Prior art keywords
hoisting machine
machine base
machine
hoisting
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2013138003A
Other languages
Japanese (ja)
Inventor
一浩 佐々木
Kazuhiro Sasaki
一浩 佐々木
川上 重信
Shigenobu Kawakami
重信 川上
谷口 淳太郎
Juntaro Taniguchi
淳太郎 谷口
健史 畑中
Kenji Hatanaka
健史 畑中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Corp
Mitsubishi Electric Building Solutions Corp
Original Assignee
Mitsubishi Electric Corp
Mitsubishi Electric Building Techno Service Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Corp, Mitsubishi Electric Building Techno Service Co Ltd filed Critical Mitsubishi Electric Corp
Priority to JP2013138003A priority Critical patent/JP2015009967A/en
Publication of JP2015009967A publication Critical patent/JP2015009967A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
  • Cage And Drive Apparatuses For Elevators (AREA)

Abstract

PROBLEM TO BE SOLVED: To replace a hoist as a roping system is 1:1 roping while utilizing existing machine bases.SOLUTION: First and second hoist base connection beams 27 and 28 are hung between a first hoist base 24 and a second hoist base 26. An additional beam 29 supporting intermediate parts of the first and second hoist base connection beams 27 and 28 is installed between a first machine base 21 and a second machine base 22. The additional beam 29 is horizontally disposed in parallel to the first and second machine bases 21 and 22. A hoist 4 is straddlingly fixed on the first and second hoist base connection beams 27 and 28 and the second hoist base 26.

Description

この発明は、機械台及び巻上機台等を有する巻上機支持装置上に巻上機が設置されているエレベータ装置、及び少なくとも巻上機の交換を含むエレベータ装置の改修方法に関するものである。   The present invention relates to an elevator apparatus in which a hoisting machine is installed on a hoisting machine support apparatus having a machine base, a hoisting machine base, and the like, and an elevator apparatus repair method including at least the hoisting machine replacement. .

従来のエレベータの改修方法では、既設の巻上機の近傍の空きスペースに新規の巻上機を設置し、ローピング方式を1:1ローピングから2:1ローピングに変更する(例えば、特許文献1、2参照)。   In the conventional elevator renovation method, a new hoisting machine is installed in an empty space near an existing hoisting machine, and the roping method is changed from 1: 1 roping to 2: 1 roping (for example, Patent Document 1, 2).

特開2008−30885号公報JP 2008-30885 A 特開2012−17165号公報JP 2012-17165 A

上記のような従来のエレベータの改修方法では、ローピング方式を2:1ローピングに変更するため、かご上にかご吊り車を、釣合おもりに釣合おもり吊り車をそれぞれ新規に取り付けなくてはならない。このため、機械室での巻上機設置作業だけではなく、かご上及び昇降路内での作業が増え、据付作業時間が長くなるとともにコストが増大する。   In the conventional elevator renovation method as described above, since the roping method is changed to 2: 1 roping, a car suspension car must be newly installed on the car and a counterweight car must be newly installed on the counterweight. . For this reason, not only the hoisting machine installation work in the machine room but also the work on the car and in the hoistway increase, the installation work time becomes longer and the cost increases.

また、例えば高速エレベータでは、機械台の間隔が長い場合がある。機械台の間隔が長いと、強度を確保するために、機械台の直上に設置される巻上機台の高さを高くしなくてはならない。しかし、機械室の天井高さは決まっているため、巻上機台の高さを高くすると、巻上機を設置するスペースを確保できなくなる場合がある。   Further, for example, in a high-speed elevator, the interval between the machine bases may be long. If the distance between the machine tables is long, the height of the hoisting machine table installed immediately above the machine table must be increased in order to ensure the strength. However, since the ceiling height of the machine room is fixed, if the height of the hoisting machine base is increased, it may be impossible to secure a space for installing the hoisting machine.

