, so that it can be easily inserted. Before the formal penetration, the penetration amount is determined according to the length of the pipeline and the preparatory length. All the inserted steel wires of the steel bundle are knitted together by a net bag along the cone. By connecting the front end and the tension rope to pull it by the machine and pull it in the opposite direction, it is possible to pull the steel drawn wire of the whole hole to a predetermined position at once. This solves the problems of smooth insertion of steel drawn wire, artificial low efficiency, and long cycle due to repeated insertion of single steel drawn wire. In addition, the full hole penetration can ensure the relative forward direction and relaxation between the steel drawn wires. Furthermore, since the pipe is prevented from being clogged by the collision of the steel bundle with the hole wall in the pipe, smooth insertion of the steel bundle can be ensured. At the end of the steel bundle of the inserted whole bundle, a steel wire net is knitted into a conical shape, and a conical protective cover is formed between the pulling rope 9 and the steel bundle, thereby separating the steel bundle and the hole wall. Prevent contact (that is, ensure that the tension rope is always in the center of the cross section in the pipeline and that there is an isolation layer between the pipe wall and the steel bundle), so that the steel bundle of the whole hole can be smoothly inserted into the hole. can be guaranteed. Next, by preparing a hole in the top plate 1 of the box beam, tensioning of the steel drawing wire and mortar pressing work are performed, so the operation space inside the box is narrow, and it is difficult to position and tension the oil cap. Solve a problem. Finally, by adding a groove to the front end of the tooth block as well as preparing a hole in the upper plate. To solve the problem of module strength of the anchor end of tooth block and difficult operation of concrete pouring. By applying construction methods such as "pull + prepare + stretch", pre-holes are installed in each part of the box beam, grooves are added, etc., and ultra-long prestressed steel bundles are inserted into the box beam, tension, mortar press,
To solve the problem that anchor embedding is difficult to operate due to space restrictions. In the construction process, the degree of difficulty in construction will be greatly reduced, and the construction cost will be reduced and the construction period will be shortened.

上記本発明の技術案によれば、「引く+備える+張る」といった施工方法を用いて、上面
超長予応力鋼製束の施工際における空間制限、手間がかかること、鋼絞線による穴壁の容
易破壊、モルタルプレスの不飽満、アンカー埋込み施工困難という課題を解決している。
According to the above technical solution of the present invention, using the construction method of "pull + prepare + stretch", there are space restrictions and labor in constructing the upper surface ultra-long prestress steel bundle, and the hole wall by the steel drawn wire It solves the problems of easy destruction of the mortar, lack of mortar press, and difficulty of embedding anchors.

また、以下の技術的効果を有する。
1 人工に代えて機械手段を採用できる。挿通機により動力を提供して鋼絞線の貫設を実
現し、効率を向上する。
2 「バラバラ→全体」にする。引張ロープを案内とすることにより、予応力束の全体整
穴貫設を実現し、1本鋼絞線による繰り返し挿通施工であれば周期が長いといった問題を
解決する。さらに、全体穴貫設により鋼絞線間の相対順方向と緩和度を保証できる。
3 ビーム面においてリービング穴道を予備する。鋼絞線と挿通機はいずれもビーム面に
配置される。挿通過程全体は基本的にビーム面で行われる。このため、有効的に下方空間
の制限による悪影響を回避できる。
4 鋼線ズレ編製により予応力接続端を錐状端にすることができる。また、前端に保護カ
バーを備えるので、鋼製束と穴壁を効果的に隔離させる
5 アンカー定着端にアンカーを深埋めるという設計により、「移変環」を支持とする。
穴口隙間を利用してアンカー具のズレを調整することによりアンカー受板への応力集中を
防止する。深埋めアンカー凹溝設計によりアンカー埋込みの施工操作を簡単化させ、施工
質量を保証できる。
6 本施工技術の応用はプレストレストが室内空間の限られた状況の下で高効率、迅速、
高品質のプレストレスト施工の完成を実現し、しかもこの技術は横展開することができ、
鋼混合梁などの下方の施工条件のないプレストレスト構造施工に応用され、広範な応用場
面を持っている。
Moreover, it has the following technical effects.
1 Mechanical means may be employed in place of manual labor. The insertion machine provides power to realize the penetration of the steel drawing wire and improve the efficiency.
2 Make it "discrete → whole". By using a tension rope as a guide, it is possible to align the prestress bundle through the whole hole, and solve the problem that the cycle is long if repeated insertion work is performed using a single steel drawn wire. In addition, the full hole penetration can ensure the relative forward direction and relaxation between the steel drawn wires.
3 Prepare a reeving hole path in the beam plane. Both the steel draw wire and the threader are placed in the plane of the beam. The entire threading process basically takes place in the plane of the beam. Therefore, it is possible to effectively avoid adverse effects due to the limitation of the lower space.
4 The prestress connection end can be made into a conical end by steel wire slip knitting. It also has a protective cover on the front end, which effectively isolates the steel bundle and the hole wall.
To prevent stress concentration on an anchor receiving plate by adjusting the displacement of an anchor tool using a hole opening. The deep-buried anchor groove design simplifies the operation of embedding the anchor and guarantees the construction weight.
6. The application of this construction technology is highly efficient, rapid, and prestressed under the limited indoor space.
We have achieved the completion of high-quality prestressed construction, and this technology can be expanded horizontally.
It is applied to the construction of prestressed structures without construction conditions below, such as steel mixed beams, and has a wide range of applications.

以上述べたのは本発明の好ましい実施例にすぎず、本発明を制限する必要のではなく、本
発明の精神と原則の内で、行ったいかなる修正、等価置換、改善なども、本発明の保護範
囲に含まれるべきである。
The above are only preferred embodiments of the present invention, and should not be construed as limiting the present invention. should be included in the scope of protection.

Claims (10)

超長予応力鋼製束の施工方法であって、
予応力管道18のポジショニングと組立するステップと、
上面予応力鋼製束を挿通させるステップと、
上面予応力緊張させるステップと、
上面予応力束管道18のモルタルプレスするステップと、
上面予応力アンカー埋込みするステップと、を含む、
ことを特徴とする超長予応力鋼製束の施工方法。
A method for constructing an ultra-long prestressed steel bundle, comprising:
positioning and assembling the prestress conduit 18;
inserting a top prestressed steel bundle;
tensioning the upper surface prestress;
mortar pressing the top prestress flux duct 18;
embedding a top surface prestress anchor;
A method for constructing an ultra-long prestressed steel bundle, characterized by:
前記予応力管道18のポジショニングと組立するステップは、
プラスチック材波紋管による縦方向予応力穴の形成をするステップと、
管道組立と鋼筋拘束とモジュール組立の交互操作するステップと、
井字状のポジショニング鋼筋と鋼筋骨により確実的に半田づけするステップと、
波紋管における断裂の検査により、波紋管のモルタルリークによる管道の塞ぎを防止する
ステップと、
套管の引き押しにより管内のコンクリート凝固を防止するステップと、を含む、
ことを特徴とする請求項1に記載の超長予応力鋼製束の施工方法。
The steps of positioning and assembling the prestress conduit 18 include:
forming a longitudinal prestress hole with a corrugated tube of plastic material;
alternately operating pipe assembly, steel bar restraint, and module assembly;
a step of reliably soldering with a well-shaped positioning steel bar and a steel bar;
inspecting for ruptures in the ripple tube to prevent blockage of the conduit due to mortar leaks in the ripple tube;
preventing concrete solidification within the tube by pulling on the bushing;
The construction method for ultra-long prestressed steel bundles according to claim 1, characterized in that:
前記上面予応力鋼製束を挿通させるステップは、
施工穴の位置に対応する延長線上において斜長予備穴を予備することにより引張ロープ9
を組するステップと、
予応力鋼製束2の全体穴貫設するステップと、を含む、
ことを特徴とする請求項1に記載の超長予応力鋼製束の施工方法。
The step of inserting the top surface prestressed steel bundle includes:
By preparing an oblique preliminary hole on the extension line corresponding to the position of the construction hole, the tension rope 9
a step of combining
drilling through the entire hole of the prestressed steel bundle 2;
The construction method for ultra-long prestressed steel bundles according to claim 1, characterized in that:
引張ロープ9は1本の鋼絞線を用い、そして機械的に挿通機により貫設する、
ことを特徴とする請求項3に記載の超長予応力鋼製束の施工方法。
The pulling rope 9 uses a single steel drawn wire and is mechanically penetrated by an inserter,
The construction method for ultra-long prestressed steel bundles according to claim 3, characterized in that:
前記上面予応力鋼製束を挿通させるステップは、
鋼絞線のズレ鋼線編製及び鋼製束の端部処理するステップと、
深埋めアンカー技術により、アンカー受板11は構成外廓辺線からの0.2m距離の構成
内部の凹溝に埋め込むと共に、緊張際にアンカー受板11と緊張オイルキャップ17の間
に延長筒を設置して移変させるするステップと、
ティースブロックの前端でリービング穴道を予備し、人工により機械を補助する形で全体
束の鋼絞線の引くことを行うと共に、鋼製束を他端まで張引すると、十分な工作長度を残
って、ホイールにより鋼絞線を切断するするステップと、を含む、
ことを特徴とする請求項3に記載の超長予応力鋼製束の施工方法。
The step of inserting the top surface prestressed steel bundle includes:
a step of braiding a steel wire with a deviation of the steel drawn wire and processing the end of the steel bundle;
With the deep-buried anchor technology, the anchor receiving plate 11 is embedded in the groove inside the structure at a distance of 0.2 m from the outer circumference of the structure, and an extension cylinder is inserted between the anchor receiving plate 11 and the tensioning oil cap 17 during tensioning. placing and translating;
A reeving hole path is prepared at the front end of the tooth block, and the steel drawing wire of the entire bundle is drawn manually by assisting the machine. , cutting the steel drawn wire with the wheel;
The construction method for ultra-long prestressed steel bundles according to claim 3, characterized in that:
前記鋼絞線のズレ鋼線編製及び鋼製束の端部処理するステップは、
鋼絞線からズレ編製によって前端で錐状体を形成するするステップと、
細鋼線により張引ロープの一端と全体束挿通がすべき鋼絞線とを円錐状に編み合わせるこ
とにより円錐状を形成するするステップと、
挿通してから未編製部位における鋼絞線をホイールにより切除するするステップと、を含
む、
ことを特徴とする請求項5に記載の超長予応力鋼製束の施工方法。
The step of weaving the steel drawn wire with deviation and treating the end of the steel bundle,
forming a cone at the front end by offset knitting from a steel wire;
forming a conical shape by conically weaving one end of the tension rope with a fine steel wire and a steel draw wire through which the entire bundle should be inserted;
cutting the steel draw wire in the unwoven portion after threading with the wheel;
The construction method for ultra-long prestressed steel bundles according to claim 5, characterized in that:
前記上面予応力緊張させるステップは、
ビーム面により2つのオイルキャップ工作予備小穴を予備し、鋼線ケーブルを貫通させて
、ビーム上面に吊上げ手段を逆さ掛けとするチェーンホイストを設置するステップと、
ビーム上面のチェーンホイストによりビーム内の緊張オイルキャップ17を吊り上げ、ビ
ーム内に操作台を載設し、または検査トラックを設置するステップと、
止め板、アンカー具、挟み片移変環を取り付けること、及び緊張工作を完成するステップ
と、を含む、
ことを特徴とする請求項1に記載の超長予応力鋼製束の施工方法。
The top surface prestressing step includes:
Preparing two oil cap spare eyelets on the beam face, passing steel wire cables through it, and installing a chain hoist with a lifting means upside down on the beam face;
lifting the taut oil cap 17 in the beam by means of a chain hoist on top of the beam and mounting a control platform or an inspection truck in the beam;
attaching a stop plate, an anchor, a clip transition ring, and completing the tensioning;
The construction method for ultra-long prestressed steel bundles according to claim 1, characterized in that:
前記上面予応力束管道18のモルタルプレスするステップは、
緊張施工してから48h以内にモルタルプレスを行うステップと、
露出した鋼絞線を切除して、アンカー埋込みを行うステップと、
アンカー受板11上のモルタル注入穴を整理するステップと、を含む、
ことを特徴とする請求項1に記載の超長予応力鋼製束の施工方法。
The step of mortar pressing the upper surface prestress flux conduit 18 includes:
a step of performing mortar pressing within 48 hours after tension construction;
cutting the exposed steel wire and embedding the anchor;
arranging the mortar injection holes on the anchor receiving plate 11;
The construction method for ultra-long prestressed steel bundles according to claim 1, characterized in that:
前記モルタルプレスの方法は、
真空抽出し、真空ポンプを起動して、システム負圧を0.07~0.1Mpaにさせるこ
と、
穴道の真空度が一定になると、ポンプを1min停止させること、
圧力低降が0.02Mpaより小さいと、穴道が真空になると判定し、圧力低降が0.0
2Mpaより大きいと、穴道が未完全密閉であり、モルタル注入前で検査および修正が必
要であると判定すること、を含む、
ことを特徴とする請求項8に記載の超長予応力鋼製束の施工方法。
The mortar press method is
vacuum extraction, starting the vacuum pump to make the system negative pressure 0.07~0.1Mpa;
Stop the pump for 1 minute when the degree of vacuum in the tunnel becomes constant,
If the pressure drop is less than 0.02Mpa, it is determined that the hole is vacuum, and the pressure drop is 0.0
Determining that if greater than 2 MPa, the hole passage is not fully sealed and requires inspection and correction prior to mortar injection;
The construction method for ultra-long prestressed steel bundles according to claim 8, characterized in that:
前記上面予応力アンカー埋込みするステップは、
鉄線により緊張端のアンカー埋込みモジュール22を上面から直接にビーム上面に固定し
て、操作空間の狭小問題を減少させるさせるステップと、
深埋めアンカー口の上面に予備穴15を設置するステップと、
アンカー埋込みコンクリートをビーム上面から注入して、振着するステップと、を含む、
ことを特徴とする請求項1に記載の超長予応力鋼製束の施工方法。
The step of embedding the top surface prestress anchor includes:
fixing the taut end anchor embedding module 22 directly from the top surface to the top surface of the beam by iron wire to reduce the problem of narrow operating space;
installing a preliminary hole 15 in the upper surface of the deep-buried anchor mouth;
pouring and shaking anchor-embedded concrete from the upper surface of the beam;
The construction method for ultra-long prestressed steel bundles according to claim 1, characterized in that:
JP2022094762A 2021-09-02 2022-06-10 Construction method for ultra-long pre-stressed steel bundle Pending JP2023036518A (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202111024863.9A CN113585091A (en) 2021-09-02 2021-09-02 Construction method of super-long prestressed steel beam
CN202111024863.9 2021-09-02

Publications (1)

Publication Number Publication Date
JP2023036518A true JP2023036518A (en) 2023-03-14

Family

ID=78241103

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2022094762A Pending JP2023036518A (en) 2021-09-02 2022-06-10 Construction method for ultra-long pre-stressed steel bundle

Country Status (3)

Country Link
JP (1) JP2023036518A (en)
CN (1) CN113585091A (en)
WO (1) WO2023029647A1 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113585091A (en) * 2021-09-02 2021-11-02 中铁北京工程局集团第二工程有限公司 Construction method of super-long prestressed steel beam
CN114438886A (en) * 2021-12-28 2022-05-06 中铁二十局集团有限公司 Continuous beam tensioning method
CN115323941B (en) * 2022-05-18 2024-06-14 山东交通学院 Assembly and method for reinforcing a continuous box girder bridge
CN116695566B (en) * 2023-05-12 2024-04-09 中建八局第三建设有限公司 Tensioning construction process of prestressed concrete beam

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005220593A (en) * 2004-02-05 2005-08-18 Kajima Corp Pc steel anchoring method and prestressed concrete bridge
JP2011032843A (en) * 2009-08-06 2011-02-17 Zenitaka Corp Cold weather curing construction system and construction method for pc grout material
CN208167553U (en) * 2018-05-02 2018-11-30 江苏省交通工程集团有限公司 Steel strand tension diverter

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5405889B2 (en) * 2009-04-30 2014-02-05 三井住友建設株式会社 Tension material tensioning method
KR100926969B1 (en) * 2009-07-10 2009-11-17 노윤근 Prestressed reinforced concrete girder and it's construction method
CN202416879U (en) * 2011-12-27 2012-09-05 广东省长大公路工程有限公司 Extending cylinder device applicable to prestressed buried anchor
CN102691268A (en) * 2012-06-12 2012-09-26 宁波二十冶建设有限公司 Stretching construction process of super-long prestressed tendon
CN103603273A (en) * 2013-11-04 2014-02-26 沈阳市政集团有限公司 Method for grouting construction of prestressed pipe
CN105839544A (en) * 2016-05-10 2016-08-10 云南建工集团有限公司 Hogging moment stretching-drawing trolley capable of working aloft in narrow space
CN207892252U (en) * 2018-01-18 2018-09-21 中铁四局集团第二工程有限公司 A kind of multi beam prestress wire lashing banding draft gear
CN108858740B (en) * 2018-06-28 2021-05-07 广西长长路桥建设有限公司 Construction method of hogging moment tensioning groove of precast beam
CN110453603A (en) * 2019-07-16 2019-11-15 中冶交通建设集团有限公司 Overpass crossbeam construction method
CN213173355U (en) * 2020-06-29 2021-05-11 中铁四局集团第五工程有限公司 T roof beam bridge floor hogging moment steel strand whole wears to restraint frock subassembly
CN113585091A (en) * 2021-09-02 2021-11-02 中铁北京工程局集团第二工程有限公司 Construction method of super-long prestressed steel beam

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005220593A (en) * 2004-02-05 2005-08-18 Kajima Corp Pc steel anchoring method and prestressed concrete bridge
JP2011032843A (en) * 2009-08-06 2011-02-17 Zenitaka Corp Cold weather curing construction system and construction method for pc grout material
CN208167553U (en) * 2018-05-02 2018-11-30 江苏省交通工程集团有限公司 Steel strand tension diverter

Also Published As

Publication number Publication date
CN113585091A (en) 2021-11-02
WO2023029647A1 (en) 2023-03-09

Similar Documents

Publication Publication Date Title
JP2023036518A (en) Construction method for ultra-long pre-stressed steel bundle
CN112942884B (en) Reinforcement construction process for enlarging cross section of column steel-clad component
CN101634144A (en) Anti-slide pile with vertical prestressed anchor cables adopting secondary grouting
CN109653531A (en) A kind of external prestressing steel strand connector and mating tensioning equipment
CN108708368A (en) Multistage anchoring prestress muscle continuous underground wall structure and its construction method
CN109869166A (en) A kind of class rectangle shield tunnel tunnel segment structure and its construction method
CN218668108U (en) Hogging moment prestressing force steel pipe truss superimposed sheet
CN104196248B (en) Steel pipe column vertical locating device and construction method thereof is inserted after contrary sequence method
CN201095831Y (en) Beam-splitting U shaped prestressing force anchorage cable
CN212296494U (en) Tunnel pipeline cable suspension device
CN111306514B (en) High-pole lamp rope distributor installation method
CN109763848B (en) Construction method of early high-strength prestressed anchor cable for tunnel and underground engineering
CN207092389U (en) A kind of steel strand connector
CN104005340B (en) Continuous beam elongated prestressing tendon lashing construction method
CN209816831U (en) Tool for installing grouting perforated pipe on underground diaphragm wall joint in pipe drawing construction method
CN206503137U (en) A kind of concrete-pile
CN206052734U (en) The component of supporting pile anchor rod secondary grouting
CN111734417A (en) Connecting structure of glass fiber reinforcement and steel bar and glass fiber reinforcement construction process
CN104294965B (en) Shear wall and construction method thereof
CN221297406U (en) Wire rope grafting machine
CN209976550U (en) Quasi-rectangular shield tunnel segment structure with temporary support
CN211848951U (en) Accurate aligning and mounting device for box bridge prestressed tendons
CN1102091C (en) Deep motor-pumped well pipe of steel bar reinforced concrete
CN218204358U (en) Prefabricated square quick concatenation formula pressure dispersion type stock
CN217580134U (en) Prestressed anchorage cable protection secondary slip casting free end sleeve structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20220611

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220628

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230508

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20231129