JP2016130444A - Construction method for base-isolated structure - Google Patents

Construction method for base-isolated structure Download PDF

Info

Publication number
JP2016130444A
JP2016130444A JP2015005735A JP2015005735A JP2016130444A JP 2016130444 A JP2016130444 A JP 2016130444A JP 2015005735 A JP2015005735 A JP 2015005735A JP 2015005735 A JP2015005735 A JP 2015005735A JP 2016130444 A JP2016130444 A JP 2016130444A
Authority
JP
Japan
Prior art keywords
seismic isolation
concrete
construction
isolation device
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2015005735A
Other languages
Japanese (ja)
Other versions
JP6441689B2 (en
Inventor
直行 ▲高▼橋
直行 ▲高▼橋
Naoyuki Takahashi
太郎 吉光
Taro Yoshimitsu
太郎 吉光
忠司 吉田
Tadashi Yoshida
忠司 吉田
悟史 赤尾
Satoshi Akao
悟史 赤尾
秀剛 塩澤
Hideyoshi Shiozawa
秀剛 塩澤
成人 岩田
Shigeto Iwata
成人 岩田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP2015005735A priority Critical patent/JP6441689B2/en
Publication of JP2016130444A publication Critical patent/JP2016130444A/en
Application granted granted Critical
Publication of JP6441689B2 publication Critical patent/JP6441689B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)
  • Vibration Prevention Devices (AREA)

Abstract

PROBLEM TO BE SOLVED: To curtail overall construction period significantly, in a construction method for a base-isolated structure constructed by a normal construction method, having a seismic isolator interposed between a lower column part of a composite structure comprising an iron column part and a concrete part, and upper column part built above the lower column part.SOLUTION: A construction method for a base-isolated structure includes a first step in which an iron column part 1a of a lower column part 1 is arranged and a seismic isolator 2 is installed above the iron column part 1a, a second step in which an upper column part 3 is arranged above the seismic isolator 2 installed in the first step, and a third step in which concrete is cast after arranging the upper column part 3 and completing the lower column part 1.SELECTED DRAWING: Figure 4

Description

本発明は、鉄柱部分とコンクリート部分の複合構造で構成された下側柱部と、当該下側柱部の上方に配設される上側柱部との間に免震装置が介装された免震構造物を順打ち工法で構築する免震構造物の施工方法に関する。   The present invention provides a seismic isolation device in which a seismic isolation device is interposed between a lower column portion composed of a composite structure of an iron column portion and a concrete portion and an upper column portion disposed above the lower column portion. The present invention relates to a method for constructing a seismic isolation structure in which a seismic structure is constructed by a sequential construction method.

下側柱部と上側柱部との間に免震装置を介装させてなる免震構造物を順打ち工法で構築する場合には、下側柱部を配設する下側柱部配設工事と、当該工程で配設された下側柱部の上方に免震装置を設置する免震装置設置工事と、当該工程で設置された免震装置の上方に上側柱部を配設する上部柱部配設工事とがこの順に行われる(例えば特許文献1を参照。)。   When building a seismic isolation structure with a seismic isolation device between the lower column and upper column, the lower column is installed to install the lower column. Construction work, seismic isolation device installation work that installs the seismic isolation device above the lower column part installed in the process, and upper part that installs the upper column part above the seismic isolation device installed in the process The column arrangement work is performed in this order (see, for example, Patent Document 1).

更に、下側柱部が、SRC造(鉄骨鉄筋コンクリート造)やCFT構造(コンクリート充填鋼管構造)のように、鉄柱部分とコンクリート部分の複合構造で構成される場合では、下側柱部配設工事において、鉄柱部分の配設に加えて、下側柱部のコンクリートを打設するコンクリート打設工事(以下「下側柱部のコンクリート打設工事」という。)が行われて、下側柱部が完成された上で、免震装置設置工事並びに上側柱部配設工事が行われる。   Furthermore, if the lower column part is composed of a composite structure of steel and concrete parts, such as SRC structure (steel reinforced concrete structure) or CFT structure (concrete-filled steel pipe structure), lower column part installation work In addition to the arrangement of the iron pillar portion, concrete placement work for placing concrete in the lower pillar portion (hereinafter referred to as “concrete placement work for the lower pillar portion”) has been carried out. Is completed, seismic isolation device installation work and upper column part installation work will be performed.

特開2011−052432号公報JP 2011-052432 A

上述した従来の免震構造物の施工方法では、下側柱部のコンクリート打設工事を行って下側柱部を完成させてから、免震装置設置工事を行うが、この下側柱部の施工状況等によっては、免震装置設置工事の開始時期が遅くなる。よって、免震装置を設置した上で行う必要がある上側柱部配設工事並びにこれを起点とする免震装置よりも上層階の躯体工事の開始時期についても、遅くなり、このことは全体工期の長期化の原因となる。   In the construction method of the conventional seismic isolation structure described above, the concrete is installed in the lower column to complete the lower column, and then the seismic isolation device is installed. Depending on the construction status, the start of seismic isolation device installation work may be delayed. Therefore, the upper column part installation work that needs to be done after installing the seismic isolation device and the start time of the frame construction on the upper floor than the seismic isolation device starting from this are also delayed, which means that the whole construction period Cause a prolonged period.

特に、免震装置を中間階に設けるような中間免震構造物では、複数階に亘る下側柱部のコンクリート打設工事がある程度の期間を要するため、この下側柱部のコンクリート打設工事が完了してから免震装置を設置した上で上層階の躯体工事を開始するとなると、全体工期が非常に長引くという問題がある。   In particular, in an intermediate seismic isolation structure where seismic isolation devices are installed on the intermediate floor, the concrete placement work for the lower pillar section over several floors requires a certain period of time. When the seismic isolation device is installed after the completion of the construction, the construction work on the upper floors will start, and there is a problem that the entire construction period will be very long.

この実情に鑑み、本発明の主たる課題は、鉄柱部分とコンクリート部分の複合構造で構成された下側柱部と、当該下側柱部の上方に配設される上側柱部との間に免震装置が介装された免震構造物を順打ち工法で構築する免震構造物の施工方法において、全体工期の大幅な短縮を実現することができる技術を提供する点にある。   In view of this situation, the main problem of the present invention is that there is no waiver between the lower column portion configured by the composite structure of the iron column portion and the concrete portion and the upper column portion disposed above the lower column portion. In the construction method of the seismic isolation structure in which the seismic isolation structure in which the seismic device is installed is constructed by the forward construction method, it is to provide a technique capable of realizing a significant reduction in the entire construction period.

本発明の第1特徴構成は、鉄柱部分とコンクリート部分の複合構造で構成された下側柱部と、当該下側柱部の上方に配設される上側柱部との間に免震装置が介装された免震構造物を順打ち工法で構築する免震構造物の施工方法であって、
前記下側柱部の鉄柱部分を配設し、その鉄柱部分の上方に免震装置を設置する第1工程と、
前記第1工程で設置した免震装置の上方に前記上側柱部を配設する第2工程と、
前記上側柱部を配設した後、コンクリートを打設して下側柱部を完成させる第3工程を備える点にある。
A first characteristic configuration of the present invention is that a seismic isolation device is provided between a lower column portion configured by a composite structure of an iron column portion and a concrete portion and an upper column portion disposed above the lower column portion. It is a construction method of a seismic isolation structure in which an installed seismic isolation structure is constructed by a sequential construction method,
A first step of disposing an iron pillar portion of the lower pillar portion and installing a seismic isolation device above the iron pillar portion;
A second step of disposing the upper column portion above the seismic isolation device installed in the first step;
After the upper column portion is disposed, a third step of placing the concrete to complete the lower column portion is provided.

本特徴構成によれば、下側柱部の鉄柱部分を配設し、その鉄柱部分の上方に免震装置を設置するので、コンクリートを打設して下側柱部を完成させる下側柱部のコンクリート打設工事に影響されずに、上側柱部の配設を先行して行うことができ、結果、全体工期の大幅な短縮を実現することができる。   According to this characteristic configuration, the iron pillar part of the lower pillar part is arranged, and the seismic isolation device is installed above the iron pillar part, so that the lower pillar part is completed by placing concrete. The upper column portion can be arranged in advance without being affected by the concrete placing work, and as a result, the overall construction period can be greatly shortened.

即ち、上記第1工程において、下側柱部の鉄柱部分を配設した段階で、下側柱部の鉄柱部分の上方に免震装置を設置する。このことにより、下側柱部のコンクリート打設工事の完了を待たずに、上記第2工程において、その免震装置の上方に上側柱部を配設した上で、免震装置よりも上層階の躯体工事を開始することができる。また、下部柱部のコンクリート工事については、第3工程において、上側柱部を配設した後に完了させて、下部柱部を完成させることができる。   That is, in the first step, the seismic isolation device is installed above the iron column portion of the lower column portion when the iron column portion of the lower column portion is disposed. Thus, without waiting for the completion of the concrete placing work for the lower column portion, in the second step, the upper column portion is disposed above the seismic isolation device, and the upper floor than the seismic isolation device. Construction of the housing can be started. Moreover, about the concrete construction of a lower pillar part, it can complete after arrange | positioning an upper pillar part in a 3rd process, and can complete a lower pillar part.

本発明の第2特徴構成は、上述の第1特徴構成を備えた免震構造物の施工方法において、
前記第1工程において、前記下側柱部の鉄柱部分を配設した後、当該鉄柱部分の上側部位に接続する状態で免震下部基礎の上側部位を構築し、その免震下部基礎の上側部位の上方に前記免震装置を設置すると共に、
前記第3工程において、前記免震下部基礎の下側部位を構築する点にある。
The second feature configuration of the present invention is a construction method of the seismic isolation structure having the first feature configuration described above.
In the first step, after arranging the iron pillar part of the lower pillar part, the upper part of the seismic isolation lower foundation is constructed in a state connected to the upper part of the iron pillar part, and the upper part of the seismic isolation lower foundation And installing the seismic isolation device above
In the third step, the lower part of the base isolation base is constructed.

本特徴構成によれば、免震装置を支持する免震下部基礎のうちで免震装置の設置面を有する上側部位を先行設置するので、免震装置を免震下部基礎の上側部位に適切に設置できながら、免震下部基礎の下側部位の同時設置が難しい状況などにおいて、免震装置の設置に要する期間を短縮し、全体工期の短縮に寄与することができる。   According to this feature configuration, the upper part having the installation surface of the seismic isolation device is pre-installed among the seismic isolation lower foundations that support the seismic isolation device. In situations where it is difficult to install the lower part of the seismic isolation base at the same time, it is possible to shorten the time required to install the seismic isolation device and contribute to shortening the overall construction period.

本発明の第3特徴構成は、上述の第2特徴構成を備えた免震構造物の施工方法において、
前記第1工程において、スラブ構築用の高さ位置にスラブ型枠を設置し、このスラブ型枠をコンクリート支持部として用いて当該スラブ型枠の上方に前記免震下部基礎の上側部位をコンクリートで構築する点にある。
The third feature configuration of the present invention is a construction method of the seismic isolation structure having the second feature configuration described above.
In the first step, a slab formwork is installed at a height position for slab construction, and the upper part of the seismic isolation lower foundation is made of concrete above the slab formwork using the slab formwork as a concrete support part. The point is to build.

本特徴構成によれば、免震下部基礎のうちで免震装置の設置面を有する上側部位を先行設置する場合において、スラブ構築用のスラブ型枠を、免震下部基礎のコンクリート支持部に活用するので、コンクリート支持用の部材を別途に設置するのに比べ、施工の省力化を図ることができる。   According to this feature configuration, the slab formwork for slab construction is utilized for the concrete support part of the seismic isolation lower foundation when the upper part having the installation surface of the seismic isolation device is installed in advance in the seismic isolation lower foundation. Therefore, labor saving of construction can be achieved as compared with the case of separately installing a member for supporting concrete.

更に、上述の第3特徴構成を備えた免震構造物の施工方法では、前記第1工程において、前記スラブ型枠の上方にスラブ構築用のコンクリートの少なくとも一部を先行打設し、スラブ型枠とスラブ構築用のコンクリートの硬化部分とを前記コンクリート支持部とすれば、スラブ構築用コンクリートの硬化部分によってコンクリート支持部の強度を高めることができ、スラブ型枠を捨て型枠とする場合に特に効果的である。   Furthermore, in the construction method of the seismic isolation structure having the third characteristic configuration described above, in the first step, at least a part of the concrete for slab construction is placed in advance above the slab formwork, and the slab type When the frame and the hardened portion of the concrete for slab construction are the concrete support portion, the strength of the concrete support portion can be increased by the hardened portion of the concrete for slab construction, and when the slab formwork is used as a discarded formwork It is particularly effective.

本発明の第4特徴構成は、上述の第1〜3の何れかの特徴構成を備えた免震構造物の施工方法において、
前記第2工程の実施前に前記免震装置の設置階の床を構築する点にある。
The fourth feature configuration of the present invention is a construction method for a seismic isolation structure having any one of the first to third feature configurations described above.
It is in the point which constructs the floor of the installation floor of the seismic isolation device before the implementation of the second step.

本特徴構成によれば、免震装置の上方に上側柱部を配設する前に当該免震装置の設置階の床を構築するので、当該床を活用して、上側柱部の配設や免震装置よりも上層階の躯体工事などを効率良く実施することができる。   According to this characteristic configuration, since the floor of the installation floor of the seismic isolation device is constructed before the upper column portion is disposed above the seismic isolation device, the upper column portion can be arranged using the floor. It is possible to carry out the construction work on the upper floor more efficiently than the seismic isolation device.

本実施形態の免震構造物の施工方法における下側柱部鉄柱部分配設工事後の建物の状態を示す図The figure which shows the state of the building after the lower column part iron pillar part arrangement construction in the construction method of the seismic isolation structure of this embodiment 本実施形態の免震構造物の施工方法における免震下部基礎上側部位構築工事後の建物の状態を示す図The figure which shows the state of the building after the seismic isolation lower base upper part site construction in the construction method of the seismic isolation structure of this embodiment 本実施形態の免震構造物の施工方法における免震装置設置工事後の建物の状態を示す図The figure which shows the state of the building after the seismic isolation apparatus installation construction in the construction method of the seismic isolation structure of this embodiment 本実施形態の免震構造物の施工方法における上側柱部配設工事後の建物の状態を示す図The figure which shows the state of the building after the upper side pillar arrangement | positioning construction in the construction method of the seismic isolation structure of this embodiment 本実施形態の免震構造物の施工方法における下側柱部コンクリート打設工事後の建物の状態を示す図The figure which shows the state of the building after the lower pillar part concrete placement construction in the construction method of the seismic isolation structure of this embodiment 本実施形態の免震構造物の施工方法における免震下部基礎下側部位構築工事後の建物の状態を示す図The figure which shows the state of the building after the seismic isolation lower foundation lower part site construction in the construction method of the seismic isolation structure of this embodiment 本実施形態の免震構造物の施工方法における免震上部基礎構築工事後の建物の状態を示す図The figure which shows the state of the building after the seismic isolation upper foundation construction in the construction method of the seismic isolation structure of this embodiment

本発明の実施形態について図面に基づいて説明する。
本実施形態の施工方法(以下「本施工方法」と呼ぶ。)で構築される建物は、図7に示すように、鉄柱部分1aとコンクリート部分1bの複合構造で構成された下側柱部1と、当該下側柱部1の上方に配設される上側柱部3との間に免震装置2が介装された免震構造物として構成され、下方から上方に向けて順にコンクリートを打設する順打ち工法で構築される。
Embodiments of the present invention will be described with reference to the drawings.
The building constructed by the construction method of the present embodiment (hereinafter referred to as “the present construction method”), as shown in FIG. 7, is a lower pillar portion 1 composed of a composite structure of a steel pillar portion 1 a and a concrete portion 1 b. And an upper base 3 disposed above the lower column 1 is configured as a seismic isolation structure in which a seismic isolation device 2 is interposed. It will be constructed by the order construction method.

免震装置2は、鋼材や鉛プラグ等のダンパー(図示省略)を内装する積層ゴム支承等のアイソレータ2cと、このアイソレータ2cの上下に位置する下部フランジ2a及び上部フランジ2bを備えて構成されている。そして、下部フランジ2aが下側柱部1の上端部側に固定されると共に上部フランジ2bが上側柱部3の下端部側に固定される状態で、免震装置2が下側柱部1と上側柱部3との間に介装される。そして、この免震装置2により、地震時において、建物の振動周期を長周期化すると共に、振動エネルギーを減衰することができる。
また、この建物は、かかる免震装置2の設置階(以下「免震装置設置階」という。)を、中間階に設けた中間免震構造物として構成されている。
The seismic isolation device 2 includes an isolator 2c such as a laminated rubber bearing in which a damper (not shown) such as a steel material or a lead plug is installed, and a lower flange 2a and an upper flange 2b positioned above and below the isolator 2c. Yes. The seismic isolation device 2 is connected to the lower column portion 1 in a state where the lower flange 2a is fixed to the upper end portion side of the lower column portion 1 and the upper flange 2b is fixed to the lower end portion side of the upper column portion 3. It is interposed between the upper column part 3. And by this seismic isolation apparatus 2, at the time of an earthquake, while making the vibration period of a building longer, vibration energy can be attenuated.
In addition, this building is configured as an intermediate seismic isolation structure in which the installation floor of the seismic isolation device 2 (hereinafter referred to as “the seismic isolation device installation floor”) is provided on the intermediate floor.

本施工方法の具体的手順は、全体工期の大幅な短縮を実現することができるものとして構成されており、以下、その具体的手順について説明する。
本施工方法では、各工事内容の詳細については後述するが、下側柱部鉄柱部分配設工事(図1参照)、免震下部基礎上側部位構築工事(図2参照)、免震装置設置工事(図3参照)、上側柱部配設工事(図4参照)、下側柱部コンクリート打設工事(図5参照)、免震下部基礎下側部位構築工事(図6参照)、及び、免震上部基礎構築工事(図7参照)の各工事を記載の順に行うものとして構成されている。尚、下側柱部鉄柱部分配設工事から免震装置設置工事までの工程が第1工程に相当し、上側柱部配設工事の工程が第2工程に相当し、下側柱部コンクリート打設工事以降の工程が第3工程に相当する。
The specific procedure of this construction method is configured to realize a significant shortening of the entire construction period, and the specific procedure will be described below.
In this construction method, the details of each construction will be described later, but the lower pillar part steel pillar part installation work (see Fig. 1), the seismic isolation lower base upper part construction work (see Fig. 2), the seismic isolation device installation work (Refer to Fig. 3), upper pillar arrangement work (see Figure 4), lower pillar concrete placement work (see Figure 5), seismic isolation lower foundation lower part construction work (see Figure 6), and exemption It is configured to perform each construction of the seismic upper foundation construction (see Fig. 7) in the order described. The process from the lower column part installation work to the seismic isolation device installation process corresponds to the first process, the upper column installation process corresponds to the second process, and the lower column part concrete placement The process after the installation work corresponds to the third process.

(下側柱部鉄柱部分配設工事)
図1に示すように、本施工方法の下側柱部鉄柱部分配設工事では、下側柱部1の鉄柱部分1aが配設される。
即ち、この工事では、下側柱部1を構成する鉄柱部分1aとコンクリート部分1b(図5参照)のうち、鉄柱部分1aのみが免震装置設置階及びそれよりも下層階を含む複数階に亘って建て込まれる。尚、本実施形態では、鉄柱部分1aとして、H形鋼をクロスさせた断面形状を有する比較的高耐力且つ高剛性のクロスH形鋼を利用しているが、別の形態の形鋼を利用しても構わない。
(Lower pillar part installation work)
As shown in FIG. 1, in the lower column part iron column part arrangement work of this construction method, the iron column part 1 a of the lower column part 1 is arranged.
That is, in this construction, among the iron pillar part 1a and the concrete part 1b (see FIG. 5) constituting the lower pillar part 1, only the iron pillar part 1a is placed on a plurality of floors including the seismic isolation device installation floor and lower floors. It is built over. In the present embodiment, a relatively high yield strength and high rigidity cross H-shaped steel having a cross-sectional shape obtained by crossing an H-shaped steel is used as the iron pillar portion 1a. However, another shape steel is used. It doesn't matter.

下側柱部1の鉄柱部分1aには、下層階の各階を支持する鉄骨梁15が接合され、更に、その鉄骨梁15の上面のスラブ構築用の高さ位置には、デッキプレート等からなるスラブ型枠16が架設される。また、下側柱部1の鉄柱部分1aは、免震装置設置階のスラブ型枠16よりも上方に突出しており、その上端部には、頭付きスタッドやボルト等の定着用材12が設けられる。   A steel beam 15 supporting each floor of the lower floor is joined to the steel pillar portion 1a of the lower column portion 1, and a slab construction height position on the upper surface of the steel beam 15 is composed of a deck plate or the like. A slab formwork 16 is installed. Further, the iron pillar portion 1a of the lower pillar portion 1 protrudes upward from the slab formwork 16 on the seismic isolation device installation floor, and a fixing material 12 such as a headed stud or a bolt is provided at an upper end portion thereof. .

(免震下部基礎上側部位構築工事)
図2に示すように、上記下側柱部鉄柱部分配設工事に続く本施工方法の免震下部基礎上側部位構築工事では、免震下部基礎5の上側部位5aが構築される。
即ち、免震装置2の下部フランジ2a側を支持するための免震下部基礎5は、スラブ型枠16よりも上方の上側部位5aと同スラブ型枠16よりも下方の下側部位5bとで構成されており、この工事では、これら部位のうち上側部位5aのみが構築される。
(Seismic isolation lower base upper part construction work)
As shown in FIG. 2, in the seismic isolation lower base upper part construction work of the present construction method following the lower pillar part pillar construction work, the upper part 5 a of the seismic isolation lower foundation 5 is constructed.
That is, the seismic isolation lower base 5 for supporting the lower flange 2 a side of the seismic isolation device 2 includes an upper part 5 a above the slab mold 16 and a lower part 5 b below the slab mold 16. In this construction, only the upper part 5a among these parts is constructed.

この工事では、スラブ型枠16よりも上方の所定高さの領域、具体的にはスラブ型枠16から後に設置される免震装置2(図3参照)を載置するためのベースプレート8までの領域において、鉄柱部分1aの周囲に適宜鉄筋及び型枠(図示省略)を配設した上でコンクリートを打設することによって、免震下部基礎5の上側部位5aが構築される。   In this construction, a region having a predetermined height above the slab form 16, specifically, from the slab form 16 to the base plate 8 on which the seismic isolation device 2 (see FIG. 3) to be installed later is placed. In the area, the upper part 5a of the seismic isolation lower foundation 5 is constructed by placing concrete after appropriately arranging reinforcing bars and formwork (not shown) around the iron pillar portion 1a.

免震下部基礎5の上側部位5aの構築手順では、スラブ型枠16の上方に適宜鉄筋及び側面型枠(図示省略)を配置した上で、スラブ型枠16の上方にスラブ構築用のコンクリートを先行打設し、スラブ型枠16とスラブ構築用のコンクリートの硬化部分であるベース部5aaをコンクリート支持部として利用する形態で、コンクリートの打設を2段階で行う。即ち、1段階目のコンクリート打設では、スラブ型枠16をコンクリート支持部として用い、その上方にコンクリートを打設することによって、後にコンクリートを打設して構築される床17(図3参照)と同等の高さのベース部5aaが構築される。これに続く2段階目のコンクリート打設では、このベース部5aaに打設したコンクリートが硬化した段階で、スラブ型枠16及びその上に構築されたベース部5aaをコンクリート支持部として用い、その上方にコンクリートを打設することによって、ベース部5aaの上方に残部5abが構築される。そして、これらベース部5aaと残部5abの一体化された構造物が、免震下部基礎5の上側部位5aとなる。   In the construction procedure of the upper part 5 a of the seismic isolation lower foundation 5, a reinforcing bar and a side mold (not shown) are appropriately disposed above the slab mold 16, and concrete for slab construction is disposed above the slab mold 16. The concrete is placed in two stages in a form in which the slab formwork 16 and the base portion 5aa, which is a hardened portion of the concrete for slab construction, are used as the concrete support portion. That is, in the first-stage concrete placement, the slab form 16 is used as a concrete support portion, and concrete is placed thereabove, and then the floor 17 is constructed by placing concrete later (see FIG. 3). The base portion 5aa having the same height as that is constructed. In the subsequent second stage of concrete placement, when the concrete placed on the base portion 5aa is hardened, the slab form 16 and the base portion 5aa constructed thereon are used as a concrete support portion, The remaining portion 5ab is constructed above the base portion 5aa by placing concrete on the base portion 5aa. The structure in which the base portion 5aa and the remaining portion 5ab are integrated becomes the upper portion 5a of the seismic isolation lower base 5.

