JP2020086768A - Apparatus and processing program for displaying construction process - Google Patents
Apparatus and processing program for displaying construction process Download PDFInfo
- Publication number
- JP2020086768A JP2020086768A JP2018218383A JP2018218383A JP2020086768A JP 2020086768 A JP2020086768 A JP 2020086768A JP 2018218383 A JP2018218383 A JP 2018218383A JP 2018218383 A JP2018218383 A JP 2018218383A JP 2020086768 A JP2020086768 A JP 2020086768A
- Authority
- JP
- Japan
- Prior art keywords
- construction process
- work
- image data
- construction
- schedule
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 377
- 238000010276 construction Methods 0.000 title claims abstract description 268
- 230000006870 function Effects 0.000 claims description 15
- 230000004044 response Effects 0.000 claims description 3
- 238000004891 communication Methods 0.000 description 13
- 239000000470 constituent Substances 0.000 description 5
- 238000010586 diagram Methods 0.000 description 5
- 238000003384 imaging method Methods 0.000 description 4
- 238000004904 shortening Methods 0.000 description 3
- 230000003111 delayed effect Effects 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000003491 array Methods 0.000 description 1
- 238000004040 coloring Methods 0.000 description 1
- 238000013500 data storage Methods 0.000 description 1
- 230000003287 optical effect Effects 0.000 description 1
- 239000004065 semiconductor Substances 0.000 description 1
- 230000003442 weekly effect Effects 0.000 description 1
Landscapes
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
本発明の実施形態は、複数の工事業者が並行して工事を進めるのに使用される工事工程表示装置および工事工程表示処理プログラムに関する。 Embodiments of the present invention relate to a construction process display device and a construction process display processing program used by a plurality of contractors to proceed with construction in parallel.
例えば、建設工事において、同時期、同一場所で複数の工事業者が並行して工事を進めることがある。 For example, in construction work, a plurality of contractors may work concurrently in the same place at the same time.
一般に、理想的な工事の進行は、土木工事、建築工事、機械設備工事、電気設備工事の順になり、工事に着工する前の計画段階では、各工事がその時期や場所において重ならないように、あるいは同時並行等が必要な工事の場合は敢えて重なるように各工事業者の工事工程表を作成する。 Generally, the ideal progress of work is civil engineering work, construction work, mechanical equipment work, electrical equipment work in order, and at the planning stage before starting construction, each work does not overlap at the time and place, Alternatively, in the case of works that require parallel work, the work schedules of each contractor are created so that they overlap.
しかしながら、実際に工事が始まると、工事業者毎に、工期の変動が頻繁に生じるため、各工事業者間でその工程の調整が必要になり、週単位や月単位など定期的に各工事業者を集めた工程会議を実施している。この工程会議において、工程の調整がしきれなくなると、例えば、優先すべき他の工事業者の工事を待つことによる工事の停滞、工期の遅延などのリスクが発生する。 However, when the construction actually starts, the construction period changes frequently for each contractor, so it is necessary to adjust the process among the contractors, and it is necessary to regularly schedule each contractor on a weekly or monthly basis. We hold the process conferences we have gathered. If the process adjustment cannot be completed at this process meeting, for example, there is a risk that the work will be delayed due to waiting for the work of another contractor who should be prioritized, and the construction period will be delayed.
工程会議では、各工事業者が各々の工事工程表を持ち寄って、お互いの都合が付くようにその工程の短縮、延長、移動等の変更を行ない調整することになるが、工事業者毎に工事工程表のフォーマットが異なる。 At the process meeting, each contractor will bring his or her construction process table and make adjustments such as shortening, extending, moving, etc. of the process so that they are convenient for each other. The format of the table is different.
このため、例えば、自業者の工事工程に影響する他業者の工事工程の見極め作業やその比較作業、影響する他業者の工事工程を自業者の工事工程へ反映する作業など、調整作業全般に非常に手間が掛かり面倒で長い時間を要する。 Therefore, for example, it is very important for general adjustment work, such as work to identify the construction process of other companies that affect the construction process of the own company and comparison work, and work to reflect the construction processes of other companies that affect the construction process of the own company. It is time-consuming, troublesome and takes a long time.
また、工程会議での工程の調整は、手間が掛かり面倒であるが故、工事業者間で口頭により工程の取り決めが行われることも少なくなく、このような場合、調整した工程の記録が存在せず調整が不十分になる。 In addition, since the process adjustment at the process meeting is time-consuming and tedious, it is not uncommon for the contractors to verbally negotiate the process.In such a case, a record of the adjusted process must exist. Adjustment is insufficient.
本発明が解決しようとする課題は、複数の工事業者間での工事工程の調整作業を容易且つ確実に行なうことが可能になる工事工程表示装置および工事工程表示処理プログラムを提供することにある。 The problem to be solved by the present invention is to provide a construction process display device and a construction process display processing program that enable adjustment work of construction processes among a plurality of contractors to be performed easily and reliably.
実施形態の工事工程表示装置は、複数の工事工程表をそれぞれ画像データとして取り込む工程表取り込み手段と、前記工程表取り込み手段により取り込まれた複数の工事工程表の画像データを、各工事工程表の同一の作業時期を示す間隔を対応させて重ねた工事工程表重ね画像データを生成する工程表重ね画像生成手段と、前記工程表重ね画像生成手段により生成された工事工程表重ね画像データを表示部に表示させる工程表重ね画像表示手段と、を備えている。 The construction process display device according to the embodiment displays a process schedule importing unit that captures a plurality of construction schedules as image data, and image data of a plurality of construction schedules captured by the process schedule capturing unit, in each construction schedule. A process table superposed image generating means for generating superposed work process table superposed image data corresponding to intervals indicating the same work time, and a display section for displaying the work process superposed image data generated by the process step superposed image generating means. And a process-table-overlapped image display means for displaying the image.
以下、実施形態の工事工程表示装置について、図面を参照して説明する。 Hereinafter, the construction process display device of the embodiment will be described with reference to the drawings.
図1は、実施形態の工事工程表示装置10を、タブレット端末を使用して実現した場合の外観構成を示す正面図である。 FIG. 1 is a front view showing an external configuration when a construction process display device 10 of the embodiment is realized using a tablet terminal.
工事工程表示装置10は、タブレット端末に限らず、PC(Personal Computer)やPDA(Personal Data Assistant)などの表示部を備えた情報機器を使用して実現できる。 The construction process display device 10 is not limited to a tablet terminal, and can be realized using an information device including a display unit such as a PC (Personal Computer) or a PDA (Personal Data Assistant).
図1では、例えば、自社工事工程表T1は表作成ツールを使用して作成され、A社工事工程表T2とB社工事工程表T3は何れも手書きにより作成された後、画像として取り込まれたものとし、当該各工事工程表T1〜T3の紙に手書きあるいは画像に付加した作業時期識別マーク「○」A1〜「○」A5および「△」B1〜「△」B4に基づいて、各工事工程表T1〜T3間で調整に必要な作業時期を示す間隔が合うように各工事工程表T1〜T3の画像を重ねて生成した工事工程表重ね画面Gを示している。 In FIG. 1, for example, the in-house work process schedule T1 is created using a table creation tool, and both the A company work process schedule T2 and the B company work process schedule T3 are created by handwriting and then captured as an image. Based on the work time identification marks “○” A1 to “○” A5 and “△” B1 to “△” B4, which are handwritten on the paper of each of the construction process tables T1 to T3 or added to the image, each construction process The construction process schedule overlapping screen G generated by superimposing the images of the respective construction process schedules T1 to T3 so that the intervals indicating the work timings required for adjustment are matched between the tables T1 to T3 is shown.
図2は、実施形態の工事工程表示装置10の電子回路の構成を示すブロック図である。 FIG. 2 is a block diagram showing the configuration of the electronic circuit of the construction process display device 10 of the embodiment.
工事工程表示装置10は、コンピュータとしてのCPU(制御部)11を備える。 The construction process display device 10 includes a CPU (control unit) 11 as a computer.
CPU11は、メモリ12に予め記憶されたプログラム、あるいはメモリカードなどの外部記録媒体14から記録媒体読取部13により読み込まれてメモリ12に記憶されたプログラム、あるいはインターネットなどの通信ネットワークN上のWebサーバ(この場合はプログラムサーバ)20から通信部15を介してダウンロードされメモリ12に記憶されたプログラムに従い、回路各部の動作を制御する。 The CPU 11 is a program pre-stored in the memory 12, a program read by the recording medium reading unit 13 from the external recording medium 14 such as a memory card and stored in the memory 12, or a Web server on the communication network N such as the Internet. The operation of each part of the circuit is controlled according to the program downloaded from the (program server in this case) 20 via the communication unit 15 and stored in the memory 12.
