JP2015507913A5 - - Google Patents

Download PDF

Info

Publication number
JP2015507913A5
JP2015507913A5 JP2014549447A JP2014549447A JP2015507913A5 JP 2015507913 A5 JP2015507913 A5 JP 2015507913A5 JP 2014549447 A JP2014549447 A JP 2014549447A JP 2014549447 A JP2014549447 A JP 2014549447A JP 2015507913 A5 JP2015507913 A5 JP 2015507913A5
Authority
JP
Japan
Prior art keywords
load unit
power generation
power
energy storage
storage device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2014549447A
Other languages
English (en)
Other versions
JP2015507913A (ja
Filing date
Publication date
Priority claimed from EP11306813.4A external-priority patent/EP2610986A1/en
Application filed filed Critical
Publication of JP2015507913A publication Critical patent/JP2015507913A/ja
Publication of JP2015507913A5 publication Critical patent/JP2015507913A5/ja
Withdrawn legal-status Critical Current

Links

Description

したがって、本発明は、スマート・メータを装備した複数の住宅に供給する大きなエネルギー貯蔵を備えた変電所レベルに適用できる。また、本発明は、複数の家電機器に供給するより小さいエネルギー貯蔵を備えた住宅レベルにも適用できる。
本発明は以下の態様を含む。
(付記1)
ある期間の間、発電施設(4)とエネルギー貯蔵装置(8)とを使用して少なくとも1つの負荷ユニット(6)に電力を分配する、特にスマート・グリッドである電力供給網(2)の停電確率を求める方法であって、該方法は、データ処理装置(10)のプロセッサ(12)によって実行される、
前記期間を数個の時間間隔に分割するステップ(20)と、
前記期間の間、前記発電施設(4)の発電能力と、前記エネルギー貯蔵装置(8)のエネルギー貯蔵装置サイズとを求めるステップ(22)と、
時間間隔毎の前記負荷ユニット(6)の負荷ユニット需要から、それぞれ、時間間隔毎の有効負荷ユニット需要を求めるステップであって、時間間隔毎の前記負荷ユニット需要は、データベースから読み出されるか、又は、電力メータを読み取ることによって得られ、前記有効負荷ユニットは前記負荷ユニット(6)のピーク需要と平均需要との間にある値を取る、前記ステップと、
前記発電能力、前記エネルギー貯蔵装置サイズ、及び、前記有効負荷ユニット需要を含むグリッド・パラメータを用いて前記停電確率を算出するステップ(24)であって、前記グリッド・パラメータの最大値が前記期間の全ての時間間隔について最適化される、前記ステップと、
を含む前記方法。
(付記2)
前記負荷ユニット需要は、時間間隔毎にいくつかの負荷ユニット需要配分を含んでおり、前記有効負荷ユニット需要を求めるステップは、各々の負荷ユニット需要配分から、時間間隔毎の有効負荷ユニット需要配分を求めることを含み、時間間隔毎の前記負荷ユニット需要配分が前記データベースから読み出され、前記いくつかの負荷ユニット需要配分を集約した多重パラメータが求められ、前記グリッド・パラメータは、前記多重パラメータを含み、かつ、前記グリッド・パラメータの最小値が、前記データ処理装置の前記プロセッサによって前記多重パラメータについて更に最適化されることを特徴とする、付記1に記載の方法。
(付記3)
前記負荷ユニット需要配分は確率的な配分であることを特徴とする、付記2に記載の方法。
(付記4)
前記負荷ユニット需要配分が所定の電力使用プロファイルとして提供されることを特徴とする、付記2または3に記載の方法。
(付記5)
前記電力使用プロファイルは、毎日、毎週、毎月又は毎年の電力使用に関するものであることを特徴とする、付記4に記載の方法。
(付記6)
前記負荷ユニット需要配分が、メータによってリアルタイムに測定されて前記データベースに提供される測定値として提供されることを特徴とする、付記2または3に記載の方法。
(付記7)
前記測定値は、各々の負荷ユニットにおいて、又は、エネルギー貯蔵装置において測定されることを特徴とする、付記6に記載の方法。
(付記8)
特にスマート・グリッドである電力供給網(2)の発電能力を適応化する方法であって、
a)前記発電能力、エネルギー貯蔵装置サイズ、及び、負荷ユニット需要を求めるステップであって、前記発電能力、及び/又は、前記エネルギー装置サイズ、及び/又は、前記負荷ユニット需要は、データベースから読み出されるか、又は、電力メータを読み取ることによって得られる、前記ステップと、
b)付記1から7のいずれか1項に記載の方法に従って、データ処理装置のプロセッサによって、前記発電能力、前記エネルギー貯蔵装置サイズ、及び、前記負荷ユニット需要に依存して、停電確率を算出するステップと、
c)前記停電確率を目標信頼性閾値と比較するステップと、
d)前記停電確率が前記目標信頼性閾値よりも小さい場合、前記発電能力を調節するステップと、
e)付記1から7のいずれか1項に記載の方法に従って、前記データ処理装置の前記プロセッサによって、前記調節された発電能力、前記エネルギー貯蔵装置サイズ、及び、前記負荷ユニット需要に依存して、新たな停電確率を算出するステップと、
f)前記新たな停電確率を前記目標信頼性閾値と比較するステップと、
g)前記新たな停電確率が前記目標信頼性閾値以上になるまで、前記ステップd)からf)を繰り返すステップと、
を含む前記方法。
(付記9)
発電施設(4)と負荷ユニット(6)とを含む、特にスマート・グリッドである電力供給網(2)のためのエネルギー貯蔵装置サイズを求める方法であって、
a)発電能力と負荷ユニット需要とを求めるステップであって、前記負荷ユニット需要はデータベースから読み出される所定の電力使用プロファイルから求められる、前記ステップと、
b)付記1から7のいずれか1項に記載の方法に従って、データ処理装置のプロセッサによって、前記発電能力、前記エネルギー貯蔵装置サイズ、及び、前記負荷ユニット需要に依存して、停電確率を算出するステップと、
c)前記停電確率を目標信頼性閾値と比較するステップと、
d)前記停電確率が前記目標信頼性閾値よりも小さい場合、前記エネルギー貯蔵装置サイズを調節するステップと、
e)付記1から7のいずれか1項に記載の方法に従って、前記データ処理装置の前記プロセッサによって、前記調節されたエネルギー貯蔵装置サイズ、前記発電能力、及び、前記負荷ユニット需要に依存して、新たな停電確率を算出するステップと、
f)前記新たな停電確率を前記目標信頼性閾値と比較するステップと、
g)前記新たな停電確率が前記目標信頼性閾値以上になるまで、前記ステップd)からf)を繰り返すステップと、
を含む前記方法。
(付記10)
ある期間の間、発電施設(4)とエネルギー貯蔵装置(8)とを使用して少なくとも1つの負荷ユニット(6)に電力を分配する、特にスマート・グリッドである電力供給網(2)の停電確率を求めるデータ処理装置(10)であって、該データ処理装置(10)は、
前記期間を数個の時間間隔に分割する処理と、
前記期間の間、前記発電施設(4)の発電能力と前記エネルギー貯蔵装置(8)のエネルギー貯蔵装置サイズとを求める処理と、
時間間隔毎の前記負荷ユニット(6)の負荷ユニット需要から、それぞれ、時間間隔毎の有効負荷ユニット需要を求める処理であって、時間間隔毎の前記負荷ユニット需要は、データベースから読み出されるか、又は、電力メータを読み取ることによって得られ、前記有効負荷ユニットは前記負荷ユニット(6)のピーク需要と平均需要との間にある値を取る、前記処理と、
前記発電能力、前記エネルギー貯蔵装置サイズ、及び、前記有効負荷ユニット需要を含むグリッド・パラメータを用いて前記停電確率を算出する処理であって、前記グリッド・パラメータの最大値が前記期間の全ての時間間隔について最適化される、前記処理と、
を行うプロセッサ(12)を備えている、前記データ処理装置。
(付記11)
前記発電能力は確率的な発電配分を含むことを特徴とする、付記10に記載のデータ処理装置。
(付記12)
前記発電能力はいくつかの個別の発電能力を含むことを特徴とする、付記10または11に記載のデータ処理装置。
(付記13)
前記発電能力は、原子力発電設備、石炭発電設備、石油発電設備、ガス発電設備、太陽光発電設備、水力発電設備、及び、風力発電設備のグループのうちの少なくとも1つの発電設備を指していることを特徴とする、付記10から12のいずれか1項に記載のデータ処理装置。
(付記14)
前記エネルギー貯蔵装置サイズはいくつかの個別のエネルギー貯蔵装置サイズを含むことを特徴とする、付記10から13のいずれか1項に記載のデータ処理装置。

Claims (14)

  1. いくつかの時間間隔を含むある期間の間、発電施設とエネルギー貯蔵装置とを使用して少なくとも1つの負荷ユニットに電力を分配する、特にスマート・グリッドである電力供給網の停電確率を求める方法であって、該方法は、データ処理装置のプロセッサによって実行される、
    時間間隔毎の前記負荷ユニットの負荷ユニット需要から、それぞれ、時間間隔毎の有効負荷ユニット需要を求めるステップであって、時間間隔毎の前記負荷ユニット需要は、データベースから読み出されるか、又は、電力メータを読み取ることによって得られ、前記有効負荷ユニット需要は前記負荷ユニットのピーク需要と平均需要との間にある値を取る、前記ステップと、
    前記発電施設の発電能力、前記期間の間の前記エネルギー貯蔵装置のエネルギー貯蔵装置サイズ、及び、前記有効負荷ユニット需要に依存するグリッド・パラメータを用いて前記停電確率を算出するステップであって、前記グリッド・パラメータの最大値が前記期間の全ての時間間隔について最適化される、前記ステップと、
    を含む前記方法。
  2. 前記負荷ユニット需要は、時間間隔毎にいくつかの負荷ユニット需要配分を含んでおり、前記有効負荷ユニット需要を求めるステップは、各々の負荷ユニット需要配分から、時間間隔毎の有効負荷ユニット需要配分を求めることを含み、時間間隔毎の前記負荷ユニット需要配分が前記データベースから読み出され、前記いくつかの負荷ユニット需要配分を集約した多重パラメータが求められ、前記グリッド・パラメータは、前記多重パラメータを含み、かつ、前記グリッド・パラメータの最小値が、前記データ処理装置の前記プロセッサによって前記多重パラメータについて更に最適化されることを特徴とする、請求項1に記載の方法。
  3. 前記負荷ユニット需要配分は確率的な配分であることを特徴とする、請求項2に記載の方法。
  4. 前記負荷ユニット需要配分が所定の電力使用プロファイルとして提供されることを特徴とする、請求項2または3に記載の方法。
  5. 前記電力使用プロファイルは、毎日、毎週、毎月又は毎年の電力使用に関するものであることを特徴とする、請求項4に記載の方法。
  6. 前記負荷ユニット需要配分が、メータによってリアルタイムに測定されて前記データベースに提供される測定値として提供されることを特徴とする、請求項2または3に記載の方法。
  7. 前記測定値は、各々の負荷ユニットにおいて、又は、エネルギー貯蔵装置において測定されることを特徴とする、請求項6に記載の方法。
  8. 特にスマート・グリッドである電力供給網の発電能力を適応化する方法であって、
    a)前記発電能力、エネルギー貯蔵装置サイズ、及び、負荷ユニット需要を求めるステップであって、前記発電能力、及び/又は、前記エネルギー貯蔵装置サイズ、及び/又は、前記負荷ユニット需要は、データベースから読み出されるか、又は、電力メータを読み取ることによって得られる、前記ステップと、
    b)請求項1から7のいずれか1項に記載の方法に従って、データ処理装置のプロセッサによって、前記発電能力、前記エネルギー貯蔵装置サイズ、及び、前記負荷ユニット需要に依存して、停電確率を算出するステップと、
    c)前記停電確率を目標信頼性閾値と比較するステップと、
    d)前記停電確率が前記目標信頼性閾値よりも小さい場合、前記発電能力を調節するステップと、
    e)請求項1から7のいずれか1項に記載の方法に従って、前記データ処理装置の前記プロセッサによって、前記調節された発電能力、前記エネルギー貯蔵装置サイズ、及び、前記負荷ユニット需要に依存して、新たな停電確率を算出するステップと、
    f)前記新たな停電確率を前記目標信頼性閾値と比較するステップと、
    g)前記新たな停電確率が前記目標信頼性閾値以上になるまで、前記ステップd)からf)を繰り返すステップと、
    を含む前記方法。
  9. 発電施設と負荷ユニットとを含む、特にスマート・グリッドである電力供給網のためのエネルギー貯蔵装置サイズを求める方法であって、
    a)発電能力と負荷ユニット需要とを求めるステップであって、前記負荷ユニット需要はデータベースから読み出される所定の電力使用プロファイルから求められる、前記ステップと、
