JP2019056284A - Column base reinforcement unit and method for constructing structure using column base reinforcement unit - Google Patents

Column base reinforcement unit and method for constructing structure using column base reinforcement unit Download PDF

Info

Publication number
JP2019056284A
JP2019056284A JP2017182562A JP2017182562A JP2019056284A JP 2019056284 A JP2019056284 A JP 2019056284A JP 2017182562 A JP2017182562 A JP 2017182562A JP 2017182562 A JP2017182562 A JP 2017182562A JP 2019056284 A JP2019056284 A JP 2019056284A
Authority
JP
Japan
Prior art keywords
foundation
column base
reinforcing bar
column
placing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2017182562A
Other languages
Japanese (ja)
Inventor
公直 北村
Kiminao Kitamura
公直 北村
志賀 豊彦
Toyohiko Shiga
豊彦 志賀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ACT21 TOKYO KK
ACT21-TOKYO KK
Taisei Corp
Original Assignee
ACT21 TOKYO KK
ACT21-TOKYO KK
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ACT21 TOKYO KK, ACT21-TOKYO KK, Taisei Corp filed Critical ACT21 TOKYO KK
Priority to JP2017182562A priority Critical patent/JP2019056284A/en
Publication of JP2019056284A publication Critical patent/JP2019056284A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

To provide a method for constructing a structure using a column base reinforcement unit that can be placed and fixed on leveling concrete easily, and with which concrete installation for constituting a column base can be performed easily.SOLUTION: The method of the present invention includes a leveling concrete installation step, a reinforcement unit placement step for placing and fixing, on the leveling concrete, a column base reinforcement unit 10 in which reinforcements constituting a column base part are assembled as a unit in advance after the leveling concrete is hardened, a foundation reinforcement placement step for inserting and placing foundation beam main reinforcements and foundation lateral reinforcements into/on the column base reinforcement unit 10, a step of installing part of foundation concrete for installing concrete forming part of a foundation around the column base reinforcement unit 10, a column and beam assembly step for placing and fixing columns on the column base reinforcement unit to install a beam thereon, and foundation remaining part installation step for performing foundation work following the step of installing part of foundation concrete. The column and beam assembly step and the foundation remaining part installation step are performed in parallel.SELECTED DRAWING: Figure 1

Description

本発明は、柱脚部を先組した鉄筋ユニット(鉄筋かご)を用いた構築物の構築方法に関する。   The present invention relates to a method for constructing a structure using a reinforcing bar unit (reinforcing bar cage) in which column bases are pre-assembled.

従来より、施工の省略化及び工期短縮を目的として、基礎躯体のプレキャスト(PCa)工法やアンカーフレームを用いた施工方法などが実用化されてきている。例えば、特許文献1には、アンカー用フレームを用いた施工方法が開示されている。   Conventionally, for the purpose of omitting construction and shortening the construction period, a precast (PCa) construction method of a foundation frame, a construction method using an anchor frame, and the like have been put into practical use. For example, Patent Document 1 discloses a construction method using an anchor frame.

特許文献1に開示されている施工方法では、アンカー用フレームとして、本体をアングル材により矩形に形成し、この本体を基点としてアンカーボルトを立設させたものを採用している。そして、このアンカー用フレームには、本体下部に調整ボルトが備えられ、アンカー用フレームの傾きを調整し、アンカーボルトの位置決めを高精度に実施することができることが記載されている。   In the construction method disclosed in Patent Document 1, the anchor frame is formed in a rectangular shape with an angle material, and an anchor bolt is erected with the main body as a base point. It is described that the anchor frame is provided with an adjustment bolt at the lower part of the main body, the inclination of the anchor frame can be adjusted, and the anchor bolt can be positioned with high accuracy.

このような構成のアンカー用フレームを用いた施工方法では、まず、捨てコン上に主筋と肋筋から成る基礎柱型筋を配置固定し、その外側にかぶせるにように、アンカー用フレームを配置する。その後、調整ボルトでアンカー用フレームの位置調整を行い、フーチングや地中梁のための主筋や肋筋を配置し、コンクリートの打設を行う。このような特徴を持った施工方法によれば、基礎柱脚のアンカーボルトの位置決めを高精度に行うことができることが記載されている。   In the construction method using the anchor frame having such a configuration, first, the basic columnar muscle composed of the main muscle and the gluteal muscle is arranged and fixed on the throw-away container, and the anchor frame is arranged so as to cover the outside. . After that, the position of the anchor frame is adjusted with adjusting bolts, and the main bars and barbs for footing and underground beams are placed, and concrete is placed. According to the construction method having such characteristics, it is described that the anchor bolts of the foundation column base can be positioned with high accuracy.

しかし、特許文献1に記載の施工方法では、アンカー用フレームと基礎柱型筋を別体としているため、2つの構造物を個別に制作し、施工現場に搬入するタイミングを合わせる必要がある。   However, in the construction method described in Patent Document 1, since the anchor frame and the basic columnar muscle are separated, it is necessary to produce two structures individually and to match the timing of carrying them to the construction site.

また、在来工法で基礎を構築する場合、基礎全体(フーチングと地中梁)の工事を完成させ、その後に上部構造の工事に着手するという施工手順が採られることが一般的である。そうした場合、各スパンについて基礎工事と上部構造工事との間に待ち時間が発生し、全体工期が長期化するという問題がある。   Moreover, when constructing a foundation by a conventional construction method, it is common to adopt a construction procedure in which construction of the entire foundation (footing and underground beam) is completed and then construction of the superstructure is started. In such a case, there is a problem that a waiting time is generated between the foundation work and the superstructure work for each span, and the entire construction period is prolonged.

特開平7−292683号公報JP 7-292683 A

本発明では、基礎工事の完成を待たずに上部構造の構築を進めることができ、構築物を構築する際の施工期間を短縮することを可能とする柱脚鉄筋ユニット、および構築物の構築方法を提供することを目的とする。   In the present invention, it is possible to proceed with the construction of the superstructure without waiting for completion of the foundation work, and to provide a column base reinforcing bar unit and a construction construction method capable of shortening the construction period when constructing the construction. The purpose is to do.

上記目的を達成するための柱脚鉄筋ユニットは、複数の主筋と、複数の前記主筋を取り囲むように配置された複数の肋筋とを有する柱脚基礎打設用鉄筋部と、前記柱脚基礎打設用鉄筋部の内部に配置され、柱との接合を担うアンカー部と、を有し、前記柱脚基礎打設用鉄筋部には、当該柱脚基礎打設用鉄筋部の断面形状を維持する主筋位置保持プレートが複数備えられ、前記アンカー部は、前記主筋位置保持プレートに固定されていることを特徴とする。   A column base reinforcing bar unit for achieving the above object includes a column base foundation placing reinforcing bar having a plurality of main bars and a plurality of barbs arranged to surround the plurality of main bars, and the column base. An anchor portion disposed inside the placing reinforcing bar portion and responsible for joining with the column, and the column base foundation placing reinforcing bar portion has a cross-sectional shape of the column base foundation placing reinforcing bar portion. A plurality of main muscle position holding plates to be maintained are provided, and the anchor portion is fixed to the main muscle position holding plate.

また、上記のような特徴を有する柱脚鉄筋ユニットを用いた構築物の構築方法は、捨てコン打設工程と、前記捨てコンが硬化した後、柱脚部を構成する鉄筋をユニットとして予め組み上げた柱脚鉄筋ユニットを前記捨てコン上に配置、固定する鉄筋ユニット配置工程と、前記柱脚鉄筋ユニットに対して基礎梁主筋や基礎肋筋を挿通配置する基礎筋配置工程と、前記基礎柱脚鉄筋ユニットの周囲基礎の一部を形成するコンクリートを打設する基礎コンクリート一部打設工程と、前記柱脚鉄筋ユニット上に柱を配置固定し、梁を架設する柱梁建て方工程と、前記基礎コンクリート一部打設工程以後の基礎工事を行う基礎残部打設工程と、を有する構築物の構築方法であって、前記柱梁建て方工程と、前記基礎残部打設工程とを並行して行うことを特徴とする。   Moreover, the construction method of the structure using the column base reinforcing bar unit having the above-described features is a pre-assembled unit that includes the discarding component placing step and the reinforcing bars constituting the column base part after the discarding component is cured. Reinforcing bar unit placement step for placing and fixing a column base reinforcing bar unit on the throwing-off unit, a foundation reinforcing bar placement step for inserting and placing a foundation beam main reinforcement and a foundation reinforcing bar with respect to the column base reinforcement unit, and the foundation column base reinforcement A foundation concrete partial placing process for placing concrete forming a part of the surrounding foundation of the unit, a column beam building process for laying and fixing a column on the column base reinforcing bar unit, and building a beam; and the foundation A foundation remaining portion placing step for performing foundation work after the concrete partial placing step, wherein the pillar beam building method and the foundation remaining portion placing step are performed in parallel. The And butterflies.

また、上記特徴を有する柱脚鉄筋ユニットを用いた構築物の構築方法において前記柱梁建て方工程には、上階床工事を含む。このような特徴を有する事により、上階の床工事も、基礎残部打設と同時進行で行う事が可能となる。   Moreover, in the construction method of the structure using the column base reinforcing bar unit having the above characteristics, the column beam construction method includes upper floor work. By having such a feature, it is possible to carry out the floor construction on the upper floor at the same time as the foundation rest placement.

さらに、上記特徴を有する柱脚鉄筋ユニットを用いた構築物の構築方法において前記柱梁建て方工程と、前記基礎残部打設工程は、平面的に区分けされた複数のスパン毎に行われ、前記柱梁建て方工程を実施するスパンと、前記基礎残部打設工程を実施するスパンとを異ならせるようにする。このような特徴を有する事により、上階工事と基礎工事を行うスパンが平面的に重なる事が無い。よって、上階工事中に物が落下する事などにより、基礎工事中の作業者が危険にさらされる虞がなく、工事を安全に進めることができる。   Furthermore, in the construction method of the structure using the column base reinforcing bar unit having the above characteristics, the column beam building method step and the foundation remaining portion placing step are performed for each of a plurality of spans divided in a plane, The span for performing the beam building process is different from the span for performing the foundation remaining portion placing process. By having such a feature, spans for upper floor construction and foundation construction do not overlap in plane. Therefore, there is no possibility that the worker under the foundation work will be exposed to danger due to an object falling during the upper floor construction, and the construction can be proceeded safely.

上記のような特徴を有する柱脚鉄筋ユニットによれば、捨てコン上への配置、固定を容易とし、かつ柱脚を構成するためのコンクリート打設をも容易に行うことが可能となる。また、このような効果を奏する柱脚鉄筋ユニットを用いた構築物の構築方法によれば、基礎残部打設工程と、上部構造の施工とをほとんど並行して進めることが可能となり、工期を短縮することができる。   According to the column base reinforcing bar unit having the above-described features, it is possible to easily place and fix it on the throwing-off container and to easily perform the concrete placement for constituting the column base. Moreover, according to the construction method of the structure using the columnar reinforcing bar unit that exhibits such an effect, it becomes possible to proceed with the foundation remaining portion placing process and the superstructure construction almost in parallel, thereby shortening the construction period. be able to.

実施形態に係る柱脚鉄筋ユニットの構成を示す斜視図である。It is a perspective view which shows the structure of the columnar reinforcement unit which concerns on embodiment. 実施形態に係る柱脚鉄筋ユニットを構成する柱脚基礎打設用鉄筋部とアンカー部を分解した様子を示す部分分解斜視図である。It is a partial exploded perspective view which shows a mode that the rebar part for column base foundation placement and the anchor part which comprise the column base reinforcing bar unit which concerns on embodiment were decomposed | disassembled. 柱脚鉄筋ユニットの周囲にラス型枠を設置した場合の変形例を示す図である。It is a figure which shows the modification at the time of installing the lath formwork around a column base reinforcing bar unit. 柱脚鉄筋ユニットを構成するアンカー部として鉄骨を採用する場合の例を示す図である。It is a figure which shows the example in the case of employ | adopting a steel frame as an anchor part which comprises a column leg reinforcement unit. 主筋位置保持プレートに定着板を一体化させた場合の例を示す図である。It is a figure which shows the example at the time of integrating a fixing board with the main muscle position holding | maintenance plate. 主筋保持プレートの平面形態を口の字型とした場合の例を示す図である。It is a figure which shows the example at the time of making the planar form of a main reinforcement holding | maintenance plate into a square shape. 主筋保持プレートの平面形態を井の字型とした場合の例を示す図である。It is a figure which shows the example at the time of making the plane form of a main reinforcement holding | maintenance plate into a well shape. 捨てコン打設工程の説明図である。It is explanatory drawing of a throwing away con placement process. 鉄筋ユニット配置工程の説明図である。It is explanatory drawing of a reinforcing bar unit arrangement process. トラック等により柱脚鉄筋ユニットを搬送する様子を示すイメージ図である。It is an image figure which shows a mode that a columnar reinforcement unit is conveyed by a track | truck etc. FIG. 基礎筋配置工程の説明図である。It is explanatory drawing of a basic muscle arrangement | positioning process. 基礎筋配置工程後、フーチング形成範囲に型枠を設置した様子を示す図である。It is a figure which shows a mode that the formwork was installed in the footing formation range after the basic reinforcement arrangement | positioning process. コンクリート一部打設工程の説明図である。It is explanatory drawing of a concrete partial placement process. コンクリート一部打設工程において構成したフーチングの上部に柱部材を立設した様子を示す図である。It is a figure which shows a mode that the column member was erected on the upper part of the footing comprised in the concrete partial placement process. 柱梁建て方工程における鉄骨梁やデッキプレートの架設と、基礎残部打設工程を同時進行で行う様子を示す図である。It is a figure which shows a mode that the construction of a steel beam and a deck plate and the foundation remainder placement process in a column beam construction process are performed simultaneously. 広い面積の工事範囲を複数のスパンに分けた状態を説明するための図である。It is a figure for demonstrating the state which divided the construction range of a large area into the some span.

以下、本発明の柱脚鉄筋ユニットおよび柱脚鉄筋ユニットを用いた構築物の構築方法に係る実施の形態について、図面を参照して詳細に説明する。   DESCRIPTION OF EMBODIMENTS Hereinafter, an embodiment according to a column base reinforcing bar unit and a method for constructing a structure using the column base reinforcing bar unit of the present invention will be described in detail with reference to the drawings.

[柱脚鉄筋ユニット]
まず、本発明に係る柱脚鉄筋ユニットについて、図1および図2を参照して説明する。なお、図1は、実施形態に係る柱脚鉄筋ユニットの構成を示す斜視図であり、図2は、柱脚鉄筋ユニットを柱脚基部打設用鉄筋部とアンカー部とに分解した様子を示す部分分解斜視図である。
[Column Rebar Unit]
First, a columnar reinforcing bar unit according to the present invention will be described with reference to FIGS. 1 and 2. FIG. 1 is a perspective view showing a configuration of a column base reinforcing bar unit according to the embodiment, and FIG. 2 shows a state in which the column base reinforcing bar unit is disassembled into a column base base placing reinforcing bar portion and an anchor portion. It is a partial exploded perspective view.

本実施形態に係る柱脚鉄筋ユニット10は、柱脚基礎打設用鉄筋部12と、アンカー部24とを基本として構成されている。柱脚基礎打設用鉄筋部12は、柱脚配置方向に沿って配置された複数の主筋14(14a,14b)と、この主筋14を取り囲むように配置された複数の肋筋16とを有する。主筋14としては、例えば矩形の頂点に配置された長尺主筋14aと、各長尺主筋14aの間に配置された短尺主筋14bとを備える。長尺主筋14aはネジ鉄筋とし、間に配置された短尺主筋14bは、必要に応じてネジ鉄筋としても良い。ネジ鉄筋を用いると、汎用のネジ鉄筋用ナット等を螺合し、位置決めやレベル出し、付属物の配置位置調整などを行うことが可能となるからである。また、ネジ鉄筋を用いると、ネジ式定着金物を設置することにより、主筋長さを短くすることや、端部L型定着を省略できる。   The column base reinforcing bar unit 10 according to the present embodiment is configured on the basis of a column base foundation placing reinforcing bar portion 12 and an anchor portion 24. The column base foundation placement reinforcing bar portion 12 includes a plurality of main bars 14 (14a, 14b) arranged along the column base arrangement direction, and a plurality of barbs 16 arranged so as to surround the main bar 14. . The main muscle 14 includes, for example, a long main muscle 14a arranged at a rectangular apex and a short main muscle 14b arranged between the long main muscles 14a. The long main reinforcing bar 14a may be a screw reinforcing bar, and the short main reinforcing bar 14b arranged between them may be a screw reinforcing bar as necessary. This is because when a screw rebar is used, a general-purpose screw rebar nut and the like can be screwed together to perform positioning, leveling, and adjustment of the position of an accessory. In addition, when screw rebars are used, the length of the main bars can be shortened and the end L-type fixing can be omitted by installing a screw-type fixing hardware.

長尺主筋14aは、短尺主筋14bに比べて長尺となるように構成されており、配置時に上端の水平高さを揃えた場合には、下端側の突出量が多くなるように構成されている。長尺主筋14aの下端には、ベース金物18が備えられている。ベース金物18は、具体的構成は問わないが、例えば図1、図2に示すように、ソケット18aと、このソケット18aの一方の端部に設けられた平板18bにより構成すれば良く、ベース金物18の上部には、レベル調整ナット17を備えるようにすると良い。長尺主筋14aの下端部に螺合しているレベル調整ナット17を回転させてソケット18aに対する長尺主筋14aの挿嵌状態を調整することにより、柱脚鉄筋ユニット10を安定して配置することができると共に、レベル出しや傾き調整を行うことが可能となるからである。また、ベース金物18に平板18bを備える事により、設置面となる捨てコン上にアンカーが埋設されている場合には、当該アンカーに対する固定面を構成することも可能となる。   The long main bar 14a is configured to be longer than the short main bar 14b. When the horizontal height of the upper end is aligned at the time of arrangement, the long main bar 14a is configured to increase the protruding amount on the lower end side. Yes. A base hardware 18 is provided at the lower end of the long main bar 14a. The base hardware 18 may be of any specific configuration, but for example, as shown in FIGS. 1 and 2, it may be configured by a socket 18a and a flat plate 18b provided at one end of the socket 18a. A level adjusting nut 17 may be provided on the upper portion of 18. By rotating the level adjustment nut 17 screwed into the lower end of the long main bar 14a and adjusting the insertion state of the long main bar 14a with respect to the socket 18a, the column base reinforcing bar unit 10 can be stably arranged. This is because leveling and tilt adjustment can be performed. In addition, by providing the base hardware 18 with the flat plate 18b, when the anchor is embedded on the throwing-down container serving as the installation surface, it is possible to configure a fixing surface for the anchor.

短尺主筋14bは、長尺主筋14aの間に複数配置される主筋であり、本実施形態に係る柱脚鉄筋ユニット10の場合、その下端位置が長尺主筋14aよりも上側に位置し、浮いた状態となるように構成されている。このような構成とすることで、柱脚鉄筋ユニット10のレベル出しや傾き調整を行う際、長尺主筋14aに備えたレベル調整ナット17の螺合状態を調整すれば良いからである。また、各短尺主筋14b並びに長尺主筋14aの下端側には、定着体20を備えるようにすると良い。定着体20は、コンクリートに対する鉄筋の定着(抜け止め)を図る要素であり、例えば主筋14としてネジ鉄筋を採用している場合には、プレートナットなどを螺合する構成とすることができる。このような定着体20を備える構成とすることで、鉄筋を曲げる事なく簡易に、コンクリートへの定着を図ることができる。勿論、設計上定着長さが十分であれば、鉄筋曲げも定着体20も不要である。   The short main bars 14b are a plurality of main bars arranged between the long main bars 14a. In the case of the columnar reinforcing bar unit 10 according to the present embodiment, the lower end position is located above the long main bars 14a and floats. It is comprised so that it may be in a state. This is because, with such a configuration, when leveling and tilt adjustment of the columnar reinforcing bar unit 10 are performed, the screwing state of the level adjusting nut 17 provided in the long main reinforcing bar 14a may be adjusted. In addition, it is preferable to provide the fixing body 20 on the lower end side of each short major bar 14b and the long major bar 14a. The fixing body 20 is an element for fixing (retaining) the reinforcing bar to the concrete. For example, when a screw reinforcing bar is used as the main reinforcing bar 14, a plate nut or the like can be screwed together. By setting it as the structure provided with such a fixing body 20, fixing to concrete can be aimed at easily, without bending a reinforcing bar. Of course, if the fixing length is sufficient in design, neither the reinforcing bar bending nor the fixing body 20 is required.

柱脚基礎打設用鉄筋部12を構成する肋筋16は、長尺主筋14aと、短尺主筋14bの配置方向と直交する方向に配置され、複数の長尺主筋14a、および短尺主筋14bを囲繞するように配置される鉄筋であり、主筋14を構成する鉄筋に比べて細いものとされている。肋筋16は、長尺主筋14aおよび短尺主筋14bの長手方向に沿って複数配置されている。   The reinforcing bar 16 constituting the column base foundation placing reinforcing bar 12 is arranged in a direction orthogonal to the arrangement direction of the long main bars 14a and the short main bars 14b, and surrounds the plurality of long main bars 14a and the short main bars 14b. The reinforcing bars are arranged so as to be narrower than the reinforcing bars constituting the main bars 14. A plurality of the gluteal muscles 16 are arranged along the longitudinal direction of the long major muscle 14a and the short major muscle 14b.

また、本実施形態に係る柱脚基礎打設用鉄筋部12の内部には、主筋位置保持プレート22a,22bが配置されている。主筋位置保持プレート22a,22bは、柱脚基礎打設用鉄筋部12の断面形状を維持するための補強と共に、柱脚基礎打設用鉄筋部12に対して後述するアンカー部24を接続支持する役割を担う要素である。主筋位置保持プレート22a,22bの具体的形態は問わないが、図1、図2に示す形態の場合、その平面形状をX型とし、長尺主筋14aのうち、対角線上に配置された長尺主筋14a同士を接続するように構成している。また、図1、図2に示す例では、2つの主筋位置保持プレート22a,22bを備える構成としているが、さらに複数のプレートを備える構成としても良い。   Further, main bar position holding plates 22a and 22b are arranged inside the column base foundation placing reinforcing bar portion 12 according to the present embodiment. The main bar position holding plates 22a and 22b are connected to and supported by the anchor base 24, which will be described later, with respect to the column base foundation placement reinforcing bar 12 together with reinforcement for maintaining the cross-sectional shape of the column base foundation placement reinforcing bar 12. It is an element that plays a role. Although the specific form of main muscle position holding | maintenance plate 22a, 22b is not ask | required, in the case of the form shown in FIG. 1, FIG. 2, the planar shape is set to X type, and the long shape arrange | positioned diagonally among the long main muscles 14a. The main bars 14a are connected to each other. Moreover, although it is set as the structure provided with the two main muscle position holding | maintenance plates 22a and 22b in the example shown in FIG. 1, FIG. 2, it is good also as a structure further provided with a some plate.

ここで、上記説明、並びに図1、および図2では、4本の長尺主筋14aを矩形に配置することで、柱脚基礎打設鉄筋部12の平面形状(断面形状)は、矩形とするように記載した。しかしながら、柱脚基礎打設鉄筋部12の平面形状は、建築する建物の柱の形状等に応じて、多角形や円形とすることができ、必要に応じて長尺主筋14aの数を増減させるようにすれば良い。   Here, in the above description and FIGS. 1 and 2, the four long main reinforcing bars 14 a are arranged in a rectangular shape, so that the planar shape (cross-sectional shape) of the column base foundation placing reinforcing bar portion 12 is a rectangular shape. It was described as follows. However, the planar shape of the column base foundation placing reinforcing bar portion 12 can be a polygon or a circle according to the shape of the column of the building to be constructed, etc., and the number of the long main bars 14a is increased or decreased as necessary. You can do that.

アンカー部24は、柱の下端部を支持するアンカーを構成する部位である。図1、および図2に示す例においてアンカー部24は、柱脚基礎打設用鉄筋部12を構成する主筋14の配置方向に沿って配置された複数のアンカーボルト26(図1、図2に示す例では8本)によって構成されている。複数のアンカーボルト26は、柱を固定するために定められたボルト穴に対応する位置に備えられる。また、複数のアンカーボルト26には、その位置決めのためのテンプレート28が備えられている。   The anchor part 24 is a part that constitutes an anchor that supports the lower end of the column. In the example shown in FIGS. 1 and 2, the anchor portion 24 has a plurality of anchor bolts 26 (in FIGS. 1 and 2) arranged along the arrangement direction of the main reinforcing bars 14 constituting the column base foundation placing reinforcing bar portion 12. In the example shown, it is composed of 8). The plurality of anchor bolts 26 are provided at positions corresponding to the bolt holes defined for fixing the pillars. The plurality of anchor bolts 26 are provided with a template 28 for positioning.

柱脚基礎打設用鉄筋部12に対するアンカー部24の固定は、その形態によって種々選択することができるが、図1、図2に示す形態の場合、アンカー部24は、主筋位置保持プレート22aを介して固定するように構成されている。具体的には、図2に示すアンカー部24は、アンカーボルト26を2本一対として4箇所に備える構成としている。対を成すアンカーボルト26の下端部には、定着板30が備えられている。   The anchor part 24 can be fixed to the column base foundation placing reinforcing bar part 12 in various ways depending on its form. In the case of the form shown in FIGS. 1 and 2, the anchor part 24 is provided with the main bar position holding plate 22a. It is comprised so that it may fix via. Specifically, the anchor part 24 shown in FIG. 2 is configured to include two anchor bolts 26 in four locations. A fixing plate 30 is provided at the lower end of the pair of anchor bolts 26.

定着板30は、上部プレートと下部プレートより構成され、各プレートがアンカーボルト26に対してナット30aにより固定されている。アンカー部24は、この定着板30の上部プレートと下部プレートの間に主筋位置保持プレート22aを挟み込んで固定することで、柱脚基礎打設用鉄筋部12に対する固定が成される。   The fixing plate 30 includes an upper plate and a lower plate, and each plate is fixed to the anchor bolt 26 by a nut 30a. The anchor portion 24 is fixed to the column base foundation placement reinforcing bar portion 12 by sandwiching and fixing the main bar position holding plate 22a between the upper plate and the lower plate of the fixing plate 30.

このような構成の柱脚鉄筋ユニット10によれば、PCaユニットに比べて軽量で、搬送コストが安価となる。また当然に、揚重機も小型化することができ、安価となる。また、作業現場において、柱脚を構成するための鉄筋の数の確認や、準備が不要となる。さらに、柱脚鉄筋ユニット10を設置する際の傾き調整も容易に行うことができる。   According to the column base reinforcing bar unit 10 having such a configuration, it is lighter than the PCa unit and the conveyance cost is low. Naturally, the lifting machine can also be reduced in size and is inexpensive. In addition, it is not necessary to check the number of rebars for preparing the column base and to prepare at the work site. Furthermore, it is possible to easily adjust the inclination when installing the column base reinforcing bar unit 10.

[変形例]
また、上記実施形態では、柱脚鉄筋ユニット10は、単に柱脚基礎打設用鉄筋部12とアンカー部24から構成されるように記載した。しかしながら、本実施形態に係る柱脚鉄筋ユニット10は、図3に示すように、柱脚基礎打設用鉄筋部12の外周に、ラス型枠32等の付帯物を配置する構成としても良い。ラスなどの「型枠」を予め柱脚鉄筋ユニット10に配置すれば、柱脚先行打設のための型枠を予めユニットに組み込むこととなり、現場での工数削減に寄与することができる。また、本変形例において、埋設部分に設ける型枠をラスとすれば型枠撤去工事が不要となる。このような構成とする場合において、柱脚鉄筋ユニット10に梁筋や、はかま筋を貫通させるには、単にラスの一部に開口を設ければ良く、施工効率も良い。なお、打ち放し仕上げとしてコンクリート表面が現れる部分では、柱脚鉄筋ユニット10に備える型枠として、ラスではない種類の型枠(撤去可能なもの)を配置するようにしても良い。
[Modification]
Moreover, in the said embodiment, the column base reinforcement unit 10 described so that it might be comprised only from the column base foundation placement reinforcing bar part 12 and the anchor part 24. FIG. However, as shown in FIG. 3, the column base reinforcing bar unit 10 according to the present embodiment may be configured such that an accessory such as a lath mold 32 is arranged on the outer periphery of the column base foundation placing reinforcing bar portion 12. If a “formwork” such as a lath is placed in the column base reinforcing bar unit 10 in advance, the formwork for the column base advance placement is incorporated in the unit in advance, which can contribute to reduction in the number of man-hours on site. Further, in this modification, if the mold provided in the buried portion is a lath, the mold removal work is not necessary. In the case of such a configuration, in order to allow the beam-base reinforcing bar unit 10 to pass through the beam bars and the hook-skin bars, it is only necessary to provide an opening in a part of the lath, and the construction efficiency is good. Note that, in a portion where the concrete surface appears as a finish finish, as a mold provided for the column base reinforcing bar unit 10, a type of mold (which can be removed) other than a lath may be arranged.

また上記実施形態においては、アンカー部24について、単に複数のアンカーボルト26を配置し、これを柱脚基礎打設用鉄筋部12に接続する構成としている。しかしながら、本発明に係る柱脚鉄筋ユニット10としては、図4に示すように、アンカー部24として鉄骨を採用することもできる。このように、アンカー部24の構成は、建築物の仕様によって、その形態を種々対応するものへと変換して構成することができる。
また、上記実施形態では、アンカーボルト26を固定する定着板30について、対を成すプレートにより構成され、主筋位置保持プレート22aを挟持する旨記載した。しかしながら、実施形態に係る主筋位置保持プレート22aは、図5に示すように、定着板30を一体とした形態としても良い。
Moreover, in the said embodiment, it is set as the structure which arrange | positions the several anchor bolt 26 only about the anchor part 24, and connects this to the reinforcement part 12 for column base foundation placement. However, as the columnar reinforcing bar unit 10 according to the present invention, a steel frame may be employed as the anchor portion 24 as shown in FIG. Thus, the configuration of the anchor portion 24 can be configured by converting its form into various types according to the specifications of the building.
In the above-described embodiment, the fixing plate 30 that fixes the anchor bolt 26 is configured by a pair of plates and sandwiches the main bar position holding plate 22a. However, the main bar position holding plate 22a according to the embodiment may have a configuration in which the fixing plate 30 is integrated as shown in FIG.

また、主筋位置保持プレート22bに関しては、筋交部も不要とすることができるため、例えば図6に示すような口の字型や、図7に示すような井の字型の他、主筋14の配置形態の補強に寄与することができれば、分割されている形態としても良い。
また、主筋位置保持プレート22a,22bは、その主面形態に沿ったリブ材を備え、剛性を高めるようにしても良い。リブ材により補強を行う事で、主筋位置保持プレート22a,22b自体の厚みを厚くすることなく、部材の剛性(強度)を上げることができる。また、構成材料として薄肉材を使用することができるため、厚肉材による剛性強化に比べ、軽量化、および材料コストの低減を図る事もできる。
In addition, since the main muscle position holding plate 22b can also eliminate the need for a muscular intersection, for example, the main muscle 14 in addition to the mouth shape as shown in FIG. 6 and the well shape as shown in FIG. If it can contribute to reinforcement of the arrangement form, it may be divided.
Further, the main muscle position holding plates 22a and 22b may be provided with rib members along the main surface form to increase the rigidity. By reinforcing the rib material, the rigidity (strength) of the member can be increased without increasing the thickness of the main bar position holding plates 22a and 22b themselves. In addition, since a thin material can be used as a constituent material, the weight can be reduced and the material cost can be reduced as compared with the rigidity enhancement by a thick material.

[構築方法]
次に、上記のような構成の柱脚鉄筋ユニット10を用いた構築物の構築方法について、図8から図16を参照して説明する。
まず、図8に示すようにして、施工範囲における基礎形成部に生コンクリート50を打設する(捨てコン打設工程)。生コンクリート50が硬化した後、図9に示すように、予め定められた柱設置位置に柱脚鉄筋ユニット10を配置する。ここで、柱脚鉄筋ユニット10は、予め工場、あるいは現場敷地内の先組ヤード等で組み上げたものを施工現場に搬入する。柱脚鉄筋ユニット10の搬入は、図10にイメージを示すようにトラック等によって搬送すれば良い。このため、搬送形態がPCaユニットを用いる場合と近似するが、鉄筋、あるいは鉄筋と鉄骨のみの構成とされる柱脚鉄筋ユニット10は、PCaユニットに比べて軽量で、同じ積載能力を有するトラックで運べる数量を増やすことができる(鉄筋ユニット配置工程)。なお、柱脚鉄筋ユニット10を運搬・揚重する際に、ユニットの剛性が不足する場合には、図9に二点鎖線で示すような斜め補強筋34を肋筋16に結束するなどして、剛性を向上させると良い。振動によるズレ防止や、精度確保を図ることができるからである。ここで、斜め補強筋34を埋設させる場合に、そのかぶり寸法が不足する部分が生じる場合には、斜め補強筋34を主筋14の内側に組み込む構成とすることで、柱脚鉄筋ユニット10の外形寸法を抑えるようにしても良い。
[How to build]
Next, a construction method using the columnar reinforcing bar unit 10 having the above-described configuration will be described with reference to FIGS.
First, as shown in FIG. 8, the ready-mixed concrete 50 is placed in the foundation forming portion in the construction range (abandoned con placement step). After the ready-mixed concrete 50 is hardened, as shown in FIG. 9, the column base reinforcing bar unit 10 is arranged at a predetermined column installation position. Here, the column base reinforcing bar unit 10 carries in a construction site a prefabricated factory or a pre-assembled yard in the site site. The column rebar unit 10 may be carried by a truck or the like as shown in FIG. For this reason, although the conveyance form is similar to the case where the PCa unit is used, the column base reinforcing bar unit 10 which is composed of a reinforcing bar or only a reinforcing bar and a steel frame is a truck which is lighter than the PCa unit and has the same loading capacity. The amount that can be carried can be increased (rebar unit arrangement process). When the column base reinforcing bar unit 10 is transported / lifted, if the unit has insufficient rigidity, an oblique reinforcing bar 34 as shown by a two-dot chain line in FIG. It is better to improve the rigidity. This is because it is possible to prevent displacement due to vibration and to ensure accuracy. Here, in the case where the diagonal reinforcing bars 34 are embedded, if there is a portion where the cover size is insufficient, the outer shape of the columnar reinforcing bar unit 10 is configured by incorporating the diagonal reinforcing bars 34 inside the main bars 14. You may make it suppress a dimension.

また、柱脚鉄筋ユニット10の剛性を高める手段としては、上述した斜め補強筋34を組み込む事の他、主筋位置保持プレート22a,22bの数を増やすという手段もある。このため、いずれの手段により柱脚鉄筋ユニット10における剛性の向上を図るかは、施工条件を考慮の上、設計判断すれば良い。   As a means for increasing the rigidity of the column base reinforcing bar unit 10, there is a means for increasing the number of main bar position holding plates 22a and 22b in addition to incorporating the diagonal reinforcing bars 34 described above. For this reason, which means should be used to improve the rigidity of the column-base reinforcing bar unit 10 may be determined by considering the construction conditions.

柱脚鉄筋ユニット10を配置した後、柱脚鉄筋ユニット10を含む基礎を構成するための鉄筋を配置する。具体的には図11に示すように、柱脚鉄筋ユニット10の側面を貫通させるように配置する、地中梁や柱脚鉄筋ユニット10の下部フーチングを構成するための主筋52,54の挿通を行う。次いで、地中梁を構成するための肋筋56、およびフーチングを構成するための肋筋58の配置を行う(基礎筋配置工程)。   After the column base reinforcing bar unit 10 is arranged, the reinforcing bars for constituting the foundation including the column base reinforcing bar unit 10 are arranged. Specifically, as shown in FIG. 11, insertion of main bars 52 and 54 for constituting the lower footing of the underground beam and the column base reinforcing bar unit 10 arranged so as to penetrate the side surface of the column base reinforcing bar unit 10 is performed. Do. Next, the reinforcement 56 for constituting the underground beam and the reinforcement 58 for constituting the footing are arranged (basic reinforcement arrangement step).

基礎筋配置工程終了後、図12に示すように、フーチングを構成する範囲に止め型枠60を設置する。その後、止め型枠60を設置した範囲に生コンクリートを打設して、図13に示すようなフーチング62を構成する。実施形態に係る柱脚鉄筋ユニット10は、既に主筋14と肋筋16を備えているため、周囲に型枠を設置するだけで容易にコンクリートを打設して、フーチング62を構成することができる(コンクリート一部打設工程)。ここで、例えば柱脚鉄筋ユニット10として、図3に示すようなラス型枠32を備えるものを採用する場合に、コンクリート埋設部分にラス(ラス型枠32)を配置する構成とすることで、型枠撤去工程が不要となると共に、上述したように、梁筋や、はかま筋(地中梁や下部フーチングを構成するための主筋52,54や肋筋56,58)を貫通させることも容易となり、施工効率を向上させることができる。   After the basic muscle placement step is completed, as shown in FIG. 12, the stop mold 60 is installed in the range constituting the footing. Thereafter, the ready-mixed concrete is placed in the range where the stop mold 60 is installed to form the footing 62 as shown in FIG. Since the columnar reinforcing bar unit 10 according to the embodiment already includes the main reinforcing bar 14 and the reinforcing bar 16, the concrete can be easily placed and the footing 62 can be configured simply by installing a formwork around it. (Concrete part placement process). Here, for example, when adopting a thing equipped with a lath mold frame 32 as shown in FIG. 3 as the column base reinforcing bar unit 10, by adopting a configuration in which the lath (lass mold frame 32) is arranged in the concrete embedded portion, The mold removal step is not necessary, and as described above, it is easy to penetrate the beam bars and the hook-skin bars (the main bars 52 and 54 and the barbs 56 and 58 for forming the underground beam and the lower footing). Thus, the construction efficiency can be improved.

フーチング等一部基礎形成後、柱脚鉄筋ユニット10を介して構成されたフーチング62から突出するアンカーボルト26に柱部材64を設置、固定する(図14参照)その後、図15に示すように、立設した柱部材64間に上層階の鉄骨梁66や床デッキプレート68等を架設する(柱梁建て方工程)。また、一部基礎形成後、柱梁建て方工程と並行して、残りの基礎部分について、地中梁を形成するための止め型枠を設置し(不図示)、コンクリート打設等の基礎工事を行う(基礎残部打設工程)。ここで、柱梁建て方工程と基礎残部打設工程とは、図15に示すように上下で重ならない位置で作業を行うようにする。上層階からの物の落下による事故等を防止する観点からである。   After forming a part of the foundation such as the footing, the column member 64 is installed and fixed to the anchor bolt 26 protruding from the footing 62 configured through the column base reinforcing bar unit 10 (see FIG. 14). Then, as shown in FIG. A steel beam 66 on the upper floor, a floor deck plate 68, and the like are erected between the standing column members 64 (column beam building process). In addition, after the formation of a part of the foundation, in parallel with the column beam construction process, the remaining foundation part was installed with a stop form for forming underground beams (not shown), and foundation work such as concrete placement (Basic rest placement process). Here, the column beam erection method and the foundation remaining portion placing step are performed at positions that do not overlap vertically as shown in FIG. This is from the viewpoint of preventing accidents caused by falling objects from upper floors.

また、本実施形態に係る建築工法を実施する場合、例えば図16に示すA〜Hのそれぞれが、工事区域を区分けした各スパンであるとした場合、柱梁建て方工程と、基礎残部打設工程は、それぞれ異なるスパンをスタートとして、時計回り、あるいは反時計回りでスパンを切り替えるように作業を進めるようにすると良い。より具体的には、例えば柱梁建て方工程については、スパンAを基点として、時計回りにスパンE、スパンF、スパンG、スパンH、スパンD、スパンC、スパンBと作業を進めるようにすれば良い。一方、基礎残部打設工程では、例えばスパンHを基点として、スパンD、スパンC、スパンB、スパンA、スパンE、スパンF、スパンGといった順序で作業進めるようにすれば良い。   Moreover, when implementing the construction method according to the present embodiment, for example, when each of A to H shown in FIG. 16 is each span that divides the construction area, the column beam building method and the foundation remaining portion placement In the process, it is preferable to start the different spans and proceed to switch the spans clockwise or counterclockwise. More specifically, for example, in the column beam building process, the operation is advanced in the clockwise direction with span A as the base point, span E, span F, span G, span H, span D, span C, and span B. Just do it. On the other hand, in the foundation remaining portion placing step, for example, the operation may be performed in the order of span D, span C, span B, span A, span E, span F, and span G, starting from span H.

このように、本実施形態に係る柱脚鉄筋ユニットを用いた建築工法によれば、上層階の梁の建て方作業のような上部構造工事を、基礎工事の完了を待たずに前倒しで行う事が可能となる。よって、平面積が大きい倉庫のような多スパン建物の工期を大幅に短縮することが可能となる。   As described above, according to the construction method using the column base reinforcing bar unit according to the present embodiment, the superstructure work such as the beam construction work on the upper floor can be performed ahead of time without waiting for the completion of the foundation work. Is possible. Therefore, the construction period of a multi-span building such as a warehouse having a large flat area can be greatly shortened.

また、実施形態に係る柱脚鉄筋ユニット10は、ユニット化する構成範囲をさらに広げたものであっても良い。例えば、柱脚鉄筋ユニット10の近傍に配される地中梁の主筋52(地中梁の主筋の一部)や、この主筋52周りの肋筋56を予め配筋し、これを1つのユニットとするものである。このような大型ユニットを捨てコン配置工程後に生コンクリート50上に配置し、下部フーチングを構成するための主筋54や肋筋58を配筋することで、現場施工時における揚重回数や工数の低減を図ることができる。なお、実施形態に係る柱脚鉄筋ユニット10は、PCaに比べて軽量なため、このような大型ユニットを構成した場合であっても、運搬、および揚重に支障を来すことがない。   Further, the columnar reinforcing bar unit 10 according to the embodiment may be a unit in which the configuration range to be unitized is further expanded. For example, the main beam 52 of the underground beam (a part of the main beam of the underground beam) arranged in the vicinity of the column base reinforcing bar unit 10 and the reinforcing bar 56 around the main beam 52 are arranged in advance, and this is arranged as one unit. It is what. By discarding such a large unit and placing it on the ready-mixed concrete 50 after the con placement process, and arranging the main reinforcement 54 and the reinforced reinforcement 58 to form the lower footing, the number of lifting operations and man-hours during on-site construction are reduced Can be achieved. In addition, since the columnar reinforcement unit 10 which concerns on embodiment is lightweight compared with PCa, even if it is a case where such a large sized unit is comprised, it will not interfere with conveyance and lifting.

上記実施形態においては、基礎工事と上層階(例えば2階部分の梁、床のデッキ工事等)を並行して行う点を記載し、この場合には、柱梁建て方工程と、基礎残部打設工程とを異なるスパンで行う事が良い旨記載した。しかしながら、例えば5階建ての建物の場合、2階の床のデッキ工事が終われば(または床打設工程が終われば)、3階以上の建て方工程と基礎残部打設工程とを同じスパンで行うこともできる。上述した上層階工事部からの落下物による事故の危険性が無いからである。このような工法によれば、2階の床部分が日陰、あるいは雨除けとなるため、暑中や雨天時の作業環境が改善されることとなる。   In the above embodiment, the point that the foundation work and the upper floor (for example, the beam on the second floor, the floor deck work, etc.) are performed in parallel is described. It was stated that the installation process should be done in a different span. However, for example, in the case of a five-story building, once the floor construction on the second floor is completed (or the floor placing process is finished), the building process and the foundation remaining part placing process on the third floor or more are performed in the same span. It can also be done. This is because there is no risk of accidents due to falling objects from the above-mentioned upper floor construction section. According to such a construction method, since the floor portion of the second floor is shaded or protected from rain, the working environment in the heat and rain is improved.

また、上記実施形態においては、柱梁鉄筋ユニット10の上部に立設する柱について、アンカーボルト26に接続される鉄骨柱などを想定して記載しているが、柱脚部としての利用が可能であれば、上部構造物に関する限定は無い。例えば鉄筋コンクリートによる柱を適用したり、柱脚部と柱の間に免震ユニットを介在させるような適用方法であっても良い。   Further, in the above embodiment, the column standing on the upper part of the column beam reinforcing unit 10 is described assuming a steel column connected to the anchor bolt 26, but it can be used as a column base. If so, there is no limitation on the superstructure. For example, an application method in which a column made of reinforced concrete is applied or a seismic isolation unit is interposed between the column base and the column may be used.

また、柱脚鉄筋ユニット10のアンカー部24に対する柱の接続、固定工法等についても限定するものでは無く、既存の各種技術を適用することができ、例えばNCベース工法などの適用も可能となる。   Further, the connection of the column to the anchor portion 24 of the column base reinforcing bar unit 10 and the fixing method are not limited, and various existing techniques can be applied. For example, an NC base method can be applied.

さらに、上記実施形態では、主に建物を対象とした柱脚鉄筋ユニット、およびこれを用いた構築方法であるように説明したが、橋梁など、建築物以外の構造物を構築する際に適用することもできる。   Furthermore, in the above-described embodiment, it has been described that the column-base reinforcing bar unit is mainly intended for buildings and the construction method using the same. However, the present invention is applied when constructing structures other than buildings such as bridges. You can also.

また、当然に、上記実施形態に係る構築方法を実施するにあたっては、既知の施工技術を適用することで、施工精度の向上や労力の軽減を図るようにしても良い。例えば、柱脚鉄筋ユニット10の高さが高い場合には、上述した特許文献1に開示されているような仮設斜材(斜め鉄筋)を配置し、柱脚鉄筋ユニット10の水平維持を図るようにしても良い。   Naturally, when implementing the construction method according to the above-described embodiment, the construction accuracy may be improved and the labor may be reduced by applying a known construction technique. For example, when the height of the columnar reinforcing bar unit 10 is high, a temporary diagonal member (diagonal reinforcing bar) as disclosed in Patent Document 1 described above is arranged to maintain the columnar reinforcing bar unit 10 horizontally. Anyway.

また、柱脚鉄筋ユニット10の設置に関する汎用性が高いことより、柱脚鉄筋ユニット10の設置個所に杭頭などが突設している場合には、当該杭頭を避ける治具金物を配置し、この治具金物に対して柱脚鉄筋ユニット10を配置するようにしても良い。   Also, because of the high versatility related to the installation of the column base rebar unit 10, when a pile head or the like protrudes from the installation location of the column base reinforcement unit 10, a jig hardware that avoids the pile head is arranged. Further, the column base reinforcing bar unit 10 may be arranged with respect to the jig hardware.

10………柱脚鉄筋ユニット、12………柱脚基礎打設用鉄筋部、14………主筋、14a………長尺主筋、14b………短尺主筋、16………肋筋、17………レベル調整ナット、18………ベース金物、18a………ソケット、18b………平板、20………定着体、22a,22b………主筋位置保持プレート、24………アンカー部、26………アンカーボルト、28………テンプレート、30………定着板、30a………ナット、32………ラス型枠、34………斜め補強筋、50………生コンクリート、52………主筋、54………主筋、56………肋筋、58………肋筋、60………止め型枠、62………フーチング、64………柱部材、66………鉄骨梁、68………デッキプレート。 10 ......... Column base reinforcement unit, 12 ......... Column base foundation reinforcement, 14 ......... Main reinforcement, 14a ......... Long main reinforcement, 14b ......... Short main reinforcement, 16 ......... Reinforcement, 17 ......... Level adjustment nut, 18 ......... Base hardware, 18a ......... Socket, 18b ......... Plate, 20 ...... Fixing body, 22a, 22b ......... Main bar position holding plate, 24 ......... Anchor 26, ... Anchor bolt, 28 ... Template, 30 ... Fixing plate, 30a ... Nuts, 32 ... Lath form, 34 ... Diagonal reinforcement, 50 ... Ready-mixed concrete , 52... Main muscle, 54... Main muscle, 56... Gluteal muscle, 58... Gluteal muscle, 60... …… Steel beam, 68 ……… Deck plate.

Claims (4)

複数の主筋と、複数の前記主筋を取り囲むように配置された複数の肋筋とを有する柱脚基礎打設用鉄筋部と、
前記柱脚基礎打設用鉄筋部の内部に配置され、柱との接合を担うアンカー部と、を有し、
前記柱脚基礎打設用鉄筋部には、当該柱脚基礎打設用鉄筋部の断面形状を維持する主筋位置保持プレートが複数備えられ、
前記アンカー部は、前記主筋位置保持プレートに固定されていることを特徴とする柱脚鉄筋ユニット。
A column base foundation placing reinforcing bar portion having a plurality of main bars and a plurality of barbs arranged to surround the plurality of main bars;
An anchor portion that is arranged inside the column base foundation placing reinforcing bar portion and bears a connection with the column;
A plurality of main bar position holding plates for maintaining the cross-sectional shape of the column base foundation placement reinforcing bars are provided in the column base foundation placement reinforcing bars,
The anchor base is fixed to the main bar position holding plate.
捨てコン打設工程と、
前記捨てコンが硬化した後、柱脚部を構成する鉄筋をユニットとして予め組み上げた柱脚鉄筋ユニットを前記捨てコン上に配置、固定する鉄筋ユニット配置工程と、
前記柱脚鉄筋ユニットに対して基礎梁主筋や基礎肋筋を挿通配置する基礎筋配置工程と、
前記柱脚鉄筋ユニットの周囲に基礎の一部を形成するコンクリートを打設する基礎コンクリート一部打設工程と、
前記柱脚鉄筋ユニット上に柱を配置固定し、梁を架設する柱梁建て方工程と、
前記基礎コンクリート一部打設工程以後の基礎工事を行う基礎残部打設工程と、
を有する構築物の構築方法であって、
前記柱梁建て方工程と、前記基礎残部打設工程とを並行して行うことを特徴とする柱脚鉄筋ユニットを用いた構築物の構築方法。
Abandoned con placement process,
After the abandoned container is cured, a reinforcing bar unit arranging step for arranging and fixing the column base reinforcing bar unit assembled in advance as a unit with the reinforcing bars constituting the column base part on the discarded container;
A foundation reinforcement arrangement step of inserting and arranging foundation beam reinforcements and foundation reinforcements with respect to the column base reinforcement unit;
A foundation concrete part placing step for placing concrete that forms part of the foundation around the column base reinforcing bar unit;
Column beam construction method of arranging and fixing columns on the column base reinforcing bar unit and erection of the beams,
Foundation remaining part placing process for performing foundation work after the foundation concrete part placing process,
A method for constructing a construct having
A method for constructing a structure using a column base reinforcing bar unit, wherein the column beam building method step and the foundation remaining portion placing step are performed in parallel.
前記柱梁建て方工程には、上階床工事を含むことを特徴とする請求項2に記載の柱脚鉄筋ユニットを用いた構築物の構築方法。   The method for constructing a structure using the column base reinforcing bar unit according to claim 2, wherein the column beam building process includes upper floor construction. 前記柱梁建て方工程と、前記基礎残部打設工程は、平面的に区分けされた複数のスパン毎に行われ、前記柱梁建て方工程を実施するスパンと、前記基礎残部打設工程を実施するスパンとを異ならせたことを特徴とする請求項2又は3に記載の柱脚鉄筋ユニットを用いた構築物の構築方法。   The column beam erection method and the foundation remaining portion placing step are performed for each of a plurality of spans divided in a plane, and the span for performing the column beam erection method and the foundation remaining portion placing step are performed. The method for constructing a structure using the columnar reinforcing bar unit according to claim 2 or 3, wherein the span to be made is different.
JP2017182562A 2017-09-22 2017-09-22 Column base reinforcement unit and method for constructing structure using column base reinforcement unit Pending JP2019056284A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017182562A JP2019056284A (en) 2017-09-22 2017-09-22 Column base reinforcement unit and method for constructing structure using column base reinforcement unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017182562A JP2019056284A (en) 2017-09-22 2017-09-22 Column base reinforcement unit and method for constructing structure using column base reinforcement unit

Publications (1)

Publication Number Publication Date
JP2019056284A true JP2019056284A (en) 2019-04-11

Family

ID=66106447

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017182562A Pending JP2019056284A (en) 2017-09-22 2017-09-22 Column base reinforcement unit and method for constructing structure using column base reinforcement unit

Country Status (1)

Country Link
JP (1) JP2019056284A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112211045A (en) * 2020-10-19 2021-01-12 中建八局广西建设有限公司 Base plate embedded structure of straddle type monorail traffic and construction method
CN114922428A (en) * 2022-05-16 2022-08-19 吉林省新生建筑工程有限公司 Wall module pre-assembly method assembly type building construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112211045A (en) * 2020-10-19 2021-01-12 中建八局广西建设有限公司 Base plate embedded structure of straddle type monorail traffic and construction method
CN114922428A (en) * 2022-05-16 2022-08-19 吉林省新生建筑工程有限公司 Wall module pre-assembly method assembly type building construction method

Similar Documents

Publication Publication Date Title
JP2018115489A (en) Anchor frame and method of building steel frame structure using the same
KR20200032316A (en) Method for Forming Top-down-typed Underground Strucutre using Trus-typed Support
JP2019056284A (en) Column base reinforcement unit and method for constructing structure using column base reinforcement unit
JP2915897B1 (en) Building construction method
JP2016205051A (en) Construction method for structure
KR102149662B1 (en) Method for constructing transfer layer of building using precast concrete slab
JP6849491B2 (en) Exposed column base structure of steel columns and its construction method
KR101880813B1 (en) A sandwitch pc pannel structure and construction method of structure using thereof
JP3421298B2 (en) Internal stairs for buildings and method of construction
JP6690988B2 (en) How to build a composite foundation structure
JP5912194B1 (en) Construction method of wooden building and basic member used in the construction method
JP2002030672A (en) Structure of joining foundation pile to pier base and method of constructing the structure
JP6953723B2 (en) Construction method of seismic isolation structure
JP2017203303A (en) Construction method of composite foundation structure
JP2022096117A (en) Equipment foundation structure
KR20130022656A (en) Hybrid building construction method combining dry type and wet type
JP5345238B1 (en) Construction method of base-isolated base structure and base-isolated base structure
JPH1129910A (en) Method for constructing concrete pier
JPH0657710A (en) Construction of concrete main tower
JP2000160687A (en) Construction method for composite structure and precast concrete column
JP6577786B2 (en) Anchoring structure of pile head joint in pile head base isolation structure
JP5635939B2 (en) Construction method of column beam frame
JP7198148B2 (en) Precast construction method for balcony floor
JP6300228B2 (en) Flat slab structure
KR102266630B1 (en) Construction method of building with composite beam structure using module deck