CPU11には、システムおよびデータバス(Bus)を介して、メモリ12、記録媒体読取部13、通信部15、タッチパネル式表示部16、撮像部(デジタルカメラ)17<工程表取り込み手段>、音声入力部18a、音声出力部18b、近距離無線通信部19が接続される。 The CPU 11, via the system and the data bus (Bus), the memory 12, the recording medium reading unit 13, the communication unit 15, the touch panel type display unit 16, the image pickup unit (digital camera) 17 <process chart capturing means>, voice input The unit 18a, the voice output unit 18b, and the short-range wireless communication unit 19 are connected.
近距離無線通信部19は、Bluetooth(登録商標)などの通信機能を有し、CPU11の制御により、他の工事工程表示装置10などの外部の情報機器30と通信接続する。 The short-range wireless communication unit 19 has a communication function such as Bluetooth (registered trademark), and is connected to an external information device 30 such as another construction process display device 10 under the control of the CPU 11.
メモリ12には、本装置10の全体的な動作を制御するためのシステムプログラムのほか、工事工程表示処理プログラム12a、画像/図形処理プログラム12bなどのプログラムデータが記憶される。工事工程表示処理プログラム12aおよび画像/図形処理プログラム12bをCPU11が実行することにより得られる機能については、後述する。 The memory 12 stores program data such as a construction process display processing program 12a and an image/graphics processing program 12b as well as a system program for controlling the overall operation of the apparatus 10. Functions obtained by the CPU 11 executing the construction process display processing program 12a and the image/graphics processing program 12b will be described later.
また、メモリ12には、作業時期認識データ12c、作業場所認識データ12d、工事工程表画像データ12e1,12e2,…、工事工程表重ね画像データ12fなどを記憶するためのデータ記憶エリアが確保される。 Further, the memory 12 has a data storage area for storing work time recognition data 12c, work location recognition data 12d, construction process sheet image data 12e1, 12e2,..., Construction process sheet overlapping image data 12f, and the like. ..
作業時期認識データ12cは、画像データに含まれる作業時期に対応する間隔を認識するための予め定められた作業時期識別マーク(「○」や「△」…など)のデータである。 The work time recognition data 12c is data of a predetermined work time identification mark (such as “◯” or “Δ”...) for recognizing an interval corresponding to the work time included in the image data.
なお、作業時期認識データ12cは、他の実施形態として、画像データに含まれるテキストから数字との組み合わせからなる作業時期に関する情報(30年,31年,1月,2月,1週,2週,1日,2日など)を認識するための認識対象文字(「年」「月」「週」「日」など)のデータとしてもよい。 In addition, as another embodiment, the work time recognition data 12c is information (30 years, 31 years, January, February, 1 week, 2 weeks) related to the work time, which is a combination of a text included in the image data and a numeral. , 1st, 2nd, etc.) may be data of recognition target characters (“year”, “month”, “week”, “day”, etc.).
作業場所認識データ12dは、画像データに含まれる作業場所に対応する表記を認識するための予め定められた作業場所識別マーク(「◎」など:図4参照)のデータである。 The work place recognition data 12d is data of a predetermined work place identification mark (such as “⊚”: see FIG. 4) for recognizing the notation corresponding to the work place included in the image data.
なお、作業場所認識データ12dは、他の実施形態として、画像データに含まれるテキストから数字または他の文字との組み合わせからなる作業場所に関する情報(B1F,1F,2F,地階,1階,2階,屋上,A棟,B棟など)を認識するための認識対象文字(「F」「B」「R」「階」「地」「屋」「室」「棟」など)のデータとしてもよい。 As another embodiment, the work place recognition data 12d is information (B1F, 1F, 2F, basement, first floor, second floor) about a work place which is a combination of a text included in image data and a number or another character. , Rooftop, A building, B building, etc.) may be data of recognition target characters (“F”, “B”, “R”, “floor”, “ground”, “roof”, “room”, “building”, etc.) ..
工事工程表画像データ12e1,12e2,…は、撮像部17により撮影された複数の工事業者の工事工程表T1,T2,…の画像データであり、各工事工程表画像データ12e1,12e2,…には、各工事業者の識別子IDのデータ(各工事業者が使用する工事工程表示装置10の通信アドレスなど)が対応付けられて記憶される。 The construction process table image data 12e1, 12e2,... Is image data of the construction process tables T1, T2,... Of a plurality of construction companies photographed by the imaging unit 17, and is included in each construction process table image data 12e1, 12e2,. Is stored in association with the identifier ID data of each contractor (such as the communication address of the construction process display device 10 used by each contractor).
工事工程表重ね画像データ12fは、複数の工事工程表画像データ12e1,12e2,…を1画面に重ねた画像データである。 The construction process sheet superposed image data 12f is image data obtained by superposing a plurality of construction process sheet image data 12e1, 12e2,... On one screen.
本実施形態の工事工程表示装置10は、CPU11が、工事工程表示処理プログラム12aおよび画像/図形処理プログラム12bを実行することにより、少なくとも以下(1)〜(8)の機能を有する。 The construction process display device 10 of the present embodiment has at least the following functions (1) to (8) when the CPU 11 executes the construction process display processing program 12a and the image/graphics processing program 12b.
(1)撮像部17により撮影した複数の工事業者の工事工程表T1,T2,…の画像データ12e1,12e2,…を、1画面に重ね(メモリ上での処理)、工事工程表重ね画像データ12fを生成する機能<工程表重ね画像生成手段>。 (1) Image data 12e1, 12e2,... Of the construction process charts T1, T2,... Of a plurality of construction companies photographed by the image pickup unit 17 are overlaid on one screen (processing on the memory), construction process chart overlaid image data Function for generating 12f <process chart superimposed image generation means>.
(2)工事工程表重ね画像データ12fを生成する際に、各工事工程表画像データ(T1)12e1,(T2)12e2,…に含まれる作業時期識別マーク(「○」A1,A2,…や「△」B1,B2,…など)を認識し、または作業時期に関する情報(文字列)を認識し、各工程表間の同一の作業時期に対応する間隔を合わせて画像の拡大/縮小を行ない重ね合わせ処理する機能。 (2) When generating the construction process sheet overlapping image data 12f, the work time identification marks (“○” A1, A2,... Or included in each construction process sheet image data (T1) 12e1, (T2) 12e2,... “Δ” B1, B2, etc.) or information (character string) related to the work period is recognized, and the image is enlarged/reduced at intervals corresponding to the same work period between the process charts. A function to perform overlay processing.
なお、作業時期識別マーク(「○」A1,A2,…や「△」B1,B2,…など)は、ユーザによって、工事工程表T1,T2,…を撮影する前に手書きで付加されるか、または撮影された後の画像に付加される。 It should be noted that the work time identification marks (“○” A1, A2,..., “Δ” B1, B2,...) Are handwritten by the user before photographing the construction process chart T1, T2,. , Or added to the captured image.
(3)工事工程表重ね画像データ12fをタッチパネル式表示部16に工事工程表重ね画面Gとして表示させる機能<工程表重ね画像表示手段>。 (3) A function of displaying the construction process sheet overlapping image data 12f on the touch panel type display unit 16 as a construction process sheet overlapping screen G <process sheet overlapping image display means>.
(4)工事工程表重ね画面Gとしてタッチパネル式表示部16に表示された工事工程表重ね画像データ12fの各工程表T1,T2,…の枠などに対するユーザのタッチ操作に応じて、各工事工程表画像データ(T1)12e1,(T2)12e2,…の重なる位置を移動させる機能。 (4) Each construction process according to the user's touch operation on the frame of each process chart T1, T2,... Of the construction process schedule overlap image data 12f displayed on the touch panel type display unit 16 as the construction process schedule superposition screen G. A function of moving the overlapping position of the front image data (T1) 12e1, (T2) 12e2,....
