JP2016140124A - 電力供給システム - Google Patents
電力供給システム Download PDFInfo
- Publication number
- JP2016140124A JP2016140124A JP2015012015A JP2015012015A JP2016140124A JP 2016140124 A JP2016140124 A JP 2016140124A JP 2015012015 A JP2015012015 A JP 2015012015A JP 2015012015 A JP2015012015 A JP 2015012015A JP 2016140124 A JP2016140124 A JP 2016140124A
- Authority
- JP
- Japan
- Prior art keywords
- power
- storage device
- control unit
- generation unit
- amount
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B10/00—Integration of renewable energy sources in buildings
- Y02B10/10—Photovoltaic [PV]
Abstract
Description
売電量抑制処理とは、所定の条件を満たした場合に、太陽光発電部20からの電力を商用電源60へと売電するのを抑制するための処理である。なお、以下では便宜上、売電量抑制処理以外の処理をエコモードの実行の処理と称する。
なお、売電量抑制処理についての詳細な説明については後述する。
制御部31は、ステップS101の処理を行った後、ステップS102へ移行する。
制御部31は、太陽光発電部20の発電量が所定量以上であって、且つ蓄電装置30が満充電ではないと判定した場合には、ステップS103へ移行する。
制御部31は、太陽光発電部20の発電量が所定量以上であって、且つ蓄電装置30が満充電ではない、ものでない(すなわち、太陽光発電部20の発電量が所定量未満である、又は蓄電装置30が満充電である)と判定した場合には、ステップS111へ移行する。
制御部31は、ステップS103の処理を行った後、ステップS104へ移行する。
制御部31は、ステップS104の処理を行った後、ステップS105へ移行する。
制御部31は、商用電源60からの買電量が100W(第一設定量)よりも少ないと判定した場合には、ステップS106へ移行する。
制御部31は、制御部31は、商用電源60からの買電量が100W(第一設定量)以上であると判定した場合には、ステップS107へ移行する。
制御部31は、ステップS106の処理を行った後、ステップS109へ移行する。
制御部31は、商用電源60からの買電量が2000W(第二設定量)以上であると判定した場合には、ステップS111へ移行する。
制御部31は、商用電源60からの買電量が2000W(第二設定量)未満であると判定した場合には、ステップS108へ移行する。
制御部31は、ステップS108の処理を行った後、ステップS109へ移行する。
制御部31は、蓄電装置30が満充電であるか、又は蓄電装置30に蓄電される電力量が0(ゼロ)であると判定した場合には、ステップS110へ移行する。
制御部31は、蓄電装置30が満充電ではなく、且つ蓄電装置30に蓄電される電力量が0(ゼロ)ではないと判定した場合には、ステップS101へ移行する。
制御部31は、ステップS110の処理を行った後、ステップS101へ移行する。
制御部31は、蓄電装置30の残容量が規定値より小さいと判定した場合には、ステップS110へ移行する。
制御部31は、蓄電装置30の残容量が規定値以上であると判定した場合には、ステップS112へ移行する。
制御部31は、ステップS112の処理を行った後、ステップS101へ移行する。
なお、図4は、エコモードが実行された場合における、家庭内負荷50の消費電力と、太陽光発電部20で発電された電力と、売電された電力と、充電された電力との関係の一例を示している。ここで、図4は、後述する中間期(例えば6月)のある1日を例にあげたものとする。
また、制御部31は、今月が中間期ではない(非中間期である)と判定した場合には、売電量抑制処理を終了して、エコモードの実行の処理に戻る。
制御部31は、ステップS202の処理を行った後、ステップS203へ移行する。
制御部31は、現在の時刻が8時を過ぎていると判定した場合には、ステップS204へ移行する。
制御部31は、現在の時刻が8時を過ぎていない(8時前である)と判定した場合には、ステップS206へ移行する。
制御部31は、蓄電装置30の残容量が、当該蓄電装置30の蓄電容量の半分以上であると判定した場合には、ステップS205へ移行する。
制御部31は、蓄電装置30の残容量が、当該蓄電装置30の蓄電容量の半分未満であると判定した場合には、ステップS206へ移行する。
制御部31は、ステップS205の処理を行った後、ステップS206へ移行する。
制御部31は、現在の時刻が11時を過ぎていると判定した場合には、ステップS207へ移行する。
制御部31は、現在の時刻が11時を過ぎていない(8時から11時までの時間帯である)と判定した場合には、再びステップS206へ移行する。
制御部31は、太陽光発電部20の発電量が0(ゼロ)よりも大きいと判定した場合には、ステップS208へ移行する。
制御部31は、太陽光発電部20の発電量が0(ゼロ)以下であると判定した場合には、ステップS209へ移行する。
制御部31は、ステップS209の処理を行った後、ステップS210へ移行する。
制御部31は、現在の時刻が14時を過ぎていると判定した場合には、ステップS214へ移行する。
制御部31は、現在の時刻が14時を過ぎていない(11時から14時までの時間帯である)と判定した場合には、再びステップS207へ移行する。
制御部31は、ステップS208の処理を行った後、ステップS213へ移行する。
制御部31は、現在の時刻が14時を過ぎていると判定した場合には、ステップS214へ移行する。
制御部31は、現在の時刻が14時を過ぎていない(11時から14時までの時間帯である)と判定した場合には、再びステップS213へ移行する(すなわち、現在の時刻が14時を過ぎるまで、ステップS213の処理を繰り返す)。
制御部31は、太陽光発電部20の発電量が0(ゼロ)よりも大きく、また商用電源60からの買電量が0(ゼロ)よりも大きいと判定した場合には、ステップS217へ移行する。
制御部31は、太陽光発電部20の発電量が0(ゼロ)以下である、又は商用電源60からの買電量が0(ゼロ)以下であると判定した場合には、ステップS215へ移行する。
制御部31は、太陽光発電部20の発電量が0(ゼロ)未満であると判定した場合には、ステップS217へ移行する。
制御部31は、太陽光発電部20の発電量が0(ゼロ)以上であると判定した場合には、ステップS216へ移行する。
制御部31は、ステップS216の処理を行った後、ステップS214へ移行する。
制御部31は、ステップS217の処理を行った後、ステップS218へ移行する。
制御部31は、現在の時刻が20時を過ぎていると判定した場合には、売電量抑制処理を終了して、エコモードの実行の処理に戻る。
制御部31は、現在の時刻が20時を過ぎていない(14時から20時までの時間帯である)と判定した場合には、ステップS214へ移行する。
太陽光(自然エネルギー)を利用して発電可能であると共に当該発電された電力を商用電源60へと売電可能な太陽光発電部20(発電部)と、
太陽光発電部20(発電部)で発電された電力を充電可能であると共に当該充電された電力を家庭内負荷50の消費電力に応じて当該家庭内負荷50へと放電可能な蓄電装置30と、
前記蓄電装置30の充放電を制御する制御部31と、
を具備し、
前記制御部31は、
太陽光発電部20(発電部)で発電された電力を前記商用電源60へと売電するのを抑制するエコモードの売電量抑制処理を実行可能であり、
前記売電量抑制処理を実行する場合には、
前記蓄電装置30に充電された電力を、所定の放電時間帯(8時から11時まで)に前記家庭内負荷50の消費電力を増加させることによって前記家庭内負荷50へと放電し、
前記放電時間帯後の所定の充電可能時間帯(11時から14時まで)に、太陽光発電部20(発電部)で発電された電力を前記蓄電装置30に充電するものである。
前記制御部31は、
前記放電時間帯においては、前記蓄電装置30に前記充電時間帯における充電可能な容量を確保するまで前記蓄電装置30に充電された電力の放電を継続させるものである。
前記制御部31は、
前記充電可能時間帯においては、前記容量を満たすまで前記蓄電装置30の充電を継続させるものである。
前記制御部31は、
前記充電時間帯後に前記太陽光発電部20(発電部)で電力が発電され、且つ前記商用電源60から買電された場合には、前記蓄電装置30に充電された電力を前記家庭内負荷50へと放電するものである。
前記制御部31は、
現在の日付に関する情報を取得可能であって、
前記現在の日付に関する情報に基づいて、前記売電量抑制処理を実行するか否かを判定するものである。
また、本実施形態に係る家庭内負荷50は、本発明に係る負荷の一実施形態である。
また、本実施形態に係る蓄電装置30は、本発明に係る蓄電装置の一実施形態である。
また、本実施形態に係る蓄電装置30の制御部31は、本発明に係る制御部の一実施形態である。
20 太陽光発電部
30 蓄電装置
50 家庭内負荷
60 商用電源
Claims (5)
- 自然エネルギーを利用して発電可能であると共に当該発電された電力を商用電源へと売電可能な発電部と、
前記発電部で発電された電力を充電可能であると共に当該充電された電力を負荷の消費電力に応じて当該負荷へと放電可能な蓄電装置と、
前記蓄電装置の充放電を制御する制御部と、
を具備し、
前記制御部は、
前記発電部で発電された電力を前記商用電源へと売電するのを抑制する売電量抑制処理を実行可能であり、
前記売電量抑制処理を実行する場合には、前記蓄電装置に充電された電力を、所定の放電時間帯に前記負荷の消費電力を増加させることによって前記負荷へと放電し、
前記放電時間帯後の所定の充電時間帯に、前記発電部で発電された電力を前記蓄電装置に充電する、
電力供給システム。 - 前記制御部は、
前記放電時間帯においては、前記蓄電装置に前記充電時間帯における充電可能な容量を確保するまで前記蓄電装置に充電された電力の放電を継続させる、
請求項1に記載の電力供給システム。 - 前記制御部は、
前記充電時間帯においては、前記容量を満たすまで前記蓄電装置の充電を継続させる、
請求項2に記載の電力供給システム。 - 前記制御部は、
前記充電時間帯後に前記発電部で電力が発電され、且つ前記商用電源から買電された場合には、前記蓄電装置に充電された電力を前記負荷へと放電する、
請求項1から3に記載の電力供給システム。 - 前記制御部は、
現在の日付に関する情報を取得可能であって、前記現在の日付に関する情報に基づいて、前記売電量抑制処理を実行するか否かを判定する、
請求項1から4に記載の電力供給システム。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2015012015A JP6109208B2 (ja) | 2015-01-26 | 2015-01-26 | 電力供給システム |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2015012015A JP6109208B2 (ja) | 2015-01-26 | 2015-01-26 | 電力供給システム |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2016140124A true JP2016140124A (ja) | 2016-08-04 |
JP6109208B2 JP6109208B2 (ja) | 2017-04-05 |
Family
ID=56559445
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2015012015A Active JP6109208B2 (ja) | 2015-01-26 | 2015-01-26 | 電力供給システム |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP6109208B2 (ja) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2016140125A (ja) * | 2015-01-26 | 2016-08-04 | 大和ハウス工業株式会社 | 電力供給システム |
JP2016185055A (ja) * | 2015-03-27 | 2016-10-20 | 大和ハウス工業株式会社 | 集合住宅用電力供給システム |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009284586A (ja) * | 2008-05-20 | 2009-12-03 | Nippon Telegr & Teleph Corp <Ntt> | 電力システムおよびその制御方法 |
JP2010288393A (ja) * | 2009-06-12 | 2010-12-24 | Sharp Corp | 電力運用システム、電力運用方法、太陽光発電装置、およびコントローラ |
JP2012120419A (ja) * | 2010-11-10 | 2012-06-21 | Mitsubishi Heavy Ind Ltd | 蓄電池運用制御装置及び蓄電池運用制御方法ならびにそのプログラム |
JP2012139019A (ja) * | 2010-12-27 | 2012-07-19 | Noritz Corp | パワーコンディショナ |
JP2013192351A (ja) * | 2012-03-13 | 2013-09-26 | Omron Corp | 電力調整装置、電力調整方法、プログラム、および電力システム |
JP2014053989A (ja) * | 2012-09-05 | 2014-03-20 | Mitsubishi Electric Corp | バッテリ充放電システム |
JP2014165952A (ja) * | 2013-02-21 | 2014-09-08 | Daiwa House Industry Co Ltd | 電力供給システム |
US20140306534A1 (en) * | 2013-04-15 | 2014-10-16 | Nec Laboratories America, Inc. | Pmu based distributed generation control for microgrid during islanding process |
JP2016140125A (ja) * | 2015-01-26 | 2016-08-04 | 大和ハウス工業株式会社 | 電力供給システム |
-
2015
- 2015-01-26 JP JP2015012015A patent/JP6109208B2/ja active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009284586A (ja) * | 2008-05-20 | 2009-12-03 | Nippon Telegr & Teleph Corp <Ntt> | 電力システムおよびその制御方法 |
JP2010288393A (ja) * | 2009-06-12 | 2010-12-24 | Sharp Corp | 電力運用システム、電力運用方法、太陽光発電装置、およびコントローラ |
JP2012120419A (ja) * | 2010-11-10 | 2012-06-21 | Mitsubishi Heavy Ind Ltd | 蓄電池運用制御装置及び蓄電池運用制御方法ならびにそのプログラム |
JP2012139019A (ja) * | 2010-12-27 | 2012-07-19 | Noritz Corp | パワーコンディショナ |
JP2013192351A (ja) * | 2012-03-13 | 2013-09-26 | Omron Corp | 電力調整装置、電力調整方法、プログラム、および電力システム |
JP2014053989A (ja) * | 2012-09-05 | 2014-03-20 | Mitsubishi Electric Corp | バッテリ充放電システム |
JP2014165952A (ja) * | 2013-02-21 | 2014-09-08 | Daiwa House Industry Co Ltd | 電力供給システム |
US20140306534A1 (en) * | 2013-04-15 | 2014-10-16 | Nec Laboratories America, Inc. | Pmu based distributed generation control for microgrid during islanding process |
JP2016140125A (ja) * | 2015-01-26 | 2016-08-04 | 大和ハウス工業株式会社 | 電力供給システム |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2016140125A (ja) * | 2015-01-26 | 2016-08-04 | 大和ハウス工業株式会社 | 電力供給システム |
JP2016185055A (ja) * | 2015-03-27 | 2016-10-20 | 大和ハウス工業株式会社 | 集合住宅用電力供給システム |
Also Published As
Publication number | Publication date |
---|---|
JP6109208B2 (ja) | 2017-04-05 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6109108B2 (ja) | 電力供給システム | |
JP6109209B2 (ja) | 電力供給システム | |
JP2014165952A (ja) | 電力供給システム | |
JP6143821B2 (ja) | 電力供給システム | |
JP6462369B2 (ja) | 電力供給システム | |
JP5944269B2 (ja) | 電力供給システム | |
JP6167438B2 (ja) | 電力供給システム | |
JP6109208B2 (ja) | 電力供給システム | |
JP6054670B2 (ja) | 電力供給システム | |
JP6025443B2 (ja) | 電力供給システム | |
JP2021057180A (ja) | 電力供給システム | |
JP6920876B2 (ja) | 電力供給システム | |
JP6432099B2 (ja) | 電力供給システム | |
JP7349840B2 (ja) | 電力供給システム | |
JP6280741B2 (ja) | 電力供給システム | |
JP6085785B2 (ja) | 電力供給システム | |
JP2016073073A (ja) | 電力供給システム | |
JP5869539B2 (ja) | 電力供給システム | |
JP2016052156A (ja) | 電力供給システム | |
JP6378871B2 (ja) | 電力供給システム | |
JP2021057181A (ja) | 電力供給システム | |
JP6378955B2 (ja) | 電力供給システム | |
JP5939938B2 (ja) | 電力供給システム | |
JP2019118176A (ja) | 電力供給システム | |
JP7303717B2 (ja) | 電力融通システム |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20160804 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20160823 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20161021 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20170228 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20170307 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 6109208 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |