JP2016079596A - Construction method for building with underground base isolation layer, and building constructed by the construction method - Google Patents

Construction method for building with underground base isolation layer, and building constructed by the construction method Download PDF

Info

Publication number
JP2016079596A
JP2016079596A JP2014209651A JP2014209651A JP2016079596A JP 2016079596 A JP2016079596 A JP 2016079596A JP 2014209651 A JP2014209651 A JP 2014209651A JP 2014209651 A JP2014209651 A JP 2014209651A JP 2016079596 A JP2016079596 A JP 2016079596A
Authority
JP
Japan
Prior art keywords
floor
seismic isolation
isolation layer
base
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2014209651A
Other languages
Japanese (ja)
Other versions
JP6379975B2 (en
Inventor
潔 田辺
Kiyoshi Tanabe
潔 田辺
嘉宏 青山
Yoshihiro Aoyama
嘉宏 青山
博樹 笠原
Hiroki Kasahara
博樹 笠原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2014209651A priority Critical patent/JP6379975B2/en
Publication of JP2016079596A publication Critical patent/JP2016079596A/en
Application granted granted Critical
Publication of JP6379975B2 publication Critical patent/JP6379975B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

PROBLEM TO BE SOLVED: To enhance workability of a process for constructing a base isolation layer, when constructing a building with an underground base isolation layer by a reversed placing method.SOLUTION: A construction method for a building with an underground base isolation layer comprises the following steps for: erecting a reversely placed column 12 in a ground; excavating the ground and constructing a floor frame of a floor above a base isolation layer 20, such that the floor frame is supported by the reversely placed column 12; constructing a base isolation layer floor 22 such that the base isolation layer floor is supported by the reversely placed column 12, when the ground has been excavated to a depth below a depth of the base isolation layer 20; installing a temporary column between the floor frame of the floor above the base isolation layer 20 and the base isolation layer floor 22, for receiving the floor frame of the floor above the base isolation layer 20 with the column; cutting a part of the reversely placed column 12 above the base isolation layer floor 22 while receiving the floor frame of the floor above the base isolation layer 20 with the column, and installing a seismic isolator 24 at a cut part of the reversely placed column 12; and constructing a base isolation foundation 21 above the seismic isolator 24 such that the base isolation foundation is supported by the reversely placed column 12.SELECTED DRAWING: Figure 1

Description

本発明は、地下部に免震層が有る建物を逆打ち工法により構築する方法、及び該構築方法により構築された建物に関する。   The present invention relates to a method for constructing a building having a base-isolated layer in an underground portion by a reverse driving method, and a building constructed by the construction method.

地下部に免震層が有る建物を逆打ち工法により構築する方法として、特許文献1に記載の方法が知られている。この特許文献1に記載の方法では、最終掘削レベルまで掘削して掘削底面に免震層床を構築し、該免震層床の上に免震基礎を構築し、その後に、免震層床と免震基礎との間に仮設ジャッキを設置して該仮設ジャッキで建物の荷重を支持し、この状態で、逆打ち支柱における免震層床と免震基礎との間の部分を切除して当該部分に免震装置を設置し、その後に、建物の荷重を免震装置に受け替える。   As a method for constructing a building having a seismic isolation layer in the basement by a back-strike method, a method described in Patent Document 1 is known. In the method described in Patent Document 1, the base layer is excavated to the final excavation level, the base layer is constructed on the bottom surface of the excavation, the base layer is constructed on the base layer, and then the base layer is separated. A temporary jack is installed between the base and the base and the load on the building is supported by the temporary jack. In this state, the part between the base layer and the base is removed on the back strut. Install a seismic isolation device in the area, and then transfer the building load to the seismic isolation device.

特許第3648651号公報Japanese Patent No. 3648651

上記特許文献1に記載の方法では、仮設ジャッキの設置、逆打ち支柱の一部の切除、及び免震装置の設置の作業を、免震層床と免震基礎との間という天井が非常に低い(例えば、1.5m以下)狭い空間で実施しなければならず、使用できる重機も限定されることから、作業性に問題があった。   In the method described in Patent Document 1, the ceiling between the seismic isolation floor and the seismic isolation foundation is very difficult for the installation of the temporary jack, the excision of a part of the backlash strut, and the installation of the seismic isolation device. Since it must be carried out in a low (for example, 1.5 m or less) narrow space and the heavy equipment that can be used is limited, there is a problem in workability.

本発明は、上記事情に鑑みてなされたものであり、地下部に免震層が有る建物を逆打ち工法により構築するにあたり、免震層を構築する工程の作業性を向上させることを課題にするものである。   The present invention has been made in view of the above circumstances, and it is an object to improve the workability of the process of constructing the seismic isolation layer in constructing the building having the seismic isolation layer in the basement by the backlash method. To do.

上記課題を解決するために、本発明に係る地下部に免震層が有る建物の構築方法は、免震層床、該免震層床の上に設置された免震装置、及び該免震装置の上に構築された免震基礎を備える免震層が地下部に有る建物を逆打ち工法により構築する方法であって、地盤中に逆打ち支柱を建込む工程と、地盤を掘削し、前記免震層の上階の床躯体を前記逆打ち支柱に支持されるように構築する工程と、地盤を前記免震層の深さよりも下側まで掘削した段階で、前記免震層床を前記逆打ち支柱に支持されるように構築する工程と、前記免震層の上階の床躯体と前記免震層床との間に仮設支柱を設置して、前記免震層の上階の床躯体を前記仮設支柱で受ける工程と、前記仮設支柱で前記免震層の上階の床躯体を受けた状態で、前記逆打ち支柱の前記免震層床の上の一部を切除し、前記逆打ち支柱の切除された部分に前記免震装置を設置する工程と、前記免震装置の上に前記免震基礎を前記逆打ち支柱に支持されるように構築する工程と、を備える。   In order to solve the above problems, a method for constructing a building having a base isolation layer in the basement according to the present invention includes a base isolation floor, a base isolation device installed on the base isolation floor, and the base isolation A method of constructing a building having an isolation layer in the basement with an isolation base built on top of the device by a back-strike method, a process of building a back strut in the ground, excavating the ground, The step of constructing the floor structure of the upper floor of the seismic isolation layer so as to be supported by the reverse struts, and the stage of excavating the ground below the depth of the seismic isolation layer, the seismic isolation layer floor A step of constructing to be supported by the striking struts, and installing a temporary strut between the seismic isolation layer upper floor and the seismic isolation floor, Receiving the floor frame with the temporary support column, and receiving the seismic isolation of the back strut column with the temporary support column receiving the floor frame of the upper floor of the seismic isolation layer. A part of the floor is excised, and the seismic isolation device is installed on the excised part of the reverse strut, and the base is supported on the reverse strut on the seismic isolation device. And constructing as described above.

前記地下部に免震層が有る建物の構築方法において、前記仮設支柱で受ける床躯体は、前記逆打ち支柱に支持される最上段の床躯体であってもよい。   In the method for constructing a building having a base isolation layer in the basement, the floor frame received by the temporary support column may be an uppermost floor frame supported by the counter-strike column.

また、本発明に係る建物は、上記構築方法で構築されたことを特徴とする。   A building according to the present invention is constructed by the construction method described above.

本発明によれば、地下部に免震層が有る建物を逆打ち工法により構築するにあたり、免震層を構築する工程の作業性を向上させることができる。   ADVANTAGE OF THE INVENTION According to this invention, when constructing | assembling the building which has a base isolation layer in a basement part by the reverse driving method, the workability | operativity of the process of constructing a base isolation layer can be improved.

一実施形態に係る地下構造の概略構成を示す立断面図である。It is an elevation sectional view showing a schematic structure of an underground structure according to an embodiment. 地下部分を有するビルの建替えの手順を示す立断面図である。It is an elevation sectional view showing the procedure of rebuilding a building having an underground part. 地下部分を有するビルの建替えの手順を示す立断面図である。It is an elevation sectional view showing the procedure of rebuilding a building having an underground part. 地下部分を有するビルの建替えの手順を示す立断面図である。It is an elevation sectional view showing the procedure of rebuilding a building having an underground part. 地下部分を有するビルの建替えの手順を示す立断面図である。It is an elevation sectional view showing the procedure of rebuilding a building having an underground part. 地下部分を有するビルの建替えの手順を示す立断面図である。It is an elevation sectional view showing the procedure of rebuilding a building having an underground part. 地下部分を有するビルの建替えの手順を示す立断面図である。It is an elevation sectional view showing the procedure of rebuilding a building having an underground part. 地下部分を有するビルの建替えの手順を示す立断面図である。It is an elevation sectional view showing the procedure of rebuilding a building having an underground part. 地下部分を有するビルの建替えの手順を示す立断面図である。It is an elevation sectional view showing the procedure of rebuilding a building having an underground part.

