JP2020201834A - Process control system - Google Patents

Process control system Download PDF

Info

Publication number
JP2020201834A
JP2020201834A JP2019109792A JP2019109792A JP2020201834A JP 2020201834 A JP2020201834 A JP 2020201834A JP 2019109792 A JP2019109792 A JP 2019109792A JP 2019109792 A JP2019109792 A JP 2019109792A JP 2020201834 A JP2020201834 A JP 2020201834A
Authority
JP
Japan
Prior art keywords
days
database
pattern
month
projects
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2019109792A
Other languages
Japanese (ja)
Inventor
啓太 三好
Keita Miyoshi
啓太 三好
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP2019109792A priority Critical patent/JP2020201834A/en
Publication of JP2020201834A publication Critical patent/JP2020201834A/en
Pending legal-status Critical Current

Links

Images

Abstract

To solve the problem that loss of business chances may be caused here and there by process delay or as construction cases of house building, reforming, etc., which are complicated in process control are left as they are.SOLUTION: A process control system comprises: an item processing part which manages progress states of respective processes of respective registered items, visualizes and presents the process states of the respective processes as a user attains access, and warms delays of respective processes; an actual result totaling processing part which totals and stores actual result monthly information by process patterns and process IDs based upon information in a progress management database in a progress total database; and a work predictive processing part which calculates the numbers of items for each next day by process IDs and a predicted value of the number of required days based upon past actual result information stored in the actual result total database, and stores them in a work prediction database.SELECTED DRAWING: Figure 1

Description

本発明は、工事を伴う工程管理システムに関する。 The present invention relates to a process control system that involves construction.

住宅の工事の工程管理を容易に行うための「物件規模や諸条件を考慮した適切な工期を設定し、かつ工期の補正や修正、他邸との調整も容易な工程管理システム」について、特開2005−267488号公報(特許文献1)に記載がある。 Special feature on "a process control system that sets an appropriate construction period in consideration of the size of the property and various conditions, and makes it easy to correct or correct the construction period and coordinate with other residences" to facilitate the process management of housing construction. It is described in Kai 2005-267488 (Patent Document 1).

特開2005−267488号公報Japanese Unexamined Patent Publication No. 2005-267488

住宅建築やリフォームビジネス等の工事では、取り扱う商材毎に工程や工数が異なり、工程管理が複雑な工事案件において、工程遅延や案件の放置による商機損失が散見される。 In construction such as housing construction and remodeling business, the process and man-hours differ depending on the products handled, and in construction projects where process control is complicated, business opportunity loss due to process delay or neglect of the project is scattered.

取り扱う商材が増えるほど、より工程管理が複雑になる為、案件毎の進捗状況を可視化した上で、適切なタイミングで各工程を進め、確実に商機獲得することが必要不可欠である。特許文献1では物件規模や諸条件を考慮した適切な工期を設定する点について記載されているが、人の判断で工期を設定することになり、設定した工期の妥当性という点は考慮されていない。また、工事に至るまでの打合せや契約に関する工程が考慮されていない。 As the number of products handled increases, process control becomes more complicated. Therefore, it is indispensable to visualize the progress status of each project, proceed with each process at an appropriate timing, and surely acquire business opportunities. Patent Document 1 describes the point of setting an appropriate construction period in consideration of the property scale and various conditions, but the construction period is set by human judgment, and the validity of the set construction period is taken into consideration. Absent. In addition, the process related to meetings and contracts leading up to construction is not taken into consideration.

そこで本発明では、案件登録から工完に至るすべての工程において、過去の実績から各工程の適切な処理タイミングを工事毎に算出し、進捗遅れが直観的に分かるように表現することで管理者から担当者へのフォローが手厚くできるようにして、工程遅延や機会損失の削減を目的とする。 Therefore, in the present invention, in all processes from project registration to completion of construction, the appropriate processing timing of each process is calculated for each construction from the past results, and the progress delay is expressed intuitively by the administrator. The purpose is to reduce process delays and opportunity losses by making it possible to follow up with the person in charge.

本発明の工程管理システムの好ましい例では、工事を伴う案件の各工程の進捗状況を管理する工程管理システムであって、進捗管理データベースと、実績集計データベースと、作業予測データベースとを有するデータベースサーバと、演算処理を行うアプリケーションサーバとを備え、進捗管理データベースは、各案件の各工程の進捗状況、実績日を保持し、実績集計データベースは、各案件の各工程を処理した月単位の実績を案件数と平均所要日数で集計した情報を保持し、作業予測データベースは、翌月の工程パターン・工程ID毎の案件数と、各工程に要する日数の予測値を保持し、アプリケーションサーバは、登録された各案件の各工程の進捗状況を管理し、ユーザからのアクセスに各工程の進捗状況を可視化して提示すると共に、各工程の遅延を警告する案件処理部と、進捗管理データベースの情報に基づき工程パターン・工程ID毎の月単位の実績情報を集計して実績集計データベースに格納する実績集計処理部と、実績集計データベースに格納する過去の実績情報に基づき、翌月の工程パターン・工程ID毎の案件数と、所要日数の予測値を算出して作業予測データベースへ格納する作業予測処理部とを備えて構成する。 A preferred example of the process management system of the present invention is a process management system that manages the progress of each process of a project involving construction work, and includes a database server having a progress management database, a performance aggregation database, and a work prediction database. , Equipped with an application server that performs arithmetic processing, the progress management database holds the progress status and actual date of each process of each matter, and the actual result aggregation database keeps the monthly actual results of processing each process of each matter. The work prediction database holds the information aggregated by the number and the average required days, the number of cases for each process pattern / process ID of the next month, and the predicted value of the number of days required for each process, and the application server is registered. The progress status of each process of each project is managed, the progress status of each process is visualized and presented to the access from the user, and the process is based on the information of the project processing department that warns of the delay of each process and the progress management database. Based on the performance totaling processing unit that aggregates monthly performance information for each pattern / process ID and stores it in the performance totaling database, and the past performance information stored in the performance totaling database, the matter for each process pattern / process ID of the next month It is configured to include a work prediction processing unit that calculates the number and the predicted value of the required number of days and stores it in the work prediction database.

また、本発明の他の特徴として、前記工程管理システムにおいて、アプリケーションサーバの前記作業予測処理部は、実績集計データベースに格納する過去の実績情報に基づき、工程パターン・工程ID毎に案件数と所要日数の線型回帰モデルを計算し、および直近の月の案件数と前年同月の案件数との比較より案件数の増加率を計算し、前記線型回帰モデル、および案件数の増加率に従って翌月の工程パターン・工程ID毎の案件数と、所要日数の予測値を算出して作業予測データベースへ格納することを特徴とする。 Further, as another feature of the present invention, in the process management system, the work prediction processing unit of the application server requires the number of cases for each process pattern / process ID based on the past performance information stored in the performance aggregation database. Calculate the linear regression model of the number of days, calculate the rate of increase in the number of projects by comparing the number of projects in the latest month with the number of projects in the same month of the previous year, and follow the linear regression model and the rate of increase in the number of projects in the next month. It is characterized in that the number of cases for each pattern / process ID and the predicted value of the required number of days are calculated and stored in the work prediction database.

過去の実績を基に各工程の処理タイミングを工事毎に定めることで、適切な処理タイミングを把握でき、管理者から担当者へのフォローがより容易になり、計画的に案件を遂行することが可能となる。 By determining the processing timing of each process for each construction based on past results, it is possible to grasp the appropriate processing timing, make it easier for the manager to follow up with the person in charge, and execute the project systematically. It will be possible.

本実施形態における工程管理システムの全体構成例を示す図である。It is a figure which shows the whole structure example of the process control system in this embodiment. 工事マスタのデータ構造例を示す図である。It is a figure which shows the data structure example of a construction master. 工程定義マスタのデータ構造例を示す図である。It is a figure which shows the data structure example of the process definition master. 進捗管理DBのデータ構造例を示す図である。It is a figure which shows the data structure example of the progress management DB. 実績集計DBのデータ構造例を示す図である。It is a figure which shows the data structure example of the performance totaling DB. 作業予測DBのデータ構造例を示す図である。It is a figure which shows the data structure example of the work prediction DB. 実績集計処理部、および作業予測処理部の処理フローである。This is the processing flow of the performance aggregation processing unit and the work prediction processing unit. 案件毎の進捗状況を一覧化した場合のイメージ図である。It is an image diagram when the progress status for each case is listed. 実績集計DBに格納する過去の実績情報に基づき、工程パターン・工程ID毎に案件数と所要日数の線型回帰モデルを計算する処理を説明する図である。It is a figure explaining the process of calculating the linear regression model of the number of cases and the required number of days for each process pattern / process ID based on the past performance information stored in the performance totaling DB. 各種サーバ、ユーザ端末の物理的な構成の例を示す図である。It is a figure which shows the example of the physical configuration of various servers and user terminals.

以下に本発明の実施形態について図面を用いて詳細に説明する。図1は、本実施形態における工程管理システム100の全体構成例を示す図である。 Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 is a diagram showing an overall configuration example of the process control system 100 according to the present embodiment.

図1に示すように本実施形態における工程管理システム100は、各種データを格納しているデータベースサーバ101と、演算処理を行うアプリケーションサーバ102と、各工程の進捗状態の入力、工程管理の処理結果の表示等を行うユーザインタフェースを提供するユーザ端末103と、スケジューリングされたジョブを実行するバッチサーバ104とがネットワーク105を介して通信可能に接続されている。 As shown in FIG. 1, the process management system 100 in the present embodiment includes a database server 101 that stores various data, an application server 102 that performs arithmetic processing, input of progress status of each process, and processing result of process management. The user terminal 103 that provides the user interface for displaying the data and the batch server 104 that executes the scheduled job are connected to each other so as to be able to communicate with each other via the network 105.

アプリケーションサーバ102は、演算処理部301で格納されたプログラムが実行されて、案件処理部401、実績集計処理部402、作業予測処理部403の各機能が実現される。
案件処理部401は、ユーザ端末103からのアクセスによって起動され、登録された各案件の各工程データを進捗管理DB203上で更新、管理して、ユーザの要求に応じて各案件の各工程の進捗状況をユーザインタフェース上に報告する。
実績集計処理部402は、月次処理として起動され、案件の進捗状況を実績として保持している進捗管理DB203を検索して、処理実行月に実績のある工程パターン・工程ID別案件数を実績集計DB204に格納する。
作業予測処理部403は、実績集計DB204に記録されている過去の実績情報より工程パターン・工程ID毎に処理した案件数と各工程の所要日数の相関関係を求め、翌月の案件数と所要日数を予測して、案件処理部401がユーザに対して工程の遅延を警告する警告開始相対日数を更新する。
In the application server 102, the program stored in the arithmetic processing unit 301 is executed, and the functions of the matter processing unit 401, the actual result aggregation processing unit 402, and the work prediction processing unit 403 are realized.
The matter processing unit 401 is activated by access from the user terminal 103, updates and manages each process data of each registered matter on the progress management DB 203, and progresses each process of each matter according to the user's request. Report the situation on the user interface.
The result totaling processing unit 402 is started as a monthly process, searches for the progress management DB 203 that holds the progress status of the matter as a result, and records the number of cases by process pattern / process ID that has a record in the process execution month. It is stored in the aggregation DB 204.
The work prediction processing unit 403 obtains the correlation between the number of cases processed for each process pattern / process ID and the required number of days for each process from the past actual result information recorded in the actual result totaling DB 204, and obtains the correlation between the number of cases and the required number of days for the next month. Is predicted, and the matter processing unit 401 updates the warning start relative number of days to warn the user of the process delay.

ユーザ端末103は、工程管理者、各工程の実施者が使用する端末であり、ユーザ操作により、案件登録をはじめとする案件を進める為の各種処理、各工程の進捗状態の入力、工程管理の処理結果の表示等を行う。ユーザ端末103は例えば、会社や工場内の、または個人のパーソナルコンピュータやサーバであり、複数台存在する。あるいはユーザ端末103は、スマートフォンやタブレット端末などの、通信機能を有する通信デバイスであってもよい。 The user terminal 103 is a terminal used by a process manager and an implementer of each process, and is used for various processes for advancing a project such as project registration, input of progress status of each process, and process control by user operation. Display the processing result, etc. The user terminal 103 is, for example, a personal computer or server in a company or factory, or an individual, and there are a plurality of user terminals 103. Alternatively, the user terminal 103 may be a communication device having a communication function, such as a smartphone or a tablet terminal.

ネットワーク105は、通信キャリアなどによって提供される無線ネットワークまたは有線ネットワークである。ネットワーク105は、個別の会社などが所有するネットワークを、ネットワーク105の一部に含んでもよく、複数種類のプロトコルを通過させるネットワークであってもよい。 The network 105 is a wireless network or a wired network provided by a communication carrier or the like. The network 105 may include a network owned by an individual company or the like as a part of the network 105, or may be a network through which a plurality of types of protocols are passed.

図2A乃至図2Eは、データベースサーバ101で保持する各データベースのデータ構造例を示す。 2A to 2E show an example of a data structure of each database held by the database server 101.

図2Aにデータ構造例を示す工事マスタ201は、予め定義してデータベースに登録しておき、工事を分類分けした工事分類を主キーとし、工事の基本情報として、工事を識別する為の工事分類、工事分類に対応する名称として工事名、工事分類と図2Bに示す工程パターンを紐付けるために工程パターンを保持している。図2Aに示す例では、フローリングはAという工事分類で識別され、フローリング工事を進めるにあたって必要となる工程は、工程定義マスタで工程パターン10として定義されている工程である。 The construction master 201 whose data structure example is shown in FIG. 2A is defined in advance and registered in the database, and the construction classification for classifying the construction is used as the primary key, and the construction classification for identifying the construction is used as the basic information of the construction. , The process name is held as a name corresponding to the construction classification, and the process pattern is held in order to link the construction classification with the process pattern shown in FIG. 2B. In the example shown in FIG. 2A, the flooring is identified by the construction classification A, and the process required to proceed with the flooring construction is the process defined as the process pattern 10 in the process definition master.

図2Bにデータ構造例を示す工程定義マスタ202は、各工事案件を進める上で必要となる工程を定義しており、工程有無をパターン化することで工程パターンとして定義する。各工程を識別する為の工程ID、工程IDに対応する名称として工程名を保持し、工程パターン・工程ID毎に対象外フラグ、警告要否フラグ、警告開始相対日数を定義する。 The process definition master 202, which shows an example of a data structure in FIG. 2B, defines a process required for advancing each construction project, and defines the process as a process pattern by patterning the presence or absence of the process. The process name is retained as the process ID for identifying each process and the name corresponding to the process ID, and the non-target flag, warning necessity flag, and warning start relative number of days are defined for each process pattern / process ID.

対象外フラグは工程パターン・工程IDに対応して処理対象の工程であるかを定義し、“0”であれば処理対象であり、“1”であれば処理対象外の工程を意味する。また、警告要否フラグで、該当する工程パターン・工程IDの工程において、警告表示をするかしないかを定義する。警告要否フラグが“0”であれば進捗遅れは管理せず、警告表示しないことになり、“1”にすることで対象の工程は警告表示対象となる。警告表示するにあたり、警告表示する為の基準値を警告開始相対日数として定義する。警告開始相対日数は、対象の工程で許容する所要日数を意味し、前工程の実績日から当日までの日数と比較することで警告表示する。 The non-target flag defines whether or not the process is a process target according to the process pattern / process ID. If it is "0", it means a process target, and if it is "1", it means a process that is not a process target. In addition, the warning necessity flag defines whether or not to display a warning in the process of the corresponding process pattern / process ID. If the warning necessity flag is "0", the progress delay is not managed and the warning is not displayed. By setting it to "1", the target process becomes the warning display target. When displaying a warning, the reference value for displaying the warning is defined as the relative number of days for warning start. The relative number of days for starting a warning means the required number of days allowed in the target process, and a warning is displayed by comparing with the number of days from the actual date of the previous process to the current day.

図2A、Bに示す例では、フローリング工事の作業工程は工程パターン10で定義される。現場確認依頼や現場確認は対象外フラグが“0”である為、処理対象として定義されていることになる。ただし、現場確認依頼は警告要否フラグが“0”である為、進捗遅れは管理しないが、現場確認は警告要否フラグが“1”である為、進捗が遅れていれば、警告表示することになる。警告表示するタイミングとしては、警告開始相対日数が“1”である為、前工程である現場確認依頼の実績日(終了日)の1日後に未処理の状態であれば、例えば点滅として遅延警告を行う。 In the example shown in FIGS. 2A and 2B, the work process of the flooring work is defined by the process pattern 10. Since the non-target flag is "0" for the site confirmation request and the site confirmation, it is defined as a processing target. However, since the warning necessity flag is "0" in the site confirmation request, the progress delay is not managed, but in the site confirmation, the warning necessity flag is "1", so if the progress is delayed, a warning is displayed. It will be. As for the timing to display the warning, since the relative number of days for warning start is "1", if it is in an unprocessed state one day after the actual date (end date) of the site confirmation request, which is the previous process, for example, a delay warning is displayed as blinking. I do.

図2Cにデータ構造例を示す進捗管理DB203は、ユーザがユーザ端末103から新たな工事を含む新規案件を登録する操作に従い、案件処理部401が、工事マスタ201と工程定義マスタ202の定義情報を基に、対象案件に必要となる工程情報を取得して新たなデータレコードを作成する。その後、該当案件のデータレコードには、案件処理部401が、ユーザ端末103からの報告などにより、実行した各工程の処理状態や実績日を保持する。 In the progress management DB 203 in which the data structure example is shown in FIG. 2C, the matter processing unit 401 sets the definition information of the construction master 201 and the process definition master 202 according to the operation of the user registering a new matter including new construction from the user terminal 103. Based on this, the process information required for the target project is acquired and a new data record is created. After that, in the data record of the corresponding matter, the matter processing unit 401 holds the processing state and the actual date of each executed process by reporting from the user terminal 103 or the like.

進捗管理DB203には、案件を識別する為の案件番号があり、案件番号に紐付く工事(1件の案件に複数の工事が含まれる場合がある。)の順番を連番として保持する。また、連番における具体的な工事を工事分類として保持し、工事分類に紐付く工程パターンを工程定義マスタ202から取得し、工程パターンとして保持する。
更に、各工程の進捗状況を保持するとともに、警告表示する為の基準日を管理日付(該当工程を管理開始する日付として前工程の実績日が入れられる。)として保持し、警告開始日付へ管理日付に工程定義マスタの警告開始相対日数を足し算した日付を保持する。
進捗管理DB203の予定日には、案件処理部401で必要に応じて入力した処理予定日を保持し(予定日はユーザが例えば顧客の希望日などをユーザ端末103から入力した日付などを登録して、ユーザへの提示画面に表示されるが、案件処理部401の処理では参照されない。)、実績日には案件処理部401にて該当工程IDに対応する処理を確定させた日付を保持する。
The progress management DB 203 has a project number for identifying the project, and holds the order of the works associated with the project number (a plurality of works may be included in one project) as a serial number. Further, the specific work in the serial number is held as the work classification, and the process pattern associated with the work classification is acquired from the process definition master 202 and held as the process pattern.
Furthermore, the progress status of each process is held, and the reference date for displaying the warning is held as the management date (the actual date of the previous process is entered as the date when the corresponding process is started to be managed) and managed to the warning start date. Holds the date obtained by adding the number of days relative to the warning start of the process definition master to the date.
In the scheduled date of the progress management DB 203, the scheduled processing date input by the matter processing unit 401 as necessary is retained (the scheduled date is registered as the date when the user inputs, for example, the customer's desired date from the user terminal 103, etc.). Although it is displayed on the presentation screen to the user, it is not referred to in the processing of the matter processing unit 401.) However, the actual date holds the date when the processing corresponding to the corresponding process ID is confirmed by the matter processing unit 401. ..

図2Cに示す例では、案件番号“0001”には工事が2つあり、1つ目がフローリング、2つ目がカーポートとなる。フローリングの工程パターンは“10”であり、工程ID“01010”である案件登録は、2018年01月01日に処理されたことを意味する。なお案件登録は最初の工程となる為、管理日付、警告開始日付、予定日には実績日と同じ値が入ることになる。 In the example shown in FIG. 2C, the project number "0001" has two works, the first is the flooring and the second is the carport. The flooring process pattern is "10", which means that the matter registration with the process ID "01010" was processed on January 01, 2018. Since the matter registration is the first process, the same values as the actual date will be entered in the management date, warning start date, and scheduled date.

工程管理システム100は、工事を伴う案件の各工程の進捗状況を見える化したシステムである。ユーザ端末103から指示を受けてアプリケーションサーバ102の案件処理部401を実行する。各案件に対するユーザからの指示に応じた処理を案件処理部401で実行し、処理結果をユーザ端末103に表示すると共に、その処理実績を進捗管理DB203へ格納する。進捗管理DB203へは処理実績として、処理日付および各工程の状態が保持される。 The process control system 100 is a system that visualizes the progress of each process of a project involving construction. Upon receiving an instruction from the user terminal 103, the matter processing unit 401 of the application server 102 is executed. The matter processing unit 401 executes the processing according to the instruction from the user for each matter, displays the processing result on the user terminal 103, and stores the processing result in the progress management DB 203. The processing date and the state of each process are stored in the progress management DB 203 as the processing results.

各工程の状態として、「処理対象外」、「未処理」、「処理中」、「処理済」がある。「処理対象外」とは、処理する必要がない工程を意味し、図2Bに示す工程定義マスタにて定義する。「未処理」は、前工程が完了し、次に処理すべき工程の状態である。「処理中」は、処理対象データの一部が処理済もしくは、一時保存された状態である。「処理済」は、処理すべき対象データがすべて処理済となった状態を示す。 As the state of each process, there are "not processed", "unprocessed", "processing", and "processed". “Not subject to processing” means a process that does not need to be processed, and is defined by the process definition master shown in FIG. 2B. “Unprocessed” is a state in which the previous process is completed and the process to be processed next. "Processing" is a state in which a part of the data to be processed has been processed or temporarily saved. "Processed" indicates a state in which all the target data to be processed has been processed.

このように、進捗管理DB203へ格納されたデータは、ユーザ端末103からアプリケーションサーバ102へ出力指示が送られた結果、アプリケーションサーバ102を介して対象案件のデータを取得し、ユーザ端末へ返される。ユーザ端末103はアプリケーションサーバ102から受信したデータを編集し、対象案件の工程管理表として表示する。 As a result of the output instruction being sent from the user terminal 103 to the application server 102, the data stored in the progress management DB 203 acquires the data of the target matter via the application server 102 and is returned to the user terminal. The user terminal 103 edits the data received from the application server 102 and displays it as a process control table of the target matter.

図4に工程管理表の表示例を示す。図4に示す工程管理表の表示例では、進捗管理DB203で保持している各工程の進捗状況と実績日を用いて進捗状況を可視化しており、案件に紐付く工事毎に進捗状況を示す。各工程の進捗状況を四角のマーク及び実績日で表現しており、△(日付無)は「未処理」、△(日付有)は「処理中」、完(日付有)は「処理済」、「−」(ハイフン)は「処理対象外」、空白は未到達工程を意味する。 FIG. 4 shows a display example of the process control table. In the display example of the process control table shown in FIG. 4, the progress status is visualized using the progress status and the actual date of each process held in the progress management DB 203, and the progress status is shown for each work linked to the project. .. The progress of each process is represented by a square mark and the actual date. △ (without date) is "unprocessed", △ (with date) is "processed", and completed (with date) is "processed". , "-" (Hyphen) means "not subject to processing", and blank means unreached process.

図4に示す表示例におけるフローリングであれば、案件登録は完了しており、現場確認や現場確認依頼は作業対象外である為、次に実施すべき処理は見積書作成となる。また、進捗管理DB203の各工程における進捗状況が処理済以外であり、現在の運用日付が進捗管理DB203の警告開始日付を過ぎている場合は、対象となる工程が予定より遅れていると判断し、遅れている工程を例えば点滅で表現する。 In the case of the flooring in the display example shown in FIG. 4, since the matter registration has been completed and the site confirmation and the site confirmation request are not subject to work, the next process to be performed is to create a quotation. Further, if the progress status in each process of the progress management DB 203 is other than processed and the current operation date is past the warning start date of the progress management DB 203, it is determined that the target process is behind schedule. , The delayed process is represented by blinking, for example.

このように工程管理システム100は各工程の進捗状況に遅れが生じた際に、遅れている工程に対して警告表示をする機能を備える。本実施例では、警告表示機能において、警告表示する為の基準となる図2Bに示す工程定義マスタの警告開始相対日数を過去実績を基に算出することが特徴である。このような処理を行う工程管理システム100により、複数の部署を跨って推進する各案件の進捗状況を共有することが可能となり、各部署で各工程の処理状況を把握することができ、互いにフォローし合うことで着実に案件を推進することができる。 As described above, the process control system 100 has a function of displaying a warning for the delayed process when the progress of each process is delayed. The feature of this embodiment is that the warning display function calculates the relative number of days for warning start of the process definition master shown in FIG. 2B, which is a reference for displaying a warning, based on past results. The process control system 100 that performs such processing makes it possible to share the progress status of each project promoted across a plurality of departments, and each department can grasp the processing status of each process and follow each other. By interacting with each other, we can steadily promote the project.

図2Dにデータ構造例を示す実績集計DB204は、進捗管理DB203を基に実績集計処理部402で単位月あたりに各工程で処理した案件数及び所要日数の平均値を算出し、集計した情報を保持する。
図2Dに示す例では、2016年01月と、2016年02月に全工程における処理した案件数及び所要日数の平均値を算出して、各工程ごとに集計した情報を記録している。例えば、2016年01月の工程パターン“10”の工程ID“02010”(現場確認)を集計処理した案件数は160件であり、平均して現場確認依頼してから5日間要したことを意味している。
また、図2Dに示す例では、工程パターン“10”の各工程IDの案件数が順次減っていくのは、案件登録はしたけれど、顧客の意向、その他の理由で、打合せまで行く前の工程で打ち切られた案件が発生するため、または前月からの繰り越しなども存在するためである。
The actual result aggregation DB 204 showing an example of the data structure in FIG. 2D calculates the average value of the number of cases processed in each process and the required number of days per unit month by the actual result aggregation processing unit 402 based on the progress management DB 203, and aggregates the information. Hold.
In the example shown in FIG. 2D, the average value of the number of cases processed and the required number of days in all the processes in January 2016 and February 2016 is calculated, and the information aggregated for each process is recorded. For example, in January 2016, the number of cases for which the process ID “02010” (site confirmation) of the process pattern “10” was aggregated was 160, which means that it took 5 days after requesting the site confirmation on average. doing.
Further, in the example shown in FIG. 2D, the number of cases of each process ID of the process pattern "10" gradually decreases because the case is registered but the process before going to the meeting due to the customer's intention or other reasons. This is because there will be cases that have been terminated in, or there will be carry-overs from the previous month.

