JP2014125807A - Base isolation retrofit construction for existing building - Google Patents

Base isolation retrofit construction for existing building Download PDF

Info

Publication number
JP2014125807A
JP2014125807A JP2012283979A JP2012283979A JP2014125807A JP 2014125807 A JP2014125807 A JP 2014125807A JP 2012283979 A JP2012283979 A JP 2012283979A JP 2012283979 A JP2012283979 A JP 2012283979A JP 2014125807 A JP2014125807 A JP 2014125807A
Authority
JP
Japan
Prior art keywords
existing
existing building
seismic isolation
foundation
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2012283979A
Other languages
Japanese (ja)
Inventor
Masahiro Asai
政宏 浅井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2012283979A priority Critical patent/JP2014125807A/en
Publication of JP2014125807A publication Critical patent/JP2014125807A/en
Pending legal-status Critical Current

Links

Images

Abstract

PROBLEM TO BE SOLVED: To provide an effective and suitable base isolation retrofit construction method by which, when an existing building is renovated into a building having base isolation structure by subjecting the existing building to base isolation retrofit, excavation work on a bearing ground under the existing building can be reduced as much as possible.SOLUTION: After existing foundations 4 of an existing building 1 to be renovated are reinforced through work from a floor right above the existing foundations 4 in order to use existing foundations 4 as an upper foundations 6 of the existing building 1 after being subjected to base isolation retrofit, the whole existing building is jacked up onto a bearing ground 9 to thereby secure a clearance 13 finally serving as a base isolation pit 12 between the bearing ground and upper foundations. Lower foundations are newly provided at a bottom part of the clearance, a base isolation device is installed between the lower foundations and upper foundations, and the whole existing building is supported in a base-isolated state by the base isolation device through the upper foundations.

Description

本発明は既存建物を免震構造の建物に改修するための免震化工法に関する。   The present invention relates to a seismic isolation method for renovating an existing building to a base-isolated structure.

周知のように、建物全体を免震装置により水平方向に(3次元免震構造においては鉛直方向にも)変位可能に免震支持する免震構造では、基礎部に設けた免震ピットの底部に下部基礎を設けるとともに、建物の底部には上部基礎を下部基礎とは絶縁した状態で設けて、それら下部基礎と上部基礎との間に設置した積層ゴム等の免震装置を介して建物全体を免震支持することが基本となる。   As is well known, in the seismic isolation structure in which the entire building is supported by seismic isolation so that it can be displaced in the horizontal direction (also in the vertical direction in the case of a 3D seismic isolation structure), the bottom of the base isolation pit provided on the foundation A lower foundation is installed on the bottom of the building, and the upper foundation is insulated from the lower foundation at the bottom of the building, and the entire building is installed via a seismic isolation device such as laminated rubber installed between the lower foundation and the upper foundation. It is fundamental to support seismic isolation.

最近においては、以前に建設された重要な建物や歴史的な建造物の耐震性能を向上させるべく、既存建物を免震構造の建物に改修する免震化(いわゆる免震レトロフィット)も行われるようになってきている。   Recently, in order to improve the seismic performance of important buildings and historical buildings that have been constructed before, seismic isolation (so-called seismic isolation retrofit) is performed to upgrade existing buildings to seismic isolation structures. It has become like this.

既存建物を免震化するための工法としては、たとえば特許文献1に示されるように、既存建物全体を各種のアンダーピニング工法によって支持しつつ既存基礎下の支持地盤を全面的に掘削して免震ピットを形成し、免震ピットの底部に下部基礎を施工するとともに下部基礎上に免震装置を設置して、その免震装置によって既存建物全体を免震支持するという工法が最も一般的である。
その場合、既存建物における既存基礎は免震化後には上部基礎として機能するものとなる必要があるから、既存基礎の強度が不十分であるような場合には予め補強を行う必要がある。
As a method for making an existing building seismic isolation, as shown in Patent Document 1, for example, the entire existing building is supported by various underpinning methods, and the supporting ground under the existing foundation is excavated completely. The most common method is to form a seismic pit, construct a lower foundation at the bottom of the seismic isolation pit, install a seismic isolation device on the lower foundation, and use the seismic isolation device to support the entire existing building. is there.
In that case, since the existing foundation in the existing building needs to function as an upper foundation after the seismic isolation, it is necessary to reinforce in advance if the strength of the existing foundation is insufficient.

特開2002−242450号公報JP 2002-242450 A

しかし、上記のような従来一般的な免震化工法において免震ピットを形成する場合には、既存建物の下部の支持地盤に対して大規模な掘削工事を実施しなければならず、しかもその作業は大型重機を使用できない狭隘な空間での非効率的な作業とならざるを得ないことが通常であるから、そのために多大な改修費用と工期を要することが不可避である。   However, when a seismic isolation pit is formed in the conventional seismic isolation method as described above, a large-scale excavation work must be carried out on the supporting ground below the existing building. Since the work usually has to be an inefficient work in a narrow space where large heavy machinery cannot be used, it is inevitable that a large amount of repair cost and work period are required for that purpose.

したがって、既存建物の免震化を広く普及するためには、免震化に際して既存建物の下部に対する掘削工事を可及的に削減することが必要であるとされ、それを可能とする有効適切な免震化工法の開発が望まれているのが実状である。   Therefore, in order to widely spread seismic isolation of existing buildings, it is necessary to reduce excavation work to the lower part of existing buildings as much as possible during seismic isolation. In fact, the development of seismic isolation methods is desired.

上記事情に鑑み、本発明は、既存建物を免震構造の建物に改修するための免震化工法であって、改修対象の既存建物における既存基礎を免震化後の上部基礎とするべく直上階からの作業により補強を行った後、前記既存建物の全体を支持地盤上にジャッキアップすることにより、該支持地盤と前記上部基礎との間に免震ピットとなるクリアランスを確保し、前記クリアランスの底部に下部基礎を新設するとともに、該下部基礎と前記上部基礎との間に免震装置を設置して、該免震装置により前記上部基礎を介して前記既存建物の全体を免震支持することを特徴とする。   In view of the above circumstances, the present invention is a seismic isolation method for renovating an existing building to a base-isolated structure, and the existing foundation in the target building to be refurbished is directly above the base after the seismic isolation. After reinforcing the work from the floor, by jacking up the entire existing building on the supporting ground, a clearance to be a seismic isolation pit is secured between the supporting ground and the upper foundation, and the clearance A base is newly installed at the bottom of the base, and a seismic isolation device is installed between the lower base and the upper base, and the seismic isolation device supports the entire existing building through the upper base. It is characterized by that.

本発明によれば、従来一般的な免震化工法のように免震ピットを形成するために既存建物の下部の支持地盤全体に対して全面的な掘削を行うのではなく、既存建物全体をジャッキアップすることによって免震ピットを確保するので、既存建物の下部に対する掘削は既存基礎に対する補強とジャッキアップ作業を実施するうえで必要となる最少限の範囲に対してのみ行えば良く、したがって従来工法に比べて掘削工事を大幅に削減することが可能であってそれによる工費削減と工期短縮を実現できる。
また、従来工法においては既存建物の地下部に対する大掛かりな地下工事が主体となるのに対し、本実施形態の工法では実質的に既存建物の内外から地表部に対する作業が中心となるので地下工事を大幅に軽減可能であり、その点においても施工性を大きく改善し得る。
According to the present invention, in order to form a seismic isolation pit as in the conventional general seismic isolation method, the entire existing building is not excavated for the entire supporting ground below the existing building. Since the seismic isolation pit is secured by jacking up, excavation to the lower part of the existing building only needs to be carried out to the minimum range necessary for reinforcing the existing foundation and jacking up, and thus the conventional Compared to the construction method, excavation work can be greatly reduced, which can reduce the construction cost and the construction period.
In addition, the conventional construction method mainly involves large-scale underground work for the underground part of the existing building, whereas the construction method of this embodiment is mainly for the work on the surface part from the inside and outside of the existing building. It can be greatly reduced, and in this respect, the workability can be greatly improved.

本発明の免震化工法の実施形態を示すもので、免震化対象の既存建物の基礎部を示す概略図である。The embodiment of the seismic isolation method of the present invention is a schematic diagram showing the foundation of an existing building to be seismically isolated. 同、既存基礎を補強して上部基礎を新設した状態を示す図である。It is a figure which shows the state which reinforces the existing foundation and newly established the upper foundation. 同、既存建物全体をジャッキアップして免震ピットとなるクリアランスを確保した状態を示す図である。It is a figure which shows the state which secured the clearance used as a seismic isolation pit by jacking up the whole existing building. 同、完成状態を示す図である。It is a figure which shows a completion state similarly.

以下、本発明の免震化工法の実施形態について図1〜図4を参照して説明する。   Hereinafter, an embodiment of the seismic isolation method of the present invention will be described with reference to FIGS.

図1は本発明による改修対象の既存建物1の基礎部の概略構成を示すものである。この既存建物1は地上部の躯体が既存柱2としての鉄骨柱と既存梁3としての鉄骨梁とによる鉄骨造によるものであり、既存基礎4は基礎梁5とフーチング16による直接基礎とされているものである。   FIG. 1 shows a schematic configuration of a foundation of an existing building 1 to be repaired according to the present invention. In this existing building 1, the ground frame is made of steel with a steel column as an existing column 2 and a steel beam as an existing beam 3, and the existing foundation 4 is a direct foundation by a foundation beam 5 and a footing 16. It is what.

本実施形態ではその既存建物1を免震構造の建物に改修する(免震化する)に当たり、既存基礎4が改修後には上部基礎6として機能し得るものとなるように、まず図2に示すように既存基礎4の要所に補強基礎梁7を増設する等の補強を行う。
その補強作業は既存基礎4の直上階(図示例では地上1階)から行うものとし、そのためには1階の床スラブ8を必要な範囲だけ解体して、既存建物1の内部からの作業により既存建物1の直下の支持地盤9を既存基礎4の周囲の必要個所を局所的に掘削することにより、補強基礎梁7の増設スペースとその作業のための作業空間を確保すれば良い。
In this embodiment, when the existing building 1 is renovated into a base-isolated structure (is seismically isolated), the existing foundation 4 is first shown in FIG. 2 so that it can function as the upper foundation 6 after the renovation. In this way, reinforcement such as the addition of a reinforcing foundation beam 7 is performed at a point of the existing foundation 4.
The reinforcement work is performed from the floor directly above the existing foundation 4 (in the illustrated example, the first floor above the ground). For that purpose, the floor slab 8 on the first floor is disassembled to the extent necessary and the work from the inside of the existing building 1 is performed. An additional space for the reinforcing foundation beam 7 and a work space for the work may be secured by excavating the supporting ground 9 directly under the existing building 1 at necessary locations around the existing foundation 4.

次いで、図3に示すように既存建物1の全体をジャッキアップする。
すなわち、所要台数のジャッキ10を要所に設置し、それらジャッキ10を同期させて制御しつつ作動させて既存建物1の全体を持ち上げて徐々に上昇させていく。
その際、ジャッキ10の設置位置は既存柱2の直下や図示例のようにその周囲に増設した補強基礎梁7の位置とすれば良く、必要であればジャッキ10の設置スペースを確保するために支持地盤9を必要最少限の範囲で掘削すれば良い。
なお、ジャッキ10の反力は従来一般的な各種のアンダーピニング工法等により支障なく確保できるが、必要であれば適宜の仮設基礎を設けたり、ジャッキアップ時の水平変位を拘束するために要所に仮設の水平拘束部材11を設置する等して既存建物1の全体を安定に支持すれば良い。
Next, as shown in FIG. 3, the entire existing building 1 is jacked up.
That is, the required number of jacks 10 are installed at important points, and the jacks 10 are operated while being controlled in synchronization, and the entire existing building 1 is lifted and gradually raised.
At that time, the installation position of the jack 10 may be the position of the reinforcing foundation beam 7 directly below the existing pillar 2 or the surrounding area as shown in the figure, and if necessary, in order to secure the installation space of the jack 10 What is necessary is just to excavate the support ground 9 in the required minimum range.
The reaction force of the jack 10 can be secured without any trouble by various conventional underpinning methods. However, if necessary, it is important to provide an appropriate temporary foundation or constrain horizontal displacement during jack-up. It is only necessary to stably support the entire existing building 1 by installing a temporary horizontal restraint member 11 or the like.

上記のようにして既存建物1全体をジャッキアップして、上部基礎6(補強後の既存基礎4)と支持地盤9との間に最終的には免震ピット12となるクリアランス13を確保する。
そのクリアランス13の所要高さ(すなわちジャッキアップにより上昇させる距離)は、後施工する下部基礎14(図示は略したが下部基礎梁を含む)の版厚および免震装置15の高さ寸法も考慮して、最終的に所定高さの免震ピット12を確保し得るように適宜設定すれば良いが、通常は2m程度で十分である。
As described above, the entire existing building 1 is jacked up, and a clearance 13 that finally becomes the seismic isolation pit 12 is secured between the upper foundation 6 (the existing foundation 4 after reinforcement) and the supporting ground 9.
The required height of the clearance 13 (that is, the distance to be raised by jacking up) also takes into account the plate thickness of the lower foundation 14 (not shown but including the lower foundation beam) to be post-worked and the height dimension of the seismic isolation device 15 Then, it may be set as appropriate so that the seismic isolation pit 12 having a predetermined height can be finally secured, but about 2 m is usually sufficient.

以上のようにして免震ピット12となるクリアランス13を確保したうえで、図4に示すようにクリアランス13の底部に対して下部基礎14(下部基礎梁を含む)を新設するとともに、下部基礎14(下部基礎梁を含む)上に所望台数の免震装置15を要所に設置してその上部を上部基礎6に対して接合することにより、それら免震装置15によって上部基礎6を介して既存建物1全体を免震支持する。
しかる後に、ジャッキ10および水平拘束部材11を撤去するとともに、他に適宜の仮設材を設置しておいた場合にはそれら仮設材も撤去する。
After securing the clearance 13 to be the seismic isolation pit 12 as described above, the lower foundation 14 (including the lower foundation beam) is newly installed on the bottom of the clearance 13 as shown in FIG. By installing the desired number of seismic isolation devices 15 on the main points (including the lower foundation beams) and joining the upper part to the upper foundation 6, existing seismic isolation devices 15 through the upper foundation 6 Seismic isolation support for the entire building 1.
Thereafter, the jack 10 and the horizontal restraint member 11 are removed, and if any other temporary material is installed, the temporary material is also removed.

本実施形態の免震化工法によれば、従来一般的な免震化工法のように免震ピット12を形成するために既存建物1の下部の支持地盤9を全面的に掘り下げるのではなく、逆に既存建物1全体をジャッキアップすることによって免震ピット12を形成するので、既存建物1の下部の支持地盤9に対する掘削は既存基礎4に対する補強とジャッキ10の設置スペースを確保するうえで必要となる最少限の範囲に対してのみ局所的に行えば良く、したがって従来工法に比べて掘削工事を大幅に削減することが可能であり、それによる工費削減と工期短縮を実現できる。   According to the seismic isolation method of this embodiment, instead of digging down the supporting ground 9 at the bottom of the existing building 1 in order to form the seismic isolation pit 12 as in the conventional general seismic isolation method, Conversely, since the seismic isolation pit 12 is formed by jacking up the entire existing building 1, excavation of the supporting ground 9 at the lower part of the existing building 1 is necessary to reinforce the existing foundation 4 and secure the installation space of the jack 10. Therefore, the excavation work can be greatly reduced as compared with the conventional method, so that the construction cost and the construction period can be shortened.

すなわち、本実施形態の工法により施工する免震ピット12と同等の免震ピットを従来工法により支持地盤を掘削して施工する場合には、既存建物1の直下の支持地盤9を図4に鎖線で示す範囲まで深く掘削する必要があるのに対し、本実施形態では実質的に地表部をわずかに浅く掘削するだけで足り、それに要する工費と工期を従来工法に比べて大幅に軽減することが可能となる。
また、従来工法においては既存建物1の下部に対する大掛かりな地下工事が主体となるのに対し、本実施形態の工法では実質的に既存建物1の内外からの地表部に対する作業が中心となるので、地下工事を軽減できる点においても施工性を大きく改善し得るものである。
That is, in the case where a base isolation pit equivalent to the base isolation pit 12 constructed by the construction method of the present embodiment is excavated and constructed by the conventional construction method, the support ground 9 directly under the existing building 1 is shown by a chain line in FIG. However, in this embodiment, it is only necessary to excavate the surface part slightly shallower, and the cost and time required for the excavation can be greatly reduced compared to the conventional method. It becomes possible.
Moreover, in the conventional construction method, large-scale underground work for the lower part of the existing building 1 is mainly performed, whereas in the construction method of the present embodiment, the work on the ground surface portion from the inside and outside of the existing building 1 is mainly performed. In terms of reducing underground work, the workability can be greatly improved.

勿論、本実施形態の工法による場合には、単に免震化に伴う改修が必要となるばかりでなく、改修後には既存建物1の全体の高さが改修前よりもジャッキアップした分だけ高くなることからそれに伴う改修工事も当然に必要となるが、建物全体がたとえば2m程度高くなったとしても使用勝手はさして変わるものではないし、そのための改修費用も掘削工事の削減により十分に相殺することが可能である。
なお、本実施形態の工法による改修(免震化)により建物高さは高くはなるが面積は変わらないので法的には増築には該当せず、また既存建物の過半に及ぶような大規模な改修工事に該当するものでもないので、通常は確認申請等の煩雑な法的手続きは必要としない。
Of course, in the case of the construction method according to the present embodiment, not only the renovation accompanying the seismic isolation is required, but also the total height of the existing building 1 becomes higher by the amount jacked up than before the renovation. Therefore, the renovation work that accompanies it is of course necessary, but even if the entire building is about 2 meters high, for example, the convenience of use will not change, and the renovation costs for that purpose can be offset sufficiently by reducing excavation work. Is possible.
In addition, although the building height is increased by the renovation (seismic isolation) by the construction method of this embodiment, the area does not change, so it is not legally an extension, and it is a large scale that covers the majority of existing buildings It does not correspond to any renovation work, so it usually does not require complicated legal procedures such as application for confirmation.

以上で本発明の実施形態について説明したが、上記実施形態はあくまで一例に過ぎず、本発明の免震化工法における具体的な工程や、既存基礎に対する補強の程度、改修後の免震ピットや免震装置等の細部の具体的な構成その他については、免震化対象の既存建物の構造や規模、必要とされる免震性能、支持地盤の状況その他の諸条件を考慮して最適設計すれば良い。   Although the embodiment of the present invention has been described above, the above embodiment is merely an example, the specific steps in the seismic isolation method of the present invention, the degree of reinforcement with respect to the existing foundation, the seismic isolation pit after repair, The specific configuration and other details of the seismic isolation device, etc. should be optimally designed in consideration of the structure and size of the existing building subject to seismic isolation, the required seismic isolation performance, the status of the supporting ground, and other conditions. It ’s fine.

たとえば、上記実施形態は既存建物の既存基礎が直接基礎である場合の適用例であるが、既存基礎が杭基礎の場合にも杭頭部への改修が必要とはなるだけで実質的に上記実施形態と同様の工程により適用可能である。   For example, the above embodiment is an application example in the case where the existing foundation of the existing building is a direct foundation, but even if the existing foundation is a pile foundation, only the repair to the pile head is necessary and the above-mentioned embodiment is substantially the above. The present invention can be applied by the same process as the embodiment.

1 既存建物
2 既存柱
3 既存梁
4 既存基礎
5 基礎梁
6 上部基礎
7 補強基礎梁
8 床スラブ
9 支持地盤
10 ジャッキ
11 水平拘束部材
12 免震ピット
13 クリアランス
14 下部基礎
15 免震装置
16 フーチング
DESCRIPTION OF SYMBOLS 1 Existing building 2 Existing pillar 3 Existing beam 4 Existing foundation 5 Foundation beam 6 Upper foundation 7 Reinforcement foundation beam 8 Floor slab 9 Support ground 10 Jack 11 Horizontal restraint member 12 Seismic isolation pit 13 Clearance 14 Lower foundation 15 Seismic isolation device 16 Footing

Claims (1)

既存建物を免震構造の建物に改修するための免震化工法であって、
改修対象の既存建物における既存基礎を免震化後の上部基礎とするべく直上階からの作業により補強を行った後、
前記既存建物の全体を支持地盤上にジャッキアップすることにより、該支持地盤と前記上部基礎との間に免震ピットとなるクリアランスを確保し、
前記クリアランスの底部に下部基礎を新設するとともに、該下部基礎と前記上部基礎との間に免震装置を設置して、該免震装置により前記上部基礎を介して前記既存建物の全体を免震支持することを特徴とする既存建物の免震化工法。
A seismic isolation method for renovating an existing building to a seismically isolated building,
After reinforcing the existing foundation in the existing building to be refurbished from the upper floor to make it the upper foundation after seismic isolation,
By jacking up the entire existing building on a supporting ground, a clearance to be a seismic isolation pit is secured between the supporting ground and the upper foundation,
A lower foundation is newly installed at the bottom of the clearance, and a seismic isolation device is installed between the lower foundation and the upper foundation, and the entire existing building is seismically isolated via the upper foundation by the seismic isolation device. Seismic isolation method for existing buildings, characterized by support.
JP2012283979A 2012-12-27 2012-12-27 Base isolation retrofit construction for existing building Pending JP2014125807A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2012283979A JP2014125807A (en) 2012-12-27 2012-12-27 Base isolation retrofit construction for existing building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2012283979A JP2014125807A (en) 2012-12-27 2012-12-27 Base isolation retrofit construction for existing building

Publications (1)

Publication Number Publication Date
JP2014125807A true JP2014125807A (en) 2014-07-07

Family

ID=51405532

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012283979A Pending JP2014125807A (en) 2012-12-27 2012-12-27 Base isolation retrofit construction for existing building

Country Status (1)

Country Link
JP (1) JP2014125807A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836839A (en) * 2016-11-29 2017-06-13 大连久鼎祥瑞特种工程技术研究院有限公司 Fabric structure jacking increasing layer method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09317208A (en) * 1996-05-29 1997-12-09 Taisei Corp Base isolation construction method for existing wooden house
JP2001271497A (en) * 2000-03-24 2001-10-05 Kajima Corp Temporary bearing construction method for existing building

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09317208A (en) * 1996-05-29 1997-12-09 Taisei Corp Base isolation construction method for existing wooden house
JP2001271497A (en) * 2000-03-24 2001-10-05 Kajima Corp Temporary bearing construction method for existing building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836839A (en) * 2016-11-29 2017-06-13 大连久鼎祥瑞特种工程技术研究院有限公司 Fabric structure jacking increasing layer method

Similar Documents

Publication Publication Date Title
JP2020522635A (en) Open caisson construction structure and construction method
JP5811389B2 (en) Construction method for underground structures
JP2017014853A (en) Method for replacing seismic isolator
JP5038170B2 (en) How to rebuild a structure
JP2012112121A (en) Excavation method of ground under spread foundation and base-isolating method of existing building
CN107460886B (en) Light steel structure assembly and decoration integrated building foundation and construction method thereof
JP5698405B1 (en) Ground improvement solid foundation method
JP4624867B2 (en) Seismic isolation repair method for existing buildings
JP6052541B2 (en) Seismic isolation method for existing buildings
JP5540044B2 (en) Hydraulic jack jig used for restoration work for uneven settlement of buildings and repair method for unevenly settled buildings using this jig
JP5465086B2 (en) Construction method of underground structure
JP2014125807A (en) Base isolation retrofit construction for existing building
JP5316897B2 (en) Seismic isolation method
JP4228308B2 (en) Reinforcement method for existing floors and seismic isolation method for existing buildings
JP2016089481A (en) Extension method for underground facility
AU2020100004A4 (en) A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method
JP5739051B1 (en) Liquefaction countermeasure structure for ground improvement solid foundation and correction method for occurrence of uneven settlement due to liquefaction
JP4896549B2 (en) Structure setting method
JP2017036559A (en) Seismic isolator replacement method
JP6379975B2 (en) Construction method of a building having a base-isolated layer in the basement, and a building constructed by the construction method
JP2016079651A (en) Support structure
JP6534026B2 (en) Seismic isolation building and its construction method
JP2014025309A (en) Construction method for new foundation, and temporary support plate
JP3975438B2 (en) Inclined repair method for dirt concrete building
JP2017002697A (en) Seismic isolation method using ground reinforcement

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20150611

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20160407

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20160419

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20161101