    b)請求項1から7のいずれか1項に記載の方法に従って、データ処理装置のプロセッサによって、前記発電能力、前記エネルギー貯蔵装置サイズ、及び、前記負荷ユニット需要に依存して、停電確率を算出するステップと、
    c)前記停電確率を目標信頼性閾値と比較するステップと、
    d)前記停電確率が前記目標信頼性閾値よりも小さい場合、前記エネルギー貯蔵装置サイズを調節するステップと、
    e)請求項1から7のいずれか1項に記載の方法に従って、前記データ処理装置の前記プロセッサによって、前記調節されたエネルギー貯蔵装置サイズ、前記発電能力、及び、前記負荷ユニット需要に依存して、新たな停電確率を算出するステップと、
    f)前記新たな停電確率を前記目標信頼性閾値と比較するステップと、
    g)前記新たな停電確率が前記目標信頼性閾値以上になるまで、前記ステップd)からf)を繰り返すステップと、
    を含む前記方法。
  10. いくつかの時間間隔を含むある期間の間、発電施設とエネルギー貯蔵装置とを使用して少なくとも1つの負荷ユニットに電力を分配する、特にスマート・グリッドである電力供給網の停電確率を求めるデータ処理装置であって、該データ処理装置は、
    時間間隔毎の前記負荷ユニットの負荷ユニット需要から、それぞれ、時間間隔毎の有効負荷ユニット需要を求める処理であって、時間間隔毎の前記負荷ユニット需要は、データベースから読み出されるか、又は、電力メータを読み取ることによって得られ、前記有効負荷ユニット需要は前記負荷ユニットのピーク需要と平均需要との間にある値を取る、前記処理と、
    前記発電施設の発電能力、前記期間の間の前記エネルギー貯蔵装置のエネルギー貯蔵装置サイズ、及び、前記有効負荷ユニット需要に依存するグリッド・パラメータを用いて前記停電確率を算出する処理であって、前記グリッド・パラメータの最大値が前記期間の全ての時間間隔について最適化される、前記処理と、
    を行うプロセッサを備えている、前記データ処理装置。
  11. 前記発電能力は確率的な発電配分を含むことを特徴とする、請求項10に記載のデータ処理装置。
  12. 前記発電能力はいくつかの個別の発電能力を含むことを特徴とする、請求項10または11に記載のデータ処理装置。
  13. 前記発電能力は、原子力発電設備、石炭発電設備、石油発電設備、ガス発電設備、太陽光発電設備、水力発電設備、及び、風力発電設備のグループのうちの少なくとも1つの発電設備を指していることを特徴とする、請求項10から12のいずれか1項に記載のデータ処理装置。
  14. 前記エネルギー貯蔵装置サイズはいくつかの個別のエネルギー貯蔵装置サイズを含むことを特徴とする、請求項10から13のいずれか1項に記載のデータ処理装置。
JP2014549447A 2011-12-30 2012-12-21 発電能力の適応化とエネルギー貯蔵装置サイズの決定 Withdrawn JP2015507913A (ja)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
EP11306813.4 2011-12-30
EP11306813.4A EP2610986A1 (en) 2011-12-30 2011-12-30 A method for determining a power outage probability of an electrical power grid, a method for an adaptation of a power generation capacity and a method for determining an energy storage unit size
PCT/EP2012/076603 WO2013098233A2 (en) 2011-12-30 2012-12-21 Adaptation of a power generation capacity and determining of an energy storage unit size

Publications (2)