図2Eにデータ構造例を示す作業予測DB205は、実績集計DB204に保持する実績情報を基に作業予測処理部403で算出する翌月の各工程で処理する案件数及び所要日数の予測値を保持する。
図2Eに示す例では、年月“000000”で示す工程パターン“10”の工程ID“02010”(現場確認)のデータは、実績集計DB204に保持する過去の実績情報を基に算出した結果、処理案件数が100件の場合は所要日数が4日であるが、処理する案件数が150件になった場合は所要日数が5日、処理する案件数が200件になった場合は所要日数が7日かかることを意味する。そのような相関関係の結果を踏まえ、2016年02月における工程パターン“10”の工程ID“02010”(現場確認)は206件の案件を処理することが予測され、それらの所要日数は平均で7日かかることを予測していることを示す。
The work prediction DB 205 showing an example of the data structure in FIG. 2E holds the predicted values of the number of cases to be processed and the required number of days to be processed in each process of the next month calculated by the work prediction processing unit 403 based on the performance information held in the performance totaling DB 204. ..
In the example shown in FIG. 2E, the data of the process ID “02010” (site confirmation) of the process pattern “10” indicated by the year and month “000000” is calculated based on the past actual information held in the actual result aggregation DB 204. If the number of cases to be processed is 100, the required number of days is 4 days, but if the number of cases to be processed is 150, the required number of days is 5 days, and if the number of cases to be processed is 200, the required number of days is required. Means that it takes 7 days. Based on the results of such a correlation, it is predicted that the process ID "02010" (site confirmation) of the process pattern "10" in February 2016 will process 206 cases, and the required number of days for them is on average. Indicates that it is expected to take 7 days.

図3に本実施例の特徴である作業予測DB205のデータを生成するプロセスである実績集計処理部402および案件作業予測処理部403の処理フローを示す。 FIG. 3 shows the processing flow of the performance aggregation processing unit 402 and the matter work prediction processing unit 403, which are the processes for generating the data of the work prediction DB 205, which is a feature of this embodiment.

ステップS101において、作業予測DB205に翌月の各工程で処理する案件数及び所要日数の予測値を生成する為に、実績集計処理部402が月次処理(処理実行月の月末最終日の夜に当月の実績情報の集計を行う)としてバッチサーバ104へ処理指示を発して、進捗管理DB203の情報を基に実績集計DB204に当月の実績情報を生成する。 In step S101, in order to generate the predicted value of the number of cases to be processed and the required number of days to be processed in each process of the next month in the work prediction DB 205, the performance aggregation processing unit 402 performs monthly processing (the current month on the night of the last day of the end of the processing execution month). A processing instruction is issued to the batch server 104 to generate the actual information of the current month in the actual result totaling DB 204 based on the information of the progress management DB 203.

実績集計処理S101では、案件の進捗状況を実績として保持している進捗管理DB203の実績日を基に集計期間内に処理した案件数を工程パターン・工程ID毎に集計し、実績集計DB204の案件数に集計結果の工程パターン・工程ID別案件数を格納する。また、前工程IDと当該工程IDの実績日の差分を算出し、集計期間内において、当該工程パターン・工程IDにおいて要した日数の平均値を算出し、実績集計DB204の該当工程パターン・工程IDの所要日数に算出した平均所要日数を格納する。 In the actual result totaling process S101, the number of cases processed within the totaling period is totaled for each process pattern / process ID based on the actual date of the progress management DB 203 that holds the progress status of the matter as a result, and the case of the actual result totaling DB 204. The number of cases by process pattern / process ID of the aggregation result is stored in the number. In addition, the difference between the previous process ID and the actual date of the process ID is calculated, the average value of the number of days required for the process pattern / process ID is calculated within the aggregation period, and the corresponding process pattern / process ID of the actual aggregation DB 204 is calculated. Store the calculated average required days in the required days of.

生成された実績集計DB204の当月の実績情報、および記録されている過去の実績情報を基に、作業予測処理部403において、以下のステップの処理により、翌月の各工程パターン・工程IDごとの案件数、および所要日数を予測して、作業予測DB205に格納する。 Based on the current month's performance information of the generated performance aggregation DB 204 and the recorded past performance information, the work prediction processing unit 403 processes the following steps to create a matter for each process pattern / process ID of the next month. The number and the required number of days are predicted and stored in the work prediction DB 205.

ステップS201において、作業予測処理部403が実績集計DB204に記録されている実績情報の過去データより適当なデータを選択して集計し、工程パターン・工程ID毎に処理した案件数と各工程の所要日数の相関関係を算出する。 In step S201, the work prediction processing unit 403 selects and aggregates appropriate data from the past data of the actual information recorded in the actual result aggregation DB 204, aggregates the data, processes the number of cases for each process pattern / process ID, and requires each process. Calculate the correlation of the number of days.

例えば、ある工程パターン・工程IDの業務、作業を実施する担当者は、当然、他の工程パターン・工程IDの業務、作業も兼務していることになるが、各種の案件が混在して受注する住宅建築やリフォームビジネス等の工事案件において、担当者の総数に大きな変更が無ければ、概略、ある工程パターン・工程IDの業務、作業に振り分けられる担当者の最大工数は均一になると予測できる。 For example, the person in charge of carrying out the work and work of a certain process pattern / process ID naturally also has the work and work of another process pattern / process ID, but various projects are mixed and ordered. If there is no major change in the total number of persons in charge in construction projects such as housing construction and remodeling business, it can be predicted that the maximum number of steps of persons in charge assigned to the outline, the work of a certain process pattern / process ID, and the work will be uniform.

そのような条件において、図5(A)に示すのは、実績集計DB204に記録されている過去の実績情報の中で、例えば担当者の総数がほぼ同じで、工程パターンが10、工程IDが02010(現場確認)の工程に振り分けられる担当者の最大工数が均一と見なせる2016年1月から2017年12月までの実績情報の例である。これらのデータを見ると、案件数が多くなると、1件の案件を処理する所要日数が増えることが分かる。これは、処理すべき案件数が多いと、着手が遅れ、待ち時間が増えることに因ります。 Under such conditions, FIG. 5A shows, in the past performance information recorded in the performance tabulation DB 204, for example, the total number of persons in charge is almost the same, the process pattern is 10, and the process ID is. This is an example of actual information from January 2016 to December 2017, where the maximum man-hours assigned to the process of 02010 (site confirmation) can be regarded as uniform. Looking at these data, it can be seen that as the number of cases increases, the number of days required to process one case increases. This is because if the number of cases to be processed is large, the start will be delayed and the waiting time will increase.

図5(B)に、図5(A)に示す実績集計DB204の実績情報の案件数と所要日数をプロットした散布図を示す。案件数と所要日数は正の相関関係が見られる。案件数xと所要日数yの間の相関係数rxyは数式(1)で求められる。 FIG. 5B shows a scatter plot in which the number of projects and the required number of days of the actual information of the actual result aggregation DB 204 shown in FIG. 5A are plotted. There is a positive correlation between the number of projects and the number of days required. The correlation coefficient r xy between the number of cases x i and the required number of days y i can be obtained by the mathematical formula (1).

Figure 2020201834
Figure 2020201834

案件数xと所要日数yの間の相関係数rxyは0.933となり、強い直線関係が見られるので、所要日数yが案件数xの回帰関数y=ax+bで近似される線型モデルを考える。 The correlation coefficient r xy between the number of projects x i and the required number of days y i is 0.933, and a strong linear relationship can be seen. Therefore, a linear model in which the required number of days y i is approximated by the regression function y = ax + b of the number of projects x i. think of.

ここで、回帰係数a、切片bは、それぞれ数式(2)、数式(3)で求められる。 Here, the regression coefficient a and the intercept b are obtained by the mathematical formulas (2) and (3), respectively.

Figure 2020201834
Figure 2020201834

Figure 2020201834
Figure 2020201834

図5(C)に示すように、実績集計DB204に記録されている過去の実績情報より、工程パターン・工程ID毎に案件数xと所要日数yの線型回帰モデルを計算する。 As shown in FIG. 5C, a linear regression model of the number of cases x i and the required number of days y i is calculated for each process pattern / process ID from the past actual information recorded in the actual result aggregation DB 204.

算出した線型回帰モデルに従って、図5(D)に示すように、作業予測DB205へ、年月を「000000」として、工程パターン・工程ID毎に案件数を50件単位に増分させた案件数と工程の所要時間の相関関係の予測値を格納する。 According to the calculated linear regression model, as shown in FIG. 5D, the number of cases is incremented by 50 for each process pattern / process ID in the work prediction DB205 with the year and month set to "000000". Stores the predicted value of the correlation of the time required for the process.

ステップS202において、作業予測処理部403が実績集計DB204に記録されている実績情報を読み出し、処理実行月(当月)を含めて直近3カ月(処理実行月、1カ月前、2カ月前)の各工程パターン・工程ID毎の案件数と、前年同月の各工程パターン・工程ID毎の案件数をそれぞれ比較して、各月毎の前年からの案件数の増加率を算出して、直近3カ月の案件数の増加率の平均を各工程パターン・工程ID毎の案件数の前年からの増加率とする前年比算出処理を実行する。 In step S202, the work prediction processing unit 403 reads out the actual information recorded in the actual result totaling DB 204, and each of the latest 3 months (processing execution month, 1 month ago, 2 months ago) including the processing execution month (current month). Compare the number of projects for each process pattern / process ID with the number of projects for each process pattern / process ID in the same month of the previous year, and calculate the rate of increase in the number of projects for each month from the previous year for the last 3 months. The year-on-year calculation process is executed with the average rate of increase in the number of projects in each process pattern and process ID as the rate of increase from the previous year in the number of projects.

ステップS203において、作業予測処理部403がS202で算出した前年からの増加率を利用し、処理実行月(当月)の翌月の前年同月における工程パターン・工程ID毎の案件数に算出した増加率を掛算することで、直近の案件数推移を基に処理実行月の翌月の工程パターン・工程ID毎の予測案件数を算出する。 In step S203, the work prediction processing unit 403 uses the rate of increase from the previous year calculated in S202 to calculate the rate of increase for each process pattern / process ID in the same month of the previous year of the month following the processing execution month (current month). By multiplying, the predicted number of projects for each process pattern / process ID of the month following the processing execution month is calculated based on the latest transition of the number of projects.

ステップS204において、作業予測処理部403がS203で算出した翌月の工程パターン・工程ID毎の予測案件数を用いて、作業予測DB205に格納されている年月が「000000」で、同一工程パターン・同一工程IDの案件数が50ごとに増加するデータと比較して、前記予測案件数と一致する、または前記予測案件数を間に挟む両案件数を持つデータレコードの所要日数を読み出して、前記予測案件数を間に挟む両案件数との比例配分に応じて、処理実行月の翌月の該当工程パターン・工程IDの予測所要日数を算出する。 例えば、図2Eの作業予測DB205において、年月“201601”、工程パターン“10”、工程ID“02010”(現場確認)の予測案件数が“194”とS203で算出されたとすれば、S204において、年月“000000”、工程パターン“10”、工程ID“02010”、案件数“150”、所要日数“5”のデータレコードと、年月“000000”、工程パターン“10”、工程ID“02010”、案件数“200”、所要日数“7”のデータレコードが参照されて、予測案件数“194”が、案件数“150”と案件数“200”の間に挟まれた比例配分に応じて、処理実行月の翌月の該当工程パターン・工程IDの予測所要日数を“7”と算出する。 In step S204, the year and month stored in the work prediction DB 205 is "000000" using the process pattern of the next month calculated by the work prediction processing unit 403 in S203 and the number of predicted cases for each process ID, and the same process pattern. Compared with the data in which the number of cases with the same process ID increases every 50, the required number of days of the data record that matches the predicted number of cases or has both cases with the predicted number of cases in between is read out and described above. The number of days required for forecasting the corresponding process pattern / process ID in the month following the processing execution month is calculated according to the proportional distribution with the number of both projects with the predicted number of projects in between. For example, in the work prediction DB 205 of FIG. 2E, if the number of predicted cases of the year / month “201601”, the process pattern “10”, and the process ID “02010” (site confirmation) is calculated as “194” in S203, in S204. , Year / month "000000", process pattern "10", process ID "02010", number of projects "150", required number of days "5" and year / month "000000", process pattern "10", process ID " The data records of "02010", the number of cases "200", and the required number of days "7" are referred to, and the predicted number of cases "194" is proportionally distributed between the number of cases "150" and the number of cases "200". Accordingly, the predicted required number of days for the corresponding process pattern / process ID in the month following the processing execution month is calculated as “7”.

以上のように、翌月案件数予測処理S203及び所要日数算出処理S204により算出した予測値である処理実行月(当月)の翌月における工程パターン・工程ID毎の案件数及び所要日数を作業予測DB205へ翌月分のデータとして格納する。 As described above, the number of projects and the required number of days for each process pattern / process ID in the month following the processing execution month (current month), which is the predicted value calculated by the next month number of projects prediction process S203 and the required number of days calculation process S204, are sent to the work prediction DB 205. Store as data for the next month.

ステップS205において、作業予測処理部403が、作業予測DB205へ格納した処理実行月の翌月の工程パターン・工程ID毎における所要日数を工程定義マスタ202の該当工程パターン・工程IDに対応した警告開始相対日数の欄へ格納する。 In step S205, the work prediction processing unit 403 sets the required number of days for each process pattern / process ID of the month following the processing execution month stored in the work prediction DB 205 as a warning start relative corresponding to the corresponding process pattern / process ID of the process definition master 202. Store in the number of days column.

翌月において、案件処理部401は、各案件の各工程の進捗遅れの管理を、更新された工程定義マスタ202の警告開始相対日数の値に基づいて実行する。 In the next month, the matter processing unit 401 manages the progress delay of each process of each matter based on the value of the number of days relative to the warning start of the updated process definition master 202.

以上、本実施形態について具体的に説明したが、本実施形態によれば、過去の実績から案件数や工事に応じた所要日数を予測することで、各工事における各工程の適切な処理タイミングを把握することが可能となり、管理者から担当者へのフォローが容易となる。また、予測値があることで関係部署および顧客との調整もスムーズに行え、工程遅延や案件の放置による商機損失を削減することができると考える。 The present embodiment has been specifically described above, but according to the present embodiment, the appropriate processing timing of each process in each construction can be determined by predicting the number of projects and the required number of days according to the construction from the past results. It becomes possible to grasp, and it becomes easy for the manager to follow up with the person in charge. In addition, it is thought that the forecast value makes it possible to smoothly coordinate with related departments and customers, and reduce business opportunity loss due to process delays and neglect of projects.

最後に、図6は、図1で示したデータベースサーバ101、アプリケーションサーバ102、ユーザ端末103、バッチサーバ104の物理的な構成を示す図である。本実施例ではこれらのサーバ(またはユーザ端末)には、プロセッサ(CPU)601、メモリ602、補助記憶装置603、及び通信インターフェース(通信I/F)604を有する計算機600が用いられる。この計算機は一例として、パーソナルコンピュータ(PC)等の汎用的な計算機でよい。計算機600はまた、入力インターフェース(入力I/F)605及び出力インターフェース(出力I/F)608を有してもよい。入力インターフェース605は、キーボード606やマウス607などが接続され、オペレータからの入力を受けるインターフェースである。出力インターフェース608は、ディスプレイ装置609やプリンタなどが接続され、プログラムの実行結果をオペレータが視認可能な形式で出力するインターフェースである。 Finally, FIG. 6 is a diagram showing the physical configurations of the database server 101, the application server 102, the user terminal 103, and the batch server 104 shown in FIG. In this embodiment, as these servers (or user terminals), a computer 600 having a processor (CPU) 601, a memory 602, an auxiliary storage device 603, and a communication interface (communication I / F) 604 is used. As an example, this computer may be a general-purpose computer such as a personal computer (PC). The computer 600 may also have an input interface (input I / F) 605 and an output interface (output I / F) 608. The input interface 605 is an interface to which a keyboard 606, a mouse 607, or the like is connected and receives input from an operator. The output interface 608 is an interface to which a display device 609, a printer, or the like is connected, and outputs a program execution result in a format that can be visually recognized by an operator.

本実施例では、これらのサーバがそれぞれ物理的に異なる計算機である例を説明する。ただし必ずしもこれらのサーバが、異なる計算機である必要はなく、上で述べたいくつかのサーバが有する機能部が、単一の計算機上に実装されていてもよい。 In this embodiment, an example in which these servers are physically different computers will be described. However, these servers do not necessarily have to be different computers, and the functional parts of some of the servers described above may be implemented on a single computer.

100・・・工程管理システム、101・・・データベースサーバ、102・・・アプリケーションサーバ、103・・・ユーザ端末、104・・・バッチサーバ、105・・・ネットワーク、201・・・工事マスタ、202・・・工程定義マスタ、203・・・進捗管理DB、204・・・実績集計DB、205・・・作業予測DB、301・・・演算処理部、401・・・案件処理部、402・・・実績集計処理部、403・・・作業予測処理部、600・・・計算機、601・・・プロセッサ(CPU)、602・・・メモリ、603・・・補助記憶装置、604・・・通信インターフェース(通信I/F)、605・・・入力インターフェース(入力I/F)、606・・・キーボード、607・・・マウス、608・・・出力インターフェース(出力I/F)、609・・・ディスプレイ装置。 100 ... Process management system, 101 ... Database server, 102 ... Application server, 103 ... User terminal, 104 ... Batch server, 105 ... Network, 201 ... Construction master, 202・ ・ ・ Process definition master, 203 ・ ・ ・ Progress management DB, 204 ・ ・ ・ Achievement totaling DB, 205 ・ ・ ・ Work prediction DB, 301 ・ ・ ・ Calculation processing unit, 401 ・ ・ ・ Item processing department, 402 ・ ・-Achievement aggregation processing unit, 403 ... Work prediction processing unit, 600 ... Computer, 601 ... Processor (CPU), 602 ... Memory, 603 ... Auxiliary storage device, 604 ... Communication interface (Communication I / F), 605 ... Input interface (Input I / F), 606 ... Keyboard, 607 ... Mouse, 608 ... Output interface (Output I / F), 609 ... Display apparatus.

Claims (6)

工事を伴う案件の各工程の進捗状況を管理する工程管理システムであって、
進捗管理データベースと、実績集計データベースと、作業予測データベースとを有するデータベースサーバと、
演算処理を行うアプリケーションサーバと、
を備え、
進捗管理データベースは、各案件の各工程の進捗状況、実績日を保持し、
実績集計データベースは、各案件の各工程を処理した月単位の実績を案件数と平均所要日数で集計した情報を保持し、
作業予測データベースは、翌月の工程パターン・工程ID毎の案件数と、各工程に要する日数の予測値を保持し、
アプリケーションサーバは、
登録された各案件の各工程の進捗状況を管理し、ユーザからのアクセスに各工程の進捗状況を可視化して提示すると共に、各工程の遅延を警告する案件処理部と、
進捗管理データベースの情報に基づき工程パターン・工程ID毎の月単位の実績情報を集計して実績集計データベースに格納する実績集計処理部と、
実績集計データベースに格納する過去の実績情報に基づき、翌月の工程パターン・工程ID毎の案件数と、所要日数の予測値を算出して作業予測データベースへ格納する作業予測処理部と、
を備えることを特徴とする工程管理システム。
It is a process control system that manages the progress of each process of a project that involves construction.
A database server having a progress management database, a performance aggregation database, and a work prediction database,
An application server that performs arithmetic processing and
With
The progress management database keeps the progress status and actual date of each process of each project,
The performance aggregation database holds information that aggregates the monthly results of processing each process of each project by the number of projects and the average required number of days.
The work prediction database holds the number of cases for each process pattern / process ID of the next month and the predicted value of the number of days required for each process.
The application server
The matter processing department that manages the progress status of each process of each registered matter, visualizes and presents the progress status of each process to the access from the user, and warns of the delay of each process.
A performance totaling processing unit that aggregates monthly performance information for each process pattern / process ID based on the information in the progress management database and stores it in the performance totaling database.
Based on the past performance information stored in the performance aggregation database, the work prediction processing unit that calculates the number of projects for each process pattern / process ID of the next month and the predicted value of the required number of days and stores it in the work prediction database.
A process control system characterized by being equipped with.
アプリケーションサーバの前記作業予測処理部は、
実績集計データベースに格納する過去の実績情報に基づき、工程パターン・工程ID毎に案件数と所要日数の線型回帰モデルを計算し、および直近の月の案件数と前年同月の案件数との比較より案件数の増加率を計算し、前記線型回帰モデル、および案件数の増加率に従って翌月の工程パターン・工程ID毎の案件数と、所要日数の予測値を算出して作業予測データベースへ格納することを特徴とする請求項1に記載の工程管理システム。
The work prediction processing unit of the application server
Based on the past performance information stored in the performance summary database, calculate a linear regression model of the number of cases and the required number of days for each process pattern / process ID, and compare the number of cases in the latest month with the number of cases in the same month of the previous year. Calculate the rate of increase in the number of projects, calculate the number of projects for each process pattern / process ID of the next month and the predicted value of the required number of days according to the linear regression model and the rate of increase in the number of projects, and store them in the work forecast database. The process control system according to claim 1.
データベースサーバは更に、工事に対応する工程パターン・工程ID毎に警告開始相対日数のデータを保持する工程定義マスタを有し、
前記作業予測処理部は、翌月の工程パターン・工程ID毎の案件数と、所要日数の予測値を算出した際に、工程パターン・工程ID毎の所要日数により、工程定義マスタの該当工程の警告開始相対日数を更新することを特徴とする請求項1に記載の工程管理システム。
The database server also has a process definition master that holds data on the relative number of days for warning start for each process pattern / process ID corresponding to construction.
When the work prediction processing unit calculates the number of cases for each process pattern / process ID of the next month and the predicted value of the required number of days, the work prediction processing unit warns of the corresponding process of the process definition master based on the required number of days for each process pattern / process ID. The process control system according to claim 1, wherein the relative start days are updated.
前記案件処理部は、各案件の各工程の進捗状況を管理して、前工程の実績日より前記工程定義マスタの警告開始相対日数が経過後に未処理の状態である工程がある場合には、ユーザ端末へ遅延警告を表示することを特徴とする請求項3に記載の工程管理システム。 The matter processing unit manages the progress of each process of each matter, and if there is a process that is in an unprocessed state after the relative number of days for warning start of the process definition master has elapsed from the actual date of the previous process, The process control system according to claim 3, wherein a delay warning is displayed on the user terminal. 前記作業予測処理部が実績集計データベースに格納する過去の実績情報に基づき、直近の月の案件数と前年同月の案件数との比較より案件数の増加率を計算する処理は、処理実行月を含めて直近3カ月(処理実行月、1カ月前、2カ月前)の各工程・工程ID毎の案件数と、前年同月の各工程パターン・工程ID毎の案件数をそれぞれ比較して、各月毎の前年からの案件数の増加率を算出して、直近3カ月の案件数の増加率の平均を各工程パターン・工程ID毎の案件数の前年からの増加率とする処理であることを特徴とする請求項2に記載の工程管理システム。 Based on the past performance information stored in the performance aggregation database by the work prediction processing unit, the process of calculating the increase rate of the number of cases by comparing the number of cases in the latest month with the number of cases in the same month of the previous year is the processing execution month. Including, compare the number of projects for each process / process ID in the last 3 months (processing execution month, 1 month ago, 2 months ago) with the number of projects for each process pattern / process ID in the same month of the previous year. It is a process that calculates the monthly increase rate of the number of projects from the previous year and sets the average of the increase rate of the number of projects in the last 3 months as the increase rate of the number of projects for each process pattern / process ID from the previous year. 2. The process control system according to claim 2. アプリケーションサーバの前記実績集計処理部は、
進捗管理データベースの各案件の各工程の進捗情報に基づき、集計期間内に処理した案件数を工程パターン・工程ID毎に集計し、および前工程IDと当該工程IDの実績日の差分を算出し、集計期間内において、当該工程パターン・工程IDにおいて要した日数の平均値を算出し、実績集計データベースの月単位の工程パターン・工程ID毎の案件数と所要日数に格納することを特徴とする請求項1に記載の工程管理システム。
The performance aggregation processing unit of the application server
Based on the progress information of each process of each project in the progress management database, the number of projects processed within the aggregation period is aggregated for each process pattern / process ID, and the difference between the previous process ID and the actual date of the process ID is calculated. It is a feature that the average value of the number of days required for the process pattern / process ID is calculated within the aggregation period and stored in the number of cases and the required number of days for each monthly process pattern / process ID of the actual aggregation database. The process control system according to claim 1.
JP2019109792A 2019-06-12 2019-06-12 Process control system Pending JP2020201834A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2019109792A JP2020201834A (en) 2019-06-12 2019-06-12 Process control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019109792A JP2020201834A (en) 2019-06-12 2019-06-12 Process control system

Publications (1)

Publication Number Publication Date
JP2020201834A true JP2020201834A (en) 2020-12-17

Family

ID=73742212

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019109792A Pending JP2020201834A (en) 2019-06-12 2019-06-12 Process control system

Country Status (1)

Country Link
JP (1) JP2020201834A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2024034060A1 (en) * 2022-08-10 2024-02-15 三菱電機ビルソリューションズ株式会社 Construction management system and construction management method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2024034060A1 (en) * 2022-08-10 2024-02-15 三菱電機ビルソリューションズ株式会社 Construction management system and construction management method

Similar Documents

Publication Publication Date Title
US20200104169A1 (en) Systems and methods of a production environment tool
JP2011134268A (en) Apparatus and method for processing information, and computer program
JP2017162044A (en) Production planning device, production planning method and production planning program
US20140344181A1 (en) Construction trade building information management system, software and method
US20180365608A1 (en) Quantitive time estimation systems and methods of project management systems
JP2014191716A (en) Duty management support system, duty management support device and duty management support method
JP2020201834A (en) Process control system
US20230229989A1 (en) Punch item worker interface
Stadnicka et al. Development of a rule base and algorithm for a quotation preparation process: a case study with a VSM approach
US11481702B1 (en) Worksite information management system
US11086585B2 (en) Information processing device, information processing method and storage medium
Zhang et al. Scheduling with compressible and stochastic release dates
CN111191999B (en) Product research and development management method, device, computer equipment and storage medium
JP7029993B2 (en) Store-specific productivity evaluation system, store-specific productivity evaluation method, and store-specific productivity evaluation program
JP2021125264A (en) Information processing device
JP6626327B2 (en) Gantt chart generation program, Gantt chart generation device, and Gantt chart generation method
JP2009048572A (en) Service record management system, method, and program
AU2016202814A1 (en) Systems and methods for managing cpu usage during qualitatively assessment of task data
JP2018169674A (en) Order placement control apparatus
JP5984686B2 (en) Information processing apparatus and program
JP2006190199A (en) Cad progress managing system and its method and program
JP7295758B2 (en) Sales support system
CN117196270B (en) Method, system, equipment and medium for issuing work supervision information
JP7304139B2 (en) PROJECT SUPPORT SYSTEM, PROJECT SUPPORT DEVICE AND PROJECT SUPPORT METHOD
JP4279342B1 (en) Awareness program and system