(5)工事工程表重ね画面Gとしてタッチパネル式表示部16に表示された工事工程表重ね画像データ12fの各工程表T1,T2,…の工程バー(該当する工事の作業時期の範囲を示す棒状表示体)Tna,Tnb,…(n=1,2,…)に対するユーザのタッチ操作に応じて、タッチ位置に対応する工程バーTna,Tnb,…を図形として抽出し、抽出した工程バーを画面G上でコピー、移動、貼付け、延長、短縮などにより編集処理(調整)する機能<作業時期変更手段>。 (5) Process bar of each process chart T1, T2,... Of the construction process chart overlapped image data 12f displayed on the touch panel type display unit 16 as the construction process chart overlap screen G (a bar indicating the range of the work period of the corresponding construction) (Display body) Tna, Tnb,... (n=1, 2,...) In response to a user's touch operation, the process bars Tna, Tnb,... Corresponding to the touch position are extracted as graphics, and the extracted process bar is displayed on the screen. Function to edit (adjust) by copying, moving, pasting, extending, shortening, etc. on G <Working time changing means>.
(6)各工事工程表画像データ(T1)12e1,(T2)12e2,…が重なった範囲において、当該各工事工程表画像データ(T1)12e1,(T2)12e2,…が識別可能なように透過して表示させる(色や線種を異ならせる処理を含む)機能。 (6) In a range where the construction process sheet image data (T1) 12e1, (T2) 12e2,... Are overlapped, the construction process sheet image data (T1) 12e1, (T2) 12e2,. A function to display transparently (including processing to change the color and line type).
(7)工程バーTna,Tnb,…を編集処理(調整)した状態で、各工事工程表画像データ(T1)12e1,(T2)12e2,…を更新する機能<工程表画像更新手段>。 (7) Function of updating each construction process table image data (T1) 12e1, (T2) 12e2,... In the state where the process bars Tna, Tnb,... Are edited (adjusted) <process table image updating means>.
(8)工事工程表重ね画面Gとしてタッチパネル式表示部16に表示された工事工程表重ね画像データ12fまたは更新した各工事工程表画像データ(T1)12e1,(T2)12e2,…を、外部に出力する機能<工程表画像出力手段>。 (8) The construction process sheet overlapping image data 12f displayed on the touch panel type display unit 16 as the construction process sheet overlapping screen G or each updated construction process sheet image data (T1) 12e1, (T2) 12e2,... Output function <Process table image output means>.
このように構成された工事工程表示装置10は、CPU11が工事工程表示処理プログラム12aおよび画像/図形処理プログラム12bに記述された命令に従い各部の動作を制御し、ソフトウエアとハードウエアとが協働して動作することにより、以下の動作説明で述べるような、工事工程表示機能(図3)を実現する。 In the construction process display device 10 configured as described above, the CPU 11 controls the operation of each unit according to the instructions described in the construction process display processing program 12a and the image/graphics processing program 12b, and software and hardware cooperate with each other. By doing so, the construction process display function (FIG. 3) as described in the following operation description is realized.
次に、このように構成した工事工程表示装置10の動作について説明する。 Next, the operation of the construction process display device 10 thus configured will be described.
図3は、工事工程表示装置10の工事工程表示処理プログラム12aおよび画像/図形処理プログラム12bに従った工事工程表示処理を示すフローチャートである。 FIG. 3 is a flowchart showing the construction process display processing according to the construction process display processing program 12a and the image/graphics processing program 12b of the construction process display device 10.
図4は、複数の工事業者の工事工程表T1,T2を示す図であり、同図(A)は電気工事工程表T1を示す図、同図(B)は機械工事工程表T2を示す図である。 4A and 4B are diagrams showing construction process charts T1 and T2 of a plurality of contractors. FIG. 4A shows an electric construction process chart T1, and FIG. 4B shows a mechanical construction process chart T2. Is.
本実施形態において、各工事工程表T1,T2は、各工事業者により紙または板書(手書き)によって用意され、各工事工程表T1,T2のサイズは勿論、作業時期を示す横方向の間隔、作業種または作業場所を示す縦方向の配列を含むフォーマットが異なるものと仮定する。 In the present embodiment, the respective construction process charts T1 and T2 are prepared by paper or blackboard (handwritten) by each construction contractor, and the size of each construction process chart T1 and T2, as well as the lateral interval and the work indicating the work period, Assume different formats, including vertical arrays of species or work locations.
図4の具体例では、各工事工程表T1,T2により横方向に示される全体の工事時期は、工事工程表T1が「3月」〜翌年「2月」、工事工程表T2が「1月」〜翌年「3月」と異なり、その各月の間隔も大きく異なる。また、縦方向に配列して示される作業場所も、電気工事工程表T1は1行目「1F」〜4行目「4F」、機械工事工程表T2は1行目「地2」、2行目「地1」、3行目「3階」、4行目「屋上」と異なる。 In the specific example of FIG. 4, the overall construction time shown in the horizontal direction by the construction process charts T1 and T2 is from “March” to the next year “February” for the construction schedule T1 and “January for the construction schedule T2” in the next year. "~" next year's "March", the intervals of each month also differ greatly. Further, regarding the work places arranged in the vertical direction, the electrical work process chart T1 is the first line “1F” to the fourth row “4F”, and the mechanical work process chart T2 is the first line “ground 2”, two rows. It differs from the line "ground 1", the third line "3rd floor", and the fourth line "rooftop".
本実施形態の具体例では、工程会議において、電気工事業者が紙で持参あるいは板書した電気工事工程表T1(図4(A)参照)と、機械工事業者が紙で持参あるいは板書した機械工事工程表T2(図4(B)参照)とを用いて、工程の調整を行なうものと仮定する。 In the specific example of the present embodiment, the electrical work process table T1 (refer to FIG. 4A) brought by or written on paper by the electrician and the mechanical work process brought on or written by the mechanical contractor at the process meeting. It is assumed that the process adjustment is performed using Table T2 (see FIG. 4B).
図5は、工事工程表示装置10の工事工程表示処理に従い電気工事工程表T1の画像データ12e1と機械工事工程表T2の画像データ12e2とを重ねて生成した工事工程表重ね画面Gの表示動作を示す図である。 FIG. 5 shows the display operation of the construction process table overlapping screen G generated by superimposing the image data 12e1 of the electrical construction process table T1 and the image data 12e2 of the mechanical construction process table T2 according to the construction process display processing of the construction process display device 10. FIG.
図6は、工事工程表示装置10の工事工程表示処理に従った工事工程表重ね画面Gでの工程の調整に応じた表示動作(その1)を示す図である。 FIG. 6 is a diagram showing a display operation (No. 1) according to the adjustment of the process on the construction process table overlapping screen G according to the construction process display process of the construction process display device 10.
図7は、工事工程表示装置10の工事工程表示処理に従った工事工程表重ね画面Gでの工程の調整に応じた表示動作(その2)を示す図である。 FIG. 7 is a diagram showing a display operation (No. 2) according to the adjustment of the process on the construction process table overlapping screen G according to the construction process display process of the construction process display device 10.
工事工程表示処理の開始に従い、例えば、タッチパネル式表示部16に表示された処理メニューおいて、「工程表取り込み」を示す項目がユーザによりタッチされると、CPU11は、撮像部(カメラ)17を起動させ、工事工程表Tn(n=1,2,…)の取り込みをユーザに促すメッセージを表示部16に表示させる。 When the construction process display process is started, for example, when the user touches an item indicating “take in process table” in the process menu displayed on the touch panel type display unit 16, the CPU 11 causes the image pickup unit (camera) 17 to operate. It is activated and a message prompting the user to take in the work schedule Tn (n=1, 2,...) Is displayed on the display unit 16.
ここで、工事工程表T1,T2には、工事時期の間隔を合わせるための工事時期識別マーク「○」A1〜「○」A11を、各工事工程表T1,T2の工程の調整に必要となる例えば各月の境界の位置に、ユーザの手書きにより付加しておく。 Here, in the construction process charts T1 and T2, construction timing identification marks “◯” A1 to “◯” A11 for matching the intervals of the construction timings are necessary for adjusting the processes of the construction schedules T1 and T2. For example, it is added by handwriting at the position of the boundary of each month.
また、工事工程表T1,T2には、当該工事工程表T1,T2間で同じ作業場所に対応する表記を認識するための作業場所識別マーク「◎」Mを、同じ作業場所の表記(T1では「3F」、T2では「3階」)のある位置に、ユーザの手書きにより付加しておく。 Further, in the construction process charts T1 and T2, a work place identification mark “⊚” M for recognizing the notation corresponding to the same work place between the construction process charts T1 and T2, and the notation of the same work place (in T1 It is added by handwriting to the position of "3F" or "3rd floor" in T2).