Publication Number Publication Date
JP2015507913A JP2015507913A (ja) 2015-03-12
JP2015507913A5 true JP2015507913A5 (ja) 2016-02-18

Family

ID=47559426

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014549447A Withdrawn JP2015507913A (ja) 2011-12-30 2012-12-21 発電能力の適応化とエネルギー貯蔵装置サイズの決定

Country Status (6)

Country Link
US (1) US20140365419A1 (ja)
EP (2) EP2610986A1 (ja)
JP (1) JP2015507913A (ja)
KR (1) KR20140105506A (ja)
CN (1) CN104054228A (ja)
WO (1) WO2013098233A2 (ja)

Families Citing this family (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20160155077A1 (en) * 2014-12-02 2016-06-02 Opower, Inc. Generating a green business guide
WO2016144357A1 (en) * 2015-03-12 2016-09-15 Hewlett Packard Enterprise Development Lp Power distribution plan
CN106156921B (zh) * 2015-04-10 2021-11-09 华北电力大学(保定) 基于Copula理论的电动汽车光伏充电站储能配置选择方法
US10141739B1 (en) * 2015-05-26 2018-11-27 The Watt Stopper, Inc. System for distributing DC power to and controlling building devices
EP3664246A1 (en) * 2015-06-12 2020-06-10 Enphase Energy, Inc. Method and apparatus for control of intelligent loads in microgrids
CN105260797B (zh) * 2015-10-22 2022-04-15 华北电力大学 一种微网储能电站规划控制方法
US10298012B2 (en) 2016-09-29 2019-05-21 Enel X North America, Inc. Network operations center including automated validation, estimation, and editing configuration engine
US10191506B2 (en) 2016-09-29 2019-01-29 Enel X North America, Inc. Demand response dispatch prediction system including automated validation, estimation, and editing rules configuration engine
US10461533B2 (en) 2016-09-29 2019-10-29 Enel X North America, Inc. Apparatus and method for automated validation, estimation, and editing configuration
US10170910B2 (en) 2016-09-29 2019-01-01 Enel X North America, Inc. Energy baselining system including automated validation, estimation, and editing rules configuration engine
US10423186B2 (en) 2016-09-29 2019-09-24 Enel X North America, Inc. Building control system including automated validation, estimation, and editing rules configuration engine
US10566791B2 (en) 2016-09-29 2020-02-18 Enel X North America, Inc. Automated validation, estimation, and editing processor
US10291022B2 (en) 2016-09-29 2019-05-14 Enel X North America, Inc. Apparatus and method for automated configuration of estimation rules in a network operations center
US10203714B2 (en) * 2016-09-29 2019-02-12 Enel X North America, Inc. Brown out prediction system including automated validation, estimation, and editing rules configuration engine
CN106952027A (zh) * 2017-03-11 2017-07-14 国网浙江省电力公司台州供电公司 一种10kV配电网线路规划接入容量计算方法
US10590860B2 (en) * 2017-04-14 2020-03-17 Solar Turbines Incorporated Engine load estimation strategy in gas turbine engine system
KR200488852Y1 (ko) 2017-06-23 2019-03-27 김동욱 면도기
DE102017117216A1 (de) * 2017-07-31 2019-01-31 Easyoptimize Gmbh Dimensionierung eines Energiespeichers
US20190123580A1 (en) * 2017-10-23 2019-04-25 Sigora International Inc. Management of a power-distribution system
CN108427856B (zh) * 2018-04-04 2021-08-20 哈尔滨工业大学 一种配电网10千伏杆塔故障概率曲线拟合方法
DE102018213862A1 (de) * 2018-08-31 2020-03-05 Siemens Aktiengesellschaft Verfahren zum Steuern eines Austauschs von Energie zwischen Energiesubsystemen zu angeglichenen Konditionen; Steuerungszentrale; Energiesystem; Computerprogramm sowie Speichermedium
CN109829563B (zh) * 2018-12-18 2023-08-29 广东电网有限责任公司电力调度控制中心 一种基于多参数规划的馈线传输极限容量评估方法
CN110048470A (zh) * 2019-05-22 2019-07-23 国网天津市电力公司 风电电力系统自动发电控制调节容量的确定方法及装置
CN110728006B (zh) * 2019-10-08 2023-07-04 杭州阳斯信息技术有限公司 一种基于网格的供电单元自动划分方法
US11681438B2 (en) * 2021-05-28 2023-06-20 Dell Products L.P. Minimizing cost of disk fulfillment
CN113496316B (zh) * 2021-09-09 2022-02-11 广东电网有限责任公司惠州供电局 基于源荷时序耦合的容量配置方法、装置、系统及介质

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6981379B2 (en) * 2003-07-23 2006-01-03 The Japan Research Institute, Limited Power supply system
US8471531B2 (en) * 2007-03-20 2013-06-25 Belkin International, Inc. Estimated remaining life of a battery included in an uninterruptible power supply
CN101562339A (zh) * 2009-05-08 2009-10-21 东南大学 基于成功流的配电系统可靠性指标计算方法
US8401709B2 (en) * 2009-11-03 2013-03-19 Spirae, Inc. Dynamic distributed power grid control system
US9251479B2 (en) * 2010-07-02 2016-02-02 General Electric Technology Gmbh Multi-interval dispatch method for enabling dispatchers in power grid control centers to manage changes
US8538593B2 (en) * 2010-07-02 2013-09-17 Alstom Grid Inc. Method for integrating individual load forecasts into a composite load forecast to present a comprehensive synchronized and harmonized load forecast
US8774975B2 (en) * 2011-02-08 2014-07-08 Avista Corporation Outage management algorithm
US20140278162A1 (en) * 2013-03-15 2014-09-18 Echelon Corporation Detecting and locating power outages via low voltage grid mapping
US20160241031A1 (en) * 2015-02-18 2016-08-18 Nec Laboratories America, Inc. Dynamic probability-based power outage management system
US10164431B2 (en) * 2015-03-17 2018-12-25 General Electric Technology Gmbh Outage management and prediction for a power grid system

Similar Documents

Publication Publication Date Title
JP2015507913A5 (ja)
Bao et al. Modeling and evaluating nodal resilience of multi-energy systems under windstorms
Eser et al. Effect of increased renewables generation on operation of thermal power plants
Roy et al. Optimum sizing of wind-battery systems incorporating resource uncertainty
Liu et al. Coordination of hydro units with wind power generation using interval optimization
US20140365419A1 (en) Adaptation of a power generation capacity and determining of an energy storage unit size
US11249121B2 (en) Method of utility usage divergence identification between recurring consumption data indicative of repeating periodic consumption patterns and utility consumption data
CN111103565A (zh) 一种基于智能电能表计量误差分析的数据变换方法及系统
US10997674B2 (en) Determining a characteristic of an inertial contribution to an electric power grid
Edimu et al. Using probability distribution functions in reliability analyses
CN111784030B (zh) 一种基于空间相关性的分布式光伏功率预测方法及装置
Mohan et al. Solar energy disaggregation using whole-house consumption signals
Ahlert et al. Assessing the impact of price forecast errors on the economics of distributed storage systems
CN107844896A (zh) 适用于高风电渗透率电力系统的风电置信容量评估方法
Han et al. A study of the reduction of the regional aggregated wind power forecast error by spatial smoothing effects in the Maritimes Canada
Goergens et al. Determination of the potential to provide reactive power from distribution grids to the transmission grid using optimal power flow
CN105488342A (zh) 一种配电网升压运行项目碳减排量的核算方法
Faranda et al. SCADA system for optimization of energy exchange with the BESS in a residential case
Ried et al. Profitability of photovoltaic battery systems considering temporal resolution
JP2016039652A (ja) 配電系統管理装置、配電系統システムおよび配電系統管理方法
Amarasinghe et al. Capacity credit evaluation of wind and solar power generation using non-sequential Monte Carlo Simulation
Klonari et al. Probabilistic modeling of short term fluctuations of photovoltaic power injection for the evaluation of overvoltage risk in low voltage grids
Klonari et al. Probabilistic analysis tool of the voltage profile in low voltage grids
Sørnes et al. Analysis of the impact resolution has on load matching in the Norwegian context
Brusca A new statistical based energetic-economic methodology for wind turbine systems evaluation