JP2014062407A - Structure and method for fixing platform door - Google Patents

Structure and method for fixing platform door Download PDF

Info

Publication number
JP2014062407A
JP2014062407A JP2012208483A JP2012208483A JP2014062407A JP 2014062407 A JP2014062407 A JP 2014062407A JP 2012208483 A JP2012208483 A JP 2012208483A JP 2012208483 A JP2012208483 A JP 2012208483A JP 2014062407 A JP2014062407 A JP 2014062407A
Authority
JP
Japan
Prior art keywords
platform
embankment
plate
platform door
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2012208483A
Other languages
Japanese (ja)
Other versions
JP6021545B2 (en
Inventor
Seitaro Hidaka
晴太郎 日▲高▼
Kazuma Yoshimoto
一馬 吉本
Haruo Moro
晴夫 茂呂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Mitsubishi Heavy Industries Transportation Equipment Engineering and Service Co Ltd
Original Assignee
Fujita Corp
Mitsubishi Heavy Industries Transportation Equipment Engineering and Service Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=50617869&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=JP2014062407(A) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by Fujita Corp, Mitsubishi Heavy Industries Transportation Equipment Engineering and Service Co Ltd filed Critical Fujita Corp
Priority to JP2012208483A priority Critical patent/JP6021545B2/en
Publication of JP2014062407A publication Critical patent/JP2014062407A/en
Application granted granted Critical
Publication of JP6021545B2 publication Critical patent/JP6021545B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
  • Platform Screen Doors And Railroad Systems (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a structure and a method for fixing a platform door, which enable the platform door to be stably and simply installed on a banking type platform.SOLUTION: A structure for fixing a platform door includes: a concrete slab 2 which is installed on a top surface of fill 32 of a banking type platform 30 formed of the fill and which has the platform door 20 placed on one side; and a rock bolt 3 which has a bolt part 4 penetrating the inside of the fill 32 to be connected to the concrete slab 2 and grout 5 to be injected into the periphery of the penetrating bolt part 4, and which fixes the concrete slab 2 to the fill 32.

Description

本発明は、プラットホーム上にプラットホームドアを固定するプラットホームドア固定構造及びプラットホームドア固定方法に関するものである。   The present invention relates to a platform door fixing structure and a platform door fixing method for fixing a platform door on a platform.

プラットホームに設置されるプラットホームドアは、乗客の転落などを防止するため、既存のプラットホームに新設されることが望まれる。一方で、既存のプラットホームには、土砂等からなる盛土部分の端部を、石又はコンクリート製ブロックで抑える構造を有する盛土式プラットホームや、鉄骨とコンクリート版からなる桁式プラットホームなどがある。
特許文献1には、盛土式プラットホームを桁式ホーム化する際の仮ホーム構造に関する技術が開示されている。
It is desirable that the platform door installed on the platform is newly installed on the existing platform in order to prevent passengers from falling. On the other hand, existing platforms include an embankment type platform having a structure in which an end portion of an embankment portion made of earth and sand is held by a stone or concrete block, and a girder platform made of a steel frame and a concrete plate.
Patent Document 1 discloses a technique related to a temporary home structure when a banking platform is changed to a girder type platform.

特開2011−196094号公報JP 2011-196094 A

プラットホームドアを既存のプラットホームに設置するためには、プラットホームがプラットホームドアの荷重に耐えられることや、プラットホームドアに接続される電気ケーブルを敷設するダクトを設けることが要求される。また、プラットホームドア設置工事は、列車が運行していない深夜の僅かな時間帯に限られるため、工期が長期化する傾向にある。   In order to install the platform door on an existing platform, it is required that the platform can withstand the load of the platform door and that a duct for laying an electric cable connected to the platform door is required. Moreover, since the platform door installation work is limited to a few hours at midnight when the train is not operating, the construction period tends to be prolonged.

盛土式プラットホームの場合、荷重に耐えられる構造に改良したり、電気ケーブル用ダクトを敷設したりするため、桁式プラットホームに変更してもよいが、盛土部分の除去や鉄骨構造の新設等に時間がかかる。また、盛土式プラットホームから桁式プラットホームへの変更工事中は、長期間、仮設ホームとなる。   In the case of an embankment type platform, it may be changed to a girder type platform in order to improve the structure to withstand the load or to install a duct for electric cables, but it takes time to remove the embankment part or to newly install a steel structure. It takes. In addition, during the change work from the embankment platform to the girder platform, it will be a temporary home for a long time.

また、桁式プラットホームへ変更しないで、盛土部分端部の石又はコンクリート製ブロックを活用する場合でも、盛土部分を補強したり、電気ケーブル用ダクトを敷設する空間を形成したりするため、桁式プラットホームに比べて工期が長期化すると共にコストも割高になることが予想される。   Also, even when using stone or concrete blocks at the end of the embankment part without changing to a girder platform, the girder system is used to reinforce the embankment part or to form a space for laying electrical cable ducts. Compared to the platform, the construction period will be longer and the cost will be higher.

本発明は、このような事情に鑑みてなされたものであって、プラットホームドアを安定的かつ簡易に盛土式プラットホーム上に設置することが可能なプラットホームドア固定構造及びプラットホームドア固定方法を提供することを目的とする。   The present invention has been made in view of such circumstances, and provides a platform door fixing structure and a platform door fixing method capable of stably and easily installing a platform door on an embankment type platform. With the goal.

上記課題を解決するために、本発明のプラットホームドア固定構造及びプラットホームドア固定方法は以下の手段を採用する。
すなわち、本発明に係るプラットホームドア固定構造は、盛土で形成された盛土式プラットホームの前記盛土上面に設置され、一側にプラットホームドア装置が載置されるコンクリート製の板状部材と、前記盛土内部へ貫入されて前記板状部材と接続される棒状部材と、貫入された前記棒状部材の周囲に注入されるグラウトとを有し、前記盛土に対して前記板状部材を固定する支持部とを備える。
In order to solve the above problems, the platform door fixing structure and the platform door fixing method of the present invention employ the following means.
That is, the platform door fixing structure according to the present invention is a concrete plate-like member that is installed on the embankment upper surface of an embankment type platform formed of embankment and on which one platform door device is placed, and the interior of the embankment A rod-like member that is inserted into the plate-like member and connected to the plate-like member, and a grout that is injected around the penetrated rod-like member, and a support portion that fixes the plate-like member to the embankment. Prepare.

この発明によれば、盛土式プラットホームの盛土上面にコンクリート製の板状部材が設置され、板状部材は、プラットホームの盛土内部へ貫入された棒状部材と接続され、かつ、貫入された棒状部材の周囲にグラウトが注入されることによって、盛土に対して固定される。プラットホームドア装置は、盛土に対して固定された板状部材に載置されることから、プラットホーム上に安定的に据え付けられる。
また、板状部材は、プラットホームの盛土を多量に除去することなく盛土上面に固定されるため、プラットホームドア装置を簡易に据え付けることができる。
According to this invention, the plate-shaped member made of concrete is installed on the embankment upper surface of the embankment type platform, the plate-shaped member is connected to the bar-shaped member penetrating into the embankment of the platform, and the bar-shaped member of the penetrating It is fixed to the embankment by injecting grout around it. Since the platform door device is placed on a plate-like member fixed to the embankment, the platform door device is stably installed on the platform.
Further, since the plate-like member is fixed to the upper surface of the embankment without removing a large amount of the embankment of the platform, the platform door device can be easily installed.

