JP2017117247A - Project management device and project management method - Google Patents

Project management device and project management method Download PDF

Info

Publication number
JP2017117247A
JP2017117247A JP2015252792A JP2015252792A JP2017117247A JP 2017117247 A JP2017117247 A JP 2017117247A JP 2015252792 A JP2015252792 A JP 2015252792A JP 2015252792 A JP2015252792 A JP 2015252792A JP 2017117247 A JP2017117247 A JP 2017117247A
Authority
JP
Japan
Prior art keywords
plan
task
days
change
date
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2015252792A
Other languages
Japanese (ja)
Inventor
坂本 英治
Eiji Sakamoto
英治 坂本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Corp
Original Assignee
Mitsubishi Electric Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Corp filed Critical Mitsubishi Electric Corp
Priority to JP2015252792A priority Critical patent/JP2017117247A/en
Publication of JP2017117247A publication Critical patent/JP2017117247A/en
Pending legal-status Critical Current

Links

Images

Abstract

PROBLEM TO BE SOLVED: To provide a project management device and a project management method with which it is possible to precisely grasp the progress of a task.SOLUTION: A project management device according to the present invention comprises: a plan input unit 2 for accepting input of the plan start day and plan completion day of a task; a progress input unit 3 for accepting input of a progress rate indicating the progress of the task; a lead lag calculation unit 5 for calculating a lead lag in days indicating a lead or lag of the task in days, as referenced to the current date, on the basis of the plan start day and plan completion day, the progress rate, and the current date; a plan change detection unit 6 for detecting a change of the plan completion day, and calculating a plan completion change in days that indicates a difference in days between a changed plan completion day and the plan completion day before the change; and a display control unit 7 for exercising control so that at least a lead or lag in days is displayed. When the plan change detection unit 6 detects a change of the plan completion day, the display control unit 7 exercises control so that at least a lead or lag in days and a plan completion change in days are displayed.SELECTED DRAWING: Figure 1

Description

本発明は、少なくとも1つのタスクを含むプロジェクトを管理するプロジェクト管理装置およびプロジェクト管理方法に関する。   The present invention relates to a project management apparatus and a project management method for managing a project including at least one task.

従来、プロジェクトのタスクの進捗状況を表示する手段として、左から右方向に時間軸を表示し、計画開始日から計画完了日までの予定期間を線分で表示し、予定期間の線分の長さを100%として進捗した割合の長さだけ予定期間の線分の左端から異なった太さに変えて表示し、タスクの作業の進み遅れを図形の形または色で表示する技術が開示されている(例えば、特許文献1参照)。   Conventionally, as a means of displaying the progress of project tasks, the time axis is displayed from left to right, the planned period from the plan start date to the plan completion date is displayed as a line, and the length of the line in the planned period is displayed. Disclosed is a technology for displaying the progress and delay of a task work in the shape or color of a figure by changing the thickness from the left end of the scheduled period to a different thickness by the length of the progress rate with 100% as the progress rate (For example, refer to Patent Document 1).

特開2002−7654号公報JP 2002-7654 A

一般的に、例えば、タスクの作業が遅れている場合は、タスクの作業を行う担当者がタスクの計画を変更する(具体的には、タスクの計画完了日を延長する)。また、プロジェクトの管理者が、プロジェクト全体の管理を行っている。   In general, for example, when task work is delayed, a person in charge of the task changes the task plan (specifically, the task plan completion date is extended). The project manager manages the entire project.

特許文献1では、タスクの計画が変更された場合において、変更後の計画についてタスクの作業の進み遅れが表示される。この場合、プロジェクトの管理者は、実際には当初の計画からタスクの作業が遅れているにもかかわらず、あたかもタスクの作業が順調に行われているかのように見える。このように、プロジェクトの管理者は、タスクの進捗状況を的確に把握することができているとはいえなかった。   In Patent Document 1, when the task plan is changed, the progress of the task work is displayed for the changed plan. In this case, the manager of the project looks as if the task work is proceeding smoothly even though the task work is actually delayed from the original plan. Thus, it cannot be said that the project manager was able to accurately grasp the progress of the task.

本発明は、このような問題を解決するためになされたものであり、タスクの進捗状況を的確に把握することが可能なプロジェクト管理装置およびプロジェクト管理方法を提供することを目的とする。   The present invention has been made to solve such problems, and an object of the present invention is to provide a project management apparatus and a project management method capable of accurately grasping the progress of a task.

上記の課題を解決するために、本発明によるプロジェクト管理装置は、少なくとも1つのタスクを含むプロジェクトを管理するプロジェクト管理装置であって、タスクの計画開始日および計画完了日の入力を受け付ける計画入力部と、タスクの進捗を示す進捗率の入力を受け付ける進捗入力部と、計画開始日、計画完了日、進捗率、および現在の日付に基づいて、現在の日付を基準としたタスクの進みまたは遅れの日数を示す進み遅れ日数を算出する進み遅れ算出部と、計画完了日の変更を検出し、変更前の計画完了日と変更後の計画完了日との差の日数を示す計画完了変更日数を算出する計画変更検出部と、少なくとも進み遅れ日数を表示するよう制御する表示制御部とを備え、計画変更検出部が計画完了日の変更を検出した場合において、表示制御部は、少なくとも進み遅れ日数および計画完了変更日数を表示するよう制御する。   In order to solve the above problems, a project management apparatus according to the present invention is a project management apparatus for managing a project including at least one task, and receives a plan start date and a plan completion date of the task. And a progress input part that accepts the input of the progress rate indicating the progress of the task, and the progress or delay of the task based on the current date based on the plan start date, the plan completion date, the progress rate, and the current date The advance / delay calculation unit that calculates the advance / delay days indicating the number of days, and the change of the plan completion date are detected, and the plan completion change days indicating the difference between the plan completion date before the change and the plan completion date after the change are calculated In the case where the plan change detection unit detects a change in the plan completion date, and a display control unit that controls to display at least the advance / delay days. Display control unit controls to display at least a lead-lag days and Planning complete change days.

また、本発明によるプロジェクト管理方法は、少なくとも1つのタスクを含むプロジェクトを管理するプロジェクト管理方法であって、(a)タスクの計画開始日および計画完了日の入力を受け付ける工程と、(b)タスクの進捗を示す進捗率の入力を受け付ける工程と、(c)計画開始日、計画完了日、進捗率、および現在の日付に基づいて、現在の日付を基準としたタスクの進みまたは遅れの日数を示す進み遅れ日数を算出する工程と、(d)計画完了日の変更を検出し、変更前の計画完了日と変更後の計画完了日との差の日数を示す計画完了変更日数を算出する工程と、(e)少なくとも進み遅れ日数を表示するよう制御する工程とを備え、工程(d)で計画完了日の変更を検出した場合において、工程(e)は、少なくとも進み遅れ日数および計画完了変更日数を表示するよう制御する。   In addition, a project management method according to the present invention is a project management method for managing a project including at least one task, wherein (a) receiving a plan start date and a plan completion date of the task; A step of accepting an input of a progress rate indicating the progress of the task, and (c) the number of days of progress or delay of the task based on the current date based on the plan start date, the plan completion date, the progress rate, and the current date A step of calculating the advance / delay days shown, and (d) a step of detecting a change in the plan completion date and calculating a plan completion change day indicating the difference between the plan completion date before the change and the plan completion date after the change. And (e) a step of controlling to display at least the number of advance / delay days, and when the change of the planned completion date is detected in step (d), the step (e) is at least the advance / delay Control so as to display the number and plan completion change the number of days.