以下、本発明の一実施形態を、図面を参照しながら説明する。図1は、一実施形態に係る逆打ち工法により構築された建物の地下部10を示す立断面図である。この図に示すように、地下部10は、地下1階の床下の梁を免震基礎21とする免震層20を備える。また、地下部10は、掘削底面以深に構築された杭11と、杭11に下端が埋設された逆打ち支柱12と、掘削底面上に構築された基礎13と、各階の床14や梁15とを備えている。また、地下部10の周囲には山留壁1が構築されている。逆打ち支柱12は、クロスH型鋼や鋼管等の鉄骨である。   Hereinafter, an embodiment of the present invention will be described with reference to the drawings. FIG. 1 is an elevational cross-sectional view showing an underground portion 10 of a building constructed by a reverse driving method according to an embodiment. As shown in this figure, the basement 10 includes a base isolation layer 20 that uses a beam under the floor of the first basement floor as a base isolation base 21. The underground portion 10 includes a pile 11 constructed deeper than the bottom of the excavation, a reverse strut 12 with a lower end embedded in the pile 11, a foundation 13 constructed on the excavation bottom, a floor 14 and a beam 15 on each floor. And. In addition, a mountain retaining wall 1 is constructed around the underground portion 10. The counter strut 12 is a steel frame such as cross H-shaped steel or steel pipe.

免震層20は、上記免震基礎21と、免震基礎21の下に構築された免震層床22と、免震層床22の外周部に構築された免震擁壁23と、免震基礎21と免震層床22との間の空間に配された複数の免震装置24とを備えている。免震層床22は、鉄筋コンクリート造又は鉄骨鉄筋コンクリート造であり、逆打ち支柱12により支持されている。また、免震層床22の外周部は山留壁1まで広がっており、免震擁壁23が、山留壁1に面して構築されている。ここで、免震基礎21の外周と免震擁壁23との間には空間が形成されており、免震基礎21は、免震層床22及び免震擁壁23から縁が切られた状態になっている。   The base isolation layer 20 includes the base isolation base 21, the base isolation floor 22 constructed under the base isolation base 21, the base isolation wall 23 built around the outer periphery of the base isolation floor 22, A plurality of seismic isolation devices 24 arranged in the space between the seismic foundation 21 and the seismic isolation floor 22 are provided. The seismic isolation floor 22 is a reinforced concrete structure or a steel-framed reinforced concrete structure, and is supported by the back strut 12. Moreover, the outer peripheral part of the seismic isolation layer floor 22 extends to the mountain retaining wall 1, and the seismic isolation retaining wall 23 is constructed facing the mountain retaining wall 1. Here, a space is formed between the outer periphery of the base isolation base 21 and the base isolation retaining wall 23, and the base of the base isolation base 21 is cut from the base isolation floor 22 and the base isolation retaining wall 23. It is in a state.

逆打ち支柱12は、免震基礎21と免震層床22との間の位置で上下に分断されており、逆打ち支柱12の上側部分と下側部分との間に免震装置24が設置されている。この免震装置24は積層ゴム支承等であり、免震装置24の下部は免震層床22に固定され、免震装置24の上部は免震基礎21に固定されている。   The striking strut 12 is divided up and down at a position between the base isolation base 21 and the seismic isolation floor 22, and a seismic isolation device 24 is installed between the upper part and the lower part of the striking strut 12. Has been. The seismic isolation device 24 is a laminated rubber bearing or the like. The lower part of the seismic isolation device 24 is fixed to the seismic isolation floor 22, and the upper part of the seismic isolation device 24 is fixed to the seismic isolation base 21.

図2〜図8は、地下部10を構築する手順を示す立面図である。まず、図2に示すように、山留壁1、杭11の構築と逆打ち支柱12の建込みとを実施し、その後に1階床レベル1FL以深までの1次掘削を掘削して1階の床14及び梁15を構築する。床14及び梁15は逆打ち支柱12の頭部と一体化させる。なお、1階の床14及び梁15を構築した後、山留壁1と1階の躯体との間に山留め支保工としての切梁2を設置する。次に、図3に示すように、免震層床22よりも深い位置までの2次掘削を実施し、免震層床22を構築する。   2 to 8 are elevation views showing a procedure for constructing the underground part 10. First, as shown in FIG. 2, the construction of the mountain retaining wall 1 and the pile 11 and the installation of the back struts 12 are carried out, and then the first excavation up to the first floor level 1FL and deeper is excavated. The floor 14 and the beam 15 are constructed. The floor 14 and the beam 15 are integrated with the head of the counter strut 12. In addition, after constructing the floor 14 and the beam 15 on the first floor, the cut beam 2 as a mountain retaining support is installed between the retaining wall 1 and the first-floor frame. Next, as shown in FIG. 3, secondary excavation to a position deeper than the seismic isolation floor 22 is performed to construct the seismic isolation floor 22.