このように、免震下部基礎5の上側部位5aにおけるコンクリート打設を2段階で行うことで、比較的重量が大きい残部5abのコンクリートを、予め構築したベース部5aaで支持することができる。よって、スラブ型枠16をコンクリート支持部として利用するための補強等を省略又は簡略化することができる。尚、本実施形態では、このベース部5aaのコンクリート打設を、免震装置設置階の床17(図3参照)のコンクリート打設よりも先行して行うように構成したが、当然、これらのコンクリート打設を同時に行っても構わない。   Thus, the concrete of the remaining part 5ab with comparatively large weight can be supported by the base part 5aa constructed | assembled previously by performing concrete placement in the upper part 5a of the seismic isolation lower base 5 in two steps. Therefore, reinforcement for using the slab formwork 16 as a concrete support portion can be omitted or simplified. In this embodiment, the concrete placement of the base portion 5aa is configured to be performed prior to the concrete placement of the floor 17 (see FIG. 3) of the seismic isolation device installation floor. You may perform concrete placement at the same time.

免震下部基礎5の上端面(残部5abの上端面)側には、免震下部基礎5の上端面よりも所定高さ分上方に突出した姿勢で免震装置固定用のナット10aが立設されている。更に、その上方には、後に免震装置2(図3参照)を載置するためのベースプレート8が設置されている。そして、そのベースプレート8の水平度や高さ等の調整を行った上で、当該免震下部基礎5の上端面とベースプレート8の間の隙間に無収縮モルタル7が充填され、ベースプレート8の設置が完了する。   On the upper end surface of the seismic isolation lower foundation 5 (upper end surface of the remaining portion 5ab), a nut 10a for fixing the seismic isolation device is erected in a posture protruding above the upper end surface of the seismic isolation lower foundation 5 by a predetermined height. Has been. Furthermore, a base plate 8 for placing the seismic isolation device 2 (see FIG. 3) later is installed above the base plate 8. Then, after adjusting the level and height of the base plate 8, the space between the upper end surface of the base isolation base 5 and the base plate 8 is filled with the non-shrink mortar 7, and the base plate 8 is installed. Complete.

(免震装置設置工事)
図3に示すように、上記免震下部基礎上側部位構築工事に続く本施工方法の免震装置設置工事では、下側柱部1の鉄柱部分1aの上方に免震装置2が設置される。
即ち、この免震装置設置工事では、先ず、下側柱部1の鉄柱部分1aの上方に構築された免震下部基礎5の上側部位5aの上端面(具体的にはベースプレート8の上面)である免震装置設置面に免震装置2が載置される。次に、免震装置2の下部フランジ2aに形成されたボルト挿通孔(図示省略)に上方から挿通されたボルト10bが、免震下部基礎5側のナット10aに締結されることで、免震装置2の下部フランジ2aが免震下部基礎5の上端面に固定される。
(Seismic isolation device installation work)
As shown in FIG. 3, the seismic isolation device 2 is installed above the iron pillar portion 1 a of the lower column portion 1 in the seismic isolation device installation work of the present construction method following the seismic isolation lower base upper part construction work.
That is, in this seismic isolation device installation work, first, on the upper end surface (specifically, the upper surface of the base plate 8) of the upper part 5a of the seismic isolation lower foundation 5 constructed above the iron column part 1a of the lower column part 1. The seismic isolation device 2 is placed on a certain seismic isolation device installation surface. Next, the bolt 10b inserted from above into a bolt insertion hole (not shown) formed in the lower flange 2a of the seismic isolation device 2 is fastened to the nut 10a on the seismic isolation lower foundation 5 side, so that the seismic isolation is achieved. The lower flange 2 a of the device 2 is fixed to the upper end surface of the seismic isolation lower foundation 5.

この工事と同時に、免震装置設置階の床17のコンクリート打設工事が行われる。また、下側柱部鉄柱部分配設工事が完了し、下側柱部1の鉄柱部分1aが建て込まれた段階で、免震装置設置階及びその下層階において、本免震装置設置工事と同時に他の工事を行っても構わない。   Simultaneously with this construction, concrete placement work for the floor 17 on the seismic isolation device installation floor is performed. In addition, at the stage where the lower pillar part installation work is completed and the iron pillar part 1a of the lower pillar part 1 is built, the seismic isolation equipment installation work and Other construction may be performed at the same time.

(上側柱部配設工事)
図4に示すように、上記免震装置設置工事に続く本施工方法の上側柱部配設工事では、免震装置2の上方に上側柱部3が配設される。
かかる上側柱部3は、免震装置設置階よりも上の上層階に建て込まれ、H形鋼3aからなるS造(鉄骨造)の柱部として構成されている。そして、この工事では、先ず、免震装置2の上部フランジ2bの上面に上側柱部3が載置される。次に、免震装置2の上部フランジ2bに形成されたボルト挿通孔(図示省略)に下方から挿通されたボルト11bが、上側柱部3を構成するH形鋼3aの下端面に接合された接合プレートに接合されたナット11aに締結されることで、免震装置2の上部フランジ2bが上側柱部3の下端面に固定される。
(Upper column arrangement work)
As shown in FIG. 4, the upper column portion 3 is disposed above the seismic isolation device 2 in the upper column portion arrangement work of the present construction method following the seismic isolation device installation work.
The upper column portion 3 is built as an upper floor above the floor where the seismic isolation device is installed, and is configured as an S structure (steel structure) column section made of H-shaped steel 3a. In this construction, first, the upper column portion 3 is placed on the upper surface of the upper flange 2 b of the seismic isolation device 2. Next, a bolt 11b inserted from below into a bolt insertion hole (not shown) formed in the upper flange 2b of the seismic isolation device 2 was joined to the lower end surface of the H-shaped steel 3a constituting the upper column portion 3. By fastening to the nut 11 a joined to the joining plate, the upper flange 2 b of the seismic isolation device 2 is fixed to the lower end surface of the upper column part 3.

この上側柱部配設工事が完了して上側柱部3が配設された段階で、後述する下側柱部コンクリート打設工事(図5参照)の完了を待たずに、免震装置2よりも上層階において上側柱部3への鉄骨梁20の接合や当該鉄骨梁20へのスラブ型枠21の架設などの躯体工事を開始することができる。即ち、下側柱部コンクリート打設工事に影響されずに、上層階の躯体工事の起点となる上側柱部3の配設が先行して行われ、結果、全体工期の大幅な短縮が実現されることになる。   The seismic isolation device 2 does not wait for completion of the lower column concrete placing work (see FIG. 5), which will be described later, when the upper column part 3 is arranged and the upper column part 3 is arranged. In addition, on the upper floor, it is possible to start the frame work such as the joining of the steel beam 20 to the upper column part 3 and the construction of the slab form 21 on the steel beam 20. That is, the upper column part 3 that is the starting point of the upper-level frame construction is preceded without being affected by the lower column part concrete placing work, and as a result, the overall construction period is significantly shortened. Will be.

(下側柱部コンクリート打設工事)
図5に示すように、上記上側柱部配設工事に続く本施工方法の下側柱部コンクリート打設工事では、下側柱部1のコンクリートが打設されて、下側柱部1が完成される。
即ち、この工事では、予め下側柱部鉄柱部分配設工事で配設された鉄柱部分1aの周囲に適宜鉄筋及び型枠(図示省略)を配設した上でコンクリートを打設することによって、形鋼からなる鉄柱部分1aとその周囲に構築されたコンクリート部分1bを備えたSRC造(複合構造の一例)の下側柱部1が構築される。
(Lower column concrete placement work)
As shown in FIG. 5, in the lower column part concrete placement work following the above upper column part installation work, the concrete of the lower column part 1 is placed and the lower column part 1 is completed. Is done.
That is, in this construction, by placing concrete and reinforcing frames (not shown) around the iron pillar portion 1a previously arranged in the lower pillar portion iron pillar portion arrangement construction, by placing concrete, The lower column part 1 of an SRC structure (an example of a composite structure) including an iron column part 1a made of a shape steel and a concrete part 1b built around the iron column part 1a is constructed.

(免震下部基礎下側部位構築工事)
図6に示すように、上記下側柱部コンクリート打設工事に続く本施工方法の免震下部基礎下側部位構築工事では、免震下部基礎5の下側部位5bが構築される。
即ち、この工事では、スラブ型枠16よりも下方の所定高さの領域、具体的には下側柱部1のコンクリート部位の上端部からスラブ型枠16までの領域において、鉄柱部分1aの周囲に適宜鉄筋及び型枠(図示省略)を配設した上でコンクリートを打設することによって、免震下部基礎5の下側部位5bが構築される。そして、この下側部位5bと免震装置2の設置前に構築した上側部位5aとが一体となって、免震装置2の下部フランジ2a側を支持するための免震下部基礎5として機能することになる。
(Seismically isolated lower foundation lower part construction work)
As shown in FIG. 6, in the seismic isolation lower foundation lower part construction work of this construction method following the lower column concrete placing work, the lower part 5b of the seismic isolation lower foundation 5 is constructed.
That is, in this construction, in the region of a predetermined height below the slab mold 16, specifically, in the region from the upper end of the concrete portion of the lower column part 1 to the slab mold 16, The lower part 5b of the seismic isolation lower foundation 5 is constructed by placing concrete after appropriately arranging reinforcing bars and formwork (not shown). And this lower part 5b and the upper part 5a constructed | assembled before installation of the seismic isolation apparatus 2 are united, and it functions as the seismic isolation lower base 5 for supporting the lower flange 2a side of the seismic isolation apparatus 2. It will be.

(免震上部基礎構築工事)
図7に示すように、上記免震下部基礎下側部位構築工事に続く本施工方法の免震上部基礎構築工事では、免震装置2の上部フランジ2b側に対する免震上部基礎6が構築される。
即ち、この工事では、免震装置2の上部フランジ2bよりも上方の所定高さ領域、具体的には免震装置2の上部フランジ2bから免震装置設置階の1つ上の階のスラブ型枠21までの領域において、上側柱部3(H形鋼3a)の周囲に適宜鉄筋及び型枠(図示省略)を配設した上でコンクリートを打設することによって、免震装置2の上部フランジ2b側を支持するための免震上部基礎6が構築される。
(Seismic isolation upper foundation construction)
As shown in FIG. 7, in the seismic isolation upper foundation construction of this construction method following the base isolation lower foundation lower part construction, the seismic isolation upper foundation 6 for the upper flange 2 b side of the seismic isolation device 2 is constructed. .
That is, in this construction, a slab type of a predetermined height region above the upper flange 2b of the seismic isolation device 2, more specifically, a slab type one floor above the seismic isolation device installation floor from the upper flange 2b of the seismic isolation device 2. The upper flange of the seismic isolation device 2 is placed in the region up to the frame 21 by placing concrete after appropriately arranging reinforcing bars and a mold (not shown) around the upper column 3 (H-shaped steel 3a). The seismic isolation upper foundation 6 for supporting the 2b side is constructed.

尚、本実施形態では、この免震上部基礎構築工事が完了した段階で、免震装置設置階よりも上層階の床22のコンクリート打設を行うが、かかるコンクリート打設は、免震上部基礎構築工事の前やこれと同時に行っても構わない。   In this embodiment, when the seismic isolation upper foundation construction is completed, the concrete is placed on the floor 22 on the upper floor of the seismic isolation device installation floor. You can do it before construction or at the same time.

〔別実施形態〕
(1)上記実施形態では、免震下部基礎5を、免震装置2の設置前に構築される上側部位5aと、免震装置2の設置後に構築される下側部位5bとで構成したが、このように部位を分けて構築するのではなく、免震装置2の設置前に免震下部基礎5全体を構築しても構わない。
[Another embodiment]
(1) In the above embodiment, the seismic isolation lower foundation 5 is configured with the upper part 5 a constructed before the installation of the seismic isolation device 2 and the lower part 5 b constructed after the installation of the seismic isolation device 2. Instead of constructing the parts separately in this way, the entire seismic isolation lower foundation 5 may be constructed before the seismic isolation device 2 is installed.

(2)上記実施形態では、免震下部基礎5の上側部位5aの上端面を免震装置設置面としたが、下側柱部1の鉄柱部分1aの上端面を免震装置設置面としても構わない。この場合、下側柱部鉄柱部分配設工事を完了した段階で免震装置設置工事を実行することができ、免震装置下部基礎の構築を必要に応じて免震装置設置工事の後に行うことができるので、全体工事の更なる短縮を図ることができる。 (2) In the above embodiment, the upper end surface of the upper part 5a of the seismic isolation lower base 5 is the seismic isolation device installation surface, but the upper end surface of the iron column portion 1a of the lower column part 1 is also the seismic isolation device installation surface. I do not care. In this case, the seismic isolation device installation work can be carried out at the stage where the lower column steel pillar part installation work has been completed, and the construction of the lower base of the seismic isolation device should be performed after the seismic isolation device installation work as necessary As a result, the overall construction can be further shortened.

(3)上記実施形態では、免震下部基礎5の上側部位5aを構築するにあたり、スラブ型枠16の上方にスラブ構築用のコンクリートを先行打設してベース部5aaを構築し、スラブ型枠16に加えて硬化したベース部5aaをコンクリート支持部として利用する形態で、コンクリートの打設を2段階で行うように構成したが、コンクリートを支持可能な範囲内で、免震下部基礎5の上側部位5aを1段階のコンクリート打設で構築しても構わない。 (3) In the above embodiment, when the upper part 5a of the seismic isolation lower foundation 5 is constructed, the base portion 5aa is constructed by placing concrete for slab construction in advance above the slab form 16, and the slab form In addition to 16, the hardened base portion 5aa is used as a concrete support portion, and the concrete is placed in two stages. However, within the range in which concrete can be supported, the upper side of the seismic isolation lower foundation 5 The part 5a may be constructed by single-stage concrete placement.

(4)上記実施形態では、免震装置設置工事と同時に、免震装置設置階の床17のコンクリート打設工事を行うように構成したが、免震装置設置工事の前の免震下部基礎上側部位構築工事と同時や、免震装置設置工事の後の上側柱部配設工事と同時など、別の時期に免震装置設置階の床17のコンクリート打設工事を行っても構わない。 (4) In the above embodiment, the concrete placement work is performed on the floor 17 of the seismic isolation device installation floor simultaneously with the seismic isolation device installation work. The concrete placement work on the floor 17 of the seismic isolation device installation floor may be performed at another time, such as at the same time as the part construction work or at the same time as the upper pillar arrangement work after the seismic isolation equipment installation work.

(5)上記実施形態では、免震装置設置階のスラブ型枠16を、免震下部基礎5のコンクリート支持部として利用したが、別の部位や取り外し可能な型枠など別のものを当該免震下部基礎5のコンクリート支持部として利用しても構わない。 (5) In the above embodiment, the slab formwork 16 on the seismic isolation device installation floor is used as the concrete support part of the seismic isolation lower foundation 5, but other parts such as another part and removable formwork are exempted. You may use as a concrete support part of the seismic base 5.

(6)上記実施形態では、下部柱部コンクリート打設工事を行った後に免震下部基礎下側部位構築工事を行ったが、これら工事を同時に行っても構わない。 (6) In the above embodiment, the seismic isolation lower foundation lower part construction work was performed after the lower column part concrete placing work, but these works may be performed simultaneously.

(7)本実施形態では、下側柱部1を、形鋼からなる鉄柱部分1aと、その周囲に適宜鉄筋を配設してコンクリートを打設してなるコンクリート部分1bを備えたSRC造(鉄骨鉄筋コンクリート造)としたが、鋼管からなる鉄柱部分と、その内部に適宜鉄筋を配設してコンクリートを打設してなるコンクリート部分とからなるCFT構造(コンクリート充填鋼管構造)としても構わない。 (7) In this embodiment, the lower column portion 1 is an SRC structure including a steel column portion 1a made of a shape steel and a concrete portion 1b formed by placing concrete reinforcing bars around the steel column portion 1a. However, it may be a CFT structure (concrete-filled steel pipe structure) comprising a steel pillar portion made of a steel pipe and a concrete portion formed by placing a reinforcing bar in the interior and placing concrete.

(8)本実施形態では、上側柱部3を、S造(鉄骨造)としたが、RC造(鉄筋コンクリート造)、SRC造、CFT構造等、如何なる構造を採用しても構わない。 (8) In the present embodiment, the upper column portion 3 is S structure (steel structure), but any structure such as RC structure (reinforced concrete structure), SRC structure, CFT structure, etc. may be adopted.

(9)本実施形態では、積層ゴム支承式の免震装置2を採用したが、すべり支承式、転がり支承式、又はこれらを組み合わせた複合方式など、他の方式の免震装置を採用しても構わない。 (9) In this embodiment, the laminated rubber bearing type seismic isolation device 2 is employed, but other types of seismic isolation devices such as a sliding bearing type, a rolling bearing type, or a combination of these are employed. It doesn't matter.

1 :下側柱部
1a :鉄柱部分
1b :コンクリート部分
2 :免震装置
3 :上側柱部
5 :免震下部基礎
5a :上側部位
5b :下側部位
16 :スラブ型枠
17 :免震装置の設置階の床
21 :スラブ型枠
1: Lower column part 1a: Iron column part 1b: Concrete part 2: Seismic isolation device 3: Upper column part 5: Seismic isolation lower foundation 5a: Upper part 5b: Lower part 16: Slab formwork 17: Seismic isolation device Installation floor 21: Slab formwork

Claims (4)

鉄柱部分とコンクリート部分の複合構造で構成された下側柱部と、当該下側柱部の上方に配設される上側柱部との間に免震装置が介装された免震構造物を順打ち工法で構築する免震構造物の施工方法であって、
前記下側柱部の鉄柱部分を配設し、その鉄柱部分の上方に免震装置を設置する第1工程と、
前記第1工程で設置した免震装置の上方に前記上側柱部を配設する第2工程と、
前記上側柱部を配設した後、コンクリートを打設して下側柱部を完成させる第3工程を備える免震構造物の施工方法。
A seismic isolation structure in which a seismic isolation device is interposed between a lower column portion composed of a composite structure of a steel column portion and a concrete portion and an upper column portion disposed above the lower column portion. It is a construction method of a seismic isolation structure built by the order construction method,
A first step of disposing an iron pillar portion of the lower pillar portion and installing a seismic isolation device above the iron pillar portion;
A second step of disposing the upper column portion above the seismic isolation device installed in the first step;
A method of constructing a base-isolated structure comprising a third step of placing the upper column portion and then placing concrete to complete the lower column portion.
前記第1工程において、前記下側柱部の鉄柱部分を配設した後、当該鉄柱部分の上側部位に接続する状態で免震下部基礎の上側部位を構築し、その免震下部基礎の上側部位の上方に前記免震装置を設置すると共に、
前記第3工程において、前記免震下部基礎の下側部位を構築する請求項1に記載の免震構造物の施工方法。
In the first step, after arranging the iron pillar part of the lower pillar part, the upper part of the seismic isolation lower foundation is constructed in a state connected to the upper part of the iron pillar part, and the upper part of the seismic isolation lower foundation And installing the seismic isolation device above
The construction method of the seismic isolation structure according to claim 1, wherein, in the third step, a lower part of the base isolation base is constructed.
前記第1工程において、スラブ構築用の高さ位置にスラブ型枠を設置し、このスラブ型枠をコンクリート支持部として用いて当該スラブ型枠の上方に前記免震下部基礎の上側部位をコンクリートで構築する請求項2に記載の免震構造物の施工方法。   In the first step, a slab formwork is installed at a height position for slab construction, and the upper part of the seismic isolation lower foundation is made of concrete above the slab formwork using the slab formwork as a concrete support part. The construction method of the seismic isolation structure of Claim 2 to construct | assemble. 前記第2工程の実施前に前記免震装置の設置階の床を構築する請求項1〜3の何れか1項に記載の免震構造物の施工方法。   The construction method of the seismic isolation structure of any one of Claims 1-3 which construct | assembles the floor of the installation floor of the said seismic isolation apparatus before implementation of the said 2nd process.
JP2015005735A 2015-01-15 2015-01-15 How to install seismic isolation structures Expired - Fee Related JP6441689B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015005735A JP6441689B2 (en) 2015-01-15 2015-01-15 How to install seismic isolation structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015005735A JP6441689B2 (en) 2015-01-15 2015-01-15 How to install seismic isolation structures

Publications (2)

Publication Number Publication Date
JP2016130444A true JP2016130444A (en) 2016-07-21
JP6441689B2 JP6441689B2 (en) 2018-12-19

Family

ID=56415740

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015005735A Expired - Fee Related JP6441689B2 (en) 2015-01-15 2015-01-15 How to install seismic isolation structures

Country Status (1)

Country Link
JP (1) JP6441689B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018096188A (en) * 2016-12-17 2018-06-21 大成建設株式会社 Junction structure of seismic isolator to steel-pipe column, and base isolated building
JP7429596B2 (en) 2020-05-08 2024-02-08 株式会社竹中工務店 seismic isolation building

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007077698A (en) * 2005-09-15 2007-03-29 Jfe Steel Kk Structure having base isolation/seismic response control function
JP2014020097A (en) * 2012-07-18 2014-02-03 Mitsubishi Heavy Ind Ltd Seismic isolator supporting structure and construction method for the same

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007077698A (en) * 2005-09-15 2007-03-29 Jfe Steel Kk Structure having base isolation/seismic response control function
JP2014020097A (en) * 2012-07-18 2014-02-03 Mitsubishi Heavy Ind Ltd Seismic isolator supporting structure and construction method for the same

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018096188A (en) * 2016-12-17 2018-06-21 大成建設株式会社 Junction structure of seismic isolator to steel-pipe column, and base isolated building
JP7429596B2 (en) 2020-05-08 2024-02-08 株式会社竹中工務店 seismic isolation building

Also Published As

Publication number Publication date
JP6441689B2 (en) 2018-12-19

Similar Documents

Publication Publication Date Title
JP2016098586A (en) Reinforced concrete column-steel beam joint member and manufacturing method thereof and building construction method
JP4658006B2 (en) Seismic isolation method for existing buildings and temporary seismic control panel
JP5713710B2 (en) Seismic isolation structure and its construction method
JP6441689B2 (en) How to install seismic isolation structures
JP6339923B2 (en) How to build a building frame
JP6057579B2 (en) Seismic isolation device support structure and construction method of seismic isolation device support structure
JP2011149265A (en) Beam member and building structure
JP2016037761A (en) Temporary support structure for base-isolating work, and base-isolating method for existing building
JP6849491B2 (en) Exposed column base structure of steel columns and its construction method
JP2001329715A (en) Method of constructing base-isolated structure
JP6404013B2 (en) Construction method of seismic isolation building
JP6247117B2 (en) Temporary structure during seismic isolation of existing building
JP2008057189A (en) Base isolation construction method for existing building
JP5319445B2 (en) Building construction method
JP2007154565A (en) Joint structure and construction method of column and beam-less slab
JP5353130B2 (en) Finishing method for reinforced columns, mounting structure for reinforced column finishing materials
JP2015101890A (en) Support structure and construction method
JP6114071B2 (en) Seismic isolation method for existing buildings and temporary structure under construction
JP6300228B2 (en) Flat slab structure
JP6261333B2 (en) Seismic reinforcement method
JP3903315B2 (en) Preservation method of existing outer wall structure
JP2002115401A (en) Base isolation construction method
JP5375174B2 (en) Construction method of column beam frame
JP6706111B2 (en) Seismic isolation building construction method
JP2017500460A (en) Machine table foundation

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20171225

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20181018

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20181031

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20181122

R150 Certificate of patent or registration of utility model

Ref document number: 6441689

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees