JP2014108735A - Work barge - Google Patents

Work barge Download PDF

Info

Publication number
JP2014108735A
JP2014108735A JP2012264442A JP2012264442A JP2014108735A JP 2014108735 A JP2014108735 A JP 2014108735A JP 2012264442 A JP2012264442 A JP 2012264442A JP 2012264442 A JP2012264442 A JP 2012264442A JP 2014108735 A JP2014108735 A JP 2014108735A
Authority
JP
Japan
Prior art keywords
main body
ship
fair
underwater
leader
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2012264442A
Other languages
Japanese (ja)
Inventor
Toshiichi Oka
寿一 岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2012264442A priority Critical patent/JP2014108735A/en
Publication of JP2014108735A publication Critical patent/JP2014108735A/en
Pending legal-status Critical Current

Links

Landscapes

  • Jib Cranes (AREA)

Abstract

PROBLEM TO BE SOLVED: To efficiently make a material carrying vessel come alongside a work barge.SOLUTION: A through-hole is formed at a center portion in a fore-and-aft direction of a left side edge portion of a barge body 11. An underwater fair-leader 41 is inserted in the through-hole. The underwater fair-leader 41 is detachably attached to the barge body 11 at an upper part thereof. On the barge body 11 behind the underwater fair-leader 41, a winch 25 is installed. A wire rope 55 fed forward by the winch 25 is led from the barge body 11 into water immediately below the barge body 11 by the underwater fair-leader 41, bent and extended to a left front side, and fixed to an anchor 5 at one end. Near the underwater fair-leader 41 in the barge body 11, a material carrying vessel 81 is made to come alongside. At that time, the material carrying vessel 81 is positioned on a left side of a crane 70. Under the material carrying vessel 81, the wire rope 55 extending from the underwater fair-leader 41 to the anchor 5 is positioned.

Description

本発明は、作業台船に関し、詳しくは、作業台船を係留する技術に関する。   The present invention relates to a work table ship, and more particularly to a technique for mooring a work table ship.

特許文献1では、作業台船の台船本体が平面視で矩形状を成しており、台船本体上の四隅には、ウインチとフェアリーダとがそれぞれ設置されている。各ウインチは、係留用のワイヤーロープを巻き取り・繰り出し可能である。フェアリーダは、ウインチより繰り出されるワイヤーロープを案内する機能を有している。各ワイヤーロープの一端(繰り出し側端)には、それぞれ、係留用のアンカーが連結されている。特許文献1では、台船本体上の各ウインチからのワイヤーロープを、各々に対応するフェアリーダに掛けまわした上で、台船本体の四方(前方、後方、左方、及び右方)にそれぞれ繰り出して、更に、アンカーを水底に接地させることで、作業台船を係留している。   In Patent Document 1, the base ship body of the work table ship has a rectangular shape in plan view, and winches and fair leaders are respectively installed at the four corners on the base ship body. Each winch can wind and unwind a wire rope for mooring. The fair leader has a function of guiding the wire rope fed out from the winch. Anchors for mooring are connected to one end (feeding side end) of each wire rope. In Patent Document 1, the wire rope from each winch on the main body of the trolley is hung on the fair leader corresponding to each, and the four directions (front, rear, left, and right) of the main body are respectively The work boat is moored by unwinding and grounding the anchor to the bottom of the water.

特開平04−146887号公報Japanese Patent Laid-Open No. 04-146887

しかしながら、特許文献1のように作業台船の係留を行うときには、台船本体上からフェアリーダを介してその四方に繰り出されたワイヤーロープが、台船本体の外縁部近傍の水面を通って、水底のアンカーまで延びる。
このため、作業台船本体の外縁部に例えば資材運搬船を接舷させるときには、水面近くのワイヤーロープを避けて資材運搬船を作業台船本体の外縁部に近づけなければならない。従って、作業台船における接舷可能箇所が制限され、また、資材運搬船の作業台船への接舷作業を効率的に行うことができなかった。
本発明は、このような実状に鑑み、資材運搬船などの船を効率良く接舷可能な作業台船を提供することを目的とする。
However, when mooring the work platform as in Patent Document 1, the wire rope fed out in the four directions from the top of the platform via the fair leader passes through the water surface near the outer edge of the platform, Extends to the bottom anchor.
For this reason, when, for example, a material carrier ship is brought into contact with the outer edge portion of the work table ship body, the material carrier ship must be brought closer to the outer edge portion of the work table ship body while avoiding a wire rope near the water surface. Accordingly, the places where the work table ship can be contacted are limited, and the work of contacting the material carrier ship to the work table ship cannot be performed efficiently.
In view of such a situation, an object of the present invention is to provide a work platform ship capable of efficiently bringing a ship such as a material transport ship into contact.

そのため本発明に係る作業台船は、上下方向に貫通する貫通孔が形成されて水面上に浮かぶ台船本体と、この台船本体上に設置されて係留索を巻き取り・繰り出し可能なウインチと、台船本体の貫通孔に挿入されて台船本体上から水中に延出し、上部が台船本体に着脱可能に取り付けられる筒状のガイド装置本体、このガイド装置本体の上端部に設けられる第1ガイド部、及び、ガイド装置本体の下端部に設けられる第2ガイド部を備える係留索ガイド装置と、を含んで構成される。ウインチより繰り出される係留索については、係留索ガイド装置の第1ガイド部、ガイド装置本体内、及び、第2ガイド部を経て、外部のアンカーに一端が固定される。   Therefore, the work table ship according to the present invention includes a base ship body that has a through-hole penetrating in the vertical direction and floats on the water surface, and a winch that is installed on the base ship body and can wind and unwind the mooring line. A cylindrical guide device main body inserted into a through hole of the base boat main body and extending underwater from the top of the base boat main body, and the upper part is detachably attached to the main body of the base ship. 1 mooring guide apparatus provided with the 2nd guide part provided in the lower end part of 1 guide part and a guide apparatus main body. As for the mooring line fed out from the winch, one end is fixed to an external anchor through the first guide part of the mooring line guide apparatus, the inside of the guide apparatus main body, and the second guide part.

本発明によれば、係留索ガイド装置は、台船本体の貫通孔に挿入されて台船本体上から水中に延出する筒状のガイド装置本体、このガイド装置本体の上端部に設けられる第1ガイド部、及び、ガイド装置本体の下端部に設けられる第2ガイド部を備える。これにより、ウインチより繰り出される係留索が、水中に位置する上記第2ガイド部を経てアンカーに固定されるので、台船本体に接舷される船の下方に係留索を位置させることができる。従って、係留中の作業台船に船を接舷させるときに、係留索を避けて船を作業台船に近づける手間を軽減することができるので、作業台船に船を効率良く接舷させることができる。
また本発明によれば、係留索ガイド装置を構成するガイド装置本体が、台船本体に着脱可能に取り付けられる。これにより、作業台船の移動時(例えば曳航時)には、台船本体から係留索ガイド装置を取り外すことができるので、作業台船が受ける抵抗を抑制することができ、ひいては、作業台船の移動をスムーズに行うことができる。
According to the present invention, the mooring line guide device is inserted into the through hole of the base boat main body and extends into the water from the top of the base boat main body, and is provided at the upper end of the guide device main body. 1 guide part and the 2nd guide part provided in the lower end part of a guide apparatus main body are provided. As a result, the mooring line fed out from the winch is fixed to the anchor via the second guide portion located in the water, so that the mooring line can be positioned below the ship that is in contact with the main body of the carriage. Therefore, it is possible to reduce the effort to avoid the mooring line and bring the ship close to the work table ship when the ship is attached to the work table ship that is moored. Can do.
Moreover, according to this invention, the guide apparatus main body which comprises a mooring rope guide apparatus is attached to a trolley main body so that attachment or detachment is possible. As a result, the mooring line guide device can be removed from the main body of the work table when the work table ship moves (for example, when towing), so that the resistance received by the work table ship can be suppressed. Can be moved smoothly.

本発明の一実施形態における作業台船の概略平面図1 is a schematic plan view of a work table ship according to an embodiment of the present invention. 図1のA−A断面図AA sectional view of FIG. 係留索ガイド装置の概略構成を示す図The figure which shows schematic structure of a mooring line guide apparatus

図1は、本発明の一実施形態における作業台船の概略構成を示す。図2は、図1のA−A断面を示す。
尚、図1では、後述するワイヤーロープ55、56の水中部分を破線で示している。
また、本実施形態では、ダム工事で使用される作業台船を例にとって本発明に係る作業台船の説明を行うが、本発明に係る作業台船の用途はこれに限らず、あらゆる水上作業に用いられ得る。
また、本実施形態では、便宜上、作業台船のうち、ダム堤体に対向する側を前側として、前後左右を規定している。
FIG. 1 shows a schematic configuration of a work platform ship according to an embodiment of the present invention. FIG. 2 shows an AA cross section of FIG.
In addition, in FIG. 1, the underwater part of the wire ropes 55 and 56 mentioned later is shown with the broken line.
Further, in this embodiment, the work table ship according to the present invention will be described taking a work table ship used in dam construction as an example. However, the use of the work table ship according to the present invention is not limited to this, and any surface work. Can be used.
Further, in the present embodiment, for the sake of convenience, the front, rear, left and right are defined with the side facing the dam dam body as the front side of the work platform ship.

ダム堤体1の上流側に位置するダム貯水池2には、その水面上に作業台船10が浮かんでいる。
ダム堤体1の左岸3にはアンカー4、5が設けられている。アンカー4、5は、水面より高位に位置している。
アンカー4、5は、例えば、左岸3の岩盤にカバーコンクリート(図示せず)を打設し、このカバーコンクリートにアンカープレート(図示せず)を取り付けることで形成され得る。
尚、アンカー4、5については、一体的に設けられてもよい。
In the dam reservoir 2 located on the upstream side of the dam body 1, a work table ship 10 floats on the water surface.
Anchors 4 and 5 are provided on the left bank 3 of the dam body 1. The anchors 4 and 5 are located higher than the water surface.
The anchors 4 and 5 can be formed, for example, by placing cover concrete (not shown) on the rock on the left bank 3 and attaching an anchor plate (not shown) to the cover concrete.
The anchors 4 and 5 may be provided integrally.

ダム堤体1の右岸6にはアンカー7、8が設けられている。アンカー7、8は、水面より高位に位置している。
アンカー7、8については、アンカー4、5と同様に右岸6に形成され得るので、その説明を省略する。
尚、アンカー7、8についても、アンカー4、5と同様に一体的に設けられてもよい。
Anchors 7 and 8 are provided on the right bank 6 of the dam body 1. The anchors 7 and 8 are located higher than the water surface.
Since the anchors 7 and 8 can be formed on the right bank 6 similarly to the anchors 4 and 5, the description thereof is omitted.
The anchors 7 and 8 may also be provided integrally in the same manner as the anchors 4 and 5.

作業台船10は、平面視で矩形状を成す台船本体11と、6個のウインチ21〜26と、4個のフェアリーダ31〜34と、2個の水中フェアリーダ41、42と、を含んで構成される。
台船本体11は、複数の直方体状の浮体を平面状に組み立てて形成されている。
台船本体11の左右両側縁部の前端部には、それぞれ、左前フェアリーダ31と右前フェアリーダ32とが設けられている。
The work table ship 10 includes a table ship main body 11 having a rectangular shape in plan view, six winches 21 to 26, four fair leaders 31 to 34, and two underwater fair leaders 41 and 42. Consists of including.
The carrier main body 11 is formed by assembling a plurality of rectangular parallelepiped floating bodies into a flat shape.
A left front fair leader 31 and a right front fair leader 32 are provided at the front ends of the left and right side edges of the main body 11 respectively.

左前フェアリーダ31の後方の台船本体11上には、左前ウインチ21が設置されている。
左前ウインチ21より前方に繰り出されるワイヤーロープ(係留索)51は、左前フェアリーダ31にて左前方に屈曲されて延びて、一端(繰り出し側端)がアンカー4に固定される。
ワイヤーロープ51の他端側(巻き取り側)は、左前ウインチ21のドラム(図示せず)に巻き付けられている。
左前ウインチ21は、電動モータ又は油圧モータを回転駆動源として上述のドラムを回転させることにより、ワイヤーロープ51の巻き取り・繰り出しを行う。
A front left winch 21 is installed on the main body 11 behind the front left fairlead 31.
A wire rope (a mooring line) 51 fed forward from the left front winch 21 is bent and extended to the left front by the left front fair leader 31, and one end (feeding side end) is fixed to the anchor 4.
The other end side (winding side) of the wire rope 51 is wound around a drum (not shown) of the left front winch 21.
The left front winch 21 winds and unwinds the wire rope 51 by rotating the drum described above using an electric motor or a hydraulic motor as a rotational drive source.

右前フェアリーダ32の後方の台船本体11上には、右前ウインチ22が設置されている。
右前ウインチ22より前方に繰り出されるワイヤーロープ(係留索)52は、右前フェアリーダ32にて右前方に屈曲されて延びて、一端(繰り出し側端)がアンカー7に固定される。
ワイヤーロープ52の他端側(巻き取り側)は、右前ウインチ22のドラム(図示せず)に巻き付けられている。
右前ウインチ22は、電動モータ又は油圧モータを回転駆動源として上述のドラムを回転させることにより、ワイヤーロープ52の巻き取り・繰り出しを行う。
A right front winch 22 is installed on the main body 11 behind the right front fairlead 32.
A wire rope (mooring line) 52 fed forward from the right front winch 22 is bent and extended right forward by the right front fair leader 32, and one end (feeding side end) is fixed to the anchor 7.
The other end side (winding side) of the wire rope 52 is wound around a drum (not shown) of the right front winch 22.
The right front winch 22 winds and unwinds the wire rope 52 by rotating the drum described above using an electric motor or a hydraulic motor as a rotational drive source.

台船本体11の左右両側縁部の後端部には、それぞれ、左後フェアリーダ33と右後フェアリーダ34とが設けられている。
左後フェアリーダ33の前方の台船本体11上には、左後ウインチ23が設置されている。
左後ウインチ23より後方に繰り出されるワイヤーロープ(係留索)53は、左後フェアリーダ33にて右後方に屈曲されて延びており、一端(繰り出し側端)に予め固定された錨61が、水底に接地されている。
ワイヤーロープ53の他端側(巻き取り側)は、左後ウインチ23のドラム(図示せず)に巻き付けられている。
左後ウインチ23は、電動モータ又は油圧モータを回転駆動源として上述のドラムを回転させることにより、ワイヤーロープ53の巻き取り・繰り出しを行う。
A left rear fair leader 33 and a right rear fair leader 34 are provided at the rear ends of the left and right side edges of the carriage main body 11, respectively.
A left rear winch 23 is installed on the carriage main body 11 in front of the left rear fair leader 33.
A wire rope (mooring line) 53 that is fed backward from the left rear winch 23 is bent and extended to the right rear by the left rear fair leader 33, and a hook 61 fixed in advance at one end (feeding side end) Grounded at the bottom of the water.
The other end side (winding side) of the wire rope 53 is wound around a drum (not shown) of the left rear winch 23.
The left rear winch 23 winds and unwinds the wire rope 53 by rotating the drum described above using an electric motor or a hydraulic motor as a rotational drive source.

右後フェアリーダ34の前方の台船本体11上には、右後ウインチ24が設置されている。
右後ウインチ24より後方に繰り出されるワイヤーロープ(係留索)54は、右後フェアリーダ34にて左後方に屈曲されて延びており、一端(繰り出し側端)に予め固定された錨62が、水底に接地されている。
ワイヤーロープ54の他端側(巻き取り側)は、右後ウインチ24のドラム(図示せず)に巻き付けられている。
右後ウインチ24は、電動モータ又は油圧モータを回転駆動源として上述のドラムを回転させることにより、ワイヤーロープ54の巻き取り・繰り出しを行う。
A right rear winch 24 is installed on the main body 11 in front of the right rear fairlead 34.
A wire rope (mooring line) 54 that is fed backward from the right rear winch 24 is bent and extended to the left rear by the right rear fair leader 34, and a hook 62 fixed in advance at one end (feeding side end) Grounded at the bottom of the water.
The other end side (winding side) of the wire rope 54 is wound around a drum (not shown) of the right rear winch 24.
The right rear winch 24 winds and unwinds the wire rope 54 by rotating the drum described above using an electric motor or a hydraulic motor as a rotational drive source.

台船本体11の左右両側縁部のうち前後方向での中央部には、それぞれ、上下方向に貫通する貫通孔13、14が形成されている。
左貫通孔13には水中フェアリーダ41が挿入される。水中フェアリーダ41は、本発明に係る係留索ガイド装置に対応するものであり、その上部にて、台船本体11に着脱可能に取り付けられている。
水中フェアリーダ41の後方の台船本体11上には、左中ウインチ25が設置されている。
Through holes 13 and 14 penetrating in the vertical direction are respectively formed in the central part in the front-rear direction of the left and right side edges of the carriage main body 11.
An underwater fair leader 41 is inserted into the left through hole 13. The underwater fair leader 41 corresponds to the mooring line guide device according to the present invention, and is detachably attached to the carriage main body 11 at the upper part thereof.
A left middle winch 25 is installed on the carriage main body 11 behind the underwater fair leader 41.

左中ウインチ25より前方に繰り出されるワイヤーロープ(係留索)55は、水中フェアリーダ41にて台船本体11上から直下の水中に導かれ、更に左前方に屈曲されて延びて、一端(繰り出し側端)がアンカー5に固定される。
ワイヤーロープ55の他端側(巻き取り側)は、左中ウインチ25のドラム(図示せず)に巻き付けられている。
左中ウインチ25は、電動モータ又は油圧モータを回転駆動源として上述のドラムを回転させることにより、ワイヤーロープ55の巻き取り・繰り出しを行う。
A wire rope (mooring line) 55 fed forward from the left middle winch 25 is guided by the underwater fair leader 41 to the water immediately below the main body 11 and further bent and extended to the left front, and has one end (feed out). The side end) is fixed to the anchor 5.
The other end side (winding side) of the wire rope 55 is wound around a drum (not shown) of the left middle winch 25.
The left middle winch 25 winds and unwinds the wire rope 55 by rotating the drum described above using an electric motor or a hydraulic motor as a rotational drive source.

ここで、水中フェアリーダ41の構成について、図3を用いて説明する。
図3は、図2の部分Bの部分拡大図であり、水中フェアリーダ41の概略構成を示す。
水中フェアリーダ41は、上下方向に延在して所定長さを有する筒状のフェアリーダ本体44と、フェアリーダ本体44の上端部に設けられる第1ガイド部45と、フェアリーダ本体44の下端部に設けられる第2ガイド部46と、を含んで構成される。ここで、フェアリーダ本体44の所定長さについては、後述する資材運搬船81、82の寸法や接舷状況などを考慮して設定され得る。
Here, the configuration of the underwater fair leader 41 will be described with reference to FIG.
FIG. 3 is a partially enlarged view of the portion B in FIG. 2 and shows a schematic configuration of the underwater fair leader 41.
The underwater fair leader 41 includes a cylindrical fair leader main body 44 that extends in the vertical direction and has a predetermined length, a first guide portion 45 provided at the upper end of the fair leader main body 44, and a lower end of the fair leader main body 44. And a second guide part 46 provided in the part. Here, the predetermined length of the fair leader main body 44 can be set in consideration of the dimensions of the material transporting ships 81 and 82 described later, the circumstance of contact, and the like.

フェアリーダ本体44は、本発明に係るガイド装置本体に対応するものであり、台船本体11の左貫通孔13に挿入されて、台船本体11上から水中に延出している。
フェアリーダ本体44は、その上端部にフランジ部44aを備え、このフランジ部44aを介して、台船本体11に固定されている。尚、フェアリーダ本体44の台船本体11への固定箇所は、フェアリーダ本体44の上端部に限らず、フェアリーダ本体44の上部の任意の箇所であり得る。
The fair leader main body 44 corresponds to the guide device main body according to the present invention, is inserted into the left through-hole 13 of the trolley main body 11, and extends from above the trolley main body 11 into the water.
The fair leader main body 44 includes a flange portion 44a at an upper end portion thereof, and is fixed to the carriage main body 11 through the flange portion 44a. The location where the fair leader main body 44 is fixed to the carriage main body 11 is not limited to the upper end portion of the fair leader main body 44, and may be an arbitrary location on the upper portion of the fair leader main body 44.

第1ガイド部45は、回転自在なシーブ47を含んで構成されている。このシーブ47には、ワイヤーロープ55が巻き掛けられている。
第1ガイド部45では、左中ウインチ25より繰り出されるワイヤーロープ55が、シーブ47を介して、フェアリーダ本体44内に導かれる。
The first guide portion 45 includes a rotatable sheave 47. A wire rope 55 is wound around the sheave 47.
In the first guide portion 45, the wire rope 55 fed out from the left middle winch 25 is guided into the fair leader main body 44 through the sheave 47.

第2ガイド部46は、フェアリーダ本体44の中心軸を回転軸としてフェアリーダ本体44に対して回転自在なように、フェアリーダ本体44の下端に取り付けられている。
第2ガイド部46では、互いに逆方向に回転自在な一対のシーブ48、49でワイヤーロープ55を挟みつつ、いずれか一方のシーブにワイヤーロープ55が巻き掛けられる。尚、図3では、シーブ49にワイヤーロープ55が巻き掛けられている状態を示している。
第2ガイド部46は、フェアリーダ本体44内から水中へ延びるワイヤーロープ55を、アンカー5に向かう方向に屈曲させる機能を有する。
従って、左中ウインチ25より繰り出されるワイヤーロープ55は、第1ガイド部45、フェアリーダ本体44内、及び、第2ガイド部46を経て、アンカー5に一端(繰り出し側端)が固定される。
The second guide portion 46 is attached to the lower end of the fair leader body 44 so as to be rotatable with respect to the fair leader body 44 with the central axis of the fair leader body 44 as a rotation axis.
In the second guide portion 46, the wire rope 55 is wound around one of the sheaves while the wire rope 55 is sandwiched between a pair of sheaves 48 and 49 that are rotatable in opposite directions. 3 shows a state in which the wire rope 55 is wound around the sheave 49.
The second guide portion 46 has a function of bending a wire rope 55 extending from the fair leader main body 44 into the water in a direction toward the anchor 5.
Accordingly, the wire rope 55 fed out from the left middle winch 25 is fixed to the anchor 5 at one end (feed-out side end) through the first guide portion 45, the fair leader body 44, and the second guide portion 46.

図1及び図2に戻って、右貫通孔14には水中フェアリーダ42が挿入される。水中フェアリーダ42は、本発明に係る係留索ガイド装置に対応するものであり、その上部にて、台船本体11に着脱可能に取り付けられている。尚、水中フェアリーダ42の構成は、水中フェアリーダ41の構成と同様であるので、その説明を省略する。   Returning to FIGS. 1 and 2, the underwater fair leader 42 is inserted into the right through hole 14. The underwater fair leader 42 corresponds to the mooring line guide device according to the present invention, and is detachably attached to the carriage main body 11 at the upper part thereof. In addition, since the structure of the underwater fair leader 42 is the same as that of the underwater fair leader 41, the description is abbreviate | omitted.

水中フェアリーダ42の後方の台船本体11上には、右中ウインチ26が設置されている。
右中ウインチ26より前方に繰り出されるワイヤーロープ(係留索)56は、水中フェアリーダ42にて台船本体11上から直下の水中に導かれ、更に右前方に屈曲されて延びて、一端(繰り出し側端)がアンカー8に固定される。
ワイヤーロープ56は、その他端側(巻き取り側)が、右中ウインチ26のドラム(図示せず)に巻き付けられている。
右中ウインチ26は、電動モータ又は油圧モータを回転駆動源として上述のドラムを回転させることにより、ワイヤーロープ56の巻き取り・繰り出しを行う。
A right middle winch 26 is provided on the main body 11 behind the underwater fair leader 42.
A wire rope (mooring line) 56 fed forward from the right middle winch 26 is guided by the underwater fair leader 42 into the water immediately below the main body 11 and further bent and extended forward to the right, one end (fed out). The side end) is fixed to the anchor 8.
The other end side (winding side) of the wire rope 56 is wound around a drum (not shown) of the right middle winch 26.
The right middle winch 26 winds and unwinds the wire rope 56 by rotating the drum described above using an electric motor or a hydraulic motor as a rotational drive source.

台船本体11上の前側中央部には、クレーン70が配置されている。クレーン70は、例えば、クローラクレーンであり、下部にクローラを装備した全旋回式ベースマシン71と、このベースマシン71に基端部が枢支されて上下方向に揺動可能なブーム72とを含んで構成される。
台船本体11における左貫通孔13及び水中フェアリーダ41の近傍の左側縁部(外縁部)には、資材運搬船81が接舷されている。このときに、資材運搬船81は、クレーン70の左方に位置している。また、資材運搬船81の下方には、水中フェアリーダ41の第2ガイド部46からアンカー5に延びるワイヤーロープ55が位置している。
台船本体11における右貫通孔14及び水中フェアリーダ42の近傍の右側縁部(外縁部)には、資材運搬船82が接舷されている。このときに、資材運搬船82は、クレーン70の右方に位置している。また、資材運搬船82の下方には、水中フェアリーダ42の第2ガイド部46からアンカー8に延びるワイヤーロープ56が位置している。
A crane 70 is disposed at the front center on the main body 11. The crane 70 is, for example, a crawler crane, and includes an all-swivel base machine 71 equipped with a crawler at a lower portion, and a boom 72 that is pivotally supported by the base machine 71 and swingable in the vertical direction. Consists of.
A material carrier 81 is in contact with a left side edge (outer edge) in the vicinity of the left through hole 13 and the underwater fair leader 41 in the main body 11. At this time, the material carrier 81 is located on the left side of the crane 70. A wire rope 55 extending from the second guide portion 46 of the underwater fair leader 41 to the anchor 5 is located below the material carrier 81.
A material carrier 82 is in contact with the right edge (outer edge) in the vicinity of the right through hole 14 and the underwater fair leader 42 in the main body 11. At this time, the material carrier 82 is located on the right side of the crane 70. A wire rope 56 extending from the second guide portion 46 of the underwater fair leader 42 to the anchor 8 is positioned below the material carrier 82.

台船本体11には、ワイヤーロープ53、54のサグ(弛み)により、後方への引張力が作用している。
このため、台船本体11は、後方への引張力に対する反力を、主としてワイヤーロープ55、56から得ることで、その位置を保持している。
尚、ワイヤーロープ51、52については、主として、クレーン70の旋回による台船本体11のブレを抑制する機能を有する。
また、作業台船10の後退時には、ウインチ21、22、25、26よりワイヤーロープ51、52、55、56を繰り出してこれらワイヤーロープを弛ませることで、上述の後方への引張力により、作業台船10がスムーズに後退する。
A backward pulling force is applied to the main body 11 due to the sag (slack) of the wire ropes 53 and 54.
For this reason, the main body 11 maintains its position by obtaining a reaction force against the rearward tensile force mainly from the wire ropes 55 and 56.
The wire ropes 51 and 52 mainly have a function of suppressing the shake of the main body 11 due to the turning of the crane 70.
Further, when the work table ship 10 is retracted, the wire ropes 51, 52, 55, and 56 are unwound from the winches 21, 22, 25, and 26 to loosen the wire ropes. The trolley 10 moves backward smoothly.

次に、作業台船10を用いる作業の一例として、既設ダムの改修工事を例に取って、以下説明する。
既設ダムの改修工事では、ダム堤体1へのアクセスが困難なことから、ダム貯水池2に作業台船10を浮かべて、作業台船10から作業することが必要となる場合が多い。
この作業の一例としては、作業台船10上のクレーン70を用いて、資材運搬船81、82上の資材を、ダム堤体1の工事箇所に荷揚げする作業を挙げることができる。
Next, as an example of the work using the work table ship 10, a repair work for an existing dam will be taken as an example and described below.
In the renovation work for existing dams, it is difficult to access the dam dam body 1, so it is often necessary to work from the work table ship 10 by floating the work table ship 10 in the dam reservoir 2.
As an example of this work, the work of unloading the material on the material carrying ships 81 and 82 to the construction site of the dam body 1 using the crane 70 on the work table ship 10 can be mentioned.

この荷揚げ作業に際して、クレーン70が搭載された作業台船10を用いる場合には、クレーン70の作業半径が大きくなると、クレーン70の吊り能力が低下する。この対策としては、クレーン70をダム堤体1に接近させることで、クレーン70の作業半径を小さくすることにより、クレーン70の吊り能力の低下を抑制することが考えられる。
クレーン70をダム堤体1に接近させるためには、作業台船10もダム堤体1に接近させる必要がある。
At the time of this unloading operation, when the work platform ship 10 on which the crane 70 is mounted is used, when the work radius of the crane 70 is increased, the lifting ability of the crane 70 is reduced. As a countermeasure against this, it is conceivable that the crane 70 is moved closer to the dam dam body 1 to reduce the working radius of the crane 70, thereby suppressing the decrease in the suspension capacity of the crane 70.
In order for the crane 70 to approach the dam dam body 1, the work table ship 10 also needs to be brought close to the dam dam body 1.

しかしながら、作業台船10を係留するためのアンカーをダム堤体1に設けることは、ダム堤体1に負担がかかるので、実現性が低い。
それゆえ、左岸3にアンカー4を設けると共に、右岸6にアンカー7を設けて、各アンカーにワイヤーロープ51、52の一端を固定して、ワイヤーロープ51、52を介して、作業台船10を係留することが考えられる。
However, providing the anchor for mooring the work platform ship 10 in the dam dam body 1 imposes a burden on the dam dam body 1, so that the feasibility is low.
Therefore, the anchor 4 is provided on the left bank 3, the anchor 7 is provided on the right bank 6, one end of the wire ropes 51, 52 is fixed to each anchor, and the work table ship 10 is connected via the wire ropes 51, 52. It can be moored.

しかしながら、フェアリーダ31、32からアンカー4、7に向かうワイヤーロープ51、52の延在方向と、作業台船10の前進方向とが成す角の角度が比較的大きいので、作業台船10をダム堤体1に接近させるのに必要とされる牽引力を、ウインチ21、22の巻き取り力でカバーすることが難しい。
このため、本実施形態では、左岸3にアンカー5を設けると共に、右岸6にアンカー8を設けて、各アンカーにワイヤーロープ55、56の一端を固定して、作業台船10を係留している。
すなわち、フェアリーダ31、32より後方に位置する水中フェアリーダ41、42からアンカー5、8に向かうワイヤーロープ55、56の延在方向と、作業台船10の前進方向とが成す角の角度が、ワイヤーロープ51、52の延在方向と、作業台船10の前進方向とが成す角の角度に比べて小さいので、作業台船10をダム堤体1に接近させるのに必要とされる牽引力を、ウインチ25、26の巻き取り力でカバーすることができる。
However, since the angle formed by the extending direction of the wire ropes 51 and 52 from the fair leaders 31 and 32 to the anchors 4 and 7 and the forward direction of the worktable ship 10 is relatively large, the worktable ship 10 is It is difficult to cover the traction force required to approach the dam body 1 with the winding force of the winches 21 and 22.
For this reason, in this embodiment, while providing the anchor 5 in the left bank 3, the anchor 8 is provided in the right bank 6, the end of the wire ropes 55 and 56 is fixed to each anchor, and the work platform ship 10 is moored. .
That is, the angle formed by the extending direction of the wire ropes 55 and 56 from the underwater fair leaders 41 and 42 located behind the fair leaders 31 and 32 to the anchors 5 and 8 and the forward direction of the work table ship 10 is The pulling force required to bring the work table ship 10 closer to the dam body 1 is smaller than the angle formed by the extending direction of the wire ropes 51 and 52 and the forward direction of the work table ship 10. Can be covered with the winding force of the winches 25, 26.

作業台船10をダム堤体1に接近させることにより、クレーン70をダム堤体1に接近させて、作業台船10を係留させた後に、クレーン70により、資材の荷揚げが行われる。
資材運搬船81に搭載された資材をクレーン70で荷揚げする場合には、クレーン70を左に90°旋回させる。
資材運搬船82に搭載された資材をクレーン70で荷揚げする場合には、クレーン70を右に90°旋回させる。
このように、本実施形態では、資材運搬船81、82からダム堤体1の工事箇所への資材の荷揚げを、クレーン70の旋回角度180°程度の範囲内(左右各90°程度の範囲内)で行うことができるので、クレーン作業のサイクルタイムを抑制することができる。
By bringing the work table ship 10 close to the dam body 1, the crane 70 is brought close to the dam body 1 and the work table ship 10 is moored, and then the material is unloaded by the crane 70.
When the material loaded on the material carrier 81 is unloaded by the crane 70, the crane 70 is turned 90 ° to the left.
When the material loaded on the material carrier 82 is unloaded by the crane 70, the crane 70 is turned 90 ° to the right.
Thus, in this embodiment, the material unloading from the material carriers 81 and 82 to the construction site of the dam dam body 1 is within the range of the turning angle of the crane 70 of about 180 ° (within the range of about 90 ° on the left and right). Therefore, the cycle time of crane work can be suppressed.

本実施形態によれば、作業台船1は、上下方向に貫通する貫通孔13が形成されて水面上に浮かぶ台船本体11と、この台船本体11上に設置されてワイヤーロープ(係留索)55を巻き取り・繰り出し可能なウインチ25と、台船本体11の貫通孔13に挿入されて台船本体11上から水中に延出し、上部が台船本体11に着脱可能に取り付けられる筒状のフェアリーダ本体(ガイド装置本体)44、このフェアリーダ本体44の上端部に設けられる第1ガイド部45、及び、フェアリーダ本体44の下端部に設けられる第2ガイド部46を備える水中フェアリーダ(係留索ガイド装置)41と、を含んで構成される。ウインチ25より繰り出されるワイヤーロープ55は、第1ガイド部45、フェアリーダ本体44内、及び、第2ガイド部46を経て、外部のアンカー5に一端(繰り出し側端)が固定される。これにより、ウインチ25より繰り出されるワイヤーロープ55が、水中に位置する第2ガイド部46を経てアンカー5に固定されるので、台船本体11に接舷される資材運搬船81の下方にワイヤーロープ55を位置させることができる。従って、係留中の作業台船10に資材運搬船81を接舷させるときに、ワイヤーロープ55を避けて資材運搬船81を作業台船10に近づける手間を軽減することができるので、作業台船10に資材運搬船81を効率良く接舷させることができる。   According to the present embodiment, the work boat 1 has a through-hole 13 penetrating in the vertical direction and a main body 11 that floats on the surface of the water, and a wire rope (mooring cable) installed on the main body 11. ) A winch 25 capable of winding and unwinding 55 and a cylindrical shape that is inserted into the through hole 13 of the carriage main body 11 and extends from the carriage main body 11 into the water, and the upper part is detachably attached to the carriage main body 11. An underwater fair reader comprising a fair leader main body (guide device main body) 44, a first guide portion 45 provided at the upper end portion of the fair reader main body 44, and a second guide portion 46 provided at the lower end portion of the fair reader main body 44. (A mooring line guide device) 41. One end of the wire rope 55 fed out from the winch 25 is fixed to the external anchor 5 through the first guide portion 45, the fair leader main body 44, and the second guide portion 46. As a result, the wire rope 55 fed out from the winch 25 is fixed to the anchor 5 through the second guide portion 46 located in the water, so that the wire rope 55 is below the material carrier ship 81 that is in contact with the base body 11. Can be positioned. Accordingly, when the material carrier ship 81 is brought into contact with the moored work table ship 10, it is possible to reduce the trouble of bringing the material carrier ship 81 close to the work table ship 10 by avoiding the wire rope 55. The material transport ship 81 can be brought into contact with each other efficiently.

また本実施形態によれば、水中フェアリーダ41の第2ガイド部46はフェアリーダ本体44に対して回転自在に取り付けられているので、作業台船10の前進・後退時に、その動きに追従するようにワイヤーロープ55の延在方向を変更させて、ワイヤーロープ55をアンカー5の位置する方向に向かわせることができる。   In addition, according to the present embodiment, the second guide portion 46 of the underwater fair leader 41 is rotatably attached to the fair leader main body 44, so that the movement of the work platform ship 10 follows the movement. Thus, the extending direction of the wire rope 55 can be changed so that the wire rope 55 can be directed in the direction in which the anchor 5 is positioned.

また本実施形態によれば、水中フェアリーダ(係留索ガイド装置)41を構成するフェアリーダ本体(ガイド装置本体)44が、台船本体11に着脱可能に取り付けられる。これにより、作業台船10の移動時(例えば曳航時)には、台船本体11から水中フェアリーダ41を取り外すことができるので、作業台船10が受ける抵抗を抑制することができ、ひいては、作業台船10の移動をスムーズに行うことができる。また、台船本体11については、上述の複数の直方体状の浮体に分割されて、作業場所であるダム貯水池2に運搬されるが、フェアリーダ本体44が台船本体11に着脱可能であるので、運搬時には、取り外した状態での運搬が容易である。   Moreover, according to this embodiment, the fair leader main body (guide apparatus main body) 44 which comprises the underwater fair leader (mooring line guide apparatus) 41 is attached to the trolley main body 11 so that attachment or detachment is possible. Thereby, since the underwater fair leader 41 can be removed from the main body 11 when the work table ship 10 moves (for example, during towing), the resistance received by the work table ship 10 can be suppressed. The work table ship 10 can be moved smoothly. The carriage main body 11 is divided into the above-described plurality of rectangular parallelepiped floating bodies and transported to the dam reservoir 2 as a work place, but the fair leader body 44 is detachable from the carriage main body 11. When transporting, it is easy to transport in the removed state.

また本実施形態によれば、台船本体11の左右両側縁部(外縁部)に貫通孔13、14が形成され、台船本体11における貫通孔13、14近傍の外縁部に資材運搬船81、82が接舷される。これにより、貫通孔13、14に挿入される水中フェアリーダ41、42(フェアリーダ本体44)の上記所定長さを、資材運搬船81、82の寸法や接舷状況などに応じて、比較的簡易に設定することができる。   Moreover, according to this embodiment, the through-holes 13 and 14 are formed in the right-and-left both-sides edge (outer edge part) of the trolley main body 11, and the material carrier ship 81, 82 is bordered. As a result, the predetermined length of the underwater fair leaders 41 and 42 (fair leader main body 44) inserted into the through holes 13 and 14 is relatively simple depending on the dimensions of the material transporting ships 81 and 82, the state of contact, and the like. Can be set to

また本実施形態によれば、台船本体11上にクレーン70が配置され、台船本体11におけるクレーン70の側方に貫通孔13、14が形成される。これにより、クレーン70の側方に水中フェアリーダ41、42を設置することができるので、作業台船10における水中フェアリーダ41、42の近傍に資材運搬船81、82を接舷させることができる。従って、クレーン70の側方に資材運搬船81、82を位置させることができるので、資材運搬船81、82からダム堤体1の工事箇所への資材の荷揚げを、クレーン70の旋回角度180°程度の範囲内(左右各90°程度の範囲内)で行うことができ、ひいては、クレーン作業のサイクルタイムを抑制することができる。   Moreover, according to this embodiment, the crane 70 is arrange | positioned on the barge main body 11, and the through-holes 13 and 14 are formed in the side of the crane 70 in the barge main body 11. As shown in FIG. Thereby, since the underwater fair leaders 41 and 42 can be installed on the side of the crane 70, the material carrier ships 81 and 82 can be brought into contact with the vicinity of the underwater fair leaders 41 and 42 in the work platform ship 10. Accordingly, since the material carriers 81 and 82 can be positioned on the side of the crane 70, the material unloading from the material carriers 81 and 82 to the construction site of the dam dam body 1 can be performed at a turning angle of about 180 °. This can be performed within the range (within a range of about 90 ° on each of the left and right sides). As a result, the cycle time of crane work can be suppressed.

また本実施形態によれば、アンカー4、5、7、8は、水面より高位に位置する。これにより、作業台船10の係留用のアンカーを水面上(例えば陸上)で丈夫に形成することができるので、水中のアンカーに比べてメンテナンスの頻度を軽減することができ、また、メンテナンスを比較的容易に行うことができる。   Moreover, according to this embodiment, the anchors 4, 5, 7, and 8 are located higher than the water surface. As a result, anchors for mooring of the work table ship 10 can be firmly formed on the surface of the water (for example, on land), so that the frequency of maintenance can be reduced compared to underwater anchors, and the maintenance can be compared. Can be done easily.

1 ダム堤体
2 ダム貯水池
3 左岸
4、5 アンカー
6 右岸
7、8 アンカー
10 作業台船
11 台船本体
13 左貫通孔
14 右貫通孔
21 左前ウインチ
22 右前ウインチ
23 左後ウインチ
24 右後ウインチ
25 左中ウインチ
26 右中ウインチ
31 左前フェアリーダ
32 右前フェアリーダ
33 左後フェアリーダ
34 右後フェアリーダ
41、42 水中フェアリーダ(係留索ガイド装置)
44 フェアリーダ本体(ガイド装置本体)
44a フランジ部
45 第1ガイド部
46 第2ガイド部
47、48、49 シーブ
51〜56 ワイヤーロープ(係留索)
61、62 錨
70 クレーン
71 ベースマシン
72 ブーム
81、82 資材運搬船
DESCRIPTION OF SYMBOLS 1 Dam dam body 2 Dam reservoir 3 Left bank 4, 5 Anchor 6 Right bank 7, 8 Anchor 10 Work table ship 11 Ship body 13 Left through-hole 14 Right through-hole 21 Left front winch 22 Right front winch 23 Left rear winch 24 Right rear winch 25 Left middle winch 26 Right middle winch 31 Left front fair leader 32 Right front fair leader 33 Left rear fair leader 34 Right rear fair leader 41, 42 Underwater fair leader (mooring line guide device)
44 Fair reader body (guide device body)
44a Flange part 45 1st guide part 46 2nd guide part 47, 48, 49 Sheaves 51-56 Wire rope (mooring line)
61, 62 錨 70 Crane 71 Base machine 72 Boom 81, 82 Material carrier

Claims (4)

上下方向に貫通する貫通孔が形成されて水面上に浮かぶ台船本体と、
この台船本体上に設置されて係留索を巻き取り・繰り出し可能なウインチと、
前記台船本体の前記貫通孔に挿入されて前記台船本体上から水中に延出し、上部が前記台船本体に着脱可能に取り付けられる筒状のガイド装置本体、このガイド装置本体の上端部に設けられる第1ガイド部、及び、前記ガイド装置本体の下端部に設けられる第2ガイド部を備える係留索ガイド装置と、
を含んで構成され、
前記ウインチより繰り出される係留索は、前記第1ガイド部、前記ガイド装置本体内、及び、前記第2ガイド部を経て、外部のアンカーに一端が固定されることを特徴とする作業台船。
A base ship body that has a through-hole penetrating in the vertical direction and floats on the water surface;
A winch installed on the main body of the ship and capable of winding and unwinding mooring lines,
A cylindrical guide device main body that is inserted into the through hole of the base boat main body and extends from above the base main body to the water, and an upper part is detachably attached to the base main body. A mooring line guide device comprising a first guide portion provided, and a second guide portion provided at a lower end portion of the guide device body;
Comprising
The mooring line fed out from the winch is fixed at one end to an external anchor through the first guide portion, the guide device main body, and the second guide portion.
前記台船本体の外縁部に前記貫通孔が形成され、前記台船本体における前記貫通孔近傍の外縁部に船が接舷されることを特徴とする請求項1に記載の作業台船。   The work table ship according to claim 1, wherein the through hole is formed in an outer edge portion of the base body, and the ship is in contact with an outer edge portion in the vicinity of the through hole in the base body. 前記台船本体上にクレーンが配置され、前記台船本体における前記クレーンの側方に前記貫通孔が形成されることを特徴とする請求項1又は請求項2に記載の作業台船。   The work trolley according to claim 1 or 2, wherein a crane is disposed on the carriage main body, and the through hole is formed on a side of the crane in the carriage main body. 前記アンカーは、水面より高位に位置することを特徴とする請求項1〜請求項3のいずれか1つに記載の作業台船。   The work boat according to any one of claims 1 to 3, wherein the anchor is positioned higher than a water surface.
JP2012264442A 2012-12-03 2012-12-03 Work barge Pending JP2014108735A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2012264442A JP2014108735A (en) 2012-12-03 2012-12-03 Work barge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2012264442A JP2014108735A (en) 2012-12-03 2012-12-03 Work barge

Publications (1)

Publication Number Publication Date
JP2014108735A true JP2014108735A (en) 2014-06-12

Family

ID=51029625

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012264442A Pending JP2014108735A (en) 2012-12-03 2012-12-03 Work barge

Country Status (1)

Country Link
JP (1) JP2014108735A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110106827A (en) * 2019-05-08 2019-08-09 大连辽南船厂 Anchor arrangement for floating wharf
CN110965543A (en) * 2019-12-06 2020-04-07 中交第四航务工程局有限公司 Underwater rock block foundation bed automatic control tamping system with hydraulic driving mechanism

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4827590U (en) * 1971-08-11 1973-04-03
JPS4961292U (en) * 1972-09-11 1974-05-29
US3943871A (en) * 1974-03-22 1976-03-16 Kazuhide Tanaka Submerging system for marine structure
JPS551994Y2 (en) * 1975-10-13 1980-01-19
JPS5555086A (en) * 1978-10-19 1980-04-22 Kaiyo Giken Kk Automatic mooring device
JPS5770790A (en) * 1980-10-14 1982-05-01 Hitachi Zosen Corp Mooring method
JPS6172132A (en) * 1984-09-18 1986-04-14 Susumu Sakurada Dredging device for dam lake
JPS61285190A (en) * 1985-06-10 1986-12-15 Kayaba Ind Co Ltd Mooring device for floating structure
JPS62146798A (en) * 1985-12-20 1987-06-30 Namura Zosenjo:Kk Cargo handling device for wood on surface of water
JPS6331891A (en) * 1986-07-28 1988-02-10 Nippon Kokan Kk <Nkk> Half-spud device mounted in dredger
JPS6393298U (en) * 1986-12-09 1988-06-16
JPH0234498A (en) * 1988-07-25 1990-02-05 Mitsui Eng & Shipbuild Co Ltd Multi-point mooring method for floating type ocean structure
JPH04146887A (en) * 1990-10-09 1992-05-20 Ishikawajima Harima Heavy Ind Co Ltd Steering method for working ship and its device
JPH04303099A (en) * 1991-03-30 1992-10-27 Sumitomo Heavy Ind Ltd Ship position detector
JPH1071989A (en) * 1996-08-30 1998-03-17 Miyazaki Kensetsu Kogyo Kk Ship maneuvering winch radio operation device

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4827590U (en) * 1971-08-11 1973-04-03
JPS4961292U (en) * 1972-09-11 1974-05-29
US3943871A (en) * 1974-03-22 1976-03-16 Kazuhide Tanaka Submerging system for marine structure
JPS551994Y2 (en) * 1975-10-13 1980-01-19
JPS5555086A (en) * 1978-10-19 1980-04-22 Kaiyo Giken Kk Automatic mooring device
JPS5770790A (en) * 1980-10-14 1982-05-01 Hitachi Zosen Corp Mooring method
JPS6172132A (en) * 1984-09-18 1986-04-14 Susumu Sakurada Dredging device for dam lake
JPS61285190A (en) * 1985-06-10 1986-12-15 Kayaba Ind Co Ltd Mooring device for floating structure
JPS62146798A (en) * 1985-12-20 1987-06-30 Namura Zosenjo:Kk Cargo handling device for wood on surface of water
JPS6331891A (en) * 1986-07-28 1988-02-10 Nippon Kokan Kk <Nkk> Half-spud device mounted in dredger
JPS6393298U (en) * 1986-12-09 1988-06-16
JPH0234498A (en) * 1988-07-25 1990-02-05 Mitsui Eng & Shipbuild Co Ltd Multi-point mooring method for floating type ocean structure
JPH04146887A (en) * 1990-10-09 1992-05-20 Ishikawajima Harima Heavy Ind Co Ltd Steering method for working ship and its device
JPH04303099A (en) * 1991-03-30 1992-10-27 Sumitomo Heavy Ind Ltd Ship position detector
JPH1071989A (en) * 1996-08-30 1998-03-17 Miyazaki Kensetsu Kogyo Kk Ship maneuvering winch radio operation device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110106827A (en) * 2019-05-08 2019-08-09 大连辽南船厂 Anchor arrangement for floating wharf
CN110965543A (en) * 2019-12-06 2020-04-07 中交第四航务工程局有限公司 Underwater rock block foundation bed automatic control tamping system with hydraulic driving mechanism

Similar Documents

Publication Publication Date Title
US9463963B2 (en) Deep water knuckle boom crane
US9855999B1 (en) System for launch and recovery of remotely operated vehicles
EP0612655A2 (en) Method for the casting of anchors and mooring of platforms, and an anchor casting unit
JP5565803B2 (en) Installation method of tension mooring floating structure and ship for installation of tension mooring floating structure
CN203333189U (en) Hoisting device for ships
CN113386902B (en) Mooring method and mooring system of ship and ship
CN104828219A (en) Movable rubber fender device used for ship-to-ship barge transport operation
JP2014108735A (en) Work barge
CN202169997U (en) Heavy lift vessel with door-shaped trusses
US5230588A (en) Method and device for paying out or hauling in the supply line cable of an underwater device
US20220227467A1 (en) Deployment of Unmanned Underwater Vehicles
JP2013086522A (en) Ship
JP6949690B2 (en) Floating body mooring method and floating body
JP6006102B2 (en) Mooring method for worktable
JP7074733B2 (en) Ship
WO2013073950A1 (en) Vessel and method for towing a heavy load under water
JP2017144851A (en) Mooring rope restriction mechanism and mooring structure body
JP5684220B2 (en) How to install a buoy
KR20120058262A (en) Side by side mooring apparatus
US11585487B2 (en) Barge spud greasing system
JP2668040B2 (en) Facility and method for installing large offshore structures
JP2006044851A (en) Deep water cargo lifting device for floating crane
KR20160005887A (en) Floating crane rigging system
JPH0416793Y2 (en)
CN113830237B (en) Deep water mooring polyester cable rewinding method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20150625

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20160527

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20160628

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20160824

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20170207

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20170801