JP2019073847A - Method for fixing precast floor slab steel girder - Google Patents

Method for fixing precast floor slab steel girder Download PDF

Info

Publication number
JP2019073847A
JP2019073847A JP2017198120A JP2017198120A JP2019073847A JP 2019073847 A JP2019073847 A JP 2019073847A JP 2017198120 A JP2017198120 A JP 2017198120A JP 2017198120 A JP2017198120 A JP 2017198120A JP 2019073847 A JP2019073847 A JP 2019073847A
Authority
JP
Japan
Prior art keywords
floor slab
steel girder
fixing
new
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2017198120A
Other languages
Japanese (ja)
Other versions
JP6785739B2 (en
Inventor
俊一 山岸
Toshikazu Yamagishi
俊一 山岸
肇明 王
Tadaaki O
肇明 王
祐二 岩瀬
Yuji Iwase
祐二 岩瀬
義隆 東
Yoshitaka Azuma
義隆 東
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kawada Construction Co Ltd
Original Assignee
Kawada Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawada Construction Co Ltd filed Critical Kawada Construction Co Ltd
Priority to JP2017198120A priority Critical patent/JP6785739B2/en
Publication of JP2019073847A publication Critical patent/JP2019073847A/en
Application granted granted Critical
Publication of JP6785739B2 publication Critical patent/JP6785739B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

To provide a method for fixing a precast floor slab steel girder which ensures drying time while applying a full surface coating of a prescribed thickness in a corrosion prevention treatment, and allows moving to a next process of floor slab erection without delaying the process.SOLUTION: A new floor slab 3 is placed on a steel girder 1 with a height adjustment jig 2 interposed without waiting for a corrosion prevention treatment to dry after being passed through a steel girder treatment process. The steel girder 1 and the new floor slab 3 are connected using a fixing jig 4 to allow fixing in a state without a concrete form installed. In a concrete form installation process, a concrete form material 12 having an L-shaped cross section is brought into contact with the steel girder 1 using a concrete form support material 8. A non-contracting mortar 14 is filled in a the gap between the new floor slab 3 and the steel girder 1 per one span. After the mortar hardens, the fixing jig 4, the concrete form support material 8, and the like are all removed.SELECTED DRAWING: Figure 2

Description

この発明は、鋼桁上にコンクリート床版を載置する鋼橋で、既設のコンクリート床版をプレキャスト床版に取り換える鋼橋更新工事におけるプレキャスト床版の鋼桁固定方法に関する。   The present invention relates to a steel girder fixing method for a precast floor slab in a steel bridge renewal work in which a concrete floor slab is placed on a steel girder and an existing concrete floor slab is replaced with a precast floor slab.

道路インフラの老朽化が顕著となり、それらのうち、鋼橋の長寿命化の一方策として、自動車荷重の繰返し載荷による疲労や凍結防止剤散布による塩害などで変状が生じた鉄筋コンクリート床版をプレキャスト床版に取り換える大規模更新工事が実施されている。   Aging of road infrastructure is remarkable, and among them, as a measure for prolonging the life of steel bridges, precast concrete reinforced concrete floor slabs that are damaged due to fatigue caused by repeated loading of automobile load and salt damage caused by antifreeze agent spraying. A large-scale renewal work is being carried out to replace the floor slab.

対象となる橋梁は高速道路や幹線道路など、経済活動にとって無くてはならない基幹インフラであるため、長期間にわたる工事占有はできず、1〜2ヶ月間といった非常に短い工期の中で、既設床版等の撤去から新設床版の設置、舗装敷設等の施工を行う必要がある。   The target bridge is a basic infrastructure that is essential for economic activities, such as expressways and highways, so long-term construction can not be carried out for a long period of time, and existing floors can not be constructed within a very short construction period such as one to two months. It is necessary to set up a new floor slab and to carry out construction such as paving from removal of a plate etc.

この更新工事は、先ず既設の劣化した鉄筋コンクリート床版の撤去を行い、鋼桁のフランジ上面に付着したコンクリートなどをはつり取り、ケレンして清掃した後、複数本の鋼桁の上面橋軸方向に、1.5m〜2.5m程度に分割したプレキャスト床版を敷設するものである。   In this renewal work, first remove the existing deteriorated reinforced concrete floor slab, remove concrete etc. adhering to the upper surface of the flange of the steel girder, clean it and clean it, and then, in the axial direction of the upper surface bridge of multiple steel girder. , 1.5m ~ 2.5m is to lay a precast floor slab divided.

このプレキャスト床版の架設に際し、橋梁の縦横断勾配や施工誤差を吸収するために新設床版を鋼桁の上フランジ上面に対し隙間をあけて設置し、新設床版と鋼桁との間に厚さ40mm程度の無収縮モルタルを充填している。   When installing this precast floor slab, a new floor slab will be installed with a gap from the top of the upper flange of the steel girder to absorb the vertical cross slope of the bridge and construction errors, and between the new floor slab and the steel girder It is filled with non-shrink mortar with a thickness of about 40 mm.

更新工事の中で最も品質上重要な工種は、既設床版撤去後に行う鋼桁上フランジ上面のケレンと防錆処置、新設床版の設置後に行う鋼桁上フランジ上面とプレキャスト床版下面の隙間への無収縮モルタルの充填、特にモルタル用の型枠設置の2つの工種である。   The most important quality-relevant work types in the renewal work are kerens and anti-corrosion treatment on the upper surface of the steel girder upper surface after removal of the existing floor slab, and a clearance between the upper surface of the steel girder upper surface and the lower surface of the precast floor surface There are two types of filling, non-shrinkage mortar filling, in particular the installation of formwork for mortar.