次に、図4に示すように、複数の床仮受装置100を、免震層床22と1階の梁15との間に設置して、該床仮受装置100により、1階の床14及び梁15の荷重を支持する。床仮受装置100は、複数本の支柱102と、複数本の支柱102の上端を連結する複数の横材104と、これらを昇降可能に支持する複数(支柱102と同数)のジャッキ106とを備える。   Next, as shown in FIG. 4, a plurality of floor temporary devices 100 are installed between the seismic isolation floor 22 and the first floor beam 15, and the floor temporary devices 100 allow the floor on the first floor. 14 and the beam 15 are supported. The floor provisional receiving device 100 includes a plurality of support columns 102, a plurality of cross members 104 that connect the upper ends of the plurality of support columns 102, and a plurality of jacks 106 (the same number as the support columns 102) that support these members so as to be movable up and down. Prepare.

各床仮受装置100は、各逆打ち支柱12毎に設けられており、各逆打ち支柱12に接続された2〜4本の梁15を受ける。建物内周部では、4本の支柱102が逆打ち支柱12を中心として矩形状に配される。ここで、支柱102を梁15の直下に配して支柱102で梁15を直接受けるのではなく、各横材104を各梁15と直交するように配して、各梁15を、横材104を介して一対の支柱102で受ける。   Each floor provisional receiving device 100 is provided for each backlash strut 12 and receives 2 to 4 beams 15 connected to each backlash strut 12. In the inner periphery of the building, four support columns 102 are arranged in a rectangular shape with the back strut 12 as a center. Here, the columns 102 are not disposed directly below the beams 15 and are directly received by the columns 102, but the cross members 104 are disposed so as to be orthogonal to the beams 15, and the beams 15 are It is received by a pair of support columns 102 through 104.

また、建物外周部では、梁15と直交するように配した横材104を、他の横材104を介して又は直接に山留壁1に固定すると共に、梁15を、該梁15と直交するように配した横材104を介して一対の支柱102で受ける。   Further, at the outer periphery of the building, the cross member 104 arranged so as to be orthogonal to the beam 15 is fixed to the mountain retaining wall 1 via another cross member 104 or directly, and the beam 15 is orthogonal to the beam 15. It receives with a pair of support | pillars 102 through the horizontal member 104 arranged so.

支柱102は、逆打ち支柱12に比して断面寸法が小さい(例えば、H200×200〜H250×250)H型鋼である。なお、支柱102は、鋼管等の他の鋼材であってもよい。また、複数の横材104は、H型鋼等の鋼材であり、梁15にボルトや固定金具により固定されている。また、各ジャッキ106は、支柱102の下に設置されており、複数のジャッキ106が伸縮することにより、複数の支柱102及び横材104が昇降する。   The support column 102 is an H-shaped steel having a smaller cross-sectional dimension (for example, H200 × 200 to H250 × 250) compared to the counter-strut support column 12. The support column 102 may be another steel material such as a steel pipe. Further, the plurality of cross members 104 are steel materials such as H-shaped steel, and are fixed to the beam 15 with bolts or fixing brackets. Moreover, each jack 106 is installed under the support | pillar 102, and when the some jack 106 expands / contracts, the some support | pillar 102 and the horizontal member 104 raise / lower.

次に、図5に示すように、免震層20に免震装置24を設置する。本工程では、まず、1階の躯体の荷重を床仮受装置100で支持した状態で、逆打ち支柱12における免震装置24を設置する部分を切除する。   Next, as shown in FIG. 5, the seismic isolation device 24 is installed in the seismic isolation layer 20. In this step, first, a portion of the back strut 12 where the seismic isolation device 24 is installed is excised in a state where the load of the first-floor frame is supported by the floor provisional receiving device 100.

ここで、図6に示すように、逆打ち支柱12の切除部分12Aは、その上下の柱部12B、12Cの間に着脱可能に設けられている。切除部分12Aの上端及び下端にはそれぞれフランジ12D、12Eが設けられ、上側の柱部12Bの下端及び下側の柱部12Cの上端にはそれぞれフランジ12F、12Gが設けられており、フランジ12Dとフランジ12Fとがボルトで結合され、フランジ12Eとフランジ12Gとがボルトで結合されている。   Here, as shown in FIG. 6, the cut portion 12A of the counter strut 12 is detachably provided between the upper and lower column portions 12B and 12C. Flange portions 12D and 12E are provided at the upper end and lower end of the cut portion 12A, respectively, and flanges 12F and 12G are provided at the lower end of the upper column portion 12B and the upper end of the lower column portion 12C, respectively. The flange 12F is coupled with a bolt, and the flange 12E and the flange 12G are coupled with a bolt.

本工程では、上側のフランジ12D、12Fのボルトによる結合と下側のフランジ12E、12Gとのボルトによる結合とを解除してから、ジャッキ106で1階の床躯体及び上側の逆打ち支柱12を上昇させて上下の柱部12B、12Cの間隔を広げた状態にして、切除部分12Aを上下の柱部12B、12Cの間から抜き取る。次に、図7に示すように、上下の柱部12B、12Cの間に免震装置24を設置し、ジャッキ106で1階の躯体及び上側の柱部12Bを下降させて1階の躯体及び上側の柱部12Bの荷重を床仮受装置100から下側の柱部12Cに受け替える。   In this process, after the upper flanges 12D and 12F are joined with the bolts and the lower flanges 12E and 12G are joined with the bolts, the jack 106 is used to connect the floor frame on the first floor and the upper struts 12 on the upper floor. The cut portion 12A is extracted from between the upper and lower column portions 12B and 12C in a state where the distance between the upper and lower column portions 12B and 12C is increased. Next, as shown in FIG. 7, the seismic isolation device 24 is installed between the upper and lower column parts 12B and 12C, and the first floor case and the upper column part 12B are lowered by the jack 106, and the first floor case and The load of the upper column portion 12B is transferred from the floor provisional receiving device 100 to the lower column portion 12C.

次に、図8に示すように、免震層床22の上に免震装置24の基礎25及び免震擁壁23を構築し、基礎梁である免震基礎21を構築する。免震基礎21は上側の柱部12Bの下端に接続する。また、これと並行して、地下2階床レベルB2FL以深までの3次掘削や地下2階の床14及び梁15の構築等を進行する。なお、地下2階の躯体を構築した後、山留壁1と地下2階の躯体との間に山留め支保工としての切梁2を設置する。   Next, as shown in FIG. 8, the base 25 of the seismic isolation device 24 and the seismic isolation retaining wall 23 are constructed on the seismic isolation floor 22, and the seismic isolation foundation 21 which is a foundation beam is constructed. The seismic isolation foundation 21 is connected to the lower end of the upper column part 12B. In parallel with this, the third excavation up to the deeper level B2FL of the second basement floor, the construction of the floor 14 and the beam 15 on the second basement floor, and the like proceed. In addition, after building the basement on the second basement, a beam 2 is installed between the retaining wall 1 and the basement on the second basement.

ここで、床仮受装置100の支柱102が、梁15の直下に配されていないことから、床仮受装置100を設置した状態で、梁15の直下に基礎梁である免震基礎21を構築することができる。   Here, since the column 102 of the floor provisional device 100 is not arranged directly below the beam 15, the seismic isolation foundation 21, which is a foundation beam, is installed directly below the beam 15 with the floor temporary device 100 installed. Can be built.

次に、図9に示すように、床仮受装置100を解体する。そして、地下1階の立上り躯体を構築する。また、これと並行して、4次、5次の掘削や基礎13の構築等を進行させる。   Next, as shown in FIG. 9, the floor provisional receiving device 100 is disassembled. Then, build up the riser on the first basement floor. In parallel with this, the fourth and fifth excavations and the construction of the foundation 13 are advanced.

以上説明したように、本実施形態に係る建物の地下部10の構築方法では、まず、地盤中に逆打ち支柱12を建込んだ後、地盤を掘削し、免震基礎21の上階である1階の床14及び梁15を逆打ち支柱12に支持されるように構築する。そして、地盤を免震層床22の深さよりも下側まで掘削した後、免震層床22を構築する。   As explained above, in the construction method of the underground part 10 of the building according to the present embodiment, first, the back strut 12 is built in the ground, and then the ground is excavated to be the upper floor of the seismic isolation foundation 21. The floor 14 and the beam 15 on the first floor are constructed so as to be supported by the back strut 12. And after excavating the ground below the depth of the base isolation layer floor 22, the base isolation layer floor 22 is constructed.

ここで、本実施形態に係る建物の地下部10の構築方法では、地盤を免震層20の深さよりも下側まで掘削した段階で、免震層床22を逆打ち支柱12に支持されるように構築し、その後、1階の床14及び梁15と免震層床22との間に仮設の支柱102を設置して、1階の床14及び梁15を支柱102で受ける。そして、支柱102で1階の床14及び梁15を受けた状態で、逆打ち支柱12の免震層床22の上の一部を切除し、逆打ち支柱12の切除された部分に免震装置24を設置する。その後、免震基礎21を免震装置24の上に逆打ち支柱12に支持されるように構築する。   Here, in the construction method of the underground part 10 of the building according to the present embodiment, the seismic isolation layer floor 22 is supported by the striking struts 12 when the ground is excavated below the depth of the seismic isolation layer 20. After that, the temporary support column 102 is installed between the floor 14 and the beam 15 on the first floor and the base isolation layer floor 22, and the floor 14 and the beam 15 on the first floor are received by the support column 102. Then, in a state where the first floor 14 and the beam 15 are received by the support column 102, a part of the reverse strut 12 on the seismic isolation layer floor 22 is excised, and the isolated part of the reverse strut 12 is isolated. The device 24 is installed. Thereafter, the base isolation base 21 is constructed on the base isolation device 24 so as to be supported by the back strut 12.

ここで、免震層床22から免震基礎21の上端までの高さは、2.5〜3.0m程度であるのに対して、免震層床22から免震基礎21の下端までの高さは、1.0〜1.5m程度である。従って、免震基礎21の構築後に、逆打ち支柱12の一部を切除し、逆打ち支柱12の切除された部分に免震装置24を設置する作業を実施する場合には、当該作業を、天井が1.0〜1.5m程度と非常に低い狭い空間で実施しなければならず、使用できる重機も限定される。   Here, the height from the seismic isolation floor 22 to the upper end of the seismic isolation foundation 21 is about 2.5 to 3.0 m, whereas the height from the seismic isolation floor 22 to the lower end of the seismic isolation foundation 21. The height is about 1.0 to 1.5 m. Therefore, after the base isolation base 21 is constructed, when performing the operation of excising a part of the reverse strut 12 and installing the seismic isolation device 24 in the excised part of the reverse strut 12, The ceiling must be implemented in a very small space of about 1.0 to 1.5 m, and the heavy equipment that can be used is also limited.

それに対して、本実施形態に係る建物の地下部10の構築方法では、免震層床22を構築してから免震基礎21を構築するまでの間に、仮設の支柱102で1階の床14及び梁15を受けた状態で、逆打ち支柱12の一部を切除し、逆打ち支柱12の切除された部分に免震装置24を設置する作業を実施する。これによって、当該作業を、1階の床14及び梁15まで開放された広い空間で実施でき、使用できる重機の選択の幅が広がる。従って、当該作業を良好な作業性をもって実施できる。   On the other hand, in the construction method of the underground part 10 of the building according to the present embodiment, the floor of the first floor is provided with the temporary support column 102 between the construction of the seismic isolation floor 22 and the construction of the seismic isolation foundation 21. 14 and the beam 15 are received, a part of the striking strut 12 is excised, and the seismic isolation device 24 is installed in the excised part of the striking strut 12. As a result, the work can be performed in a wide space open to the floor 14 and the beams 15 on the first floor, and the range of selection of usable heavy machinery is expanded. Therefore, the work can be performed with good workability.

また、本実施形態に係る建物の地下部10の構築方法では、免震層20を地下1階に設けている。即ち、仮設の支柱102で受ける床躯体を、逆打ち支柱12に支持される最上段の床躯体たる1階の床14及び梁15のみとしている。   Moreover, in the construction method of the underground part 10 of the building which concerns on this embodiment, the seismic isolation layer 20 is provided in the 1st basement floor. That is, the floor frame received by the temporary support column 102 is only the floor 14 and the beam 15 on the first floor, which is the uppermost floor frame supported by the reverse strut 12.

ここで、特許文献1に記載されているように、免震層を掘削底面の基礎上に設ける場合には、免震層床と免震基礎との間に油圧ジャッキを設け、該油圧ジャッキで地下躯体全体の荷重を受けた状態で、逆打ち支柱12の一部を切除し、逆打ち支柱12の切除された部分に免震装置24を設置する作業を実施しなければならない。従って、大能力の油圧ジャッキが必要になり、コストが増大する。また、かかる大荷重を油圧ジャッキで受けた状態で、油圧ジャッキから免震装置に地下躯体の荷重を受け替えるとなると、油圧ジャッキの油圧を高精度に管理しなければ、地下躯体に大きな偏荷重が作用し、該偏荷重により地下躯体に大きな影響が及ぶことになる。従って、油圧ジャッキの油圧管理に要求される精度が高くなり、作業性が低下する。   Here, as described in Patent Document 1, when the base isolation layer is provided on the foundation of the excavation bottom, a hydraulic jack is provided between the base isolation floor and the base isolation base, and the hydraulic jack While receiving the load of the entire underground skeleton, it is necessary to cut off a part of the striking strut 12 and to install the seismic isolation device 24 in the excised part of the striking strut 12. Therefore, a high-capacity hydraulic jack is required, and the cost increases. In addition, if the load of the underground skeleton is transferred from the hydraulic jack to the seismic isolation device in a state where such a large load is received by the hydraulic jack, if the hydraulic pressure of the hydraulic jack is not managed with high accuracy, a large unbalanced load is applied to the underground skeleton. Acts, and the unbalanced load has a great influence on the underground structure. Accordingly, the accuracy required for the hydraulic pressure management of the hydraulic jack is increased, and the workability is lowered.

それに対して、本実施形態に係る建物の地下部10の構築方法では、床仮受装置100で支持する床躯体は、1階の床14及び梁15のみであることによって、特許文献1に記載の方法に比して、油圧ジャッキに要求される能力が格段に小さくなり、コストを低減できる。また、免震層20を地下2階、3階に設ける場合に比して、仮設の支柱102に作用する荷重が小さくなり、支柱102に要求される剛性が小さくなり、コストを低減できる。   On the other hand, in the construction method of the underground part 10 of the building according to the present embodiment, the floor frame supported by the floor provisional receiving device 100 is only the floor 14 and the beam 15 on the first floor, which is described in Patent Document 1. Compared with this method, the capacity required for the hydraulic jack is remarkably reduced, and the cost can be reduced. Moreover, compared with the case where the seismic isolation layer 20 is provided on the second and third floors, the load acting on the temporary support column 102 is reduced, the rigidity required for the support column 102 is reduced, and the cost can be reduced.

また、免震層20を地下2階、3階に設ける場合に比して、床仮受装置100で受ける荷重が小さくなることにより、床仮受装置100から免震装置24に1階の床14及び梁15の荷重を受け替える際に偏荷重により地下躯体に及ぶ影響が小さくなる。よって、油圧ジャッキの油圧管理に要求される精度が低くなり、施工性を向上できる。   Further, compared to the case where the seismic isolation layer 20 is provided on the 2nd and 3rd floors of the basement, the load received by the floor temporary support device 100 is reduced, so that the floor isolation device 24 transfers the first floor to the base isolation device 24. When the load on the beam 14 and the beam 15 is changed, the influence on the underground structure due to the uneven load is reduced. Therefore, the accuracy required for the hydraulic management of the hydraulic jack is lowered, and the workability can be improved.

なお、上述の実施形態は、本発明の理解を容易にするためのものであり、本発明を限定するものではない。本発明はその趣旨を逸脱することなく、変更、改良され得ると共に本発明にはその等価物が含まれることは勿論である。例えば、上述の実施形態では、免震層20を地下1階に設けたが、他の地下階に設けてもよい。   In addition, the above-mentioned embodiment is for making an understanding of this invention easy, and does not limit this invention. It goes without saying that the present invention can be changed and improved without departing from the gist thereof, and that the present invention includes equivalents thereof. For example, in the above-described embodiment, the seismic isolation layer 20 is provided on the first basement floor, but may be provided on another basement floor.

1 山留壁、2 切梁、10 地下部、11 杭、12 逆打ち支柱、12A 切除部分、12B、12C 柱部、12D、12E、12F、12G フランジ、13 基礎、14 床、15 梁、20 免震層、21 免震基礎、22 免震層床、23 免震擁壁、24 免震装置、25 基礎、100 床仮受装置、102 支柱、104 横材、106 ジャッキ DESCRIPTION OF SYMBOLS 1 Yamato wall, 2 Cut beam, 10 Underground part, 11 Pile, 12 Reverse strut, 12A Cut part, 12B, 12C Column part, 12D, 12E, 12F, 12G Flange, 13 Foundation, 14 Floor, 15 Beam, 20 Base-isolated layer, 21 Base-isolated foundation, 22 Base-isolated floor, 23 Base-isolated retaining wall, 24 Base-isolated device, 25 foundation, 100-floor provisional device, 102 Post, 104 Cross member, 106 Jack

Claims (3)

免震層床、該免震層床の上に設置された免震装置、及び該免震装置の上に構築された免震基礎を備える免震層が地下部に有る建物を逆打ち工法により構築する方法であって、
地盤中に逆打ち支柱を建込む工程と、
地盤を掘削し、前記免震層の上階の床躯体を前記逆打ち支柱に支持されるように構築する工程と、
地盤を前記免震層の深さよりも下側まで掘削した段階で、前記免震層床を前記逆打ち支柱に支持されるように構築する工程と、
前記免震層の上階の床躯体と前記免震層床との間に仮設支柱を設置して、前記免震層の上階の床躯体を前記仮設支柱で受ける工程と、
前記仮設支柱で前記免震層の上階の床躯体を受けた状態で、前記逆打ち支柱の前記免震層床の上の一部を切除し、前記逆打ち支柱の切除された部分に前記免震装置を設置する工程と、
前記免震装置の上に前記免震基礎を前記逆打ち支柱に支持されるように構築する工程と、
を備える地下部に免震層が有る建物の構築方法。
A seismic isolation floor, a base isolation device installed on the base isolation floor, and a building having a base isolation base with a base isolated constructed on the base isolation device by a reverse driving method. A method of building,
The process of erection the back struts in the ground,
Excavating the ground and constructing the upper floor of the seismic isolation layer so that it is supported by the striking struts;
A step of excavating the ground to a level below the depth of the seismic isolation layer, and building the seismic isolation floor so that it is supported by the back struts;
Installing a temporary strut between the upper floor of the seismic isolation layer and the base isolation floor, and receiving the upper floor of the seismic isolation layer with the temporary support;
In a state where the floor support of the upper floor of the seismic isolation layer is received by the temporary support column, a part of the reverse strut column on the seismic isolation layer floor is excised, and the part of the reverse strut support column is excised. The process of installing seismic isolation devices;
Constructing the seismic isolation foundation on the seismic isolation device so as to be supported by the backlash strut;
A method of building a building with a seismic isolation layer in the basement.
前記仮設支柱で受ける床躯体は、前記逆打ち支柱に支持される最上段の床躯体である請求項1に記載の地下部に免震層が有る建物の構築方法。   The method for constructing a building having a base-isolated layer in the basement according to claim 1, wherein the floor frame received by the temporary column is an uppermost floor frame supported by the counter-strike column. 請求項1又は請求項2に記載の構築方法で構築された建物。   A building constructed by the construction method according to claim 1 or 2.
JP2014209651A 2014-10-14 2014-10-14 Construction method of a building having a base-isolated layer in the basement, and a building constructed by the construction method Expired - Fee Related JP6379975B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2014209651A JP6379975B2 (en) 2014-10-14 2014-10-14 Construction method of a building having a base-isolated layer in the basement, and a building constructed by the construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2014209651A JP6379975B2 (en) 2014-10-14 2014-10-14 Construction method of a building having a base-isolated layer in the basement, and a building constructed by the construction method

Publications (2)

Publication Number Publication Date
JP2016079596A true JP2016079596A (en) 2016-05-16
JP6379975B2 JP6379975B2 (en) 2018-08-29

Family

ID=55957981

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014209651A Expired - Fee Related JP6379975B2 (en) 2014-10-14 2014-10-14 Construction method of a building having a base-isolated layer in the basement, and a building constructed by the construction method

Country Status (1)

Country Link
JP (1) JP6379975B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017031755A (en) * 2015-08-05 2017-02-09 大成建設株式会社 Base-isolated building construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10280446A (en) * 1997-04-07 1998-10-20 Taisei Corp Construction method for base-isolated building using inverse driving method
JP2001173269A (en) * 1999-12-14 2001-06-26 Shimizu Corp Constructing method for base isolation building
JP2014118756A (en) * 2012-12-17 2014-06-30 Taisei Corp Base-isolated building and construction method for the same

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10280446A (en) * 1997-04-07 1998-10-20 Taisei Corp Construction method for base-isolated building using inverse driving method
JP2001173269A (en) * 1999-12-14 2001-06-26 Shimizu Corp Constructing method for base isolation building
JP2014118756A (en) * 2012-12-17 2014-06-30 Taisei Corp Base-isolated building and construction method for the same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017031755A (en) * 2015-08-05 2017-02-09 大成建設株式会社 Base-isolated building construction method

Also Published As

Publication number Publication date
JP6379975B2 (en) 2018-08-29

Similar Documents

Publication Publication Date Title
JP6103667B1 (en) Construction method of underground structure
JP2013256793A (en) Construction method for underground structure, and underground structure
JP5984655B2 (en) Construction method of seismic isolation building
JP2012112121A (en) Excavation method of ground under spread foundation and base-isolating method of existing building
JP2009174281A (en) Reconstruction method of structure
JP6368551B2 (en) Seismic isolation method for existing buildings
JP6379975B2 (en) Construction method of a building having a base-isolated layer in the basement, and a building constructed by the construction method
JP6441030B2 (en) How to add underground facilities
JP2640969B2 (en) Basement expansion method for existing buildings
KR101426511B1 (en) A temporary skeleton system used in constructuring a underground structure of a building and a top down underground construction method using a temporary skeleton system
JP2018003559A (en) Column-beam frame repairing method and repaired column-beam frame
JP6052541B2 (en) Seismic isolation method for existing buildings
JP6334970B2 (en) Temporary support method for foundation
JP6827256B2 (en) How to rebuild the building
JP4475116B2 (en) Vertical shaft structure and its construction method
JP6529241B2 (en) Building foundation structure and construction method of building foundation structure
JP2015161059A (en) building construction method
JP2020125630A (en) Building construction method
JP6326279B2 (en) Seismic isolation repair method for pile foundation structures
KR101762207B1 (en) The speed up construction method using hemispherical joint
JP2018066220A (en) Reconstruction method of underground skeleton
JP6441029B2 (en) How to add underground facilities
JP2008303587A (en) Top-down construction method for base-isolated building
JP2020070701A (en) Underground structure, building and method for constructing underground structure
JP2006022557A (en) Base isolating technique for existing building

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20170920

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20180621

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20180703

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20180716

R150 Certificate of patent or registration of utility model

Ref document number: 6379975

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees