JP2016079754A - Method for constructing base isolation structure - Google Patents

Method for constructing base isolation structure Download PDF

Info

Publication number
JP2016079754A
JP2016079754A JP2014214804A JP2014214804A JP2016079754A JP 2016079754 A JP2016079754 A JP 2016079754A JP 2014214804 A JP2014214804 A JP 2014214804A JP 2014214804 A JP2014214804 A JP 2014214804A JP 2016079754 A JP2016079754 A JP 2016079754A
Authority
JP
Japan
Prior art keywords
seismic isolation
isolation device
concrete
base
foundation beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2014214804A
Other languages
Japanese (ja)
Other versions
JP6373719B2 (en
Inventor
俊久 石田
Toshihisa Ishida
俊久 石田
崇裕 中島
Takahiro Nakajima
崇裕 中島
正三 西山
Shozo Nishiyama
正三 西山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2014214804A priority Critical patent/JP6373719B2/en
Publication of JP2016079754A publication Critical patent/JP2016079754A/en
Application granted granted Critical
Publication of JP6373719B2 publication Critical patent/JP6373719B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Vibration Prevention Devices (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a method for constructing a base isolation structure capable of curbing a reduction in aseismic performance even when skeleton concrete shrinks.SOLUTION: In a building 1 which has a base isolation structure, an upper foundation beam 12 is supported by a base isolation device 20 installed on a mat slab 11. A method for constructing the building 1 comprises: steps S3 to S5 to construct the upper foundation beam 12 with a length longer than a design length in anticipation of shrinkage of concrete thereof and to temporarily support the upper foundation beam 12 so that the same can slide on the mat slab 11; and step S6 to install laminated rubber 201 between the upper foundation beam 12 and the mat slab 11 after the lapse of predetermined time and to support the upper foundation beam 12 with the base isolation device 20 including the laminated rubber 201.SELECTED DRAWING: Figure 2

Description

本発明は、例えば、免震構造の建物の構築方法に関する。   The present invention relates to a method for constructing a building having a seismic isolation structure, for example.

従来より、免震構造の建物がある。この建物は、例えば、基礎などの下部躯体と、この下部躯体の上に設置される複数の免震装置と、これら免震装置の上に設けられた上部躯体と、を備える。この免震装置は、アイソレータとダンパーがあり、このうちアイソレータは、上部躯体の荷重を支え、地震のときに上部構造をゆっくりと水平方向に移動させる。アイソレータの種類としては、積層ゴム、すべり支承、転がり支承などがある。   Traditionally, there are seismically isolated buildings. This building includes, for example, a lower housing such as a foundation, a plurality of seismic isolation devices installed on the lower housing, and an upper housing provided on these seismic isolation devices. This seismic isolation device has an isolator and a damper. Of these, the isolator supports the load of the upper housing and moves the upper structure slowly in the horizontal direction during an earthquake. The types of isolators include laminated rubber, sliding bearings and rolling bearings.

ところで、上部躯体が鉄筋コンクリート造でかつ所定方向に長い場合、上部躯体の構築完了後に躯体コンクリートが水和反応や乾燥により収縮し、普通コンクリートで乾燥収縮量だけでも数年間で400〜600μmとされており、一辺100mの長さの建物では4〜6cm縮む計算になる。免震構造でない建物では、基礎部分が地盤に拘束されているので、建物全体としてはそれほど収縮しない。しかし、免震建物では上部躯体が下部躯体の上に、弾性変形可能な弾性体や、水平変位可能なすべり支承、転がり支承などを介して載置されており、上部躯体と下部躯体の拘束条件が大きく違うことから、時間が経過するにつれ上部躯体と下部躯体の収縮量に大きな違いが出てしまう。収縮が進行すると上部躯体の外周部が内側に向かって移動する場合がある。すると、一辺の長さが長い建物の外周部付近では、積層ゴムの上部がコンクリートに引っ張られて水平にせん断変形し、みかけが悪いだけでなく、しかも初期収縮が収まって以降もこの変形が残存するので、建物の免震性能が低下するおそれがあった。また、上部躯体の柱芯と下部躯体の杭芯などがずれたりして、杭や基礎部分に設計想定を上回る過大な力が加わるおそれもあった。   By the way, when the upper frame is made of reinforced concrete and is long in the specified direction, after the construction of the upper frame is completed, the frame concrete shrinks due to hydration reaction and drying, and the amount of drying shrinkage is only 400 to 600 μm in several years even with the amount of drying shrinkage alone. In a building with a side of 100 m, the calculation is reduced by 4 to 6 cm. In buildings that are not seismically isolated, the foundation is constrained by the ground, so the entire building does not shrink so much. However, in base-isolated buildings, the upper housing is placed on the lower housing via elastically deformable elastic bodies, horizontally displaceable sliding bearings, rolling bearings, etc. Because of the large difference, the amount of contraction between the upper and lower housings will vary greatly over time. When contraction progresses, the outer periphery of the upper housing may move inward. Then, in the vicinity of the outer periphery of a building with a long side, the upper part of the laminated rubber is pulled by the concrete and sheared horizontally, which is not only bad in appearance, but also remains after the initial contraction has subsided. As a result, the seismic isolation performance of the building may be reduced. In addition, the column core of the upper frame and the pile core of the lower frame may be displaced, and an excessive force exceeding the design assumption may be applied to the pile and the foundation.

