JP2018123633A - Joint pile type pier, and method for constructing joint pile type pier - Google Patents

Joint pile type pier, and method for constructing joint pile type pier Download PDF

Info

Publication number
JP2018123633A
JP2018123633A JP2017018546A JP2017018546A JP2018123633A JP 2018123633 A JP2018123633 A JP 2018123633A JP 2017018546 A JP2017018546 A JP 2017018546A JP 2017018546 A JP2017018546 A JP 2017018546A JP 2018123633 A JP2018123633 A JP 2018123633A
Authority
JP
Japan
Prior art keywords
pile
steel pipe
joint
piles
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2017018546A
Other languages
Japanese (ja)
Inventor
勝哉 池野
Katsuya Ikeno
勝哉 池野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Penta Ocean Construction Co Ltd
Original Assignee
Penta Ocean Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Penta Ocean Construction Co Ltd filed Critical Penta Ocean Construction Co Ltd
Priority to JP2017018546A priority Critical patent/JP2018123633A/en
Publication of JP2018123633A publication Critical patent/JP2018123633A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

PROBLEM TO BE SOLVED: To achieve a pile type pier having high workability with low cost.SOLUTION: A joint pile type pier 1 comprises: a plurality of joint piles 100 having steel pipe piles 110 protruding onto a seabed G and concrete piles 130 joined to the steel pipe piles 110 as upper piles of the steel pipe piles 110; a superstructure 200 supported by the plurality of joint piles 100; and steel pipes 210 which are provided so as to protrude from the bottom surface side of the superstructure 200 and which cover the heads of the joint piles 100. A method for constructing the joint pile type pier 1 comprises driving the plurality of steel pipe piles 110 into the seabed G, forming the plurality of joint piles 100 by joining the concrete piles 130 to each of the plurality of steel pipe piles 110 as upper piles, and installing the superstructure 200 supported by the plurality of joint piles 100.SELECTED DRAWING: Figure 1

Description

本発明は、杭式桟橋および杭式桟橋の施工方法に関する。   The present invention relates to a pile-type pier and a method for constructing the pile-type pier.

特許文献1には、鋼管杭の上部に鋼管杭よりも曲げ耐力が大きいSC杭を接合した基礎杭構造が記載されている。この基礎杭構造によれば、地震等における建物からの水平力、および地中部での地盤変位により発生する大きな荷重に対して、耐力が不足することを抑制することができる。   Patent Document 1 describes a foundation pile structure in which an SC pile having a bending strength greater than that of a steel pipe pile is bonded to the upper portion of the steel pipe pile. According to this foundation pile structure, it is possible to suppress a lack of proof strength against a large load generated by a horizontal force from a building in an earthquake or the like and a ground displacement in the underground.

特開2010−242498号公報JP 2010-242498 A

従来の杭式桟橋は、図20に示すように、海底地盤Gに根入された複数の鋼管杭400と、これら複数の鋼管杭400により支持され、海面Sよりも上方に位置する上部工500とを備える。鋼管杭は、PHC杭等のコンクリート杭と比較して、海底地盤Gにハンマー打撃により杭を貫入することができるため、施工性の観点から優れている。その一方で、鋼管杭は一般的にコンクリート杭に比べて高価である。また、鋼管杭は海水に対する防食が必要であるため、一般的にメインテナンス費用もコンクリート杭と比較し高額となる。   As shown in FIG. 20, the conventional pile-type pier has a plurality of steel pipe piles 400 embedded in the seabed ground G, and a superstructure 500 supported by the plurality of steel pipe piles 400 and positioned above the sea level S. With. Compared with concrete piles such as PHC piles, steel pipe piles are superior in terms of workability because they can penetrate the seabed ground G by hammering. On the other hand, steel pipe piles are generally more expensive than concrete piles. In addition, since steel pipe piles must be protected against seawater, maintenance costs are generally higher than concrete piles.

本発明は、上述した背景の下になされたものであり、施工性の高い杭式桟橋を低コストで実現するための手段を提供する。   The present invention has been made under the above-described background, and provides means for realizing a pile-type jetty with high workability at low cost.

本発明は、海底地盤上に突出した鋼管杭と、前記鋼管杭の上杭として前記鋼管杭に接合されたコンクリート杭とを有する複数の継杭と、前記複数の継杭に支持される上部工とを備える継杭式桟橋を第1の態様として提案する。   The present invention provides a steel pipe pile protruding on the seabed ground, a plurality of joint piles having a concrete pile joined to the steel pipe pile as an upper pile of the steel pipe pile, and an upper structure supported by the plurality of joint piles. A joint-type pier provided with the above is proposed as a first aspect.

本発明の第1の態様にかかる継杭式桟橋の施工において、海底地盤に対する鋼管杭の貫入はハンマー打撃により行うことができる。また、杭の全てに鋼管杭が用いられる杭式桟橋と比較し、本発明の第1の態様にかかる継杭式桟橋は杭の材料費が安価である上に、海水に対する防食を要する部分が杭のごく一部に限定されるため、メインテナンス費用も低額で済む。   In the construction of the joint pile pier according to the first aspect of the present invention, penetration of the steel pipe pile into the seabed ground can be performed by hammering. In addition, compared to a pile-type pier in which steel pipe piles are used for all of the piles, the joint pile-type pier according to the first aspect of the present invention has a low material cost for the piles and has a portion that requires corrosion protection against seawater. Because it is limited to a small part of the pile, maintenance costs are low.

本発明の第1の態様において、前記継杭の頭部を覆う鋼管を備える、という構成が第2の態様として採用されてもよい。   1st aspect of this invention WHEREIN: The structure of providing the steel pipe which covers the head of the said joint pile may be employ | adopted as a 2nd aspect.

本発明の第2の態様によれば、杭において水平荷重による曲げモーメントが最も大きい杭頭部が鋼管により覆われるため、必要な強度を確保するために要する上杭(コンクリート杭)のスペックを低減できる。   According to the 2nd aspect of this invention, since the pile head with the largest bending moment by a horizontal load in a pile is covered with a steel pipe, the specification of the upper pile (concrete pile) required in order to ensure required intensity | strength is reduced. it can.

本発明の第1の態様において、前記コンクリート杭の頭部は拡径されている、という構成が第3の態様として採用されてもよい。   1st aspect of this invention WHEREIN: The structure that the diameter of the head of the said concrete pile is expanded may be employ | adopted as a 3rd aspect.

本発明の第3の態様によれば、杭において水平荷重による曲げモーメントが最も大きい杭頭部の曲げ耐性が拡径により確保される。従って、上杭に拡径されないコンクリート杭が用いられる場合と比較し、必要な強度を確保するために要する上杭(杭頭部以外の部分)の杭径が小さくなる。   According to the 3rd aspect of this invention, the bending tolerance of the pile head with the largest bending moment by a horizontal load in a pile is ensured by diameter expansion. Therefore, compared with the case where the concrete pile which is not expanded to an upper pile is used, the pile diameter of the upper pile (part other than a pile head) required in order to ensure required intensity | strength becomes small.

本発明の第1乃至第3のいずれかの態様において、前記鋼管杭の頭部における内径は前記コンクリート杭の前記鋼管杭に接合される部分の外径よりも大きく、前記鋼管杭の中に前記コンクリート杭の一部が挿入されている、という構成が第4の態様として採用されてもよい。   In any one of the first to third aspects of the present invention, the inner diameter of the head portion of the steel pipe pile is larger than the outer diameter of the portion to be joined to the steel pipe pile of the concrete pile, The structure that a part of concrete pile is inserted may be employ | adopted as a 4th aspect.

本発明の第4の態様によれば、海底地盤に貫入された鋼管杭の頭部の内側に上杭(コンクリート杭)の下端部を差し込むことでそれらの杭の接合が行われ、施工が容易である。   According to the 4th aspect of this invention, those piles are joined by inserting the lower end part of an upper pile (concrete pile) inside the head of the steel pipe pile penetrated into the seabed ground, and construction is easy. It is.

本発明の第4の態様において、前記鋼管杭と前記鋼管杭に挿入されている前記コンクリート杭の一部は水中グラウト充填により接合されている、という構成が第5の態様として採用されてもよい。   4th aspect of this invention WHEREIN: The structure that a part of said concrete pile inserted in the said steel pipe pile and the said steel pipe pile is joined by underwater grout filling may be employ | adopted as a 5th aspect. .

本発明の第5の態様によれば、鋼管杭とその上杭であるコンクリート杭の接合が容易に実現される。   According to the 5th aspect of this invention, joining of the steel pipe pile and the concrete pile which is an upper pile is implement | achieved easily.

本発明の第1乃至第3のいずれかの態様において、前記鋼管杭と前記コンクリート杭は継手を用いて接合されている、という構成が第6の態様として採用されてもよい。   In any one of the first to third aspects of the present invention, a configuration in which the steel pipe pile and the concrete pile are joined using a joint may be adopted as a sixth aspect.

本発明の第6の態様によれば、鋼管杭とその上杭であるコンクリート杭を溶接しなくとも接合することができる。   According to the sixth aspect of the present invention, the steel pipe pile and the concrete pile which is the upper pile can be joined without welding.

また、本発明は、海底地盤に複数の鋼管杭を打ち込む工程と、前記複数の鋼管杭の各々に上杭としてコンクリート杭を接合する工程と、前記コンクリート杭を接合する工程によって形成された複数の継杭に支持される上部工を設置する工程とを備える継杭式桟橋の施工方法を第7の態様として提案する。   Further, the present invention includes a plurality of steps formed by a step of driving a plurality of steel pipe piles into the seabed ground, a step of joining concrete piles as upper piles to each of the plurality of steel pipe piles, and a step of joining the concrete piles. The construction method of a joint pile type pier provided with the process of installing the superstructure supported by a joint pile is proposed as a 7th aspect.

本発明の第7の態様によれば、本発明の第1の態様にかかる継杭式桟橋が実現される。   According to the seventh aspect of the present invention, the joint pile jetty according to the first aspect of the present invention is realized.

本発明の第7の態様において、前記上部工を設置する工程は、前記継杭の上にプレキャストコンクリートの梁部を設置する工程を含む、という構成が第8の態様として採用されてもよい。   In the seventh aspect of the present invention, a configuration in which the step of installing the superstructure includes a step of installing a beam portion of precast concrete on the joint pile may be adopted as an eighth aspect.

本発明の第8の態様によれば、継杭の上にコンクリートの現場打ちにより上部工の梁部を設置する場合と比較し、施工が容易である。   According to the 8th aspect of this invention, construction is easy compared with the case where the beam part of the superstructure is installed on the joint pile by the spot casting of concrete.

本発明によれば、施工性の高い杭式桟橋が低コストで実現される。   According to the present invention, a pile-type pier having high workability is realized at low cost.

第1実施形態にかかる継杭式桟橋を水平方向に見た模式図。The schematic diagram which looked at the joint pile type pier concerning 1st Embodiment in the horizontal direction. 第1実施形態にかかる継杭式桟橋の施工方法を示すフローチャート。The flowchart which shows the construction method of the joint pile type pier concerning 1st Embodiment. 第1実施形態にかかる打ち込み工程を説明する図。The figure explaining the drive-in process concerning a 1st embodiment. 第1実施形態にかかる打ち込み工程を説明する図。The figure explaining the drive-in process concerning a 1st embodiment. 第1実施形態にかかる鋼管杭を上から見た図。The figure which looked at the steel pipe pile concerning a 1st embodiment from the top. 第1実施形態にかかる接合工程を説明する図。The figure explaining the joining process concerning a 1st embodiment. 第1実施形態にかかる鋼管杭およびコンクリート杭を上から見た図。The figure which looked at the steel pipe pile and concrete pile concerning 1st Embodiment from the top. 第1実施形態にかかる鋼管杭とコンクリート杭の接合部を示した図。The figure which showed the junction part of the steel pipe pile and concrete pile concerning 1st Embodiment. 第1実施形態にかかる設置工程を説明する図。The figure explaining the installation process concerning 1st Embodiment. 第1実施形態にかかる設置工程を説明する図。The figure explaining the installation process concerning 1st Embodiment. 第1実施形態にかかる設置工程を説明する図。The figure explaining the installation process concerning 1st Embodiment. 第2実施形態にかかる継杭式桟橋を水平方向に見た模式図。The schematic diagram which looked at the joint pile type jetty concerning 2nd Embodiment in the horizontal direction. 第2実施形態にかかる設置工程を説明する図。The figure explaining the installation process concerning 2nd Embodiment. 第2実施形態にかかる設置工程を説明する図。The figure explaining the installation process concerning 2nd Embodiment. 第2実施形態にかかる設置工程を説明する図。The figure explaining the installation process concerning 2nd Embodiment. 第2実施形態にかかる設置工程を説明する図。The figure explaining the installation process concerning 2nd Embodiment. 一変形例にかかる鋼管杭およびコンクリート杭の接合部付近を正面から見た図。The figure which looked at the junction part vicinity of the steel pipe pile and concrete pile concerning one modification from the front. 一変形例にかかる鋼管杭およびコンクリート杭を上から見た図。The figure which looked at the steel pipe pile and concrete pile concerning one modification from the top. 一変形例にかかる鋼管杭とコンクリート杭の接合部を示した図。The figure which showed the junction part of the steel pipe pile and concrete pile concerning one modification. 従来の杭式桟橋を水平方向に見た模式図。Schematic view of a conventional pile-type pier viewed horizontally.

以下、図面を参照して本発明の実施形態を説明する。   Hereinafter, embodiments of the present invention will be described with reference to the drawings.

[第1実施形態]
図1は、本実施形態にかかる継杭式桟橋1を水平方向に見た模式図である。継杭式桟橋1は、杭基礎を構成する複数の継杭100と、複数の継杭100に支持される上部工200とを備える。
[First Embodiment]
Drawing 1 is a mimetic diagram which looked at the joint pile type pier 1 concerning this embodiment in the horizontal direction. The joint pile pier 1 includes a plurality of joint piles 100 constituting a pile foundation and an upper work 200 supported by the plurality of joint piles 100.

複数の継杭100は各々、鋼管杭110とコンクリート杭130を備える。鋼管杭110は、杭頭部が海底地盤G上に突出しており、杭頭部以外の部分は海底地盤Gに貫入されている。図1の例では、継杭100は全て、杭軸方向が鉛直方向に沿うように設置されているが、継杭100の少なくとも一部が、それらの杭軸方向が鉛直方向に対し傾いた方向となるように設置されていてもよい。   Each of the plurality of joint piles 100 includes a steel pipe pile 110 and a concrete pile 130. As for the steel pipe pile 110, the pile head protrudes on the seabed ground G, and parts other than a pile head are penetrated into the seabed ground G. In the example of FIG. 1, all the joint piles 100 are installed such that the pile axial direction is along the vertical direction, but at least a part of the joint piles 100 is a direction in which the pile axial direction is inclined with respect to the vertical direction. It may be installed so that.

鋼管杭110は、例えば、JIS A5525に記載の規格に従っている。コンクリート杭130は、鋼管杭110の上杭として鋼管杭110に接合されている。コンクリート杭130は、例えばPHC坑であるが、PRC杭、ST杭、SC杭その他のコンクリート杭であってもよい。コンクリート杭130は、例えば、JIS A5373に記載の規格に従っている。   The steel pipe pile 110 conforms to the standard described in JIS A5525, for example. The concrete pile 130 is joined to the steel pipe pile 110 as an upper pile of the steel pipe pile 110. The concrete pile 130 is, for example, a PHC mine, but may be a PRC pile, an ST pile, an SC pile, or other concrete piles. The concrete pile 130 conforms to a standard described in JIS A5373, for example.

上部工200は、複数の継杭100の上に設置されている。上部工200は、海面Sよりも上に位置する。上部工200は、梁部220と、梁部220の底面側に突出するように設けられた複数の鋼管210と、梁部220の上に配置された床版230を備える。複数の鋼管210は各々、鞘管として複数の継杭100のいずれかの頭部に被せられる。   The superstructure 200 is installed on the plurality of joint piles 100. The superstructure 200 is located above the sea level S. The superstructure 200 includes a beam portion 220, a plurality of steel pipes 210 provided so as to protrude to the bottom surface side of the beam portion 220, and a floor slab 230 disposed on the beam portion 220. Each of the plurality of steel pipes 210 is put on one of the heads of the plurality of joints 100 as a sheath pipe.

次に、継杭式桟橋1の施工方法を説明する。図2は、継杭式桟橋1の施工方法を示すフローチャートである。継杭式桟橋1の施工方法は、打ち込み工程と、接合工程と、設置工程の3つに大別される。   Next, the construction method of the joint pile type pier 1 is demonstrated. FIG. 2 is a flowchart showing a construction method of the joint pile type pier 1. The construction method of the joint pile pier 1 is roughly divided into a driving process, a joining process, and an installation process.

<打ち込み工程>
打ち込み工程は、複数の鋼管杭110を海底地盤Gに打ち込む工程である。図3は、打ち込み工程を説明する図である。図3には、左から順に、建て込み済み、打ち込み中、打ち込み済みの3つの状態の鋼管杭110が示されている。
<Punching process>
The driving process is a process of driving a plurality of steel pipe piles 110 into the seabed ground G. FIG. 3 is a diagram for explaining the driving process. FIG. 3 shows the steel pipe piles 110 in three states that have been built, driven, and driven in order from the left.

打ち込み工程においては、まず、クレーン(図示略)により鋼管杭110を海中に吊り込み、下端が海底地盤Gの所定位置の上に接するように鋼管杭110を設置(建て込み)する(図3の左側の図)。続いて、建て込み済みの鋼管杭110の頭部の上にヤットコ300を設置し、ヤットコ300の頭部を杭打機(図示略)で下方に打撃する。ヤットコ300を介した杭打機の打撃力により、鋼管杭110は海底地盤G内へと打ち込まれる(図3の中央の図)。鋼管杭110の杭頭位置が設計された所定の高さに達すると、杭打機による打撃が終了され、ヤットコ300を鋼管杭110の上から取り除かれ、打ち込み工程が完了する(図3の右側の図)。なお、図示は省略するが、鋼管杭を打ち込む際には導材(定規材)を設置することが一般的である。   In the driving step, first, the steel pipe pile 110 is suspended in the sea by a crane (not shown), and the steel pipe pile 110 is installed (built) so that the lower end is in contact with a predetermined position of the seabed ground G (FIG. 3). (Figure on the left). Subsequently, the Yatco 300 is installed on the head of the steel pipe pile 110 that has been built, and the head of the Yatco 300 is hit downward with a pile driver (not shown). The steel pipe pile 110 is driven into the seabed ground G by the striking force of the pile driving machine through the Yatco 300 (the middle diagram in FIG. 3). When the pile head position of the steel pipe pile 110 reaches a designed height, the hitting by the pile driving machine is terminated, the Yatco 300 is removed from the steel pipe pile 110, and the driving process is completed (right side of FIG. 3). Figure). In addition, although illustration is abbreviate | omitted, when driving a steel pipe pile, it is common to install a conducting material (ruler material).

上記の打ち込み工程は、複数の鋼管杭110の各々に関し行われる。その結果、図4に示すように、大部分が海底地盤G内に貫入された高さの揃った複数の鋼管杭110の杭頭が海底地盤Gから上に突出した状態となる。   The above driving process is performed for each of the plurality of steel pipe piles 110. As a result, as shown in FIG. 4, the pile heads of a plurality of steel pipe piles 110 that are mostly inserted into the seabed ground G and have the same height protrude from the seabed ground G upward.

打ち込み工程が完了した状態の鋼管杭110は、その大部分が海底地盤G内に貫入されており、海水に接する部分は杭頭部およびその近傍の部分に限られている。従って、鋼管杭110の全てが防食される必要はなく、必要に応じて海水に接する限られた部分のみが防食されればよい。   Most of the steel pipe pile 110 in a state where the driving process has been completed is penetrated into the seabed ground G, and the portion in contact with seawater is limited to the pile head and the vicinity thereof. Therefore, it is not necessary for all of the steel pipe piles 110 to be anticorrosive, and only a limited portion in contact with seawater needs to be anticorrosive as necessary.

<接合工程>
接合工程は、鋼管杭110の上杭としてコンクリート杭130を鋼管杭110に接合して継杭100を形成する工程である。
<Joint process>
The joining process is a process of joining the concrete pile 130 to the steel pipe pile 110 as the upper pile of the steel pipe pile 110 to form the joint pile 100.

接合工程において、まず、クレーンにより海中に吊り込まれたコンクリート杭130の下端部が鋼管杭110の頭部の内側に挿入される。そのため、鋼管杭110は、頭部における内径がコンクリート杭130の下端部(鋼管杭110に接合される部分)における外径よりも大きいものが用いられる。   In the joining process, first, the lower end portion of the concrete pile 130 suspended in the sea by a crane is inserted inside the head of the steel pipe pile 110. Therefore, the steel pipe pile 110 having a larger inner diameter at the head than the outer diameter at the lower end portion of the concrete pile 130 (part joined to the steel pipe pile 110) is used.

上記のように、鋼管杭110の頭部における内径が、コンクリート杭130の下端部における外径よりも大きいため、鋼管杭110の内側にコンクリート杭130が必要以上に落ち込まないように、鋼管杭110の頭部付近の内周面にはストッパとして機能する支持部材120が設けられている。   As described above, since the inner diameter of the head of the steel pipe pile 110 is larger than the outer diameter of the lower end of the concrete pile 130, the steel pipe pile 110 is prevented from dropping more than necessary inside the steel pipe pile 110. A support member 120 functioning as a stopper is provided on the inner peripheral surface in the vicinity of the head.

図5は、鋼管杭110を図4の矢印X1の方向に見た図である。支持部材120は、複数の固定部材121と、複数の固定部材121の上に設けられた充填剤の漏れ止め部材122を備える。複数の固定部材121は各々、鋼管杭110の内周面に、例えば溶接より、固定されている。図5に示される例では、8つの固定部材121がほぼ等しい角度を空けて配置されているが、固定部材121の個数やそれらの間隔はこれに限られない。 Figure 5 is a view of the steel pipe 110 in the direction of arrow X 1 in FIG. 4. The support member 120 includes a plurality of fixing members 121 and a filler leakage prevention member 122 provided on the plurality of fixing members 121. Each of the plurality of fixing members 121 is fixed to the inner peripheral surface of the steel pipe pile 110 by welding, for example. In the example shown in FIG. 5, the eight fixing members 121 are arranged at substantially the same angle, but the number of fixing members 121 and their intervals are not limited to this.

漏れ止め部材122は、中央に円形の孔が空けられた円形の板状部材である。漏れ止め部材122の中央の孔の直径は、コンクリート杭130の外径よりも小さい。漏れ止め部材122は、外周が鋼管杭110の内周面と接する状態で複数の固定部材121の上に固定されている。   The leakage preventing member 122 is a circular plate member having a circular hole in the center. The diameter of the hole in the center of the leakage preventing member 122 is smaller than the outer diameter of the concrete pile 130. The leakage preventing member 122 is fixed on the plurality of fixing members 121 in a state where the outer periphery is in contact with the inner peripheral surface of the steel pipe pile 110.

図6は、複数の鋼管杭110の各々の上に、コンクリート杭130が設置された状態を示している。すなわち、図4の状態の鋼管杭110の頭部の内側に、クレーンにより海中に吊り込んだコンクリート杭130の下端部が挿入されると、コンクリート杭130は下端部が支持部材120の上に接した状態で鋼管杭110に下方から支持された状態となる。   FIG. 6 shows a state in which the concrete pile 130 is installed on each of the plurality of steel pipe piles 110. That is, when the lower end of the concrete pile 130 suspended in the sea by a crane is inserted inside the head of the steel pipe pile 110 in the state of FIG. 4, the lower end of the concrete pile 130 is in contact with the support member 120. In this state, the steel pipe pile 110 is supported from below.

図7は、鋼管杭110およびコンクリート杭130を図6の矢印X2の方向に見た図である。鋼管杭110の内周面とコンクリート杭130の外周面の間に生じる隙間の底面は漏れ止め部材122により塞がれた状態となる。 Figure 7 is a view of the steel pipe piles 110 and concrete piles 130 in the direction of arrow X 2 in FIG. The bottom surface of the gap generated between the inner peripheral surface of the steel pipe pile 110 and the outer peripheral surface of the concrete pile 130 is in a state of being blocked by the leakage preventing member 122.

接合工程において、鋼管杭110の上にコンクリート杭130が設置されると、続いて、鋼管杭110とコンクリート杭130の水中グラウト接合が行われる。具体的には、鋼管杭110の内周面とコンクリート杭130の外周面の間に生じる隙間にグラウト材の充填が行われる。グラウト材としては、例えば、水中硬化型の無収縮モルタルが用いられる。隙間に充填されたグラウト材は硬化し、鋼管杭110とコンクリート杭130を固着する。   In the joining step, when the concrete pile 130 is installed on the steel pipe pile 110, the steel pipe pile 110 and the concrete pile 130 are subsequently subjected to underwater grout joining. Specifically, the grout material is filled in the gap formed between the inner peripheral surface of the steel pipe pile 110 and the outer peripheral surface of the concrete pile 130. As the grout material, for example, an underwater curing type non-shrink mortar is used. The grout material filled in the gap is cured and the steel pipe pile 110 and the concrete pile 130 are fixed.

図8は、水中グラウト接合が完了した状態の鋼管杭110とコンクリート杭130の接合部を示した図である。グラウト材140により固着された鋼管杭110とコンクリート杭130は継杭100を形成する。   FIG. 8 is a view showing a joint between the steel pipe pile 110 and the concrete pile 130 in a state where the underwater grout joining is completed. The steel pipe pile 110 and the concrete pile 130 fixed by the grout material 140 form the joint pile 100.

<設置工程>
設置工程は、複数の継杭100の上部に上部工200を設置する工程である。図9〜図11は、設置工程を説明する図である。
<Installation process>
The installation process is a process of installing the superstructure 200 on top of the plurality of joint piles 100. 9-11 is a figure explaining an installation process.

設置工程において、まず、継杭100の各々の上に梁部アセンブリ201が1つずつ設置される。図9に示されるように、梁部アセンブリ201は、底面側に突出するように設けられた鋼管210を備える。梁部アセンブリ201はプレキャストコンクリートのブロックである。鋼管210は梁部アセンブリ201の底面の概ね中央において下方に突出する状態で梁部アセンブリ201に固着されている。なお、鋼管210が梁部アセンブリ201の底面から下方に突出しない構成が採用されてもよい。   In the installation process, first, one beam assembly 201 is installed on each of the joint piles 100. As shown in FIG. 9, the beam assembly 201 includes a steel pipe 210 provided so as to protrude to the bottom surface side. The beam assembly 201 is a precast concrete block. The steel pipe 210 is fixed to the beam assembly 201 so as to protrude downward in the approximate center of the bottom surface of the beam assembly 201. A configuration in which the steel pipe 210 does not protrude downward from the bottom surface of the beam assembly 201 may be employed.

鋼管210の内径はコンクリート杭130の頭部の外径より大きい。従って、クレーンで吊った梁部アセンブリ201の鋼管210の位置をコンクリート杭130の頭部の位置に合わせて、梁部アセンブリ201を下ろしていくと、コンクリート杭130の頭部に鋼管210が被さった状態で、梁部アセンブリ201がコンクリート杭130の上に載った状態となる。   The inner diameter of the steel pipe 210 is larger than the outer diameter of the head of the concrete pile 130. Therefore, when the position of the steel pipe 210 of the beam assembly 201 hung by the crane is adjusted to the position of the head of the concrete pile 130 and the beam assembly 201 is lowered, the steel pipe 210 covers the head of the concrete pile 130. In this state, the beam assembly 201 is placed on the concrete pile 130.

複数のコンクリート杭130の各々の上に梁部アセンブリ201が配置された後、コンクリート杭130と鋼管210のグラウト接合が行われる。その後、例えばコンクリートの打設により、隣り合う梁部アセンブリ201の連結が行われる。図10は、隣り合う梁部アセンブリ201が連結された状態を示した図である。図10において、隣り合う梁部アセンブリ201を連結するために打設されたコンクリートはコンクリート224として示されている。このようにして複数の梁部アセンブリ201を含む梁部220が構成される。   After the beam assembly 201 is disposed on each of the plurality of concrete piles 130, the concrete pile 130 and the steel pipe 210 are grouted together. Thereafter, the adjacent beam assembly 201 is connected, for example, by placing concrete. FIG. 10 is a diagram showing a state where adjacent beam assembly 201 is connected. In FIG. 10, the concrete cast to connect adjacent beam assembly 201 is shown as concrete 224. In this way, the beam portion 220 including the plurality of beam portion assemblies 201 is configured.

続いて、梁部220の上に床版230が設置される。図11は、床版230の設置が完了した状態を示している。床版230の設置により設置工程が完了する。また、設置工程の完了により、継杭式桟橋1の施工が完了する。   Subsequently, the floor slab 230 is installed on the beam portion 220. FIG. 11 shows a state where the installation of the floor slab 230 is completed. Installation of the floor slab 230 completes the installation process. Moreover, construction of the joint pile pier 1 is completed by completing the installation process.

上述した継杭式桟橋1の杭基礎のうち海底地盤Gに貫入される部分には鋼管杭が用いられる。従って、海底地盤Gへの打ち込みにより杭の貫入が可能である。また、上述した継杭式桟橋1の杭基礎のうち海水中の大部分と干満帯および飛沫帯の部分にはコンクリート杭が用いられる。従って、杭基礎のうち防食を要する部分がごく限られている。   A steel pipe pile is used for the portion of the pile foundation of the joint pile pier 1 described above that penetrates into the seabed ground G. Therefore, the pile can be penetrated by driving into the seabed ground G. Moreover, a concrete pile is used for the most part in seawater, the tidal zone, and the part of a splash zone among the pile foundations of the joint pile type pier 1 mentioned above. Therefore, the part which requires anticorrosion among pile foundations is very limited.

また、上述した継杭式桟橋1の杭頭部(継杭100の頭部)は鋼管により覆われている。杭において杭頭部は水平荷重による曲げモーメントが最大となるが、同径の鋼管杭と比較して曲げ耐性に劣るコンクリート杭の頭部が鋼管により補強される。従って、必要な強度を確保するために要するコンクリート杭130の直径が小さくて済む場合が多い。   Moreover, the pile head of the joint pile type pier 1 mentioned above (head part of the joint pile 100) is covered with the steel pipe. In piles, the pile head has the greatest bending moment due to horizontal load, but the head of a concrete pile that is inferior in bending resistance compared to steel pipe piles of the same diameter is reinforced by steel pipes. Therefore, the diameter of the concrete pile 130 required to ensure the necessary strength is often small.

また、上述した継杭式桟橋1の杭基礎のうち海水中の大部分にはコンクリート杭が用いられる。コンクリート杭は同程度の直径の鋼管杭と比較して一般的に水平方向の変位量が少ない。従って、鋼管杭のみの杭基礎を備える桟橋と比較して、継杭式桟橋1は水平変位が抑えられる点で優れている。   Moreover, a concrete pile is used for the most part in seawater among the pile foundations of the joint pile type pier 1 mentioned above. Concrete piles generally have less horizontal displacement than steel pipe piles of the same diameter. Therefore, compared with the pier provided with the pile foundation only of a steel pipe pile, the joint pile type pier 1 is excellent in the point that horizontal displacement is suppressed.

[第2実施形態]
以下に第2実施形態にかかる継杭式桟橋1Aを説明する。継杭式桟橋1Aは、杭基礎と上部工の連結部分の構成が上述した第1実施形態にかかる継杭式桟橋1と異なっている。継杭式桟橋1Aは多くの点で継杭式桟橋1と共通または類似している。従って、以下の説明において、継杭式桟橋1Aが継杭式桟橋1と共通して備える構成部には、継杭式桟橋1の説明において用いた符号と同じ符号を用いる。また、継杭式桟橋1Aが備える構成部のうち継杭式桟橋1が備える構成部に対応するものには、対応する継杭式桟橋1の構成部に用いた符号の末尾に「A」を付したものを用いる。
[Second Embodiment]
The joint pile type pier 1A concerning 2nd Embodiment is demonstrated below. The joint pile-type pier 1A is different from the joint pile-type pier 1 according to the first embodiment described above in terms of the structure of the connecting portion between the pile foundation and the superstructure. The joint pile pier 1A is common or similar to the joint pile pier 1 in many respects. Therefore, in the following description, the same reference numerals as those used in the description of the joint pile pier 1 are used for components that the joint pile pier 1A includes in common with the joint pile pier 1. In addition, among the components provided in the joint pile pier 1A, those corresponding to the components provided in the joint pile pier 1 have “A” at the end of the reference numerals used for the components of the corresponding pile pile pier 1. Use the attached ones.

図12は、継杭式桟橋1Aを水平方向に見た模式図である。継杭式桟橋1Aは、杭基礎を構成する複数の継杭100Aと、複数の継杭100Aに支持される上部工200Aを備える。複数の継杭100Aの各々は、海底地盤Gから突出した鋼管杭110と、鋼管杭110の上杭として鋼管杭110に接合されたコンクリート杭130Aとを含む。上部工200Aは、梁部220Aと床版230を備える。   FIG. 12 is a schematic view of the joint pile pier 1A viewed in the horizontal direction. The joint pile type pier 1A includes a plurality of joint piles 100A constituting a pile foundation and an upper work 200A supported by the plurality of joint piles 100A. Each of the plurality of joint piles 100 </ b> A includes a steel pipe pile 110 protruding from the seabed ground G, and a concrete pile 130 </ b> A joined to the steel pipe pile 110 as an upper pile of the steel pipe pile 110. The superstructure 200A includes a beam portion 220A and a floor slab 230.

図13〜図16は、設置工程(杭基礎の上に上部工200Aを設置する工程)を説明する図である。図13は、海底地盤Gに打ち込まれた複数の鋼管杭110の各々の上にコンクリート杭130Aが配置され、水中グラウト接合により鋼管杭110とコンクリート杭130Aの固着が完了した状態を示している。図13に示されるように、コンクリート杭130Aは他の部分よりも拡径された頭部131を有する。即ち、頭部131の外径は、コンクリート杭130Aの頭部131以外の部分の外径よりも大きい。   FIGS. 13-16 is a figure explaining the installation process (process which installs the superstructure 200A on a pile foundation). FIG. 13 shows a state in which the concrete pile 130A is arranged on each of the plurality of steel pipe piles 110 driven into the seabed ground G, and the steel pipe pile 110 and the concrete pile 130A are fixed by underwater grouting. As shown in FIG. 13, the concrete pile 130 </ b> A has a head 131 whose diameter is larger than that of other portions. That is, the outer diameter of the head 131 is larger than the outer diameter of the portion other than the head 131 of the concrete pile 130A.

図14に示されるように、梁部220Aはプレキャストコンクリートブロックで作られた複数の梁部アセンブリ201Aを含む。梁部アセンブリ201Aは、その中央に上下方向に貫通するように空けられた孔225の内側を水平方向に橋渡しするように配置されたバー226を備える。バー226は、例えばH鋼である。孔225の直径は、コンクリート杭130Aの頭部131の外径より大きい。なお、梁部220Aの構成は一例に過ぎず、他の構成であってもよい。   As shown in FIG. 14, the beam portion 220A includes a plurality of beam portion assemblies 201A made of precast concrete blocks. The beam assembly 201A includes a bar 226 disposed at the center so as to bridge the inside of a hole 225 that is pierced in the vertical direction in the horizontal direction. The bar 226 is, for example, H steel. The diameter of the hole 225 is larger than the outer diameter of the head 131 of the concrete pile 130A. The configuration of the beam portion 220A is merely an example, and other configurations may be used.

設置工程において、梁部アセンブリ201Aは孔225と頭部131との位置合わせが行われた状態で下ろされる。その結果、孔225に頭部131が挿入された状態で頭部131の上面にバー226の下面が接し、バー226を介して梁部220Aの梁部アセンブリ201Aが継杭100の上に載った状態となる。   In the installation process, the beam assembly 201A is lowered with the holes 225 and the head 131 aligned. As a result, the lower surface of the bar 226 is in contact with the upper surface of the head 131 with the head 131 inserted in the hole 225, and the beam assembly 201A of the beam 220A is placed on the joint pile 100 through the bar 226. It becomes a state.

続いて、頭部131と孔225のグラウト接合が行われる。その後、隣り合う梁部アセンブリ201Aの連結が行われる。隣り合う梁部アセンブリ201Aの連結の方法は、例えば継杭式桟橋1における場合と同様である。図15は、隣り合う梁部アセンブリ201Aが連結された状態を示している。その後、図16に示されるように、梁部220Aの上に床版230が設置される。これにより、継杭式桟橋1Aの施工が完了する。   Subsequently, grouting of the head 131 and the hole 225 is performed. Thereafter, the adjacent beam assembly 201A is connected. The method of connecting the adjacent beam assembly 201A is the same as that in the joint pile pier 1, for example. FIG. 15 shows a state in which the adjacent beam assembly 201A is connected. Thereafter, as shown in FIG. 16, the floor slab 230 is installed on the beam portion 220A. Thereby, construction of the joint pile type pier 1A is completed.

継杭式桟橋1Aには、継杭式桟橋1において用いられる鋼管210は用いられない。すなわち、継杭式桟橋1Aにおいて、コンクリート杭の頭部は鋼管により補強されることはない。しかしながら、継杭式桟橋1Aにおいて用いられるコンクリート杭130Aは拡径された頭部131を有するため、杭頭部において要求される曲げ耐性が確保されている。   The steel pipe 210 used in the joint pile pier 1 is not used for the joint pile pier 1A. That is, in the joint pile type pier 1A, the head portion of the concrete pile is not reinforced by the steel pipe. However, since the concrete pile 130A used in the joint pile type pier 1A has the enlarged head 131, the bending resistance required in the pile head is secured.

なお、頭部131はコンクリート杭130Aの頭部131以外の部分と一体成形されてもよいし、頭部が拡径されていないコンクリート杭の頭部を拡径部材で覆うことによって製造されてもよい。   The head 131 may be integrally formed with a portion other than the head 131 of the concrete pile 130A, or may be manufactured by covering the head of a concrete pile that has not been enlarged in diameter with a diameter-expanding member. Good.

[変形例]
本発明は、上述した実施形態と異なる形態で実施してもよい。また、以下に示す変形例は、各々を組み合わせてもよい。
コンクリート杭130は、杭軸方向において一定の間隔で節が形成されたコンクリート杭(例えば、節付きPHC杭)であってもよい。節が形成されていない場合に比べてコンクリート杭130とグラウト材140の接触面積が増し、これに伴い、鋼管杭110とコンクリート杭130との付着力も増して継杭全体としての強度が増すからである。
[Modification]
The present invention may be implemented in a form different from the above-described embodiment. Moreover, you may combine each of the modification shown below.
The concrete pile 130 may be a concrete pile (for example, a PHC pile with a node) in which nodes are formed at regular intervals in the pile axis direction. Since the contact area between the concrete pile 130 and the grout material 140 is increased as compared with the case where no node is formed, the adhesion force between the steel pipe pile 110 and the concrete pile 130 is also increased, and the strength of the joint pile as a whole is increased. It is.

鋼管杭とコンクリート杭の接合は、グラウト接合以外の方法で行われてもよい。接合方法として、継手を用いた接合方法がある。図17は、この変形例にかかる鋼管杭110、およびコンクリート杭130Bの境界部付近を正面から見た図である。図18は、鋼管杭110とコンクリート杭130Bの接合部を示した図である。図19は、鋼管杭110、およびコンクリート杭130Bを、図18の矢印X3の方向に見た図である。 The steel pipe pile and the concrete pile may be joined by a method other than grout joining. As a joining method, there is a joining method using a joint. FIG. 17 is a front view of the vicinity of the boundary between the steel pipe pile 110 and the concrete pile 130B according to this modification. FIG. 18 is a view showing a joint portion between the steel pipe pile 110 and the concrete pile 130B. Figure 19 is a steel pipe pile 110, and a concrete pile 130B, a view looking in the direction of arrow X 3 in FIG. 18.

図17および図18に示すように、鋼管杭110とコンクリート杭130Bは、外径の大きさが同じである。また、図18に示すように、鋼管杭110の頭部付近の内周面にはストッパとして機能する支持部材120Bが設けられている。支持部材120Bは、その外周面が鋼管杭110の内周面に固着された円筒状の部材である。支持部材120Bの上端の位置は鋼管杭110の上端の位置と揃えられている。接合工程では、コンクリート杭130Bが鋼管杭110の上に配置される。これにより、コンクリート杭130Bは、鋼管杭110、および支持部材120Bに下方から支持された状態となる。   As shown in FIGS. 17 and 18, the steel pipe pile 110 and the concrete pile 130 </ b> B have the same outer diameter. Further, as shown in FIG. 18, a support member 120 </ b> B that functions as a stopper is provided on the inner peripheral surface near the head of the steel pipe pile 110. The support member 120 </ b> B is a cylindrical member whose outer peripheral surface is fixed to the inner peripheral surface of the steel pipe pile 110. The position of the upper end of the support member 120B is aligned with the position of the upper end of the steel pipe pile 110. In the joining step, the concrete pile 130B is disposed on the steel pipe pile 110. Thereby, the concrete pile 130B will be in the state supported by the steel pipe pile 110 and the support member 120B from the downward direction.

接合工程では、次に、鋼管杭110とコンクリート杭130Bが継手150を用いて接合される。継手150は、第1部分151と第2部分152とを含む機械式継手である。第1部分151は、鋼管杭110とコンクリート杭130Bとの境界付近の部分の周囲のうちの一部分を覆う。第2部分152は、当該境界付近の部分の周囲のうちの残りの部分を覆う。第1部分151と第2部分152との両端部が、それぞれ複数のボルト160を用いて接合されている。
継手150を用いることで、鋼管杭とその上杭であるコンクリート杭を溶接しなくとも接合することができる。また、鋼管杭の内径を、コンクリート杭の外径よりも大きくしなくてもよい。なお、この変形例で説明した継手150の構成は一例に過ぎず、他の構成の継手が採用されてもよい。
Next, in the joining step, the steel pipe pile 110 and the concrete pile 130B are joined using the joint 150. The joint 150 is a mechanical joint that includes a first portion 151 and a second portion 152. The first portion 151 covers a part of the periphery of the portion near the boundary between the steel pipe pile 110 and the concrete pile 130B. The second portion 152 covers the remaining portion around the portion near the boundary. Both ends of the first portion 151 and the second portion 152 are joined using a plurality of bolts 160, respectively.
By using the joint 150, the steel pipe pile and the concrete pile which is the upper pile can be joined without welding. Moreover, it is not necessary to make the internal diameter of a steel pipe pile larger than the outer diameter of a concrete pile. In addition, the structure of the joint 150 demonstrated in this modification is only an example, and the joint of another structure may be employ | adopted.

なお、本願の発明は、上述した実施形態に限定されることなく、請求の範囲に記載した発明の範囲内で種々の変形が可能である。例えば、図示された継杭式桟橋1または継杭式桟橋1Aの構成部の形状や個数等は一例であって、様々に変更されてよい。例えば、上述した第1実施形態において、複数の継杭100の各々の上に1つずつ梁部アセンブリ201または201Aが設置された後、隣り合う梁部アセンブリ201または201Aの連結が行われる。これに代えて、複数の継杭100の上に、複数の鋼管210が底面側に突出するように設けられた1つの梁部が設置されてもよい。   The invention of the present application is not limited to the above-described embodiment, and various modifications can be made within the scope of the invention described in the claims. For example, the shape, the number, and the like of the components of the illustrated pile-type pier 1 or the pile-type pier 1A are examples, and may be variously changed. For example, in the first embodiment described above, after the beam assembly 201 or 201A is installed on each of the plurality of joints 100, the adjacent beam assembly 201 or 201A is connected. It replaces with this and one beam part provided so that a plurality of steel pipes 210 may protrude on the bottom side may be installed on a plurality of joints 100.

1,1A…継杭式桟橋、100,100A…継杭、110…鋼管杭、120,120B…支持部材、121…固定部材、122…漏れ止め部材、130,130A,130B…コンクリート杭、131…頭部、140…グラウト材、150…継手、151…第1部分、152…第2部分、160…ボルト、200,200A…上部工、201,201A…梁部アセンブリ、210…鋼管、220,220A…梁部、224…コンクリート、225…孔、226…バー、230…床版、300…ヤットコ。 DESCRIPTION OF SYMBOLS 1,1A ... Joint pile type jetty, 100, 100A ... Joint pile, 110 ... Steel pipe pile, 120, 120B ... Support member, 121 ... Fixing member, 122 ... Leak prevention member, 130, 130A, 130B ... Concrete pile, 131 ... Head, 140 ... grouting material, 150 ... joint, 151 ... first part, 152 ... second part, 160 ... bolt, 200,200A ... superstructure, 201,201A ... beam assembly, 210 ... steel pipe, 220,220A ... beam part, 224 ... concrete, 225 ... hole, 226 ... bar, 230 ... floor slab, 300 ... Yatco.

Claims (8)

海底地盤上に突出した鋼管杭と、前記鋼管杭の上杭として前記鋼管杭に接合されたコンクリート杭とを有する複数の継杭と、
前記複数の継杭に支持される上部工と
を備える継杭式桟橋。
A plurality of joint piles having a steel pipe pile protruding on the seabed ground, and a concrete pile joined to the steel pipe pile as an upper pile of the steel pipe pile;
A pile-type jetty comprising: an upper work supported by the plurality of piles.
前記継杭の頭部を覆う鋼管を備える
請求項1に記載の継杭式桟橋。
The pier pile type jetty according to claim 1, further comprising a steel pipe covering a head portion of the pier pile.
前記コンクリート杭の頭部は拡径されている
請求項1に記載の継杭式桟橋。
The joint pile type pier according to claim 1, wherein a head portion of the concrete pile is expanded.
前記鋼管杭の頭部における内径は前記コンクリート杭の前記鋼管杭に接合される部分の外径よりも大きく、前記鋼管杭の中に前記コンクリート杭の一部が挿入されている
請求項1乃至3のいずれか1項に記載の継杭式桟橋。
The internal diameter in the head of the said steel pipe pile is larger than the outer diameter of the part joined to the said steel pipe pile of the said concrete pile, and a part of said concrete pile is inserted in the said steel pipe pile. The joint pier according to any one of the above.
前記鋼管杭と前記鋼管杭に挿入されている前記コンクリート杭の一部は水中グラウト充填により接合されている
請求項4に記載の継杭式桟橋。
The joint pile type pier according to claim 4, wherein a part of the steel pipe pile and the concrete pile inserted into the steel pipe pile are joined by underwater grout filling.
前記鋼管杭と前記コンクリート杭は継手を用いて接合されている
請求項1乃至3のいずれか1項に記載の継杭式桟橋。
The joint pile type pier according to any one of claims 1 to 3, wherein the steel pipe pile and the concrete pile are joined using a joint.
海底地盤に複数の鋼管杭を打ち込む工程と、
前記複数の鋼管杭の各々に上杭としてコンクリート杭を接合する工程と、
前記コンクリート杭を接合する工程によって形成された複数の継杭に支持される上部工を設置する工程と
を備える継杭式桟橋の施工方法。
A process of driving a plurality of steel pipe piles into the submarine ground;
Joining a concrete pile as an upper pile to each of the plurality of steel pipe piles;
And a step of installing superstructures supported by a plurality of joints formed by the step of joining the concrete piles.
前記上部工を設置する工程は、前記継杭の上にプレキャストコンクリートの梁部を設置する工程を含む
請求項7に記載の継杭式桟橋の施工方法。
The method for constructing a joint pile pier according to claim 7, wherein the step of installing the superstructure includes a step of installing a beam portion of precast concrete on the joint pile.
JP2017018546A 2017-02-03 2017-02-03 Joint pile type pier, and method for constructing joint pile type pier Pending JP2018123633A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017018546A JP2018123633A (en) 2017-02-03 2017-02-03 Joint pile type pier, and method for constructing joint pile type pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017018546A JP2018123633A (en) 2017-02-03 2017-02-03 Joint pile type pier, and method for constructing joint pile type pier

Publications (1)

Publication Number Publication Date
JP2018123633A true JP2018123633A (en) 2018-08-09

Family

ID=63111066

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017018546A Pending JP2018123633A (en) 2017-02-03 2017-02-03 Joint pile type pier, and method for constructing joint pile type pier

Country Status (1)

Country Link
JP (1) JP2018123633A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5116912U (en) * 1974-07-25 1976-02-06
JPH09158176A (en) * 1995-12-01 1997-06-17 Shintoku Kogyo Kk Connection metallic material of pile
JP2000120062A (en) * 1998-10-19 2000-04-25 Hiroshi Kitamura Joint structure of concrete pile
JP2000248526A (en) * 1999-03-03 2000-09-12 Nippon Steel Corp Pier structure and constructing method thereof
JP2002121754A (en) * 2000-10-13 2002-04-26 Ohbayashi Corp Method for constructing underwater foundation
JP2007197975A (en) * 2006-01-25 2007-08-09 Taisei Corp Structure and method for connecting pile head part and precast girder together

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5116912U (en) * 1974-07-25 1976-02-06
JPH09158176A (en) * 1995-12-01 1997-06-17 Shintoku Kogyo Kk Connection metallic material of pile
JP2000120062A (en) * 1998-10-19 2000-04-25 Hiroshi Kitamura Joint structure of concrete pile
JP2000248526A (en) * 1999-03-03 2000-09-12 Nippon Steel Corp Pier structure and constructing method thereof
JP2002121754A (en) * 2000-10-13 2002-04-26 Ohbayashi Corp Method for constructing underwater foundation
JP2007197975A (en) * 2006-01-25 2007-08-09 Taisei Corp Structure and method for connecting pile head part and precast girder together

Similar Documents

Publication Publication Date Title
JP3747198B2 (en) Steel pipe sheet pile foundation
US7150584B2 (en) Steel-pipe sheet pile and coupling structure of steel-pipe sheet piles
JP2018084048A (en) Steel pipe pile, pile head structure, pile type construction, construction method for steel pipe pile, and construction method for pile type construction
JP6033139B2 (en) Joint structure of pile and footing
JP4705513B2 (en) Foundation structure
JP4571878B2 (en) Reinforcement method for underwater foundation of existing structure
JP2006316495A (en) Foundation structure of bridge pier and its construction method
JP5147361B2 (en) Repair and reinforcement structure for floating structures
JP7017541B2 (en) Improvement structure and improvement method of existing sheet pile type quay
KR101341176B1 (en) Offshore pile-type support structure and construction method thereof
KR102076969B1 (en) Top-down construction method for concrete building structure using steel pile underground wall and shear support plate
JP2018123633A (en) Joint pile type pier, and method for constructing joint pile type pier
JP2013177741A (en) Earthquake strengthening structure of existent structure foundation employing composite ground pile foundation technique
JP2011117249A (en) Embankment reinforcing method
JP6656901B2 (en) Construction method of segments and submerged structures
JP5747516B2 (en) Shield tunnel
JP2007051500A (en) Joint structure of column and pile
KR20100004125U (en) A pile head reinforcement structure of concrete pile
JP2019056231A (en) Quay wall structure
KR20160092001A (en) Support post structure for safety fence
JP3735813B2 (en) Seismic pile group structure
KR101237986B1 (en) Structure of offshore structure and construction method thereof
JP6925091B1 (en) Box culvert
JP5556652B2 (en) Welding joint method and welded joint structure of shelter inner shell unit
JP2006257744A (en) Soil cement column wall, and foundation structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20191219

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20201016

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20201020

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20210511