また、本発明に係るプラットホームドア固定構造は、盛土で形成された盛土式プラットホームの前記盛土上面に設置され、一側にプラットホームドア装置が載置されるコンクリート製の板状部材と、前記盛土内部に設置されて前記板状部材と接続され、前記盛土に対して前記板状部材を固定するブロック部材とを備える。   The platform door fixing structure according to the present invention is a concrete plate-like member installed on the embankment upper surface of an embankment type platform formed by embankment, on which a platform door device is placed, and the interior of the embankment And a block member that is connected to the plate member and fixes the plate member to the embankment.

この発明によれば、盛土式プラットホームの盛土上面にコンクリート製の板状部材が設置され、板状部材は、プラットホームの盛土内部に設置されたブロック部材と接続されることによって、盛土に対して固定される。プラットホームドア装置は、盛土に対して固定された板状部材に載置されることから、プラットホーム上に安定的に据え付けられる。
また、板状部材やブロック部材は、プラットホームの盛土を多量に除去することなく盛土上面や盛土内部に固定されるため、プラットホームドア装置を簡易に据え付けることができる。
According to this invention, the plate-shaped member made of concrete is installed on the embankment upper surface of the embankment type platform, and the plate-shaped member is fixed to the embankment by being connected to the block member installed inside the embankment of the platform. Is done. Since the platform door device is placed on a plate-like member fixed to the embankment, the platform door device is stably installed on the platform.
Further, since the plate-like member and the block member are fixed to the upper surface of the embankment or inside the embankment without removing a large amount of the embankment of the platform, the platform door device can be easily installed.

上記発明において、前記板状部材の前記プラットホーム延在方向の長さは、前記プラットホームドア装置の閉状態の扉部と前記扉部を支持する本体部を合わせた長さよりも短く、前記本体部が前記板状部材の一端部に載置されてもよい。   In the above invention, the length of the plate-shaped member in the platform extending direction is shorter than the combined length of the closed door portion of the platform door device and the main body portion supporting the door portion, and the main body portion is You may mount in the one end part of the said plate-shaped member.

この発明によれば、板状部材のプラットホーム延在方向の長さは、プラットホームドア装置の載置に必要となる長さのみである。したがって、盛土式プラットホームを改装して、プラットホームの盛土上面に板状部材を設置する際、プラットホームの盛土上面全てを除去することなく、必要部分のみを除去すればよいため、プラットホームドア装置の固定にかかる手間を低減できる。   According to the present invention, the length of the plate-like member in the platform extending direction is only the length necessary for placing the platform door device. Therefore, when remodeling the embankment platform and installing plate members on the upper surface of the platform embankment, it is necessary to remove only the necessary parts without removing the entire embankment upper surface of the platform. Such labor can be reduced.

上記発明において、前記板状部材の側面に沿って、前記プラットホームドア装置と接続される電気ケーブルが敷設されてもよい。   In the above invention, an electric cable connected to the platform door device may be laid along the side surface of the plate-like member.

この発明によれば、プラットホームドア装置と接続される電気ケーブル、例えば電源ケーブル、信号ケーブル等が、板状部材の側面に沿って敷設されることから、板状部材の下面側に別途配線用ダクト等を設置しなくてもよい。板状部材の下面側に配線用ダクトを設置しようとすると、盛土を除去する必要があるが、本発明では盛土の除去が不要になり、簡易に電気ケーブルを敷設できる。   According to the present invention, since an electric cable connected to the platform door device, for example, a power cable, a signal cable, and the like is laid along the side surface of the plate member, a separate wiring duct is provided on the lower surface side of the plate member. Etc. need not be installed. If it is going to install the duct for wiring in the lower surface side of a plate-shaped member, it is necessary to remove embankment, but in this invention, removal of embankment becomes unnecessary and an electric cable can be laid easily.

上記発明において、前記板状部材の上面に設置される点字タイルの裏面に沿って、前記プラットホームドア装置と接続される電気ケーブルが敷設されてもよい。   In the above invention, an electric cable connected to the platform door device may be laid along the back surface of the Braille tile installed on the upper surface of the plate-like member.

この発明によれば、プラットホームドア装置と接続される電気ケーブル、例えば電源ケーブル、信号ケーブル等が、板状部材の上面に設置される点字タイルの裏面に沿って敷設されることから、電気ケーブルの敷設工事やプラットホームドアシステムのメンテナンス作業の際に、線路上やプラットホーム下へ降りる必要が無く、作業が容易になり、安全性が向上する。   According to the present invention, an electrical cable connected to the platform door device, for example, a power cable, a signal cable, and the like is laid along the back surface of the Braille tile installed on the upper surface of the plate-like member. During laying work and platform door system maintenance work, there is no need to descend down on the track or below the platform, which facilitates the work and improves safety.

上記発明において、前記板状部材に形成され、前記点字タイルの裏面側に形成される凹状の溝内部に、前記電気ケーブルが内部に敷設されるダクトが設置されてもよい。   The said invention WHEREIN: The duct by which the said electric cable is laid inside may be installed in the concave groove | channel formed in the said plate-shaped member and formed in the back surface side of the said Braille tile.

この発明によれば、板状部材にて、凹状の溝が、点字タイルよりも下方、かつ点字タイルの裏面側に形成され、溝内部にダクトが設けられる。そして、ダクトには、内部に電気ケーブルが敷設される。よって、点字タイルがダクト上に設置されることから、電気ケーブルはダクトによって保護される。   According to this invention, in the plate-like member, the concave groove is formed below the Braille tile and on the back side of the Braille tile, and the duct is provided inside the groove. An electric cable is laid inside the duct. Therefore, since the braille tile is installed on the duct, the electric cable is protected by the duct.

また、本発明に係るプラットホームドア固定方法は、盛土で形成された盛土式プラットホームの上面にコンクリート製の板状部材を設置するステップと、前記盛土内部へ棒状部材を貫入するステップと、貫入された前記棒状部材の周囲にグラウトを注入するステップと、前記棒状部材を前記板状部材と接続するステップと、前記板状部材の一側にプラットホームドア装置を載置するステップとを含む。   The platform door fixing method according to the present invention includes a step of installing a concrete plate-like member on the upper surface of the embankment type platform formed by embedding, a step of penetrating a rod-like member into the embankment, and a penetration Injecting grout around the rod-like member, connecting the rod-like member with the plate-like member, and placing a platform door device on one side of the plate-like member.

また、本発明に係るプラットホームドア固定方法は、盛土で形成された盛土式プラットホームの内部にブロック部材を設置するステップと、前記ブロック部材の上面にコンクリート製の板状部材を設置するステップと、前記ブロック部材を前記板状部材と接続するステップと、前記板状部材の一側にプラットホームドア装置を載置するステップとを含む。   In addition, the platform door fixing method according to the present invention includes a step of installing a block member inside an embankment type platform formed by embankment, a step of installing a plate member made of concrete on the upper surface of the block member, Connecting a block member with the plate-like member, and placing a platform door device on one side of the plate-like member.

本発明によれば、プラットホームドアが載置される板状部材が、棒状部材とグラウトを有する支持部によって固定されるため、プラットホームドアを安定的かつ簡易に盛土式プラットホーム上に設置することができる。   According to the present invention, since the plate-like member on which the platform door is placed is fixed by the support portion having the rod-like member and the grout, the platform door can be stably and easily installed on the embankment type platform. .

本発明の第1実施形態に係るプラットホームドア固定構造を示す平面図である。It is a top view which shows the platform door fixing structure which concerns on 1st Embodiment of this invention. 本発明の第1実施形態に係るプラットホームドア固定構造を示す縦断面図である。It is a longitudinal cross-sectional view which shows the platform door fixing structure which concerns on 1st Embodiment of this invention. 本発明の第1実施形態に係るプラットホームドア固定構造を示す平面図である。It is a top view which shows the platform door fixing structure which concerns on 1st Embodiment of this invention. 本発明の第1実施形態に係るプラットホームドア固定構造のコンクリート版を示す部分拡大縦断面図である。It is a partial expanded longitudinal cross-sectional view which shows the concrete plate of the platform door fixing structure which concerns on 1st Embodiment of this invention. 図3のV-V線で切断した断面図である。It is sectional drawing cut | disconnected by the VV line | wire of FIG. 本発明の第2実施形態に係るプラットホームドア固定構造を示す縦断面図である。It is a longitudinal cross-sectional view which shows the platform door fixing structure which concerns on 2nd Embodiment of this invention. 本発明の第2実施形態に係るプラットホームドア固定構造を示す平面図である。It is a top view which shows the platform door fixing structure which concerns on 2nd Embodiment of this invention.

[第1実施形態]
以下に、本発明の第1実施形態に係るプラットホームドア固定構造1について、図面を参照して説明する。
本実施形態に係るプラットホームドア固定構造1は、プラットホームドア20を盛土式プラットホーム30に固定する。
プラットホームドア20は、扉部22と、扉部22を支持する戸袋部21を備える。プラットホームドア20は、プラットホーム30上にプラットホーム30の延在方向に沿って複数台設置され、プラットホーム30からの乗客の転落などを防止する。また、プラットホームドア20には、戸袋部21内部に収容されたモータ(図示せず。)や制御盤(図示せず。)に電気的に接続される電気ケーブル40(図2及び図4参照)が接続される。
[First Embodiment]
Hereinafter, a platform door fixing structure 1 according to a first embodiment of the present invention will be described with reference to the drawings.
The platform door fixing structure 1 according to the present embodiment fixes the platform door 20 to the embankment platform 30.
The platform door 20 includes a door portion 22 and a door pocket portion 21 that supports the door portion 22. A plurality of platform doors 20 are installed on the platform 30 along the extending direction of the platform 30 to prevent passengers from falling from the platform 30. Further, the platform door 20 has an electric cable 40 (see FIGS. 2 and 4) electrically connected to a motor (not shown) and a control panel (not shown) housed in the door pocket 21. Is connected.

プラットホームドア20は、例えば腰高式であり、設置面から天板上端まで約1.3m〜1.4mの高さを有する。扉部22は、電力によって駆動するモータ、モータによって動作するベルト等の伝動機構によって、戸袋部21に対して出入する。   The platform door 20 is a waist height type, for example, and has a height of about 1.3 m to 1.4 m from the installation surface to the top edge of the top plate. The door portion 22 enters and exits the door pocket portion 21 by a transmission mechanism such as a motor driven by electric power and a belt operated by the motor.

電気ケーブル40は、例えば電源ケーブル、信号ケーブル等である。電源ケーブルは、プラットホームドア20外部の電源と接続され、例えばモータや制御盤等へ電力を供給する。また、信号ケーブルは、例えば制御盤と外部の制御盤とを結び、信号ケーブルによって扉部22の開閉に関する制御信号等が送受信される。   The electric cable 40 is, for example, a power cable or a signal cable. The power cable is connected to a power source outside the platform door 20 and supplies power to, for example, a motor and a control panel. Further, the signal cable connects, for example, a control panel and an external control panel, and a control signal related to opening and closing of the door portion 22 is transmitted and received by the signal cable.

電気ケーブル40は、図2及び図4に示すように、配線用ダクト8の内部に敷設される。配線用ダクト8は、プラットホームドア20の延在方向に沿って設けられる。配線用ダクト8は、電気ケーブル40を収容する収容部8Aと、収容部8Aを覆う蓋部8Bを有する。蓋部8Bの上面には、点字タイル12(視覚障がい者誘導用タイル)が貼られる。点字タイル12は、例えば、図4に示すように、例えば厚さ約2mmのプレート部と、プレート部から突設された高さ約5mmの複数の突起部を有する。   As shown in FIGS. 2 and 4, the electric cable 40 is laid inside the wiring duct 8. The wiring duct 8 is provided along the extending direction of the platform door 20. The duct 8 for wiring has the accommodating part 8A which accommodates the electric cable 40, and the cover part 8B which covers the accommodating part 8A. Braille tiles 12 (tiles for visually impaired persons) are pasted on the upper surface of the lid 8B. For example, as shown in FIG. 4, the Braille tile 12 includes a plate portion having a thickness of about 2 mm, and a plurality of protrusion portions having a height of about 5 mm protruding from the plate portion.

プラットホームドア20の設置に伴って、点字タイル12と電気ケーブル40の両方を敷設する必要がある。本実施形態のように点字タイル12の下側に配線用ダクト8を設置することで、電気ケーブル40の敷設が、点字タイル12の敷設と共にプラットホーム30上の作業で完了する。そのため、プラットホーム下の退避スペースに線路側から配線用ダクトや電気ケーブルを敷設する場合に比べて、設置作業が容易になり工期を短縮化できる。   With the installation of the platform door 20, it is necessary to lay both the braille tile 12 and the electric cable 40. By installing the wiring duct 8 on the lower side of the Braille tile 12 as in the present embodiment, the laying of the electric cable 40 is completed by the work on the platform 30 together with the laying of the Braille tile 12. Therefore, compared to the case where a wiring duct or an electric cable is laid from the track side in the retreat space under the platform, the installation work is facilitated and the construction period can be shortened.

プラットホームドア固定構造1は、プラットホーム30の盛土32の上面に設置される板状のコンクリート版2と、コンクリート版2と接続され、盛土32の内部に定着されるロックボルト3を備える。   The platform door fixing structure 1 includes a plate-shaped concrete plate 2 installed on the upper surface of the embankment 32 of the platform 30, and a lock bolt 3 connected to the concrete plate 2 and fixed inside the embankment 32.

コンクリート版2は、平面視した形状が長方形のプレキャストコンクリート版であり、内部に強度に応じた鉄筋が配置される。コンクリート版2の一側では、ロックボルト3が接続される。ロックボルト3は、コンクリート版2を貫通して盛土32の内部へ貫入される。コンクリート版2の他側には、プラットホームドア20の戸袋部21が載置される。戸袋部21は、接着系アンカー6(例えば、ケミカルアンカー)によってコンクリート版2に固定される。   The concrete plate 2 is a precast concrete plate having a rectangular shape in plan view, and a reinforcing bar corresponding to the strength is disposed inside. On one side of the concrete plate 2, a lock bolt 3 is connected. The rock bolt 3 penetrates the concrete plate 2 and penetrates into the embankment 32. On the other side of the concrete plate 2, a door pocket portion 21 of the platform door 20 is placed. The door pocket portion 21 is fixed to the concrete plate 2 by an adhesive anchor 6 (for example, a chemical anchor).

コンクリート版2の強度は、コンクリート版2にプラットホームドア20が載置されたときのプラットホームドア20にかかる群集横荷重、列車通過風荷重や台風荷重などを考慮して決定される。コンクリート版2の上面には、点字タイル12を設置するための段差部2Aが形成される。   The strength of the concrete slab 2 is determined in consideration of the crowd lateral load applied to the platform door 20 when the platform door 20 is placed on the concrete slab 2, the train passing wind load, the typhoon load, and the like. On the upper surface of the concrete plate 2, a stepped portion 2 </ b> A for installing the braille tile 12 is formed.

ロックボルト3は、図2に示すように、盛土32の内部に貫入されるボルト部4と、ボルト部4の周囲に注入されるグラウト5を有する。ロックボルト3によって、コンクリート版2は、プラットホーム30の盛土32に対して固定される。なお、図1及び図3では、ロックボルト3が1本のみ設置される例を示しているが、複数本のロックボルト3が設置されてもよい。これにより、コンクリート版2の盛土に対する固定を一層確実にし、コンクリート版2の面内の回転を確実に抑制できる。   As shown in FIG. 2, the lock bolt 3 has a bolt part 4 that penetrates into the embankment 32 and a grout 5 that is injected around the bolt part 4. The concrete plate 2 is fixed to the embankment 32 of the platform 30 by the lock bolt 3. 1 and 3 show an example in which only one lock bolt 3 is installed, a plurality of lock bolts 3 may be installed. Thereby, fixation with respect to the embankment of the concrete plate 2 can be further ensured, and rotation within the surface of the concrete plate 2 can be reliably suppressed.

ボルト部4は、中空の筒状部材であり、筒状部材の壁面に貫通孔(図示せず。)が形成される。ボルト部4は、盛土32内部へ貫入された後、上端部からグラウト5が注入される。注入されたグラウト5は、上述したボルト部4の貫通孔を通過して、盛土32とボルト部4間の隙間に充填される。グラウト5が硬化すると、ボルト部4とグラウト5が一体化する。そして、ボルト部4の上端部は、コンクリート版2に金具(ナット等)を用いて固定される。なお、ボルト部4は、筒状部材に限られず、異形棒鋼、ネジ節棒鋼などアンカー工のうちロックボルト工に使用される鋼材でもよい。   The bolt part 4 is a hollow cylindrical member, and a through hole (not shown) is formed in the wall surface of the cylindrical member. After the bolt part 4 is penetrated into the embankment 32, the grout 5 is injected from the upper end part. The injected grout 5 passes through the through hole of the bolt part 4 described above, and is filled in the gap between the embankment 32 and the bolt part 4. When the grout 5 is cured, the bolt part 4 and the grout 5 are integrated. And the upper end part of the bolt part 4 is fixed to the concrete plate 2 using metal fittings (nuts etc.). In addition, the bolt part 4 is not restricted to a cylindrical member, The steel material used for a rock bolt work among anchor works, such as a deformed steel bar and a screw node steel, may be used.

ロックボルト3の強度や盛土32中の定着長さは、コンクリート版2に作用するモーメントによって、コンクリート版2に発生する引き抜き力を考慮して決定される。なお、定着長さは、盛土32が有する摩擦抵抗力によっても変化する。ロックボルト3は、引き抜き力に対して抵抗することができ、コンクリート版2がプラットホームドア20に作用する群集横荷重によって線路側に転倒することを防止する。   The strength of the rock bolt 3 and the fixing length in the embankment 32 are determined in consideration of the pulling force generated in the concrete plate 2 by the moment acting on the concrete plate 2. Note that the fixing length also changes depending on the frictional resistance of the embankment 32. The lock bolt 3 can resist the pulling force and prevents the concrete plate 2 from falling to the track side due to the lateral load of the crowd acting on the platform door 20.

次に、本実施形態に係るコンクリート版2を用いたプラットホームドア20の電気ケーブル40の配線方法について説明する。電気ケーブル40は、図2及び図4に示すように、コンクリート版2の上面において、点字タイル12と共に設置される場合について説明したが、本実施形態は別の方法で電気ケーブル40を配線してもよい。   Next, the wiring method of the electric cable 40 of the platform door 20 using the concrete plate 2 according to the present embodiment will be described. As shown in FIGS. 2 and 4, the electric cable 40 has been described with respect to the case where it is installed together with the braille tiles 12 on the upper surface of the concrete plate 2. However, in the present embodiment, the electric cable 40 is wired by another method. Also good.

例えば、電気ケーブル40は、図3及び図5に示すように、配線用ダクト10内部に敷設されてもよい。配線用ダクト10は、コンクリート版2の側面に沿って、例えば、プラットホーム30の延設方向に沿う第1の方向と、第1の方向に対して直交する第2の方向に設置される。これにより、電気ケーブル40は、配線用ダクト10によって、線路側と反対側でプラットホーム30の延設方向に沿って敷設され、さらに、プラットホームドア20に向かって敷設される。そして、電気ケーブル40は、コンクリート版2に予め形成された溝2C内に配線されて、プラットホームドア20と接続される。配線用ダクト10の深さは、電気ケーブル40の太さや設置する電気ケーブル40の本数によるが、図5に示すように、コンクリート版2の厚さよりも浅くてもよい。これにより、プラットホームドア20と接続される電気ケーブル40の敷設工事を簡単かつ迅速に行うことができる。   For example, the electric cable 40 may be laid inside the wiring duct 10 as shown in FIGS. 3 and 5. The wiring duct 10 is installed along the side surface of the concrete plate 2 in, for example, a first direction along the extending direction of the platform 30 and a second direction orthogonal to the first direction. Thereby, the electric cable 40 is laid along the extending direction of the platform 30 on the side opposite to the track side by the wiring duct 10 and further laid toward the platform door 20. The electric cable 40 is wired in a groove 2 </ b> C formed in the concrete plate 2 in advance and is connected to the platform door 20. The depth of the wiring duct 10 depends on the thickness of the electric cable 40 and the number of electric cables 40 to be installed, but may be shallower than the thickness of the concrete plate 2 as shown in FIG. Thereby, the laying construction of the electric cable 40 connected to the platform door 20 can be performed easily and quickly.

また、電気ケーブル40は、図2に示すように、配線用ダクト7内部に敷設されてもよい。配線用ダクト7は、コンクリート版2の下面に沿って、例えば、プラットホーム30の延設方向に沿う方向に設置される。これにより、電気ケーブル40は、配線用ダクト7によって、コンクリート版2の下面側でプラットホーム30の延設方向に沿って敷設され、さらに、プラットホームドア20に立ち上がって敷設される。そして、電気ケーブル40は、コンクリート版2に予め形成された貫通孔(図示せず。)内に配線されて、プラットホームドア20と接続される。コンクリート版2の下面側に長尺状の配線用ダクト7が敷設されることによって、断続的に配置される複数のコンクリート版2を同一水平面に設置しやすくなる。配線用ダクト7は、プラットホーム30のうち盛土32の端部に設けられているブロック33を取り外した後、プラットホーム30の延設方向に沿って敷設される。   Moreover, the electrical cable 40 may be laid inside the wiring duct 7 as shown in FIG. The wiring duct 7 is installed along the lower surface of the concrete plate 2 in, for example, a direction along the extending direction of the platform 30. Thereby, the electric cable 40 is laid along the extending direction of the platform 30 on the lower surface side of the concrete plate 2 by the wiring duct 7, and is further erected and laid on the platform door 20. The electric cable 40 is wired in a through hole (not shown) formed in the concrete plate 2 in advance and connected to the platform door 20. By laying the long wiring duct 7 on the lower surface side of the concrete plate 2, it becomes easy to install a plurality of intermittently arranged concrete plates 2 on the same horizontal plane. The wiring duct 7 is laid along the extending direction of the platform 30 after removing the block 33 provided at the end of the embankment 32 of the platform 30.

次に、本実施形態に係るプラットホームドア固定構造1を用いたプラットホームドア20の設置方法について説明する。   Next, an installation method of the platform door 20 using the platform door fixing structure 1 according to the present embodiment will be described.

既存の盛土式プラットホーム30にプラットホームドア20を設置する場合、まず、コンクリート版2を設置する部分の境界について、プラットホーム30の上面から床材31にカッターによって切り込みを入れる。切り込みを入れる位置は、図3に示した目地11や配線用ダクト10を設ける部分を考慮してコンクリート版2よりも十数mm程度、外側とする。   When installing the platform door 20 on the existing embankment type platform 30, first, the boundary of the portion where the concrete plate 2 is installed is cut into the floor material 31 from the upper surface of the platform 30 with a cutter. In consideration of the portion where the joint 11 and the wiring duct 10 shown in FIG. 3 are provided, the position where the incision is made is about 10 mm or more outside the concrete plate 2.

そして、コンクリート版2の厚さと、コンクリート版2の下面に敷設する均しコンクリートやモルタルの厚さを考慮して、プラットホーム30の上面のうちコンクリート版2を設置する部分の床材31や盛土32を除去する。次に、プラットホーム30の床材31や盛土32を除去した部分に、均しコンクリートやモルタルを施した後、コンクリート版2を設置する。   Then, considering the thickness of the concrete plate 2 and the thickness of the leveled concrete and mortar laid on the lower surface of the concrete plate 2, the floor material 31 and the embankment 32 of the portion of the upper surface of the platform 30 where the concrete plate 2 is installed. Remove. Next, after leveling concrete or mortar is applied to the part of the platform 30 from which the floor material 31 and the embankment 32 have been removed, the concrete plate 2 is installed.

その後、予め決められた定着長さとなるように、ロックボルト3のボルト部4を、コンクリート版2の上面側からプラットホーム30の盛土32の内部に貫入し、ボルト部4の端部からグラウト5を注入する。これにより、ロックボルト3が盛土32に設置される。また、ロックボルト3の地上側の上端部とコンクリート版2とを接続する。次に、既存のプラットホーム30の上面と新たに設置したコンクリート版2との間の隙間に目地材を施し目地11を形成する。以上より、コンクリート版2がプラットホーム30の盛土32に対して固定される。   Thereafter, the bolt portion 4 of the lock bolt 3 is inserted into the embankment 32 of the platform 30 from the upper surface side of the concrete plate 2 so that the fixing length is determined in advance, and the grout 5 is inserted from the end portion of the bolt portion 4. inject. Thereby, the lock bolt 3 is installed on the embankment 32. Further, the upper end of the rock bolt 3 on the ground side and the concrete plate 2 are connected. Next, joint material is applied to the gap between the upper surface of the existing platform 30 and the newly installed concrete plate 2 to form the joint 11. From the above, the concrete plate 2 is fixed to the embankment 32 of the platform 30.

そして、プラットホームドア20の戸袋部21をコンクリート版2の上面に設置し、接着系アンカー6等によって、戸袋部21をコンクリート版2に対して固定する。これにより、プラットホームドア20の設置が完了する。コンクリート版2は、既存のプラットホーム30の上面の床材31や盛土32が切り欠かれた部分に設置され、既存の床材31や目地11によって拘束されるため、コンクリート版2の面内方向の回転が発生しない。   And the door pocket part 21 of the platform door 20 is installed in the upper surface of the concrete plate 2, and the door pocket part 21 is fixed with respect to the concrete plate 2 with the adhesive anchor 6 grade | etc.,. Thereby, the installation of the platform door 20 is completed. The concrete plate 2 is installed in a portion where the floor material 31 and the embankment 32 on the upper surface of the existing platform 30 are cut out, and is restrained by the existing floor material 31 and joints 11. There is no rotation.

以上、本実施形態によれば、盛土式プラットホーム30の盛土32の上面にコンクリート版2が設置される。コンクリート版2は、プラットホーム30の盛土32の内部へ貫入されたロックボルト3と接続され、かつ、貫入されたロックボルト3のボルト部4の周囲にグラウト5が注入され硬化することによって、盛土32に対して固定される。プラットホームドア20は、盛土32に対して確実に固定されたコンクリート版2に載置されることから、プラットホーム30上に安定的に据え付けられる。   As described above, according to the present embodiment, the concrete plate 2 is installed on the upper surface of the embankment 32 of the embankment platform 30. The concrete plate 2 is connected to the lock bolt 3 penetrating into the embankment 32 of the platform 30, and the grout 5 is injected around the bolt portion 4 of the penetrated lock bolt 3 to be hardened. Fixed against. Since the platform door 20 is placed on the concrete plate 2 that is securely fixed to the embankment 32, the platform door 20 is stably installed on the platform 30.

また、コンクリート版2は、プラットホーム30の盛土32を大規模に除去することなく、コンクリート版2を設置するために床材31や盛土32を必要な分だけ除去するだけで固定される。そのため、本実施形態によれば、簡易にプラットホームドア20を据え付けることができる。すなわち、コンクリート版2のプラットホーム30の延在方向の長さは、図3に示すように、プラットホームドア20の載置に必要となる長さのみである。したがって、盛土式プラットホーム30を改装して、プラットホーム30の盛土32の上面にコンクリート版2を設置する際、プラットホーム30の延在方向全ての床材31や盛土32を除去することなく、必要部分のみを除去すればよいため、プラットホームドア20の固定にかかる手間やコストを低減できる。   Moreover, the concrete plate 2 is fixed by removing only the necessary amount of the floor material 31 and the fill 32 in order to install the concrete plate 2 without removing the fill 32 of the platform 30 on a large scale. Therefore, according to this embodiment, the platform door 20 can be installed easily. That is, the length of the concrete plate 2 in the extending direction of the platform 30 is only a length necessary for placing the platform door 20 as shown in FIG. Therefore, when the embankment type platform 30 is refurbished and the concrete plate 2 is installed on the upper surface of the embankment 32 of the platform 30, only the necessary portions are removed without removing all the floor materials 31 and embankments 32 in the extending direction of the platform 30. Therefore, the labor and cost for fixing the platform door 20 can be reduced.

更に、盛土式プラットホームから桁式プラットホームへの変更工事や、プラットホーム下の退避スペースへの電気ケーブル等の敷設工事が不要になるため、線路側からの作業を省略又は低減でき、作業時の安全性が向上する。また、仮設ホームの設置期間を短縮化でき、乗降客の安全も確保しやすくなる。   In addition, the construction work from the embankment platform to the girder platform and the construction work of electrical cables etc. in the evacuation space under the platform are not required, so work from the track side can be omitted or reduced, and safety during work Will improve. Moreover, the installation period of the temporary home can be shortened, and it becomes easy to ensure the safety of passengers.

[第2実施形態]
次に、本発明の第2実施形態に係るプラットホームドア固定構造1について、図6及び図7を参照して説明する。なお、以下では、第1実施形態と異なる構成及び作用について説明し、重複する説明については省略する。
[Second Embodiment]
Next, a platform door fixing structure 1 according to a second embodiment of the present invention will be described with reference to FIGS. In the following, configurations and operations different from those of the first embodiment will be described, and redundant descriptions will be omitted.

上述した第1実施形態に係るプラットホームドア固定構造1は、コンクリート版2とロックボルト3を備えるが、本実施形態に係るプラットホームドア固定構造1は、ロックボルト3の代わりにコンクリートブロック51と固定ボルト52を備え、カウンターウェイト方式でプラットホームドア20を固定する。これにより、盛土式プラットホーム30の盛土32のN値が2程度である軟弱な地盤にも、プラットホームドア20をプラットホーム30上に安定的に固定できる。   The platform door fixing structure 1 according to the first embodiment described above includes the concrete plate 2 and the lock bolt 3, but the platform door fixing structure 1 according to the present embodiment has a concrete block 51 and a fixing bolt instead of the lock bolt 3. 52, and the platform door 20 is fixed by a counterweight method. Thereby, the platform door 20 can be stably fixed on the platform 30 even on a soft ground in which the N value of the embankment 32 of the embankment platform 30 is about 2.

コンクリート版2のうち戸袋部21が固定される側に対して反対側には、複数本(図5の例では4本)の固定ボルト52が接続される。固定ボルト52は、プラットホーム30の内部に設けられた複数のコンクリートブロック51を上方に貫通してコンクリート版2と接続される。固定ボルト52は、コンクリート版2の上面では、例えば座金54を介してナット53が締結される。   A plurality of (four in the example of FIG. 5) fixing bolts 52 are connected to the side of the concrete plate 2 opposite to the side on which the door pocket portion 21 is fixed. The fixing bolt 52 passes through a plurality of concrete blocks 51 provided inside the platform 30 and is connected to the concrete plate 2. The fixing bolt 52 is fastened with a nut 53 on the upper surface of the concrete plate 2 via, for example, a washer 54.

コンクリートブロック51は、コンクリート版2の下面側に設置される。コンクリートブロック51の強度、重量、横断面積や深さ等は、コンクリート版2に作用するモーメントを考慮して決定される。コンクリートブロック51は、コンクリート版2がプラットホームドア20に作用する群集横荷重によって線路側に転倒することを防止する。本実施形態の図6及び図7に示す例では、コンクリートブロック51を2個ずつ3段で積み上げる例を示している。このように、コンクリートブロック51を複数の部材とすることで、運搬や取付けを容易にし、作業性を向上させることができる。   The concrete block 51 is installed on the lower surface side of the concrete plate 2. The strength, weight, cross-sectional area, depth, and the like of the concrete block 51 are determined in consideration of the moment acting on the concrete plate 2. The concrete block 51 prevents the concrete slab 2 from falling to the track side due to the lateral load of the crowd acting on the platform door 20. In the example shown in FIGS. 6 and 7 of the present embodiment, an example is shown in which two concrete blocks 51 are stacked in three stages. Thus, by making the concrete block 51 into a plurality of members, transportation and attachment can be facilitated and workability can be improved.

次に、本実施形態に係るプラットホームドア固定構造1を用いたプラットホームドア20の設置方法について説明する。   Next, an installation method of the platform door 20 using the platform door fixing structure 1 according to the present embodiment will be described.

第2実施形態の場合、第1実施形態と異なり、コンクリート版2や、コンクリート版2の下面に敷設する均しコンクリートやモルタルに加えて、コンクリートブロック51を埋設する部分を考慮して、プラットホーム30の上面のうちコンクリート版2を設置する部分の床材31や盛土32を除去する。次に、プラットホーム30の床材31や盛土32を除去した部分に、コンクリートブロック51を積み上げて設置する。このとき、コンクリートブロック51に固定ボルト52を貫通させておく。そして、均しコンクリートやモルタルを施した後、コンクリート版2の貫通孔に固定ボルト52を貫通させながら、コンクリート版2を設置する。   In the case of the second embodiment, unlike the first embodiment, in addition to the concrete plate 2 and the leveled concrete and mortar laid on the lower surface of the concrete plate 2, the platform 30 is considered in consideration of the portion in which the concrete block 51 is embedded. The floor material 31 and the embankment 32 of the part which installs the concrete slab 2 among the upper surfaces of are removed. Next, the concrete blocks 51 are stacked and installed on the platform 30 where the floor material 31 and the embankment 32 are removed. At this time, the fixing bolt 52 is passed through the concrete block 51. Then, after applying leveled concrete or mortar, the concrete plate 2 is installed while the fixing bolts 52 are passed through the through holes of the concrete plate 2.

その後、コンクリート版2の上面側にて、固定ボルト52の上端部に、座金54を通した後、ナット53を締結する。これにより、固定ボルト52を介して、コンクリートブロック51とコンクリート版2とが接続する。次に、既存のプラットホーム30の上面と新たに設置したコンクリート版2との間の隙間に目地材を施し目地を形成する。以上より、コンクリート版2がプラットホーム30上で安定的に固定される。   Thereafter, the washer 54 is passed through the upper end portion of the fixing bolt 52 on the upper surface side of the concrete plate 2, and then the nut 53 is fastened. Thereby, the concrete block 51 and the concrete plate 2 are connected via the fixing bolt 52. Next, joint material is applied to the gap between the upper surface of the existing platform 30 and the newly installed concrete plate 2 to form joints. As described above, the concrete plate 2 is stably fixed on the platform 30.

そして、プラットホームドア20の戸袋部21をコンクリート版2の上面に設置し、接着系アンカー6等によって、戸袋部21をコンクリート版2に対して固定する。これにより、プラットホームドア20の設置が完了する。コンクリート版2は、既存のプラットホーム30の上面の床材31や盛土32が切り欠かれた部分に設置され、既存の床材31や目地11によって拘束されるため、コンクリート版2の面内方向の回転が発生しない。   And the door pocket part 21 of the platform door 20 is installed in the upper surface of the concrete plate 2, and the door pocket part 21 is fixed with respect to the concrete plate 2 with the adhesive anchor 6 grade | etc.,. Thereby, the installation of the platform door 20 is completed. The concrete plate 2 is installed in a portion where the floor material 31 and the embankment 32 on the upper surface of the existing platform 30 are cut out, and is restrained by the existing floor material 31 and joints 11. There is no rotation.

以上、本実施形態によれば、盛土式プラットホーム30の盛土32の上面にコンクリート版2が設置される。コンクリート版2は、固定ボルト52によってコンクリートブロック51と接続されることによって、プラットホーム30に対して固定される。プラットホームドア20は、プラットホーム30に対して確実に固定されたコンクリート版2に載置されることから、プラットホーム30上に安定的に据え付けられる。   As described above, according to the present embodiment, the concrete plate 2 is installed on the upper surface of the embankment 32 of the embankment platform 30. The concrete plate 2 is fixed to the platform 30 by being connected to the concrete block 51 by fixing bolts 52. Since the platform door 20 is placed on the concrete plate 2 that is securely fixed to the platform 30, the platform door 20 is stably installed on the platform 30.

また、コンクリート版2は、第1実施形態と同様に、プラットホーム30の盛土32を大規模に除去することなく、コンクリート版2を設置するために床材31や盛土32を必要な分だけ除去するだけで固定される。そのため、本実施形態によれば、簡易にプラットホームドア20を据え付けることができる。したがって、プラットホームドア20の固定にかかる手間やコストを低減できる。   Moreover, the concrete plate 2 removes the floor material 31 and the embankment 32 as much as necessary to install the concrete plate 2 without removing the embankment 32 of the platform 30 on a large scale, as in the first embodiment. Just fixed. Therefore, according to this embodiment, the platform door 20 can be installed easily. Therefore, it is possible to reduce labor and cost for fixing the platform door 20.

1 プラットホームドア固定構造
2 コンクリート版(板状部材)
3 ロックボルト(支持部)
4 ボルト部(棒状部材)
5 グラウト
12 点字タイル
20 プラットホームドア
21 戸袋部
22 扉部
30 プラットホーム
51 コンクリートブロック
52 固定ボルト
1 Platform door fixing structure 2 Concrete plate (plate-like member)
3 Rock bolt (support)
4 Bolt part (bar-shaped member)
5 Grout 12 Braille tile 20 Platform door 21 Door part 22 Door part 30 Platform 51 Concrete block 52 Fixing bolt

Claims (8)

盛土で形成された盛土式プラットホームの前記盛土上面に設置され、一側にプラットホームドア装置が載置されるコンクリート製の板状部材と、
前記盛土内部へ貫入されて前記板状部材と接続される棒状部材と、貫入された前記棒状部材の周囲に注入されるグラウトとを有し、前記盛土に対して前記板状部材を固定する支持部と、
を備えるプラットホームドア固定構造。
A concrete plate-like member which is installed on the embankment upper surface of the embankment platform formed by embankment and on which one platform door device is placed;
A bar-like member that penetrates into the embankment and is connected to the plate-like member, and a grout that is injected around the penetrated bar-like member, and supports the plate-like member with respect to the embankment And
Platform door fixing structure.
盛土で形成された盛土式プラットホームの前記盛土上面に設置され、一側にプラットホームドア装置が載置されるコンクリート製の板状部材と、
前記盛土内部に設置されて前記板状部材と接続され、前記盛土に対して前記板状部材を固定するブロック部材と、
を備えるプラットホームドア固定構造。
A concrete plate-like member which is installed on the embankment upper surface of the embankment platform formed by embankment and on which one platform door device is placed;
A block member installed inside the embankment and connected to the plate-like member, and fixing the plate-like member to the embankment;
Platform door fixing structure.
前記板状部材の前記プラットホーム延在方向の長さは、前記プラットホームドア装置の閉状態の扉部と前記扉部を支持する本体部を合わせた長さよりも短く、前記本体部が前記板状部材の一端部に載置される請求項1に記載のプラットホームドア固定構造。   The length of the plate-like member in the platform extending direction is shorter than the combined length of the closed door portion of the platform door device and the main body portion supporting the door portion, and the main body portion is the plate-like member. The platform door fixing structure according to claim 1, which is placed at one end of the platform door. 前記板状部材の側面に沿って、前記プラットホームドア装置と接続される電気ケーブルが敷設される請求項1又は2に記載のプラットホームドア固定構造。   The platform door fixing structure according to claim 1 or 2, wherein an electric cable connected to the platform door device is laid along a side surface of the plate-like member. 前記板状部材の上面に設置される点字タイルの裏面に沿って、前記プラットホームドア装置と接続される電気ケーブルが敷設される請求項1又は2に記載のプラットホームドア固定構造。   The platform door fixing structure according to claim 1 or 2, wherein an electric cable connected to the platform door device is laid along a back surface of a Braille tile installed on an upper surface of the plate-like member. 前記板状部材に形成され、前記点字タイルの裏面側に形成される凹状の溝内部に、前記電気ケーブルが内部に敷設されるダクトが設置される請求項4に記載のプラットホームドア固定構造。   The platform door fixing structure according to claim 4, wherein a duct in which the electric cable is laid is installed in a concave groove formed in the plate-like member and formed on the back side of the Braille tile. 盛土で形成された盛土式プラットホームの上面にコンクリート製の板状部材を設置するステップと、
前記盛土内部へ棒状部材を貫入するステップと、
貫入された前記棒状部材の周囲にグラウトを注入するステップと、
前記棒状部材を前記板状部材と接続するステップと、
前記板状部材の一側にプラットホームドア装置を載置するステップと、
を含むプラットホームドア固定方法。
Installing a concrete plate-like member on the upper surface of the embankment platform formed by embankment;
Penetrating a rod-shaped member into the embankment;
Injecting grout around the penetrating rod member;
Connecting the rod-shaped member to the plate-shaped member;
Placing a platform door device on one side of the plate member;
Including platform door fixing method.
盛土で形成された盛土式プラットホームの内部にブロック部材を設置するステップと、
前記ブロック部材の上面にコンクリート製の板状部材を設置するステップと、
前記ブロック部材を前記板状部材と接続するステップと、
前記板状部材の一側にプラットホームドア装置を載置するステップと、
を含むプラットホームドア固定方法。

Installing a block member inside an embankment type platform formed by embankment;
Installing a concrete plate-like member on the upper surface of the block member;
Connecting the block member with the plate member;
Placing a platform door device on one side of the plate member;
Including platform door fixing method.

JP2012208483A 2012-09-21 2012-09-21 Platform door fixing structure and platform door fixing method Active JP6021545B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2012208483A JP6021545B2 (en) 2012-09-21 2012-09-21 Platform door fixing structure and platform door fixing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2012208483A JP6021545B2 (en) 2012-09-21 2012-09-21 Platform door fixing structure and platform door fixing method

Publications (2)

Publication Number Publication Date
JP2014062407A true JP2014062407A (en) 2014-04-10
JP6021545B2 JP6021545B2 (en) 2016-11-09

Family

ID=50617869

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012208483A Active JP6021545B2 (en) 2012-09-21 2012-09-21 Platform door fixing structure and platform door fixing method

Country Status (1)

Country Link
JP (1) JP6021545B2 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5848483B1 (en) * 2015-06-29 2016-01-27 東日本旅客鉄道株式会社 Home door cable laying structure and home door cable cabinet used therefor
JP2018178362A (en) * 2017-04-03 2018-11-15 東鉄工業株式会社 Counter-weight block construction method
JP2019143449A (en) * 2018-02-23 2019-08-29 東急建設株式会社 Foundation structure of platform door, construction method therefor and screw-in jig
JP2020165098A (en) * 2019-03-28 2020-10-08 東日本旅客鉄道株式会社 Station platform reinforcement structure
JP2020165094A (en) * 2019-03-28 2020-10-08 東日本旅客鉄道株式会社 Station platform reinforcement structure
JP2020165092A (en) * 2019-03-28 2020-10-08 東日本旅客鉄道株式会社 Station platform reinforcement structure
JP7401958B2 (en) 2020-06-03 2023-12-20 東日本旅客鉄道株式会社 Platform door installation structure
JP7504377B2 (en) 2021-02-15 2024-06-24 西日本旅客鉄道株式会社 Platform fence foundation structure and platform fence construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62288205A (en) * 1986-06-06 1987-12-15 財団法人鉄道総合技術研究所 Platform raising assembling construction method of station
JP2002250016A (en) * 2001-02-23 2002-09-06 Yutaka Seisakusho:Kk Braille block with heater
JP2003138573A (en) * 2001-11-01 2003-05-14 Shimizu Corp Platform and its repairing method
US20080190031A1 (en) * 2005-07-14 2008-08-14 Kaba Gilgen Ag Sliding Door Construction for Platforms and Method for Assembly Thereof
JP2011089361A (en) * 2009-10-26 2011-05-06 Nishi Nippon Spc Kk Slope reinforcing method
JP2011195009A (en) * 2010-03-19 2011-10-06 East Japan Railway Co Method of installing movable platform fence to platform and installation tool set of movable platform fence

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62288205A (en) * 1986-06-06 1987-12-15 財団法人鉄道総合技術研究所 Platform raising assembling construction method of station
JP2002250016A (en) * 2001-02-23 2002-09-06 Yutaka Seisakusho:Kk Braille block with heater
JP2003138573A (en) * 2001-11-01 2003-05-14 Shimizu Corp Platform and its repairing method
US20080190031A1 (en) * 2005-07-14 2008-08-14 Kaba Gilgen Ag Sliding Door Construction for Platforms and Method for Assembly Thereof
JP2011089361A (en) * 2009-10-26 2011-05-06 Nishi Nippon Spc Kk Slope reinforcing method
JP2011195009A (en) * 2010-03-19 2011-10-06 East Japan Railway Co Method of installing movable platform fence to platform and installation tool set of movable platform fence

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5848483B1 (en) * 2015-06-29 2016-01-27 東日本旅客鉄道株式会社 Home door cable laying structure and home door cable cabinet used therefor
JP2018178362A (en) * 2017-04-03 2018-11-15 東鉄工業株式会社 Counter-weight block construction method
JP2019143449A (en) * 2018-02-23 2019-08-29 東急建設株式会社 Foundation structure of platform door, construction method therefor and screw-in jig
JP2020165098A (en) * 2019-03-28 2020-10-08 東日本旅客鉄道株式会社 Station platform reinforcement structure
JP2020165094A (en) * 2019-03-28 2020-10-08 東日本旅客鉄道株式会社 Station platform reinforcement structure
JP2020165092A (en) * 2019-03-28 2020-10-08 東日本旅客鉄道株式会社 Station platform reinforcement structure
JP7191754B2 (en) 2019-03-28 2022-12-19 東日本旅客鉄道株式会社 Station platform reinforcement structure
JP7194627B2 (en) 2019-03-28 2022-12-22 東日本旅客鉄道株式会社 Station platform reinforcement structure
JP7194626B2 (en) 2019-03-28 2022-12-22 東日本旅客鉄道株式会社 Station platform reinforcement structure
JP7401958B2 (en) 2020-06-03 2023-12-20 東日本旅客鉄道株式会社 Platform door installation structure
JP7504377B2 (en) 2021-02-15 2024-06-24 西日本旅客鉄道株式会社 Platform fence foundation structure and platform fence construction method

Also Published As

Publication number Publication date
JP6021545B2 (en) 2016-11-09

Similar Documents

Publication Publication Date Title
JP6021545B2 (en) Platform door fixing structure and platform door fixing method
US20140223851A1 (en) Prefabricated reinforced concrete wall panel and installation method
CN107558633A (en) It is provided with the installation method of the prefabricated panel with distribution box
KR20190022132A (en) Top-down method using precast-concrete colum
JP5854506B2 (en) How to change the basic form of an existing building
JP5865567B2 (en) Connecting slab and its construction method
JPH11148231A (en) Assembled and laid building reinforcing structure, its reinforcing method, and base isolating construction method
CN111364520A (en) Prefabricated multi-way cable well and construction method thereof
KR101531766B1 (en) Method of Pre-supported tunnel costructed in a soft ground
JP5749620B2 (en) Seismic isolation method for existing buildings
AU2012101074A4 (en) A component tunnel ceiling structure and method of installing the same
JPH0996197A (en) Structure of support wall and construction method therefor
JP5308592B1 (en) Installation method of railroad platform platform fence
JP6252860B2 (en) Construction method of seismic isolation building
JP5139718B2 (en) Construction method of pre-packed concrete girder
JP2001303592A (en) Method for installing and fixing block
JP6895740B2 (en) Horizontal force restraint structure
JP5982143B2 (en) Reinforcing structure and reinforcing method for existing structure
JP2006002428A (en) Reinforcing method of existing floor and base isolation method of existing building
KR101389123B1 (en) Pile type protecting wall
JP4511080B2 (en) Construction method of underground structure
JP5167578B2 (en) Construction method for underground structures
JP6047397B2 (en) Embankment and natural ground composite reinforced earth wall structure and embankment and natural ground composite reinforced earth wall construction method
JP4840297B2 (en) Construction method of underground structure, underground structure
JP2017036594A (en) Earthquake-resistant structure and earthquake-resistance providing method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20150430

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20160210

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20160223

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20160425

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20160906

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20161004

R150 Certificate of patent or registration of utility model

Ref document number: 6021545

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R371 Transfer withdrawn

Free format text: JAPANESE INTERMEDIATE CODE: R371

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250