この問題を解決するため、例えば、上部躯体を構築する前に、建物の外周部では、免震装置の上部をコンクリートの収縮量の分だけ変位させておく方法が提案されている(特許文献1参照)。
具体的には、予め、免震装置の上部を、コンクリートの収縮により変位する方向とは反対側に向かって、上部躯体の構築後に生じるコンクリート収縮量に等しい分だけ変位させ、取付部材によりこの変位を保持状態としておく。そして、上部躯体の構築後に、この保持状態を解除する。したがって、躯体コンクリートが収縮すると、免震装置の上部が本来の適正な位置に戻ることになる。
In order to solve this problem, for example, before constructing the upper frame, a method has been proposed in which the upper part of the seismic isolation device is displaced by the amount of shrinkage of the concrete at the outer periphery of the building (Patent Document 1). reference).
Specifically, the upper part of the seismic isolation device is displaced in advance in the direction opposite to the direction displaced by concrete contraction by an amount equal to the amount of concrete shrinkage that occurs after construction of the upper frame, and this displacement is performed by the mounting member. Is held. Then, after the upper casing is constructed, this holding state is released. Therefore, when the frame concrete contracts, the upper part of the seismic isolation device returns to its original proper position.

特開2006−97325号公報JP 2006-97325 A

しかしながら、特許文献1に示された方法では、以下のような問題があった。
実際には、上部躯体のコンクリートは、外装材や内装材によって拘束されるので、コンクリートの収縮量を正確に予測することは困難である。
また、免震装置の上部を水平方向に変位させるために、かなり大きな力を加える必要がある。しかも、免震装置に鉛直荷重が作用していない状態で、この免震装置を水平方向に変位させた場合、弾性部材の上面が傾斜する可能性が高い。
そのため、躯体コンクリートの収縮により免震性能が低下するおそれがあった。
However, the method disclosed in Patent Document 1 has the following problems.
Actually, since the concrete of the upper frame is restrained by the exterior material and the interior material, it is difficult to accurately predict the shrinkage amount of the concrete.
Moreover, in order to displace the upper part of a seismic isolation apparatus to a horizontal direction, it is necessary to apply a quite big force. In addition, when the seismic isolation device is displaced in the horizontal direction in a state where no vertical load is applied to the seismic isolation device, there is a high possibility that the upper surface of the elastic member is inclined.
For this reason, there is a possibility that the seismic isolation performance may be reduced due to the shrinkage of the concrete frame.

本発明は、躯体コンクリートが収縮しても、免震性能の低下を抑制できる免震構造物の構築方法を提供することを目的とする。   An object of this invention is to provide the construction method of the seismic isolation structure which can suppress the fall of seismic isolation performance, even if a frame concrete shrink | contracts.

請求項1に記載の免震構造物の構築方法は、下部躯体(例えば、後述のマットスラブ11)の上に設けられた免震装置(例えば、後述の免震装置20)により上部躯体(例えば、後述の上部基礎梁12)を支持する免震構造物の構築方法であって、当該上部躯体のうち少なくとも最も外側の部分を前記下部躯体から摺動可能に仮支持する工程(例えば、後述のステップS3〜S5)と、所定期間経過後、当該仮支持した箇所またはその近傍に、積層ゴムを取り付けて、当該積層ゴムを含む免震装置により前記上部躯体を支持する工程(例えば、後述のステップS6)と、を備えることを特徴とする。   The construction method of the seismic isolation structure according to claim 1 is a method of constructing an upper housing (for example, a seismic isolation device 20 described later) provided on a lower housing (for example, mat slab 11 described later). , A method for constructing a base-isolated structure that supports an upper base beam 12 described later, and a step of temporarily supporting at least the outermost part of the upper casing from the lower casing (for example, described later) Steps S <b> 3 to S <b> 5) and a step of attaching a laminated rubber to the temporarily supported portion or the vicinity thereof after a predetermined period of time and supporting the upper housing by a seismic isolation device including the laminated rubber (for example, steps described later) S6).

ここで、所定期間とは、コンクリートの体積変化(収縮)が概ね収束するまでの期間であり、コンクリートの体積変化の大部分を占める水和反応による収縮(自己収縮)と、コンクリート中の水が空中に散逸することによる収縮(乾燥収縮)と、の二つの収縮がある。これらの収縮は、コンクリート打設から数か月で収束するので、仮支持する期間は、2、3か月以上で長い方が望ましい。しかし、他の工事工程との関係上は短い方がよいので、少なくとも初期収縮が緩やかとなるコンクリート打設後数時間は必要である。   Here, the predetermined period is a period until the volume change (shrinkage) of the concrete substantially converges. The shrinkage due to the hydration reaction (self-shrinkage), which accounts for most of the volume change of the concrete, and the water in the concrete There are two types of shrinkage: shrinkage due to dissipation in the air (dry shrinkage). Since these shrinkage converges within a few months after placing the concrete, it is desirable that the temporary support period be longer than a few months. However, since it is better to be short in relation to other construction processes, at least several hours after placing the concrete where initial shrinkage is moderate are necessary.

請求項2に記載の免震構造物の構築方法は、下部躯体(例えば、後述のマットスラブ11)の上に設けられた免震装置(例えば、後述の免震装置20)により上部躯体(例えば、後述の上部基礎梁12)を支持する免震構造物の構築方法であって、前記上部躯体のコンクリートの収縮量を見込んで、当該上部躯体を設計上の寸法よりも長く構築するとともに、当該上部躯体を前記下部躯体から仮支持する工程(例えば、後述のステップS3〜S5)と、所定期間経過後、前記免震装置を取り付けて、当該免震装置により前記上部躯体を支持する工程(例えば、後述のステップS6)と、を備えることを特徴とする。   The construction method of the seismic isolation structure according to claim 2 is such that the upper housing (for example, the seismic isolation device 20 described later) provided on the lower housing (for example, mat slab 11 described later) is used. , A method for constructing a base-isolated structure for supporting an upper foundation beam 12), which will be described later, in consideration of the amount of shrinkage of the concrete of the upper frame, and constructing the upper frame longer than the design dimensions, A step of temporarily supporting the upper housing from the lower housing (for example, steps S3 to S5 described later), and a step of attaching the seismic isolation device after a predetermined period of time and supporting the upper housing by the seismic isolation device (for example, Step S6) described below.