従来のモルタル用型枠としては、例えば特許文献1に記載されるような、床版と鋼桁のフランジとの間に挟み込む硬質ゴム等の弾性力を備える型枠材が採用されてきた。
特開平10−96209号公報
As a conventional mortar form, for example, a form having elastic force such as hard rubber sandwiched between a floor plate and a flange of a steel girder as described in Patent Document 1 has been adopted.
JP 10-96209 A

この型枠材の場合、角柱状の硬質ゴムや硬質スポンジ(以下、スポンジゴムという)を鋼桁上フランジ上面に糊で接着するものであった。このような型枠材を用いる鋼橋更新工事の従来の施工方法を図3及び図4を用いて説明する。図3は従来の鋼橋更新工事におけるプレキャスト床版載置状況を示す底面図、図4は従来の鋼橋更新工事を行う場合の工程を示す説明図である。   In the case of this formwork material, a prismatic hard rubber or hard sponge (hereinafter referred to as sponge rubber) is adhered to the upper surface of the upper flange of the steel girder with glue. The conventional construction method of steel bridge renewal work using such a formwork material is demonstrated using FIG.3 and FIG.4. FIG. 3 is a bottom view showing the installation situation of precast floor slabs in the conventional steel bridge renewal work, and FIG. 4 is an explanatory view showing a process in the case of performing the conventional steel bridge renewal work.

図4(a)に示すように、鋼桁1上に載置していた図示しない既設のコンクリート床版を撤去した後は、上フランジ1aの上面1bのケレンと防錆処置を行う鋼桁処置工程を先行する。これは、鋼桁1に付着したコンクリートなどのはつり及びケレン清掃した後、外環境に触れる可能性がある上フランジ1aの外縁部、すなわちスポンジゴムによる型枠材100と上フランジ1aが接する箇所に対して速乾性の有機ジンクリッチペイントやローバルなどの防錆塗料による防錆処置を行うものであった。   As shown in FIG. 4 (a), after removing the existing concrete floor slab (not shown) placed on the steel girder 1, the steel girder treatment is performed to remove rust from the upper surface 1b of the upper flange 1a. The process precedes. This is because the outer edge portion of the upper flange 1a which may touch the external environment after cleaning the concrete and the like attached to the steel girder 1, that is, the location where the form material 100 made of sponge rubber and the upper flange 1a contact. On the other hand, anti-corrosion treatment was carried out with anti-corrosion paint such as quick-drying organic zinc rich paint and Loval.

この鋼桁処置工程を経た後、上フランジ1aの上面1bに角柱状のスポンジゴムによる型枠材100を貼り付け(図4(b))、更に上フランジ1a上に高さ調整治具2を適宜配置しながら、プレキャストコンクリートで作製した新設床版3を載置し(図4(c))、その後新設床版3と上フランジ1a上面との隙間内に無収縮モルタル14を充填するものであった(図4(d))。   After this steel girder treatment process, a form material 100 made of square pillar-shaped sponge rubber is attached to the upper surface 1b of the upper flange 1a (FIG. 4 (b)), and the height adjusting jig 2 is further mounted on the upper flange 1a. Place the new floor 3 made of precast concrete while placing it properly (Fig. 4 (c)), and then fill the gap between the new floor 3 and the upper surface of the upper flange 1a with the non-shrinkage mortar 14 There was (Fig. 4 (d)).

ところでこのような鋼橋の更新工事では、非常に短い工期等の制約条件の中で床版の取替えを終了させるために、既設床版の撤去から新設床版の設置までをクレーン1基あたり1日6枚程度の施工速度で行う必要がある。一方、施工を進める上で、品質上重要な工種は道路管理者の検査確認を受ける必要があり、このような工種は目視確認できる昼間のうちの作業としなければならない。従って、昼間のうちに鋼桁上フランジ上面の防錆処置とモルタル用の型枠設置が完了して、これらの検査確認を受けなければ次工程を進めることができなかった。   By the way, in such renewal work of steel bridges, in order to complete the replacement of the floor under the constraints such as very short construction period, 1 crane per removal from the existing floor to installation of the new floor is required. It is necessary to carry out at a construction speed of about six days. On the other hand, in order to proceed with construction, it is necessary for the type of work that is important for quality to be subject to the inspection confirmation of the road administrator, and such work type must be done during the daytime when visual confirmation can be made. Therefore, after the anticorrosion treatment on the upper surface of the upper flange of the steel girder and the installation of a mold for mortar were completed in the daytime, the next process could not be advanced unless these inspections were confirmed.

このため従来の更新工事では、既設床版の撤去・ケレン・防錆処置・モルタル用型枠設置までを行う昼間班と、その後の新設床版の設置・スタッド溶稙・モルタル充填までを行う夜間班との2交代制を採っていた。この場合、前述した品質上重要な2つの工種が昼間班における1日の作業内容の後半に偏ることになっていた。   For this reason, in the conventional renewal work, the daytime weir to remove the existing floor slab-installation of the kelen, anti-corrosion treatment and mortar formwork, and the nighttime to install the new floor slab thereafter-stud molten metal and mortar filling It had a two-shift system with the nephew. In this case, the two quality-important work types mentioned above are biased in the latter half of the daily work contents in the daytime weir.

施工の合理性を求めて、数量の少ない工種であるスタッド溶稙・モルタル充填を鋼橋の1径間単位に集約する場合が増えてきていた。   In order to find the rationality of construction, cases have been increasing in which stud molten metal and mortar filling, which is a small amount of work, are consolidated into one span unit of a steel bridge.

従来の鋼橋の更新工事で1日ごとにプレキャスト床版をスタッド溶稙とモルタル充填で鋼桁に固定する場合には、次工程のモルタル用型枠設置を速やかに行う必要があるため、乾燥時間を考慮して所定厚の塗り込みができていない問題点があった。   In the case of fixing the precast floor slab to the steel girder with stud molten metal and mortar filling every day in the renewal work of the conventional steel bridge, it is necessary to quickly install the mortar formwork for the next process, so drying There was a problem that the coating of the predetermined thickness was not completed in consideration of the time.

一方、新設プレキャスト床版を1径間単位で載置する場合、施工時の工事車両による鋼桁のたわみや揺れなどにより架設済みのプレキャスト床版が動いてしまい、完成時に床版出来形が確保できなくなることが懸念されるため、床版架設の都度に速やかに固定したいという要請もあった。   On the other hand, when placing a new precast floor slab in one span unit, the precast floor slab already installed moves due to the deflection or shaking of the steel girder by the construction vehicle at the time of construction, and the floor slab completion form is secured There is also a demand that it be fixed promptly each time the floor plate is erected because there is a concern that it will not be possible.

又、1径間単位でモルタルを充填する場合には、モルタルによってフランジ面が被覆されるまでに日数が経過することになり、全面ケレンした鋼フランジが再発錆してしまうため、床版架設前にフランジ全面に防錆処置を施す必要がある。この塗装の乾燥時間を考慮すると型枠設置及び新設床版の架設に遅れが生じてしまう問題点があった。   In addition, when mortar is filled in one span unit, the number of days elapses until the flange surface is covered with the mortar, and the steel flange which has been fully surfaced will be re-rusted before the floor plate construction It is necessary to apply anticorrosion measures to the entire surface of the flange. Considering the drying time of the coating, there is a problem that a delay occurs in the installation of the formwork and the construction of the new floor slab.

ところで従来の型枠材でスポンジゴムを用いない場合には、鋼製の山形鋼を鋼フランジに溶接することもあったが、山形鋼を溶接して型枠とする場合には、現場溶接作業が必要であることに加え、既設橋の出来形に合わせた誤差吸収は難しく、さらに山形鋼の塗装が困難であるといった問題点があった。   By the way, when sponge rubber was not used by the conventional formwork material, steel angle steel was sometimes welded to a steel flange, but when welding an angle steel to make a formwork, on-site welding work In addition, it is difficult to absorb errors in accordance with the shape of the existing bridge, and it is also difficult to coat the angle steel.

一方、スポンジゴムを型枠として用いる場合には幾分誤差を吸収する可能性はあったが、鋼桁上フランジの板厚が変化する場合には追従が困難になりがちであった。新設の鋼橋の場合、例えば新東名高速道路のプレキャスト床版では、上フランジの板厚変化を下側に変更して上面を平滑にするなどスポンジゴムでの施工性が考慮された設計を行うことで対応していたが、更新工事の対象となる古い橋梁では、板厚変化が上側であるばかりか、板幅変化も非常に多く、特に図3に示すような鋼桁の添接部1cについては添接板や高力ボルトが上フランジ外縁近くまで配置されるため、高力ボルトのかぶりを考慮したスポンジゴムの設置ができないのが現状であった。   On the other hand, when sponge rubber was used as a mold, there was a possibility of absorbing some errors, but when the plate thickness of the steel girder upper flange changed, it tended to be difficult to follow. In the case of a new steel bridge, for example, in the case of a precast floor slab of the Shin-Tomei Expressway, the design is considered in consideration of the workability with sponge rubber, such as changing the plate thickness change of the upper flange downward and smoothing the upper surface However, in the case of the old bridge to be subjected to the renewal work, not only the plate thickness change is on the upper side, but also the plate width change is very large, especially the welded joint 1c of the steel girder as shown in FIG. In the current situation, it was impossible to install sponge rubber considering the fog of the high strength bolt because the joint plate and the high strength bolt were placed close to the upper flange outer edge.

そのため、添接部では高力ボルトのかぶりを無視して、ボルトと干渉する部位のスポンジゴムを切り欠いて設置したり、添接部の鋼フランジにスポンジゴム支持用の鋼板を現場仮溶接(図3の添接拡幅部1c)してボルトのかぶりを確保するなど種々の工夫がなされているものの品質と出来栄えを満たす方法は見つかっていないのが現状であった。   Therefore, neglect the fog of high strength bolt in the joint part and cut out and install the sponge rubber of the part that interferes with the bolt, or temporarily weld the steel rubber supporting steel sheet to the steel flange of the joint part At present, no method has been found to satisfy the quality and quality of the products although various improvements have been made such as securing the fog of the bolt by means of the attachment widening portion 1c of FIG.

この発明は、従来の鋼橋更新工事におけるプレキャスト床版の鋼桁固定方法が有する上記の問題点を解消すべくなされたものであり、防錆処置における所定厚の全面塗装を行って鋼桁の高耐久化を可能とすると共に塗装の乾燥時間を確保しながら次工程の床版架設に移ることを可能として、従来工法と比較しても工程の遅延がないプレキャスト床版の鋼桁固定方法を提供することを目的としている。   The present invention has been made to solve the above-mentioned problems with the method of fixing steel girder of precast floor slab in the conventional steel bridge renewal work. A method of fixing steel girders of precast floor slabs with no delay in the process compared to the conventional method, as it is possible to move to floor plate construction of the next process while securing high drying time and securing the drying time of painting. It is intended to be provided.

又、プレキャスト床版を架設の都度、安全に速やかに設置することが可能で、プレキャスト床版を確実に固定して完成時の床版出来形が確保でき、床版施工の高精度化が図れるプレキャスト床版の鋼桁固定方法を提供することを目的としている。   Also, each time a precast floor slab is erected, it can be safely and promptly installed, and the precast floor slab can be securely fixed to ensure completion of the floor slab at the time of completion, and high precision of floor slab construction can be achieved. The purpose is to provide a method for fixing steel girder of precast floor slabs.

又、透明な型枠材を用いた場合にはモルタル部の充填確認が可能で将来劣化後の脱落等のリスクがない型枠材を用いるプレキャスト床版の鋼桁固定方法を提供することを目的としている。   In addition, it is an object of the present invention to provide a method of fixing steel girder of a precast floor slab using a formwork material which enables filling confirmation of the mortar part when transparent formwork material is used and there is no risk of falling off after deterioration in the future. And

上記課題を解決するため、この発明のプレキャスト床版の鋼桁固定方法は、鋼桁上にコンクリート床版を載置する鋼橋で既設のコンクリート床版をプレキャスト床版に取り換え固定するため、既設コンクリート床版の撤去を行った後、鋼桁の上フランジ上面のケレンと防錆処置を行う鋼桁処置工程と、新設のプレキャスト床版を前記上フランジ上面に対し隙間をあけて載置する新設床版載置工程と、この新設床版と前記上フランジ上面との隙間を塞ぐ型枠材を設置する型枠設置工程と、この隙間内に無収縮モルタルを充填するモルタル充填工程を有するプレキャスト床版の鋼桁固定方法において、前記新設床版載置工程は、前記鋼桁処置工程を行った後、前記新設床版と前記上フランジ上面の間に高さ調整治具を介在させながら、前記新設床版に取付けて垂下する固定治具を前記上フランジ下面に当接することで前記新設床版を鋼桁に固定する新設床版載置固定工程であり、前記型枠設置工程は、前記新設床版に取付けて垂下する型枠支持材を用いて前記型枠材の下部を前記上フランジの側面に当接して固定する型枠設置工程であることを特徴とするものである。   In order to solve the above problems, the method for fixing steel girder of precast floor slab according to the present invention is to replace the existing concrete floor slab with the precast floor slab by steel bridge which mounts the concrete floor slab on the steel girder. After removal of the concrete floor slab, the steel girder treatment process to carry out anti-corrosion treatment with kerens on the upper flange upper surface of the steel girder, and a new construction in which a new precast floor slab is placed with a clearance from the upper flange upper surface. Precast floor having a floor plate setting process, a frame installation process for installing a frame material for closing the gap between the new floor plate and the upper surface of the upper flange, and a mortar filling process for filling non-shrinkage mortar in the gap In the method of fixing a steel girder of a plate, the new-floor-placement step includes the step of treating the steel girder, and then interposing a height adjustment jig between the new-build floor and the upper flange upper surface. New floor A new installation floor fixation step of fixing the new installation floor to the steel girder by contacting a fixing jig attached to the lower flange and affixing the suspension to the lower surface of the upper flange, and the form installation process is performed on the new installation floor It is characterized in that it is a formwork installation process which abuts and fixes the lower part of the above-mentioned formwork material to the side of the above-mentioned upper flange using the formwork support material which attaches and hangs down.

高さ調整治具は、上フランジ上面に適宜載置してモルタル内に埋設可能な素材とするか、あるいは新設床版に挿入螺合して先端部を上フランジ上面に当接する高さ調整可能なボルト等を用いる。   The height adjustment jig can be appropriately placed on the upper surface of the upper flange to make it a material that can be embedded in the mortar, or it can be adjusted in height by inserting and screwing a new floor plate and contacting the tip with the upper surface of the upper flange Use a bolt or the like.

固定治具は、新設床版下面に先埋めされたインサートに螺着するボルトを垂下して、これに固定用板材を取り付け、その一端部を上フランジ下面側に配置し、鋼桁と新設床版を接続して固定する。   Fixing jigs are made by hanging a bolt to be screwed to the insert that is pre-filled on the lower surface of the new floor, attaching a fixing plate to this, arranging one end on the lower surface side of the upper flange, steel girder and new floor Connect and fix the plate.

型枠支持材は、新設床版下面に先埋めされたインサートに螺着するボルトを垂下して、これに型枠材及び新設床版に当接する型枠押さえ材と、この型枠押さえ材を支持する横端太材及び締結材を有する。   The formwork support material is obtained by hanging down a bolt screwed to an insert pre-filled on the lower surface of the new floor slab, to which a formwork pressing material to be in contact with the formwork material and the new floor slab, and this formwork presser material It has a horizontal end material and a fastening material to support.

請求項2記載のプレキャスト床版の鋼桁固定方法における新設床版載置固定工程は、前記鋼桁処置工程を行った後、防錆処置の乾燥を待たずに前記新設床版を鋼桁に固定することを特徴とするものである。型枠材の設置は、鋼桁上フランジ上面の防錆処置が完了した後、道路管理者の検査確認を受け、その後行う。   In the method for fixing a steel girder of a precast floor slab according to claim 2, the installation and fixing process of the new gullet performs the treatment process for the steel girder, and then waits for the rust prevention treatment to dry. It is characterized by fixing. Installation of the formwork material is carried out after receiving an inspection confirmation from the road administrator after the anticorrosion treatment on the upper surface of the steel girder upper flange is completed.

請求項3記載のプレキャスト床版の鋼桁固定方法における型枠設置工程は、一辺が前記上フランジの側面に当接し他辺が前記新設床版の下面に当接する断面L型の型枠材を用いることを特徴とするものである。型枠材は加工が容易な材料が望ましくモルタル硬化後に撤去する。   The mold installation step in the method for fixing steel girder of precast floor slab according to claim 3 is a molding material having an L-shaped cross section in which one side abuts the side surface of the upper flange and the other side abuts the lower surface of the new floor slab It is characterized by using. The form material is preferably a material that is easy to process, and is removed after mortar hardening.

請求項4記載のプレキャスト床版の鋼桁固定方法における断面L型の型枠材は、モルタル充填状況を直接目視確認し得る透明な型枠材を用いることを特徴とするものである。型枠材は透過性を備える合成樹脂材を用いるのが望ましい。   In the method for fixing a steel girder of a precast floor slab according to claim 4, a form material having an L-shaped cross section is characterized by using a transparent form material capable of directly visually confirming the mortar filling condition. It is desirable to use a synthetic resin material having permeability for the form material.

この発明のプレキャスト床版の鋼桁固定方法は、新設床版に取付けて垂下する型枠支持材を用い、型枠材の下部を上フランジの側面に当接して固定する型枠設置工程を設けるので、モルタル硬化後に脱型することができ、スポンジゴムのような異物を床版内に留める必要がないため将来劣化後の脱落等のリスクがない。   The method of fixing steel girder of precast floor slab according to the present invention comprises using a form supporting member which is attached to a new floor version and suspended, and providing a form setting process of fixing the lower part of the form material in contact with the side of the upper flange Therefore, it is possible to demold after hardening of the mortar, and there is no risk of falling off after deterioration in the future because it is not necessary to keep foreign substances such as sponge rubber in the floor plate.

又、新設床版を鋼桁に固定するので架設の都度、安全に速やかに設置することが可能となり、平面・高さなどの完成時の床版出来形を確保して、床版施工の高精度化が図れる。又、型枠を後付け構造とするので、鋼桁上フランジ上面の防錆塗装の乾燥時間を確保できるため所定厚の全面塗装を行うことができ鋼桁の高耐久化が期待できる。   In addition, because the new floor slab is fixed to the steel girder, it becomes possible to install safely and promptly each time of erection, and the floor slab completion form at the time of completion such as plane and height is secured, and the height of floor slab construction is high. Accuracy can be improved. In addition, since the formwork has a retrofit structure, the drying time of the rustproof coating on the upper surface of the upper flange of the steel girder can be secured, so that the entire surface can be coated with a predetermined thickness, and high durability of the steel girder can be expected.

請求項2記載のプレキャスト床版の鋼桁固定方法は、鋼桁処置工程を行った後、防錆処置の乾燥を待たずに新設床版を鋼桁に固定するので、従来工法と同等以上の施工スピードが期待できる。   In the method of fixing steel girder of precast floor slab according to claim 2, after carrying out the steel girder treatment process, the new girder is fixed to the steel girder without waiting for drying of the anticorrosion treatment. Construction speed can be expected.

請求項3記載のプレキャスト床版の鋼桁固定方法は、断面L型の型枠材を用いるので型枠の組み立て・解体作業が容易となる。   In the method of fixing a steel girder of a precast floor slab according to a third aspect of the present invention, since the L-shaped cross section is used, the work of assembling and disassembling the form becomes easy.

請求項4記載のプレキャスト床版の鋼桁固定方法は、透明な型枠材を用いるのでモルタル充填状況を直接目視確認でき、モルタルの充填不良を防止して見映えと維持管理性に優れる。   In the method of fixing a steel girder of a precast floor slab according to claim 4, since the transparent formwork material is used, the mortar filling condition can be directly visually confirmed, and the filling defect of the mortar is prevented, and the appearance and maintenance management are excellent.

鋼橋更新工事におけるプレキャスト床版載置状況の底面図である。It is a bottom view of the precast floor slab placement situation in steel bridge renewal construction. 鋼橋更新工事を行う場合の工程を示す説明図である。It is explanatory drawing which shows the process in the case of performing steel bridge update construction. 従来の鋼橋更新工事におけるプレキャスト床版載置状況の底面図である。It is a bottom view of the precast floor slab mounting condition in the conventional steel bridge renewal construction. 従来の鋼橋更新工事を行う場合の工程を示す説明図である。It is explanatory drawing which shows the process in the case of performing the conventional steel bridge update construction.

次にこの発明の実施の形態を添付図面に基づき詳細に説明する。図1は鋼橋更新工事におけるプレキャスト床版載置状況の底面図、図2は鋼橋更新工事を行う場合の工程を示す説明図である。   Next, an embodiment of the present invention will be described in detail based on the attached drawings. FIG. 1 is a bottom view of a precast floor slab installation situation in steel bridge renewal work, and FIG. 2 is an explanatory view showing a process of steel bridge renewal work.

図2(a)に示すように、鋼桁1上に載置していた図示しない既設のコンクリート床版を撤去した後は、上フランジ1aの上面1bのケレンと防錆処置を行う鋼桁処置工程を先行する。鋼桁1に付着したコンクリートなどのはつり及びケレン清掃した後、防錆塗料による防錆処置を行う。フランジ面への塗装は、スプレーあるいはハケ塗りで有機ジンクリッチペイントを例えば60μm程度塗布する。   As shown in FIG. 2 (a), after removing the existing concrete floor slab (not shown) placed on the steel girder 1, the steel girder treatment is performed to remove rust from the upper surface 1b of the upper flange 1a. The process precedes. After cleaning the concrete and the like adhering to the steel girder 1 and cleaning it, anti-corrosion treatment is performed with anti-corrosion paint. For coating on the flange surface, an organic zinc rich paint is applied by, for example, about 60 μm by spraying or brushing.

鋼桁処置工程を経た後、高さ調整治具2を介在させながら新設床版3を載置する(図2(b))。高さ調整治具2は高さ調整ボルトあるいは高さ調整ゴム板を用いる。これにより浮かした新設床版3の下面3aに固定治具4を取り付ける。固定治具4は、新設床版3の下面3aに先埋めされたセラミックインサート5と、これに螺着する取付ボルト6、取付ボルト6の下方で支持する固定用板材7を有し、この固定用板材7の一端部を上フランジ1aの下面1d側に差し入れ、挿通する第一固定ボルト7aの先端をこの下面1dに当接すると共に、固定用板材7の他端部にも第二固定ボルト7bを挿通してその先端を新設床版3の下面3aに当接して鋼桁1と新設床版3を接続して固定する。なお、1日ごとにプレキャスト床版をスタッド溶植とモルタル充填で鋼桁に固定する場合には、固定治具4を用いた固定を省略することもある。   After passing through the steel girder treatment process, the new floor slab 3 is placed with the height adjustment jig 2 interposed (FIG. 2 (b)). The height adjusting jig 2 uses a height adjusting bolt or a height adjusting rubber plate. The fixing jig 4 is attached to the lower surface 3 a of the newly installed floor slab 3 which is floated by this. The fixing jig 4 has the ceramic insert 5 previously embedded in the lower surface 3 a of the new floor plate 3, the mounting bolt 6 screwed to this, and the fixing plate 7 supported below the mounting bolt 6. One end of the plate member 7 is inserted into the lower surface 1d of the upper flange 1a, and the tip of the first fixing bolt 7a to be inserted abuts against the lower surface 1d, and the other fixing member 7 also has a second fixing bolt 7b. The steel girder 1 and the new floor plate 3 are connected and fixed by bringing the tip into contact with the lower surface 3a of the new floor plate 3 and connecting the steel girder 1 and the new floor plate 3 to each other. In the case where the precast floor slab is fixed to the steel girder by stud welding and mortar filling every one day, fixing using the fixing jig 4 may be omitted.

新設床版は型枠を設置しない状態で架設し、逐次固定治具4を用いて鋼桁1に固定する。この新設床版載置工程は、鋼桁処置工程で行った防錆処置の乾燥を待たずに施工する。フランジ全面に所定厚の防錆処置を施す場合には日数が経過しても再発錆する恐れが無いので、道路管理者の検査確認を受けながら1径間の新設床版の載置工程を遂行した後に型枠設置工程(図2(c))に移行する。   The newly installed floor slab is constructed in a state in which no formwork is installed, and is fixed to the steel girder 1 sequentially using the fixing jig 4. This new floor slab mounting step is to be carried out without waiting for the rust prevention treatment performed in the steel girder treatment step to dry. When rust prevention treatment of a predetermined thickness is applied to the entire surface of the flange, there is no risk of re-eating even if the days have passed, so the installation process of a new floor slab for one span is performed while receiving inspection confirmation from the road administrator Then, the process proceeds to a form setting process (FIG. 2 (c)).

この工程で用いる型枠支持材8は、前述のセラミックインサート5に螺着する取付ボルト6を利用し、このボルト6に締結材9を挿通して横端太材10を支持し、この横端太材10上に適宜間隔で型枠押さえ材11を配置する。型枠押さえ材11は、その先端を断面L型の型枠材12に当接し、後端上面にはスペーサ13を介在させて新設床版3の下面3aに当接する。   The frame support member 8 used in this step utilizes the mounting bolt 6 screwed to the ceramic insert 5 described above, and the fastening member 9 is inserted into the bolt 6 to support the lateral end thick member 10, and the lateral end The form holding members 11 are disposed on the thick material 10 at appropriate intervals. The mold presser member 11 has its front end in contact with the mold member 12 with an L-shaped cross section, and the spacer 13 is interposed on the upper surface of the rear end so as to be in contact with the lower surface 3 a of the new floor slab 3.

型枠材12は一辺が上フランジ1aの側面に当接し、他辺が新設床版3の下面4に当接するL型部材であって、加工が容易な材料、例えば塩ビ製のアングル、望ましくは透明なアクリル樹脂製等のアングルを用いる。このような材料を用いることで、図1に示すような古い橋梁で非常に多くみられる添接拡幅部1cによる板幅が変化する箇所でも容易に型枠の設置ができる。型枠支持材8は、適宜間隔で設置するが、固定治具4で固定用板材7を支持する取付ボルト6にも締結材9を予め挿通しておくことで兼用が可能となる。   The formwork member 12 is an L-shaped member whose one side abuts the side surface of the upper flange 1a and the other side abuts the lower surface 4 of the new floor slab 3 and is a material easy to process, for example, an angle made of polyvinyl chloride Use an angle made of transparent acrylic resin or the like. By using such a material, it is possible to easily install the mold even at a place where the plate width changes due to the joint widening portion 1c, which is very often found in old bridges as shown in FIG. The mold supporting members 8 are installed at appropriate intervals, but they can also be used by inserting the fastening members 9 in advance through the mounting bolts 6 that support the fixing plate 7 with the fixing jig 4.

この型枠設置工程と並行して、床版接合部3bの図示しない鉄筋組立や底面型枠の組み立てを行い、ジベル溶稙後に1径間ごと新設床版4と上フランジ1a上面との隙間内に無収縮モルタル14を充填し(図2(d))、モルタルが硬化した後に固定治具4や型枠支持材8等を全て撤去する(図2(e))。   Parallel to this form setting process, rebar assembly (not shown) of the floor slab joint 3b and assembly of the bottom form frame are carried out, and within the gap between the new floor 4 and the upper surface of the upper flange 1a The mortar is filled with non-shrinkage mortar 14 (FIG. 2 (d)), and after the mortar is hardened, all the fixing jig 4 and the form support 8 are removed (FIG. 2 (e)).

1 鋼桁
2 高さ調整治具
3 新設床版
4 固定治具
8 型枠支持材
12 型枠材
14 無収縮モルタル
1 Steel gir 2 Height adjustment jig 3 New floor version 4 Fixing jig 8 Formwork support material 12 Formwork material 14 Non-shrink mortar

Claims (4)

鋼桁上にコンクリート床版を載置する鋼橋で既設のコンクリート床版をプレキャスト床版に取り換え固定するため、既設コンクリート床版の撤去を行った後、鋼桁の上フランジ上面のケレンと防錆処置を行う鋼桁処置工程と、新設のプレキャスト床版を前記上フランジ上面に対し隙間をあけて載置する新設床版載置工程と、この新設床版と前記上フランジ上面との隙間を塞ぐ型枠材を設置する型枠設置工程と、この隙間内に無収縮モルタルを充填するモルタル充填工程を有するプレキャスト床版の鋼桁固定方法において、前記新設床版載置工程は、前記鋼桁処置工程を行った後、前記新設床版と前記上フランジ上面の間に高さ調整治具を介在させながら、前記新設床版に取付けて垂下する固定治具を前記上フランジ下面に当接することで前記新設床版を鋼桁に固定する新設床版載置固定工程であり、前記型枠設置工程は、前記新設床版に取付けて垂下する型枠支持材を用いて前記型枠材の下部を前記上フランジの側面に当接して固定する型枠設置工程であることを特徴とするプレキャスト床版の鋼桁固定方法。 After removing the existing concrete floor slab in order to replace and fix the existing concrete floor slab to the precast floor slab by the steel bridge where the concrete floor slab is placed on the steel girder, the kerren and prevention of the upper flange upper surface of the steel girder A steel girder treatment step for rusting treatment, a new floor plate placement step for placing a new precast floor plate with a gap from the upper surface of the upper flange, and a gap between the new floor plate and the upper flange surface In the steel girder fixing method of a precast floor slab having a mold installation process for installing a mold material to be closed and a mortar filling process for filling a non-shrink mortar in the gap, the new floor slab mounting process includes the steel girder installation process After performing the treatment process, while interposing a height adjustment jig between the newly installed floor slab and the upper flange upper surface, a fixing jig attached to the newly installed floor slab and suspended is brought into contact with the lower flange lower surface In the above It is a new floor plate placement fixing process which fixes a floor slab to a steel girder, and the formwork installation process uses the formwork support material which is attached to the new build floorboard and hangs down, the lower part of the formwork material is the above A method of fixing a steel girder of a precast floor slab, characterized in that it is a form installation step of fixing by abutting against the side surface of the upper flange. 前記新設床版載置固定工程は、前記鋼桁処置工程を行った後、防錆処置の乾燥を待たずに前記新設床版を鋼桁に固定することを特徴とする請求項1記載のプレキャスト床版の鋼桁固定方法。 The precast as set forth in claim 1, wherein the new deck installation and fixing step fixes the new deck to the steel girder without waiting for the anticorrosion treatment to dry after performing the steel girder disposal step. How to fix steel girder of floor slabs. 前記型枠設置工程は、一辺が前記上フランジの側面に当接し他辺が前記新設床版の下面に当接する断面L型の型枠材を用いることを特徴とする請求項1、請求項2記載のプレキャスト床版の鋼桁固定方法。 In the formwork installation step, a formwork member having an L-shaped cross section in which one side abuts on the side surface of the upper flange and the other side abuts on the lower surface of the new floor slab is used. Method of fixing steel girder of precast floor plate as described. 前記断面L型の型枠材は、モルタル充填状況を直接目視確認し得る透明な型枠材を用いることを特徴とする請求項3記載のプレキャスト床版の鋼桁固定方法。 The method for fixing a steel girder of a precast floor slab according to claim 3, characterized in that the form material of the L-shaped cross section is a transparent form material capable of directly visually confirming the mortar filling condition.
JP2017198120A 2017-10-12 2017-10-12 Steel girder fixing method for precast floor slabs Active JP6785739B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017198120A JP6785739B2 (en) 2017-10-12 2017-10-12 Steel girder fixing method for precast floor slabs

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017198120A JP6785739B2 (en) 2017-10-12 2017-10-12 Steel girder fixing method for precast floor slabs

Publications (2)

Publication Number Publication Date
JP2019073847A true JP2019073847A (en) 2019-05-16
JP6785739B2 JP6785739B2 (en) 2020-11-18

Family

ID=66543834

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017198120A Active JP6785739B2 (en) 2017-10-12 2017-10-12 Steel girder fixing method for precast floor slabs

Country Status (1)

Country Link
JP (1) JP6785739B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110983967A (en) * 2019-12-27 2020-04-10 同济大学建筑设计研究院(集团)有限公司 Bridge deck continuous process
CN111576228A (en) * 2020-05-26 2020-08-25 浙江交通职业技术学院 Assembling method of steel-concrete combined beam bridge structure with overall performance
JP7000604B1 (en) 2021-01-18 2022-01-19 株式会社ピーエス三菱 Rust prevention method for upper flange of steel girder
JP7024130B1 (en) 2021-06-14 2022-02-22 オリエンタル白石株式会社 Filling formwork under the PCa deck
JP7371315B2 (en) 2019-12-26 2023-10-31 株式会社竹中工務店 Precast floor slab construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61198310U (en) * 1985-05-28 1986-12-11
JPH01102105A (en) * 1987-10-15 1989-04-19 Oriental Concrete Kk Method for fixing precast concrete floor panel and steel beam
JPH1096209A (en) * 1996-09-20 1998-04-14 P S Co Ltd Precast concrete floor slab, manufacture thereof, and connection structure of precast floor slab and girder
US5978997A (en) * 1997-07-22 1999-11-09 Grossman; Stanley J. Composite structural member with thin deck portion and method of fabricating the same
JP2009281111A (en) * 2008-05-26 2009-12-03 Railway Technical Res Inst Fixing device for floor slab for railway track
JP2012026230A (en) * 2010-07-27 2012-02-09 Kawasaki Heavy Ind Ltd Railroad bridge composite structure and composition method
JP2014177766A (en) * 2013-03-13 2014-09-25 Kumagai Gumi Co Ltd Method for constructing concrete precast floor slab for bridge
JP2015200157A (en) * 2014-04-10 2015-11-12 株式会社横河住金ブリッジ Waterproof-rustproof structure of sandwich type composite floor slab

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61198310U (en) * 1985-05-28 1986-12-11
JPH01102105A (en) * 1987-10-15 1989-04-19 Oriental Concrete Kk Method for fixing precast concrete floor panel and steel beam
JPH1096209A (en) * 1996-09-20 1998-04-14 P S Co Ltd Precast concrete floor slab, manufacture thereof, and connection structure of precast floor slab and girder
US5978997A (en) * 1997-07-22 1999-11-09 Grossman; Stanley J. Composite structural member with thin deck portion and method of fabricating the same
JP2009281111A (en) * 2008-05-26 2009-12-03 Railway Technical Res Inst Fixing device for floor slab for railway track
JP2012026230A (en) * 2010-07-27 2012-02-09 Kawasaki Heavy Ind Ltd Railroad bridge composite structure and composition method
JP2014177766A (en) * 2013-03-13 2014-09-25 Kumagai Gumi Co Ltd Method for constructing concrete precast floor slab for bridge
JP2015200157A (en) * 2014-04-10 2015-11-12 株式会社横河住金ブリッジ Waterproof-rustproof structure of sandwich type composite floor slab

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7371315B2 (en) 2019-12-26 2023-10-31 株式会社竹中工務店 Precast floor slab construction method
CN110983967A (en) * 2019-12-27 2020-04-10 同济大学建筑设计研究院(集团)有限公司 Bridge deck continuous process
CN110983967B (en) * 2019-12-27 2021-09-28 同济大学建筑设计研究院(集团)有限公司 Bridge deck continuous process
CN111576228A (en) * 2020-05-26 2020-08-25 浙江交通职业技术学院 Assembling method of steel-concrete combined beam bridge structure with overall performance
CN111576228B (en) * 2020-05-26 2021-07-13 浙江交通职业技术学院 Assembling method of steel-concrete combined beam bridge structure with overall performance
JP7000604B1 (en) 2021-01-18 2022-01-19 株式会社ピーエス三菱 Rust prevention method for upper flange of steel girder
JP2022110384A (en) * 2021-01-18 2022-07-29 株式会社ピーエス三菱 Rust prevention method of steel girder upper flange
JP7024130B1 (en) 2021-06-14 2022-02-22 オリエンタル白石株式会社 Filling formwork under the PCa deck
JP2022190461A (en) * 2021-06-14 2022-12-26 オリエンタル白石株式会社 FILLING FORM UNDER PCa FLOOR SLAB

Also Published As

Publication number Publication date
JP6785739B2 (en) 2020-11-18

Similar Documents

Publication Publication Date Title
JP2019073847A (en) Method for fixing precast floor slab steel girder
JP5266291B2 (en) Construction method of bridge deck and joint structure of precast deck
CN108755405B (en) Assembly type steel plate bridge deck continuous structure and construction method
KR101796210B1 (en) Bracket for cantilever and cantilever construction method using the bracket
KR100985139B1 (en) Reinforcement method and apparatus for upper concrete structure by using reinforcement members having reinforcement fibers thereon
KR100696398B1 (en) Expansion joint for highways, bridges and the like and assembling method for use the same
JP3128947U (en) Bridge inspection road structure
KR101584086B1 (en) Removable leak-proof apparatus for expansion-contraction joint of bridge using a permanent magnet
JPH0449210Y2 (en)
JP4137287B2 (en) High durability structure embedded formwork method
JP2010189918A (en) Form for floor slab and floor slab construction method
JP4845039B2 (en) RC slab minority main girder bridge
JPH0959929A (en) Repair and reinforcing method of top of reinforced concrete floor slab
JP2007077746A (en) Reinforcing structure and reinforcing construction method of steel floor slab
JP2017133320A (en) Structure and method for reinforcing steel floor slab of bridge
JP2013151788A (en) Construction of segment girder and girder bridge with external cables to prevent salt damage, and installation method thereof
CN112239993A (en) Bridge anti-overturning device adaptive to multidirectional displacement and construction method thereof
CN210712537U (en) Install bridge telescoping device fast
JP5417807B2 (en) Reinforcing bar holding structure, reinforcing bar holding method, reinforcing method for reinforced concrete structure
JP2016094819A (en) Fixing structure for floor slab panel
Bottenberg Fiber-reinforced polymer decks for movable bridges
JP2015117515A (en) Inner tunnel watchman passage structure, and construction method for the same
KR20020023018A (en) Connection method between composite or precast deck and girders
KR20200134406A (en) An expansion joint
CN201857576U (en) Supporting device for installing post-tensioned precast prestressed concrete box girder

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20190701

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20200520

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20200601

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20200716

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20201022

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20201027

R150 Certificate of patent or registration of utility model

Ref document number: 6785739

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250