工事工程表示装置10の撮像部17により、先ず、電気工事工程表T1を撮影すると、CPU11は、撮影された電気工事工程表T1の画像データ12e1を取り込み(ステップS1)、タッチパネル式表示部16に表示させ、メモリ12に記憶させ保存する(ステップS2)<工程表取り込み手段>。 First, when the electric work process chart T1 is photographed by the imaging unit 17 of the construction process display device 10, the CPU 11 takes in the image data 12e1 of the photographed electric construction process chart T1 (step S1), and the touch panel type display unit 16 is displayed. It is displayed, stored in the memory 12 and saved (step S2) <process chart loading means>.
続いて、工程の調整に追加すべき機械工事工程表T2を撮影すると(ステップS3(Yes))、CPU11は、撮影された機械工事工程表T2の画像データ12e2を取り込み(ステップS1)、タッチパネル式表示部16に表示させ、メモリ12に記憶させ保存する(ステップS2)<工程表取り込み手段>。 Subsequently, when the machine work process chart T2 to be added to the process adjustment is photographed (step S3 (Yes)), the CPU 11 takes in the image data 12e2 of the photographed machine work process chart T2 (step S1), and the touch panel type. It is displayed on the display unit 16 and stored in the memory 12 and saved (step S2) <process chart loading means>.
この際、CPU11は、各工事工程表T1,T2の一部に記述されていた各工事業者の識別子ID1,ID2(各工事業者が使用する工事工程表示装置10の通信アドレスなど)を文字認識し、メモリ12に記憶させる各工事工程表画像データ(T1)12e1,(T2)12e2に対応付けて記憶させる。なお、各工事業者の識別子ID1,ID2は、各工事工程表画像データ(T1)12e1,(T2)12e2を取り込む毎に、タッチパネル式表示部16に表示させたソフトキーボードのユーザ操作に応じて入力してもよい。 At this time, the CPU 11 character-recognizes the identifiers ID1 and ID2 (such as the communication address of the construction process display device 10 used by each construction company) of each construction company described in a part of each construction process table T1 and T2. , (T1) 12e1 and (T2) 12e2 stored in the memory 12 in association with each other. It should be noted that the identifiers ID1 and ID2 of the respective contractors are input according to the user operation of the soft keyboard displayed on the touch panel type display unit 16 every time the respective construction process chart image data (T1) 12e1 and (T2) 12e2 are fetched. You may.
なお、工事時期識別マーク「○」A1〜「○」A11および作業場所識別マーク「◎」Mは、各工事工程表T1,T2の画像データ12e1,12e2を取り込んでタッチパネル式表示部16に表示させた段階で、当該タッチパネル式表示部16に対するユーザのタッチ操作に応じて付加してもよい。 The construction time identification marks "○" A1 to "○" A11 and the work place identification mark "⊚" M are displayed on the touch panel display unit 16 by capturing the image data 12e1 and 12e2 of the respective construction process charts T1 and T2. At the stage when the touch panel type display unit 16 is touched, the touch panel type display unit 16 may be added according to a touch operation performed by the user.
ここで、例えば、タッチパネル式表示部16に表示された処理メニューおいて、「工程表重ねる」を示す項目がユーザによりタッチされると(ステップS4)、CPU11は、メモリ12に記憶されている作業時期認識データ12c(作業時期識別マーク「○」あるいは認識対象文字「月」)に基づき、メモリ12に保存された各工事工程表画像データ(T1)12e1,(T2)12e2に含まれる工程の調整に必要な作業時期(「3月」〜「2月」)の間隔、あるいは作業時期に関する文字列(「1月」〜「12月」)を認識する(ステップS5)<作業時期認識手段>。 Here, for example, in the process menu displayed on the touch panel type display unit 16, when the user touches the item indicating “overlap process step” (step S4), the CPU 11 causes the work stored in the memory 12 to be performed. Adjustment of the process included in each construction process schedule image data (T1) 12e1, (T2) 12e2 saved in the memory 12 based on the time recognition data 12c (work time identification mark “◯” or recognition target character “month”) The work time interval (“March” to “February”) required for the operation or the character string (“January” to “December”) related to the work time is recognized (step S5) <work time recognizing means>.
また、CPU11は、メモリ12に記憶されている作業場所認識データ12d(作業場所識別マーク「◎」あるいは認識対象文字「F」「地」「階」「屋」)に基づき、メモリ12に保存された各工事工程表画像データ(T1)12e1,(T2)12e2に含まれる同じ作業場所に対応する表記(工程表T1では「3F」、工程表T2では「3階」)あるいは作業場所に関する文字列(工程表T1では「1F」〜「4F」、工程表T2では「地2」「地1」「3階」「屋上」)を認識する(ステップS6)<作業場所認識手段>。 Further, the CPU 11 stores the work location recognition data 12d (work location identification mark “⊚” or recognition target characters “F” “ground” “floor” “ya”) stored in the memory 12 in the memory 12 based on the work location recognition data 12d. A notation (“3F” in the process chart T1 and “3rd floor” in the process chart T2) corresponding to the same work place included in each of the construction process chart image data (T1) 12e1, (T2) 12e2 or a character string related to the work place ("1F" to "4F" in the process chart T1 and "ground 2", "ground 1", "third floor", "rooftop" in the process table T2) are recognized (step S6) <workplace recognition means>.
すると、CPU11は、各工事工程表画像データ(T1)12e1,(T2)12e2において、ステップS5にて認識された作業時期(「3月」〜「2月」)の間隔が対応するように、当該各画像データ(T1)12e1,(T2)12e2を拡大または縮小し(ここでは画像データ(T2)12e2を横方向に拡大)、図5に示すように、当該各画像データ(T1)12e1,(T2)12e2を上下に重ねた工事工程表重ね画像データ12fを生成し<工程表重ね画像生成手段>、工事工程表重ね画面Gとしてタッチパネル式表示部16に表示させる(ステップS7)<工程表重ね画像表示手段>。 Then, the CPU 11 causes the work time schedule image data (T1) 12e1, (T2) 12e2 to correspond to the intervals of the work periods (“March” to “February”) recognized in step S5. Each of the image data (T1) 12e1 and (T2) 12e2 is enlarged or reduced (here, the image data (T2) 12e2 is enlarged in the horizontal direction), and as shown in FIG. (T2) Construction process table superposed image data 12f in which 12e2 is vertically superposed is generated <process table superposed image generating means>, and is displayed on the touch panel type display unit 16 as a construction process superposition screen G (step S7) <process chart Overlaid image display means>.
これにより、ユーザは、各工事業者が持ち寄ったり板書したりした異なるフォーマットの工事工程表T1,T2,…を、当該工程表T1,T2,…それぞれの工程の調整に必要な作業時期に対応する表の間隔を合わせて一体化した工事工程表重ね画面Gにして閲覧することができ、工事全体の工程を容易に把握して検討できるようになる。よって、例えば、自業者の工事工程に影響する他業者の工事工程が、工事全体の工程の中で何処に存在するのかを、容易に確認できるようになる。 As a result, the user responds to the work schedules T1, T2,... Of different formats brought by each construction contractor or written on the blackboard in accordance with the work time necessary for adjusting the respective schedules T1, T2,. It is possible to view the construction process table overlapping screen G, which is integrated with the intervals of the tables, so that the process of the entire construction can be easily grasped and studied. Therefore, for example, it becomes possible to easily confirm where the construction process of another contractor, which influences the construction process of the own contractor, exists in the whole construction process.
そして、CPU11は、タッチパネル式表示部16に表示された工事工程表重ね画像データ12fに含まれる、ステップS6にて認識された各工程表T1,T2間で同一の作業場所の表記(工程表T1では「3F」、工程表T2では「3階」)が存在する当該各工程表T1,T2のセルを、反転処理や色付け処理などにより識別表示Hさせる(ステップS8)<作業場所識別表示手段>。 Then, the CPU 11 indicates the same work place between the process charts T1 and T2 recognized in step S6, which is included in the construction process chart superimposed image data 12f displayed on the touch panel display unit 16 (the process chart T1). "3F", and "3rd floor" in the process chart T2), the cells of the respective process charts T1 and T2 in which there exists are identified and displayed H by inversion processing or coloring processing (step S8) <work place identification display means> ..
これにより、ユーザは、自業者の工事工程と他業者の工事工程との間で、同一の作業場所であるところのお互いの工事工程を容易に把握することができ、例えば、同一の作業場所でお互いの作業時期が被ってしまうところを素早く確認できるようになる。 As a result, the user can easily understand each other's work process in the same work place between the work process of the own company and the work process of another company, for example, in the same work place. You will be able to quickly see where each other's work time will be overwhelmed.
