JP2018071287A - Construction method of pipe roof - Google Patents

Construction method of pipe roof Download PDF

Info

Publication number
JP2018071287A
JP2018071287A JP2016215361A JP2016215361A JP2018071287A JP 2018071287 A JP2018071287 A JP 2018071287A JP 2016215361 A JP2016215361 A JP 2016215361A JP 2016215361 A JP2016215361 A JP 2016215361A JP 2018071287 A JP2018071287 A JP 2018071287A
Authority
JP
Japan
Prior art keywords
tunnel
shaft
underground
small
general
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2016215361A
Other languages
Japanese (ja)
Other versions
JP6715164B2 (en
Inventor
正一 金野
Shoichi Konno
正一 金野
佐藤 徹
Toru Sato
徹 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Iseki Kaihatsu Koki KK
Original Assignee
Taisei Corp
Iseki Kaihatsu Koki KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp, Iseki Kaihatsu Koki KK filed Critical Taisei Corp
Priority to JP2016215361A priority Critical patent/JP6715164B2/en
Publication of JP2018071287A publication Critical patent/JP2018071287A/en
Application granted granted Critical
Publication of JP6715164B2 publication Critical patent/JP6715164B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a construction method of a pipe roof capable of controlling a drilling amount.SOLUTION: A construction method of a pipe roof which connects a plurality of underground spaces installed underground with a pipe roof is provided. A step of constructing a reference tunnel 3 with a larger diameter from a departure shaft 1 toward an arrival shaft 2, a step of constructing a general tunnel 4A with a smaller diameter from the departure shaft toward the arrival shaft using a general drilling machine 6 with a smaller diameter sized to able to pass through the inner space of a reference tunnel, a step of pulling the general drilling machine which arrived at the arrival shaft back to the departure shaft through a reference tunnel are provided. In addition, a step of constructing a separate general tunnel 4B with a smaller diameter from the departure shaft toward the arrival shaft by the general drilling machine pulled back to the departure shaft and pulling the general tunnel 4B with a smaller diameter back to the side of the departure shaft through a reference tunnel is repeated for as many times as needed.SELECTED DRAWING: Figure 1B

Description

本発明は、地中に設けられた複数の地中空間をパイプルーフで接続させるパイプルーフの施工方法に関するものである。   The present invention relates to a pipe roof construction method in which a plurality of underground spaces provided in the ground are connected by a pipe roof.

特許文献1には、地中に管を連続して押し込むことでトンネルを構築する推進工法において、管の先頭で地盤を掘削させる掘進機が開示されている。この掘進機は、前面のカッタヘッドによって後続する管の外径と同程度の掘削が行えるうえに、カッタヘッドを中心に向けて屈折させることで、管の内部を通して掘進機を発進立坑側に引き戻すことができる構成となっている。   Patent Document 1 discloses an excavator that excavates the ground at the top of a pipe in a propulsion method in which a tunnel is constructed by continuously pushing the pipe into the ground. This excavator can excavate to the same extent as the outer diameter of the following pipe by the front cutter head, and refracts the cutter head toward the center to pull the excavator back to the start shaft side through the inside of the pipe. It has a configuration that can.

このような掘進機は、特許文献2,3に開示されているように、パイプルーフを構築する際などに使用される。パイプルーフは、地中に複数の推進管(トンネル)を並べることによって形成されるため、並べる推進管の数だけ掘進機を掘進させることになる。   Such an excavator is used when constructing a pipe roof as disclosed in Patent Documents 2 and 3. Since the pipe roof is formed by arranging a plurality of propulsion pipes (tunnels) in the ground, the excavator is dug by the number of propulsion pipes arranged.

特開平9−144485号公報JP-A-9-144485 特開2001−32672号公報JP 2001-32672 A 特開2002−147172号公報JP 2002-147172 A

しかしながらカッタヘッドを中心に向けて屈折させて発進立坑側に回収することが可能な拡縮掘進機(以下、カッタ部が縮径可能に構成された掘進機を「拡縮掘進機」という。)は、複雑な構造となるため機材費が高くなる。また、断面を小さくし難いため、小径のトンネルでよい場合であっても、拡縮掘進機の大きさに合わせた断面となって、工費が嵩む原因ともなる。   However, an expansion / reduction excavator that can be refracted toward the center of the cutter head and collected on the start shaft side (hereinafter, an excavator configured so that the cutter portion can be reduced in diameter is referred to as an “expansion / reduction excavator”) is used. Equipment cost increases due to the complicated structure. Moreover, since it is difficult to reduce the cross section, even if a small-diameter tunnel is sufficient, the cross section is adapted to the size of the expansion / contraction excavation machine, which causes the construction cost to increase.

さらに、推進管の数が多くなる場合に、工期短縮などを目的に並行して掘進機による掘進作業を行おうとすると、拡縮掘進機を複数用意することになり、さらに工費が増加する要因となる。   In addition, when the number of propelling pipes is increased, if the excavation work is carried out by the excavator in parallel for the purpose of shortening the construction period, a plurality of expansion / contraction excavators will be prepared, which will further increase the construction cost. .

そこで、本発明は、掘削量を抑えることが可能なパイプルーフの施工方法を提供することを目的としている。   Accordingly, an object of the present invention is to provide a pipe roof construction method capable of suppressing the amount of excavation.

前記目的を達成するために、本発明のパイプルーフの施工方法は、地中に設けられた複数の地中空間をパイプルーフで接続させるパイプルーフの施工方法であって、第1の地中空間から第2の地中空間に向けて大径の大トンネルを構築する工程と、前記大トンネルの内空を通過可能な大きさの小径の小掘進機を使用して前記第1の地中空間から前記第2の地中空間に向けて小径の小トンネルを構築する工程と、前記第2の地中空間に到達した前記小掘進機を前記大トンネルに通して前記第1の地中空間に引き戻す工程とを備え、前記第1の地中空間に戻された前記小掘進機により、前記第1の地中空間から前記第2の地中空間に向けて別の小径の小トンネルを構築するとともに、前記大トンネルに通して前記第1の地中空間側に引き戻す工程を、必要な数だけ繰り返すことを特徴とする。   In order to achieve the above object, a pipe roof construction method of the present invention is a pipe roof construction method for connecting a plurality of underground spaces provided in the ground with a pipe roof, the first underground space. The first underground space using a step of constructing a large tunnel having a large diameter from the first to the second hollow and a small digging machine having a small diameter capable of passing through the inner space of the large tunnel. A small tunnel having a small diameter toward the second hollow, and passing the small digging machine that has reached between the second hollows through the large tunnel between the first hollows. A small tunnel having another small diameter from the first underground space to the second hollow space by the small excavator returned between the first hollow spaces. And pulling back to the first underground space side through the large tunnel. , And repeating as many times as necessary.

ここで、前記第2の地中空間は、前記第1の地中空間よりも狭い狭小空間であってもよい。また、前記大トンネルは、前面のカッタ部が縮径可能な拡縮掘進機によって構築され、前記拡縮掘進機は前記大トンネルに通して前記第1の地中空間に引き戻される構成とすることができる。   Here, the second underground space may be a narrow space narrower than the first underground space. The large tunnel may be constructed by an expansion / reduction machine capable of reducing the diameter of the front cutter, and the expansion / reduction machine may be pulled back through the large tunnel between the first ground hollows. .

さらに、前記第1の地中空間又は前記第2の地中空間から第3の地中空間に向けて、前記小掘進機が通過可能な大径の大トンネルを構築する工程と、前記第1の地中空間又は前記第2の地中空間から前記第3の地中空間に向けて前記小掘進機によって小トンネルを構築する工程と、前記第3の地中空間に到達した前記小掘進機を前記大トンネルに通して前記第1の地中空間又は前記第2の地中空間に引き戻す工程とを備えた構成とすることができる。   Further, a step of constructing a large-diameter large tunnel through which the small excavator can pass from the first underground space or the second underground space to a third hollow space; and Constructing a small tunnel by the small digging machine from the underground space or the second underground space between the third underground cavities, and the small digging machine reaching between the third underground cavities Through the large tunnel and pulling back between the first underground space or the second underground hollow.

このように構成された本発明のパイプルーフの施工方法は、最初に第1の地中空間から第2の地中空間に向けて大径の大トンネルを構築し、その後は、大トンネルを通して回収可能な小径の小掘進機によって小トンネルを構築していく。   The construction method of the pipe roof of the present invention configured as described above first constructs a large-diameter large tunnel from the first underground space to the second underground hollow, and then collects it through the large tunnel. Small tunnels will be built using small digging machines with a small diameter.

このため、大径のトンネルだけでパイプルーフを構築する場合と比べて、掘削量を抑えることができる。また、第2の地中空間においてクレーンを使って掘進機を投入したり撤去したりする必要がないため、第2の地中空間が狭小空間であっても施工することができる。   For this reason, compared with the case where a pipe roof is constructed only with a large diameter tunnel, the amount of excavation can be suppressed. In addition, since it is not necessary to input or remove the excavator using a crane in the second underground space, construction can be performed even if the second underground space is a narrow space.

さらに、大トンネルを前面のカッタ部が縮径可能な拡縮掘進機によって構築する場合は、第2の地中空間に到達後に、簡単に第1の地中空間側へ引き戻すことができる。   Furthermore, when a large tunnel is constructed by an expansion / contraction excavating machine whose front cutter can reduce the diameter, it can be easily pulled back to the first underground space side after reaching the second hollow.

また、地中空間が3つとなる場合であっても、大トンネルを小掘進機の回収用に利用することで、掘削量を抑えて複数箇所にパイプルーフを構築することができる。   Even when there are three underground spaces, by using the large tunnel for collecting the small excavator, it is possible to construct pipe roofs at a plurality of locations while suppressing the amount of excavation.

本実施の形態のパイプルーフの施工方法において、基準トンネルを構築する工程を説明するための模式平面図である。In the construction method of the pipe roof of this Embodiment, it is a schematic plan view for demonstrating the process of constructing | assembling a reference | standard tunnel. 基準トンネルに隣接して一般トンネルを構築する工程を説明するための模式平面図である。It is a schematic plan view for demonstrating the process of constructing | assembling a general tunnel adjacent to a reference | standard tunnel. 発進立坑と到達立坑との間にパイプルーフが構築された構成を説明する平面図である。It is a top view explaining the structure by which the pipe roof was constructed | assembled between the starting shaft and the reaching shaft. 図2のA−A矢視方向で見た断面図である。It is sectional drawing seen in the AA arrow direction of FIG. 地中を掘進中の拡縮掘進機の状態を説明するための断面図である。It is sectional drawing for demonstrating the state of the expansion / contraction excavation machine under excavation in the ground. カッタヘッドを縮径させて拡縮掘進機を引き戻す工程を説明するための断面図である。It is sectional drawing for demonstrating the process of reducing the diameter of a cutter head and pulling back an expansion / contraction machine. 基準管と一般推進管との連結状態を説明するための横断面図である。It is a transverse cross section for explaining the connection state of a standard pipe and a general propulsion pipe. 実施例のパイプルーフの施工方法を説明するための模式平面図である。It is a schematic plan view for demonstrating the construction method of the pipe roof of an Example.

以下、本発明の実施の形態について図面を参照して説明する。図1A,1Bは、本実施の形態のパイプルーフの施工方法を説明する模式図、図2,3は、第1の地中空間となる発進立坑1と第2の地中空間となる到達立坑2との間をパイプルーフ30で接続した構成を説明する図である。   Hereinafter, embodiments of the present invention will be described with reference to the drawings. 1A and 1B are schematic diagrams for explaining a pipe roof construction method according to the present embodiment, and FIGS. 2 and 3 are a start shaft 1 serving as a first underground space and a reaching shaft serving as a second underground space. It is a figure explaining the structure which connected between 2 with the pipe roof 30. FIG.

パイプルーフ30は、地表の道路や線路などの沈下を抑えながら地中にトンネルや地下空間を構築するために設けられる。本実施の形態では、推進工法によってパイプルーフ30を構築する場合について説明する。   The pipe roof 30 is provided for constructing a tunnel or an underground space in the ground while suppressing the settlement of roads and tracks on the surface. In the present embodiment, a case where the pipe roof 30 is constructed by the propulsion method will be described.

推進工法では、発進立坑1から掘進機を発進させ、地盤を切削しながら地中に押し出された掘進機の後方に、推進管を推し込んでいくことでトンネルを構築する。   In the propulsion method, the excavator is started from the start shaft 1, and a tunnel is constructed by pushing the propulsion pipe behind the excavator pushed into the ground while cutting the ground.

掘進機は、到達立坑2に到達すると、クレーンなどで吊り上げられて、再び発進立坑1からの掘進や別の箇所での掘進に使用されることになる。このため、発進立坑1や到達立坑2の周囲には、クレーンの据え付けや資材などを設置しておくための作業ヤードが、通常は必要となる。   When the excavator reaches the reaching shaft 2, it is lifted by a crane or the like and used again for excavation from the starting shaft 1 or for excavation at another location. For this reason, a work yard for installing cranes and installing materials is usually required around the start shaft 1 and the reach shaft 2.

ここで、都心部の現場などにおいては、発進立坑1や到達立坑2を構築するための用地や、作業ヤードのための用地を充分に確保できない場合がある。本実施の形態では、そのような場合においても実施できるパイプルーフ30の施工方法について説明する。   Here, there are cases where a site for constructing the start shaft 1 and the reach shaft 2 and a site for a work yard cannot be sufficiently secured in a site in the city center. In the present embodiment, a construction method of the pipe roof 30 that can be implemented even in such a case will be described.

まず発進立坑1については、掘進機を組み立てたり資材を搬入したりするための空間が確保できるものとする。また、発進立坑1の周囲にもクレーンを据え付けたり、資材を仮置きしたりするための作業ヤードが確保できるものとする。   First, regarding the start shaft 1, a space for assembling an excavator and carrying in materials can be secured. In addition, it is assumed that a work yard for installing a crane or temporarily placing materials around the start shaft 1 can be secured.

詳細には、図2及びその図のA−A矢視方向で見た図3に示すように、山留壁11によって囲まれて掘り下げられた発進立坑1は、比較的大きな空洞に形成される。   Specifically, as shown in FIG. 2 and FIG. 3 as viewed in the direction of arrows AA in the figure, the start shaft 1 surrounded by the mountain retaining wall 11 and dug down is formed in a relatively large cavity. .

発進立坑1の底面にはコンクリートが敷き均された底盤12が設けられ、その上に掘進機の発進架台13が設置される。発進架台13は、掘進機を発進させるステージとなったり、推進させるための反力を確保したりするための架台で、比較的大型になる。   On the bottom of the start shaft 1 is provided a floor 12 on which concrete is spread and leveled, and a start frame 13 for the excavator is installed thereon. The starting stand 13 is a stage for starting a digging machine or securing a reaction force for propulsion, and is relatively large.

これに対して、到達立坑2側では、発進立坑1側のように広い用地や作業ヤードが確保できない状況にあるものとする。この到達立坑2は、山留壁21によって囲まれて、底面にはコンクリートが敷き均された底盤22が設けられる。   On the other hand, on the side of the reaching shaft 2, it is assumed that a large site or work yard cannot be secured as on the start shaft 1 side. This reach shaft 2 is surrounded by a mountain retaining wall 21, and a bottom plate 22 is provided with a concrete spread on the bottom surface.

この底盤22の上には、到達した掘進機を載せるための到達架台23が設置される。この到達架台23は、発進架台13よりも小型にすることができる。また、ここでは到達立坑2として説明するが、地上を開削できない場合は、地下空洞を第2の地中空間にすることもできる。要するに第2の地中空間では、掘進機を到達させ、作業員が掘進機を横移動させる作業空間が確保できればよい。   On the bottom plate 22, a reaching platform 23 for placing the reached excavator is installed. This arrival stand 23 can be made smaller than the start stand 13. Moreover, although demonstrated here as the reach shaft 2, when the ground cannot be excavated, an underground cavity can also be made into 2nd underground space. In short, in the second underground space, it is sufficient that the excavator can be reached and a work space in which the worker can move the excavator laterally can be secured.

本実施の形態のパイプルーフ30の施工方法では、2種類の掘進機を使用する。第1の掘進機は、図4A,4Bに示すような、前面のカッタ部が縮径可能な拡縮掘進機5である。   In the construction method of the pipe roof 30 of the present embodiment, two types of excavators are used. The first excavation machine is an expansion / contraction excavation machine 5 as shown in FIGS. 4A and 4B in which the front cutter can be reduced in diameter.

この拡縮掘進機5は、円筒状の本体部52と、カッタ部となるカッタヘッド51とによって主に構成される。また、本体部52の外側には、一回り内径が大きな先導管53が配置される。   The expansion / contraction machine 5 is mainly configured by a cylindrical main body 52 and a cutter head 51 serving as a cutter unit. In addition, a leading conduit 53 having a single inner diameter is disposed outside the main body 52.

カッタヘッド51は、通常のカッタビットに加えて、先導管53の直径と略同じ径に広げることができるスポーク512と、そのスポーク512の先端に取り付けられるオーバービット511とを備えている。   The cutter head 51 includes, in addition to a normal cutter bit, a spoke 512 that can be expanded to substantially the same diameter as the tip conduit 53 and an overbit 511 that is attached to the tip of the spoke 512.

オーバービット511が取り付けられるスポーク512は、図4Bに示すように、ピン513を回動支点にしてカッタヘッド51の中心に向けて屈折させることができる。   As shown in FIG. 4B, the spoke 512 to which the overbit 511 is attached can be refracted toward the center of the cutter head 51 using the pin 513 as a rotation fulcrum.

一方、本体部52は、カッタヘッド51を回転駆動させるモータ部521と、ジャッキ部522と、掘削された土砂をトンネル外に排出させるための排泥管523とによって主に構成される。   On the other hand, the main body portion 52 is mainly configured by a motor portion 521 that rotationally drives the cutter head 51, a jack portion 522, and a mud pipe 523 for discharging the excavated earth and sand outside the tunnel.

本体部52は、カッタヘッド51側とモータ部521側とが隔壁524によって仕切られている。また、本体部52の後端部54には、ワイヤロープ551を連結させるための金具541が取り付けられる。   In the main body 52, the cutter head 51 side and the motor unit 521 side are partitioned by a partition wall 524. A metal fitting 541 for connecting the wire rope 551 is attached to the rear end portion 54 of the main body portion 52.

ジャッキ部522は、周方向に間隔を置いて複数、配置されており、カッタヘッド51を地盤に押し付ける力が付与できるとともに、推進方向を制御させることができる。   A plurality of jack portions 522 are arranged at intervals in the circumferential direction, and a force for pressing the cutter head 51 against the ground can be applied and the propulsion direction can be controlled.

排泥管523は、後端がトンネル内の配管32の先端に接続されており、カッタヘッド51で掘削された土砂や掘削面を安定させるために注入された泥水などを、発進立坑1に向けて搬送させることができる。   The mud discharge pipe 523 is connected to the tip of the pipe 32 in the tunnel at the rear end, and the mud etc. injected to stabilize the earth and sand excavated by the cutter head 51 and the excavation surface are directed to the starting shaft 1. Can be transported.

先導管53は、拡縮掘進機5を収容可能な内空が形成された管材で、後方に接続される基準管31と同じ直径に形成される。この基準管31は、先導管53の後方に押し込まれる推進管で、基準トンネル3の外殻の構成部材である。   The front conduit 53 is a tube material in which an inner space that can accommodate the expansion / contraction machine 5 is formed, and is formed to have the same diameter as the reference tube 31 connected to the rear. The reference pipe 31 is a propulsion pipe that is pushed behind the leading conduit 53 and is a constituent member of the outer shell of the reference tunnel 3.

すなわち図2に示すように、複数の基準管31,・・・を繋げることによって、発進立坑1と到達立坑2との間が基準トンネル3によって接続されることになる。この基準トンネル3を、直径が大径となる大トンネルとする。   That is, as shown in FIG. 2, the start tunnel 1 and the arrival shaft 2 are connected by the reference tunnel 3 by connecting a plurality of reference pipes 31. The reference tunnel 3 is a large tunnel having a large diameter.

一方もう一種類の掘進機として、基準トンネル3の内空を通過可能な大きさの小径の小掘進機を一般掘進機6として使用する。この一般掘進機6は、前面にカッタ部としてのカッタヘッド61を備えているが、このカッタヘッド61は縮径させることができない。   On the other hand, as another type of excavator, a small-diameter small-diameter having a size capable of passing through the inner space of the reference tunnel 3 is used as the general excavator 6. The general excavator 6 includes a cutter head 61 as a cutter unit on the front surface, but the cutter head 61 cannot be reduced in diameter.

そして、一般掘進機6の後方には一般推進管41が接続され、一般推進管41によって構成される小径の小トンネルを、一般トンネル4A−4Jとする。図5は、基準管31と一般推進管41との連結状態を示している。   A general propulsion pipe 41 is connected to the rear of the general excavator 6, and a small tunnel having a small diameter constituted by the general propulsion pipe 41 is referred to as a general tunnel 4A-4J. FIG. 5 shows a connection state between the reference pipe 31 and the general propulsion pipe 41.

基準管31の外周の対向する位置には、一対のメス型の凹継手311,311が設けられる。そして、一般推進管41の外周の対向する位置には、メス型の凹継手411とオス型の凸継手412がそれぞれ設けられる。   A pair of female concave joints 311 and 311 are provided at opposing positions on the outer periphery of the reference tube 31. A female-type concave joint 411 and a male-type convex joint 412 are respectively provided at opposing positions on the outer periphery of the general propulsion pipe 41.

基準管31の凹継手311は、管軸方向に平行する方向に連続して延伸されており、その内空に一般推進管41の凸継手412を挿し込むことができる。すなわち、先行して地中に推し込まれた基準管31に対して、発進立坑1側に開放された凹継手311の開口に一般推進管41の凸継手412の先端を挿し込み、一般推進管41を基準管31に沿って推し込むことで、基準管31に一般推進管41を連結させることができる。   The concave joint 311 of the reference pipe 31 is continuously extended in a direction parallel to the pipe axis direction, and the convex joint 412 of the general propulsion pipe 41 can be inserted into the inner space thereof. That is, the tip of the convex joint 412 of the general propulsion pipe 41 is inserted into the opening of the concave joint 311 opened to the start shaft 1 side with respect to the reference pipe 31 that has been pushed into the ground in advance. By pushing 41 along the reference tube 31, the general propulsion tube 41 can be connected to the reference tube 31.

このようにして地中に推し込まれた一般推進管41に対しては、凹継手411に隣接させる別の一般推進管41の凸継手412を挿し込むことで、一般推進管41,41同士を連結させることができる。   By inserting the convex joint 412 of another general propulsion pipe 41 adjacent to the concave joint 411 to the general propulsion pipe 41 pushed into the ground in this way, the general propulsion pipes 41 and 41 are connected to each other. Can be linked.

次に、本実施の形態のパイプルーフ30の施工方法、及びその作用について説明する。   Next, the construction method of the pipe roof 30 of this Embodiment and its effect | action are demonstrated.

まず図1Aに示すように、発進立坑1からオーバービット511が先端に取り付けられたスポーク512を拡げた状態の拡縮掘進機5を発進させ、到達立坑2に向けて基準トンネル3を構築する。   First, as shown in FIG. 1A, the expansion / reduction excavator 5 in a state where the spoke 512 with the over bit 511 attached to the tip is expanded from the start shaft 1 is started, and the reference tunnel 3 is constructed toward the arrival shaft 2.

基準トンネル3の外殻は、図2に示すように、拡縮掘進機5の先導管53に続いて推し込まれる複数の基準管31,・・・によって形成される。この基準トンネル3の直径を、例えば1100mmにする。   As shown in FIG. 2, the outer shell of the reference tunnel 3 is formed by a plurality of reference pipes 31,. The diameter of the reference tunnel 3 is set to 1100 mm, for example.

拡縮掘進機5が到達立坑2に到達すると、図4Bに示すように、到達立坑2内に突出させたスポーク512,512を、カッタヘッド51の中心に向けて屈折させて、基準トンネル3の内空を通過可能な状態にする。   When the expansion / contraction machine 5 reaches the reaching shaft 2, as shown in FIG. 4B, the spokes 512 and 512 projecting into the reaching shaft 2 are refracted toward the center of the cutter head 51, so that the inside of the reference tunnel 3 Make the sky passable.

続いて、拡縮掘進機5の後端部54の金具541にワイヤロープ551の一端を係留させる。このワイヤロープ551の他端は、図3に示すように、発進立坑1の発進架台13上に設置されたウインチ55に接続されている。   Subsequently, one end of the wire rope 551 is moored to the metal fitting 541 of the rear end portion 54 of the expansion / contraction machine 5. As shown in FIG. 3, the other end of the wire rope 551 is connected to a winch 55 installed on the start frame 13 of the start shaft 1.

このウインチ55を稼働させると、ワイヤロープ551が巻き取られて、拡縮掘進機5を後進させることができる。すなわち、拡縮掘進機5は、発進立坑1に向けて引き戻されることになる。発進立坑1内に回収された拡縮掘進機5は、その後の工程で使用しない場合は、クレーン14によって吊り上げられて発進立坑1から撤去される。   When the winch 55 is operated, the wire rope 551 is wound up, and the expansion / contraction excavation machine 5 can be moved backward. That is, the expansion / contraction excavation machine 5 is pulled back toward the start shaft 1. The expansion / reduction machine 5 collected in the start shaft 1 is lifted by the crane 14 and removed from the start shaft 1 when not used in the subsequent process.

この拡縮掘進機5に代えて、発進立坑1には、クレーン14で吊り上げられた一般掘進機6が搬入される。一般掘進機6は、発進架台13に載せられて、基準トンネル3の坑口の隣にセットされる。   Instead of the expansion / contraction excavator 5, the general excavator 6 lifted by the crane 14 is carried into the start shaft 1. The general excavator 6 is placed on the start stand 13 and set next to the wellhead of the reference tunnel 3.

図1Bに示すように、一般掘進機6によって一般トンネル4Aが構築される。この一般トンネル4Aの外殻は、図2に示すように、一般掘進機6の先導管に続いて推し込まれる複数の一般推進管41,・・・によって形成される。この一般トンネル4Aの直径を、例えば800mmにする。   As shown in FIG. 1B, a general tunnel 4 </ b> A is constructed by the general excavator 6. As shown in FIG. 2, the outer shell of the general tunnel 4 </ b> A is formed by a plurality of general propulsion pipes 41,. The diameter of this general tunnel 4A is set to 800 mm, for example.

一般掘進機6の到達立坑2への到達後は、図1Bに示すように、到達立坑2内の空間に押し出された一般掘進機6を横移動させ、先行して構築された大径の基準トンネル3の坑口前に設置する。   After reaching the reach shaft 2 of the general excavator 6, as shown in FIG. 1B, the general excavator 6 pushed into the space in the reach shaft 2 is moved laterally, and a large diameter reference constructed in advance. It is installed in front of the tunnel 3 tunnel.

その後、一般掘進機6には、上述した拡縮掘進機5と同様にワイヤロープ551が後端に係留されて、ウインチ55の稼働によって基準トンネル3を通して発進立坑1まで引き戻される。   Thereafter, the wire rope 551 is moored at the rear end of the general excavator 6 in the same manner as the expansion / contraction excavator 5 described above, and is pulled back to the start shaft 1 through the reference tunnel 3 by the operation of the winch 55.

発進立坑1に回収された一般掘進機6は、引き続き一般トンネル4Bの構築に使用される。ここで、図5に示すように、基準トンネル3の両側には、一般トンネル4Aと一般トンネル4Bとが連結される。   The general excavator 6 collected in the start shaft 1 is continuously used to construct the general tunnel 4B. Here, as shown in FIG. 5, the general tunnel 4 </ b> A and the general tunnel 4 </ b> B are connected to both sides of the reference tunnel 3.

さらに、一般トンネル4Bの構築に使用された一般掘進機6は、上述した手順で発進立坑1に引き戻されて、同径の一般トンネル4Cの構築に使用される。その後も図2に示すように、基準トンネル3を中心に、左右交互に両側に一般トンネル4D,4E,4F,4G,4H,4I,4Jが構築される。   Further, the general excavator 6 used for constructing the general tunnel 4B is pulled back to the start shaft 1 by the above-described procedure and used for constructing the general tunnel 4C having the same diameter. After that, as shown in FIG. 2, general tunnels 4D, 4E, 4F, 4G, 4H, 4I, and 4J are constructed on both sides alternately with the reference tunnel 3 as the center.

このように構成された本実施の形態のパイプルーフ30の施工方法は、最初に発進立坑1から到達立坑2に向けて大径の基準トンネル3を構築し、その後は、基準トンネル3を通して回収可能な小径の一般掘進機6によって一般トンネル4A−4Jを構築していく。   In the construction method of the pipe roof 30 of the present embodiment configured as described above, a large-diameter reference tunnel 3 is first constructed from the starting shaft 1 to the reaching shaft 2, and thereafter, it can be recovered through the reference tunnel 3. The general tunnel 4A-4J is constructed by the general excavator 6 having a small diameter.

このため、大径のトンネルだけでパイプルーフを構築する場合と比べて、掘削量を大幅に抑えることができる。パイプルーフ30の工費は、掘削量に比例して増加するため、掘削量の削減は、工期及び工費の低減に大きく貢献することができる。   For this reason, compared with the case where a pipe roof is constructed | assembled only with a large diameter tunnel, the amount of excavation can be suppressed significantly. Since the construction cost of the pipe roof 30 increases in proportion to the excavation amount, the reduction of the excavation amount can greatly contribute to the reduction of the construction period and the construction cost.

また、到達立坑2側でクレーンを使って掘進機を投入したり撤去したりする必要がないため、到達立坑2のための用地が充分に確保できず狭小空間となってしまっても施工することができる。要するに、基準トンネル3が接続用トンネルの機能を果たすため、到達立坑2が狭小空間であっても施工が可能になる。   In addition, it is not necessary to load or remove the excavator using a crane on the side of the vertical shaft 2, so it is possible to construct even if the site for the vertical shaft 2 cannot be secured sufficiently and becomes a small space. Can do. In short, since the reference tunnel 3 functions as a connection tunnel, the construction can be performed even if the reaching shaft 2 is a narrow space.

さらに、最初に構築される基準トンネル3を、前面のカッタヘッド51が縮径可能な拡縮掘進機5によって構築する場合は、到達立坑2に到達後に、スポーク512を屈折させることで簡単に発進立坑1側へ引き戻すことができる。   Furthermore, when the reference tunnel 3 to be constructed first is constructed by the expansion / reduction excavator 5 in which the front cutter head 51 can reduce the diameter, after reaching the arrival shaft 2, the spoke 512 can be refracted to easily refract the start shaft. It can be pulled back to the 1 side.

また、複数の一般掘進機6,6を使用して並行して一般トンネル4A−4Jを構築するようにすれば、工期を大幅に短縮させることができる。汎用的な一般掘進機6であれば、比較的安価で増設することができる。   If the general tunnel 4A-4J is constructed in parallel using a plurality of general excavators 6 and 6, the construction period can be greatly shortened. If it is a general purpose general excavator 6, it can be expanded at a relatively low cost.

次に、前記実施の形態で説明したパイプルーフの施工方法とは別の形態について、図6を参照しながら説明する。なお、前記実施の形態で説明した内容と同一乃至均等な部分の説明については、同一用語や同一符号を付して説明する。   Next, another embodiment different from the pipe roof construction method described in the above embodiment will be described with reference to FIG. Note that the description of the same or equivalent parts as those described in the above embodiment will be described with the same terms and the same reference numerals.

前記実施の形態では、発進立坑1と到達立坑2という2つの地中空間を接続させるパイプルーフ30を構築する場合について説明した。本実施例では、3つの地中空間をそれぞれ接続させるパイプルーフ30A,30Bの施工方法について説明する。   In the above-described embodiment, the case where the pipe roof 30 that connects the two underground spaces, the start shaft 1 and the arrival shaft 2, is described. In the present embodiment, a construction method of the pipe roofs 30A and 30B for connecting the three underground spaces will be described.

第1の地中空間となる第1立坑71は、掘進機を組み立てたり資材を搬入したりするための空間が確保できるものとする。また、第1立坑71の周囲にもクレーンを据え付けたり、資材を仮置きしたりするための作業ヤードが確保できるものとする。   The first shaft 71 serving as the first underground space can secure a space for assembling an excavator or carrying in materials. In addition, it is assumed that a work yard for installing a crane or temporarily placing materials around the first shaft 71 can be secured.

一方、第1立坑71と対向する位置に設けられる第2の地中空間となる第2立坑72は、第1立坑71側のように広い用地や作業ヤードが確保できない状況にあるものとする。   On the other hand, suppose that the 2nd shaft 72 used as the 2nd underground space provided in the position facing the 1st shaft 71 is in the condition which cannot secure a wide site and a work yard like the 1st shaft 71 side.

また、第2立坑72と対向する位置に設けられる第3の地中空間となる第3立坑73も、第1立坑71側のように広い用地や作業ヤードが確保できない状況にあるものとする。要するに、掘進機の搬入や撤去、資機材の仮置き等は、すべて第1立坑71側で行われる状況であるものとする。   Moreover, the 3rd shaft 73 used as the 3rd underground space provided in the position facing the 2nd shaft 72 is also in the condition which cannot secure a wide site and work yard like the 1st shaft 71 side. In short, it is assumed that the carrying and removal of the excavator and the temporary placement of materials and equipment are all performed on the first shaft 71 side.

まず、第1立坑71から第2立坑72に向けて大径の大トンネルとなる基準トンネル3Aが、拡縮掘進機5によって構築される。続いて、前記実施の形態で説明したように、基準トンネル3Aの内空を通過可能な大きさの一般掘進機6を使用して、第1立坑71から第2立坑72に向けて小径の小トンネルとなる一般トンネル4が構築される。   First, the reference tunnel 3 </ b> A that becomes a large-diameter large tunnel from the first vertical shaft 71 to the second vertical shaft 72 is constructed by the expansion / contraction advancement machine 5. Subsequently, as described in the above-described embodiment, the small-diameter small diameter from the first shaft 71 to the second shaft 72 using the general excavator 6 having a size capable of passing through the inner space of the reference tunnel 3A. A general tunnel 4 serving as a tunnel is constructed.

そして、第1立坑71と第2立坑72とを繋ぐパイプルーフ30Aの構築後、又はパイプルーフ30Aの構築と並行して、第2立坑72から第3立坑73に向けて大径の大トンネルとなる基準トンネル3Bが、拡縮掘進機5によって構築される。   Then, after the construction of the pipe roof 30A connecting the first shaft 71 and the second shaft 72, or in parallel with the construction of the pipe roof 30A, a large tunnel having a large diameter from the second shaft 72 to the third shaft 73 The reference tunnel 3 </ b> B is constructed by the expansion / contraction excavation machine 5.

続いて、基準トンネル3A,3Bの内空を通過可能な大きさの一般掘進機6を使用して、第2立坑72から第3立坑73に向けて小径の小トンネルとなる一般トンネル4が構築される。   Subsequently, the general tunnel 4 that is a small tunnel having a small diameter from the second shaft 72 to the third shaft 73 is constructed using the general excavator 6 having a size capable of passing through the inner space of the reference tunnels 3A and 3B. Is done.

このように、地中空間が3となる場合であっても、大径の基準トンネル3A、3Bを一般掘進機6の回収用や搬送用に利用することで、掘削量を抑えて複数箇所にパイプルーフ30A,30Bを構築することができる。   Thus, even when the underground space is 3, the large diameter reference tunnels 3A and 3B are used for collecting and transporting the general excavator 6, thereby reducing the amount of excavation at a plurality of locations. Pipe roof 30A, 30B can be constructed.

また、第2立坑72や第3立坑73のために充分な用地が確保できない場合であっても、複数のパイプルーフ30A,30Bを構築することができる。要するに、基準トンネル3A,3Bが接続用トンネルの機能を果たすため、第2立坑72や第3立坑73が狭小空間であっても施工が可能になる。   Moreover, even if it is a case where sufficient site cannot be ensured for the 2nd vertical shaft 72 or the 3rd vertical shaft 73, several pipe roof 30A, 30B can be constructed | assembled. In short, since the reference tunnels 3A and 3B fulfill the function of a connection tunnel, construction is possible even if the second shaft 72 and the third shaft 73 are narrow spaces.

なお、この他の構成及び作用効果については、前記実施の形態と略同様であるため説明を省略する。   Other configurations and operational effects are substantially the same as those in the above-described embodiment, and thus description thereof is omitted.

以上、図面を参照して、本発明の実施の形態を詳述してきたが、具体的な構成は、この実施の形態及び実施例に限らず、本発明の要旨を逸脱しない程度の設計的変更は、本発明に含まれる。   The embodiment of the present invention has been described in detail above with reference to the drawings. However, the specific configuration is not limited to the embodiment and the example, and the design change is within a range not departing from the gist of the present invention. Are included in the present invention.

例えば、前記実施の形態及び実施例では、基準トンネル3,3A,3Bを拡縮掘進機5によって構築する場合について説明したが、これに限定されるものではなく、大径の汎用的な掘進機を使用して大径の大トンネルを構築し、その大径の掘進機については、到達立坑2内で分解して撤去するなどの方法を採用することもできる。   For example, in the said embodiment and Example, although the case where the reference | standard tunnels 3, 3A, 3B were constructed | assembled by the expansion / contraction excavation machine 5 was demonstrated, it is not limited to this, A large diameter general purpose excavation machine is used. It is also possible to construct a large-diameter large tunnel by using it, and for the large-diameter excavator, it is possible to adopt a method such as disassembling and removing within the reach shaft 2.

また、前記実施の形態では、基準トンネル3と一般トンネル4A−4Jとがすべて連結されるパイプルーフ30を例に説明したが、これに限定されるものではなく、大トンネルと小トンネルが間隔を置いて埋設されるパイプルーフを構築する場合にも、本発明を適用することができる。   In the above embodiment, the pipe roof 30 in which the reference tunnel 3 and the general tunnel 4A-4J are all connected has been described as an example. However, the present invention is not limited to this, and the large tunnel and the small tunnel are spaced apart from each other. The present invention can also be applied to the construction of a pipe roof that is laid and buried.

さらに、前記実施例では、第2立坑72と第3立坑とを接続するパイプルーフ30Bを構築する場合について説明したが、これに限定されるものではなく、第1の地中空間と第3の地中空間との間をパイプルーフで接続させる場合にも、本発明を適用することができる。   Furthermore, although the said Example demonstrated the case where the pipe roof 30B which connects the 2nd vertical shaft 72 and the 3rd vertical shaft was constructed, it is not limited to this, The 1st underground space and 3rd The present invention can also be applied when connecting the underground space with a pipe roof.

また、前記実施例では、3つの地中空間(71,72,73)を2つのパイプルーフ30A,30Bによってそれぞれ接続する場合について説明したが、これに限定されるものではなく、4つ以上の地中空間の間をパイプルーフでそれぞれ接続させる場合にも、本発明を適用することができる。   Moreover, although the said Example demonstrated the case where three underground space (71, 72, 73) was connected by two pipe roof 30A, 30B, respectively, it is not limited to this, Four or more The present invention can also be applied when connecting underground spaces with pipe roofs.

1 発進立坑(第1の地中空間)
2 到達立坑(第2の地中空間)
30 パイプルーフ
3 基準トンネル(大トンネル)
4A−4J 一般トンネル(小トンネル)
5 拡縮掘進機
51 カッタヘッド(カッタ部)
6 一般掘進機(小掘進機)
71 第1立坑(第1の地中空間)
72 第2立坑(第2の地中空間)
73 第3立坑(第3の地中空間)
30A,30B パイプルーフ
3A,3B 基準トンネル(大トンネル)
4 一般トンネル(小トンネル)
1 Start shaft (first underground space)
2 Reaching shaft (second underground space)
30 Pipe roof 3 Standard tunnel (large tunnel)
4A-4J General tunnel (small tunnel)
5 Expansion / Reduction Machine 51 Cutter Head (Cutter)
6 General excavator (small excavator)
71 First shaft (first underground space)
72 Second shaft (second underground space)
73 3rd shaft (third underground space)
30A, 30B Pipe roof 3A, 3B Standard tunnel (large tunnel)
4 General tunnel (small tunnel)

Claims (4)

地中に設けられた複数の地中空間をパイプルーフで接続させるパイプルーフの施工方法であって、
第1の地中空間から第2の地中空間に向けて大径の大トンネルを構築する工程と、
前記大トンネルの内空を通過可能な大きさの小径の小掘進機を使用して前記第1の地中空間から前記第2の地中空間に向けて小径の小トンネルを構築する工程と、
前記第2の地中空間に到達した前記小掘進機を前記大トンネルに通して前記第1の地中空間に引き戻す工程とを備え、
前記第1の地中空間に戻された前記小掘進機により、前記第1の地中空間から前記第2の地中空間に向けて別の小径の小トンネルを構築するとともに、前記大トンネルに通して前記第1の地中空間側に引き戻す工程を、必要な数だけ繰り返すことを特徴とするパイプルーフの施工方法。
A pipe roof construction method for connecting a plurality of underground spaces provided in the ground with a pipe roof,
Constructing a large tunnel with a large diameter from the first underground space to the second hollow space;
Constructing a small-diameter small tunnel from the first underground space to the second underground hollow using a small-diameter small-diameter machine capable of passing through the inside of the large tunnel;
A step of pulling the small excavator that has reached between the second hollows through the large tunnel and pulling back between the first hollows,
With the small excavator returned between the first underground hollows, another small-diameter small tunnel is constructed from the first underground space to the second underground hollow, and the large tunnel is A method for constructing a pipe roof, characterized in that the step of pulling back to the first underground space side is repeated as many times as necessary.
前記第2の地中空間は、前記第1の地中空間よりも狭い狭小空間であることを特徴とする請求項1に記載のパイプルーフの施工方法。   The pipe roof construction method according to claim 1, wherein the second underground space is a narrow space narrower than the first underground space. 前記大トンネルは、前面のカッタ部が縮径可能な拡縮掘進機によって構築され、前記拡縮掘進機は前記大トンネルに通して前記第1の地中空間に引き戻されることを特徴とする請求項1又は2に記載のパイプルーフの施工方法。   The large tunnel is constructed by an expansion / contraction machine capable of reducing the diameter of a front cutter, and the expansion / contraction machine is pulled back through the large tunnel between the first hollows. Or the construction method of the pipe roof of 2. 前記第1の地中空間又は前記第2の地中空間から第3の地中空間に向けて、前記小掘進機が通過可能な大径の大トンネルを構築する工程と、
前記第1の地中空間又は前記第2の地中空間から前記第3の地中空間に向けて前記小掘進機によって小トンネルを構築する工程と、
前記第3の地中空間に到達した前記小掘進機を前記大トンネルに通して前記第1の地中空間又は前記第2の地中空間に引き戻す工程とを備えたことを特徴とする請求項1乃至3のいずれか一項に記載のパイプルーフの施工方法。
Constructing a large-diameter large tunnel through which the small digging machine can pass from the first underground space or the second underground space to a third underground hollow;
Constructing a small tunnel by the small excavator from the first underground space or the second underground space to the space between the third underground hollows;
The step of pulling the small digging machine that has reached between the third underground hollows through the large tunnel and pulling back between the first underground space or the second underground hollows is provided. The pipe roof construction method according to any one of claims 1 to 3.
JP2016215361A 2016-11-02 2016-11-02 Pipe roof construction method Active JP6715164B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016215361A JP6715164B2 (en) 2016-11-02 2016-11-02 Pipe roof construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016215361A JP6715164B2 (en) 2016-11-02 2016-11-02 Pipe roof construction method

Publications (2)

Publication Number Publication Date
JP2018071287A true JP2018071287A (en) 2018-05-10
JP6715164B2 JP6715164B2 (en) 2020-07-01

Family

ID=62111530

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016215361A Active JP6715164B2 (en) 2016-11-02 2016-11-02 Pipe roof construction method

Country Status (1)

Country Link
JP (1) JP6715164B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110067561A (en) * 2019-04-26 2019-07-30 中铁二十三局集团有限公司 Under wear both wired Urban Underground mining sectbn construction methods

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110067561A (en) * 2019-04-26 2019-07-30 中铁二十三局集团有限公司 Under wear both wired Urban Underground mining sectbn construction methods

Also Published As

Publication number Publication date
JP6715164B2 (en) 2020-07-01

Similar Documents

Publication Publication Date Title
JP6289045B2 (en) How to build a shield tunnel
JP4317843B2 (en) Construction method for underground structures
CN105421463B (en) Longitudinal excavation construction method of long-span dense-support super-long deep foundation pit
JP2010090608A (en) Method for constructing underground space and structure of the underground space
JP2020007728A (en) Connecting structure, pile-type structure, and removal method of pile-type structure
JP2008223397A (en) Construction method for underground structure
JP6715164B2 (en) Pipe roof construction method
KR20090011442A (en) Tunnel boring method using sheet pile and tunnel structure therof
JP7177233B2 (en) Start Reaction Force Structure and Method for Concrete Box or Open Shield Machine
JP7357517B2 (en) Pipe construction method using propulsion method
JP5885229B2 (en) Reaction force device
JP6510432B2 (en) Construction method of underground structure
JP2005120652A (en) Underground tunnel structure and method of constructing the same
JP2011063957A (en) Method for removing upper portion of pile
JP5136344B2 (en) Construction method of rectangular tunnel and rectangular tunnel
JP6510690B1 (en) Construction method of underground structure
CN102535515A (en) Supporting device and supporting method for working well
KR101620787B1 (en) underground excavation construction method
JP5394454B2 (en) Open shield method
JP7088818B2 (en) Installation method of rectangular propulsion pipe and manufacturing method of underground structure equipped with rectangular propulsion pipe
JP4944754B2 (en) Propulsion box, propulsion method and construction method of large section tunnel
JP5999792B2 (en) Construction method of reaction force device
JP5158631B2 (en) Construction method of tunnel junction
JP2787367B2 (en) Construction method of large-scale underground space by honeycomb shield method
KR20090117095A (en) Excavator and construction method for underground structure using the same

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20190805

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20200520

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20200602

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20200608

R150 Certificate of patent or registration of utility model

Ref document number: 6715164

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250