JP2018150792A - Concrete finishing method - Google Patents

Concrete finishing method Download PDF

Info

Publication number
JP2018150792A
JP2018150792A JP2018034325A JP2018034325A JP2018150792A JP 2018150792 A JP2018150792 A JP 2018150792A JP 2018034325 A JP2018034325 A JP 2018034325A JP 2018034325 A JP2018034325 A JP 2018034325A JP 2018150792 A JP2018150792 A JP 2018150792A
Authority
JP
Japan
Prior art keywords
concrete
tamping
rails
leveling
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2018034325A
Other languages
Japanese (ja)
Other versions
JP6437150B2 (en
Inventor
公夫 中川
Kimio Nakagawa
公夫 中川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Floor Support Co Ltd
Original Assignee
Floor Support Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Floor Support Co Ltd filed Critical Floor Support Co Ltd
Priority to JP2018034325A priority Critical patent/JP6437150B2/en
Publication of JP2018150792A publication Critical patent/JP2018150792A/en
Application granted granted Critical
Publication of JP6437150B2 publication Critical patent/JP6437150B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a concrete finishing method which expands an area to be leveled in a short period at a time compared to manual leveling and neatly finishes a concrete surface with sufficient strength.SOLUTION: A concrete finishing method comprises: a first leveling process to level concrete UC placed between two rails 20, before the same hardens, with a rotary driven tube roller 10 driven on the rails; and a first tamping process to tamp a surface of the concrete, leveled in the first leveling process before the same hardens, with a vibratory tamping machine.SELECTED DRAWING: Figure 1

Description

本発明は、平面(床面)および法面(傾斜面)の両方において、硬化前のコンクリートを流し込んで均してから硬化させるコンクリート施工法に関する。   The present invention relates to a concrete construction method in which concrete before being hardened is poured and leveled on both a flat surface (floor surface) and a slope surface (inclined surface).

従来、硬化前のコンクリートの表面と接触する均し板と、均し板に搭載された振動発生手段と、均し板に取り付けられた操作ハンドルとを備えた均し装置を用いてコンクリートの表面を平準化する均し工程と、プロペラ状の動力式回転鏝を有する平面均し機と、平板状の仕上げ鏝と、仕上げ鏝をコンクリートの表面へ押圧する重錘とを備えた仕上げ装置を用いてコンクリートの表面を仕上げる仕上げ工程とを備えた床面施工法が知られている(例えば、特許文献1)。   Conventionally, the surface of the concrete using a leveling device having a leveling plate in contact with the surface of the concrete before hardening, a vibration generating means mounted on the leveling plate, and an operation handle attached to the leveling plate A finishing device equipped with a leveling process for leveling, a leveling machine with a propeller-like power rotary rod, a flat finishing rod, and a weight for pressing the finishing rod against the concrete surface A floor surface construction method including a finishing process for finishing the surface of concrete is known (for example, Patent Document 1).

特許3913263号公報Japanese Patent No. 3913263

しかしながら、上述した従来の床面施工法の均し装置を用いた均し工程は、コンクリートの強度を上げるために均し装置を振動させながらコンクリートを叩きながら均す所謂、タンピング工程であり、硬化前のコンクリートがある程度均されてからでなければ、均し装置を使用できない。   However, the above-described leveling process using the leveling apparatus of the conventional floor construction method is a so-called tamping process in which the leveling apparatus is vibrated to beat the concrete while vibrating the leveling apparatus in order to increase the strength of the concrete. The leveling device can only be used after the previous concrete has been leveled.

そのため、生コンクリートを流し込む工程である所謂、生コンクリート打設工程の後、作業者がかき板やコンクリートを均す荒均し工程、および作業者が木製の直線定規をコンクリートに当ててきれいに均す定規擦り工程をする必要があり、その後に上述した均し装置を用いてコンクリートの表面を平準化する均し工程を行っていた。   Therefore, after the so-called ready-mixed concrete pouring process, which is the process of pouring ready-mixed concrete, the roughening process in which the operator leveles the chopping board and concrete, and the operator applies a wooden straight ruler to the concrete to level it cleanly. It was necessary to perform a ruler rubbing process, and thereafter, a leveling process was performed to level the surface of the concrete using the above-described leveling apparatus.

均し装置を用いた均し工程よりも前工程では、広い範囲を施工する場合、多数の作業者が荒均し工程や定規擦り工程をする必要があり、少ない人数では短時間で広い範囲の生コンクリートをきれいに均すことが困難であるという問題があった。   In the process before the leveling process using the leveling device, when a wide range is to be constructed, it is necessary for a large number of workers to perform the leveling process and ruler rubbing process. There was a problem that it was difficult to level the green concrete cleanly.

そこで、本発明は、前述したような従来技術の問題を解決するものであって、すなわち、本発明の目的は、手作業で均す場合と比べて、短時間で一度に均す範囲を広くするコンクリート施工法を提供することである。   Therefore, the present invention solves the problems of the prior art as described above, that is, the purpose of the present invention is to widen the range to be averaged in a short time compared to the case of leveling by hand. It is to provide a concrete construction method.

本請求項1に係る発明は、硬化前のコンクリートを流し込んで均してから硬化させるコンクリート施工法において、2本のレール上において回転駆動式チューブローラをレールに沿って移動させて2本のレール間の硬化前のコンクリートを均す第1均し工程と、前記第1均し工程で均した硬化前のコンクリートの表面を振動式タンピング機を用いてタンピングする第1タンピング工程とを具備することにより、前述した課題を解決するものである。   According to the first aspect of the present invention, in the concrete construction method in which the uncured concrete is poured, leveled, and hardened, the two drive rails are moved along the rails on the two rails. A first leveling step of leveling the uncured concrete, and a first tamping step of tamping the surface of the concrete before curing leveled in the first leveling step using a vibratory tamping machine. Thus, the above-described problem is solved.

本請求項2に係る発明は、請求項1に記載されたコンクリート施工法の構成に加えて、前記第1均し工程の回転駆動式チューブローラの移動方向に対する回転方向が、移動方向に転がるときの回転方向と逆方向であり、前記回転駆動式チューブローラが、駆動手段によって逆方向に回転しながらレール上をスライド移動することにより、前述した課題をさらに解決するものである。   In the invention according to claim 2, in addition to the concrete construction method described in claim 1, when the rotation direction of the first leveling step with respect to the moving direction of the rotationally driven tube roller rolls in the moving direction. The rotational drive tube roller slides on the rail while being rotated in the reverse direction by the driving means, thereby further solving the above-described problem.

本請求項3に係る発明は、請求項1または請求項2に記載されたコンクリート施工法の構成に加えて、前記第1均し工程において、前記2本のレールが水平方向に対して傾いて設置され、前記回転駆動式チューブローラの移動方向が、斜面下方から斜面上方へ向かう方向であることにより、前述した課題をさらに解決するものである。   In the invention according to claim 3, in addition to the concrete construction method described in claim 1 or claim 2, in the first leveling step, the two rails are inclined with respect to the horizontal direction. It is installed, and the moving direction of the rotationally driven tube roller is a direction from the lower side of the slope to the upper side of the slope, thereby further solving the aforementioned problems.

本請求項4に係る発明は、請求項3に記載されたコンクリート施工法の構成に加えて、前記第1タンピング工程において、前記振動式タンピング機の移動方向が、前記斜面上方から斜面下方へ向かう方向であることにより、前述した課題をさらに解決するものである。   According to the fourth aspect of the present invention, in addition to the concrete construction method described in the third aspect, in the first tamping step, the moving direction of the vibratory tamping machine is directed from the upper side of the slope to the lower side of the slope. By being in the direction, the above-described problem is further solved.

本請求項5に係る発明は、請求項1乃至請求項4のいずれか1つに記載されたコンクリート施工法の構成に加えて、前記2本のレールの内側には、レール延設方向に沿って弾性体が設けられていることにより、前述した課題をさらに解決するものである。   In the invention according to claim 5, in addition to the configuration of the concrete construction method described in any one of claims 1 to 4, the inside of the two rails is along the rail extending direction. Thus, the above-described problem is further solved by providing the elastic body.

本請求項6に係る発明は、請求項1乃至請求項5のいずれか1つに記載されたコンクリート施工法の構成に加えて、前記第1均し工程を2本のレールの外側で間隔を空けて複数箇所で行い、前記2本のレール間のコンクリートを硬化させるとともにレールを除去するレール除去工程と、前記レール除去工程の後に2ヶ所の硬化コンクリート間にコンクリートを流し込んで回転駆動式チューブローラを2ヶ所の硬化コンクリートに沿って移動させて2ヶ所の硬化コンクリート間の硬化前のコンクリートを均す第2均し工程とをさらに具備することにより、前述した課題をさらに解決するものである。   In the invention according to claim 6, in addition to the configuration of the concrete construction method described in any one of claims 1 to 5, the first leveling step is performed outside the two rails. Rotating drive type tube roller which is carried out at a plurality of positions and hardens the concrete between the two rails and removes the rail, and the concrete is poured between the two hardened concretes after the rail removing step. The above-mentioned problem is further solved by further including a second leveling step of moving the two along the two hardened concretes and leveling the unhardened concrete between the two hardened concretes.

本請求項7に係る発明は、請求項6に記載されたコンクリート施工法の構成に加えて、前記第2均し工程で均した硬化前のコンクリートの表面を振動式タンピング機を用いてタンピングする第2タンピング工程をさらに具備することにより、前述した課題をさらに解決するものである。   According to the seventh aspect of the invention, in addition to the concrete construction method described in the sixth aspect, the surface of the concrete before hardening leveled in the second leveling step is tamped using a vibration type tamping machine. By further comprising the second tamping step, the above-described problem is further solved.

本請求項8に係る発明は、硬化前のコンクリートを流し込んで均してから硬化させるコンクリート施工法において、施工面である平面に設置された2本のレール上において回転駆動式チューブローラをレールに沿って移動させて2本のレール間の硬化前のコンクリートを均す第1均し工程を具備することにより、前述した課題を解決するものである。   According to the eighth aspect of the present invention, in the concrete construction method in which the uncured concrete is poured, leveled, and hardened, the rotationally driven tube roller is used as the rail on the two rails installed on the flat surface as the construction surface. The above-described problem is solved by providing a first leveling step that moves along the rail and smooths the concrete before hardening between the two rails.

本請求項9に係る発明は、硬化前のコンクリートを流し込んで均してから硬化させるコンクリート施工法において、施工面である傾斜面の傾斜方向に沿って設置された2本のレール上において回転駆動式チューブローラをレールに沿って移動させて2本のレール間の硬化前のコンクリートを均す第1均し工程を具備することにより、前述した課題を解決するものである。   The invention according to claim 9 is a concrete construction method in which concrete before being hardened is poured, hardened and hardened, and is driven to rotate on two rails installed along the slope direction of the slope which is the construction surface. The above-described problem is solved by providing a first leveling step of moving the type tube roller along the rails to level the unhardened concrete between the two rails.

本発明のコンクリート施工法は、硬化前のコンクリートを流し込んで均してから硬化させることができるばかりでなく、以下のような特有の効果を奏することができる。   The concrete construction method of the present invention can not only be hardened by pouring and smoothing the uncured concrete, but also has the following specific effects.

本請求項1に係る発明のコンクリート施工法によれば、2本のレールである所謂、アングル間の硬化前のコンクリートに対して回転駆動式チューブローラの平滑さおよび自重が作用して、手作業で均す場合と比べて、一度に均す範囲が広くなるとともに短時間で均されるため、コンクリートの表面をきれいに仕上げることができる。   According to the concrete construction method of the invention according to claim 1, the smoothness and the own weight of the rotationally driven tube roller act on the so-called concrete that is the two rails before being hardened between the angles, so that manual work is performed. Compared with the case of leveling, the range to be leveled at once is widened and the leveling is done in a short time, so that the concrete surface can be finished cleanly.

つまり、従来の手作業による荒均し工程および定規擦り工程が不要になるため、作業者の人数を少なくするとともに短時間で広い範囲のコンクリートをきれいに均すことができる。   In other words, the conventional manual leveling process and ruler rubbing process are not required, so that the number of workers can be reduced and a wide range of concrete can be leveled cleanly in a short time.

さらに、硬化前のコンクリートの内部に振動が加わって内部のエアーが表面に移動して表面から逃げてコンクリートの密度が高くなるため、コンクリートの強度を上げることができる。   Furthermore, vibration is applied to the inside of the concrete before hardening, and the air inside moves to the surface and escapes from the surface to increase the density of the concrete, so that the strength of the concrete can be increased.

また、硬化前のコンクリートの内部に振動が加わって内部の比重の大きい骨材が下方へ移動(沈降)するとともに比重の小さい余剰水が表面に移動して表面に浮いて、コンクリートの密度が高くなるため、コンクリートの強度を上げることができる。   In addition, vibration is applied to the inside of the concrete before hardening, and the aggregate with a large specific gravity moves downward (sinks), and excess water with a small specific gravity moves to the surface and floats on the surface, and the density of the concrete is high. Therefore, the strength of the concrete can be increased.

つまり、タンピングにより、コンクリート内の良質なセメントペースト層をコンクリート表層に成形することができる。   That is, a high quality cement paste layer in the concrete can be formed on the concrete surface layer by tamping.

さらに、第1均し工程および第1タンピング工程の両工程に機械が用いられて第1均し工程で均されたコンクリートの表面が硬化前に第1タンピング工程で素早く広範囲にタンピングされて、確実にコンクリートの内部のエアーおよび余剰水が逃げるため、短時間で広範囲にわたって施工した場合であっても、コンクリートの内部の細かい水の通り道やエアーだまりを無くしてクラックを発生しにくくすることができる。   In addition, the machine is used in both the first leveling process and the first tamping process, and the surface of the concrete leveled in the first leveling process is tamped quickly and extensively in the first tamping process before hardening. In addition, since the air and excess water inside the concrete escape, even if it is constructed over a wide range in a short time, it is possible to eliminate the passage of fine water and the air pool inside the concrete and make it difficult to generate cracks.

本請求項2に係る発明のコンクリート施工法によれば、請求項1に係る発明が奏する効果に加えて、回転駆動式チューブローラの回転運動によって移動方向上流側から下流側へ余分な硬化前のコンクリートがかき出されるため、凹凸が少ないコンクリートの表面を容易に作成することができる。   According to the concrete construction method of the invention according to claim 2, in addition to the effect of the invention according to claim 1, before the excessive hardening from the upstream side in the moving direction to the downstream side by the rotational movement of the rotationally driven tube roller. Since the concrete is scraped out, it is possible to easily create a concrete surface with few irregularities.

本請求項3に係る発明のコンクリート施工法によれば、請求項1または請求項2に係る発明が奏する効果に加えて、2本のレール間の硬化前のコンクリートの余分な部分が斜面下方から上方へかき出されながら2本のレール間の硬化前のコンクリートの表面が均されるため、硬化前のコンクリートの表面が斜面下方へ流れてしまうことを回避できる。   According to the concrete construction method of the invention according to claim 3, in addition to the effect of the invention according to claim 1 or claim 2, the extra portion of the concrete before hardening between the two rails is from below the slope. Since the surface of the concrete before hardening between the two rails is leveled while being scraped upward, it can be avoided that the surface of the concrete before hardening flows downward on the slope.

本請求項4に係る発明のコンクリート施工法によれば、請求項3に係る発明が奏する効果に加えて、硬化前のコンクリートの水分は斜面上方から下方へ向かって流れて、斜面下方と比べて斜面上方の方が早く乾く傾向があり、早く乾く側から先にタンピングが行われるため、コンクリートの硬化前にエアーおよび余剰水を確実に逃がしてコンクリートのクラック発生を回避できる。   According to the concrete construction method of the invention according to claim 4, in addition to the effect of the invention according to claim 3, the moisture of the concrete before hardening flows downward from the upper side of the slope, compared with the lower side of the slope. There is a tendency that the upper part of the slope dries faster, and tamping is performed first from the side that dries faster, so that air and excess water can be surely released before the concrete is hardened, and cracking of the concrete can be avoided.

本請求項5に係る発明のコンクリート施工法によれば、請求項1乃至請求項4のいずれか1つに係る発明が奏する効果に加えて、第1均し工程のときは弾性体が硬化前のコンクリートから力を受けてレール幅方向に圧縮変形するが、2本のレールの内側のコンクリートが硬化してレール幅方向に収縮すると弾性体が元の形状に戻ろうとして、コンクリートの幅方向両端で2本のレールの外側に引っ張られる力が弾性体で緩和されるため、2本のレールを設置したことで発生する外側に引っ張られる力に起因するクラック発生を回避できる。   According to the concrete construction method of the invention according to claim 5, in addition to the effect exerted by the invention according to any one of claims 1 to 4, the elastic body is not cured at the time of the first leveling step. Compressed and deformed in the rail width direction under the force of the concrete, but when the concrete inside the two rails hardened and contracted in the rail width direction, the elastic body tried to return to its original shape, and both ends of the concrete width direction Thus, since the force pulled to the outside of the two rails is relieved by the elastic body, it is possible to avoid the occurrence of cracks due to the force pulled to the outside generated by installing the two rails.

本請求項6に係る発明のコンクリート施工法によれば、請求項1乃至請求項5のいずれか1つに係る発明が奏する効果に加えて、第1均し工程で均した複数のコンクリートの幅方向端部が第2均し工程で2本のレールの役割を果たして、第1均し工程と同様に、手作業で均す場合と比べて、一度に均す範囲が広くなるとともに短時間で均されるため、コンクリートの表面をきれいに仕上げることができる。   According to the concrete construction method of the invention according to claim 6, in addition to the effect of the invention according to any one of claims 1 to 5, the widths of the plurality of concrete leveled in the first leveling step The end of the direction plays the role of two rails in the second leveling process, and in the same way as in the first leveling process, the range to be leveled at a time is wider and shorter than in the case of manual leveling. Since it is leveled, the concrete surface can be finished cleanly.

本請求項7に係る発明のコンクリート施工法によれば、請求項6に係る発明が奏する効果に加えて、第1タンピング工程と同様に、硬化前のコンクリートの内部に振動が加わって内部のエアーが表面に移動して表面から逃げてコンクリートの密度が高くなるため、コンクリートの強度を上げることができる。   According to the concrete construction method of the invention according to claim 7, in addition to the effect produced by the invention according to claim 6, as in the first tamping step, vibration is applied to the interior of the concrete before hardening, and the internal air Since it moves to the surface and escapes from the surface and the density of the concrete increases, the strength of the concrete can be increased.

また、硬化前のコンクリートの内部に振動が加わって内部の比重の大きい骨材が下方へ移動するとともに比重の小さい余剰水が表面に移動して表面に浮いて、コンクリートの密度が高くなるため、コンクリートの強度を上げることができる。   In addition, vibration is applied to the inside of the concrete before hardening, and the aggregate with a large specific gravity moves downward and surplus water with a small specific gravity moves to the surface and floats on the surface, and the density of the concrete increases. The strength of concrete can be increased.

本請求項8に係る発明のコンクリート施工法によれば、施工面である平面において、2本のレールである所謂、アングル間の硬化前のコンクリートに対して回転駆動式チューブローラの平滑さおよび自重が作用して、手作業で均す場合と比べて、一度に均す範囲が広くなるとともに短時間で均されるため、コンクリートの表面をきれいに仕上げることができる。   According to the concrete construction method of the invention according to claim 8, the smoothness and self-weight of the rotationally driven tube roller with respect to the so-called concrete before curing between the angles, which are two rails, in the plane which is the construction surface. As compared with the case of manual leveling, the range to be leveled at once is widened and leveled in a short time, so that the concrete surface can be finished cleanly.

つまり、従来の手作業による荒均し工程および定規擦り工程が不要になるため、作業者の人数を少なくするとともに短時間で広い範囲のコンクリートをきれいに均すことができる。   In other words, the conventional manual leveling process and ruler rubbing process are not required, so that the number of workers can be reduced and a wide range of concrete can be leveled cleanly in a short time.

本請求項9に係る発明のコンクリート施工法によれば、施工面である傾斜面において、2本のレールである所謂、アングル間の硬化前のコンクリートに対して回転駆動式チューブローラの平滑さおよび自重が作用して、手作業で均す場合と比べて、一度に均す範囲が広くなるとともに短時間で均されるため、コンクリートの表面をきれいに仕上げることができる。   According to the concrete construction method of the invention according to claim 9, the smoothness of the rotationally driven tube roller and the so-called concrete between the angles, which are two rails, on the inclined surface that is the construction surface, and Compared to the case of manual leveling due to its own weight, the leveling range is widened at once and leveled in a short time, so that the concrete surface can be finished cleanly.

つまり、従来の手作業による荒均し工程および定規擦り工程が不要になるため、作業者の人数を少なくするとともに短時間で広い範囲のコンクリートをきれいに均すことができる。
In other words, the conventional manual leveling process and ruler rubbing process are not required, so that the number of workers can be reduced and a wide range of concrete can be leveled cleanly in a short time.

本発明の第1実施例のコンクリート施工法の第1均し工程の様子を示す斜視図。The perspective view which shows the mode of the 1st leveling process of the concrete construction method of 1st Example of this invention. (A)(B)は図1の符号2A、符号2Bから視た図。(A) (B) is the figure seen from the code | symbol 2A of FIG. 1, and the code | symbol 2B. 本発明のコンクリート施工法のフローを示す図。The figure which shows the flow of the concrete construction method of this invention. 本発明の第1実施例の第1タンピング工程の様子を示す斜視図。The perspective view which shows the mode of the 1st tamping process of 1st Example of this invention. (A)(B)はタンピング前後のコンクリートの内部を示す概念図。(A) (B) is a conceptual diagram which shows the inside of the concrete before and behind tamping. 本発明の第1実施例の第1均し工程および第2均し工程の場所の関係を示す図。The figure which shows the relationship of the place of the 1st leveling process and 2nd leveling process of 1st Example of this invention. 本発明の第1実施例の第2均し工程の様子を示す斜視図。The perspective view which shows the mode of the 2nd leveling process of 1st Example of this invention. 本発明の第2実施例のレールを示す斜視図。The perspective view which shows the rail of 2nd Example of this invention. (A)(B)は図8の符号9−9で視たコンクリート硬化前および硬化後の断面図。(A) and (B) are cross-sectional views before and after concrete hardening as seen by reference numeral 9-9 in FIG.

本発明のコンクリート施工法は、施工面である平面に沿って、または、傾斜面の傾斜方向に沿って設置された2本のレール上において回転駆動式チューブローラをレールに沿って移動させて2本のレール間の硬化前のコンクリートを均す第1均し工程を具備することにより、コンクリートの表面をきれいに仕上げるものであれば、その具体的な実施態様は、如何なるものであっても構わない。   According to the concrete construction method of the present invention, the rotationally driven tube roller is moved along the rail along the two rails installed along the plane which is the construction surface or along the inclination direction of the inclined surface. As long as the surface of the concrete is finished finely by providing the first leveling step of leveling the concrete before hardening between the rails of the books, any specific embodiment may be used. .

例えば、レール(アングル)は、金属製パイプ、木製角材、コンクリート面の一部など、少なくとも一部が回転駆動式チューブローラと接触して回転駆動式チューブローラを移動方向へ案内するものであれば如何なるものであっても構わない。   For example, if the rail (angle) is at least partly in contact with the rotationally driven tube roller, such as a metal pipe, wooden square, or part of the concrete surface, the rotationally driven tube roller is guided in the moving direction. It doesn't matter what.

また、振動式タンピング機は、少なくとも一部が振動することによって硬化前のコンクリートを叩く構成であればよく、コンクリートの表面を接触する箇所は、板状部の平面でもよいし、ローラ部の曲面でもよい。   Further, the vibration tamping machine may be configured to strike at least a portion of the concrete before being hardened by vibration, and the surface contacting the concrete may be a flat plate surface or a curved surface of the roller portion. But you can.

以下に、本発明の第1実施例であるコンクリート施工法について、図1乃至図7に基づいて説明する。   Below, the concrete construction method which is 1st Example of this invention is demonstrated based on FIG. 1 thru | or FIG.

ここで、図1は、本発明の第1実施例のコンクリート施工法の第1均し工程の様子を示す斜視図であり、図2(A)は、図1の符号2Aから視た平面図であり、図2(B)は、符号2Bから視た側面図であり、図3は、本発明のコンクリート施工法の概略のフローを示す図であり、図4は、本発明の第1実施例の第1タンピング工程の様子を示す斜視図であり、図5(A)は、タンピング前のコンクリートの内部を示す概念図であり、図5(B)は、タンピング後のコンクリートの内部を示す概念図であり、図6は、本発明の第1実施例の第1均し工程および第2均し工程の場所の関係を示す図であり、図7は、本発明の第1実施例の第2均し工程の様子を示す斜視図である。   Here, FIG. 1 is a perspective view showing the state of the first leveling step of the concrete construction method of the first embodiment of the present invention, and FIG. 2 (A) is a plan view seen from the reference numeral 2A in FIG. FIG. 2 (B) is a side view as viewed from reference numeral 2B, FIG. 3 is a diagram showing a schematic flow of the concrete construction method of the present invention, and FIG. 4 is a first embodiment of the present invention. It is a perspective view which shows the mode of the 1st tamping process of an example, FIG. 5 (A) is a conceptual diagram which shows the inside of the concrete before tamping, and FIG. 5 (B) shows the inside of the concrete after tamping. FIG. 6 is a conceptual diagram, FIG. 6 is a diagram showing the relationship between the locations of the first leveling process and the second leveling process of the first embodiment of the present invention, and FIG. 7 is the diagram of the first embodiment of the present invention. It is a perspective view which shows the mode of a 2nd leveling process.

本発明の第1実施例であるコンクリート施工法は、図1乃至図3に示すように、硬化前のコンクリートUCを流し込むコンクリート流し込み工程の後、均し工程を有している。   As shown in FIGS. 1 to 3, the concrete construction method according to the first embodiment of the present invention has a leveling step after the concrete pouring step for pouring the concrete UC before curing.

均し工程である第1均し工程は、図1乃至図2(B)に示すように、2本のレールである所謂、アングル上において回転駆動式チューブローラ10をレール20に沿って移動させて2本のレール間の硬化前のコンクリートUCを均す。   As shown in FIGS. 1 to 2B, the first leveling process, which is a leveling process, moves the rotationally driven tube roller 10 along the rail 20 on a so-called angle, which is two rails. Level the concrete UC before hardening between the two rails.

一例として、回転駆動式チューブローラ10は、回転軸部11と、駆動手段12と、回転チューブローラ部13と、ハンドル部14と、2本の牽引ロープ15、16とを備えている。   As an example, the rotationally driven tube roller 10 includes a rotating shaft portion 11, a driving means 12, a rotating tube roller portion 13, a handle portion 14, and two tow ropes 15 and 16.

このうち、回転軸部11は、長尺に設けられ、回転チューブローラ部13の内部に挿通されている。   Among these, the rotating shaft portion 11 is provided in a long shape and is inserted into the rotating tube roller portion 13.

駆動手段12は、回転軸部11の一端側に設けられ、例えば、油圧によって回転チューブローラ部13が回転軸部11に対して回転するように両者間に力を加えるように構成されている。   The driving means 12 is provided on one end side of the rotating shaft portion 11 and is configured to apply a force between the rotating tube roller portion 13 and the rotating shaft portion 11 so that the rotating tube roller portion 13 rotates with respect to the rotating shaft portion 11, for example.

回転チューブローラ部13は、駆動手段12から力を受けて回転し、本実施例では、回転駆動式チューブローラ10の移動方向に対してレール上を転がる回転方向と逆方向に回転する。   The rotating tube roller portion 13 is rotated by receiving a force from the driving means 12, and in this embodiment, the rotating tube roller portion 13 rotates in the direction opposite to the rotating direction of rolling on the rail with respect to the moving direction of the rotationally driven tube roller 10.

回転チューブローラ部13の幅は、1m〜30m程であり、直径は、10cm〜50cm程である。   The width | variety of the rotation tube roller part 13 is about 1-30 m, and a diameter is about 10-50 cm.

ハンドル部14は、回転軸部11における駆動手段12が設けられている側に回転軸部11と一体に設けられている。   The handle portion 14 is provided integrally with the rotary shaft portion 11 on the side where the driving means 12 is provided in the rotary shaft portion 11.

2本の牽引ロープ15、16のうち、1本の牽引ロープ15の一端側は、ハンドル部14と連結され、他端側は、作業者や牽引機によって引っ張られる。   Of the two tow ropes 15 and 16, one end of one tow rope 15 is connected to the handle portion 14, and the other end is pulled by an operator or a towing machine.

もう1本の牽引ロープ16の一端側は、回転軸部11の他端と連結され、他端側は、作業者や牽引機によって引っ張られる。   One end side of the other traction rope 16 is connected to the other end of the rotating shaft portion 11, and the other end side is pulled by an operator or a traction machine.

本実施例では、土手斜面にコンクリート施工する場合について説明する。   In this embodiment, a case where concrete construction is performed on a bank slope will be described.

図1に示すように、土手斜面において、斜面下方BLから斜面上方UPへ向かって2本のレール20が間隔を空けて互いに略平行に設置される。   As shown in FIG. 1, on the bank slope, the two rails 20 are installed substantially parallel to each other at an interval from the slope lower BL toward the slope upper UP.

そして、水平方向に対して傾いて設置された2本のレール20の間にコンクリートが流し込まれる。   And concrete is poured between the two rails 20 inclined with respect to the horizontal direction.

作業者は、かき板やレーキなどで、施工面に対して大きな偏りが無いよう大まかに生コンクリートを敷き均す。   The worker roughly lays the ready-mixed concrete with a shaving board or rake so that there is no large deviation from the construction surface.

そして、レベル棒を用いてコンクリート施工のレベルを決め、2本のレール20をそのレベルに合わせる。   Then, the level of concrete construction is determined using the level bar, and the two rails 20 are adjusted to the level.

第1均し工程として、回転駆動式チューブローラ10を、2本のレール20における斜面下方側のレール上に置き、回転チューブローラ部13の両端近傍を、2本のレール20と接触させる。   As the first leveling step, the rotationally driven tube roller 10 is placed on the rail on the lower side of the inclined surface of the two rails 20, and the vicinity of both ends of the rotating tube roller unit 13 is brought into contact with the two rails 20.

そして、回転駆動式チューブローラ10を駆動させながら、2本の牽引ロープ15、16を引っ張って、回転駆動式チューブローラ10をレール20に沿って斜面下方BLから斜面上方UPへ向かってゆっくり移動させる。   Then, while driving the rotationally driven tube roller 10, the two pulling ropes 15 and 16 are pulled, and the rotationally driven tube roller 10 is slowly moved along the rail 20 from the lower slope BL to the upper slope UP. .

これにより、2本のレール間の硬化前のコンクリートUCに対して回転駆動式チューブローラ10の平滑さおよび自重が作用して、手作業で均す場合と比べて、一度に均す範囲が広くなるとともに短時間で均される。   As a result, the smoothness and the own weight of the rotationally driven tube roller 10 acts on the concrete UC before hardening between the two rails, so that the range to be leveled at a time is wider than when leveling by hand. And is leveled in a short time.

つまり、従来の手作業による荒均し工程および定規擦り工程が不要になる。   That is, the conventional manual roughening process and ruler rubbing process are unnecessary.

さらに、回転駆動式チューブローラ10の移動方向に対する回転チューブローラ部13の回転方向が、移動方向に転がるときの回転方向と逆方向であり、回転チューブローラ部13が、駆動手段12によって逆方向に回転しながらレール上をスライド移動する。   Further, the rotation direction of the rotation tube roller portion 13 relative to the movement direction of the rotation drive type tube roller 10 is opposite to the rotation direction when rolling in the movement direction, and the rotation tube roller portion 13 is reversed by the drive means 12. Slide on the rail while rotating.

これにより、余分な硬化前のコンクリートUCは、回転チューブローラ部13の回転運動によって回転駆動式チューブローラ10の移動方向上流側から下流側(前方)へかき出される。   As a result, the excess uncured concrete UC is scraped from the upstream side in the moving direction of the rotationally driven tube roller 10 to the downstream side (forward) by the rotational movement of the rotary tube roller unit 13.

その結果、凹凸が少ない硬化前のコンクリートUCの表面を容易に作成することができる。   As a result, it is possible to easily create the surface of the concrete UC before being hardened with less unevenness.

なお、斜面下方BLからコンクリートが均されていくので、斜面下方BLから斜面上方UPへ向かって均していく際、均されたコンクリートが斜面下方BLへ崩れてしまう虞がない。   In addition, since the concrete is leveled from the lower slope BL, there is no possibility that the leveled concrete collapses to the lower slope BL when leveling from the lower slope BL to the upper slope UP.

つまり、斜面上方UPから斜面下方BLへ向かって均していくと、コンクリートが自重によって斜面上方UPから斜面下方BLへ向かって移動しようとするため、均されたコンクリートが崩れてしまう虞が生じるが、斜面下方BLから斜面上方UPへ向かって均していくことで、斜面下方BLのコンクリートが斜面上方UPのコンクリートを支えるため、均されたコンクリートが斜面下方BLへ崩れることを回避できる。   In other words, when leveling from the upper slope UP to the lower slope BL, the concrete tends to move from the upper slope UP to the lower slope BL due to its own weight, so there is a risk that the leveled concrete will collapse. Since the concrete below the slope BL supports the concrete above the slope UP by leveling from the slope lower BL toward the slope upper UP, the leveled concrete can be prevented from collapsing to the slope lower BL.

次に、硬化前のコンクリートUCの表面を叩いてコンクリートに振動を加えるタンピング工程を行う。   Next, a tamping step of applying vibration to the concrete by hitting the surface of the concrete UC before curing is performed.

タンピング工程である第1タンピング工程では、振動式タンピング機30を用いる。   In the first tamping process, which is a tamping process, the vibratory tamping machine 30 is used.

振動式タンピング機30は、一例として、タンピング板部31と、振動手段32と、ハンドルバー33とを備えている。   As an example, the vibration type tamping machine 30 includes a tamping plate portion 31, a vibration unit 32, and a handle bar 33.

タンピング板部31は、横方向に長尺に設けられている。   The tamping plate portion 31 is long in the lateral direction.

タンピング板部31の横幅は、100cm〜300cm程であり、前後方向の長さは、15cm〜50cm程である。   The lateral width of the tamping plate portion 31 is about 100 cm to 300 cm, and the length in the front-rear direction is about 15 cm to 50 cm.

振動手段32は、タンピング板部31の上に設けられ、タンピング板部31と一体にタンピング板部31の面に対して垂直方向に振動するように構成されている。   The vibration means 32 is provided on the tamping plate portion 31 and configured to vibrate in a direction perpendicular to the surface of the tamping plate portion 31 integrally with the tamping plate portion 31.

振動手段32は、エンジンによる構成でもよいし、充電式バッテリーを電源とした電動モータによる構成でもよい。   The vibration means 32 may be configured by an engine, or may be configured by an electric motor using a rechargeable battery as a power source.

ハンドルバー33は、タンピング板部31と接続されている。   The handle bar 33 is connected to the tamping plate portion 31.

振動式タンピング機30が駆動しているとき、タンピング板部31は、振動によってコンクリート面から浮いた状態となるため、作業者は、1人でも容易に振動式タンピング機30を操作して移動させることができる。   When the vibration tamping machine 30 is driven, the tamping plate portion 31 is lifted from the concrete surface by vibration, so that one operator can easily operate and move the vibration tamping machine 30. be able to.

タンピング前では、図5(A)に示すように、硬化前のコンクリートUCの中のセメントC1の内部に細かなエアーARや余剰水WTがある。また、硬化前のコンクリートUCの中の骨材C2の下方に余剰水WTが溜まりやすい。さらに、比重の違いによってセメントC1や骨材C2より比重の小さい水が上方へ移動しようとして、細かい水の通り道WPが形成されている。   Before tamping, as shown in FIG. 5 (A), fine air AR and surplus water WT exist inside the cement C1 in the concrete UC before hardening. Moreover, the excess water WT tends to accumulate below the aggregate C2 in the concrete UC before hardening. Furthermore, a small water passage WP is formed as water having a specific gravity smaller than that of the cement C1 and the aggregate C2 moves upward due to the difference in specific gravity.

振動式タンピング機30によって硬化前のコンクリートUCをタンピングすることにより、図5(B)に示すように、硬化前のコンクリートUCの内部に振動が加わって内部のエアーARが表面に移動して表面から逃げてコンクリートの密度が高くなる。   By tamping the uncured concrete UC with the vibration type tamping machine 30, as shown in FIG. 5 (B), vibration is applied to the interior of the uncured concrete UC, and the internal air AR moves to the surface. Run away from the concrete and increase the density of the concrete.

さらに、硬化前のコンクリートUCの内部に振動が加わって内部の比重の大きい骨材C2が下方へ移動(沈降)するとともに比重の小さい余剰水WTが表面に移動して表面に浮いて、コンクリートの密度が高くなる。   Further, vibration is applied to the inside of the concrete UC before hardening, and the aggregate C2 having a large specific gravity moves downward (sinks), and the excess water WT having a small specific gravity moves to the surface and floats on the surface. Density increases.

つまり、余剰水WTが表面に移動して表面に浮き、充分な締固め仕上げにより、余剰水を取り除き、レイタンス等コンクリート表層の脆弱部を除去し、良質なセメントペースト層をコンクリート表層に形成することにより、コンクリートの密度が高くなる。   In other words, surplus water WT moves to the surface and floats on the surface, and with sufficient compaction finish, remove surplus water, remove weak parts of concrete surface layer such as latency, and form a good cement paste layer on concrete surface layer This increases the density of the concrete.

その結果、硬化後のコンクリートCCの強度を上げることができる。   As a result, the strength of the concrete CC after curing can be increased.

また、第1均し工程および第1タンピング工程の両工程に機械が用いられて第1均し工程で均されたコンクリートの表面が硬化前に第1タンピング工程で素早く広範囲にタンピングされて、確実にコンクリートの内部のエアーARおよび余剰水WTが逃げる。   In addition, the machine is used in both the first leveling process and the first tamping process, and the surface of the concrete leveled in the first leveling process is tamped quickly and extensively in the first tamping process before hardening. In addition, the air AR inside the concrete and the excess water WT escape.

その結果、短時間で広範囲にわたって施工した場合であっても、コンクリートの内部の細かい水の通り道WPやエアーARのたまりを無くしてクラックを発生しにくくすることができる。   As a result, even when constructed over a wide range in a short time, it is possible to eliminate the accumulation of fine water passages WP and air AR inside the concrete and make it difficult to generate cracks.

本実施例では、コンクリート施工面が傾斜している。   In this embodiment, the concrete construction surface is inclined.

第1タンピング工程において、振動式タンピング機30の移動方向が、斜面上方UPから斜面下方BLへ向かう方向である。   In the first tamping step, the moving direction of the vibratory tamping machine 30 is a direction from the upper slope UP to the lower slope BL.

これにより、硬化前のコンクリートUCの水分は斜面上方UPから下方へ向かって流れて、斜面下方BLと比べて斜面上方UPの方が早く乾く傾向があり、早く乾く側から先にタンピングが行われる。   As a result, the moisture of the concrete UC before hardening flows downward from the upper slope UP, and the upper slope UP tends to dry faster than the lower slope BL, and tamping is performed earlier from the faster drying side. .

その結果、コンクリートの硬化前にエアーARおよび余剰水WTを確実に逃がして硬化後のコンクリートCCのクラック発生を回避できる。   As a result, it is possible to reliably release the air AR and excess water WT before the concrete is hardened, and to avoid the cracking of the concrete CC after the hardening.

施工位置基準において、タンピング工程の次に、硬化待ち工程、ノロ出し工程、フレスノや刷毛引きによる最終仕上げ工程、養生工程の順で行う。   In the construction position standard, after the tamping process, the curing waiting process, the squeezing process, the final finishing process by fresno or brushing, and the curing process are performed in this order.

硬化待ち工程の後、レール20を除去するレール除去工程を行う。   After the curing waiting process, a rail removing process for removing the rail 20 is performed.

続いて、第1均し工程および第1タンピング工程を、位置をずらして行う。   Subsequently, the first leveling step and the first tamping step are performed while shifting the positions.

具体的には、図6に示すように、回転駆動式チューブローラ10の幅を考慮して、2本のレール20の外側で所定間隔を空けた領域A1、領域A2、領域A3において、第1均し工程および第1タンピング工程を順に行う。   Specifically, as shown in FIG. 6, in consideration of the width of the rotationally driven tube roller 10, the first region A1, the second region A2, and the third region A3 are spaced apart from each other by a predetermined distance outside the two rails 20. A leveling step and a first tamping step are sequentially performed.

なお、領域A1、領域A2、領域A3の順で第1均し工程を行ってから第1タンピング工程を行う場合、領域A1における傾斜上下方向の上端から中央までタンピングし、次に、領域A2における傾斜上下方向の上端から中央までタンピングし、続いて、領域A3における傾斜上下方向の上端から中央までタンピングし、その後、領域A1における傾斜上下方向の中央から下端までタンピングし、次に、領域A2における傾斜上下方向の中央から下端までタンピングし、続いて、領域A3における傾斜上下方向の中央から下端までタンピングするとよい。   In the case where the first tamping step is performed after the first leveling step in the order of the region A1, the region A2, and the region A3, the tamping is performed from the upper end to the center in the inclined vertical direction in the region A1, and then in the region A2. Tamping from the upper end to the center of the tilted vertical direction, followed by tamping from the upper end to the center of the tilted vertical direction in the region A3, and then tamping from the center to the lower end of the tilted vertical direction in the region A1, and then in the region A2 It is preferable to perform tamping from the center to the lower end in the tilted vertical direction, and then tamping from the center to the lower end in the tilted vertical direction in the region A3.

その後、領域A1、領域A2、領域A3において、コンクリートが硬化したら、領域B1、領域B2、領域B3において、第2均し工程を行い、その後、第1タンピング工程と同様に第2タンピング工程を行う。   Then, if concrete hardens | cures in area | region A1, area | region A2, and area | region A3, in area | region B1, area | region B2, and area | region B3, a 2nd tamping process will be performed similarly to a 1st tamping process after that. .

図7に示すように、第2均し工程では、第1均し工程の2本のレール20を必要とせず、2本のレール20に代えて領域A1、領域A2、領域A3の硬化後のコンクリートCCの表面の一部を用いる。   As shown in FIG. 7, in the second leveling step, the two rails 20 of the first leveling step are not required, and instead of the two rails 20, the regions A1, A2, and A3 are cured. Part of the surface of concrete CC is used.

本実施例では、第1均し工程を2本のレール20の外側で間隔を空けて複数箇所で行い、2本のレール間のコンクリートを硬化させるとともにレール20を除去するレール除去工程と、レール除去工程の後に2ヶ所の硬化コンクリート間にコンクリートを流し込んで回転駆動式チューブローラ10を2ヶ所の硬化コンクリート(CC)に沿って移動させて2ヶ所の硬化コンクリート間の硬化前のコンクリートUCを均す第2均し工程とをさらに具備する。   In the present embodiment, the first leveling step is performed at a plurality of locations at intervals on the outside of the two rails 20, and the rail removal step of hardening the concrete between the two rails and removing the rails 20; After the removal process, the concrete is poured between the two hardened concretes, and the rotationally driven tube roller 10 is moved along the two hardened concretes (CC) so that the concrete UC before hardening between the two hardened concretes is leveled. And a second leveling step.

これにより、第1均し工程で均した複数のコンクリートが硬化し、これらの硬化後のコンクリートCCの幅方向端部が第2均し工程で2本のレール20の役割を果たして、第1均し工程と同様に、手作業で均す場合と比べて、一度に均す範囲が広くなるとともに短時間で均される。   As a result, the plurality of concrete leveled in the first leveling process is cured, and the end portions in the width direction of the concrete CC after curing serve as the two rails 20 in the second leveling process. As in the case of the step, the range to be averaged at once is widened and the leveling is performed in a short time compared to the case of manual leveling.

その結果、硬化前のコンクリートUCの表面をきれいに仕上げることができる。   As a result, the surface of the concrete UC before curing can be finished cleanly.

なお、第1均し工程と同様、回転駆動式チューブローラ10を斜面下方BLから斜面上方UPへ向かって移動させながら、回転チューブローラ部13を逆回転させるとよい。   As in the first leveling step, the rotary tube roller unit 13 may be rotated in the reverse direction while moving the rotationally driven tube roller 10 from the lower slope BL to the upper slope UP.

さらに、本実施例では、第2均し工程で均した硬化前のコンクリートUCの表面を振動式タンピング機30を用いてタンピングする第2タンピング工程をさらに具備する。   Further, the present embodiment further includes a second tamping step in which the surface of the concrete UC before hardening leveled in the second leveling step is tamped using the vibration type tamping machine 30.

これにより、第1タンピング工程と同様に、領域B1、領域B2、領域B3においても、硬化前のコンクリートUCの内部に振動が加わって内部のエアーARが表面に移動して表面から逃げてコンクリートの密度が高くなる。   As a result, similarly to the first tamping step, also in the regions B1, B2, and B3, vibration is applied to the inside of the concrete UC before curing, and the internal air AR moves to the surface and escapes from the surface, so that the concrete Density increases.

さらに、硬化前のコンクリートUCの内部に振動が加わって内部の比重の大きい骨材C2が下方へ移動するとともに比重の小さい余剰水WTが表面に移動して表面に浮いて、コンクリートの密度が高くなる。   Furthermore, vibration is applied to the inside of the concrete UC before hardening, and the aggregate C2 having a large specific gravity moves downward, and the excess water WT having a small specific gravity moves to the surface and floats on the surface, thereby increasing the density of the concrete. Become.

その結果、領域B1、領域B2、領域B3においても、硬化後のコンクリートCCの強度を上げることができる。   As a result, the strength of the concrete CC after curing can be increased also in the region B1, the region B2, and the region B3.

なお、第1タンピング工程と同様、斜面上方UPから斜面下方BLに向かって振動式タンピング機30を移動させるとよい。   As in the first tamping step, the vibratory tamping machine 30 may be moved from the upper slope UP to the lower slope BL.

以上のように、土手斜面にコンクリート施工する場合について説明したが、水平面にコンクリート施工してもよい。   As mentioned above, although the case where concrete construction was carried out on the bank slope was demonstrated, you may construct concrete on a horizontal surface.

また、コンクリート施工する場所は、屋外、屋内のいずれでもよい。   Also, the concrete construction place may be outdoor or indoor.

さらに、回転チューブローラ部13の回転方向は、回転駆動式チューブローラ10の移動方向に対してレール上を転がる回転方向と逆方向としたが、転がる回転方向と同じでもよい。   Furthermore, although the rotation direction of the rotation tube roller part 13 was made into the reverse direction to the rotation direction which rolls on a rail with respect to the moving direction of the rotation drive type tube roller 10, it may be the same as the rotation direction which rolls.

回転駆動式チューブローラ10の自重によって硬化前のコンクリートUCを均すことができるからである。   It is because the concrete UC before hardening can be leveled by the dead weight of the rotationally driven tube roller 10.

<参考事項>
カラクリート(登録商標)やフェロコン(登録商標)、ベスコン(登録商標)カラー、カラーハード(登録商標)EM等のセメント系仕上げ材の表面にクラックが発生する場合がある。
<Reference matters>
Cracks may occur on the surface of cementitious finishing materials such as Caracreet (registered trademark), Ferrocon (registered trademark), Vescon (registered trademark) color, Color Hard (registered trademark) EM, and the like.

このクラックは、大別すると次の2つに分類される。
1.下地の影響ではなく、カラクリート(登録商標)やフェロコン(登録商標)等セメント系仕上げ材の表層に発生するクラック。
2.コンクリートやモルタル等、カラクリート(登録商標)等を施工する下地に入ったクラックが仕上げ材表面に表れたクラック。
This crack is roughly classified into the following two.
1. Cracks generated on the surface of cementitious finishing materials such as Caracreet (registered trademark) and Ferrocon (registered trademark), not the influence of the groundwork.
2. A crack that appears on the surface of a finished material when a concrete or mortar, such as Karakreet (registered trademark) is applied.

この2種類のクラックの入る原因について解説し、防止または減少方法を説明する。
1.「カラクリート(登録商標)、フェロコン(登録商標)の材料のみに入るクラック」の発生原
The cause of these two types of cracks will be explained, and the prevention or reduction method will be explained.
1. Origin of “cracks that can only enter materials of Caracreet (registered trademark) and ferrocon (registered trademark)”

(1)クラックの入り方は次に「(A)、(B)の2種」が挙げられる (1) Next, “2 types of (A) and (B)” can be cited as the method of cracking.

(A)亀甲状のヘアークラックが無数に入る。 (A) Turtle-shaped hair cracks are innumerable.

大きさはおおよそ一片2〜5cm程度、幅は微細で表層0.1mm程度に表れ内部には進行しない。   The size is about 2 to 5 cm on a piece, the width is fine and the surface layer appears to be about 0.1 mm, and does not progress inside.

殆ど入っている事がわからない程度のクラック幅であるが、逆光による反射や水洗いしたときの水のしみ込み(光線と水の浸潤状態)で認められる非常に細微なクラック   The crack width is such that it is almost impossible to see that it is contained, but it is a very fine crack that is recognized by reflection from backlight or water penetration when washed with water (light and water infiltration state).

(B)長さ5〜10cm、幅0.5〜1mm程度で比較的直線状に入る。 (B) It enters a relatively straight line with a length of about 5 to 10 cm and a width of about 0.5 to 1 mm.

柱周りなどで床の動きを拘束される部分ではなく、何でもない平面に突然入る   It suddenly enters an empty plane, not the part where the movement of the floor is restricted around the pillar

(2)クラックの発生原因についての考 (2) Consideration about the cause of cracks

(A)亀甲状のヘアークラックの原因
ポルトランドセメントが完全に水和反応をするために必要な最低水分量は、使用ポルトランドセメント量の25%と言われている。
(A) Causes of turtle-shaped hair cracks The minimum amount of water required for Portland cement to fully hydrate is said to be 25% of the amount of Portland cement used.

25%以上の水分は、全てセメントの反応には寄与しない余剰の水分になる。   Water of 25% or more becomes surplus water that does not contribute to the cement reaction.

このことを前提として、次に(a)、(b)が成り立つ   On the premise of this, (a) and (b) hold next

(a)セメントの水和反応による収縮(化学的収縮)
ポルトランドセメントに水を加えると水和反応を起こし硬化する。このときの水和反応は、収縮硬化である。すなわち、セメントと水との反応によって出来た生成物の容積は、反応しない前のセメントと水の合計容積よりも減少する。
(A) Shrinkage due to hydration of cement (chemical shrinkage)
When water is added to Portland cement, it causes a hydration reaction and hardens. The hydration reaction at this time is shrinkage hardening. That is, the volume of the product produced by the reaction between cement and water is smaller than the total volume of cement and water before the reaction.

このときの容積減少量は、化学的結合に要する水量(理論水量)の約25%に相当すると言われている。   The volume reduction amount at this time is said to correspond to about 25% of the amount of water required for chemical bonding (theoretical water amount).

セメントが硬化するための理論水量は、セメント量の約25%であることから、100gのセメントが、完全に水和するためには役25g(25cc)の水を必要とする。   Since the theoretical amount of water for hardening the cement is about 25% of the amount of cement, 100 g of cement requires 25 g (25 cc) of water to be fully hydrated.

この水量の25%、すなわち25×25%=6.25ccが、この反応プロセスによる容積減少となる。   25% of this amount of water, ie 25 × 25% = 6.25 cc, is the volume reduction due to this reaction process.

混練直後は「セメント+水=125」であったが、反応後は「セメント+水=118.75」になった。   Immediately after kneading, “cement + water = 125”, but after the reaction, “cement + water = 118.75”.

これは、水和反応により「水6.25」が使用され、減少していることを表している   This indicates that “water 6.25” is used and decreased due to the hydration reaction.

(b)セメントの乾燥収縮(物理的収縮)
コンクリートやモルタルを作るときにはセメントの他に砂や砂利、砕砂や砕石などの骨材を混入する。
(B) Drying shrinkage (physical shrinkage) of cement
When making concrete or mortar, sand, gravel, aggregates such as crushed sand and crushed stone are mixed in addition to cement.

骨材の表面が水で濡れるために、骨材表面に吸着される水量は、配合にも左右されるが、おおよそセメント重量の約15%になると言われている。   Since the surface of the aggregate is wetted with water, the amount of water adsorbed on the aggregate surface is said to be approximately 15% of the cement weight, although it depends on the formulation.

反応には寄与せず、ただ骨材の表面を濡らすだけの自由水(ルーズな水という)として持っている。この自由水は、乾燥した空気中で全て蒸発する。   It doesn't contribute to the reaction, it has as free water (loose water) that just wets the surface of the aggregate. All this free water evaporates in dry air.

蒸発した水の容積分だけ容積減少となる。   The volume is reduced by the volume of the evaporated water.

この水の蒸発後の空隙を埋めようとする力が収縮力となる(物理的収縮)。   The force to fill the voids after the evaporation of water becomes the contraction force (physical contraction).

すなわち、理論水量(25%)+骨材表面吸着水(15%)=約40% がコンクリートを練るための最低のW/C(水セメント比)であるが、その内の15%は蒸発してしまう水である。   That is, the theoretical water volume (25%) + aggregate surface adsorbed water (15%) = about 40% is the lowest W / C (water cement ratio) for kneading concrete, but 15% of that is evaporated. It is water that ends up.

前記(a)化学的収縮(6.25%)と(b)物理的収縮(15%)の2つの収縮が合算され、セメントにはクラックが入る。収縮量は合計量、すなわちセメントの21.25%となる。   The two shrinkages (a) chemical shrinkage (6.25%) and (b) physical shrinkage (15%) are added, and the cement is cracked. The amount of shrinkage is the total amount, ie 21.25% of the cement.

以上がカラクリート(登録商標)やフェロコン(登録商標)の表面に入る亀甲状のヘアークラックの発生メカニズムとなる。   The above is the generation mechanism of the turtle-shaped hair crack which enters the surface of Caracreet (registered trademark) or ferrocon (registered trademark).

この現象は、カラクリート(登録商標)やフェロコン(登録商標)のみに発生する現象のように考えられることがあるが、これはポルトランドセメントを使用している材料全て、例えば、普段のコンクリートやモルタル、成型品の舗道用コンクリート平板などにも当てはまる現象である。   This phenomenon may be thought of as occurring only in Caracreet (registered trademark) or ferrocon (registered trademark), but this is due to all materials using Portland cement, such as ordinary concrete and mortar. This phenomenon also applies to concrete pavement plates for molded products.

コンクリートやモルタルに発生が見えないのは、表面が粗面なため目立ちにくくなっているだけである。特に、手で押さえるコンクリート面では、発生は殆ど見えない。
防止方法
上記の21.25%の収縮は理論水量に近いため防ぐことができないが、打設直後からの保水養生を丁寧に行いセメントの水和反応が十分に行える環境を整えれば、収縮した分をセメントの反応時に生成する反応性生物(エトリンガイトなど)が埋めるため、殆ど目立たなくなる。
The only thing that can't be seen in concrete or mortar is that the surface is rough, making it less noticeable. In particular, the occurrence is hardly visible on the concrete surface pressed by hand.
Prevention method The above 21.25% shrinkage cannot be prevented because it is close to the theoretical amount of water, but it was shrunk if the water hydration treatment was carefully carried out immediately after placing and the environment for sufficient cement hydration reaction was prepared. Reactive organisms (such as ettringite) produced during the cement reaction fill up the minute, making it almost inconspicuous.

この微細クラックが原因となり、下地コンクリートに影響を与えることはない   This fine crack does not affect the underlying concrete.

(B)長さ5〜10cm、幅0.5〜1mm程度で比較的直線状に入るクラックの原因
風や日差しなどの影響で仕上げ材表面の水が急激に蒸発した場合に発生するクラックである。プラスチックひび割れと称する。
(B) Causes of cracks that enter a relatively straight line with a length of about 5 to 10 cm and a width of about 0.5 to 1 mm. These cracks occur when the water on the surface of the finishing material evaporates rapidly due to the influence of wind or sunlight. . This is called a plastic crack.

まだ十分に固くなっていない施工直後〜硬化途上の材料中の水が主に風や太陽の日差しの影響で急激に蒸発した場合、表面にクラックとして入る。   Immediately after construction, which has not been sufficiently hardened, when water in the curing material evaporates abruptly mainly due to the influence of wind or sunlight, it enters the surface as cracks.

材料の硬化収縮が大きいから入る、無収縮材だから入りにくいということではなく、材料の物性が出る前に入ってしまうクラックである。   It is a crack that enters before the physical properties of the material come out, not because it is a non-shrinkable material, because it is hard to shrink.

この現象は、無収縮材料やコンクリートやモルタルでも急激に混練水が蒸発すれば起こる。
防止方法
「風や日差し防止対策が必要である」
初期に急激に水が蒸発させないこと、乾燥させないために風や日差しを防ぐことが大切である。
This phenomenon occurs even when the kneaded water evaporates rapidly even in a non-shrinkable material, concrete or mortar.
Preventive measures “Wind and sun protection measures are required”
It is important to prevent wind and sun from preventing water from evaporating suddenly in the early stages and from drying out.

屋内では開口部を塞ぎ、ドア等からの風を目張りなどで防ぐなどの対策が重要である。   It is important to take measures such as closing the opening indoors to prevent wind from the doors and the like.

冬場は、ジェットヒーターなどの温風で入る場合がある。   In winter, it may enter with warm air such as a jet heater.

ジェットヒーターの風で床が乾燥しないよう、噴き出しの風が床に当たらないように架台の上に置いたり、口を上に向け空間を暖める工夫が必要である。   In order to prevent the floor from being dried by the wind of the jet heater, it is necessary to put it on a pedestal so that the blown air does not hit the floor or to warm the space with the mouth facing up.

屋外では積極的な風や日差し対策が取れないため、屋根壁をつけてからの打設をお勧めする。   Since it is not possible to take positive wind and sun measures outdoors, it is recommended that the roof be installed after the roof is attached.

上記(A)、(B)の2種が下地コンクリートやモルタルに影響ではなく仕上げ材のみに入るクラックである。
2.「コンクリートやモルタル等、下地のクラックが仕上げ材表面に表れたクラック」の発生原因
コンクリート等に入るクラックは配合(セメント量や水量、S/A)や配筋、建築物の構造、沈下、剥離など様々な要因の複合により発生するので一概に原因を特定することができない。
The above two types (A) and (B) are cracks that do not affect the base concrete and mortar but enter only the finishing material.
2. Causes of “cracks in which concrete and mortar cracks appear on the surface of the finish” Cracks entering concrete, etc. are mixed (cement amount, water amount, S / A), reinforcement, building structure, settlement, peeling Because it is caused by a combination of various factors, the cause cannot be specified.

代表的な事柄を抽出して原因の考察と対策を列記する   Extract representative matters and list the causes and countermeasures

(C)コンクリートの配合に起因するクラック
前述した(A)のようにコンクリートを混練するための水量は、理論水量25%と骨材吸着水量15%合わせて40%が最低水量となる(水セメント比 W/C)。
(C) Cracks due to concrete mix The amount of water for kneading concrete as described in (A) above is 40%, which is 25% theoretical water and 15% aggregate adsorbed water (water cement). Ratio W / C).

コンクリートは現場作業のポンプ圧送のしやすさや配り易さ等の施工性の目的からさらに水を追加して流動性を改良した後に打設している(水セメント比 65%が最大値)。   Concrete is placed after improving the flowability by adding water for the purpose of workability, such as ease of pumping and distribution on site, (65% water cement ratio is the maximum value).

施工性改良のために入れた分を含めた数値と最低水量40%との差が余剰の水量になる。   The difference between the numerical value including the amount added for improving workability and the minimum water amount of 40% is the excess water amount.

例えばセメント量 300kg/立方メートルの場合
避けられない理論水量25%と骨材吸着水量15%、合わせて40%を基本と考えると
最低水量は(25+15=40%) 300×0.40=120kg
最大の水セメント比を考えると 300×0.65=195kg
すなわち、195−120=75kg が余剰水量である硬化に伴って蒸発する。
For example, when the amount of cement is 300 kg / cubic meter. If the basic water volume is 25%, the aggregate adsorbed water volume is 15%, and the total water volume is 40%, the minimum water volume is (25 + 15 = 40%) 300 × 0.40 = 120kg
Considering the maximum water cement ratio, 300 × 0.65 = 195kg
That is, 195-120 = 75 kg evaporates with curing, which is the amount of excess water.

蒸発して出来た水の抜けた隙間を埋めようとする力が収縮力であり、クラックの一番の原因になる。   The force that tries to fill the gaps through which water evaporates is the contraction force, which is the primary cause of cracks.

理論水量で考えるとさらに余剰水は多くなり
理論水量は(25%) 300×0.25=75kg
最大の水セメント比を考えると 300×0.65=195kg
すなわち、195−75=120kg が余剰水量となる。
Considering the theoretical water volume, the amount of surplus water is further increased. The theoretical water volume is (25%) 300 x 0.25 = 75 kg.
Considering the maximum water cement ratio, 300 × 0.65 = 195kg
That is, 195-75 = 120 kg is the surplus water amount.

吸着水の45kg+施工性のための余剰水の(0〜75kg)の合計水量=45〜120kgが蒸発・収縮しクラックの原因となる。   The total water amount of 45 kg of adsorbed water + surplus water (0 to 75 kg) for workability = 45 to 120 kg evaporates and contracts, causing cracks.

この数値を小さくした分だけ収縮も小さくなり、クラックが入りにくくなる。
防止方
As the numerical value is reduced, shrinkage is reduced and cracks are less likely to occur.
How to prevent

(i)水セメント比(理論水量25%+吸着水15%)40%を超えた分の水量が余剰水になり、収縮の原因になるので施工に差し障りのない範囲で固練りコンクリート打設とする。 (I) Water cement ratio (theoretical water volume 25% + adsorbed water 15%) The amount of water exceeding 40% becomes surplus water and causes shrinkage. To do.

65%より60%、50%と水セメント比が少なくなれば、コンクリートの流動性が悪くなり施工性が落ちるが、収縮は小さくなりクラックの減少につながる   If the water-cement ratio decreases from 65% to 60% and 50%, the fluidity of concrete deteriorates and the workability decreases, but the shrinkage decreases and cracks are reduced.

(ii)目地を設ける(土間コンクリートの場合)
「コンクリートは必ず収縮する」との考え方から、その収縮を自由に出させるのではなく定められた場所に誘導する目的で目地を設ける。
誘発目地(カッター目地)
水が蒸発することで起こる収縮クラックは防げないので、コンクリート打設の当日、または翌日にコンクリート表面にダイヤモンドカッターなどで深さ20〜25mm程度の切れ込みを入れ、断面欠損を作りクラックをこの切れ込みに集中させるような手法を取る。
(Ii) Establish joints (for soil concrete)
Based on the idea that “concrete always shrinks”, joints are provided for the purpose of guiding the shrinkage to a specific place rather than letting it go freely.
Induction joint (cutter joint)
Shrinkage cracks caused by evaporation of water cannot be prevented, so on the day of concrete placement or the next day, cut the surface of the concrete with a diamond cutter, etc. to a depth of about 20-25mm to create a cross-sectional defect and make the crack into this cut. Take a technique to concentrate.

この切れ込みが誘発目地(カッター目地)となる。
誘発目地の作成場所
柱芯、柱間の見栄えのよい箇所でおおよそ5m間隔でカッター切断し誘発目地を作成する。
This cut becomes a trigger joint (cutter joint).
The place where the induction joint is created The cutter joint is cut at intervals of about 5 m at the pillar core and the good-looking part between the pillars, and the induction joint is created.

誘発目地の作成は打設の当日〜翌日が適当であり、何日も経過した後ではすでにコンクリートの硬化に伴う収縮とひび割れが始まっているため誘発効果が少なくなる。
伸縮目地(エキスパンションジョイント)
大きな面積では誘発目地2〜4本に1箇所の割合で伸縮目地(エキスパンションジョイント)を設ける。これによりコンクリート版の伸縮を受け止める。
スラブコンクリート
スラブコンクリートは土間コンクリートと異なり、設計上定められたコンクリート厚を連続で確保しなくてはならないので、上記に挙げたような切れ込みを入れて断面欠損させることはできない。
It is appropriate to create the induction joint from that day to the next day of the placement, and after many days, the induction effect is reduced because the shrinkage and cracking due to hardening of the concrete has already started.
Expansion joint (expansion joint)
In a large area, two to four trigger joints are provided with expansion joints (expansion joints). This catches the expansion and contraction of the concrete plate.
Slab concrete Unlike slab concrete, slab concrete must ensure the concrete thickness determined by design continuously, so it is not possible to make a cross-sectional defect by making the above-mentioned cuts.

柱や梁などの構造上で荷重などが許せれば、カッターで切断する厚み分をコンクリート打設時に厚く打ち(「ふかす」と表現する)その厚い分を切断するのであれば断面欠損作成も可能である   If loads are allowed on the structure of pillars and beams, etc., it is possible to create a cross-sectional defect if the thick part to be cut with the cutter is cast thickly (expressed as “fluff”) when the concrete is placed. Is

(iii)鉄筋量を増やす
無筋コンクリートは有筋コンクリートに、シングル筋やダブル筋にするなどの方策が有効である。
(Iii) Increasing the amount of reinforcing bars It is effective to use unreinforced concrete in the form of single reinforcement or double reinforcement for reinforced concrete.

ただし、鉄筋を入れる目的はクラック防止ではなく、コンクリートの収縮を拘束することが目的である。入ったクラックを分散させ大きく口を開けることを防ぐ目的である。   However, the purpose of inserting reinforcing bars is not to prevent cracking but to constrain the shrinkage of concrete. The purpose is to prevent cracks from entering and spreading the mouth.

固練りコンクリートや誘発目地の設置などとの組み合わせが必要である   It is necessary to combine with mixed concrete and induction joints.

(iv)真空コンクリート工法を採用
大気圧により余剰水を抜く真空コンクリート工法もひび割れ防止には有効である。
(Iv) Adopting vacuum concrete construction method Vacuum concrete construction method that drains excess water by atmospheric pressure is also effective in preventing cracks.

施工性確保のために理論水量(W/C 40%)より多く水を入れることは仕方がないが、打設直後にこの余剰水を抜いてしまう真空コンクリート工法を採用すれば固練りコンクリート打設と同じ効果が求められるので効果的である。   In order to ensure workability, it is unavoidable to add more water than the theoretical water volume (W / C 40%). It is effective because the same effect is required.

注意事項として、コンクリート表面を網下駄やスポンジスリッパで歩ける程度に締まらせてから、この工法を行っても十分な脱水は出来ず、また内部までの効果的な脱水は望めないので効果が少ない。この工法を効果的に行うのであれば打設直後の流動性のある、柔らかいコンクリートに行うことが必要である。   As a precaution, even if this method is used after tightening the concrete surface to the extent that it can be walked with mesh clogs or sponge slippers, sufficient dehydration cannot be achieved, and effective dehydration to the inside cannot be expected, so there is little effect. If this construction method is to be carried out effectively, it is necessary to use soft concrete with fluidity immediately after placement.

また、抜いた余剰水はセメントの影響で強アルカリ性(PH13程度)であるため、そのまま下水には流せない。中和した後に流すことが必要になる   Moreover, since the excess water extracted is strong alkalinity (about PH13) under the influence of cement, it cannot be poured into sewage as it is. It will be necessary to flush after neutralization

(D)コンクリートの配合を変更してクラック要因を減らす
普通コンクリートの打設ではなく以下の方法もひび割れ防止には有効である
(D) Change the concrete mix to reduce the cause of cracking The following methods are effective for preventing cracking instead of placing concrete.

(i)ファイバーコンクリートの打設
コンクリート混練用ファイバー(繊維)の種類は「スチール繊維」、「ビニロン繊維」、「ナイロン繊維」、「ガラス繊維」等があるが、現場で使用されるのは分散能力の関係からスチール繊維が多い。
(I) Placing fiber concrete There are various types of fibers for mixing concrete (steel fiber), "vinylon fiber", "nylon fiber", "glass fiber", etc. There are many steel fibers because of their ability.

スチールファイバーは鉄筋量に比べ表面積が大きく、またコンクリートに混ぜ込んだ場合には三次元ランダムにファイバーが分散しているので、鉄筋よりさらに収縮の拘束力が強いとされているのでひび割れが入りにくくなる。   Steel fiber has a larger surface area than the amount of rebar, and when mixed with concrete, the fiber is dispersed three-dimensionally randomly. Become.

ただし、スラブコンクリートは、コストがかかる、空気量が増える、流動性が低下する、などの欠点もあるので使用には注意が必要である。   However, slab concrete needs to be used with caution because it has disadvantages such as high cost, increased air volume, and decreased fluidity.

注意事項として、「エントラップエアー(混練時に巻き込んだ空気)」が増加するので、仕上げ材表面に空気ふくれが出る可能性が高くなる。ベースコンクリートの空気量をできる限り少なくして、打ち込み時にはタッピングを念入りに行う必要がある。   As a precaution, since “entrap air (air entrained during kneading)” increases, there is a high possibility that air swells on the surface of the finish. It is necessary to reduce the amount of air in the base concrete as much as possible and carefully perform tapping when driving.

また、「流動性が3〜4cm低下」するため、軟らかなベースコンクリートにファイバーを添加する傾向にある。軟らかなコンクリートでは、ブリージングが増加するため、ファイバーを沈めるためのタッピング作業などで表面にレイタンスなどの脆弱層が厚くできる。仕上げ材の剥離につながる危険性があるので、配合上のベースコンクリートは基本の15cm程度を確保する必要がある(ファイバー混入後のコンクリートの、筒先スランプではない)。   Moreover, since “the fluidity is reduced by 3 to 4 cm”, the fiber tends to be added to the soft base concrete. In soft concrete, breathing increases, so that a brittle layer such as latency can be thickened on the surface by tapping work to sink the fiber. Since there is a risk of peeling off the finishing material, it is necessary to secure a base concrete of about 15 cm as a base on blending (not concrete tube slump after fiber mixing).

ファイバー混入後の筒先のスランプを15〜18cmとすると、ベースコンクリートのスランプは20cm近くか、それ以上になる可能性が高いので、そのようなコンクリートは不可である   If the slump at the end of the tube after fiber mixing is 15 to 18 cm, the concrete concrete slump is likely to be close to 20 cm or more, so such concrete is not possible.

(ii)流動化コンクリートの打設
ひび割れ防止には、水セメント比を押さえた固練りコンクリートが有効である。
(Ii) Placing fluidized concrete To prevent cracking, solid concrete with a reduced water-cement ratio is effective.

固練りコンクリートは、打設時の施工性が悪いので敬遠される傾向にある。流動化コンクリートは薬品により、一定時間流動性を確保したコンクリートである。   Solid concrete has a tendency to be avoided because the workability at the time of placing is poor. Fluidized concrete is concrete in which fluidity is secured for a certain period of time with chemicals.

たとえば、 元のスランプ 8cm→ 流動化後のスランプ18cm
元のスランプ12cm→ 流動化後のスランプ18cm
等、ポンプ圧送に差し障りない軟らかなコンクリートになるが、30〜60分後には元のスランプに戻るコンクリートである。
For example, original slump 8cm → fluidized slump 18cm
Original slump 12cm → Slump 18cm after fluidization
It becomes a soft concrete that does not interfere with pumping, etc., but it returns to the original slump after 30 to 60 minutes.

たとえば、「元のスランプ8cm→ 流動化後のスランプ18cm」であれば、コンクリート混練時の水量はスランプ8cmの水量と同じなので固練りコンクリートとなりひび割れの少ないコンクリートが打設できる。   For example, if “original slump 8 cm → fluidized slump 18 cm”, the amount of water at the time of concrete mixing is the same as that of slump 8 cm.

カラクリート(登録商標)などの散布型仕上げ材を施工する際の注意事項として、流動性を保っているのは打設前後の30〜60分の短時間である。その時間を過ぎると元のスランプの固いコンクリートに戻るので、作業者は「固練りコンクリートを打設している」との意識を持って作業者の手配や作業段取りを組まないと施工タイミングを逸してしまう危険性がある   As a precaution when constructing a spray-type finishing material such as Caracreet (registered trademark), the fluidity is maintained for a short period of 30 to 60 minutes before and after placing. After that time, it will return to the hard concrete of the original slump, so if the worker is not aware of the fact that `` mixed concrete is placed '' and does not arrange the worker or set up the work, the construction timing will be lost. There is a risk that

(iii)膨張コンクリートの打設
膨張材を混入したコンクリートを打設する。
(Iii) Placing of expansive concrete Placing concrete mixed with expansive material.

実際は「0を無収縮と考えた場合」、プラス(+)側に膨張させるのではなくコンクリートの収縮する分を見越して「限りなく0に近くなるように膨張材を添加し補償すること」を目的とする収縮補償コンクリートである。   Actually, “When 0 is considered as no shrinkage”, instead of expanding to the plus (+) side, anticipating the amount of shrinkage of the concrete, “adding and compensating for an expansion material so that it is as close to 0 as possible” The target shrinkage compensation concrete.

水セメント比(理論水量25%+吸着水15%)40%を超えた分の水量が余剰水になり、収縮の原因になるが、その収縮する分を膨張材混入により補償する。   The amount of water exceeding the water-cement ratio (theoretical water amount 25% + adsorbed water 15%) 40% becomes surplus water and causes shrinkage, but the shrinking amount is compensated by mixing in the expanding material.

カラクリート(登録商標)などの散布型仕上げ材を施工する際の注意事項として、打設後の早期の水養生、保水養生が必要である。膨張過程では水分を必要とするので、仕上げ材を施工し表面に傷が付かなくなったら速やかに保水養生を行う。   As a precaution when constructing spray-type finishing materials such as Caracreet (registered trademark), early water curing and water retention curing after placing are necessary. Since moisture is required in the expansion process, apply a finishing material and immediately perform water retention curing when the surface is not damaged.

「セメントにはなぜ骨材を入れるのか?」について
セメントを水のみで練ったものを「セメントペースト」という。
About "Why is aggregate put in cement?" What kneaded cement only with water is called "cement paste".

セメントペーストだけでもかなりの高強度が出る。   The cement paste alone gives a very high strength.

セメントペーストは、乾燥による収縮が極めて大きいので、ペーストだけで構造物を作ると
→乾燥収縮に伴うひび割れが発生
→硬化途中で発生する反応熱により、ひび割れが発生
→そのため、水がしみ込みやすくなり、鉄筋があれば錆びる
などの不具合がでる。
Cement paste has a very large shrinkage due to drying, so if a structure is made with only the paste, → cracking occurs due to drying shrinkage → cracking occurs due to reaction heat generated during curing → so that water can easily penetrate. If there is a reinforcing bar, it will cause problems such as rusting.

骨材を入れることによって全体の収縮量を小さくし、ひび割れ発生を抑制することができる   By adding aggregate, the overall shrinkage can be reduced and cracking can be suppressed.

(A1)セメントペーストに砂を入れてモルタルとして使用 (A1) Put sand into cement paste and use as mortar

(A2)セメントペーストに砂と砂利を入れてコンクリートとして使用。 (A2) Sand and gravel are put into cement paste and used as concrete.

砂や砂利を入れると骨材分だけセメントペーストが少なくなる。また砂利の場合には骨材同士がぶつかるので収縮が抑制されるなどの利点がある。   When sand or gravel is added, cement paste is reduced by the amount of aggregate. Moreover, in the case of gravel, since aggregates collide, there exists an advantage that shrinkage | contraction is suppressed.

セメントペーストよりモルタル、モルタルよりコンクリートの収縮が小さい。   The shrinkage of concrete is smaller than that of mortar than cement paste.

「モルタルやコンクリートの概念」について
コンクリートやモルタルを混練すると
About the concept of mortar and concrete When kneading concrete and mortar

(B1)セメントが反応するために必要な水   (B1) Water required for cement to react

(B2)骨材を濡らすための水(骨材周りに吸着される水)   (B2) Water for wetting the aggregate (water adsorbed around the aggregate)

(B3)作業性に適した流動性を得るために入れる水
の3種類が必要な水になるが、その内の(B2)と(B3)が余剰な水であり、クラックの原因にもなる。
(B3) Three types of water to be added in order to obtain fluidity suitable for workability become necessary water, but (B2) and (B3) are excess water and cause cracks. .

混練直後では、セメントは骨材と密に接している。   Immediately after kneading, the cement is in intimate contact with the aggregate.

そして、混練水(B2)および(B3)が蒸発し空隙が多くなる。   And kneading | mixing water (B2) and (B3) evaporate and a space | gap increases.

その後、水が蒸発した空隙に骨材やセメントが移動して埋める。これが収縮であり、クラックの原因である。固練りすると混練水が少ない分収縮も小さい。   After that, aggregate and cement move to fill the voids where water has evaporated. This is shrinkage and causes cracks. When it is kneaded, shrinkage is small due to less kneading water.

均一に収縮すれば体積減少ですむが、様々な原因で拘束される部分ができて実際には均一ではないため、拘束部分と自由収縮部分の歪みがクラックの原因になる。   If the shrinkage is uniform, the volume can be reduced. However, since a portion restrained for various reasons is formed and not actually uniform, distortion of the restraint portion and the free shrinkage portion causes a crack.

このようにして得られた本発明の第1実施例であるコンクリート施工法は、2本のレール上において回転駆動式チューブローラ10をレール20に沿って移動させて2本のレール間の硬化前のコンクリートUCを均す第1均し工程と、第1均し工程で均した硬化前のコンクリートUCの表面を振動式タンピング機30を用いてタンピングする第1タンピング工程とを具備することにより、硬化前のコンクリートUCおよび硬化後のコンクリートCCの表面をきれいに仕上げるとともに硬化後のコンクリートCCの強度を上げることができ、短時間で広範囲にわたって施工した場合であっても、コンクリートの内部の細かい水の通り道WPやエアーARのたまりを無くしてクラックを発生しにくくすることができる。   The concrete construction method according to the first embodiment of the present invention obtained in this way is to move the rotationally driven tube roller 10 along the rail 20 on the two rails before hardening between the two rails. A first leveling step of leveling the concrete UC, and a first tamping step of tamping the surface of the concrete UC before hardening leveled in the first leveling step using the vibration type tamping machine 30; The surface of the concrete UC before hardening and the concrete CC after hardening can be finished cleanly and the strength of the concrete CC after hardening can be increased. It is possible to make it difficult for cracks to occur by eliminating the accumulation of the passage WP and the air AR.

さらに、第1均し工程の回転駆動式チューブローラ10の移動方向に対する回転方向が、移動方向に転がるときの回転方向と逆方向であり、回転駆動式チューブローラ10が、駆動手段12によって逆方向に回転しながらレール上をスライド移動することにより、凹凸が少ない硬化前のコンクリートUCの表面を容易に作成することができる。   Furthermore, the rotation direction with respect to the moving direction of the rotationally driven tube roller 10 in the first leveling step is opposite to the rotational direction when rolling in the moving direction, and the rotationally driven tube roller 10 is reversed by the driving means 12. By sliding and moving on the rail while rotating, the surface of the concrete UC before hardening with less unevenness can be easily created.

また、第1均し工程において、2本のレール20が水平方向に対して傾いて設置され、回転駆動式チューブローラ10の移動方向が、斜面下方BLから斜面上方UPへ向かう方向であることにより、硬化前のコンクリートUCの表面が斜面下方BLへ流れてしまうことを回避できる。   In the first leveling step, the two rails 20 are installed to be inclined with respect to the horizontal direction, and the moving direction of the rotationally driven tube roller 10 is a direction from the lower slope BL to the upper slope UP. The surface of the concrete UC before hardening can be prevented from flowing to the lower slope BL.

さらに、第1タンピング工程において、振動式タンピング機30の移動方向が、斜面上方UPから斜面下方BLへ向かう方向であることにより、コンクリートの硬化前にエアーARおよび余剰水WTを確実に逃がして硬化後のコンクリートCCのクラック発生を回避できる。   Further, in the first tamping step, the moving direction of the vibratory tamping machine 30 is the direction from the upper slope UP to the lower slope BL, so that the air AR and excess water WT are surely released and hardened before the concrete is hardened. The occurrence of cracks in the concrete CC later can be avoided.

また、第1均し工程を2本のレール20の外側で間隔を空けて複数箇所で行い、2本のレール間のコンクリートを硬化させるとともにレール20を除去するレール除去工程と、レール除去工程の後に2ヶ所の硬化コンクリート間にコンクリートを流し込んで回転駆動式チューブローラ10を2ヶ所の硬化コンクリートに沿って移動させて2ヶ所の硬化コンクリート間の硬化前のコンクリートUCを均す第2均し工程とをさらに具備することにより、第1均し工程と同様に、硬化前のコンクリートUCの表面をキレイに仕上げることができる。   In addition, the first leveling step is performed at a plurality of locations at intervals on the outside of the two rails 20, and a rail removing step for hardening the concrete between the two rails and removing the rail 20, and a rail removing step A second leveling process in which concrete is poured between the two hardened concretes and the rotationally driven tube roller 10 is moved along the two hardened concretes to level the uncured concrete UC between the two hardened concretes. Furthermore, the surface of the concrete UC before hardening can be finished beautifully similarly to the first leveling step.

さらに、第2均し工程で均した硬化前のコンクリートUCの表面を振動式タンピング機30を用いてタンピングする第2タンピング工程をさらに具備することにより、第1タンピング工程と同様に、硬化後のコンクリートCCの強度を上げることができるなど、その効果は甚大である。   Furthermore, by further comprising a second tamping step of tamping the surface of the concrete UC before curing leveled in the second leveling step by using the vibration type tamping machine 30, similarly to the first tamping step, The effect is enormous, such as increasing the strength of concrete CC.

続いて、本発明の第2実施例であるコンクリート施工法について、図8乃至図9(B)に基づいて説明する。   Subsequently, a concrete construction method according to a second embodiment of the present invention will be described with reference to FIGS. 8 to 9B.

ここで、図8は、本発明の第2実施例のレール20を示す斜視図であり、図9(A)は、図8の符号9−9で視たコンクリート硬化前の断面図であり、図9(B)は、図8の符号9−9で視たコンクリート硬化後の断面図である。   Here, FIG. 8 is a perspective view showing the rail 20 of the second embodiment of the present invention, and FIG. 9 (A) is a cross-sectional view before hardening the concrete as seen by reference numeral 9-9 in FIG. FIG. 9B is a cross-sectional view after the concrete is hardened, as viewed by reference numeral 9-9 in FIG.

第2実施例のコンクリート施工法は、第1実施例のコンクリート施工法の2本のレール20の内側に弾性体を設けたものであり、多くの要素について第1実施例のコンクリート施工法と共通するので、共通する事項については詳しい説明を省略する。   The concrete construction method of the second embodiment is provided with elastic bodies inside the two rails 20 of the concrete construction method of the first embodiment, and many elements are common to the concrete construction method of the first embodiment. Therefore, detailed description of common items is omitted.

図8に示すように、2本のレール20の内側には、レール延設方向に沿って弾性体の一例としてゴム部21が設けられている。   As shown in FIG. 8, a rubber portion 21 is provided inside the two rails 20 as an example of an elastic body along the rail extending direction.

図9(A)に示すように、2本のレール20の間に生コンクリートを流し込み、第1均し工程で均したとき、ゴム部21は、硬化前のコンクリートUCから力を受け、押しつぶされるようにレール幅方向に僅かに圧縮変形する。   As shown in FIG. 9 (A), when the ready-mixed concrete is poured between the two rails 20 and leveled in the first leveling step, the rubber part 21 receives a force from the concrete UC before curing and is crushed. Thus, it is slightly compressed and deformed in the rail width direction.

そして、図9(B)に示すように、2本のレール20の内側のコンクリートが硬化する際、コンクリートの内部の水分が抜けてコンクリートがレール幅方向に僅かに収縮する。   Then, as shown in FIG. 9B, when the concrete inside the two rails 20 is hardened, moisture inside the concrete is lost and the concrete is slightly contracted in the rail width direction.

この際、ゴム部21は元の形状に戻ろうとして、コンクリートの幅方向両端で2本のレール20の外側に引っ張られる力が弾性体で緩和される。   At this time, the rubber part 21 tries to return to the original shape, and the force pulled to the outside of the two rails 20 at both ends in the width direction of the concrete is relaxed by the elastic body.

その結果、2本のレール20を設置したことで発生する外側に引っ張られる力に起因するクラック発生を回避できる。   As a result, it is possible to avoid the occurrence of cracks due to the outward pulling force generated by installing the two rails 20.

なお、本実施例のレール20は、断面四角形のパイプであるが、前述した実施例と同じ断面円形のパイプでもよい。   The rail 20 of the present embodiment is a pipe having a square cross section, but may be a pipe having the same cross section as that of the above-described embodiment.

このようにして得られた本発明の第2実施例であるコンクリート施工法は、2本のレール20の内側には、レール延設方向に沿って弾性体としてのゴム部21が設けられていることにより、2本のレール20を設置したことでコンクリートが硬化する際の水和反応および余剰水の除去乾燥などによって収縮するときに発生する外側に引っ張られる力に起因するクラック発生を回避できるなど、その効果は甚大である。   In the concrete construction method according to the second embodiment of the present invention thus obtained, a rubber portion 21 as an elastic body is provided inside the two rails 20 along the rail extending direction. By installing the two rails 20, it is possible to avoid the occurrence of cracks due to the outward pulling force generated when shrinking due to the hydration reaction when the concrete hardens and the removal and drying of excess water, etc. The effect is enormous.

10 ・・・ 回転駆動式チューブローラ
11 ・・・ 回転軸部
12 ・・・ 駆動手段
13 ・・・ 回転チューブローラ部
14 ・・・ ハンドル部
15 ・・・ 牽引ロープ
16 ・・・ 牽引ロープ
20 ・・・ レール
21 ・・・ ゴム部(弾性体)
30 ・・・ 振動式タンピング機
31 ・・・ タンピング板部
32 ・・・ 振動手段
33 ・・・ ハンドルバー
UC ・・・ (硬化前の)コンクリート
CC ・・・ (硬化後の)コンクリート
BL ・・・ 斜面下方
UP ・・・ 斜面上方
C1 ・・・ セメント
C2 ・・・ 骨材
WT ・・・ 余剰水
WP ・・・ 細かい水の通り道
AR ・・・ エアー
DESCRIPTION OF SYMBOLS 10 ... Rotation drive type tube roller 11 ... Rotation shaft part 12 ... Drive means 13 ... Rotation tube roller part 14 ... Handle part 15 ... Tow rope 16 ... Tow rope 20 .. Rail 21 ... Rubber part (elastic body)
30 ... Vibration type tamping machine 31 ... Tamping plate part 32 ... Vibration means 33 ... Handle bar UC ... Concrete CC (before hardening) ... Concrete BL (after hardening)・ Lower slope UP ... Upper slope C1 ... Cement C2 ... Aggregate WT ... Excess water WP ... Fine water passage AR ... Air

Claims (7)

硬化前のコンクリートを流し込んで均してから硬化させるコンクリート施工法において、
2本のレール上において回転駆動式チューブローラをレールに沿って移動させて2本のレール間の硬化前のコンクリートを均す第1均し工程と、
前記第1均し工程で均した硬化前のコンクリートの表面を振動式タンピング機を用いてタンピングする第1タンピング工程とを具備し、
2本のレールの間の領域の全面に対して前記第1均し工程を行ってから前記第1タンピング工程を行い、
前記第1タンピング工程は、前記振動式タンピング機のタンピング板部の面に対して垂直方向に振動することで行うことを特徴とするコンクリート施工法。
In the concrete construction method in which the concrete before hardening is poured, leveled and hardened,
A first leveling step of leveling the uncured concrete between the two rails by moving a rotationally driven tube roller along the rails on the two rails;
A first tamping step of tamping the surface of the concrete before hardening leveled in the first leveling step using a vibration tamping machine,
Performing the first tamping step after performing the first leveling step on the entire surface of the region between the two rails;
The first tamping step is performed by vibrating in a direction perpendicular to a surface of a tamping plate portion of the vibration type tamping machine.
前記第1均し工程の回転駆動式チューブローラの移動方向に対する回転方向が、移動方向に転がるときの回転方向と逆方向であり、
前記回転駆動式チューブローラが、駆動手段によって逆方向に回転しながらレール上をスライド移動することを特徴とする請求項1に記載のコンクリート施工法。
The rotation direction with respect to the moving direction of the rotationally driven tube roller in the first leveling step is opposite to the rotating direction when rolling in the moving direction,
2. The concrete construction method according to claim 1, wherein the rotationally driven tube roller slides on the rail while being rotated in the reverse direction by the driving means.
前記第1均し工程において、前記2本のレールが水平方向に対して傾いて設置され、
前記回転駆動式チューブローラの移動方向が、斜面下方から斜面上方へ向かう方向であることを特徴とする請求項1または請求項2に記載のコンクリート施工法。
In the first leveling step, the two rails are installed inclined with respect to the horizontal direction,
The concrete construction method according to claim 1 or 2, wherein a moving direction of the rotationally driven tube roller is a direction from a lower slope to an upper slope.
前記第1タンピング工程において、前記振動式タンピング機の移動方向が、前記斜面上方から斜面下方へ向かう方向であることを特徴とする請求項3に記載のコンクリート施工法。   The concrete construction method according to claim 3, wherein in the first tamping step, the moving direction of the vibratory tamping machine is a direction from the upper side of the slope toward the lower side of the slope. 前記2本のレールの内側には、レール延設方向に沿って弾性体が設けられていることを特徴とする請求項1乃至請求項4のいずれか1つに記載のコンクリート施工法。   The concrete construction method according to any one of claims 1 to 4, wherein an elastic body is provided inside the two rails along a rail extending direction. 前記第1均し工程を2本のレールの外側で間隔を空けて複数箇所で行い、前記2本のレール間のコンクリートを硬化させるとともにレールを除去するレール除去工程と、
前記レール除去工程の後に2ヶ所の硬化コンクリート間にコンクリートを流し込んで回転駆動式チューブローラを2ヶ所の硬化コンクリートに沿って移動させて2ヶ所の硬化コンクリート間の硬化前のコンクリートを均す第2均し工程とをさらに具備することを特徴とする請求項1乃至請求項5のいずれか1つに記載のコンクリート施工法。
The first leveling step is performed at a plurality of locations at intervals on the outside of the two rails, the rail removal step of hardening the concrete between the two rails and removing the rails;
After the rail removal step, the concrete is poured between the two hardened concretes, and the rotationally driven tube roller is moved along the two hardened concretes to level the unhardened concrete between the two hardened concretes. 6. The concrete construction method according to any one of claims 1 to 5, further comprising a leveling step.
前記第2均し工程で均した硬化前のコンクリートの表面を振動式タンピング機を用いてタンピングする第2タンピング工程をさらに具備することを特徴とする請求項6に記載のコンクリート施工法。   The concrete construction method according to claim 6, further comprising a second tamping step of tamping the surface of the concrete before hardening leveled in the second leveling step using a vibration tamping machine.
JP2018034325A 2018-02-28 2018-02-28 Concrete construction method Active JP6437150B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2018034325A JP6437150B2 (en) 2018-02-28 2018-02-28 Concrete construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018034325A JP6437150B2 (en) 2018-02-28 2018-02-28 Concrete construction method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2017152152A Division JP6301539B1 (en) 2017-08-07 2017-08-07 Concrete construction method

Publications (2)

Publication Number Publication Date
JP2018150792A true JP2018150792A (en) 2018-09-27
JP6437150B2 JP6437150B2 (en) 2018-12-12

Family

ID=63680218

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018034325A Active JP6437150B2 (en) 2018-02-28 2018-02-28 Concrete construction method

Country Status (1)

Country Link
JP (1) JP6437150B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610786A (en) * 2018-11-20 2019-04-12 陈爱兰 A kind of interior wall leveling unit for construction and decoration
KR20210111526A (en) * 2020-03-03 2021-09-13 홍익대학교세종캠퍼스산학협력단 Decoration concrete paving method
JP2022024180A (en) * 2020-03-27 2022-02-08 株式会社フロアエージェント Method of constructing concrete floor surface
CN114704051A (en) * 2022-04-14 2022-07-05 江苏迅霆建设工程有限公司 Plastering device for wall
KR102438099B1 (en) * 2022-02-15 2022-08-30 트리폴건설(주) Concrete gradient forming apparatus and method for constructing embedded rail track using the same
CN117988532A (en) * 2024-04-07 2024-05-07 山西省建筑科学研究院集团有限公司 Repairing and heat-insulating mortar smearing device for building wall heat-insulating system

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6393962A (en) * 1986-10-09 1988-04-25 フリ−工業株式会社 Method for casting concrete
JPH0620761U (en) * 1992-03-16 1994-03-18 大和ハウス工業株式会社 Concrete pouring rail support structure
JPH06173453A (en) * 1992-12-07 1994-06-21 Akira Muroboshi Floor direct finish method after placing of concrete
JP3010300U (en) * 1994-10-18 1995-04-25 大和ハウス工業株式会社 Concrete pouring rail support structure
JP2004204472A (en) * 2002-12-24 2004-07-22 Hatano Co Ltd Box drawing form
JP2006257808A (en) * 2005-03-18 2006-09-28 Nippo Corporation:Kk Method and apparatus for moving paving machine in concrete paving

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6393962A (en) * 1986-10-09 1988-04-25 フリ−工業株式会社 Method for casting concrete
JPH0620761U (en) * 1992-03-16 1994-03-18 大和ハウス工業株式会社 Concrete pouring rail support structure
JPH06173453A (en) * 1992-12-07 1994-06-21 Akira Muroboshi Floor direct finish method after placing of concrete
JP3010300U (en) * 1994-10-18 1995-04-25 大和ハウス工業株式会社 Concrete pouring rail support structure
JP2004204472A (en) * 2002-12-24 2004-07-22 Hatano Co Ltd Box drawing form
JP2006257808A (en) * 2005-03-18 2006-09-28 Nippo Corporation:Kk Method and apparatus for moving paving machine in concrete paving

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109610786A (en) * 2018-11-20 2019-04-12 陈爱兰 A kind of interior wall leveling unit for construction and decoration
KR20210111526A (en) * 2020-03-03 2021-09-13 홍익대학교세종캠퍼스산학협력단 Decoration concrete paving method
KR102421703B1 (en) * 2020-03-03 2022-07-18 홍익대학교세종캠퍼스산학협력단 Decoration concrete paving method
JP2022024180A (en) * 2020-03-27 2022-02-08 株式会社フロアエージェント Method of constructing concrete floor surface
JP7072955B2 (en) 2020-03-27 2022-05-23 株式会社フロアエージェント Construction method of concrete floor
WO2022210682A1 (en) * 2020-03-27 2022-10-06 株式会社フロアエージェント Method for constructing concrete floor
KR102438099B1 (en) * 2022-02-15 2022-08-30 트리폴건설(주) Concrete gradient forming apparatus and method for constructing embedded rail track using the same
CN114704051A (en) * 2022-04-14 2022-07-05 江苏迅霆建设工程有限公司 Plastering device for wall
CN114704051B (en) * 2022-04-14 2023-02-03 江苏迅霆建设工程有限公司 Plastering device for wall
CN117988532A (en) * 2024-04-07 2024-05-07 山西省建筑科学研究院集团有限公司 Repairing and heat-insulating mortar smearing device for building wall heat-insulating system
CN117988532B (en) * 2024-04-07 2024-06-04 山西省建筑科学研究院集团有限公司 Repairing and heat-insulating mortar smearing device for building wall heat-insulating system

Also Published As

Publication number Publication date
JP6437150B2 (en) 2018-12-12

Similar Documents

Publication Publication Date Title
JP6437150B2 (en) Concrete construction method
JP5850698B2 (en) Floor slab reinforcement method
JP6301539B1 (en) Concrete construction method
JPH11302061A (en) Concrete for placing joint and method for placing joint using the concrete for placing joint
CN105951842A (en) Raft lower reversed beam polystyrene board caul construction method
JP6051497B1 (en) Inorganic material construction method
JP6191936B1 (en) Concrete construction method
GB2282593A (en) Water permeable concrete constructions
JP5974346B1 (en) Inorganic material construction method
CN111042310A (en) Basement bottom plate structure and construction method thereof
Lomboy et al. Semi-flowable self-consolidating concrete and its application
CN115324349A (en) Construction method for mass concrete of linear accelerator
KR20170026091A (en) Constructing method of connecting type retaining wall using high performance shotcrete composition
JP2016199904A (en) Construction method for floor slab structure
Singh et al. Concrete in Residential Construction
JP7142869B1 (en) Inorganic material construction method
JP7142868B1 (en) Inorganic material construction method
CN108532985A (en) Foundation beam board construction method
JP7455680B2 (en) Method of constructing structures made of earth-based materials
CN114541337B (en) Method for repairing damage of abrasion section of debris flow drainage groove
Surahyo et al. Poor Construction Methods
Specifications Standards
Mantawy OPTIMIZATION OF ADVANCED CEMENTITIOUS MATERIAL OVERLAYS AND UPGRADES, INCLUDING SHOTCRETE
CA1135572A (en) Surface finishes for rigid structures
JP2004346644A (en) Concrete laying construction method for slope face

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20180717

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20180919

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20181009

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20181109

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20181113

R150 Certificate of patent or registration of utility model

Ref document number: 6437150

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250