図5に示す工事工程表重ね画面Gでは、電気工事の工程表T1と機械工事の工程表T2との間で、識別表示Hされた同一の作業場所「3F」「3階」に対応する各工程バーT1c,T2cが示す作業時期に基づき、「3F(3階)」で行う工事の作業時期が一部被ってしまうことを容易に確認できる。 In the construction process schedule overlapping screen G shown in FIG. 5, between the work schedule T1 for electrical work and the process schedule T2 for mechanical work, each of the same work locations “3F” and “3rd floor” that are identified and displayed H is identified. Based on the work time indicated by the process bars T1c and T2c, it can be easily confirmed that the work time of the work to be performed on "3F (3rd floor)" will be partially covered.
ここで、同一の作業場所「3F(3階)」で作業時期が一部被っていることを確認した各工程バーT1c,T2cを正確に比較するため、ユーザが、各工程バーT1c,T2cの一方(ここではT2c)をタッチ操作して指定すると(ステップS9(Yes))、CPU11は、指定された工程バーT2cを図形編集(コピー・移動・貼付け・延長(拡大)・短縮(縮小))の対象物として抽出する(ステップS10)。 Here, in order to accurately compare the process bars T1c and T2c, which are confirmed to have partially covered the work time at the same work place “3F (3rd floor)”, the user needs to compare the process bars T1c and T2c. If one (here, T2c) is touch-operated and designated (step S9 (Yes)), the CPU 11 performs graphic editing (copy/move/paste/extend (enlarge)/shorten (reduce)) the designated process bar T2c. (Step S10).
ユーザがタッチ操作して指定した「3階」の機械工事の工程バーT2cから、そのタッチ操作位置を、矢印Mcに示すように、「3F」の電気工事の工程バーT1cの位置まで移動すると、CPU11は、工程バーT2cをコピーし、コピーした工程バーT2cをユーザのタッチ操作位置の移動(Mc)に応じて移動させ、移動後のタッチ操作位置である工程バーT1cに重ねて貼り付ける(ステップS10)。 When the user moves the touch operation position from the process bar T2c for mechanical work on the "3rd floor" designated by touch operation to the position of the process bar T1c for electric work on "3F" as indicated by an arrow Mc, The CPU 11 copies the process bar T2c, moves the copied process bar T2c according to the movement (Mc) of the touch operation position of the user, and superimposes it on the process bar T1c that is the touch operation position after the movement (step). S10).
これにより、ユーザは、同一の作業場所「3F(3階)」で作業時期が一部被っている各工程バーT1c,T2cを直接比較して、「3F(3階)」の電気工事を始める予定の「7月」に「3F(3階)」の機械工事が終わる予定の「7月」が被ることを一目瞭然に確認できる。 As a result, the user directly compares the process bars T1c and T2c partially covered by the work at the same work place “3F (3rd floor)” and starts electrical work on “3F (3rd floor)”. It is possible to see at a glance that "July," which is scheduled to end the mechanical work on "3rd floor (3rd floor)," will occur during the scheduled "July."
この後、「3F(3階)」の電気工事と機械工事との作業時期の被り「7月」を解消するため、例えば、電気工事の工程バーT1cをユーザがタッチ操作して指定し、そのタッチ操作位置を一月分の表の間隔で右方向に移動させると、CPU11は、図6の矢印m1に示すように、当該電気工事の工程バーT1cをユーザ操作に応じて移動させ、「8月」〜「12月」の範囲に作業時期を調整した工程バーT1c´にして表示させる(ステップS9(Yes))→S10)<作業時期変更手段>。 After that, in order to eliminate the “July” that is a work period between the electric work and the mechanical work on the “3F (3rd floor)”, for example, the user touches and specifies the process bar T1c of the electric work, and When the touch operation position is moved to the right at the interval of the table for one month, the CPU 11 moves the process bar T1c of the electric work in response to the user operation, as indicated by an arrow m1 in FIG. The process bar T1c' whose work time is adjusted in the range of "month" to "December" is displayed (step S9 (Yes))→S10) <work time changing means>.
ここで、タッチパネル式表示部16に表示された処理メニューおいて、「決定」を示す項目がユーザによりタッチされると(ステップS13(Yes))、CPU11は、図6に示すように、「3F」の電気工事を一月先に移動して調整した状態での工程バーT1c´を有する工事工程表重ね画像データ12fに対応させて、当該工事工程表重ね画像データ12fの生成元であるメモリ12内の電気工事の工事工程表画像データ12e1と機械工事の工事工程表画像データ12e2とを更新して保存する(ステップS14)<工程表画像更新手段>。 Here, in the processing menu displayed on the touch-panel display unit 16, when the user touches the item indicating “OK” (step S13 (Yes)), the CPU 11 displays “3F” as shown in FIG. In correspondence with the construction process sheet overlay image data 12f having the process bar T1c′ in a state where the electrical work of “” is moved one month ahead and adjusted, the memory 12 that is the generation source of the construction process sheet overlay image data 12f. The construction process sheet image data 12e1 for electrical work and the construction process sheet image data 12e2 for mechanical work are updated and stored (step S14) <process sheet image updating means>.
また、図5で示したように、同一の作業場所「3F(3階)」で電気工事と機械工事の作業時期が被っている工程バーT1cの表示位置に、工程バーT2cをコピー・移動・貼付けし、当該各工程バーT1c,T2cを直接比較した状態で、例えば、「2F」の電気工事(工程バーT1b「5月」〜「6月」)が終わらないと「3階」の機械工事(工程バーT2c)を開始できないとの理由により、当該直接比較している機械工事の工程バーT2c(「6月」〜「7月」)をユーザがタッチ操作して指定し、そのタッチ操作位置を一月分の表の間隔で右方向に移動させると、CPU11は、図7の矢印m2に示すように、当該直接比較している機械工事の工程バーT2cをユーザ操作に応じて移動させ、「7月」〜「8月」の範囲に作業時期を調整した工程バーT2c´にして表示させる(ステップS9(Yes))→S10)<作業時期変更手段>。 Further, as shown in FIG. 5, the process bar T2c is copied/moved/displayed at the display position of the process bar T1c which is subject to the electric work and the mechanical work at the same work place “3F (3rd floor)”. In the state of pasting and directly comparing the process bars T1c and T2c, for example, if the electrical work of "2F" (process bar T1b "May" to "June") is not completed, "3rd floor" mechanical work Since the (process bar T2c) cannot be started, the user touch-designates the process bar T2c (“June” to “July”) of the machine work that is directly compared, and the touch operation position is specified. Is moved to the right at an interval of the table for one month, the CPU 11 moves the process bar T2c of the machine work which is directly compared according to a user operation, as indicated by an arrow m2 in FIG. The process bar T2c' having the work timing adjusted in the range of "July" to "August" is displayed (step S9 (Yes))→S10) <work timing changing means>.
この際、CPU11は、作業時期を調整した工程バーT2c´について、工程表T2→T1間で移動された工程バーT2cを変更(調整)したものであると判定し(ステップS11(Yes))、図7の矢印m2´に示すように、当該工程バーT2cの移動元である工程表T2の工程バーT2cを、作業時期の変更(調整)を反映させた工程バーT2c´にして表示させる(ステップS12)。 At this time, the CPU 11 determines that the process bar T2c moved between the process charts T2 and T1 has been changed (adjusted) for the process bar T2c′ whose work time has been adjusted (step S11 (Yes)), As shown by an arrow m2′ in FIG. 7, the process bar T2c of the process table T2, which is the movement source of the process bar T2c, is displayed as a process bar T2c′ that reflects the change (adjustment) of the work time (step). S12).
続いて、「7月」〜「8月」の範囲に移動して調整した「3階」の機械工事(工程バーT2c´)と「3F」の電気工事(工程バーT1c)との作業時期の被りを解消するため、例えば、電気工事の工程バーT1cの開始位置に相当する左端をユーザがタッチ操作して指定し、そのタッチ操作位置を二月分の表の間隔で右方向に移動させると、CPU11は、図7の矢印shに示すように、当該電気工事の工程バーT1cをユーザ操作に応じて短縮し、「9月」〜「12月」の範囲に作業時期を詰めて調整した工程バーT1c´´にして表示させる(ステップS9(Yes))→S10)<作業時期変更手段>。 Subsequently, the work time of the “3rd floor” mechanical work (process bar T2c′) and the “3F” electrical work (process bar T1c) that were adjusted by moving to the range from “July” to “August” In order to eliminate the overburden, for example, when the user touches and specifies the left end corresponding to the start position of the process bar T1c for electrical work, and moves the touch operation position to the right at the interval of the table for February. The CPU 11 shortens the process bar T1c of the electric work according to a user operation, as shown by an arrow sh in FIG. 7, and adjusts the work period by adjusting the work time in the range from “September” to “December”. The bar T1c″ is displayed (step S9 (Yes))→S10) <work timing changing means>.
ここで、タッチパネル式表示部16に表示された処理メニューおいて、「決定」を示す項目がユーザによりタッチされると(ステップS13(Yes))、CPU11は、図7に示すように、「3階」の機械工事を「7月」〜「8月」に移動して調整(工程バーT2c´)すると共に、「3F」の電気工事を「9月」〜「12月」の4か月に短縮して調整(工程バーT1c´´)した状態での工事工程表重ね画像データ12fに対応させて、当該工事工程表重ね画像データ12fの生成元であるメモリ12内の電気工事の工事工程表画像データ12e1と機械工事の工事工程表画像データ12e2とを更新して保存する(ステップS14)<工程表画像更新手段>。 Here, in the process menu displayed on the touch panel type display unit 16, when the user touches the item indicating “OK” (step S13 (Yes)), the CPU 11 displays “3” as shown in FIG. The mechanical work on the “floor” was moved from “July” to “August” and adjusted (process bar T2c′), and the electrical work on “3F” was performed in four months from “September” to “December”. Corresponding to the construction process schedule overlay image data 12f in the state of being shortened and adjusted (process bar T1c″), the construction schedule of electrical work in the memory 12 that is the generation source of the construction process schedule overlay image data 12f. The image data 12e1 and the construction process sheet image data 12e2 for mechanical work are updated and stored (step S14) <process sheet image updating means>.
これにより、例えば、複数の工事業者間で互いに影響する工事工程を、工事工程表重ね画面Gにて容易に素早く確認できるだけでなく、作業時期として影響のある工事工程(工程バーTna,Tnb,…(n=1,2))を、当該工程バーTna,Tnb,…(n=1,2)の移動、短縮、延長によって容易に調整できるようになる。 Thereby, for example, not only can the construction processes which affect each other among a plurality of contractors be easily and quickly confirmed on the construction process table overlapping screen G, but also the construction processes (process bars Tna, Tnb,... (N=1, 2)) can be easily adjusted by moving, shortening, or extending the process bars Tna, Tnb,... (N=1, 2).
この後、タッチパネル式表示部16に表示された処理メニューおいて、「共有」を示す項目がユーザによりタッチされると(ステップS15(Yes))、CPU11は、ステップS14にて更新して保存したメモリ12内の各工事工程表画像データ(T1)12e1,(T2)12e2を、当該各工事工程表画像データ(T1)12e1,(T2)12e2に対応付けられた各工事業者の識別子ID1,ID2に基づいて、各工事業者が使用する工事工程表示装置10に送信する(ステップS16)。なおこの際、図6、図7で示したように、各工事業者の工事工程を調整した状態での工事工程表重ね画面Gに対応する工事工程表重ね画像データ12fも加えて、各工事業者が使用する工事工程表示装置10に送信してもよいのは勿論である<工程表画像出力手段>。 After that, when the user touches the item indicating “shared” in the processing menu displayed on the touch panel display unit 16 (step S15 (Yes)), the CPU 11 updates and saves in step S14. The construction process sheet image data (T1) 12e1, (T2) 12e2 in the memory 12 are assigned to the construction process sheet image data (T1) 12e1, (T2) 12e2 by identifiers ID1, ID2 of the respective construction companies. Based on the above, it is transmitted to the construction process display device 10 used by each construction company (step S16). At this time, as shown in FIG. 6 and FIG. 7, each construction company also adds the construction process sheet overlapping image data 12f corresponding to the construction process sheet overlapping screen G in a state where the construction process of each construction company is adjusted. Needless to say, it may be transmitted to the construction process display device 10 used by <procedure table image output means>.
これにより、複数の工事業者間で適切に工事工程を調整した後の新たな工事工程表T1,T2を、各工事業者が容易且つ確実に受け取って、各工事業者が担当する工事を円滑に進めることができる。 Thereby, each construction company can easily and surely receive the new construction process tables T1 and T2 after the construction process is appropriately adjusted among the plurality of construction companies, and the construction undertaken by each construction company can be smoothly advanced. be able to.
なお、メモリ12内の各工事工程表画像データ(T1)12e1,(T2)12e2および工事工程表重ね画像データ12fは、例えば、近距離無線通信部19を介して通信接続された印刷装置へ送信して紙に印刷し、印刷した紙の各工事工程表T1,T2および工事工程表重ね画面Gを各対応する工事業者に渡して情報共有してもよい。 The construction process sheet image data (T1) 12e1, (T2) 12e2 and the construction process sheet overlapping image data 12f in the memory 12 are transmitted to, for example, a printing apparatus communicatively connected via the short-range wireless communication unit 19. Then, the information may be printed on paper, and the construction process charts T1 and T2 and the construction process chart overlapping screen G of the printed paper may be given to the corresponding construction contractors for information sharing.
したがって、このように構成した工事工程表示装置10によれば、複数の工事業者それぞれの工事工程表T1,T2,…を、工事工程表画像データ(T1)12e1,(T2)12e2,…として取り込み<工程表取り込み手段>、取り込んだ各工事工程表画像データ12e1,12e2,…を、当該各画像データ12e1,12e2,…間で同一の作業時期の間隔が合うように拡大または縮小して重ねた工事工程表重ね画像データ12fを生成し<作業時期認識手段><工程表重ね画像生成手段>、生成した工事工程表重ね画像データ12fを工事工程表重ね画面Gとしてタッチパネル式表示部16に表示させる<工程表重ね画像表示手段>。工事工程表重ね画面Gにおいて、例えば、自業者と他業者の工程表T1,T2,…間で作業時期が被るなどの影響ある工程バーTna,Tnb,…(n=1,2,…)を対象に、ユーザがタッチして移動、延長、短縮の操作を行なうと、当該タッチ操作に応じてその対象の工程バーTna,Tnb,…が移動、延長、短縮され、工事工程が調整される<作業時期変更手段>。 Therefore, according to the construction process display device 10 configured as above, the construction process tables T1, T2,... Of the plurality of construction companies are imported as the construction process table image data (T1) 12e1, (T2) 12e2,. <Process table importing means> The acquired construction process table image data 12e1, 12e2,... Are enlarged or reduced so that the image data 12e1, 12e2,. The construction process table overlapping image data 12f is generated <work time recognition means> <process table overlapping image generating means>, and the generated construction process table overlapping image data 12f is displayed on the touch panel type display unit 16 as a construction process table overlapping screen G. <Process table superimposed image display means>. On the construction process table superimposing screen G, for example, process bars Tna, Tnb,... (n=1, 2,...) Affecting the work time between the own company and another company's process tables T1, T2,. When the user touches, moves, extends, or shortens the object, the target process bars Tna, Tnb,... Are moved, extended, or shortened according to the touch operation, and the construction process is adjusted. Work timing changing means>.
そして、工事工程が調整された工事工程表重ね画像データ12fに対応して、各工事工程表画像データ(T1)12e1,(T2)12e2,…が更新され<工程表画像更新手段>、更新された各工事工程表画像データ12e1,12e2,…が、例えば、各工事業者の工事工程表示装置10あるいは情報機器30に送信されて情報共有される<工程表画像出力手段>。 Then, in correspondence with the construction process sheet overlapping image data 12f in which the construction process is adjusted, each construction process sheet image data (T1) 12e1, (T2) 12e2,... Is updated <process sheet image updating means> and is updated. Each of the construction process sheet image data 12e1, 12e2,... Is transmitted to, for example, the construction process display device 10 or the information device 30 of each construction company to share information <process sheet image output means>.
これにより、例えば、工程会議の場において、複数の工事業者がそれぞれ持ち寄った工事工程表が、異なるフォーマットで作成されていたとしても、当該複数の工事業者間での工事工程の調整作業を容易且つ確実に行なうことが可能になる。 Thereby, for example, even if the construction process charts brought in by a plurality of contractors are created in different formats at a process meeting place, it is easy and easy to adjust the construction process among the plurality of contractors. It becomes possible to carry out surely.
また、このように構成した工事工程表示装置10によれば、工事工程表重ね画面G(工事工程表重ね画像データ12f)において、重ねられた各工事工程表画像データ(T1)12e1,(T2)12e2,…間に同一の作業場所を示す表のセルがある場合は、当該同一の作業場所を示す表のセルが識別表示される<作業場所認識手段><作業場所識別表示手段>。 Further, according to the construction process display device 10 configured in this way, on the construction process table overlapping screen G (construction process table overlapping image data 12f), the respective construction process table image data (T1) 12e1, (T2) that are overlapped If there is a cell of the table showing the same work place between 12e2,..., A cell of the table showing the same work place is identified and displayed <Work place recognition means> <Work place identification display means>.
これにより、複数の工事業者間で、同一の作業場所にて、その作業時期が被っていたりいなかったりする工程バーTna,Tnb,…(n=1,2,…)を、容易且つ素早く見つけ出して調整することが可能になる。 This makes it possible for a plurality of contractors to easily and quickly find the process bars Tna, Tnb,... (n=1, 2,...) Which may or may not be subjected to the work at the same work place. Can be adjusted.
なお、本実施形態の工事工程表示装置10では、各工事業者の工事工程表T1,T2,…を、撮像部(カメラ)17により撮影し、工事工程表画像データ12e1,12e2,…として取り込む場合について説明した。これに限らず、紙の工事工程表T1,T2,…を外部のスキャナにより読み取り、工事工程表示装置10に工事工程表画像データ12e1,12e2,…として取り込んだり、各工事業者の情報機器30から送信された工事工程表T1,T2,…の表データを工事工程表示装置10で受信し、工事工程表画像データ12e1,12e2,…に変換して取り込んだりしてもよい。 In the construction process display device 10 of the present embodiment, when the construction process chart T1, T2,... Of each construction contractor is photographed by the imaging unit (camera) 17 and fetched as construction process chart image data 12e1, 12e2,. I explained. Not limited to this, the paper construction process chart T1, T2,... Is read by an external scanner, and is loaded into the construction process display device 10 as construction process chart image data 12e1, 12e2,. The table data of the transmitted construction process charts T1, T2,... May be received by the construction process display device 10 and converted into the construction process chart image data 12e1, 12e2,.
また、本実施形態の工事工程表示装置10において、工事工程表重ね画像データ12fは、各工事工程表画像データ(T1)12e1,(T2)12e2,…の、ユーザが指定したユーザ所望の範囲の作業時期(年、月、週など)だけを切り出して生成可能な構成としてもよい。 Further, in the construction process display device 10 according to the present embodiment, the construction process sheet overlap image data 12f is within a user-specified range of each construction process sheet image data (T1) 12e1, (T2) 12e2,. It may be configured such that only the work period (year, month, week, etc.) is cut out and can be generated.
また、本実施形態の工事工程表示装置10を、大画面のタッチパネル式表示部16を有する情報機器を用いて構成し、例えば、工程会議に集まった複数の工事業者の各々が当該情報機器上に表示された工事工程表重ね画面Gを対象に、互いにタッチ操作し合って工事工程の調整を行なうようにしてもよい。 Further, the construction process display device 10 of the present embodiment is configured by using an information device having a large-screen touch panel type display unit 16, and, for example, each of a plurality of construction companies gathered in a process meeting displays on the information device. The construction process may be adjusted by touching each other on the displayed construction process schedule overlapping screen G.
前記各実施形態において記載した工事工程表示装置10による各処理の手法、すなわち、図3のフローチャートに示す工事工程表示処理等の各手法は、何れもコンピュータに実行させることができるプログラムとして、メモリカード(ROMカード、RAMカード等)、磁気ディスク(フロッピ(登録商標)ディスク、ハードディスク等)、光ディスク(CD−ROM、DVD等)、半導体メモリ等の外部記録装置の媒体に記録して配布することができる。そして、表示部を備えた電子機器のコンピュータ(CPU)は、この外部記録装置の媒体に記録されたプログラムを記憶装置に読み込み、この読み込んだプログラムによって動作が制御されることにより、前記各実施形態において説明した工事工程表示機能を実現し、前述した手法による同様の処理を実行することができる。 The method of each process by the construction process display device 10 described in each of the embodiments, that is, each process such as the construction process display process shown in the flowchart of FIG. 3 is a memory card as a program that can be executed by a computer. (ROM card, RAM card, etc.), magnetic disk (floppy (registered trademark) disk, hard disk, etc.), optical disk (CD-ROM, DVD, etc.), semiconductor memory, and the like can be recorded and distributed on a medium of an external recording device. it can. Then, the computer (CPU) of the electronic device including the display unit reads the program recorded in the medium of the external recording device into the storage device, and the operation is controlled by the read program, whereby each of the embodiments described above is performed. It is possible to realize the construction process display function described in 1 above and execute the same processing by the method described above.
また、前記各手法を実現するためのプログラムのデータは、プログラムコードの形態として通信ネットワーク(N)上を伝送させることができ、この通信ネットワーク(N)に接続されたコンピュータ装置(プログラムサーバ)から前記プログラムのデータを表示部を備えた電子機器に取り込んで記憶装置に記憶させ、前述した工事工程表示機能を実現することもできる。 Further, the data of the program for realizing each of the above methods can be transmitted on the communication network (N) in the form of a program code, and from a computer device (program server) connected to this communication network (N). The program data may be loaded into an electronic device having a display unit and stored in a storage device to realize the above-mentioned construction process display function.
本願発明は、前記各実施形態に限定されるものではなく、実施段階ではその要旨を逸脱しない範囲で種々に変形することが可能である。さらに、前記各実施形態には種々の段階の発明が含まれており、開示される複数の構成要件における適宜な組み合わせにより種々の発明が抽出され得る。例えば、各実施形態に示される全構成要件から幾つかの構成要件が削除されたり、幾つかの構成要件が異なる形態にして組み合わされても、発明が解決しようとする課題の欄で述べた課題が解決でき、発明の効果の欄で述べられている効果が得られる場合には、この構成要件が削除されたり組み合わされた構成が発明として抽出され得るものである。 The invention of the present application is not limited to the above-described embodiments, and can be variously modified at the stage of implementation without departing from the spirit of the invention. Furthermore, each of the embodiments includes inventions at various stages, and various inventions can be extracted by appropriately combining a plurality of disclosed constituent elements. For example, even if some constituent elements are deleted from all the constituent elements shown in each embodiment, or some constituent elements are combined in different forms, the problems described in the section of the problem to be solved by the invention When the above can be solved and the effects described in the section of the effects of the invention can be obtained, a structure in which these constituent requirements are deleted or combined can be extracted as the invention.
10…工事工程表示装置、11…CPU、12…メモリ、
12a…工事工程表示処理プログラム、12b…画像/図形処理プログラム、
12c…作業時期認識データ、12d…作業場所認識データ、
12e1,12e2,…工事工程表画像データ、12f…工事工程表重ね画像データ、
13…記録媒体読取部、14…外部記録媒体、15…通信部、
16…タッチパネル式表示部、17…撮像部、19…近距離無線通信部、
20…Webサーバ、30…外部機器、T1,T2,…工事工程表、
Tna,Tnb,…工程バー、A1,A2,B1,B2,…作業時期識別マーク、
M…作業場所識別マーク、G…工事工程表重ね画面。
10... Construction process display device, 11... CPU, 12... Memory,
12a... Construction process display processing program, 12b... Image/graphics processing program,
12c... work time recognition data, 12d... work place recognition data,
12e1, 12e2,... Construction process sheet image data, 12f... Construction process sheet overlapping image data,
13... Recording medium reading unit, 14... External recording medium, 15... Communication unit,
16... Touch panel type display part, 17... Imaging part, 19... Short-distance wireless communication part,
20... Web server, 30... External device, T1, T2,... Construction process table,
Tna, Tnb,... Process bar, A1, A2, B1, B2,... Work time identification mark,
M: Work place identification mark, G: Construction process table overlapping screen.
Claims (8)
前記工程表取り込み手段により取り込まれた複数の工事工程表の画像データを、各工事工程表の同一の作業時期を示す間隔を対応させて重ねた工事工程表重ね画像データを生成する工程表重ね画像生成手段と、
前記工程表重ね画像生成手段により生成された工事工程表重ね画像データを表示部に表示させる工程表重ね画像表示手段と、
を備えた工事工程表示装置。 A process chart importing means for capturing a plurality of construction process charts as image data,
Image data of a plurality of construction process charts captured by the process schedule capturing means are superposed in correspondence with intervals indicating the same work time of each construction process schedule to generate construction process schedule superimposed image data. Generating means,
A process table superimposed image display means for displaying the construction process table superimposed image data generated by the process table superimposed image generating means on a display unit,
Construction process display device.
を備えた請求項1に記載の工事工程表示装置。 The rod-shaped display body indicating the range of the work period included in each construction process schedule of the construction process schedule superposition image data displayed by the process schedule superposition image display means is moved or extended or shortened to be changed according to a user operation. Work time change means,
The construction process display device according to claim 1, further comprising:
前記工程表画像更新手段により更新された工事工程表の画像データを外部に出力する工程表画像出力手段と、
を備えた請求項2に記載の工事工程表示装置。 A process table image updating means for updating the image data of the construction process table taken in by the process table taking means, corresponding to the construction process table overlapping image data after changing the rod-shaped display body by the work time changing means; ,
A process table image output means for outputting image data of the construction process table updated by the process table image updating means to the outside,
The construction process display device according to claim 2, further comprising:
前記工程表取り込み手段により取り込まれた複数の工事工程表の画像データの各工事工程表に含まれる作業時期を認識する作業時期認識手段を有し、
前記作業時期認識手段により認識された各工事工程表に含まれる作業時期に基づいて、各工事工程表の同一の作業時期を示す間隔を対応させて重ねてなる工事工程表重ね画像データを生成する、
請求項1ないし請求項3の何れか一項に記載の工事工程表示装置。 The process table superimposed image generating means,
A work time recognition means for recognizing a work time included in each construction process schedule of the image data of the plurality of construction process schedules captured by the process schedule capturing means;
Based on the work timings included in each construction process schedule recognized by the work timing recognition means, construction process schedule superposed image data in which the intervals indicating the same work timing of each construction schedule are overlapped correspondingly is generated. ,
The construction process display device according to any one of claims 1 to 3.
前記作業場所認識手段により認識された各工事工程表に含まれる作業場所に基づいて、前記工程表重ね画像表示手段により表示部に表示された工事工程表重ね画像データの各工事工程表に含まれる同一の作業場所を識別表示させる作業場所識別表示手段と、
を備えた請求項1ないし請求項4の何れか一項に記載の工事工程表示装置。 Work location recognition means for recognizing a work location included in each construction process chart of the image data of the plurality of construction process charts captured by the process chart capturing means;
Based on the work location included in each construction process chart recognized by the work location recognizing means, included in each construction process chart of the construction process chart superposed image data displayed on the display unit by the work schedule superposed image display means. Work place identification display means for identifying and displaying the same work place,
The construction process display device according to any one of claims 1 to 4, further comprising:
前記作業時期変更手段は、前記タッチパネル式表示部に対するユーザのタッチ操作に応じて、前記工程表重ね画像表示手段により表示された工事工程表重ね画像データの各工事工程表に含まれる作業時期の範囲を示す棒状表示体を移動または延長または短縮して変更する、
請求項2又は請求項3に記載の工事工程表示装置。 The display unit is a touch panel type display unit,
The work timing changing means includes a range of work timings included in each construction process chart of the construction process schedule superimposing image data displayed by the work schedule superimposing image displaying means in response to a user's touch operation on the touch panel display unit. Change or move or extend or shorten the bar-shaped display
The construction process display device according to claim 2 or claim 3.
請求項3に記載の工事工程表示装置。 The work schedule image output means, the construction work schedule overlapping image data after changing the rod-shaped display body by the work timing changing means, and the construction process schedule image data updated by the work schedule image updating means, Output to the outside,
The construction process display device according to claim 3.
複数の工事工程表をそれぞれ画像データとして取り込む工程表取り込み手段、
前記工程表取り込み手段により取り込まれた複数の工事工程表の画像データを、各工事工程表の同一の作業時期を示す間隔を対応させて重ねた工事工程表重ね画像データを生成する工程表重ね画像生成手段、
前記工程表重ね画像生成手段により生成された工事工程表重ね画像データを前記表示部に表示させる工程表重ね画像表示手段、
として機能させるためのコンピュータ読み込み可能な工事工程表示処理プログラム。 A computer of electronic equipment equipped with a display unit,
A process chart importing unit that captures a plurality of construction schedules as image data,
Image data of a plurality of construction process charts captured by the process schedule capturing means are superposed in correspondence with intervals indicating the same work time of each construction process schedule to generate construction process schedule superimposed image data. Generation means,
A process table superimposed image display means for displaying the construction process table superimposed image data generated by the process table superimposed image generating means on the display unit,
A computer-readable construction process display processing program that functions as a computer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2018218383A JP2020086768A (en) | 2018-11-21 | 2018-11-21 | Apparatus and processing program for displaying construction process |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2018218383A JP2020086768A (en) | 2018-11-21 | 2018-11-21 | Apparatus and processing program for displaying construction process |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2020086768A true JP2020086768A (en) | 2020-06-04 |
Family
ID=70908170
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2018218383A Pending JP2020086768A (en) | 2018-11-21 | 2018-11-21 | Apparatus and processing program for displaying construction process |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2020086768A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06233032A (en) * | 1993-02-04 | 1994-08-19 | Kajima Corp | Black board information output processor |
JPH0830678A (en) * | 1994-07-12 | 1996-02-02 | Fujitsu Ltd | Schedule control processor |
JP2007072937A (en) * | 2005-09-09 | 2007-03-22 | Delta Archi Tects:Kk | Construction information distribution server and construction information distribution system |
JP2011253347A (en) * | 2010-06-02 | 2011-12-15 | Hitachi-Ge Nuclear Energy Ltd | Carry-in plan planning support system |
JP2015176240A (en) * | 2014-03-13 | 2015-10-05 | トヨタ自動車株式会社 | work plan display system |
-
2018
- 2018-11-21 JP JP2018218383A patent/JP2020086768A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06233032A (en) * | 1993-02-04 | 1994-08-19 | Kajima Corp | Black board information output processor |
JPH0830678A (en) * | 1994-07-12 | 1996-02-02 | Fujitsu Ltd | Schedule control processor |
JP2007072937A (en) * | 2005-09-09 | 2007-03-22 | Delta Archi Tects:Kk | Construction information distribution server and construction information distribution system |
JP2011253347A (en) * | 2010-06-02 | 2011-12-15 | Hitachi-Ge Nuclear Energy Ltd | Carry-in plan planning support system |
JP2015176240A (en) * | 2014-03-13 | 2015-10-05 | トヨタ自動車株式会社 | work plan display system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5835780B2 (en) | Construction site photography program | |
JP6578897B2 (en) | Information processing apparatus and information processing program | |
JP2008186095A (en) | Image processor, image processing method and program | |
JP2011199450A (en) | Conference system, information processing apparatus, display method, and display program | |
US11216611B2 (en) | Information processing apparatus and non-transitory computer readable medium | |
JP5491774B2 (en) | Data entry system and data entry method | |
JP2020086768A (en) | Apparatus and processing program for displaying construction process | |
JP2018049450A (en) | Display control method and display device | |
JP2017174248A (en) | Information processing device and information processing program | |
EP3483826A1 (en) | Content providing apparatus and computer program | |
JP6759868B2 (en) | Information processing equipment and information processing programs | |
JP2019139332A (en) | Information processor, information processing method and information processing program | |
JP2008118317A (en) | Projection device | |
JP2008033682A (en) | Document creation support device and document creation support method | |
JP3679628B2 (en) | Image processing method and apparatus | |
JP7331378B2 (en) | Information processing device and information processing program | |
JP6780392B2 (en) | Information processing equipment and information processing programs | |
KR102189292B1 (en) | Method for displaying chart and apparatus using the same | |
JP6702031B2 (en) | Information processing system and information processing program | |
US20190220802A1 (en) | Information processing apparatus and non-transitory computer readable medium | |
JP2006235835A (en) | Blackboard display system for construction | |
JP2019090848A (en) | Projector, control method thereof, program, and projection system | |
JP7524624B2 (en) | Image forming device | |
WO2022107261A1 (en) | Operation monitoring device, operation monitoring method, and operation monitoring program | |
JP2009145926A (en) | Image operation device and image operation program and recording medium and image operation method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20210908 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20220628 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20220726 |
|
RD01 | Notification of change of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: A7421 Effective date: 20230105 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20230131 |