JP2023026012A - Support structure for temporary pier and renewal method of bridge upper structure - Google Patents

Support structure for temporary pier and renewal method of bridge upper structure Download PDF

Info

Publication number
JP2023026012A
JP2023026012A JP2021131575A JP2021131575A JP2023026012A JP 2023026012 A JP2023026012 A JP 2023026012A JP 2021131575 A JP2021131575 A JP 2021131575A JP 2021131575 A JP2021131575 A JP 2021131575A JP 2023026012 A JP2023026012 A JP 2023026012A
Authority
JP
Japan
Prior art keywords
bridge
temporary
pier
existing
piers
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2021131575A
Other languages
Japanese (ja)
Other versions
JP7108108B1 (en
Inventor
通太郎 木原
Michitaro Kihara
俊也 井隼
Toshiya Ihaya
和也 崎谷
Kazuya Sakitani
明夫 正司
Akio Shoji
洋介 浦川
Yosuke Urakawa
亮 山下
Akira Yamashita
定明 中村
Sadaaki Nakamura
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
West Nippon Expressway Co Ltd
Oriental Shiraishi Corp
IHI Construction Service Co Ltd
Original Assignee
West Nippon Expressway Co Ltd
Oriental Shiraishi Corp
IHI Construction Service Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by West Nippon Expressway Co Ltd, Oriental Shiraishi Corp, IHI Construction Service Co Ltd filed Critical West Nippon Expressway Co Ltd
Priority to JP2021131575A priority Critical patent/JP7108108B1/en
Application granted granted Critical
Publication of JP7108108B1 publication Critical patent/JP7108108B1/en
Publication of JP2023026012A publication Critical patent/JP2023026012A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

To provide a support structure for a temporary pier which satisfies earthquake-resistant performance against a level 2 earthquake motion and can be installed at a low cost with a small amount of steel used without increasing the size, and to provide a method for renewing a bridge upper structure using the support structure.SOLUTION: In a support structure of a temporary pier 1 constructed between two existing piers P2, P3 erected separately and obtained by combining a plurality of steel materials, a plurality of cross beams 4 and a plurality of girder materials 5 installed on the plurality of cross beams 4 are provided, and the cross beams 4 are bridged and joined between a pair of frame bodies 3 respectively surrounding peripheries of the two existing piers P2, P3.SELECTED DRAWING: Figure 1

Description

本発明は、仮設橋脚の支持構造及び橋梁上部構造の更新方法に関し、詳しくは、レベル2地震動に対する耐震性能を有する仮設橋脚の支持構造及びそれを用いた橋梁上部構造の更新方法に関する。 TECHNICAL FIELD The present invention relates to a temporary pier support structure and bridge superstructure renewal method, and more particularly to a temporary bridge pier support structure having seismic performance against level 2 seismic motion and a bridge superstructure renewal method using the same.

高速道路などの橋梁の橋桁や床版などの上部構造(上部工)は、経年劣化に伴い一定期間経過後に架け替えて更新する必要がある。高速道路や鉄道などの橋梁の上部構造を更新する場合、高速道路等として供用しつつ更新するため、片側車線ずつ更新作業を行って、更新工事で使用できない車線の代わりに仮設構造物である仮設橋脚を構築し、その仮設橋脚の上に床版を設置して車両等が通行させて使用したいとの要請がある。このように暫定共用時の仮設橋脚は、しばしば発生する地震動(以下、レベル1地震動という。)だけでなく、橋の設計共用期間中に発生することは極めて稀であるが一旦生じると橋に及ぼす影響が甚大であると考えられる地震動(以下、レベル2地震動という。)に対する耐震性能を要求される場合がある(道路橋示方書(V耐震設計編)・同解説参照)。 Superstructures (superstructures) such as bridge girders and floor slabs of bridges such as expressways need to be replaced and renewed after a certain period of time due to deterioration over time. When renewing superstructures of bridges such as expressways and railways, in order to renew them while they are still in service as expressways, etc., the renewal work is carried out one lane at a time, and a temporary structure, which is a temporary structure, is used instead of the lane that cannot be used during the renewal work. There is a request to build a bridge pier and install a floor slab on the temporary pier so that vehicles can pass through it. In this way, the temporary piers during temporary use are not only affected by seismic motions that frequently occur (hereafter referred to as level 1 seismic motions), but they are also extremely rare during the design period of the bridge, but once they occur, they can affect the bridge. In some cases, seismic performance against seismic motions that are considered to have a tremendous impact (hereafter referred to as level 2 seismic motions) is required (see Specifications for Highway Bridges (Seismic Design Version V) and its commentary).

このような仮設橋脚は、一般的に、養生期間がなく現地作業を短期間で行えることや汎用性の問題から、鋼製部材で構成されることが多い。しかし、鋼製部材は、塑性変形が見込めないことより、レベル2地震動の応答値を弾性範囲内に収めて設計する必要がある。その結果、仮設橋脚の要求性能として、レベル2地震動に対する耐震性能があった場合、仮設部材の大型化が生じるという問題がある。 Such temporary bridge piers are generally made of steel members because there is no curing period and on-site work can be done in a short period of time and because of the problem of versatility. However, since steel members cannot be expected to undergo plastic deformation, it is necessary to design them so that the level 2 seismic motion response value is within the elastic range. As a result, if there is seismic performance against level 2 seismic motion as a required performance of the temporary pier, there is a problem that the size of the temporary members will increase.

例えば、特許文献1には、本願出願人が提案した、橋脚の柱頭部に仮支柱を設置し、PC鋼材で該柱頭部に固定すると共に、仮支柱を左右に張り出す橋体ブロックと前記仮支柱の頂部に渡って山形に配置し、型枠を組む仮斜材の頂部の周りに付着を確保する大きさのコンクリートを打設する橋梁の張出し架設工法及びそれに用いる仮支柱が開示されている(特許文献1の特許請求の範囲の請求項3、明細書の段落[0020]~[0024]、図面の図1~図4等参照)。 For example, in Patent Document 1, a temporary support is installed on the column head of a bridge pier proposed by the applicant of the present application, and fixed to the column head with a PC steel material. Disclosed is a method of overhang erection of a bridge in which concrete is placed in a mountain shape over the top of the pillars and concrete of a size that secures adhesion is placed around the top of the temporary diagonal members to form the formwork, and the temporary pillars used therefor are disclosed. (See claim 3 of the scope of claims of Patent Document 1, paragraphs [0020] to [0024] of the specification, FIGS. 1 to 4 of the drawings, etc.).

しかし、特許文献1に記載の仮支柱は、仮設橋脚の支持構造ではない上、レベル2地震動に対する耐震性能については、特に考慮されておらず、前記問題点を解決できるものではなかった。 However, the temporary pillars described in Patent Document 1 are not supporting structures for temporary bridge piers, and they do not particularly consider seismic performance against level 2 seismic motion, so they could not solve the above problems.

特開2006-52573号公報JP-A-2006-52573

そこで、本発明は、前述した問題に鑑みて案出されたものであり、その目的とするところは、レベル2地震動に対する耐震性能を満たし、大型化せずに鋼材使用量が少なく安価に設置可能な仮設橋脚の支持構造及びそれを用いた橋梁上部構造の更新方法を提供することにある。 Therefore, the present invention has been devised in view of the above-mentioned problems, and the purpose thereof is to satisfy the seismic performance against level 2 seismic motion, to be able to install at low cost with less steel material usage without increasing size. To provide a support structure for a temporary bridge pier and a method for updating a bridge superstructure using the same.

請求項1に係る仮設橋脚の支持構造は、離間して立設された2つの既設橋脚の間に構築される複数の鋼材が組み合わされた仮設橋脚の支持構造であって、複数の横梁と、これらの複数の横梁上に設置された複数の桁材と、を備え、前記横梁は、前記2つの既設橋脚の周囲をそれぞれ取り囲む一対の枠体間に架け渡されて接合されていることを特徴とする。 A support structure for a temporary bridge pier according to claim 1 is a support structure for a temporary bridge pier constructed between two existing bridge piers that are spaced apart and constructed by combining a plurality of steel members, comprising a plurality of transverse beams, and a plurality of girders installed on the plurality of cross beams, wherein the cross beams are bridged and joined between a pair of frames surrounding the two existing bridge piers. and

請求項2に係る仮設橋脚の支持構造は、請求項1に係る仮設橋脚の支持構造において、前記一対の枠体は、それぞれ前記既設橋脚に沿って立設された複数の仮設支柱で下方から支持されていることを特徴とする。 A support structure for a temporary pier according to claim 2 is the support structure for a temporary pier according to claim 1, wherein the pair of frames are supported from below by a plurality of temporary pillars respectively erected along the existing piers. It is characterized by being

請求項3に係る仮設橋脚の支持構造は、請求項1又は2に係る仮設橋脚の支持構造において、前記横梁は、地震動による前記2つの既設橋脚の応答スペクトルが同期するように前記一対の枠体と剛接合されていることを特徴とする。 A support structure for a temporary bridge pier according to claim 3 is the support structure for a temporary bridge pier according to claim 1 or 2, wherein the horizontal beams are arranged in the pair of frames so that the response spectra of the two existing piers due to earthquake motion are synchronized. It is characterized by being rigidly joined with.

請求項4に係る仮設橋脚の支持構造は、請求項1ないし3のいずれかに記載の仮設橋脚の支持構造において、離間して立設された既設橋脚が複数あり、それぞれの既設橋脚を取り囲む枠体がそれぞれ別体となってそれらの枠体が横梁で連結されていることを特徴とする。 A support structure for a temporary pier according to claim 4 is the support structure for a temporary pier according to any one of claims 1 to 3, wherein a plurality of existing piers are erected with a space therebetween, and a frame surrounding each of the existing piers is provided. It is characterized in that the bodies are separated from each other and their frame bodies are connected by horizontal beams.

請求項5に係る橋梁上部構造の更新方法は、既設橋梁の上部構造を取り替えて更新する橋梁上部構造の更新方法であって、請求項1ないし4のいずれかに記載の仮設橋脚の支持構造を備えた仮設橋脚を、離間して立設された2つの既設橋脚間に構築した後、前記仮設橋脚上に架け替える新設の上部構造を載置することを特徴とする。 A bridge superstructure renewal method according to claim 5 is a bridge superstructure renewal method for replacing and renewing the superstructure of an existing bridge, wherein the temporary pier support structure according to any one of claims 1 to 4 is provided. After constructing the provided temporary bridge pier between two existing bridge piers which are erected apart from each other, a new superstructure to be replaced is placed on the temporary bridge pier.

請求項6に係る橋梁上部構造の更新方法は、請求項5に係る橋梁上部構造の更新方法において、前記新設の上部構造は、プレキャスト製のPCa横梁を備え、上下線のそれぞれのPCa横梁同士を鋼殻を介して連結して前記仮設橋脚の上に載置し、前記2つの既設橋脚間に一時的に車線を設けて共用することを特徴とする。 A method for updating a bridge superstructure according to claim 6 is the method for updating a bridge superstructure according to claim 5, wherein the new superstructure includes precast PCa cross beams, and the PCa cross beams of the upper and lower lines are connected to each other. It is characterized in that it is connected via a steel shell and placed on the temporary pier, and a lane is temporarily provided between the two existing piers for common use.

請求項1~4に係る発明によれば、横梁が2つの既設橋脚の周囲をそれぞれ取り囲む一対の枠体間に架け渡されて接合されているので、既設橋脚を用いてレベル2地震動の水平力に対抗することができるため、レベル2地震動に対する耐震性能を有することができる。その上、請求項1~4に係る発明は、既設橋脚を用いて地震動の水平力に対抗するため、仮設橋脚単独でレベル2地震動の応答値を弾性範囲内に収めて設計する場合と比べてはるかに小型の鋼材で構成しても同様の耐震性能を有することが可能となり、仮設橋脚を鋼材使用量が少なく安価に設置することができる。 According to the invention according to claims 1 to 4, since the horizontal beam is bridged and joined between the pair of frames surrounding the two existing piers, the horizontal force of level 2 seismic motion using the existing piers Because it can withstand level 2 seismic motion, it can have seismic performance. In addition, since the invention according to claims 1 to 4 uses the existing piers to counter the horizontal force of the seismic motion, compared to the case where the response value of the level 2 seismic motion is kept within the elastic range with the temporary piers alone. Even if it is composed of much smaller steel materials, it is possible to have the same earthquake resistance performance, and the temporary piers can be installed at low cost with less steel material usage.

特に、請求項2に係る発明によれば、既設橋脚にあと施工アンカーを用いて枠体を止め付ける必要がなくなり、既設橋脚を損傷するおそれを低減することができる。また、仮設支柱は既設橋脚に沿って立設されているので、仮設支柱単体で地震動の水平力に対抗する必要がなく、鋼材のサイズを小さくして安価に設置することができる。 In particular, according to the second aspect of the invention, there is no need to use post-installed anchors to fasten the frame to the existing piers, and the possibility of damaging the existing piers can be reduced. In addition, since the temporary posts are erected along the existing piers, there is no need for the temporary posts alone to withstand the horizontal force of seismic motion, and the size of the steel materials can be reduced and the installation can be done at low cost.

特に、請求項3に係る発明によれば、さらに小型の鋼材で構成しても同様の耐震性能を有することが可能となり、仮設橋脚を鋼材使用量が少なく安価に設置することができる。 In particular, according to the third aspect of the invention, it is possible to have the same seismic performance even if the pier is made of a smaller steel material, and the temporary pier can be installed at a low cost with a small amount of steel material used.

特に、請求項4に係る発明によれば、更新工事の進捗に合わせて仮設橋脚を増設することができ、仮設橋脚の設置期間を短縮することにより、仮設材のリース料を低減できるとともに、橋梁の下部の通行等の障害を極力少なくすることができる。 In particular, according to the invention of claim 4, it is possible to increase the number of temporary piers in accordance with the progress of the renewal work, shorten the installation period of the temporary piers, thereby reducing the lease fee for temporary materials, It is possible to minimize obstacles such as traffic under the road.

請求項5及び請求項6に係る発明によれば、仮設橋脚の横梁が2つの既設橋脚の周囲をそれぞれ取り囲む一対の枠体間に架け渡されて接合されているので、仮設橋脚がレベル2地震動に対する耐震性能を有し、安全に上部構造の更新工事を行うことができる。 According to the inventions of claims 5 and 6, the lateral beams of the temporary piers are bridged and joined between a pair of frames surrounding the two existing piers, respectively, so that the temporary piers can withstand level 2 seismic motion. It has seismic resistance performance against , and it is possible to safely update the superstructure.

特に、請求項6に係る発明によれば、新設するPCa横梁を用いて、既設橋脚間に一時的に上下線のいずれか一方の車線を設けて共用するので、通行規制を少なくして安全に上部構造の更新工事を行うことができる。 In particular, according to the sixth aspect of the invention, the PCa cross beams to be newly installed are used to temporarily provide either one of the up and down lanes between the existing bridge piers for common use. Renewal work of the superstructure can be carried out.

図1は、本発明の第1実施形態に係る仮設橋脚の支持構造を有した仮設橋脚を既設橋梁の橋軸方向に沿って見た正面図である。FIG. 1 is a front view of a temporary pier having a temporary pier support structure according to a first embodiment of the present invention, viewed along the axis direction of an existing bridge. 図2は、同上の仮設橋脚を示す図1の平面図である。FIG. 2 is a plan view of FIG. 1 showing the same temporary bridge pier. 図3は、同上の仮設橋脚の鉛直断面を橋軸直角方向に見た断面図である。FIG. 3 is a cross-sectional view of a vertical cross section of the same temporary bridge pier seen in a direction perpendicular to the bridge axis. 図4は、本発明の第2実施形態に係る仮設橋脚の支持構造を有した仮設橋脚を既設橋梁の橋軸方向に沿って見た正面図である。FIG. 4 is a front view of a temporary pier having a temporary pier support structure according to a second embodiment of the present invention, viewed along the axis direction of the existing bridge. 図5は、本発明の実施形態に係る橋梁上部構造の更新方法の上下線連結横梁架設工程を示す橋梁を橋軸方向に見たパース図である。FIG. 5 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the vertical line connecting horizontal beam erection process of the bridge superstructure renewal method according to the embodiment of the present invention. 図6は、同上の橋梁上部構造の更新方法の上下線連結横梁架設工程を示す橋梁を俯瞰して見た斜視図である。FIG. 6 is a perspective view looking down on the bridge, showing a step of constructing vertical line connecting horizontal beams in the method of updating the bridge superstructure as described above. 図7は、同上の橋梁上部構造の更新方法の外ケーブル解放工程を示す橋梁を橋軸方向に見たパース図である。FIG. 7 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the outer cable release process of the method for updating the bridge superstructure. 図8は、同上の橋梁上部構造の更新方法の外ケーブル解放工程を示す図7の中央2車線部分を拡大した部分拡大斜視図である。FIG. 8 is a partially enlarged perspective view showing an outer cable release step of the above bridge superstructure renewal method, showing an enlarged central two-lane portion of FIG. 図9は、同上の橋梁上部構造の更新方法の鋼殻撤去工程を示す橋梁を橋軸方向に見たパース図である。FIG. 9 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the steel shell removal process of the bridge superstructure renewal method. 図10は、同上の橋梁上部構造の更新方法の鋼殻撤去工程を示す図9の中央2車線部分を拡大した部分拡大パース図である。FIG. 10 is a partially enlarged perspective view showing the steel shell removal step of the above bridge superstructure renewal method, showing an enlarged central two-lane portion of FIG. 図11は、同上の橋梁上部構造の更新方法の下り線横梁緊張工程を示す橋梁を橋軸方向に見たパース図である。FIG. 11 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the down-line horizontal beam tensioning process of the bridge superstructure renewal method described above. 図12は、同上の橋梁上部構造の更新方法の下り線横梁緊張工程を示す下り線側のPCa横梁の外側端部を拡大した拡大斜視図である。FIG. 12 is an enlarged perspective view showing an enlarged outer end portion of the PCa cross beam on the down line side, showing the down line cross beam tensioning process of the above bridge superstructure renewal method. 図13は、同上の橋梁上部構造の更新方法の鋼殻再設置工程を示す橋梁を橋軸方向に見たパース図である。FIG. 13 is a perspective view of the bridge as viewed in the direction of the bridge axis, showing the steel shell re-installation process of the above bridge superstructure renewal method. 図14は、同上の橋梁上部構造の更新方法の鋼殻再設置工程を示す図13の中央2車線部分を拡大した部分拡大パース図である。FIG. 14 is a partially enlarged perspective view showing the steel shell re-installation step of the above bridge superstructure renewal method, showing an enlarged central two-lane portion of FIG. 13 . 図15は、同上の橋梁上部構造の更新方法の外ケーブル再緊張工程を示す橋梁を橋軸方向に見たパース図である。FIG. 15 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the outer cable re-tensioning process of the bridge superstructure renewal method described above. 図16は、同上の橋梁上部構造の更新方法の外ケーブル再緊張工程を示す中央2車線部分を拡大した部分拡大斜視図である。FIG. 16 is a partially enlarged perspective view showing the outer cable re-tensioning process of the above bridge superstructure renewal method, showing an enlarged central two-lane portion. 図17は、同上の橋梁上部構造の更新方法の外ケーブル解放工程を示す橋梁を橋軸方向に見たパース図である。FIG. 17 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the outer cable release process of the above bridge superstructure renewal method. 図18は、同上の橋梁上部構造の更新方法の外ケーブル解放工程を示す中央2車線部分を拡大した部分拡大斜視図である。FIG. 18 is a partially enlarged perspective view showing an outer cable release step of the above bridge superstructure renewal method, showing an enlarged central two-lane portion. 図19は、同上の橋梁上部構造の更新方法の外ケーブル撤去工程を示す橋梁を橋軸方向に見たパース図である。FIG. 19 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the outer cable removal process of the bridge superstructure renewal method. 図20は、同上の橋梁上部構造の更新方法の外ケーブル撤去工程を示す中央2車線部分を拡大した部分拡大斜視図である。FIG. 20 is a partially enlarged perspective view showing an outer cable removal step of the above bridge superstructure renewal method, showing an enlarged central two-lane portion. 図21は、同上の橋梁上部構造の更新方法の鋼殻再撤去工程を示す橋梁を橋軸方向に見たパース図である。FIG. 21 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the steel shell re-removal process of the bridge superstructure renewal method described above. 図22は、同上の橋梁上部構造の更新方法の鋼殻再撤去工程を示す図21の中央2車線部分を拡大した部分拡大パース図である。FIG. 22 is a partially enlarged perspective view showing the steel shell re-removal process of the above bridge superstructure renewal method, showing an enlarged central two-lane portion of FIG. 図23は、同上の橋梁上部構造の更新方法の緊張ケーブル解放工程を示す橋梁を橋軸方向に見たパース図である。FIG. 23 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the tension cable release process of the bridge superstructure renewal method described above. 図24は、同上の橋梁上部構造の更新方法の緊張ケーブル解放工程を示す図23の中央2車線部分を拡大した部分拡大パース図である。FIG. 24 is a partially enlarged perspective view showing the tension cable releasing process of the above bridge superstructure renewal method, showing an enlarged central two-lane portion of FIG. 23 . 図25は、同上の橋梁上部構造の更新方法の緊張ケーブル撤去工程を示す橋梁を橋軸方向に見たパース図である。FIG. 25 is a perspective view of the bridge as viewed in the direction of the bridge axis, showing the tension cable removal process of the above bridge superstructure renewal method. 図26は、同上の橋梁上部構造の更新方法の緊張ケーブル撤去工程を示す図25の中央2車線部分を拡大した部分拡大パース図である。FIG. 26 is a partially enlarged perspective view showing the tension cable removal step of the above bridge superstructure renewal method, showing an enlarged central two-lane portion of FIG. 25 . 図27は、同上の橋梁上部構造の更新方法の上り線横梁緊張工程を示す橋梁を橋軸方向に見たパース図である。FIG. 27 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the up-line horizontal beam tensioning process of the method for renewing the bridge superstructure. 図28は、同上の橋梁上部構造の更新方法の上り線横梁緊張工程を示す上り線側のPCa横梁PBの外側端部を拡大した拡大斜視図である。FIG. 28 is an enlarged perspective view showing an enlarged outer end portion of the PCa cross beam PB on the inbound line side, showing the inbound line cross beam tensioning process of the above bridge superstructure renewal method. 図29は、同上の橋梁上部構造の更新方法の完了状態を示す橋梁を橋軸方向に見たパース図である。FIG. 29 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the completed state of the method for updating the bridge superstructure.

以下、本発明に係る仮設橋脚の支持構造及び橋梁上部構造の更新方法の一実施形態について、図面を参照しながら詳細に説明する。 An embodiment of a method for updating a support structure for a temporary bridge pier and a bridge superstructure according to the present invention will be described below in detail with reference to the drawings.

<仮設橋脚の支持構造>
[第1実施形態]
図1~図3を用いて、本発明の第1実施形態に係る仮設橋脚の支持構造について説明する。既設橋梁B1の上部構造B2を更新する際に、中央分離帯付近の上下1車線ずつを撤去して2つの既設橋脚P2,P3の間に構築される仮設橋脚1を例示して説明する。図1は、本発明の第1実施形態に係る仮設橋脚の支持構造を有した仮設橋脚1を既設橋梁の橋軸方向に沿って見た正面図である。また、図2は、本実施形態に係る仮設橋脚1を示す平面図であり、図3は、本実施形態に係る仮設橋脚1の鉛直断面を橋軸直角方向に見た断面図である。
<Support structure for temporary bridge piers>
[First embodiment]
A support structure for a temporary bridge pier according to a first embodiment of the present invention will be described with reference to FIGS. 1 to 3. FIG. A temporary pier 1 constructed between two existing piers P2 and P3 by removing one upper and lower lane near the median strip when updating the superstructure B2 of the existing bridge B1 will be described. FIG. 1 is a front view of a temporary pier 1 having a support structure for a temporary pier according to a first embodiment of the present invention, viewed along the axial direction of the existing bridge. 2 is a plan view showing the temporary bridge pier 1 according to this embodiment, and FIG. 3 is a cross-sectional view of the vertical cross section of the temporary bridge pier 1 according to this embodiment as seen in the direction perpendicular to the bridge axis.

先ず、簡単に既設橋梁B1について説明する。図1に示すように、既設橋梁B1は、上下各3車線ずつのRC中空床版桁の橋梁である。この既設橋梁B1は、鉛直断面において、左右一対の既設の基礎F1,F2と、これらの基礎F1,F2上に立設された4つの既設橋脚P1~P4と、RC中空床版桁からなる上部構造B2など、から構成されている。また、上部構造B2には、壁高欄K1が設けられているとともに、上部構造B2の撤去した撤去部分B2#に沿って置くだけで壁高欄として機能する載置型の仮設壁高欄K2が設置されている。 First, the existing bridge B1 will be briefly described. As shown in FIG. 1, the existing bridge B1 is a bridge of RC hollow slab girders with three lanes each for upper and lower lanes. This existing bridge B1 has, in a vertical cross section, a pair of left and right existing foundations F1 and F2, four existing bridge piers P1 to P4 erected on these foundations F1 and F2, and an upper part made up of an RC hollow floor slab girder. Structure B2 and so on. In addition, the upper structure B2 is provided with a wall balustrade K1, and a mounting-type temporary wall balustrade K2 that functions as a wall balustrade simply by being placed along the removed portion B2# of the superstructure B2 is installed. there is

図1~図3に示すように、第1実施形態に係る仮設橋脚1は、複数の鋼材が組み合わされた仮設構造物である。この仮設橋脚1は、複数の仮設支柱2と、これらの複数の仮設支柱2の上に載置された左右一対の矩形の枠体3と、これら枠体3,3間に架け渡された複数の横梁4と、これらの複数の横梁4上に設置された複数の桁材5など、から構成されている。 As shown in FIGS. 1 to 3, the temporary bridge pier 1 according to the first embodiment is a temporary structure in which a plurality of steel materials are combined. This temporary bridge pier 1 comprises a plurality of temporary supports 2, a pair of right and left rectangular frame bodies 3 mounted on the plurality of temporary support supports 2, and a plurality of frame bodies 3 and 3 bridged between the frame bodies 3 and 3. and a plurality of girders 5 installed on the plurality of horizontal beams 4, and the like.

(仮設支柱)
本実施形態に係る仮設支柱2は、H形鋼からなる支柱であり、下端が基礎F1,F2にあと施工アンカーで止め付けられた上、根巻コンクリート2aが打設されて基礎F1,F2に固定されている。また、仮設支柱2と枠体3との間には、枠体3の高さ調整が可能なようにキリンジャッキ2bが介装されている。
(temporary support)
The temporary support 2 according to the present embodiment is a support made of H-shaped steel, and the lower end is fixed to the foundations F1 and F2 with post-construction anchors, and the neck wrap concrete 2a is placed to the foundations F1 and F2. Fixed. A giraffe jack 2b is interposed between the temporary post 2 and the frame 3 so that the height of the frame 3 can be adjusted.

この仮設支柱2は、その側面が既設橋脚P2,P3に沿って取り付けられ、枠体3を下方から支持する機能を有している。このように、仮設支柱2が、既設橋脚P2,P3に沿って取り付けられているので、あと施工アンカーを用いて枠体を既設橋脚P2,P3に止め付ける必要がなくなり、既設橋脚を損傷するおそれを低減することができる。また、仮設支柱2は、既設橋脚P2,P3に沿って立設されているので、仮設支柱2単体で地震動の水平力に対抗する必要がなく、鋼材のサイズを小さくして安価に設置することができる。 The temporary supports 2 have side surfaces attached along the existing bridge piers P2 and P3 and have the function of supporting the frame 3 from below. In this way, since the temporary supports 2 are attached along the existing piers P2 and P3, there is no need to use post-construction anchors to fasten the frame to the existing piers P2 and P3, which may damage the existing piers. can be reduced. In addition, since the temporary support 2 is erected along the existing bridge piers P2 and P3, it is not necessary for the temporary support 2 alone to resist the horizontal force of the seismic motion, and the size of the steel material can be reduced and installed at a low cost. can be done.

(枠体)
本実施形態に係る枠体3は、H形鋼が既設橋脚P2,P3の周囲をそれぞれ取り囲むように溶接等で接合されて組み合わされた矩形状の枠体であり、既設橋脚P2,P3の水平断面の外周形状に、枠体3の内周面が当接するように構成されている。勿論、枠体3は、H形鋼に限られず、溝形鋼や角形鋼管など他の鋼材から構成されていても構わない。また、枠体3は、溶接で接合されているものに限られず、ボルト接合やリベット接合など、機械的に接合されていても構わない。
(frame body)
The frame body 3 according to the present embodiment is a rectangular frame body in which H-shaped steels are joined by welding or the like so as to surround the existing piers P2 and P3, respectively, and combined. It is configured such that the inner peripheral surface of the frame 3 abuts against the outer peripheral shape of the cross section. Of course, the frame 3 is not limited to H-shaped steel, and may be made of other steel such as channel steel or square steel pipe. Moreover, the frame 3 is not limited to being joined by welding, and may be joined mechanically, such as by bolting or riveting.

(横梁)
本実施形態に係る横梁4は、H形鋼からなる鋼材であり、前述の一対の枠体3,3間に架け渡されて接合されている。この横梁4は、地震動による2つの既設橋脚P2,P3の応答スペクトルが同期するように一対の枠体3,3と溶接等で剛接合されている。但し、横梁4は、枠体3,3と剛接合されているものに限られず、ピン接合されていても構わない。枠体3,3間に横梁4で軸力を伝達するように構成するだけで、既設橋脚P2,P3を利用して地震動に対抗することができるからである。
(horizontal beam)
The horizontal beam 4 according to the present embodiment is a steel material made of H-shaped steel, and is bridged and joined between the pair of frames 3, 3 described above. This cross beam 4 is rigidly joined to a pair of frames 3, 3 by welding or the like so that the response spectra of the two existing bridge piers P2, P3 due to seismic motion are synchronized. However, the horizontal beams 4 are not limited to being rigidly joined to the frames 3, 3, and may be joined by pins. This is because the existing bridge piers P2 and P3 can be used to resist the seismic motion simply by transmitting the axial force between the frames 3 and 3 with the horizontal beams 4 .

しかし、仮設橋脚1は、枠体3,3と剛接合されていることにより、地震動に対して既設橋脚と協働させ、仮設橋脚1全体を小型の鋼材で構成してもレベル2地震動に対する耐震性能を有することが可能となり、仮設橋脚を鋼材使用量が少なく安価に設置することができる。 However, since the temporary pier 1 is rigidly connected to the frames 3, 3, it can cooperate with the existing piers against seismic motion, and even if the entire temporary pier 1 is made of small-sized steel materials, it can withstand level 2 seismic motion. It is possible to have performance, and it is possible to install temporary piers at low cost with less steel usage.

(桁材)
桁材5は、H形鋼からなる鋼材であり、前述の横梁4,4上に載置されて溶接等で接合されている。本実施形態に係る桁材5は、スペーサーブロック5aを介して横梁4,4上に載置されて接合されている。勿論、桁材5及びスペーサーブロック5aと横梁4溶接で接合されているものに限られず、ボルト接合やリベット接合など、機械的に接合されていても構わない。また、スペーサーブロック5aは、桁材5と同様にH形鋼から構成しても構わない。
(Girder material)
The girder material 5 is a steel material made of H-shaped steel, placed on the horizontal beams 4, 4 and joined by welding or the like. The girder 5 according to this embodiment is placed on and joined to the lateral beams 4, 4 via spacer blocks 5a. Of course, the girder members 5 and the spacer blocks 5a are not limited to being joined to the cross beams 4 by welding, but may be joined mechanically such as by bolting or riveting. Further, the spacer block 5a may be made of H-shaped steel, like the girder 5.

以上説明した第1実施形態に係る仮設橋脚1によれば、横梁4が2つの既設橋脚P2,P3の周囲をそれぞれ取り囲む一対の枠体3間に架け渡されて接合されて既設橋脚P2,P3に支持されているので、既設橋脚P2,P3を利用してレベル2地震動の水平力に対抗することができる。このため、仮設橋脚1は、レベル2地震動に対する耐震性能を有することができる。 According to the temporary pier 1 according to the first embodiment described above, the horizontal beam 4 is bridged between and joined to the pair of frames 3 surrounding the two existing piers P2, P3. Therefore, the existing piers P2 and P3 can be used to withstand the horizontal force of the level 2 seismic motion. Therefore, the temporary bridge pier 1 can have seismic performance against level 2 seismic motion.

その上、仮設橋脚1は、既設橋脚P2,P3を用いて地震動の水平力に対抗するため、仮設橋脚1単独でレベル2地震動の応答値を弾性範囲内に収めて設計する場合と比べてはるかに小型の鋼材で構成しても同様の耐震性能を有することが可能となり、仮設橋脚1を鋼材使用量が少なく安価に設置することができる。 In addition, since the temporary pier 1 uses the existing piers P2 and P3 to resist the horizontal force of seismic motion, it is much more effective than the case where the temporary pier 1 alone is designed to keep the level 2 seismic motion response value within the elastic range. It is possible to have the same seismic performance even if it is composed of a small steel material, and the temporary bridge pier 1 can be installed at a low cost with a small amount of steel material used.

[第2実施形態]
図4を用いて、本発明の第2実施形態に係る仮設橋脚1’の支持構造について説明する。本発明の第2実施形態に係る仮設橋脚の支持構造を有した仮設橋脚1’が、前述の第1実施形態に係る仮設橋脚1と相違する点は、必須である仮設橋脚1の構成に、前述の既設橋梁B1の外側の既設橋脚P1,P4にさらに他の構成が増設されている点である。よって、その点について主に説明し、同一構成は同一符号を付し、説明を省略する。図4は、本発明の第2実施形態に係る仮設橋脚の支持構造を有した仮設橋脚1’を既設橋梁の橋軸方向に沿って見た正面図である。
[Second embodiment]
A support structure for a temporary bridge pier 1' according to a second embodiment of the present invention will be described with reference to FIG. A temporary pier 1' having a support structure for a temporary pier according to the second embodiment of the present invention differs from the temporary pier 1 according to the first embodiment described above in that the configuration of the temporary pier 1, which is essential, The difference is that other structures are added to the existing bridge piers P1 and P4 outside the existing bridge B1. Therefore, this point will be mainly described, and the same components will be denoted by the same reference numerals, and the description thereof will be omitted. FIG. 4 is a front view of a temporary pier 1' having a temporary pier support structure according to a second embodiment of the present invention, viewed along the axial direction of the existing bridge.

(ブラケット枠体)
仮設橋脚1’は、前述の既設橋脚P2,P3の外側の既設橋脚P1,P4の周囲をそれぞれ取り囲むようにブラケット枠体6を備えている。このブラケット枠体6は、H形鋼が既設橋脚P1,P4の周囲をそれぞれ取り囲むように溶接等で接合されて組み合わされた矩形状の枠体であり、枠体を構成するH形鋼の一部が既設橋梁B1の橋軸直角方向外側へブラケット部6aとして突設されている。
(bracket frame)
The temporary pier 1' has a bracket frame 6 so as to surround the existing piers P1 and P4 outside the existing piers P2 and P3. The bracket frame 6 is a rectangular frame formed by combining H-shaped steel so as to surround the existing bridge piers P1 and P4 by welding or the like. is projected outward in the direction perpendicular to the axis of the existing bridge B1 as a bracket portion 6a.

(ブラケット支柱)
このブラケット枠体6は、内側が前述の仮設支柱2で下方から支持されているとともに、外側が、ブラケット支柱7で下方から支持されている。このブラケット支柱7も、仮設支柱2と同様に、H形鋼などの鋼材から構成され、既設橋脚P1,P4に沿って立設されている。また、このブラケット支柱7の下端も、基礎F1,F2にあと施工アンカーで止め付けられた上、根巻コンクリート7aが打設されて基礎F1,F2に固定されている。なお、ブラケット支柱7は、キリンジャッキなしでブラケット枠体6に対して溶接等で剛接合されている。
(bracket strut)
The inside of the bracket frame 6 is supported from below by the above-described temporary support 2, and the outside is supported by the bracket support 7 from below. Similar to the temporary support 2, the bracket support 7 is also made of steel such as H-shaped steel, and stands along the existing bridge piers P1 and P4. The lower ends of the bracket struts 7 are also fixed to the foundations F1 and F2 with post-installed anchors, and are fixed to the foundations F1 and F2 by placing neck-wrapping concrete 7a. The bracket strut 7 is rigidly joined to the bracket frame 6 by welding or the like without giraffe jacks.

なお、ブラケット支柱7には、既設橋脚P1,P4の外周に沿って内側に向け、肘木部7bが突設されている。この肘木部7bは、既設橋脚P1,P4の外周に当接することにより、既設橋脚P1,P4を利用してブラケット部6aに作用する橋軸方向に沿った応力に対抗する機能を有している。 The bracket post 7 has an elbow joint 7b projecting inward along the outer circumference of the existing bridge piers P1 and P4. The armrest 7b has the function of resisting the axial stress acting on the bracket portion 6a using the existing piers P1 and P4 by coming into contact with the outer circumferences of the existing piers P1 and P4. .

(斜材)
また、ブラケット枠体6のブラケット部6aは、鋼材からなる複数の斜材7cでブラケット支柱7及び仮設支柱2に接合されて支持されている。
(diagonal material)
The bracket portion 6a of the bracket frame 6 is joined to and supported by the bracket strut 7 and the temporary strut 2 by a plurality of diagonal members 7c made of steel.

(第2横梁)
ブラケット枠体6と枠体3との間には、第2横梁8が架け渡されている。この第2横梁8は、H形鋼からなる鋼材であり、地震動による2つの既設橋脚P1,P2(P3,P4)の応答スペクトルが同期するようにブラケット枠体6と枠体3との間に溶接等で剛接合されている。但し、第2横梁8は、横梁4と同様に、ブラケット枠体6及び枠体3と剛接合されているものに限られず、ピン接合されていても構わない。
(Second cross beam)
A second cross beam 8 is bridged between the bracket frame 6 and the frame 3 . The second cross beam 8 is a steel material made of H-shaped steel, and is provided between the bracket frame 6 and the frame 3 so that the response spectra of the two existing bridge piers P1 and P2 (P3 and P4) due to earthquake motion are synchronized. It is rigidly joined by welding or the like. However, like the horizontal beam 4, the second horizontal beam 8 is not limited to being rigidly connected to the bracket frame 6 and the frame 3, and may be connected by pins.

また、第2横梁8の上には、前述の桁材5がスペーサーブロック5aを介して第2横梁8上に載置されて溶接等で接合されている。 On the second horizontal beam 8, the girder 5 described above is placed on the second horizontal beam 8 via spacer blocks 5a and joined by welding or the like.

(ブラケット桁材)
そして、ブラケット枠体6のブラケット部6aの上には、H形鋼からなる複数のブラケット桁材9が載置されて溶接等で接合されている。
(bracket girder material)
A plurality of bracket beam members 9 made of H-shaped steel are placed on the bracket portion 6a of the bracket frame 6 and joined by welding or the like.

以上説明した第2実施形態に係る仮設橋脚1’によれば、第2横梁8が2つの既設橋脚P1,P2(P3,P4)の周囲をそれぞれ取り囲むブラケット枠体6と枠体3との間に架け渡されて接合されて既設橋脚P1,P2(P3,P4)に支持されているので、仮設橋脚1から増設する部分も、既設橋脚P2,P3を用いてレベル2地震動の水平力に対抗することができる。 According to the temporary bridge pier 1' according to the second embodiment described above, the second cross beam 8 surrounds the two existing bridge piers P1, P2 (P3, P4) between the bracket frame 6 and the frame 3. Since it is supported by the existing piers P1 and P2 (P3 and P4), the existing piers P2 and P3 are used to counter the horizontal force of the level 2 seismic motion. can do.

また、仮設橋脚1’は、既設橋脚P1,P2を用いて地震動の水平力に対抗するため、仮設橋脚1’単独でレベル2地震動の応答値を弾性範囲内に収めて設計する場合と比べてはるかに小型の鋼材で構成しても同様の耐震性能を有することが可能となり、仮設橋脚1’を鋼材使用量が少なく安価に設置することができる。 In addition, since the temporary pier 1' uses the existing piers P1 and P2 to resist the horizontal force of the seismic motion, compared to the case where the temporary pier 1' alone is designed to keep the level 2 seismic motion response value within the elastic range. It is possible to have the same seismic performance even if it is configured with a much smaller steel material, and the temporary pier 1' can be installed at a low cost with a small amount of steel material used.

それに加え、仮設橋脚1’によれば、既設橋脚P1~P4を取り囲む枠体3,ブラケット枠体6がそれぞれ別体となってそれらが横梁4,第2横梁8で連結されているので、更新工事の進捗に合わせて仮設橋脚1から既設橋脚P4側、既設橋脚P1側と順次、仮設橋脚1’を増設することができる。このため、仮設橋脚1’によれば、仮設橋脚1’の設置期間を短縮することにより、仮設材のリース料を低減できるとともに、既設橋梁B1の下部の通行等の障害を極力少なくすることができる。なお、本発明に係る仮設橋脚は、ブラケット枠体と横梁を増設していくことで既設橋脚が4つ以上ある橋梁にも好適に適用することができる。 In addition, according to the temporary pier 1', the frame 3 and the bracket frame 6 surrounding the existing piers P1 to P4 are separated from each other and connected by the cross beams 4 and the second cross beams 8. Temporary piers 1' can be added sequentially from the temporary pier 1 to the existing pier P4 side and the existing pier P1 side in accordance with the progress of construction. For this reason, according to the temporary pier 1', by shortening the installation period of the temporary pier 1', it is possible to reduce the leasing fee for the temporary material and to minimize obstacles such as traffic under the existing bridge B1. can. The temporary bridge pier according to the present invention can be suitably applied to a bridge having four or more existing piers by adding more bracket frames and cross beams.

<橋梁上部構造の更新方法>
次に、図1,図4,図5~図29を用いて、本発明の実施形態に係る橋梁上部構造の更新方法について説明する。前述の第2実施形態に係る仮設橋脚1’を用いて、前述の4つの既設橋脚P1~P4を有する上下3車線ずつの既設橋梁B1のRC中空床版桁からなる上部構造B2をプレキャスト製のT桁T1に取り替えて更新する場合を例示して説明する。なお、本実施形態では、複数のT桁T1は、支承数を低減するためプレキャスト製のPCa横梁PBを介して設置される。
<How to update the bridge superstructure>
Next, a method for updating a bridge superstructure according to an embodiment of the present invention will be described with reference to FIGS. 1, 4 and 5 to 29. FIG. Using the temporary pier 1' according to the second embodiment described above, the superstructure B2 consisting of the RC hollow floor slab girder of the existing bridge B1 having the four existing piers P1 to P4 and three lanes each of the upper and lower sides is precast. A case of updating by replacing with T digit T1 will be described as an example. In this embodiment, the plurality of T girders T1 are installed via precast PCa cross beams PB in order to reduce the number of bearings.

(上部構造中央部撤去工程)
先ず、図1,図4に示すように、本実施形態に係る橋梁上部構造の更新方法では、上部構造B2の中央分離帯付近の上下1車線ずつの領域である撤去部分B2#を撤去する上部構造中央部撤去工程を行う。また、このとき、図4に示すように、通行車両が落下しないように撤去部分B2#に沿って前述の載置型の仮設壁高欄K2を設置する。
(Removal process of central part of upper structure)
First, as shown in FIGS. 1 and 4, in the bridge superstructure renewal method according to the present embodiment, the upper part B2#, which is an area of one upper and lower lane near the median strip of the superstructure B2, is removed. Carry out the process of removing the central part of the structure. At this time, as shown in FIG. 4, the above-described mounting type temporary wall balustrade K2 is installed along the removed portion B2# so as to prevent passing vehicles from falling.

(仮設橋脚設置工程)
その後、図4に示すように、本実施形態に係る橋梁上部構造の更新方法では、前述の仮設橋脚1’を組み立てて設置する仮設橋脚設置工程を行う。
(Temporary bridge pier installation process)
After that, as shown in FIG. 4, in the bridge superstructure renewal method according to the present embodiment, a temporary pier installation step of assembling and installing the aforementioned temporary pier 1' is performed.

但し、このとき、図1に示すように、前述の仮設橋脚1を組み立てて設置して、更新工事の進捗に合わせて仮設橋脚1’の残りの構成を順次増設してもよい。前述のように、仮設橋脚1’の設置期間を短縮することにより、仮設材のリース料を低減できるとともに、既設橋梁B1の下部の通行等の障害を極力少なくすることができるからである。 However, at this time, as shown in FIG. 1, the above-described temporary pier 1 may be assembled and installed, and the remaining components of the temporary pier 1' may be sequentially added according to the progress of the renewal work. This is because, as described above, by shortening the installation period of the temporary bridge pier 1', it is possible to reduce the leasing fee for the temporary material and to minimize obstacles such as passage under the existing bridge B1.

(上下線連結横梁架設工程)
次に、図5,図6に示すように、本実施形態に係る橋梁上部構造の更新方法では、上下線連結横梁架設工程を行う。図5は、本実施形態に係る橋梁上部構造の更新方法の上下線連結横梁架設工程を示す橋梁を橋軸方向に見たパース図であり、図6は、同上下線連結横梁架設工程を示す橋梁を俯瞰して見た斜視図である。
(Upper and lower line connection horizontal beam erection process)
Next, as shown in FIGS. 5 and 6, in the method for updating the bridge superstructure according to the present embodiment, a vertical line connecting horizontal beam construction step is performed. FIG. 5 is a perspective view of the bridge as viewed in the direction of the bridge axis, showing the vertical line connecting horizontal beam erection process of the bridge superstructure renewal method according to the present embodiment, and FIG. 6 is a bridge showing the vertical line connecting horizontal beam construction process. 1 is a perspective view of a bird's-eye view of FIG.

本工程では、予めPCブラケット及び定着具を設置して新設する上り線のPCa横梁PBと下り線のPCa横梁PB’を、鋼材からなるブロック体である鋼殻IBを介して橋軸直角方向にPC鋼材である外ケーブルで緊張して連結しておく。そして、仮設橋脚1’の桁材5の上に連結したPCa横梁PB及びPCa横梁PB’を載置する。 In this process, PC brackets and fixtures are installed in advance, and the PCa cross beam PB of the up line and the PCa cross beam PB' of the down line are newly installed in the direction perpendicular to the bridge axis through the steel shell IB, which is a block body made of steel. The outer cable made of PC steel is tensioned and connected. Then, the PCa cross-beam PB and the PCa cross-beam PB' are placed on the girder 5 of the temporary pier 1'.

(T桁載置工程)
次に、本実施形態に係る橋梁上部構造の更新方法では、前工程で載置したPCa横梁PB及びPCa横梁PB’間に複数のT桁T1を載置するT桁載置工程を行う。そして、PCブラケット及び緊張ケーブルを用いて橋軸方向にPC鋼材でPCa横梁PB及びPCa横梁PB’間を緊張し、プレストレスを導入して複数のT桁T1とPCa横梁PB及びPCa横梁PB’を一体化し、既設橋梁B1の撤去部分B2#に相当する中央部に2車線分の新規な仮設路線を開通させ、更新工事を行いながら仮設の車両用通路として共用する。
(T girder placement process)
Next, in the method for updating the bridge superstructure according to the present embodiment, a T-girder placing step of placing a plurality of T-girders T1 between the PCa lateral beams PB and PCa lateral beams PB' placed in the previous step is performed. Then, using PC brackets and tension cables, PC steel materials are tensioned between the PCa cross beams PB and PCa cross beams PB' in the bridge axis direction, and prestress is introduced to introduce a plurality of T girders T1 and PCa cross beams PB and PCa cross beams PB'. are integrated, and a new temporary road for two lanes is opened in the central part corresponding to the removed part B2# of the existing bridge B1, and it is shared as a temporary vehicle passage while performing renewal work.

このとき、仮設橋脚1’の横梁4が2つの既設橋脚P2,P3の周囲をそれぞれ取り囲む一対の枠体3間に架け渡されて接合されて既設橋脚P2,P3に支持されている。このため、仮設橋脚1’で支持された中央部の2車線分の新規な仮設路線は、既設橋脚P2,P3を用いて地震動の水平力に対抗することができ、レベル2地震動にも対抗することができる。このため、仮設橋脚1で支持された中央部の2車線分の新設の仮設路線は、レベル2地震動に対する耐震性能を有することができ、上部構造更新作業時の安全な車両通路として使用するこができる。 At this time, the lateral beams 4 of the temporary pier 1' are bridged and joined between a pair of frames 3 surrounding the two existing piers P2 and P3, respectively, and are supported by the existing piers P2 and P3. Therefore, the new temporary route for two lanes in the center supported by the temporary bridge pier 1' can withstand the horizontal force of the seismic motion using the existing piers P2 and P3, and can also withstand level 2 seismic motion. be able to. For this reason, the new temporary track for two lanes in the central part supported by the temporary bridge pier 1 can have seismic performance against level 2 seismic motion, and can be used as a safe vehicle passage during superstructure renewal work. can.

(下り線上部構造撤去工程)
次に、本実施形態に係る橋梁上部構造の更新方法では、前工程で設置した中央部の2車線分の新設路線を下り線として利用し、図5,図6で示した外側2車線分の下り線の既設の上部構造B2を撤去する下り線上部構造撤去工程を行う。
(Down line superstructure removal process)
Next, in the method for updating the bridge superstructure according to the present embodiment, the new route for two lanes in the central part installed in the previous process is used as an outbound line, and the two lanes for the outer side shown in FIGS. The outbound line superstructure removal step is performed to remove the existing outbound line superstructure B2.

(下り線新設工程)
次に、本実施形態に係る橋梁上部構造の更新方法では、前工程で撤去した外側2車線分の下り線部分に、新設の下り線のPCa横梁PB’を設置した上、複数のT桁T1を載置する下り線新設工程を行う。
(Outbound line new construction process)
Next, in the method for updating the bridge superstructure according to the present embodiment, a new outbound PCa cross beam PB' is installed on the outbound two-lane portion removed in the previous process, and a plurality of T girders T1 are installed. A new outbound line installation process is performed.

(外ケーブル解放工程)
次に、図7,図8に示すように、本実施形態に係る橋梁上部構造の更新方法では、PCa横梁PB及びPCa横梁PB’を一体化していたPC鋼材である外ケーブルを解放する外ケーブル解放工程を行う。図7は、本実施形態に係る橋梁上部構造の更新方法の外ケーブル解放工程を示す橋梁を橋軸方向に見たパース図であり、図8は、中央2車線部分を拡大して同外ケーブル解放工程を示す部分拡大斜視図である。
(Outer cable release process)
Next, as shown in FIGS. 7 and 8, in the method for updating the bridge superstructure according to the present embodiment, the outer cables made of PC steel that have integrated the PCa lateral beams PB and PCa lateral beams PB' are released. Perform the release process. FIG. 7 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the outer cable release process of the bridge superstructure renewal method according to the present embodiment. FIG. It is a partial expansion perspective view which shows a release process.

(鋼殻撤去工程)
次に、図9,図10に示すように、本実施形態に係る橋梁上部構造の更新方法では、PCa横梁PBとPCa横梁PB’との間に介装していた鋼殻IBを一時的に撤去する鋼殻撤去工程を行う。図9は、本実施形態に係る橋梁上部構造の更新方法の鋼殻撤去工程を示す橋梁を橋軸方向に見たパース図であり、図10は、図9の中央2車線部分を拡大して同鋼殻撤去工程を示す部分拡大パース図である。
(Steel shell removal process)
Next, as shown in FIGS. 9 and 10, in the bridge superstructure renewal method according to the present embodiment, the steel shell IB interposed between the PCa lateral beam PB and the PCa lateral beam PB' is temporarily Carry out the steel shell removal process to be removed. FIG. 9 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the steel shell removal process of the bridge superstructure renewal method according to the present embodiment, and FIG. It is a partially enlarged perspective view showing the same steel shell removing process.

(下り線横梁緊張工程)
次に、図11,図12に示すように、本実施形態に係る橋梁上部構造の更新方法では、前工程で鋼殻IBを撤去したスペースを利用してPC鋼材を挿入して両端部に定着具を設置し、下り線側のPCa横梁PB’を緊張して一体化する下り線横梁緊張工程を行う。図11は、本実施形態に係る橋梁上部構造の更新方法の下り線横梁緊張工程を示す橋梁を橋軸方向に見たパース図であり、図12は、同下り線横梁緊張工程を示す下り線側のPCa横梁PB’の外側端部を拡大した拡大斜視図である。
(Outbound line horizontal beam tensioning process)
Next, as shown in FIGS. 11 and 12, in the bridge superstructure renewal method according to the present embodiment, PC steel materials are inserted into the space from which the steel shell IB was removed in the previous process, and fixed to both ends. A step of tensioning the PCa cross beams PB' on the side of the down line to integrate them is performed. FIG. 11 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the down-line horizontal beam tensioning process of the bridge superstructure renewal method according to the present embodiment, and FIG. 12 is a down-line showing the down-line horizontal beam tensioning process. FIG. 11 is an enlarged perspective view of the outer end of the side PCa cross beam PB′;

(鋼殻再設置工程)
次に、図13,図14に示すように、本実施形態に係る橋梁上部構造の更新方法では、前鋼殻撤去工程で撤去した鋼殻IBを再設置する鋼殻再設置工程を行う。図13は、本実施形態に係る橋梁上部構造の更新方法の鋼殻再設置工程を示す橋梁を橋軸方向に見たパース図であり、図14は、図13の中央2車線部分を拡大して同鋼殻再設置工程を示す部分拡大パース図である。
(Steel shell re-installation process)
Next, as shown in FIGS. 13 and 14, in the bridge superstructure renewal method according to the present embodiment, a steel shell re-installation process is performed to re-install the steel shell IB removed in the previous steel shell removal process. FIG. 13 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the steel shell re-installation step of the bridge superstructure renewal method according to the present embodiment, and FIG. 14 is an enlarged view of the central two-lane portion of FIG. Fig. 10 is a partially enlarged perspective view showing the steel shell re-installation process.

(外ケーブル再緊張工程)
次に、図15,図16に示すように、本実施形態に係る橋梁上部構造の更新方法では、外ケーブルを再緊張してPCa横梁PB及びPCa横梁PB’を一体化する外ケーブル再緊張工程を行う。図15は、本実施形態に係る橋梁上部構造の更新方法の外ケーブル再緊張工程を示す橋梁を橋軸方向に見たパース図であり、図16は、中央2車線部分を拡大して同外ケーブル再緊張工程を示す部分拡大斜視図である。
(Outer cable re-tensioning process)
Next, as shown in FIGS. 15 and 16, in the method for renewing the bridge superstructure according to the present embodiment, an outer cable re-tensioning step of re-tensioning the outer cables to integrate the PCa lateral beams PB and PCa lateral beams PB'. I do. FIG. 15 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the outer cable re-tensioning process of the bridge superstructure renewal method according to this embodiment, and FIG. FIG. 4 is a partially enlarged perspective view showing a cable re-tensioning process;

(上り線上部構造撤去工程)
次に、本実施形態に係る橋梁上部構造の更新方法では、前工程終了後、更新工事の施工帯を下り線の外側2車線分から上り線の外側2車線分に変更し、図15,図16で示した外側2車線分の上り線の既設の上部構造B2を撤去する上り線上部構造撤去工程を行う。
(In-bound line superstructure removal process)
Next, in the bridge superstructure renewal method according to the present embodiment, after the preceding process is completed, the construction zone for the renewal work is changed from the outer two lanes of the outbound line to the outer two lanes of the inbound line, as shown in FIGS. An up-line superstructure removal process is performed to remove the existing superstructure B2 of the up-track for two outer lanes shown in .

(上り線新設工程)
次に、本実施形態に係る橋梁上部構造の更新方法では、前工程で撤去した外側2車線分の上り線部分に、新設の上り線のPCa横梁PBを設置した上、複数のT桁T1を載置する上り線新設工程を行う。
(In-bound line new construction process)
Next, in the method for updating the bridge superstructure according to the present embodiment, a new PCa cross-beam PB for the in-bound line is installed on the in-bound line portion of the outer two lanes removed in the previous process, and then a plurality of T girders T1 are installed. An inbound line installation process for placing is performed.

(外ケーブル解放工程)
次に、図17,図18に示すように、本実施形態に係る橋梁上部構造の更新方法では、PCa横梁PB及びPCa横梁PB’を一体化していた外ケーブルを解放する外ケーブル解放工程を行う。図17は、本実施形態に係る橋梁上部構造の更新方法の外ケーブル解放工程を示す橋梁を橋軸方向に見たパース図であり、図18は、中央2車線部分を拡大して同外ケーブル解放工程を示す部分拡大斜視図である。
(Outer cable release process)
Next, as shown in FIGS. 17 and 18, in the method for updating the bridge superstructure according to the present embodiment, an outer cable release step is performed to release the outer cable that integrates the PCa lateral beam PB and the PCa lateral beam PB'. . FIG. 17 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the outer cable release process of the bridge superstructure renewal method according to the present embodiment, and FIG. It is a partial expansion perspective view which shows a release process.

(外ケーブル撤去工程)
次に、図19,図20に示すように、本実施形態に係る橋梁上部構造の更新方法では、PCa横梁PB及びPCa横梁PB’を一体化していた外ケーブルを撤去する外ケーブル撤去工程を行う。図19は、本実施形態に係る橋梁上部構造の更新方法の外ケーブル撤去工程を示す橋梁を橋軸方向に見たパース図であり、図20は、中央2車線部分を拡大して同外ケーブル撤去工程を示す部分拡大斜視図である。
(Outer cable removal process)
Next, as shown in FIGS. 19 and 20, in the bridge superstructure renewal method according to the present embodiment, an outer cable removal step is performed to remove the outer cables that have integrated the PCa lateral beams PB and PCa lateral beams PB'. . FIG. 19 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the process of removing the outer cable in the bridge superstructure renewal method according to this embodiment, and FIG. It is a partial expansion perspective view which shows a removal process.

(鋼殻再撤去工程)
次に、図21,図22に示すように、本実施形態に係る橋梁上部構造の更新方法では、PCa横梁PBとPCa横梁PB’との間に介装していた鋼殻IBを再度撤去する鋼殻再撤去工程を行う。図21は、本実施形態に係る橋梁上部構造の更新方法の鋼殻再撤去工程を示す橋梁を橋軸方向に見たパース図であり、図22は、図21の中央2車線部分を拡大して同鋼殻再撤去工程を示す部分拡大パース図である。
(Steel shell re-removal process)
Next, as shown in FIGS. 21 and 22, in the bridge superstructure renewal method according to the present embodiment, the steel shell IB interposed between the PCa lateral beam PB and the PCa lateral beam PB' is again removed. Carry out the steel shell re-removal process. FIG. 21 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the steel shell re-removal process of the bridge superstructure renewal method according to the present embodiment, and FIG. Fig. 10 is a partially enlarged perspective view showing the steel shell re-removal process.

(緊張ケーブル解放工程)
次に、図23,図24に示すように、本実施形態に係る橋梁上部構造の更新方法では、中央線付近の上り線側PCa横梁PB同士及び下り線側PCa横梁PB’同士を緊張していた緊張ケーブルを解放する緊張ケーブル解放工程を行う。図23は、本実施形態に係る橋梁上部構造の更新方法の緊張ケーブル解放工程を示す橋梁を橋軸方向に見たパース図であり、図24は、図23の中央2車線部分を拡大して同緊張ケーブル解放工程を示す部分拡大パース図である。
(Tension cable release process)
Next, as shown in FIGS. 23 and 24, in the bridge superstructure renewal method according to the present embodiment, the up-line side PCa lateral beams PB and the down-line side PCa lateral beams PB' near the central line are strained. Perform a tension cable release step to release the tension cable. FIG. 23 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the tension cable release process of the bridge superstructure renewal method according to this embodiment, and FIG. FIG. 10 is a partially enlarged perspective view showing the same tension cable release process;

(緊張ケーブル撤去工程)
次に、図25,図26に示すように、本実施形態に係る橋梁上部構造の更新方法では、中央線付近の上り線側PCa横梁PB同士及び下り線側PCa横梁PB’同士を緊張していた緊張ケーブル及びPCブラケットを撤去する緊張ケーブル撤去工程を行う。図25は、本実施形態に係る橋梁上部構造の更新方法の緊張ケーブル撤去工程を示す橋梁を橋軸方向に見たパース図であり、図26は、図25の中央2車線部分を拡大して同緊張ケーブル撤去工程を示す部分拡大パース図である。
(Tension cable removal process)
Next, as shown in FIGS. 25 and 26, in the method for updating the bridge superstructure according to the present embodiment, the up-line side PCa lateral beams PB and the down-line side PCa lateral beams PB' near the central line are strained. A tension cable removal step is performed to remove the tension cable and PC bracket. FIG. 25 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the tension cable removal process of the bridge superstructure renewal method according to this embodiment, and FIG. It is a partially enlarged perspective view showing the same tension cable removal process.

(上り線横梁緊張工程)
次に、図27,図28に示すように、本実施形態に係る橋梁上部構造の更新方法では、鋼殻再撤去工程で鋼殻IBを撤去したスペースを利用してPC鋼材を挿入して両端部に定着具を設置し、上り線側のPCa横梁PBを緊張して一体化する上り線横梁緊張工程を行う。図27は、本実施形態に係る橋梁上部構造の更新方法の上り線横梁緊張工程を示す橋梁を橋軸方向に見たパース図であり、図28は、同上り線横梁緊張工程を示す上り線側のPCa横梁PBの外側端部を拡大した拡大斜視図である。
(Inbound line horizontal beam tensioning process)
Next, as shown in FIGS. 27 and 28, in the method for renewing the bridge superstructure according to the present embodiment, PC steel materials are inserted into the space from which the steel shell IB was removed in the steel shell re-removal process, and both ends are inserted. An up-line horizontal beam tensioning step is performed in which a fixture is installed in the part and the PCa horizontal beams PB on the up-line side are tensioned and integrated. FIG. 27 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the up-line cross-beam tensioning process of the bridge superstructure renewal method according to the present embodiment, and FIG. FIG. 11 is an enlarged perspective view of the outer end of the side PCa cross beam PB;

次に、図29に示すように、本実施形態に係る橋梁上部構造の更新方法では、新設した上り線の外側端部に沿って壁高欄K1を設置することにより、本実施形態に係る橋梁上部構造の更新方法の更新工事が完了する。図29は、本実施形態に係る橋梁上部構造の更新方法の完了状態を示す橋梁を橋軸方向に見たパース図である。 Next, as shown in FIG. 29, in the method for updating the bridge superstructure according to this embodiment, by installing the wall balustrade K1 along the outer edge of the newly installed inbound line, the bridge upper structure according to this embodiment is installed. Renewal work of the structural renewal method is completed. FIG. 29 is a perspective view of the bridge viewed in the direction of the bridge axis, showing the completed state of the method for updating the bridge superstructure according to the present embodiment.

以上説明した本実施形態に係る橋梁上部構造の更新方法によれば、前述のように、仮設橋脚1’の横梁4が2つの既設橋脚P2,P3の周囲をそれぞれ取り囲む一対の枠体3間に架け渡されて接合されているので、仮設橋脚1’がレベル2地震動に対する耐震性能を有する。このため、仮設橋脚1’(仮設橋脚1)で支持された中央部の2車線分の仮設路線は、レベル2地震動に対する耐震性能を有することができ、上部構造更新作業時の安全な車両通路として使用するこができる。よって、本実施形態に係る橋梁上部構造の更新方法によれば、安全に効率よく上部構造の更新工事を行うことができる。 According to the method for updating the bridge superstructure according to the present embodiment described above, as described above, the lateral beam 4 of the temporary bridge pier 1' is positioned between the pair of frames 3 surrounding the two existing bridge piers P2 and P3. Since it is bridged and joined, the temporary pier 1' has seismic performance against level 2 seismic motion. For this reason, the two-lane temporary road in the center supported by the temporary pier 1' (temporary pier 1) can have seismic performance against level 2 seismic motion, and can be used as a safe vehicle passage during superstructure renewal work. can be used. Therefore, according to the bridge superstructure renewal method according to the present embodiment, superstructure renewal work can be performed safely and efficiently.

また、本実施形態に係る橋梁上部構造の更新方法によれば、新設するPCa横梁PB(PB’)を用いて、既設橋脚P2,P3間に一時的に上下線のいずれか一方の車線を設けて共用するので、通行規制を少なくして安全に上部構造の更新工事を行うことができる。 Further, according to the bridge superstructure updating method according to the present embodiment, either one of the up and down lanes is temporarily provided between the existing bridge piers P2 and P3 using the newly installed PCa cross beam PB (PB'). Since it is shared by both, it is possible to safely carry out the renewal work of the superstructure with fewer traffic restrictions.

その上、本実施形態に係る橋梁上部構造の更新方法に用いる仮設橋脚1’は、既設橋脚P1~P4を取り囲む枠体3,ブラケット枠体6がそれぞれ別体となってそれらが横梁4,第2横梁8で連結されている。このため、仮設橋脚1’は、更新工事の進捗に合わせて仮設橋脚1から既設橋脚P4側、既設橋脚P1側と順次、仮設橋脚1’を増設することが可能となっている。よって、本実施形態に係る橋梁上部構造の更新方法によれば、仮設橋脚1’の設置期間を短縮することにより、仮設材のリース料を低減できるとともに、既設橋梁B1の下部の通行等の障害を極力少なくすることができる。 In addition, the temporary bridge pier 1' used in the method for updating the bridge superstructure according to the present embodiment has the frame 3 and the bracket frame 6 that surround the existing bridge piers P1 to P4. 2 are connected by a cross beam 8. Therefore, the temporary pier 1' can be added sequentially from the temporary pier 1 to the existing pier P4 side and the existing pier P1 side in accordance with the progress of the renewal work. Therefore, according to the method for updating the bridge superstructure according to the present embodiment, by shortening the installation period of the temporary bridge pier 1', it is possible to reduce the leasing fee for the temporary materials and prevent obstacles such as traffic under the existing bridge B1. can be minimized.

以上、本発明の実施形態に係る仮設橋脚の支持構造及び橋梁上部構造の更新方法について詳細に説明したが、前述した又は図示した実施形態は、いずれも本発明を実施するにあたって具体化した一実施形態を示したものに過ぎない。よって、これらによって本発明の技術的範囲が限定的に解釈されてはならないものである。 As above, the support structure of the temporary pier and the method of updating the bridge superstructure according to the embodiment of the present invention have been described in detail. It is only a representation of the form. Therefore, the technical scope of the present invention should not be construed to be limited by these.

また、本発明の実施形態に係る橋梁上部構造の更新方法として、下り線の上部構造を先に解体して更新する場合を例示したが、上り線の上部構造を先に解体して更新してもよいことは云うまでない。要するに、本発明に係る橋梁上部構造の更新方法では、仮設橋脚を用いて中央部に仮設通路を設置して共用し、上下線のいずれか一方を先に解体撤去して更新すればよい。 Further, as a method for updating a bridge superstructure according to the embodiment of the present invention, the case where the superstructure of the outbound line is first dismantled and renewed was exemplified. Needless to say, it's a good thing. In short, in the bridge superstructure renewal method according to the present invention, a temporary passageway is installed in the central part using temporary bridge piers for common use, and either one of the upper and lower lines is dismantled and removed first for renewal.

特に、4つの既設橋脚P1~P4を有する上下3車線ずつの既設橋梁B1のRC中空床版桁からなる上部構造B2をプレキャスト製のT桁T1に取り替えて更新する場合を例示して説明したが、橋脚の数や上部構造は、既設新設を問わず、どのような形式の橋梁にも適用することができる。例えば、既設のRC中空床版桁を、本願出願人が提案しているSCBR工法のように、プレキャスト横梁を介してプレキャスト製の中空ホロー桁に更新する場合にも好適に適用することができる。 In particular, the case of replacing the upper structure B2 consisting of RC hollow slab girders of the existing bridge B1 with four existing bridge piers P1 to P4 and three lanes each on the upper and lower sides with a precast T girder T1 was explained as an example. , the number of piers and superstructure can be applied to any type of bridge regardless of existing or new construction. For example, it can be suitably applied when an existing RC hollow floor slab girder is replaced with a precast hollow hollow girder via a precast cross beam, like the SCBR construction method proposed by the applicant of the present application.

1,1’:仮設橋脚
2:仮設支柱
2a:根巻コンクリート
2b:キリンジャッキ
3:枠体
4:横梁
5:桁材
5a:スペーサーブロック
6:ブラケット枠体(枠体)
6a:ブラケット部
7:ブラケット支柱(仮設支柱)
7a:根巻コンクリート
7b:肘木部
7c:斜材
8:第2横梁(横梁)
9:ブラケット桁材
B1:既設橋梁(橋梁)
B2:既設上部構造
B2#:撤去部分
K1:壁高欄
K2:仮設壁高欄
P1~P4:既設橋脚
F1,F2:基礎
PB,PB’:PCa横梁
IB:鋼殻
T1:T桁
1, 1': Temporary pier 2: Temporary support 2a: Concrete wrapped around the neck 2b: Giraffe jack 3: Frame 4: Cross beam 5: Girder 5a: Spacer block 6: Bracket frame (frame)
6a: Bracket part 7: Bracket strut (temporary strut)
7a: Neck-wrapped concrete 7b: Bracket 7c: Diagonal member 8: Second horizontal beam (horizontal beam)
9: Bracket girder material B1: Existing bridge (bridge)
B2: Existing superstructure B2#: Removal part K1: Wall balustrade K2: Temporary wall balustrade P1-P4: Existing bridge piers F1, F2: Foundation PB, PB': PCa cross beam IB: Steel shell T1: T girder

請求項1に係る仮設橋脚の支持構造は、離間して立設された2つの既設橋脚の橋軸直角方向の間に構築される複数の鋼材が組み合わされて前記既設橋脚の上部構造の更新工事の際に新設の上部構造を仮設的に支持する仮設橋脚の支持構造であって、前記既設橋脚に沿って立設された複数の仮設支柱と、これらの仮設支柱で下方から支持された一対の枠体と、これらの一対の枠体間に橋軸直角方向に架け渡された複数の横梁と、これらの複数の横梁上に前記横梁と直交するように設置されて更新の際に前記新設の上部構造を載置する複数の桁材と、を備え、前記横梁は、前記2つの既設橋脚の周囲をそれぞれ取り囲む前記一対の枠体間に架け渡されて接合されていることを特徴とする。 The support structure of the temporary pier according to claim 1 is a renewal work of the superstructure of the existing pier by combining a plurality of steel materials constructed between two existing piers erected at a distance in the direction perpendicular to the bridge axis. A support structure for temporary piers that temporarily supports a newly constructed superstructure at the time of A frame, a plurality of transverse beams spanning between the pair of frames in a direction perpendicular to the bridge axis, and a plurality of transverse beams installed perpendicular to the transverse beams at the time of renewal. and a plurality of girders for mounting a superstructure , wherein the cross beams are bridged and joined between the pair of frames surrounding the two existing bridge piers.

請求項に係る仮設橋脚の支持構造は、請求項1に係る仮設橋脚の支持構造において、前記横梁は、前記一対の枠体と剛接合されていることを特徴とする。 A support structure for a temporary pier according to claim 2 is characterized in that, in the support structure for a temporary pier according to claim 1, the lateral beam is rigidly joined to the pair of frames.

請求項に係る仮設橋脚の支持構造は、請求項1又は2に記載の仮設橋脚の支持構造において、離間して立設された既設橋脚が複数あり、それぞれの既設橋脚を取り囲む枠体がそれぞれ別体となってそれらの枠体が横梁で連結されていることを特徴とする。 A support structure for temporary piers according to claim 3 is the support structure for temporary piers according to claim 1 or 2 , wherein there are a plurality of existing piers erected with a space therebetween, and frames surrounding the existing piers are respectively It is characterized in that these frames are separate bodies and are connected by horizontal beams.

請求項に係る橋梁上部構造の更新方法は、既設橋梁の上部構造を取り替えて更新する橋梁上部構造の更新方法であって、請求項1ないしのいずれかに記載の仮設橋脚の支持構造を備えた仮設橋脚を、離間して立設された2つの既設橋脚の橋軸直角方向の間に構築した後、前記仮設橋脚上に架け替える新設の上部構造を載置することを特徴とする。 A bridge superstructure renewal method according to claim 4 is a bridge superstructure renewal method for replacing and renewing the superstructure of an existing bridge, wherein the temporary pier support structure according to any one of claims 1 to 3 is used. After constructing the provided temporary pier between two existing piers erected at a distance in the direction perpendicular to the axis of the bridge , a new superstructure to be replaced is placed on the temporary pier.

請求項に係る橋梁上部構造の更新方法は、請求項に係る橋梁上部構造の更新方法において、前記新設の上部構造は、橋軸直角方向に沿って設置された上下線に対応するプレキャスト製の一対のPCa横梁を備え、上下線のそれぞれのPCa横梁同士を、鋼材からなるブロック体である鋼殻を介して橋軸直角方向にPC鋼材である外ケーブルで連結して前記仮設橋脚の前記桁材の上に載置し、前記2つの既設橋脚の橋軸直角方向間に一時的に車線を設けて共用することを特徴とする。 A method for updating a bridge superstructure according to claim 5 is the method for updating a bridge superstructure according to claim 4 , wherein the new superstructure is made of precast material corresponding to an up/down line installed along the direction perpendicular to the bridge axis. The upper and lower PCa horizontal beams are connected to each other in the direction perpendicular to the bridge axis with an outer cable made of PC steel through a steel shell, which is a block body made of steel . It is characterized in that it is placed on a girder , and a lane is temporarily provided between the two existing bridge piers in the direction perpendicular to the bridge axis for common use.

請求項1~に係る発明によれば、横梁が2つの既設橋脚の周囲をそれぞれ取り囲む一対の枠体間に架け渡されて接合されているので、既設橋脚を用いてレベル2地震動の水平力に対抗することができるため、レベル2地震動に対する耐震性能を有することができる。その上、請求項1~に係る発明は、既設橋脚を用いて地震動の水平力に対抗するため、仮設橋脚単独でレベル2地震動の応答値を弾性範囲内に収めて設計する場合と比べてはるかに小型の鋼材で構成しても同様の耐震性能を有することが可能となり、仮設橋脚を鋼材使用量が少なく安価に設置することができる。また、請求項1~3に係る発明によれば、既設橋脚にあと施工アンカーを用いて枠体を止め付ける必要がなくなり、既設橋脚を損傷するおそれを低減することができる。また、仮設支柱は既設橋脚に沿って立設されているので、仮設支柱単体で地震動の水平力に対抗する必要がなく、鋼材のサイズを小さくして安価に設置することができる。 According to the invention according to claims 1 to 3 , since the horizontal beam is bridged and joined between the pair of frames surrounding the two existing piers, the horizontal force of the level 2 seismic motion is generated using the existing piers. Because it can withstand level 2 seismic motion, it can have seismic performance. In addition, the invention according to claims 1 to 3 uses the existing piers to resist the horizontal force of the earthquake motion, so compared to the case where the response value of the level 2 earthquake motion is kept within the elastic range by the temporary pier alone. Even if it is composed of much smaller steel materials, it is possible to have the same earthquake resistance performance, and the temporary piers can be installed at low cost using less steel material. In addition, according to the inventions of claims 1 to 3, it is not necessary to use post-installed anchors to fasten the frame to the existing piers, and the possibility of damaging the existing piers can be reduced. In addition, since the temporary columns are erected along the existing piers, there is no need for the temporary columns alone to withstand the horizontal force of the seismic motion, and the size of the steel material can be reduced and the installation cost can be reduced.

特に、請求項に係る発明によれば、さらに小型の鋼材で構成しても同様の耐震性能を有することが可能となり、仮設橋脚を鋼材使用量が少なく安価に設置することができる。 In particular, according to the invention of claim 2 , it is possible to have the same seismic performance even if it is made of a smaller steel material, and the temporary pier can be installed at a low cost with a small amount of steel material used.

特に、請求項に係る発明によれば、更新工事の進捗に合わせて仮設橋脚を増設することができ、仮設橋脚の設置期間を短縮することにより、仮設材のリース料を低減できるとともに、橋梁の下部の通行等の障害を極力少なくすることができる。 In particular, according to the invention according to claim 3 , it is possible to increase the number of temporary piers according to the progress of the renewal work, and by shortening the installation period of the temporary piers, it is possible to reduce the leasing fee for temporary materials. It is possible to minimize obstacles such as traffic under the road.

Claims (6)

離間して立設された2つの既設橋脚の間に構築される複数の鋼材が組み合わされた仮設橋脚の支持構造であって、
複数の横梁と、これらの複数の横梁上に設置された複数の桁材と、を備え、
前記横梁は、前記2つの既設橋脚の周囲をそれぞれ取り囲む一対の枠体間に架け渡されて接合されていること
を特徴とする仮設橋脚の支持構造。
A support structure for a temporary bridge pier constructed between two existing piers set apart from each other and combining a plurality of steel materials,
comprising a plurality of transverse beams and a plurality of girders installed on the plurality of transverse beams,
A support structure for a temporary bridge pier, wherein the horizontal beam is bridged between and joined to a pair of frames surrounding the two existing bridge piers.
前記一対の枠体は、それぞれ前記既設橋脚に沿って立設された複数の仮設支柱で下方から支持されていること
を特徴とする請求項1に記載の仮設橋脚の支持構造。
The support structure for a temporary pier according to claim 1, wherein the pair of frames are supported from below by a plurality of temporary pillars erected along the existing pier.
前記横梁は、地震動による前記2つの既設橋脚の応答スペクトルが同期するように前記一対の枠体と剛接合されていること
を特徴とする請求項1又は2に記載の仮設橋脚の支持構造。
The support structure for a temporary bridge pier according to claim 1 or 2, wherein the transverse beams are rigidly joined to the pair of frames so that the response spectra of the two existing piers due to seismic motion are synchronized.
離間して立設された既設橋脚が複数あり、それぞれの既設橋脚を取り囲む枠体がそれぞれ別体となってそれらの枠体が横梁で連結されていること
を特徴とする請求項1ないし3のいずれかに記載の仮設橋脚の支持構造。
There are a plurality of existing piers standing apart from each other, and frames surrounding each of the existing piers are separated from each other and are connected by cross beams. A support structure for a temporary bridge pier according to any one of the preceding claims.
既設橋梁の上部構造を取り替えて更新する橋梁上部構造の更新方法であって、
請求項1ないし4のいずれかに記載の仮設橋脚の支持構造を備えた仮設橋脚を、離間して立設された2つの既設橋脚間に構築した後、前記仮設橋脚上に架け替える新設の上部構造を載置すること
を特徴とする橋梁上部構造の更新方法。
A bridge superstructure renewal method for replacing and renewing a superstructure of an existing bridge, comprising:
After constructing a temporary pier provided with the temporary pier support structure according to any one of claims 1 to 4 between two existing piers erected at a distance, the upper part of the new construction to be replaced on the temporary pier A method for renewing a bridge superstructure, comprising placing the structure.
前記新設の上部構造は、プレキャスト製のPCa横梁を備え、上下線のそれぞれのPCa横梁同士を鋼殻を介して連結して前記仮設橋脚の上に載置し、前記2つの既設橋脚間に一時的に車線を設けて共用すること
を特徴とする請求項5に記載の橋梁上部構造の更新方法。
The new superstructure is equipped with precast PCa cross beams. The PCa cross beams of the upper and lower lines are connected to each other via steel shells and placed on the temporary piers. 6. The method for updating a bridge superstructure according to claim 5, wherein lanes are provided for common use.
JP2021131575A 2021-08-12 2021-08-12 Support structure of temporary piers and update method of bridge superstructure Active JP7108108B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2021131575A JP7108108B1 (en) 2021-08-12 2021-08-12 Support structure of temporary piers and update method of bridge superstructure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2021131575A JP7108108B1 (en) 2021-08-12 2021-08-12 Support structure of temporary piers and update method of bridge superstructure

Publications (2)

Publication Number Publication Date
JP7108108B1 JP7108108B1 (en) 2022-07-27
JP2023026012A true JP2023026012A (en) 2023-02-24

Family

ID=82607884

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2021131575A Active JP7108108B1 (en) 2021-08-12 2021-08-12 Support structure of temporary piers and update method of bridge superstructure

Country Status (1)

Country Link
JP (1) JP7108108B1 (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5729706A (en) * 1980-07-25 1982-02-17 Ishikawajima Harima Heavy Ind Long bridge having concrete vertical beam
JP2002339318A (en) * 2001-05-21 2002-11-27 Ohbayashi Corp Reinforcing method of underwater structure
JP2011058266A (en) * 2009-09-10 2011-03-24 West Japan Railway Co Temporary installation method of work stage for viaduct
KR101330145B1 (en) * 2013-03-13 2013-11-18 박종협 Longitudinal direction bridge structures carrying system and rapid replacing method of the bridge using the same
JP2021070916A (en) * 2019-10-29 2021-05-06 株式会社Ihiインフラシステム Carrying-in method of bridge article, carrying-out method of bridge article, removing method of bridge article, installation method thereof and lifting device for bridge article

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5729706A (en) * 1980-07-25 1982-02-17 Ishikawajima Harima Heavy Ind Long bridge having concrete vertical beam
JP2002339318A (en) * 2001-05-21 2002-11-27 Ohbayashi Corp Reinforcing method of underwater structure
JP2011058266A (en) * 2009-09-10 2011-03-24 West Japan Railway Co Temporary installation method of work stage for viaduct
KR101330145B1 (en) * 2013-03-13 2013-11-18 박종협 Longitudinal direction bridge structures carrying system and rapid replacing method of the bridge using the same
JP2021070916A (en) * 2019-10-29 2021-05-06 株式会社Ihiインフラシステム Carrying-in method of bridge article, carrying-out method of bridge article, removing method of bridge article, installation method thereof and lifting device for bridge article

Also Published As

Publication number Publication date
JP7108108B1 (en) 2022-07-27

Similar Documents

Publication Publication Date Title
US7478450B2 (en) Longitudinally offset bridge substructure support system
JP2004092078A (en) Structure and construction method for bridge
JP4310444B1 (en) Width expansion material for road bridges
JP2004137686A (en) Composite panel structure, panel bridge structure and construction method for continuous composite girder bridge
JP3844743B2 (en) Box girder bridge structure and its construction method
KR101242395B1 (en) Construction method for rhamen bridge
JP3701250B2 (en) Cable stayed bridge and its construction method
JP2734987B2 (en) Existing bridge repair method
JP3737475B2 (en) Box girder bridge structure and construction method
KR102163560B1 (en) Girdir and bridge having soundproof wall using the same
JP7108108B1 (en) Support structure of temporary piers and update method of bridge superstructure
JP2007211553A (en) Continuous viaduct
KR20040086653A (en) bridge and construction process with integral pier-type mixed abutment
JPH02503099A (en) Cable supported bridge and construction method
JP2018105091A (en) Method of constructing artificial ground on subbasement type road
JP2978903B1 (en) Viaduct
JP4477467B2 (en) Bridge structure and its replacement method
CN216238188U (en) High-speed railway platform beam structure
KR102207785B1 (en) PSC Decked bulb tee girder and construction method thereof
JPH03122399A (en) Method for constructing station portion by multiple serial shield construction method
JP2004300914A (en) Structure of bridge pier
JPH083921A (en) Repair method for existing bridge
CN111395204A (en) Prestressed cantilever support structure of large cantilever bent cap and construction method
JP4375788B2 (en) Construction method of upper-floor type suspension floor slab bridge
KR20030006681A (en) Apparatus and method for reinforcing a construction by enlarging its&#39; size

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20220401

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20220401

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20220510

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220620

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220712

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220714

R150 Certificate of patent or registration of utility model

Ref document number: 7108108

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350