これに対して、機械台を撤去して新たに機械台及び巻上機台を設置すれば問題ないが、既設の機械台の端部が機械室壁に埋め込まれており、機械台の撤去が困難な場合がある。この場合は、機械台を流用しつつ、ローピング方式を2:1ローピングに変更して、巻上機を小型化し、機械台及び巻上機台にかかる荷重を軽減する方法を採らざるを得ない。   On the other hand, there is no problem if the machine base is removed and a new machine base and hoisting machine base are installed, but the end of the existing machine base is embedded in the machine room wall, and the machine base is removed. It can be difficult. In this case, a method of reducing the load applied to the machine base and the hoisting machine base by reducing the hoisting machine by changing the roping method to 2: 1 roping while diverting the machine base is unavoidable. .

この発明は、上記のような課題を解決するためになされたものであり、既設の機械台を利用しつつ、ローピング方式も1:1ローピングのままとして、巻上機を交換することができるエレベータ装置及びその改修方法を得ることを目的とする。   The present invention has been made in order to solve the above-described problems, and an elevator that can replace a hoisting machine while using an existing machine base and maintaining a roping method of 1: 1 roping. The object is to obtain a device and a method for its modification.

この発明に係るエレベータ装置は、昇降路の上部の機械室に設置されている巻上機支持装置、巻上機支持装置により支持されており、かつ駆動シーブを有している巻上機、駆動シーブに巻き掛けられている懸架体、及び懸架体により吊り下げられており、巻上機により昇降路内を昇降されるかご及び釣合おもりを備え、巻上機支持装置は、機械室に互いに間隔をおいて設置されている第1及び第2の機械台と、第1の機械台に沿って第1の機械台上に設置されている第1の巻上機台と、第2の機械台に沿って第2の機械台上に設置されている第2の巻上機台と、第1の巻上機台と第2の巻上機台との間に架設されている巻上機台連結梁と、第1の機械台と第2の機械台との間に設置されており、巻上機台連結梁の中間部を支持する追加梁とを有している。   An elevator apparatus according to the present invention includes a hoisting machine support device installed in a machine room at an upper part of a hoistway, a hoisting machine supported by the hoisting machine support apparatus and having a drive sheave, a drive A suspension body that is wound around a sheave, and a suspension body that is suspended by the suspension body and that is lifted and lowered in a hoistway by a hoisting machine. First and second machine bases installed at intervals, a first hoisting machine base installed on the first machine base along the first machine base, and a second machine A second hoisting machine stand installed on the second machine stand along the stand, and a hoisting machine installed between the first hoisting machine stand and the second hoisting machine stand A base connecting beam and an additional beam installed between the first machine base and the second machine base and supporting an intermediate portion of the hoisting machine base connecting beam. It is.

この発明のエレベータ装置は、第1の機械台と第2の機械台との間に追加梁を設置し、その追加梁により巻上機台連結梁の中間部を支持するようにしたので、第1及び第2の機械台の間隔が広い場合でも第1及び第2の巻上機台及び巻上機台連結梁の高さを高くする必要がない。このため、エレベータ装置を改修する際に、既設の第1及び第2の機械台を利用しつつ、ローピング方式も1:1ローピングのままとして、巻上機を交換することができる。   In the elevator apparatus according to the present invention, the additional beam is installed between the first machine base and the second machine base, and the intermediate portion of the hoisting machine base connecting beam is supported by the additional beam. Even when the distance between the first and second machine bases is wide, it is not necessary to increase the heights of the first and second hoisting machine bases and the hoisting machine base connecting beams. For this reason, when refurbishing the elevator apparatus, the hoisting machine can be replaced while the roping method is kept at 1: 1 roping while using the existing first and second machine bases.

この発明の実施の形態1によるエレベータ装置を示す側面図である。1 is a side view showing an elevator apparatus according to Embodiment 1 of the present invention. 図1の巻上機支持装置を示す側面図である。It is a side view which shows the winding machine support apparatus of FIG. 図2の巻上機支持装置を示す平面図である。It is a top view which shows the winding machine support apparatus of FIG. 図3のそらせ車を用いない変形例を示す平面図である。It is a top view which shows the modification which does not use the deflecting wheel of FIG.

以下、この発明を実施するための形態について、図面を参照して説明する。
実施の形態1.
図1はこの発明の実施の形態1によるエレベータ装置を示す側面図である。図において、昇降路1の上部には、機械室2が設けられている。機械室2内には、巻上機支持装置3が設置されている。巻上機支持装置3上には、巻上機4が支持されている。巻上機4は、駆動シーブ5及び巻上機本体6を有している。巻上機本体6は、駆動シーブ5を回転させる巻上機モータと、駆動シーブ5の回転を制動する巻上機ブレーキとを有している。
Hereinafter, embodiments for carrying out the present invention will be described with reference to the drawings.
Embodiment 1 FIG.
1 is a side view showing an elevator apparatus according to Embodiment 1 of the present invention. In the figure, a machine room 2 is provided in the upper part of the hoistway 1. A hoisting machine support device 3 is installed in the machine room 2. On the hoisting machine support device 3, the hoisting machine 4 is supported. The hoisting machine 4 has a drive sheave 5 and a hoisting machine main body 6. The hoisting machine main body 6 includes a hoisting machine motor that rotates the driving sheave 5 and a hoisting machine brake that brakes the rotation of the driving sheave 5.

巻上機支持装置3には、そらせ車7が支持されている。駆動シーブ5及びそらせ車7には、懸架体8が巻き掛けられている。懸架体8としては、例えば、複数本のロープ又は複数本のベルトが用いられている。   A deflecting wheel 7 is supported on the hoisting machine support device 3. A suspension body 8 is wound around the drive sheave 5 and the deflecting wheel 7. As the suspension body 8, for example, a plurality of ropes or a plurality of belts are used.

懸架体8の第1の端部には、かご9が接続されている。懸架体8の第2の端部には、釣合おもり10が接続されている。かご9及び釣合おもり10は、懸架体8により1:1ローピング方式で昇降路1内に吊り下げられており、巻上機4により昇降される。   A car 9 is connected to the first end of the suspension 8. A counterweight 10 is connected to the second end of the suspension 8. The car 9 and the counterweight 10 are suspended in the hoistway 1 by the suspension body 8 by a 1: 1 roping method, and are lifted and lowered by the hoisting machine 4.

昇降路1内には、かご9の昇降を案内する一対のかごガイドレール11と、釣合おもり10の昇降を案内する一対の釣合おもりガイドレール12とが設置されている。   In the hoistway 1, a pair of car guide rails 11 that guide the raising and lowering of the car 9 and a pair of counterweight guide rails 12 that guide the raising and lowering of the counterweight 10 are installed.

かご9は、懸架体8が接続されたかご枠13と、かご枠13に支持されているかご室14とを有している。   The car 9 has a car frame 13 to which the suspension body 8 is connected and a car room 14 supported by the car frame 13.

機械室2内には、エレベータ制御装置(制御盤)15が設置されている。エレベータ制御装置15は、巻上機4の回転を制御することにより、設定した速度でかご9を昇降させる。   An elevator control device (control panel) 15 is installed in the machine room 2. The elevator control device 15 raises and lowers the car 9 at a set speed by controlling the rotation of the hoist 4.

図2は図1の巻上機支持装置3を示す側面図、図3は図2の巻上機支持装置3を示す平面図である。機械室2の床上には、第1及び第2の機械台21,22が互いに間隔をおいて設置されている。第1及び第2の機械台21,22としては、同じサイズのH形鋼が用いられている。また、第1及び第2の機械台21,22は、互いに平行かつ水平に設置されている。   2 is a side view showing the hoisting machine support device 3 of FIG. 1, and FIG. 3 is a plan view showing the hoisting machine support device 3 of FIG. On the floor of the machine room 2, first and second machine tables 21 and 22 are installed with a space therebetween. As the first and second machine bases 21 and 22, H-section steels of the same size are used. The first and second machine bases 21 and 22 are installed in parallel and horizontally with each other.

第1の機械台21上には、複数の第1の防振部材23を介して第1の巻上機台24が設置されている。第1の巻上機台24は、第1の機械台21に沿って水平に配置されている。第2の機械台22上には、複数の第2の防振部材25を介して第2の巻上機台26が設置されている。第2の巻上機台26は、第2の機械台22に沿って水平に配置されている。   A first hoisting machine base 24 is installed on the first machine base 21 via a plurality of first vibration isolation members 23. The first hoisting machine base 24 is disposed horizontally along the first machine base 21. A second hoisting machine base 26 is installed on the second machine base 22 via a plurality of second vibration isolation members 25. The second hoisting machine base 26 is disposed horizontally along the second machine base 22.

第1及び第2の巻上機台24,26としては、同じサイズのH形鋼が用いられている。また、第1及び第2の巻上機台24,26の断面のサイズは、第1及び第2の機械台21,22の断面のサイズよりも小さい。第1及び第2の防振部材23,25としては、防振ゴムが用いられている。   As the first and second hoisting machine bases 24 and 26, H-shaped steel of the same size is used. The cross-sectional size of the first and second hoisting machine bases 24 and 26 is smaller than the cross-sectional size of the first and second machine bases 21 and 22. As the first and second vibration isolation members 23 and 25, vibration isolation rubber is used.

第1の巻上機台24と第2の巻上機台26との間には、第1及び第2の巻上機台連結梁27,28が架設されている。第1及び第2の巻上機台連結梁27,28は、第1及び第2の巻上機台24,26に直角に配置されている。また、第1及び第2の巻上機台連結梁27,28は、互いに平行かつ水平に配置されている。   Between the first hoisting machine base 24 and the second hoisting machine base 26, first and second hoisting machine base connecting beams 27 and 28 are installed. The first and second hoisting machine base connecting beams 27 and 28 are arranged at right angles to the first and second hoisting machine bases 24 and 26. Further, the first and second hoisting machine base connecting beams 27 and 28 are arranged in parallel with each other and horizontally.

さらに、第1及び第2の巻上機台連結梁27,28としては、同じサイズのH形鋼が用いられている。さらにまた、第1及び第2の巻上機台連結梁27,28の一端部は、上側のフランジ部が切除されて、第1の巻上機台24の上下のフランジ部間に挿入されている。同様に、第1及び第2の巻上機台連結梁27,28の他端部は、上側のフランジ部が切除されて、第2の巻上機台26の上下のフランジ部間に挿入されている。   Furthermore, the same size H-section steel is used as the first and second hoisting machine base connecting beams 27 and 28. Furthermore, one end of the first and second hoisting machine base connecting beams 27 and 28 is inserted between the upper and lower flanges of the first hoisting machine base 24 with the upper flange part cut away. Yes. Similarly, the other flanges of the first and second hoisting machine base connecting beams 27 and 28 are inserted between the upper and lower flange parts of the second hoisting machine base 26 with the upper flange part cut away. ing.

第1の機械台21と第2の機械台22との間には、第1及び第2の巻上機台連結梁27,28の中間部を支持する追加梁29が設置されている。追加梁29としては、H形鋼が用いられている。また、追加梁29は、アンカボルトにより機械室2の床上に固定されている。   Between the first machine base 21 and the second machine base 22, an additional beam 29 that supports an intermediate portion between the first and second hoisting machine base connecting beams 27 and 28 is installed. As the additional beam 29, H-section steel is used. Further, the additional beam 29 is fixed on the floor of the machine room 2 by anchor bolts.

さらに、追加梁29は、第1及び第2の機械台21,22に平行かつ水平に配置されている。さらにまた、追加梁29の高さは、第1の機械台21の高さと、第1の防振部材23の高さと、第1の巻上機台24の下側のフランジ部の高さ(厚さ)とを加えた高さに等しい。   Further, the additional beam 29 is disposed in parallel and horizontally with the first and second machine bases 21 and 22. Furthermore, the height of the additional beam 29 is the height of the first machine base 21, the height of the first vibration isolation member 23, and the height of the lower flange portion of the first hoisting machine base 24 ( (Thickness) and the height.

巻上機4は、第1及び第2の巻上機台連結梁27,28及び第2の巻上機台26上に跨って固定されている。そらせ車7は、第2の巻上機台連結梁28上に支持されている。巻上機支持装置3に対する巻上機4及びそらせ車7の取付位置は、水平方向へ調整可能になっている。図3に示すように、機械室2の床には、懸架体8を通す第1及び第2の懸架体挿通孔(ロープ孔)30a,30bが設けられている。   The hoisting machine 4 is fixed over the first and second hoisting machine base connecting beams 27 and 28 and the second hoisting machine base 26. The deflecting wheel 7 is supported on the second hoisting machine base connecting beam 28. The mounting positions of the hoisting machine 4 and the deflecting wheel 7 with respect to the hoisting machine support device 3 can be adjusted in the horizontal direction. As shown in FIG. 3, the floor of the machine room 2 is provided with first and second suspension body insertion holes (rope holes) 30 a and 30 b through which the suspension body 8 is passed.

次に、エレベータ装置の改修方法について説明する。図1〜3で示したのは改修後のエレベータ装置であり、かご9及び釣合おもり10等は改修前のエレベータ装置のものが流用されており、主に巻上機4及びエレベータ制御装置15等が新しいものとなっている(いわゆる制御リニューアル)。   Next, the repair method of an elevator apparatus is demonstrated. 1 to 3 show the elevator apparatus after the repair, and the car 9 and the counterweight 10 etc. are diverted from the elevator apparatus before the repair, and the hoisting machine 4 and the elevator control device 15 are mainly used. Etc. are new (so-called control renewal).

このような改修工事を行う場合、第1及び第2の機械台21,22を残して、既設の巻上機台、既設の巻上機、及び既設のそらせ車等を、第1及び第2の機械台21,22上から撤去する。また、既設のエレベータ制御装置も撤去する。   When performing such a renovation work, the first and second machine bases 21 and 22 are left, and the existing hoisting machine base, the existing hoisting machine, and the existing deflector are replaced with the first and second machine bases. Is removed from the machine bases 21 and 22. The existing elevator control device will also be removed.

この後、第1の機械台21上に第1の防振部材23を介して新規の第1の巻上機台24を設置する。また、第2の機械台22上に第2の防振部材25を介して新規の第2の巻上機台26を設置する。さらに、第1の機械台21と第2の機械台22との間に新規の追加梁29を並設する。   Thereafter, a new first hoisting machine base 24 is installed on the first machine base 21 via the first vibration isolation member 23. In addition, a new second hoisting machine base 26 is installed on the second machine base 22 via the second vibration isolation member 25. Furthermore, a new additional beam 29 is provided in parallel between the first machine base 21 and the second machine base 22.

そして、第1の巻上機台24と第2の巻上機台26との間に、新規の第1及び第2の巻上機台連結梁27,28を架設する。このとき、第1及び第2の巻上機台連結梁27,28の中間部を追加梁29により支持させる。   Then, new first and second hoisting machine base connecting beams 27 and 28 are installed between the first hoisting machine base 24 and the second hoisting machine base 26. At this time, the intermediate portion of the first and second hoisting machine base connecting beams 27 and 28 is supported by the additional beam 29.

この後、巻上機支持装置3上に、新規の巻上機4及び新規のそらせ車7を設置する。このとき、巻上機4の位置とそらせ車7の位置とを調整することにより、既存の懸架体挿通孔30a,30bを改修後も利用する。また、機械室2内に新規のエレベータ制御装置15を設置する。   Thereafter, a new hoisting machine 4 and a new deflecting wheel 7 are installed on the hoisting machine support device 3. At this time, by adjusting the position of the hoisting machine 4 and the position of the deflecting wheel 7, the existing suspension body insertion holes 30a and 30b are used even after the repair. In addition, a new elevator control device 15 is installed in the machine room 2.

このようなエレベータ装置では、第1の機械台21と第2の機械台22との間に追加梁29を設置し、その追加梁29により第1及び第2の巻上機台連結梁27,28の中間部を支持するようにしたので、第1及び第2の機械台21,22の間隔が広い場合でも第1及び第2の巻上機台24,26及び第1及び第2の巻上機台連結梁27,28の高さを高くする必要がない。   In such an elevator apparatus, the additional beam 29 is installed between the first machine base 21 and the second machine base 22, and the first and second hoisting machine base connecting beams 27, 28, the first and second hoisting machine bases 24 and 26 and the first and second windings are supported even when the distance between the first and second machine bases 21 and 22 is wide. It is not necessary to increase the height of the upper machine base connecting beams 27 and 28.

このため、エレベータ装置を改修する際に、既設の第1及び第2の機械台21,22を利用しつつ、ローピング方式も1:1ローピングのままとして、巻上機4を交換することができる。また、機械室2の天井高さによらず、巻上機4を楊重することが可能となる。   For this reason, when refurbishing the elevator apparatus, the hoisting machine 4 can be replaced while using the existing first and second machine bases 21 and 22 while maintaining the roping method as 1: 1 roping. . Further, the hoisting machine 4 can be weighted regardless of the ceiling height of the machine room 2.

さらに、上記のようなエレベータ装置の改修方法によれば、作業エリアを機械室2のみに限定して、工期短縮、原価低減を図ることが可能となる。   Furthermore, according to the elevator apparatus renovation method as described above, it is possible to limit the work area to the machine room 2 only, thereby shortening the work period and reducing the cost.

さらにまた、昇降路1内のかご9及び釣合おもり10の吊り位置を変更しないので、既設の懸架体挿通孔30a,30bを流用可能となる。これにより、新規に懸架体挿通孔を開けるよりも作業日数、工事費が安価になる。また、かご9と釣合おもり10の吊り点に変更がないので、ガイドレール11,12及びガイドシューも流用可能になる。   Furthermore, since the hanging positions of the car 9 and the counterweight 10 in the hoistway 1 are not changed, the existing suspension insertion holes 30a and 30b can be used. As a result, the number of work days and the construction costs are lower than when a new suspension hole is opened. In addition, since the suspension points of the car 9 and the counterweight 10 are not changed, the guide rails 11 and 12 and the guide shoe can also be used.

なお、上記の例では、巻上機支持装置3に巻上機4及びそらせ車7が支持されているが、例えば図4に示すように、そらせ車7を用いないエレベータ装置にもこの発明は適用できる。
また、上記の改修方法では、そらせ車7を交換したが、既設のそらせ車を流用してもよい。
さらに、この発明の巻上機支持装置3は、制御リニューアルの際だけでなく、かご9等を交換する改修工事にも使用することができる。
さらにまた、巻上機台連結梁の本数は2本に限定されず、1本又は3本以上であってもよい。
また、防振部材の位置や個数も上記の例に限定されない。例えば、巻上機支持装置3と巻上機4との間に防振部材を設けてもよい。また、追加梁29と巻上機台連結梁27,28との間に防振部材を追加してもよい。
さらに、追加梁29を長さ方向に2分割して、第1及び第2の巻上機台連結梁27,28を別々に支持させてもよい。
さらにまた、第1及び第2の機械台21,22の間に2本以上の追加梁を設置してもよい。
また、エレベータ装置全体の構成は、図1に限定されるものではなく、例えば釣合おもりがかごの側方の領域に配置されるタイプのエレベータ装置等であってもよい。
In the above example, the hoisting machine 4 and the deflecting wheel 7 are supported by the hoisting machine supporting device 3, but for example, as shown in FIG. Applicable.
Further, in the above repair method, the baffle 7 is replaced, but an existing baffle may be used.
Furthermore, the hoisting machine support device 3 of the present invention can be used not only for control renewal but also for repair work for replacing the car 9 and the like.
Furthermore, the number of hoisting machine base connecting beams is not limited to two, and may be one or three or more.
Further, the position and number of the vibration isolating members are not limited to the above example. For example, a vibration isolation member may be provided between the hoisting machine support device 3 and the hoisting machine 4. Further, a vibration isolating member may be added between the additional beam 29 and the hoisting machine base connecting beams 27 and 28.
Furthermore, the additional beam 29 may be divided into two in the length direction, and the first and second hoisting machine base connecting beams 27 and 28 may be separately supported.
Furthermore, two or more additional beams may be installed between the first and second machine bases 21 and 22.
Further, the configuration of the entire elevator apparatus is not limited to that shown in FIG.

1 昇降路、2 機械室、3 巻上機支持装置、4 巻上機、5 駆動シーブ、8 懸架体、9 かご、10 釣合おもり、21 第1の機械台、22 第2の機械台、23 第1の防振部材、24 第1の巻上機台、25 第2の防振部材、26 第2の巻上機台、27 第1の巻上機台連結梁、28 第2の巻上機台連結梁、29 追加梁、30a 第1の懸架体挿通孔、30b 第2の懸架体挿通孔。   DESCRIPTION OF SYMBOLS 1 Hoistway, 2 Machine room, 3 Hoisting machine support apparatus, 4 Hoisting machine, 5 Drive sheave, 8 Suspension body, 9 Car, 10 Counterweight, 21 1st machine stand, 22 2nd machine stand, 23 1st anti-vibration member, 24 1st hoisting machine stand, 25 2nd anti-vibration member, 26 2nd hoisting machine stand, 27 1st hoisting machine base connection beam, 28 2nd hoisting Upper machine base connection beam, 29 additional beam, 30a first suspension insertion hole, 30b second suspension insertion hole.

Claims (6)

昇降路の上部の機械室に設置されている巻上機支持装置、
前記巻上機支持装置により支持されており、かつ駆動シーブを有している巻上機、
前記駆動シーブに巻き掛けられている懸架体、及び
前記懸架体により吊り下げられており、前記巻上機により前記昇降路内を昇降されるかご及び釣合おもり
を備え、
前記巻上機支持装置は、
前記機械室に互いに間隔をおいて設置されている第1及び第2の機械台と、
前記第1の機械台に沿って前記第1の機械台上に設置されている第1の巻上機台と、
前記第2の機械台に沿って前記第2の機械台上に設置されている第2の巻上機台と、
前記第1の巻上機台と前記第2の巻上機台との間に架設されている巻上機台連結梁と、
前記第1の機械台と前記第2の機械台との間に設置されており、前記巻上機台連結梁の中間部を支持する追加梁とを有しているエレベータ装置。
Hoisting machine support device installed in the machine room above the hoistway,
A hoisting machine supported by the hoisting machine support device and having a drive sheave;
A suspension body wound around the drive sheave, and a car suspended from the suspension body and moved up and down in the hoistway by the hoisting machine and a counterweight,
The hoist supporting device is
First and second machine bases installed at a distance from each other in the machine room;
A first hoisting machine base installed on the first machine base along the first machine base;
A second hoisting machine base installed on the second machine base along the second machine base;
A hoisting machine connecting beam constructed between the first hoisting machine base and the second hoisting machine base;
The elevator apparatus which is installed between the said 1st machine stand and the said 2nd machine stand, and has the additional beam which supports the intermediate part of the said winding machine stand connection beam.
前記第1の機械台と前記第1の巻上機台との間、及び前記第2の機械台と前記第2の巻上機台との間には、それぞれ防振部材が介在している請求項1記載のエレベータ装置。   Anti-vibration members are interposed between the first machine base and the first hoisting machine base and between the second machine base and the second hoisting machine base, respectively. The elevator apparatus according to claim 1. 前記巻上機支持装置に支持されており、前記懸架体が巻き掛けられているそらせ車をさらに備え、
前記巻上機支持装置に対する前記巻上機及び前記そらせ車の取付位置が調整可能になっている請求項1又は請求項2に記載のエレベータ装置。
The hoisting machine is supported by the hoisting machine support device, and further includes a deflecting wheel around which the suspension body is wound.
The elevator apparatus according to claim 1 or 2, wherein attachment positions of the hoisting machine and the deflecting wheel with respect to the hoisting machine support apparatus are adjustable.
機械室の床上に互いに間隔をおいて設置されている第1及び第2の機械台を残して、既設の巻上機台と既設の巻上機とを、前記第1及び第2の機械台上から撤去する工程、
前記第1の機械台上に新規の第1の巻上機台を設置し、前記第2の機械台上に新規の第2の巻上機台を設置し、前記第1の機械台と前記第2の機械台との間に新規の追加梁を並設する工程、
前記第1の巻上機台と前記第2の巻上機台との間に新規の巻上機台連結梁を架設するとともに、前記巻上機台連結梁の中間部を前記追加梁により支持させる工程、及び
前記第1及び第2の機械台と、前記第1及び第2の巻上機台と、前記巻上機台連結梁と、前記追加梁とを有する巻上機支持装置上に、新規の巻上機を設置する工程
を含むエレベータ装置の改修方法。
The first and second machine bases are connected to the existing hoisting machine base and the existing hoisting machine with the first and second machine bases installed on the floor of the machine room spaced apart from each other. The process of removing from the top,
A new first hoisting machine base is installed on the first machine base, a new second hoisting machine base is installed on the second machine base, and the first machine base and the Arranging a new additional beam in parallel with the second machine base;
A new hoisting machine base connecting beam is installed between the first hoisting machine base and the second hoisting machine base, and an intermediate portion of the hoisting machine base connecting beam is supported by the additional beam. And a hoisting machine support device comprising: the first and second machine bases; the first and second hoisting machine bases; the hoisting machine base connecting beam; and the additional beam. A method for refurbishing an elevator system, including the process of installing a new hoisting machine.
前記巻上機支持装置上に前記新規の巻上機とともに新規のそらせ車を設置し、前記新規の巻上機の位置と前記新規のそらせ車の位置とを調整することにより、前記機械室の床に設けられた既存の懸架体挿通孔を改修後も利用する請求項4記載のエレベータ装置の改修方法。   A new deflecting wheel is installed on the hoisting machine support device together with the new hoisting machine, and by adjusting the position of the new hoisting machine and the position of the new deflecting wheel, The repair method of the elevator apparatus of Claim 4 which utilizes the existing suspension body penetration hole provided in the floor after repair. 前記第1の機械台上に新規の第1の巻上機台を設置し、前記第2の機械台上に新規の第2の巻上機台を設置する際に、前記第1の機械台と前記第1の巻上機台との間、及び前記第2の機械台と前記第2の巻上機台との間に、それぞれ防振部材を介在させる請求項4又は請求項5に記載のエレベータ装置の改修方法。   When installing a new first hoisting machine base on the first machine base and installing a new second hoisting machine base on the second machine base, the first machine base The vibration isolating member is interposed between the first and the first hoisting machine base and between the second machine base and the second hoisting machine base, respectively. Method of repairing elevator equipment.
JP2013138003A 2013-07-01 2013-07-01 Elevator device and repair method for the same Pending JP2015009967A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013138003A JP2015009967A (en) 2013-07-01 2013-07-01 Elevator device and repair method for the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2013138003A JP2015009967A (en) 2013-07-01 2013-07-01 Elevator device and repair method for the same

Publications (1)

Publication Number Publication Date
JP2015009967A true JP2015009967A (en) 2015-01-19

Family

ID=52303451

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2013138003A Pending JP2015009967A (en) 2013-07-01 2013-07-01 Elevator device and repair method for the same

Country Status (1)

Country Link
JP (1) JP2015009967A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020196555A (en) * 2019-05-31 2020-12-10 三菱電機ビルテクノサービス株式会社 Machine stand and elevator

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020196555A (en) * 2019-05-31 2020-12-10 三菱電機ビルテクノサービス株式会社 Machine stand and elevator
JP7274941B2 (en) 2019-05-31 2023-05-17 三菱電機ビルソリューションズ株式会社 Machine table and elevator

Similar Documents

Publication Publication Date Title
JP5951104B2 (en) Elevator repair method
JP2007099515A (en) Method for mounting support means of lift cage to lift cage and lift shaft
JP2013220859A (en) Head extension method for elevator for construction
KR20160046717A (en) A machine room-less elevator refurbishing method
KR101335800B1 (en) Elevator device
JP2016040187A (en) Machine room-less elevator repairing method, and machine room-less elevator
JP6270635B2 (en) Renovation method of machine room less elevator
JP2016079002A (en) Method for lifting elevator equipment
KR20160036787A (en) Installation structure for machine room-less elevator
JP5538470B2 (en) Lift extension method for construction elevators
JP2015009967A (en) Elevator device and repair method for the same
JP2012201497A (en) Machine bed and lifting device
JP6218483B2 (en) Elevator main rope fixing device and elevator repair method
JP2013245033A (en) Method of installing hoisting machine
JP2011020804A (en) Renewal method of elevator
JP5680198B2 (en) Elevator and elevator repair method
JP5474416B2 (en) Elevator equipment
JP2016008131A (en) Elevator and remodeling method of existing elevator
JP5806166B2 (en) Elevator repair equipment installation method
JP2015157676A (en) Elevator device
JP5382443B2 (en) How to renew an elevator
WO2023175881A1 (en) Installation method for hoisting machine
JP6806660B2 (en) How to repair a machine roomless elevator
JP2015071482A (en) Elevator device modification method and elevator device