この発明によれば、上部躯体を設計上の寸法よりも大きく構築し、所定期間が経過して、上部躯体のコンクリートがある程度収縮した後に、免震装置を取り付ける。
したがって、上部躯体のコンクリートが収縮しても、免震装置をこのコンクリートの収縮後に取り付けるから、免震装置の変形が抑制される。よって、従来のように、コンクリートの収縮量を正確に予測する必要や、予め免震装置を変形させる必要がないので、免震性能の低下を防止できる。
According to the present invention, the upper casing is constructed larger than the designed dimensions, and the seismic isolation device is attached after a predetermined period of time has elapsed and the concrete of the upper casing has contracted to some extent.
Therefore, even if the concrete of the upper frame contracts, since the seismic isolation device is attached after the concrete contraction, deformation of the seismic isolation device is suppressed. Therefore, unlike the conventional case, it is not necessary to accurately predict the amount of shrinkage of the concrete, and it is not necessary to deform the seismic isolation device in advance.

請求項2に記載の免震構造物の構築方法は、前記上部躯体を前記下部躯体から仮支持する工程では、前記下部躯体の上に仮受支柱(例えば、後述の仮受支柱30)を設けて、当該仮受支柱により前記上部躯体を仮支持するとともに、当該仮受支柱と前記上部躯体または前記下部躯体との間に、すべり板(例えば、後述のすべり板40)を介装することを特徴とする。   In the method of constructing the seismic isolation structure according to claim 2, in the step of temporarily supporting the upper casing from the lower casing, provisional support columns (for example, temporary support columns 30 described later) are provided on the lower case. The temporary support column temporarily supports the upper case, and a slip plate (for example, a later-described slide plate 40) is interposed between the temporary support column and the upper case or the lower case. Features.

この発明によれば、下部躯体の上に設けた仮受支柱により上部躯体を仮支持し、この仮受支柱と上部躯体または下部躯体との間にすべり板を介装した。よって、上部躯体を仮支持した後に、この上部躯体のコンクリートが収縮して、上部躯体が水平移動しても、すべり板上を仮受支柱が摺動するので、上部躯体の安定を保つことができる。   According to the present invention, the upper casing is temporarily supported by the temporary support column provided on the lower frame, and the sliding plate is interposed between the temporary support column and the upper or lower frame. Therefore, even after the upper casing is temporarily supported, even if the concrete of the upper casing contracts and the upper casing moves horizontally, the temporary support column slides on the sliding plate, so that the stability of the upper casing can be maintained. it can.

本発明によれば、上部躯体のコンクリートが収縮しても、免震装置を収縮後に取り付けるから、免震装置の変形が抑制される。よって、従来のように、コンクリートの収縮量を正確に予測する必要や、予め免震装置を変形させる必要がないので、免震性能の低下を防止できる。   According to the present invention, even if the concrete of the upper frame contracts, the seismic isolation device is attached after contraction, so that deformation of the seismic isolation device is suppressed. Therefore, unlike the conventional case, it is not necessary to accurately predict the amount of shrinkage of the concrete, and it is not necessary to deform the seismic isolation device in advance.

本発明の第1実施形態に係る免震構造物の構築方法により構築された建物の基礎部分の断面図である。It is sectional drawing of the foundation part of the building constructed | assembled by the construction method of the seismic isolation structure which concerns on 1st Embodiment of this invention. 前記実施形態に係る免震構造物の構築方法により建物を構築する手順のフローチャートである。It is a flowchart of the procedure which builds a building with the construction method of the seismic isolation structure which concerns on the said embodiment. 前記実施形態に係る建物を構築する手順を説明する図(その1)である。It is FIG. (1) explaining the procedure which builds the building which concerns on the said embodiment. 前記実施形態に係る建物を構築する手順を説明する図(その2)である。It is FIG. (2) explaining the procedure which builds the building which concerns on the said embodiment. 前記実施形態に係る建物を構築する手順を説明する図(その3)である。It is a figure (the 3) explaining the procedure which builds the building which concerns on the said embodiment. 本発明の第2実施形態に係る免震構造物の構築方法により構築された建物の断面図である。It is sectional drawing of the building constructed | assembled by the construction method of the seismic isolation structure which concerns on 2nd Embodiment of this invention. 前記実施形態に係る建物を構築する手順を説明するための模式図である。It is a schematic diagram for demonstrating the procedure which builds the building which concerns on the said embodiment.

以下、本発明の実施形態を図面に基づいて説明する。なお、以下の実施形態の説明にあたって、同一構成要件については同一符号を付し、その説明を省略もしくは簡略化する。
〔第1実施形態〕
図1に示すように、建物1は、免震構造物であり、地盤3の上に構築された基礎2を有している。この基礎2は、杭基礎であり、杭10と、杭10の上に設けられた下部躯体としてのマットスラブ11と、マットスラブ11の上に設けられた免震装置20と、免震装置20の上に設けられた上部躯体としての上部基礎梁12と、上部基礎梁12の上に設けられた柱13と、を備えている。
つまり、建物1では、マットスラブ11の上に設けられた免震装置20により上部基礎梁12を支持する。この免震装置20は、建物1の最も外側の部分に設けられる。
Hereinafter, embodiments of the present invention will be described with reference to the drawings. In the following description of the embodiments, the same constituent elements are denoted by the same reference numerals, and the description thereof is omitted or simplified.
[First Embodiment]
As shown in FIG. 1, the building 1 is a seismic isolation structure and has a foundation 2 constructed on the ground 3. The foundation 2 is a pile foundation, and includes a pile 10, a mat slab 11 as a lower housing provided on the pile 10, a seismic isolation device 20 provided on the mat slab 11, and a seismic isolation device 20. The upper foundation beam 12 as an upper frame provided on the upper foundation beam 12 and the column 13 provided on the upper foundation beam 12 are provided.
That is, in the building 1, the upper foundation beam 12 is supported by the seismic isolation device 20 provided on the mat slab 11. The seismic isolation device 20 is provided in the outermost part of the building 1.

基礎2のマットスラブ11と上部基礎梁12との間には、免震装置20を設置するための設置スペース21が形成されている。
柱13の直下でかつマットスラブ11の上面には、鉄筋コンクリート造の下部免震基礎23が設けられており、この下部免震基礎23の上面には、下部ベースプレート231が打ち込まれている。
柱13の直下でかつ上部基礎梁12の下面には、鉄筋コンクリート造の上部免震基礎24が設けられており、この上部免震基礎24の下面には、上部ベースプレート241が打ち込まれている。
An installation space 21 for installing the seismic isolation device 20 is formed between the mat slab 11 of the foundation 2 and the upper foundation beam 12.
A lower base isolation base 23 made of reinforced concrete is provided immediately below the column 13 and on the upper surface of the mat slab 11, and a lower base plate 231 is driven into the upper surface of the lower base isolation base 23.
An upper base isolation base 24 made of reinforced concrete is provided directly below the column 13 and on the lower surface of the upper base beam 12, and an upper base plate 241 is driven into the lower surface of the upper base isolation base 24.

免震装置20は、この下部免震基礎23と上部免震基礎24との間に設けられている。
免震装置20は、積層ゴム201と、積層ゴム201の下に設けられた下フランジ202と、積層ゴム201の上に設けられた上フランジ203と、を備える。
The seismic isolation device 20 is provided between the lower base isolation base 23 and the upper base isolation base 24.
The seismic isolation device 20 includes a laminated rubber 201, a lower flange 202 provided under the laminated rubber 201, and an upper flange 203 provided on the laminated rubber 201.

積層ゴム201は、鋼板とゴムとが交互に積層されたものである。
下フランジ202は、下部ベースプレート231にボルト固定され、上フランジ203は、上部ベースプレート241にボルト固定されている。
以上の免震装置20は、下部免震基礎23に反力をとって、上部免震基礎24を下から支持しつつ、積層ゴム201が変形することでこの上部免震基礎24が水平方向に移動可能となっている。
The laminated rubber 201 is obtained by alternately laminating steel plates and rubber.
The lower flange 202 is bolted to the lower base plate 231, and the upper flange 203 is bolted to the upper base plate 241.
The above seismic isolation device 20 takes the reaction force on the lower base isolation base 23 and supports the upper base isolation base 24 from below, and the laminated rubber 201 is deformed to deform the upper base isolation base 24 in the horizontal direction. It is movable.

図2のフローチャートに示すように、ステップS1では、基礎2を構築するための地盤3を掘削する。
図3に示すように、必要に応じて地盤3に杭10を構築し、その後、この地盤3をマットスラブ11の底面となる深さまで掘削して、掘削空間を形成する。
As shown in the flowchart of FIG. 2, in step S1, the ground 3 for constructing the foundation 2 is excavated.
As shown in FIG. 3, a pile 10 is constructed on the ground 3 as necessary, and then the ground 3 is excavated to a depth that becomes the bottom surface of the mat slab 11 to form an excavation space.

ステップS2では、掘削空間において、マットスラブ11を構築し、このマットスラブ11上に仮受支柱30を摺動可能に設置する。
図3に示すように、掘削空間の底面に捨てコンクリート25を打設し、この捨てコンクリート25上に配筋してコンクリートを打設することで、マットスラブ11を構築する。
In step S <b> 2, the mat slab 11 is constructed in the excavation space, and the temporary support column 30 is slidably installed on the mat slab 11.
As shown in FIG. 3, the mat slab 11 is constructed by placing the discarded concrete 25 on the bottom surface of the excavation space and placing the concrete on the discarded concrete 25 and placing the concrete.

次に、マットスラブ11の上でかつ下部免震基礎23を構築する部分の周囲近傍に、すべり板40を設け、このすべり板40の上に仮受支柱30を設置する。   Next, a slip plate 40 is provided on the mat slab 11 and in the vicinity of the periphery of the portion for constructing the lower seismic isolation foundation 23, and the temporary support column 30 is installed on the slip plate 40.

この仮受支柱30は、マットスラブ11の上に設けられた下部支柱31と、この下部支柱31の上に設けられたジャッキ32と、ジャッキ32の上に設けられて上部基礎梁12の下面に接合される上部支柱33と、を備える。ジャッキ32は、下部支柱31と上部支柱33とを接近あるいは離間させるものである。
また、すべり板40は、仮受支柱30の下部支柱31とマットスラブ11との間に介装され、このすべり板40の上面には、例えばナイロンシートが貼り付けられている。
The provisional support column 30 includes a lower column 31 provided on the mat slab 11, a jack 32 provided on the lower column 31, and a jack 32 provided on the lower surface of the upper foundation beam 12. An upper column 33 to be joined. The jack 32 makes the lower column 31 and the upper column 33 approach or separate from each other.
The sliding plate 40 is interposed between the lower column 31 of the temporary support column 30 and the mat slab 11, and a nylon sheet, for example, is attached to the upper surface of the sliding plate 40.

ステップS3では、上部基礎梁12を構築する。
図3に示すように、仮受支柱30の上に上部基礎梁12を構築する。この上部基礎梁12は、上部基礎梁12のコンクリートの収縮量を予め計算により算定し、この算定した収縮量を見込んで、設計上の寸法よりも長く構築している。具体的には、本実施形態では、上部基礎梁12のコンクリートの収縮により、上部基礎梁12は図3中左方向に移動するので、この移動を見込んで、図3中右方向に向かって長くしている。
In step S3, the upper foundation beam 12 is constructed.
As shown in FIG. 3, the upper foundation beam 12 is constructed on the temporary support column 30. The upper foundation beam 12 is constructed to be longer than the design dimensions by calculating in advance the amount of shrinkage of the concrete of the upper foundation beam 12 and considering the calculated amount of shrinkage. Specifically, in the present embodiment, the upper foundation beam 12 moves in the left direction in FIG. 3 due to the contraction of the concrete of the upper foundation beam 12, so that the movement is expected and the length becomes longer in the right direction in FIG. doing.

このとき、仮受支柱30のジャッキ32を、下部支柱31と上部支柱33とを離間させる方向に駆動することで、マットスラブ11に反力をとって、上部基礎梁12を仮支持する。これにより、建物1の荷重は、仮受支柱30およびマットスラブ11を介して、杭10に伝達されて、上部基礎梁12は、仮受支柱30により仮支持されることになる。   At this time, the upper base beam 12 is temporarily supported by driving the jack 32 of the temporary support column 30 in a direction in which the lower column 31 and the upper column 33 are separated from each other, thereby applying a reaction force to the mat slab 11. Thereby, the load of the building 1 is transmitted to the pile 10 via the temporary support column 30 and the mat slab 11, and the upper foundation beam 12 is temporarily supported by the temporary support column 30.

ステップS4では、柱13、下部免震基礎23、および上部免震基礎24の配筋を行う。
図3に示すように、上部基礎梁12の上の柱13の柱筋13Aを配筋するとともに、マットスラブ11の上面に、下部免震基礎23の鉄筋23Aを配筋し、上部基礎梁12の下面に上部免震基礎24の鉄筋24Aを配筋する。
このとき、上部基礎梁12を設計上の寸法よりも長く構築しているので、上部免震基礎24の中心軸C2は、下部免震基礎23の中心軸C1とずれている。
In step S4, the bars 13, the lower base isolation base 23, and the upper base isolation base 24 are arranged.
As shown in FIG. 3, the bar 13 </ b> A of the column 13 on the upper foundation beam 12 is arranged, and the reinforcing bar 23 </ b> A of the lower seismic isolation foundation 23 is arranged on the upper surface of the mat slab 11. Reinforcing bars 24A of the upper seismic isolation base 24 are arranged on the lower surface.
At this time, since the upper foundation beam 12 is constructed longer than the designed dimension, the central axis C2 of the upper base isolation base 24 is shifted from the central axis C1 of the lower base isolation base 23.

ステップS5では、柱13を構築するとともに、上部免震基礎24を構築して、この上部免震基礎24に免震装置20を取り付ける。
図4に示すように、柱13の型枠を建て込んで、コンクリートを打設し、柱13を構築する。また。上部免震基礎24の鉄筋24Aに上部ベースプレート241を取り付けて型枠を建て込み、コンクリートを打設して、上部免震基礎24を構築する。さらに、この上部免震基礎24の上部ベースプレート241に免震装置20の上フランジ203をボルト固定して、免震装置20を上部免震基礎24から吊り下げ支持させる。
In step S <b> 5, the pillar 13 is constructed, the upper seismic isolation foundation 24 is constructed, and the seismic isolation device 20 is attached to the upper seismic isolation foundation 24.
As shown in FIG. 4, the formwork of the pillar 13 is built, concrete is laid, and the pillar 13 is constructed. Also. The upper base plate 241 is attached to the reinforcing bars 24A of the upper seismic isolation foundation 24, a formwork is built, concrete is placed, and the upper seismic isolation foundation 24 is constructed. Further, the upper flange 203 of the seismic isolation device 20 is bolted to the upper base plate 241 of the upper seismic isolation base 24 to suspend and support the seismic isolation device 20 from the upper base isolation base 24.

ステップS6では、所定期間つまりコンクリートの収縮が概ね収束するまでの期間が経過した後、下部免震基礎23を構築し、この下部免震基礎23に免震装置を取り付ける。
所定期間が経過すると、上部基礎梁12のコンクリートの収縮により、上部基礎梁12が図5中左方向に移動し、上部免震基礎24の中心軸C2が下部免震基礎23の中心軸C1に略一致する。このとき、仮受支柱30は、上面が上部基礎梁12に接合されているため、すべり板40上を摺動する。
In step S <b> 6, after a predetermined period, that is, a period until the contraction of concrete substantially converges, the lower base isolation base 23 is constructed, and the base isolation device is attached to the lower base isolation base 23.
When the predetermined period has elapsed, due to the contraction of the concrete of the upper foundation beam 12, the upper foundation beam 12 moves to the left in FIG. 5, and the central axis C <b> 2 of the upper base isolation base 24 changes to the central axis C <b> 1 of the lower base isolation base 23. It almost agrees. At this time, since the upper surface of the temporary support column 30 is joined to the upper foundation beam 12, the temporary support column 30 slides on the slide plate 40.

そこで、既に上部免震基礎24に固定した免震装置20の下フランジ202に、下部免震基礎23の下部ベースプレート231をボルト固定し、この状態で、下部免震基礎23の鉄筋23Aの型枠を建て込んでコンクリートを打設し、下部免震基礎23を構築する。これにより、仮受支柱30で仮支持した箇所の近傍に、積層ゴム201が取り付けられて、この積層ゴム201を介して、下部免震基礎23と上部免震基礎24とが連結され、この積層ゴム201を含む免震装置20により、上部基礎梁12が支持される。   Therefore, the lower base plate 231 of the lower base isolation base 23 is bolted to the lower flange 202 of the base isolation device 20 already fixed to the upper base isolation base 24, and in this state, the form of the reinforcing bar 23A of the lower base isolation base 23 Is built and concrete is laid, and the lower seismic isolation base 23 is constructed. Thereby, the laminated rubber 201 is attached in the vicinity of the place temporarily supported by the temporary support column 30, and the lower seismic isolation base 23 and the upper seismic isolation foundation 24 are connected via the laminated rubber 201. The upper foundation beam 12 is supported by the seismic isolation device 20 including the rubber 201.

ステップS7では、仮受支柱30を撤去する。
まず、仮受支柱30のジャッキ32を駆動して、下部支柱31と上部支柱33とを接近させることで、基礎2の仮支持を解除する。
次に、仮受支柱30を撤去する。これにより、上部基礎梁12は、免震装置20により支持される。
In step S7, the temporary support column 30 is removed.
First, the temporary support of the foundation 2 is released by driving the jack 32 of the temporary support column 30 to bring the lower column 31 and the upper column 33 closer to each other.
Next, the temporary support column 30 is removed. Thereby, the upper foundation beam 12 is supported by the seismic isolation device 20.

本実施形態によれば、以下のような効果がある。
(1)上部基礎梁12のコンクリートの収縮量を見込んで、上部基礎梁12を設計上の寸法よりも大きく構築する。そして、所定期間が経過して、上部基礎梁12のコンクリートがある程度収縮した後に、免震装置20を取り付ける。
したがって、上部基礎梁12のコンクリートが収縮しても、免震装置20をこのコンクリートの収縮後に取り付けるから、免震装置20の変形が抑制される。よって、従来のように、コンクリートの収縮量を正確に予測する必要や、予め免震装置を変形させる必要がない。
According to this embodiment, there are the following effects.
(1) The upper foundation beam 12 is constructed to be larger than the design dimension in consideration of the shrinkage amount of the concrete of the upper foundation beam 12. And after the predetermined period passes and the concrete of the upper foundation beam 12 contracts to some extent, the seismic isolation device 20 is attached.
Therefore, even if the concrete of the upper foundation beam 12 contracts, the seismic isolation device 20 is attached after the concrete contraction, so that deformation of the seismic isolation device 20 is suppressed. Therefore, unlike the prior art, there is no need to accurately predict the amount of shrinkage of the concrete or to deform the seismic isolation device in advance.

(2)マットスラブ11の上に設けた仮受支柱30により上部基礎梁12を仮支持し、この仮受支柱30とマットスラブ11との間にすべり板40を介装した。よって、上部基礎梁12を仮支持した後に、この上部基礎梁12のコンクリートが収縮して、上部基礎梁12が水平移動しても、仮受支柱30がすべり板40上を摺動するので、上部基礎梁12の安定を保つことができる。   (2) The upper foundation beam 12 was temporarily supported by a temporary support column 30 provided on the mat slab 11, and a slip plate 40 was interposed between the temporary support column 30 and the mat slab 11. Therefore, after temporarily supporting the upper foundation beam 12, even if the concrete of the upper foundation beam 12 contracts and the upper foundation beam 12 moves horizontally, the temporary support column 30 slides on the sliding plate 40. The stability of the upper foundation beam 12 can be maintained.

〔第2実施形態〕
図6は、本発明の第2実施形態に係る免震構造物の模式図である。
本実施形態では、建物1Aの外周部に本発明を適用した点が、第1実施形態と異なり、その他の構成は第1実施形態と同様である。
[Second Embodiment]
FIG. 6 is a schematic view of a seismic isolation structure according to the second embodiment of the present invention.
In this embodiment, the point which applied this invention to the outer peripheral part of the building 1A differs from 1st Embodiment, and the other structure is the same as that of 1st Embodiment.

建物1Aは、下部躯体としてのマットスラブ2と、このマットスラブ2の上に設けられた複数の免震装置20A、20Bと、これら免震装置20A、20Bの上に設けられた上部躯体としての建物本体4と、を備える。
建物本体4は、所定方向つまり図6中左右方向に延びており、鉄筋コンクリート造の柱部材および梁部材からなるラーメン構造である。
The building 1A includes a mat slab 2 as a lower casing, a plurality of seismic isolation devices 20A and 20B provided on the mat slab 2, and an upper casing provided on the seismic isolation devices 20A and 20B. And a building body 4.
The building body 4 extends in a predetermined direction, that is, in the left-right direction in FIG. 6, and has a ramen structure composed of a reinforced concrete column member and a beam member.

免震装置20A、20Bは、図6中左右方向に沿って配置されている。これら免震装置20A、20Bのうち、平面視で建物1Aの中央部側には、免震装置20Aが配置され、平面視で建物1Aの短辺側の外周部つまり最も外側の部分には、免震装置20Bが配置されている。
免震装置20A、20Bは、それぞれ、第1実施形態の免震装置20と同一構造である。
The seismic isolation devices 20A and 20B are arranged along the left-right direction in FIG. Of these seismic isolation devices 20A and 20B, the seismic isolation device 20A is arranged on the center side of the building 1A in plan view, and the outer peripheral portion on the short side of the building 1A in plan view, that is, the outermost portion, A seismic isolation device 20B is arranged.
The seismic isolation devices 20A and 20B each have the same structure as the seismic isolation device 20 of the first embodiment.

以上の建物1Aは、以下の手順で構築される。
まず、図7に示すように、地盤3を掘削してマットスラブ2を構築し、このマットスラブ2上に免震装置20Aおよび仮受支柱30を設置して、これら免震装置20Aおよび仮受支柱30上に建物本体4を構築する。
具体的には、建物1Aの中央部側では、免震装置20Aを完成させて、この免震装置20Aにより建物本体4を支持する。一方、建物1Aの外周部側では、第1実施形態のステップS1〜S5を実行するが、第1実施形態のステップS6、S7を実行せずに、免震装置20Bを未完成の状態とし、仮受支柱30により建物本体4を支持する。
The above building 1A is constructed in the following procedure.
First, as shown in FIG. 7, the ground 3 is excavated to construct the mat slab 2, the seismic isolation device 20A and the temporary support post 30 are installed on the mat slab 2, and the seismic isolation device 20A and the temporary reception are installed. The building body 4 is constructed on the column 30.
Specifically, the seismic isolation device 20A is completed on the center side of the building 1A, and the building body 4 is supported by the seismic isolation device 20A. On the other hand, on the outer peripheral side of the building 1A, steps S1 to S5 of the first embodiment are executed, but without performing steps S6 and S7 of the first embodiment, the seismic isolation device 20B is in an incomplete state, The building body 4 is supported by the temporary support columns 30.

次に、所定期間経過後、建物1Aの外周部において免震装置20Bを完成させる。
所定期間が経過すると、躯体コンクリートが収縮して、建物本体4が図7中矢印方向に変位する。この変位は、建物1Aの外周部に近くなるほど大きくなるので、建物1Aの外周部において、仮受支柱30がすべり板40上を摺動する。
そこで、第1実施形態のステップS6、S7を実行して免震装置20Bを完成させる。
Next, after the lapse of a predetermined period, the seismic isolation device 20B is completed at the outer periphery of the building 1A.
When the predetermined period elapses, the frame concrete contracts and the building body 4 is displaced in the direction of the arrow in FIG. Since this displacement becomes larger as it gets closer to the outer periphery of the building 1A, the temporary support column 30 slides on the slip plate 40 in the outer periphery of the building 1A.
Therefore, steps S6 and S7 of the first embodiment are executed to complete the seismic isolation device 20B.

本実施形態によれば、上述の(1)、(2)と同様の効果がある。   According to the present embodiment, there are the same effects as the above (1) and (2).

なお、本発明は前記実施形態に限定されるものではなく、本発明の目的を達成できる範囲での変形、改良等は本発明に含まれるものである。
例えば、上述の各実施形態では、上部基礎梁12を構築する際に、上部基礎梁12のコンクリートの収縮量を予め計算により算定し、この算定した収縮量を見込んで、基礎梁12を設計上の寸法よりも長く構築したが、これに限らず、上部基礎梁12のコンクリートの収縮量を見込むことなく、コンクリートが収縮した後に、免震装置を取り付けてもよい。
It should be noted that the present invention is not limited to the above-described embodiment, and modifications, improvements, etc. within a scope that can achieve the object of the present invention are included in the present invention.
For example, in each of the above-described embodiments, when the upper foundation beam 12 is constructed, the concrete shrinkage amount of the upper foundation beam 12 is calculated in advance, and the foundation beam 12 is designed in consideration of the calculated shrinkage amount. However, the present invention is not limited to this, and the seismic isolation device may be attached after the concrete contracts without expecting the contraction amount of the concrete of the upper foundation beam 12.

1、1A…建物(免震構造物)
2…基礎
3…地盤
4…建物本体(上部躯体)
10…杭
11…マットスラブ(下部躯体)
12…上部基礎梁(上部躯体)
13…柱
13A…柱筋
20、20A、20B…免震装置
21…設置スペース
23…下部免震基礎
23A…鉄筋
24…上部免震基礎
24A…鉄筋
25…捨てコンクリート
30…仮受支柱
31…下部支柱
32…ジャッキ
33…上部支柱
40…すべり板
201…積層ゴム
202…下フランジ
203…上フランジ
231…下部ベースプレート
241…上部ベースプレート
1, 1A ... Building (Seismic isolation structure)
2 ... Foundation 3 ... Ground 4 ... Building body (upper frame)
10 ... Pile 11 ... Mat slab (lower frame)
12 ... Upper foundation beam (upper frame)
DESCRIPTION OF SYMBOLS 13 ... Pillar 13A ... Column reinforcement 20, 20A, 20B ... Seismic isolation device 21 ... Installation space 23 ... Lower seismic isolation base 23A ... Reinforcement 24 ... Upper seismic isolation base 24A ... Reinforcement 25 ... Discard concrete 30 ... Temporary support post 31 ... Lower Support column 32 ... Jack 33 ... Upper support column 40 ... Sliding plate 201 ... Laminated rubber 202 ... Lower flange 203 ... Upper flange 231 ... Lower base plate 241 ... Upper base plate

Claims (3)

下部躯体の上に設けられた免震装置により上部躯体を支持する免震構造物の構築方法であって、
当該上部躯体のうち少なくとも最も外側の部分を前記下部躯体から摺動可能に仮支持する工程と、
所定期間経過後、当該仮支持した箇所またはその近傍に、積層ゴムを取り付けて、当該積層ゴムを含む免震装置により前記上部躯体を支持する工程と、を備えることを特徴とする免震構造物の構築方法。
A method of constructing a seismic isolation structure that supports an upper chassis by a seismic isolation device provided on the lower chassis,
Temporarily supporting at least the outermost part of the upper housing from the lower housing so as to be slidable;
Attaching a laminated rubber at or near the temporarily supported portion after a predetermined period of time, and supporting the upper housing with a seismic isolation device including the laminated rubber. How to build.
下部躯体の上に設けられた免震装置により上部躯体を支持する免震構造物の構築方法であって、
前記上部躯体のコンクリートの収縮量を見込んで、当該上部躯体を設計上の寸法よりも長く構築するとともに、当該上部躯体を前記下部躯体から仮支持する工程と、
所定期間経過後、前記免震装置を取り付けて、当該免震装置により前記上部躯体を支持する工程と、を備えることを特徴とする免震構造物の構築方法。
A method of constructing a seismic isolation structure that supports an upper chassis by a seismic isolation device provided on the lower chassis,
Expecting the amount of shrinkage of the concrete of the upper housing, constructing the upper housing longer than the design dimensions, and temporarily supporting the upper housing from the lower housing;
And a step of attaching the seismic isolation device after a predetermined period of time and supporting the upper housing by the seismic isolation device.
前記上部躯体を前記下部躯体から仮支持する工程では、前記下部躯体の上に仮受支柱を設けて、当該仮受支柱により前記上部躯体を仮支持するとともに、当該仮受支柱と前記上部躯体または前記下部躯体との間に、すべり板を介装することを特徴とする請求項1または2に記載の免震構造物の構築方法。   In the step of temporarily supporting the upper housing from the lower housing, provisional support posts are provided on the lower housing, and the upper housing is temporarily supported by the temporary support posts, and the temporary support posts and the upper housing or The construction method of the seismic isolation structure according to claim 1 or 2, wherein a slip plate is interposed between the lower casing and the lower casing.
JP2014214804A 2014-10-21 2014-10-21 Construction method of seismic isolation structure Active JP6373719B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2014214804A JP6373719B2 (en) 2014-10-21 2014-10-21 Construction method of seismic isolation structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2014214804A JP6373719B2 (en) 2014-10-21 2014-10-21 Construction method of seismic isolation structure

Publications (2)

Publication Number Publication Date
JP2016079754A true JP2016079754A (en) 2016-05-16
JP6373719B2 JP6373719B2 (en) 2018-08-15

Family

ID=55958073

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014214804A Active JP6373719B2 (en) 2014-10-21 2014-10-21 Construction method of seismic isolation structure

Country Status (1)

Country Link
JP (1) JP6373719B2 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010190029A (en) * 2009-01-26 2010-09-02 Oiles Ind Co Ltd Bearing device
JP2011017353A (en) * 2009-07-07 2011-01-27 Takenaka Komuten Co Ltd Fixing structure of seismic isolation device, and method for adjusting horizontal displacement difference of seismic isolation device

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010190029A (en) * 2009-01-26 2010-09-02 Oiles Ind Co Ltd Bearing device
JP2011017353A (en) * 2009-07-07 2011-01-27 Takenaka Komuten Co Ltd Fixing structure of seismic isolation device, and method for adjusting horizontal displacement difference of seismic isolation device

Also Published As

Publication number Publication date
JP6373719B2 (en) 2018-08-15

Similar Documents

Publication Publication Date Title
JP6339923B2 (en) How to build a building frame
JP5984655B2 (en) Construction method of seismic isolation building
JP2008031682A (en) Aseismically supporting structure during temporary bearing of building, and aseismically supporting method during temporary bearing of building
JP6483570B2 (en) How to replace the seismic isolation device
JP6066849B2 (en) Seismic isolation method for existing buildings
JP6373719B2 (en) Construction method of seismic isolation structure
JP5485085B2 (en) Axial force replacement method for existing piles
JP6368551B2 (en) Seismic isolation method for existing buildings
JP2016089481A (en) Extension method for underground facility
JP6334970B2 (en) Temporary support method for foundation
JP6087680B2 (en) Seismic isolation method for existing buildings
JP5003253B2 (en) RC beam construction method
JP6083788B2 (en) Temporary support method for foundation
JP6438202B2 (en) Construction method of projecting part of seismic isolation building
JP2002309593A (en) Method of base-isolating existing building
JP5852475B2 (en) Pile foundation reconstruction method
JP3756158B2 (en) Seismic isolation structure
JP6441028B2 (en) Seismic isolation structure
JP2006097325A (en) Vibration isolating device, construction method of vibration isolated building and vibration isolated building
JP6326279B2 (en) Seismic isolation repair method for pile foundation structures
JP2015083762A (en) Seismic isolation method for existing structure
JP3180332U (en) Concrete foundation construction set
JP6336835B2 (en) Seismic isolation structure and seismic isolation method
JP2006022557A (en) Base isolating technique for existing building
JP6544852B2 (en) Seismic isolation method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20170926

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20180709

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20180717

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20180718

R150 Certificate of patent or registration of utility model

Ref document number: 6373719

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250