本発明によると、プロジェクト管理装置は、少なくとも1つのタスクを含むプロジェクトを管理するプロジェクト管理装置であって、タスクの計画開始日および計画完了日の入力を受け付ける計画入力部と、タスクの進捗を示す進捗率の入力を受け付ける進捗入力部と、計画開始日、計画完了日、進捗率、および現在の日付に基づいて、現在の日付を基準としたタスクの進みまたは遅れの日数を示す進み遅れ日数を算出する進み遅れ算出部と、計画完了日の変更を検出し、変更前の計画完了日と変更後の計画完了日との差の日数を示す計画完了変更日数を算出する計画変更検出部と、少なくとも進み遅れ日数を表示するよう制御する表示制御部とを備え、計画変更検出部が計画完了日の変更を検出した場合において、表示制御部は、少なくとも進み遅れ日数および計画完了変更日数を表示するよう制御するため、タスクの進捗状況を的確に把握することが可能となる。   According to the present invention, the project management apparatus is a project management apparatus that manages a project including at least one task, and displays a plan input unit that receives input of a plan start date and a plan completion date of the task, and indicates the progress of the task. Progress input part that accepts input of progress rate, and advance / delay days indicating the number of days of progress or delay of the task based on the current date based on the plan start date, plan completion date, progress rate, and current date An advance / delay calculation unit for calculating, a plan change detection unit for detecting a change in the plan completion date, and calculating a plan completion change day indicating a difference between the plan completion date before the change and the plan completion date after the change, A display control unit that controls to display at least the advance / delay days, and when the plan change detection unit detects a change in the plan completion date, the display control unit is at least In order to control so as to display the lead-lag days and plan completion change the number of days, it is possible to accurately grasp the progress of the task.

また、プロジェクト管理方法は、少なくとも1つのタスクを含むプロジェクトを管理するプロジェクト管理方法であって、(a)タスクの計画開始日および計画完了日の入力を受け付ける工程と、(b)タスクの進捗を示す進捗率の入力を受け付ける工程と、(c)計画開始日、計画完了日、進捗率、および現在の日付に基づいて、現在の日付を基準としたタスクの進みまたは遅れの日数を示す進み遅れ日数を算出する工程と、(d)計画完了日の変更を検出し、変更前の計画完了日と変更後の計画完了日との差の日数を示す計画完了変更日数を算出する工程と、(e)少なくとも進み遅れ日数を表示するよう制御する工程とを備え、工程(d)で計画完了日の変更を検出した場合において、工程(e)は、少なくとも進み遅れ日数および計画完了変更日数を表示するよう制御するため、タスクの進捗状況を的確に把握することが可能となる。   The project management method is a project management method for managing a project including at least one task, wherein (a) receiving a plan start date and plan completion date of the task, and (b) progress of the task. A step of accepting an input of the progress rate shown, and (c) an advance / delay indicating the number of days of progress or delay of the task based on the current date based on the plan start date, the plan completion date, the progress rate, and the current date A step of calculating the number of days, (d) a step of detecting a change in the plan completion date and calculating a plan completion change day indicating the number of days between the plan completion date before the change and the plan completion date after the change; e) at least a step of controlling to display the advance / delay days, and when the change of the planned completion date is detected in the step (d), the step (e) includes at least the advance / delay days and the total In order to control so as to display a complete change of days, it is possible to accurately grasp the progress of the task.

本発明の実施の形態1によるプロジェクト管理装置の構成の一例を示すブロック図である。It is a block diagram which shows an example of a structure of the project management apparatus by Embodiment 1 of this invention. 本発明の実施の形態1によるタスク計画データベースに記録される情報の一例を示す図である。It is a figure which shows an example of the information recorded on the task plan database by Embodiment 1 of this invention. 本発明の実施の形態1によるプロジェクト管理装置のハードウェア構成の一例を示す図である。It is a figure which shows an example of the hardware constitutions of the project management apparatus by Embodiment 1 of this invention. 本発明の実施の形態1によるプロジェクト管理装置の動作の一例を示すフローチャートである。It is a flowchart which shows an example of operation | movement of the project management apparatus by Embodiment 1 of this invention. 本発明の実施の形態1によるタスクの進捗状況の表示の一例を示す図である。It is a figure which shows an example of the display of the progress status of the task by Embodiment 1 of this invention. 本発明の実施の形態1によるタスクの進捗状況の表示の一例を示す図である。It is a figure which shows an example of the display of the progress status of the task by Embodiment 1 of this invention. 本発明の実施の形態2によるタスク計画データベースに記録される情報の一例を示す図である。It is a figure which shows an example of the information recorded on the task plan database by Embodiment 2 of this invention. 本発明の実施の形態2によるタスクの進捗状況の表示の一例を示す図である。It is a figure which shows an example of the display of the progress status of the task by Embodiment 2 of this invention. 本発明の実施の形態3によるタスク計画データベースに記録される情報の一例を示す図である。It is a figure which shows an example of the information recorded on the task plan database by Embodiment 3 of this invention. 本発明の実施の形態3によるタスクの進捗状況の表示の一例を示す図である。It is a figure which shows an example of the display of the progress status of the task by Embodiment 3 of this invention. 本発明の実施の形態によるプロジェクト管理システムの構成の一例を示すブロック図である。It is a block diagram which shows an example of a structure of the project management system by embodiment of this invention.

本発明の実施の形態について、図面に基づいて以下に説明する。   Embodiments of the present invention will be described below with reference to the drawings.

<実施の形態1>
<構成>
図1は、本発明の実施の形態1によるプロジェクト管理装置1の構成の一例を示すブロック図である。
<Embodiment 1>
<Configuration>
FIG. 1 is a block diagram showing an example of the configuration of a project management apparatus 1 according to Embodiment 1 of the present invention.

図1に示すように、プロジェクト管理装置1は、計画入力部2と、進捗入力部3と、計画完了日変更入力部4と、進み遅れ算出部5と、計画変更検出部6と、表示制御部7とを備えている。   As shown in FIG. 1, the project management device 1 includes a plan input unit 2, a progress input unit 3, a plan completion date change input unit 4, an advance / delay calculation unit 5, a plan change detection unit 6, and display control. Part 7.

計画入力部2は、入力装置9で入力されたタスクの計画開始日および計画完了日を受け付ける。具体的には、ユーザ(例えば、タスクの担当者)は、入力装置9を用いてタスクの計画開始日および計画完了日を入力する。ここで、入力装置9としては、例えばタッチパネル、ハードウェアキーなどが挙げられる。計画入力部2が受け付けた計画開始日および計画完了日は、タスク計画データベース8に記録される。   The plan input unit 2 receives the plan start date and the plan completion date of the task input by the input device 9. Specifically, the user (for example, the person in charge of the task) inputs the planned start date and the planned completion date of the task using the input device 9. Here, examples of the input device 9 include a touch panel and hardware keys. The plan start date and the plan completion date received by the plan input unit 2 are recorded in the task plan database 8.

進捗入力部3は、入力装置9で入力されたタスクの進捗を示す進捗率を受け付ける。具体的には、ユーザは、入力装置9を用いてタスクの進捗率を入力する。ここで、進捗率とは、タスクの全作業に対する現在の進捗の割合のことをいう。進捗入力部3が受け付けた進捗率は、タスク計画データベース8に記録される。   The progress input unit 3 receives a progress rate indicating the progress of the task input by the input device 9. Specifically, the user inputs the task progress rate using the input device 9. Here, the progress rate refers to the ratio of the current progress with respect to all tasks. The progress rate received by the progress input unit 3 is recorded in the task plan database 8.

計画完了日変更入力部4は、入力装置9で入力された変更後の計画完了日を受け付ける。具体的には、ユーザは、入力装置9を用いて変更後の計画完了日を入力する。なお、計画完了日変更入力部4が変更後の計画完了日を受け付ける場合は、予め計画入力部2が計画完了日を受け付けていること(すなわち、計画入力部2で受け付けた計画完了日が、予めタスク計画データベース8に記録されていること)が前提となる。   The plan completion date change input unit 4 receives the changed plan completion date input by the input device 9. Specifically, the user inputs the changed plan completion date using the input device 9. In addition, when the plan completion date change input part 4 receives the plan completion date after a change, the plan completion part 2 has received the plan completion date beforehand (that is, the plan completion date received in the plan input part 2 is It is presupposed that it is recorded in the task plan database 8 in advance.

進み遅れ算出部5は、タスク計画データベース8に記録された計画開始日、計画完了日、および進捗率と、現在の日付とに基づいて、タスクの作業を行う期間、進捗率に相当する日付、および現在の日付を基準としたタスクの進みまたは遅れの日数を示す進み遅れ日数を算出する。進み遅れ算出部5が算出した期間、進捗率に相当する日付、および進み遅れ日数は、タスク計画データベース8に記録される。   The advance / delay calculation unit 5 performs a task operation based on the plan start date, the plan completion date, the progress rate, and the current date recorded in the task plan database 8, a date corresponding to the progress rate, And the advance / delay days indicating the days of progress or delay of the task based on the current date is calculated. The period calculated by the advance / delay calculation unit 5, the date corresponding to the progress rate, and the advance / delay days are recorded in the task plan database 8.

計画変更検出部6は、計画完了日の変更を検出し、変更前の計画完了日と変更後の計画完了日との差の日数を示す計画完了日の変更日数(計画完了変更日数)を算出する。具体的には、計画変更検出部6は、タスク計画データベース8に記録された計画完了日(変更前の計画完了日)と、計画完了日変更入力部4で受け付けられた計画完了日(変更後の計画完了日)との差の日数を算出する。計画変更検出部6が算出した計画完了日の変更日数は、タスク計画データベース8に記録される。   The plan change detection unit 6 detects the change of the plan completion date, and calculates the change date of the plan completion date (plan completion change day) indicating the number of days between the plan completion date before the change and the plan completion date after the change. To do. Specifically, the plan change detection unit 6 includes the plan completion date (plan completion date before the change) recorded in the task plan database 8 and the plan completion date received by the plan completion date change input unit 4 (after the change). The number of days of difference from the planned completion date) is calculated. The number of days of change of the plan completion date calculated by the plan change detection unit 6 is recorded in the task plan database 8.

表示制御部7は、少なくとも進み遅れ算出部5で算出された進み遅れ日数を表示装置10に表示するよう制御する。また、表示制御部7は、計画変更検出部6が計画完了日の変更を検出した場合において、計画完了日の変更日数も表示装置10に表示するよう制御する。ここで、表示装置10としては、例えば液晶表示装置などが挙げられる。なお、入力装置9および表示装置10は、タッチパネルを備える液晶表示装置など、一体に形成されてもよい。   The display control unit 7 performs control so that at least the advance / delay days calculated by the advance / delay calculation unit 5 are displayed on the display device 10. In addition, when the plan change detection unit 6 detects a change in the plan completion date, the display control unit 7 controls the display device 10 to display the number of days for the change in the plan completion date. Here, examples of the display device 10 include a liquid crystal display device. The input device 9 and the display device 10 may be integrally formed, such as a liquid crystal display device having a touch panel.

タスク計画データベース8は、図2に示すように、各タスク(図2の例では、タスクA,B)について、計画開始日、計画完了日、期間、進捗率、進捗率に相当する日付、進み遅れ日数、および計画完了日の変更日数を記録する。タスク計画データベース8は、例えばハードディスクまたは半導体メモリ等の記憶装置から構成されている。なお、図1では、タスク計画データベース8は、プロジェクト管理装置1の外部に備えられているが、プロジェクト管理装置1の内部に備えてもよい。   As shown in FIG. 2, the task plan database 8 has a plan start date, a plan completion date, a period, a progress rate, and a date corresponding to the progress rate for each task (tasks A and B in the example of FIG. 2). Record the number of days late and the number of days to change the plan completion date. The task plan database 8 includes a storage device such as a hard disk or a semiconductor memory. In FIG. 1, the task plan database 8 is provided outside the project management apparatus 1, but may be provided inside the project management apparatus 1.

図3は、プロジェクト管理装置1のハードウェア構成の一例を示すブロック図である。   FIG. 3 is a block diagram illustrating an example of a hardware configuration of the project management apparatus 1.

プロジェクト管理装置1における計画入力部2、進捗入力部3、計画完了日変更入力部4、進み遅れ算出部5、計画変更検出部6、および表示制御部7の各機能は、処理回路により実現される。すなわち、プロジェクト管理装置1は、計画開始日および計画完了日の入力を受け付け、進捗率の入力を受け付け、変更後の計画完了日を受け付け、期間、進捗率に相当する日付、および進み遅れ日数を算出し、計画完了日の変更日数を算出し、期間、進捗率に相当する日付、進み遅れ日数、および計画完了日の変更日数を表示するよう制御するための処理回路を備える。処理回路は、メモリ12に格納されるプログラムを実行するプロセッサ11(中央処理装置、処理装置、演算装置、マイクロプロセッサ、マイクロコンピュータ、DSP(Digital Signal Processor)ともいう)である。   The functions of the plan input unit 2, the progress input unit 3, the plan completion date change input unit 4, the advance / delay calculation unit 5, the plan change detection unit 6, and the display control unit 7 in the project management apparatus 1 are realized by a processing circuit. The That is, the project management apparatus 1 accepts the input of the plan start date and the plan completion date, accepts the input of the progress rate, accepts the plan completion date after the change, determines the period, the date corresponding to the progress rate, and the advance delay days And a processing circuit for controlling to display the period, the date corresponding to the progress rate, the advance delay day, and the change date of the plan completion date. The processing circuit is a processor 11 (also called a central processing unit, processing unit, arithmetic unit, microprocessor, microcomputer, DSP (Digital Signal Processor)) that executes a program stored in the memory 12.

プロジェクト管理装置1における計画入力部2、進捗入力部3、計画完了日変更入力部4、進み遅れ算出部5、計画変更検出部6、および表示制御部7の各機能は、ソフトウェア、ファームウェア、またはソフトウェアとファームウェアとの組み合わせにより実現される。ソフトウェアまたはファームウェアは、プログラムとして記述され、メモリ12に格納される。処理回路は、メモリ12に記憶されたプログラムを読み出して実行することにより、各部の機能を実現する。すなわち、プロジェクト管理装置1は、計画開始日および計画完了日の入力を受け付けるステップ、進捗率の入力を受け付けるステップ、変更後の計画完了日を受け付けるステップ、期間、進捗率に相当する日付、および進み遅れ日数を算出するステップ、計画完了日の変更日数を算出するステップ、期間、進捗率に相当する日付、進み遅れ日数、および計画完了日の変更日数を表示するよう制御するステップが結果的に実行されることになるプログラムを格納するためのメモリ12を備える。また、これらのプログラムは、計画入力部2、進捗入力部3、計画完了日変更入力部4、進み遅れ算出部5、計画変更検出部6、および表示制御部7の手順または方法をコンピュータに実行させるものであるともいえる。ここで、メモリとは、例えば、RAM(Random Access Memory)、ROM(Read Only Memory)、フラッシュメモリ、EPROM(Erasable Programmable Read Only Memory)、EEPROM(Electrically Erasable Programmable Read Only Memory)等の不揮発性または揮発性の半導体メモリ、磁気ディスク、フレキシブルディスク、光ディスク、コンパクトディスク、ミニディスク、DVD(Digital Versatile Disk)等が該当する。   The functions of the plan input unit 2, the progress input unit 3, the plan completion date change input unit 4, the advance / delay calculation unit 5, the plan change detection unit 6, and the display control unit 7 in the project management apparatus 1 are software, firmware, or Realized by a combination of software and firmware. Software or firmware is described as a program and stored in the memory 12. The processing circuit reads out and executes the program stored in the memory 12, thereby realizing the function of each unit. That is, the project management apparatus 1 receives a plan start date and a plan completion date, a step for receiving a progress rate input, a step for receiving a changed plan completion date, a period, a date corresponding to the progress rate, and a progress As a result, the step of calculating the number of days delayed, the step of calculating the number of days to change the plan completion date, the period, the date corresponding to the progress rate, the number of days to advance and delay, and the step of controlling to display the number of days to change the plan completion date are executed. A memory 12 is provided for storing the program to be executed. In addition, these programs execute the procedure or method of the plan input unit 2, the progress input unit 3, the plan completion date change input unit 4, the advance / delay calculation unit 5, the plan change detection unit 6, and the display control unit 7 on a computer. It can be said that Here, the memory is, for example, non-volatile or volatile such as RAM (Random Access Memory), ROM (Read Only Memory), flash memory, EPROM (Erasable Programmable Read Only Memory), EEPROM (Electrically Erasable Programmable Read Only Memory), etc. This includes a semiconductor memory, a magnetic disk, a flexible disk, an optical disk, a compact disk, a mini disk, a DVD (Digital Versatile Disk), and the like.

<動作>
図4は、本実施の形態1によるプロジェクト管理装置1の動作の一例を示すフローチャートである。なお、以下では、図2に示す各情報がタスク計画データベース8に記録される場合を一例として説明する。
<Operation>
FIG. 4 is a flowchart showing an example of the operation of the project management apparatus 1 according to the first embodiment. Hereinafter, a case where each piece of information shown in FIG. 2 is recorded in the task plan database 8 will be described as an example.

ステップS1において、計画入力部2は、タスクの計画開始日および計画完了日の入力を受け付ける。例えば、タスクAの担当者は、入力装置9を用いて、計画開始日として「2015/10/8(2015年10月8日)」を入力し、計画完了日として「2015/10/30」を入力する。計画入力部2が受け付けた計画開始日および計画完了日は、タスク計画データベース8に記録される。   In step S <b> 1, the plan input unit 2 receives input of a task plan start date and a plan completion date. For example, the person in charge of task A uses the input device 9 to input “2015/10/8 (October 8, 2015)” as the plan start date and “2015/10/30” as the plan completion date. Enter. The plan start date and the plan completion date received by the plan input unit 2 are recorded in the task plan database 8.

ステップS2において、進捗入力部3は、進捗率の入力を受け付ける。例えば、タスクAの担当者は、入力装置9を用いて、進捗率として「40%」を入力する。進捗入力部3が受け付けた進捗率は、タスク計画データベース8に記録される。   In step S2, the progress input unit 3 receives an input of the progress rate. For example, the person in charge of task A uses the input device 9 to input “40%” as the progress rate. The progress rate received by the progress input unit 3 is recorded in the task plan database 8.

ステップS3において、計画変更検出部6は、計画が変更されたか否かを判断する。具体的には、計画変更検出部6は、計画完了日変更入力部4が変更後の計画完了日の入力を受け付けた場合は、計画が変更されたと判断する。   In step S3, the plan change detection unit 6 determines whether or not the plan has been changed. Specifically, the plan change detection unit 6 determines that the plan has been changed when the plan completion date change input unit 4 receives an input of the changed plan completion date.

ステップS4において、進み遅れ算出部5は、タスク計画データベース8に記録された計画開始日および計画完了日に基づいて、タスクの作業を行う期間を算出する。具体的には、進み遅れ算出部5は、下記の式(1)に基づいて期間を算出する。
期間=計画完了日−計画開始日 ・・・(1)
In step S <b> 4, the advance / delay calculation unit 5 calculates a period during which the task is performed based on the plan start date and the plan completion date recorded in the task plan database 8. Specifically, the advance / delay calculation unit 5 calculates a period based on the following equation (1).
Period = Plan completion date-Plan start date (1)

なお、式(1)において、期間は休日を除く実働日数で算出されている。式(1)により、例えば、タスクAの期間は「16日」となる。進み遅れ算出部5が算出した期間は、タスク計画データベース8に記録される。また、進み遅れ算出部5がタスク計画データベース8から取得した計画開始日および計画完了日は、表示制御部7に出力される。   In the formula (1), the period is calculated by the actual working days excluding holidays. From the formula (1), for example, the period of the task A is “16 days”. The period calculated by the advance / delay calculation unit 5 is recorded in the task plan database 8. Further, the plan start date and the plan completion date acquired by the advance / delay calculation unit 5 from the task plan database 8 are output to the display control unit 7.

ステップS5において、進み遅れ算出部5は、進捗率に相当する日付を算出する。具体的には、進み遅れ算出部5は、下記の式(2)に基づいて進捗率に相当する日付を算出する。
進捗率に相当する日付=計画開始日+期間×進捗率 ・・・(2)
In step S5, the advance / delay calculation unit 5 calculates a date corresponding to the progress rate. Specifically, the advance / delay calculation unit 5 calculates a date corresponding to the progress rate based on the following equation (2).
Date corresponding to progress rate = plan start date + period x progress rate (2)

式(2)により、例えば、タスクAの進捗率に相当する日付は「2015/10/16」となる。進み遅れ算出部5が算出した進捗率に相当する日付は、タスク計画データベース8に記録されるとともに、表示制御部7に出力される。また、進み遅れ算出部5がタスク計画データベース8から取得した進捗率も表示制御部7に出力される。   From the formula (2), for example, the date corresponding to the progress rate of task A is “2015/10/16”. The date corresponding to the progress rate calculated by the advance / delay calculation unit 5 is recorded in the task plan database 8 and output to the display control unit 7. The progress rate acquired by the advance / delay calculation unit 5 from the task plan database 8 is also output to the display control unit 7.

ステップS6において、進み遅れ算出部5は、進み遅れ日数を算出する。具体的には、進み遅れ算出部5は、下記の式(3)に基づいて進み遅れ日数を算出する。
進み遅れ日数=現在の日付−進捗率に相当する日付 ・・・(3)
In step S6, the advance / delay calculation unit 5 calculates the advance / delay days. Specifically, the advance / delay calculation unit 5 calculates the advance / delay days based on the following equation (3).
Advance / Delay Days = Current Date-Date Corresponding to Progress Rate (3)

なお、式(3)において、進み遅れ日数は休日を除く実働日数で算出されている。また、進み遅れ日数が正の値の場合は「遅れ日数」となり、進み遅れ日数が負の値の場合は「進み日数」となる。式(3)により、例えば、タスクAの進み遅れ日数は「遅れ日数:2日」となる。進み遅れ算出部5が算出した進み遅れ日数は、タスク計画データベース8に記録されるとともに、表示制御部7に出力される。   In equation (3), the number of days delayed in advance is calculated as the number of working days excluding holidays. In addition, when the advance / delay days are positive, it becomes “delay days”, and when the advance / delay days is negative, it becomes “advance days”. From Formula (3), for example, the advance / delay days of task A are “delay days: 2 days”. The advance / delay days calculated by the advance / delay calculation unit 5 are recorded in the task plan database 8 and also output to the display control unit 7.

ステップS7において、表示制御部7は、計画開始日、計画完了日、進捗率に相当する日付、現在の日付、および進み遅れ日数を表示装置10に表示するよう制御する。   In step S <b> 7, the display control unit 7 controls the display device 10 to display the plan start date, the plan completion date, the date corresponding to the progress rate, the current date, and the advance delay days.

例えば、表示制御部7は、図5に示すようなタスクAの進捗状況を表示装置10に表示するよう制御する。図5の例では、タスクAの進捗が予定よりも2日遅れていることを示している。なお、図5において、進捗率に相当する日付に対応する箇所には、「進捗率40%」と表示されている。   For example, the display control unit 7 controls the display device 10 to display the progress status of the task A as shown in FIG. The example of FIG. 5 shows that the progress of task A is delayed by two days from the schedule. In FIG. 5, “progress rate 40%” is displayed at the location corresponding to the date corresponding to the progress rate.

ステップS8において、計画変更検出部6は、変更前の計画完了日と変更後の計画完了日との差の日数(計画完了日の変更日数)を算出する。なお、計画完了日の変更日数は、休日を除く実働日数で算出されている。計画変更検出部6が算出した計画完了日の変更日数は、タスク計画データベース8に記録されるとともに、表示制御部7に出力される。   In step S8, the plan change detecting unit 6 calculates the number of days (the number of days to change the plan completion date) between the plan completion date before the change and the plan completion date after the change. The number of days to change the planned completion date is calculated as the number of working days excluding holidays. The number of days of change of the plan completion date calculated by the plan change detection unit 6 is recorded in the task plan database 8 and output to the display control unit 7.

ステップS9において、進み遅れ算出部5は、上記の式(1)に基づいて、タスクの作業を行う期間を算出する。式(1)により、例えば、タスクBの期間は「26日」となる。進み遅れ算出部5が算出した期間は、タスク計画データベース8に記録される。また、進み遅れ算出部5がタスク計画データベース8から取得した計画開始日および計画完了日は、表示制御部7に出力される。   In step S <b> 9, the advance / delay calculation unit 5 calculates a period during which the task is performed based on the above formula (1). From the formula (1), for example, the period of the task B is “26 days”. The period calculated by the advance / delay calculation unit 5 is recorded in the task plan database 8. Further, the plan start date and the plan completion date acquired by the advance / delay calculation unit 5 from the task plan database 8 are output to the display control unit 7.

ステップS10において、進み遅れ算出部5は、上記の式(2)に基づいて、進捗率に相当する日付を算出する。式(2)により、例えば、タスクBの進捗率に相当する日付は「2015/10/22」となる。進み遅れ算出部5が算出した進捗率に相当する日付は、タスク計画データベース8に記録されるとともに、表示制御部7に出力される。また、進み遅れ算出部5がタスク計画データベース8から取得した進捗率も表示制御部7に出力される。   In step S10, the advance / delay calculation unit 5 calculates a date corresponding to the progress rate based on the above equation (2). From the formula (2), for example, the date corresponding to the progress rate of task B is “2015/10/22”. The date corresponding to the progress rate calculated by the advance / delay calculation unit 5 is recorded in the task plan database 8 and output to the display control unit 7. The progress rate acquired by the advance / delay calculation unit 5 from the task plan database 8 is also output to the display control unit 7.

ステップS11において、進み遅れ算出部5は、上記の式(3)に基づいて、進み遅れ日数を算出する。式(3)により、例えば、タスクBの進み遅れ日数は「進み日数:2日」となる。進み遅れ算出部5が算出した進み遅れ日数は、タスク計画データベース8に記録されるとともに、表示制御部7に出力される。   In step S11, the advance / delay calculation unit 5 calculates the advance / delay days based on the above equation (3). From equation (3), for example, the advance / delay days of task B are “advance days: 2 days”. The advance / delay days calculated by the advance / delay calculation unit 5 are recorded in the task plan database 8 and also output to the display control unit 7.

ステップS12において、表示制御部7は、計画開始日、計画完了日、進捗率に相当する日付、現在の日付、進み遅れ日数、および計画完了日の変更日数を表示装置10に表示するよう制御する。   In step S12, the display control unit 7 controls the display device 10 to display the plan start date, the plan completion date, the date corresponding to the progress rate, the current date, the advance delay date, and the plan completion date change date. .

例えば、表示制御部7は、図6に示すようなタスクBの進捗状況を表示装置10に表示するよう制御する。図6の例では、タスクBの計画完了日が10日延長され、タスクBの進捗が予定よりも2日進んでいることを示している。なお、図6において、進捗率に相当する日付に対応する箇所には、「進捗率40%」と表示されている。   For example, the display control unit 7 controls the display device 10 to display the progress status of the task B as shown in FIG. In the example of FIG. 6, the plan completion date of task B is extended by 10 days, and the progress of task B is two days ahead of the schedule. In FIG. 6, “progress rate 40%” is displayed at the location corresponding to the date corresponding to the progress rate.

なお、上記において、計画入力部2は、計画開始日および計画完了日を一度受け付ければ、再度受け付けないようにしてもよい。すなわち、一度ステップS1の処理を行えば、次回のステップS1の処理を省略してもよい。   In the above description, the plan input unit 2 may not accept again once the plan start date and the plan completion date are accepted. That is, once step S1 is performed, the next step S1 may be omitted.

上記では、タスクの進捗状況の表示例として図5,6を示したが、これに限るものではない。例えば、図2に示すような表を表示してもよい。   In the above, FIGS. 5 and 6 are shown as display examples of the progress status of the task, but the present invention is not limited to this. For example, a table as shown in FIG. 2 may be displayed.

上記において、期間、進み遅れ日数、および計画完了日の変更日数は、休日を除く実働日数で算出される場合について説明したが、これに限るものではない。例えば、期間、進み遅れ日数、および計画完了日の変更日数は、休日を含む日数で算出してもよい。   In the above description, the case where the period, the advance delay day, and the plan completion date change day are calculated using the actual work days excluding holidays, but is not limited thereto. For example, the period, the number of days delayed in advance, and the number of days for changing the planned completion date may be calculated as the number of days including holidays.

以上のことから、本実施の形態1によれば、タスクの計画を変更した場合(タスクの計画完了日を変更した場合)において、進み遅れ日数とともに計画完了日の変更日数を表示している。従って、プロジェクトの管理者は、タスクの進捗状況を的確に把握することが可能となる。   As described above, according to the first embodiment, when the task plan is changed (when the task completion date of the task is changed), the change days of the plan completion date are displayed together with the advance delay days. Therefore, the project manager can accurately grasp the progress of the task.

<実施の形態2>
本発明の実施の形態2では、少なくとも1つのタスクを担当するチーム(グループ)ごとに進捗状況を表示する場合について説明する。本実施の形態2によるプロジェクト管理装置の構成および動作については、実施の形態1と同様であるため、ここでは詳細な説明を省略する。なお、以下では、本実施の形態2によるプロジェクト管理装置は、図1に示すプロジェクト管理装置1であるものとして説明する。
<Embodiment 2>
In the second embodiment of the present invention, a case where the progress status is displayed for each team (group) in charge of at least one task will be described. Since the configuration and operation of the project management apparatus according to the second embodiment are the same as those of the first embodiment, detailed description thereof is omitted here. In the following description, it is assumed that the project management apparatus according to the second embodiment is the project management apparatus 1 shown in FIG.

図7は、本実施の形態2によるタスク計画データベース8に記録される情報の一例を示す図である。   FIG. 7 is a diagram showing an example of information recorded in the task plan database 8 according to the second embodiment.

図7に示すように、タスク計画データベース8には、各タスクを担当するチームが記録されている。図7の例では、チーム1はタスクA,B,Dを担当し、チーム2はタスクCを担当することを示している。   As shown in FIG. 7, the task plan database 8 records a team in charge of each task. In the example of FIG. 7, team 1 is responsible for tasks A, B, and D, and team 2 is responsible for task C.

図8は、タスクの進捗状況をグループごとに表示した場合の一例を示す図である。なお、図8のタスクA〜Dは、図7のタスクA〜Dに対応している。   FIG. 8 is a diagram illustrating an example of the task progress status displayed for each group. Note that tasks A to D in FIG. 8 correspond to tasks A to D in FIG. 7.

図8に示すように、チーム1が担当するタスクA,B,Dの進捗状況と、チーム2が担当するタスクCの進捗状況とが区別して表示されている。また、チーム1が担当するタスクA,B,Dの進捗状況は、まとめて表示されている。   As shown in FIG. 8, the progress status of tasks A, B, and D handled by team 1 and the progress status of task C handled by team 2 are displayed separately. In addition, the progress status of tasks A, B, and D handled by team 1 are displayed together.

なお、上記では、タスクの進捗状況の表示例として図8を示したが、これに限るものではない。例えば、図7に示すような表を表示してもよい。   In the above description, FIG. 8 is shown as an example of displaying the progress of the task, but the present invention is not limited to this. For example, a table as shown in FIG. 7 may be displayed.

図8において、チームごとに、進み遅れ日数の合計、および計画完了日数の合計を表示してもよい。また、図7において、チームごとに、進み遅れ日数の合計、および計画完了日数の合計を記録してもよい。   In FIG. 8, you may display the sum total of advance delay days and the plan completion days for every team. In FIG. 7, the total advance / delay days and the plan completion days may be recorded for each team.

上記では、チームごとにタスクの進捗状況を表示する場合について説明したが、これに限るものではない。例えば、担当者ごとにタスクの進捗状況を表示してもよい。   In the above description, the task progress status is displayed for each team. However, the present invention is not limited to this. For example, the progress of the task may be displayed for each person in charge.

上記において、期間、進み遅れ日数、および計画完了日の変更日数は、休日を除く実働日数で算出される場合について説明したが、これに限るものではない。例えば、期間、進み遅れ日数、および計画完了日の変更日数は、休日を含む日数で算出してもよい。   In the above description, the case where the period, the advance delay day, and the plan completion date change day are calculated using the actual work days excluding holidays, but is not limited thereto. For example, the period, the number of days delayed in advance, and the number of days for changing the planned completion date may be calculated as the number of days including holidays.

以上のことから、本実施の形態2によれば、チームごとにタスクの進捗状況を表示している。従って、プロジェクトの管理者は、チームごとのタスクの進捗状況を的確に把握することが可能となる。   From the above, according to the second embodiment, the progress of the task is displayed for each team. Therefore, the project manager can accurately grasp the progress of the task for each team.

<実施の形態3>
本発明の実施の形態3では、一のタスクの計画が変更された場合において、当該一のタスクに後続する他のタスクの計画も変更する場合について説明する。本実施の形態3によるプロジェクト管理装置の構成および動作については、実施の形態1と同様であるため、ここでは詳細な説明を省略する。なお、以下では、本実施の形態3によるプロジェクト管理装置は、図1に示すプロジェクト管理装置1であるものとして説明する。
<Embodiment 3>
In the third embodiment of the present invention, a case will be described in which when the plan of one task is changed, the plan of another task subsequent to the one task is also changed. Since the configuration and operation of the project management apparatus according to the third embodiment are the same as those of the first embodiment, detailed description thereof is omitted here. In the following description, it is assumed that the project management apparatus according to the third embodiment is the project management apparatus 1 shown in FIG.

図9は、本実施の形態3によるタスク計画データベース8に記録される情報の一例を示す図である。   FIG. 9 is a diagram showing an example of information recorded in the task plan database 8 according to the third embodiment.

図9に示すように、タスク計画データベース8には、後続タスクの情報が記録されている。図9の例では、タスクAの後続タスクは、タスクBであることを示している。   As shown in FIG. 9, the task plan database 8 records information on subsequent tasks. In the example of FIG. 9, the task subsequent to task A is task B.

図10は、タスクの進捗状況の表示の一例を示す図である。なお、図10の上段は計画が変更される前のタスクA,Bの進捗状況を示しており、図10の下段は計画が変更された後のタスクA,Bの進捗状況を示している。計画が変更された後のタスクA,Bは、図9のタスクA,Bに対応している。   FIG. 10 is a diagram illustrating an example of a task progress status display. 10 shows the progress of tasks A and B before the plan is changed, and the lower part of FIG. 10 shows the progress of tasks A and B after the plan is changed. Tasks A and B after the plan is changed correspond to tasks A and B in FIG.

図10に示すように、タスクAの計画完了日が変更されると、それに伴ってタスクBの計画開始日、計画完了日も変更される。そして、タスクAの進捗状況として「進み日数:1日」および「計画完了日の変更日数:4日」が表示されるとともに、タスクBの進捗状況として「進み日数:8日」および「計画完了日の変更日数:4日」が表示される。   As shown in FIG. 10, when the planned completion date of task A is changed, the planned start date and planned completion date of task B are also changed accordingly. As the progress status of task A, “advance days: 1 day” and “plan completion date change days: 4 days” are displayed, and as progress status of task B, “advance days: 8 days” and “plan completion” "Day change days: 4 days" is displayed.

なお、上記では、タスクの進捗状況の表示例として図10を示したが、これに限るものではない。例えば、図9に示すような表を表示してもよい。   In the above description, FIG. 10 is shown as a display example of the progress status of the task, but the present invention is not limited to this. For example, a table as shown in FIG. 9 may be displayed.

上記において、期間、進み遅れ日数、および計画完了日の変更日数は、休日を除く実働日数で算出される場合について説明したが、これに限るものではない。例えば、期間、進み遅れ日数、および計画完了日の変更日数は、休日を含む日数で算出してもよい。   In the above description, the case where the period, the advance delay day, and the plan completion date change day are calculated using the actual work days excluding holidays, but is not limited thereto. For example, the period, the number of days delayed in advance, and the number of days for changing the planned completion date may be calculated as the number of days including holidays.

以上のことから、本実施の形態3によれば、一のタスクの計画が変更された場合において、当該一のタスクに後続する他のタスクの計画も変更した上で、両方のタスクの進捗状況を表示している。従って、プロジェクトの管理者は、一のタスクの進捗状況とそれに後続する他のタスクの進捗状況とを的確に把握することが可能となる。   From the above, according to the third embodiment, when the plan of one task is changed, the progress status of both tasks is also changed after changing the plan of other tasks following the one task. Is displayed. Accordingly, the project manager can accurately grasp the progress of one task and the progress of other tasks following the task.

以上で説明したプロジェクト管理装置は、サーバなどを適宜に組み合わせてシステムとして構築される装置にも適用することができる。この場合、プロジェクト管理装置の各機能または各構成要素は、上記システムを構築する各機能に分散して配置される。   The project management apparatus described above can also be applied to an apparatus constructed as a system by appropriately combining servers and the like. In this case, each function or each component of the project management apparatus is distributed and arranged in each function for constructing the system.

具体的には、一例として、プロジェクト管理装置の機能をサーバに配置することができる。例えば、図11に示すように、ユーザ側に入力装置9および表示装置10を備え、サーバ13に計画入力部2、進捗入力部3、計画完了日変更入力部4、進み遅れ算出部5、計画変更検出部6、表示制御部7、およびタスク計画データベース8を備えることによって、プロジェクト管理システムを構築することができる。なお、サーバ13に備えられる各構成要素は、適宜にサーバ13、入力装置9、および表示装置10に分散して配置するようにしてもよい。タスク計画データベース8は、サーバ13の外部に設けてもよい。   Specifically, as an example, the function of the project management apparatus can be arranged on a server. For example, as shown in FIG. 11, the user side includes an input device 9 and a display device 10, and the server 13 includes a plan input unit 2, a progress input unit 3, a plan completion date change input unit 4, an advance / delay calculation unit 5, a plan By providing the change detection unit 6, the display control unit 7, and the task plan database 8, a project management system can be constructed. Each component provided in the server 13 may be appropriately distributed and arranged in the server 13, the input device 9, and the display device 10. The task plan database 8 may be provided outside the server 13.

上記の構成とした場合であっても、上記の実施の形態と同様の効果が得られる。   Even if it is a case where it is said structure, the effect similar to said embodiment is acquired.

また、上記の実施の形態における動作を実行するソフトウェア(プロジェクト管理方法)を、例えばサーバに組み込んでもよい。   Further, software (project management method) for executing the operation in the above-described embodiment may be incorporated in a server, for example.

具体的には、一例として、上記のプロジェクト管理方法は、少なくとも1つのタスクを含むプロジェクトを管理するプロジェクト管理方法であって、(a)タスクの計画開始日および計画完了日の入力を受け付ける工程と、(b)タスクの進捗を示す進捗率の入力を受け付ける工程と、(c)計画開始日、計画完了日、進捗率、および現在の日付に基づいて、現在の日付を基準としたタスクの進みまたは遅れの日数を示す進み遅れ日数を算出する工程と、(d)計画完了日の変更を検出し、変更前の計画完了日と変更後の計画完了日との差の日数を示す計画完了変更日数を算出する工程と、(e)少なくとも進み遅れ日数を表示するよう制御する工程とを備え、工程(d)で計画完了日の変更を検出した場合において、工程(e)は、少なくとも進み遅れ日数および計画完了変更日数を表示するよう制御する。   Specifically, as an example, the above-described project management method is a project management method for managing a project including at least one task, and (a) receiving an input of a plan start date and a plan completion date of the task; (B) accepting an input of a progress rate indicating the progress of the task, and (c) progress of the task based on the current date based on the plan start date, the plan completion date, the progress rate, and the current date. Or a step of calculating the advance / delay days indicating the days of delay, and (d) a plan completion change indicating the difference between the plan completion date before the change and the plan completion date after the change is detected. A step of calculating the number of days, and (e) a step of controlling to display at least the number of days of advance or delay. When a change in the planned completion date is detected in step (d), the number of steps (e) is small. Control so as to display the even lead-lag days and plan completion change the number of days.

上記より、上記の実施の形態における動作を実行するソフトウェアをサーバに組み込んで動作させることによって、上記の実施の形態と同様の効果が得られる。   As described above, the same effect as that of the above embodiment can be obtained by operating the software that executes the operation of the above embodiment in a server.

なお、本発明は、その発明の範囲内において、各実施の形態を自由に組み合わせたり、各実施の形態を適宜、変形、省略することが可能である。   It should be noted that the present invention can be freely combined with each other within the scope of the invention, and each embodiment can be appropriately modified or omitted.

1 プロジェクト管理装置、2 計画入力部、3 進捗入力部、4 計画完了日変更入力部、5 進み遅れ算出部、6 計画変更検出部、7 表示制御部、8 タスク計画データベース、9 入力装置、10 表示装置、11 プロセッサ、12 メモリ、13 サーバ。   DESCRIPTION OF SYMBOLS 1 Project management apparatus, 2 Plan input part, 3 Progress input part, 4 Plan completion date change input part, 5 Advance / lag calculation part, 6 Plan change detection part, 7 Display control part, 8 Task plan database, 9 Input device, 10 Display device, 11 processor, 12 memory, 13 server.

Claims (7)

少なくとも1つのタスクを含むプロジェクトを管理するプロジェクト管理装置であって、
前記タスクの計画開始日および計画完了日の入力を受け付ける計画入力部と、
前記タスクの進捗を示す進捗率の入力を受け付ける進捗入力部と、
前記計画開始日、前記計画完了日、前記進捗率、および現在の日付に基づいて、前記現在の日付を基準とした前記タスクの進みまたは遅れの日数を示す進み遅れ日数を算出する進み遅れ算出部と、
前記計画完了日の変更を検出し、変更前の前記計画完了日と変更後の前記計画完了日との差の日数を示す計画完了変更日数を算出する計画変更検出部と、
少なくとも前記進み遅れ日数を表示するよう制御する表示制御部と、
を備え、
前記計画変更検出部が前記計画完了日の変更を検出した場合において、
前記表示制御部は、少なくとも前記進み遅れ日数および前記計画完了変更日数を表示するよう制御することを特徴とする、プロジェクト管理装置。
A project management device for managing a project including at least one task,
A plan input unit for receiving input of a plan start date and a plan completion date of the task;
A progress input unit that receives an input of a progress rate indicating the progress of the task;
Based on the plan start date, the plan completion date, the progress rate, and the current date, an advance / delay calculation unit that calculates the advance / delay days indicating the advance or delay days of the task based on the current date When,
A plan change detecting unit that detects a change in the plan completion date and calculates a plan completion change day number indicating a difference between the plan completion date before the change and the plan completion date after the change;
A display control unit for controlling to display at least the advance / delay days; and
With
When the plan change detection unit detects a change in the plan completion date,
The display control unit controls to display at least the advance / delay days and the plan completion change days.
前記プロジェクトが複数の前記タスクを含み、前記計画変更検出部が前記計画完了日の変更を検出した場合において、
前記表示制御部は、各前記タスクのうち少なくとも1つのタスクを担当するグループごとに、前記進み遅れ日数および前記計画完了変更日数を表示するよう制御することを特徴とする、請求項1に記載のプロジェクト管理装置。
In the case where the project includes a plurality of the tasks, and the plan change detection unit detects a change in the plan completion date,
The said display control part is controlled to display the said advance / delay days and the said plan completion change days for every group which takes charge of at least 1 task among each said tasks, The feature of Claim 1 characterized by the above-mentioned. Project management device.
前記表示制御部は、前記グループごとに、前記進み遅れ日数の合計、および前記計画完了変更日数の合計を表示するよう制御することを特徴とする、請求項2に記載のプロジェクト管理装置。   The project management apparatus according to claim 2, wherein the display control unit controls to display the total of the advance / delay days and the total of the planned completion change days for each of the groups. 一の前記タスクに他の前記タスクが後続し、前記計画変更検出部が前記一のタスクの前記計画完了日の変更を検出した場合において、
前記表示制御部は、前記一のタスクの前記進み遅れ日数および前記計画完了変更日数を表示するよう制御するとともに、前記他のタスクの前記進み遅れ日数および前記計画完了変更日数を表示するよう制御することを特徴とする、請求項1に記載のプロジェクト管理装置。
In the case where one task is followed by another task, and the plan change detection unit detects a change in the plan completion date of the one task,
The display control unit controls to display the advance / delay days of the one task and the planned completion change days, and controls to display the advance / delay days and the plan completion change days of the other task. The project management apparatus according to claim 1, wherein:
前記進み遅れ算出部は、前記タスクの実働日数に基づいて前記進み遅れ日数を算出し、
前記計画変更検出部は、前記タスクの実働日数に基づいて前記計画完了変更日数を算出することを特徴とする、請求項1から4のいずれか1項に記載のプロジェクト管理装置。
The advance / delay calculation unit calculates the advance / delay days based on the actual working days of the task,
5. The project management apparatus according to claim 1, wherein the plan change detection unit calculates the plan completion change days based on the actual working days of the task.
前記表示制御部は、前記計画開始日、前記計画完了日、前記現在の日付、および前記進捗率に相当する日付をも表示するよう制御することを特徴とする、請求項1から5のいずれか1項に記載のプロジェクト管理装置。   6. The display control unit according to claim 1, wherein the display control unit controls to display the plan start date, the plan completion date, the current date, and a date corresponding to the progress rate. The project management apparatus according to item 1. 少なくとも1つのタスクを含むプロジェクトを管理するプロジェクト管理方法であって、
(a)前記タスクの計画開始日および計画完了日の入力を受け付ける工程と、
(b)前記タスクの進捗を示す進捗率の入力を受け付ける工程と、
(c)前記計画開始日、前記計画完了日、前記進捗率、および現在の日付に基づいて、前記現在の日付を基準とした前記タスクの進みまたは遅れの日数を示す進み遅れ日数を算出する工程と、
(d)前記計画完了日の変更を検出し、変更前の前記計画完了日と変更後の前記計画完了日との差の日数を示す計画完了変更日数を算出する工程と、
(e)少なくとも前記進み遅れ日数を表示するよう制御する工程と、
を備え、
前記工程(d)で前記計画完了日の変更を検出した場合において、
前記工程(e)は、少なくとも前記進み遅れ日数および前記計画完了変更日数を表示するよう制御することを特徴とする、プロジェクト管理方法。
A project management method for managing a project including at least one task,
(A) receiving an input of a plan start date and a plan completion date of the task;
(B) receiving an input of a progress rate indicating the progress of the task;
(C) calculating an advance / delay days indicating the advance or delay days of the task based on the current date based on the plan start date, the plan completion date, the progress rate, and the current date When,
(D) detecting a change in the plan completion date, and calculating a plan completion change day indicating a difference between the plan completion date before the change and the plan completion date after the change;
(E) controlling to display at least the advance delay days;
With
In the case where the change of the planned completion date is detected in the step (d),
The step (e) is controlled so as to display at least the advance / delay days and the plan completion change days.
JP2015252792A 2015-12-25 2015-12-25 Project management device and project management method Pending JP2017117247A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015252792A JP2017117247A (en) 2015-12-25 2015-12-25 Project management device and project management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015252792A JP2017117247A (en) 2015-12-25 2015-12-25 Project management device and project management method

Publications (1)

Publication Number Publication Date
JP2017117247A true JP2017117247A (en) 2017-06-29

Family

ID=59234445

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015252792A Pending JP2017117247A (en) 2015-12-25 2015-12-25 Project management device and project management method

Country Status (1)

Country Link
JP (1) JP2017117247A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7113128B1 (en) 2021-09-28 2022-08-04 東京瓦斯株式会社 Information processing device, information processing system, and program

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7113128B1 (en) 2021-09-28 2022-08-04 東京瓦斯株式会社 Information processing device, information processing system, and program
JP2023048580A (en) * 2021-09-28 2023-04-07 東京瓦斯株式会社 Information processing device, information processing system, and program

Similar Documents

Publication Publication Date Title
CN105408907B (en) For tracking the user interface of healthy behavior
JP2017142831A5 (en)
WO2017040249A1 (en) Interactive charts with dynamic progress monitoring, notification and resource allocation
JP2016126781A5 (en)
JP2017107355A (en) Schedule creation support device and method
JP6357831B2 (en) Production plan creation support program, production plan creation support method, and production plan creation support device
JP2017117247A (en) Project management device and project management method
JP5611077B2 (en) User interface program, terminal and method for switching time scale by finger pinch operation
JP2011095917A5 (en)
JP6451314B2 (en) Management device, display device, management device control method, control program, and recording medium
Saria Not all AI is created equal: strategies for safe and effective adoption
JP2008129825A (en) Computer-based method and system for managing working time
JP2019168800A (en) Process improvement support system and process improvement support method
JP2015017768A (en) Air conditioning controller, program, and air conditioning management system
JP6912148B2 (en) Personnel management system
JP2010128908A5 (en)
JP2017072927A (en) Schedule correction support device and method
JP5359311B2 (en) Workpiece manufacturing time prediction method, manufacturing date prediction method, arrival time prediction method, arrival date prediction method, workpiece manufacturing time prediction device, and arrival time prediction device
US20120226514A1 (en) Calendaring Tool Having Visual Clues to Address Conflicting Meeting Invitations
CN111191999A (en) Product research and development management method and device, computer equipment and storage medium
JP2020042767A5 (en)
JP5813845B2 (en) Evaluation value calculation device, evaluation value calculation method, and program
JP6305326B2 (en) Supervisory control device
JP2014135003A (en) Production schedule adjustment support system, production schedule adjustment support apparatus, production schedule adjustment support method, and program
CN102955763B (en) Display packing and display device