JP2013159897A - Foundation construction method - Google Patents

Foundation construction method Download PDF

Info

Publication number
JP2013159897A
JP2013159897A JP2012019807A JP2012019807A JP2013159897A JP 2013159897 A JP2013159897 A JP 2013159897A JP 2012019807 A JP2012019807 A JP 2012019807A JP 2012019807 A JP2012019807 A JP 2012019807A JP 2013159897 A JP2013159897 A JP 2013159897A
Authority
JP
Japan
Prior art keywords
steel
construction site
members
piles
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2012019807A
Other languages
Japanese (ja)
Inventor
Kazuki Yabe
和貴 矢部
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SINWA Manufacturing CO Ltd
Original Assignee
SINWA Manufacturing CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SINWA Manufacturing CO Ltd filed Critical SINWA Manufacturing CO Ltd
Priority to JP2012019807A priority Critical patent/JP2013159897A/en
Publication of JP2013159897A publication Critical patent/JP2013159897A/en
Pending legal-status Critical Current

Links

Images

Abstract

PROBLEM TO BE SOLVED: To shorten a construction period by simplifying processes of constructing a foundation at a construction site.SOLUTION: Steel-made members are assembled at a factory in advance, and arranged and interconnected at a construction site according to design drawings, and piles are driven after the steel members are arranged. In a method of assembling the steel-made members from the beginning at the construction site, more processes at the construction site are required and a construction period becomes longer, but when the steel members are assembled at the factory in advance, the processes at the construction site can be simplified to contribute to shortening of the construction period at the construction site. Positions where the respective piles are driven need to be accurately measured in a method of arranging the steel-made members after driving the piles, but the sizes, shapes, etc., of the steel-made members are already based upon the design drawings in the method of driving the piles after the steel-made members are arranged, so that when the steel-made members are connected at the construction site, the positions where the piles are driven are naturally determined based on the positions of the steel-made members having been arranged.

Description

本発明は建築物の基礎を構築する方法に関する。   The present invention relates to a method of building a building foundation.

建築物の基礎を構築する場合には、一般に、地面に掘削した複数の穴にそれぞれ杭を打ち込み、各々の杭と杭の間に鋼製部材を渡して水平レベルの調整をした後、これらの鋼製部材に木製などの型枠を取り付け、コンクリートを打設している。例えば特許文献1においては、杭を地面に打ち込み、その杭の突出部分を囲むように配置した型枠部材の内部にコンクリ−トを打設するという方法が開示されている。   When building foundations for buildings, generally, piles are driven into holes drilled in the ground, steel members are passed between each pile, and the horizontal level is adjusted. A formwork such as wood is attached to a steel member, and concrete is cast. For example, Patent Document 1 discloses a method in which a pile is driven into the ground and a concrete is placed inside a formwork member disposed so as to surround the protruding portion of the pile.

特開2002−309589号公報JP 2002-309589 A

ところで、建築資材の価格上昇や建築現場の作業員の人件費上昇などを背景として、建築基礎を構築するときの工程をできるだけ簡略化して工期を短縮することが求められている。そこで、本発明は、建築現場において基礎を構築する工程を簡略化して工期短縮を実現することを目的とする。   By the way, against the background of rising prices of building materials and labor costs of workers at construction sites, it is required to simplify the process when building a building foundation as much as possible to shorten the construction period. Then, this invention aims at simplifying the process of building a foundation in a construction site, and implement | achieving construction period shortening.

本発明は、予め組み立てられた複数の鋼製部材を建築現場に配置して相互に連結する工程と、連結された鋼製部材の位置を基準にして地中に杭を打ち込む工程と、杭が打ち込まれた後の前記鋼製部材に型枠を取り付ける工程と、前記型枠によって囲まれた領域にコンクリートを打設する工程とを備える基礎構築方法を提供する。   The present invention includes a step of arranging a plurality of pre-assembled steel members on a construction site and interconnecting them, a step of driving a pile into the ground based on the position of the connected steel members, and a pile Provided is a foundation construction method comprising a step of attaching a mold to the steel member after being driven and a step of placing concrete in a region surrounded by the mold.

本発明によれば、建築現場において基礎を構築する工程を簡略化して工期短縮を実現することが可能となる。   ADVANTAGE OF THE INVENTION According to this invention, it becomes possible to simplify the process of constructing a foundation at a construction site and to shorten the construction period.

墨出し作業を説明する斜視図である。It is a perspective view explaining inking process. 基礎フレームが組み立てられているときの様子を示す斜視図である。It is a perspective view which shows a mode when the foundation frame is assembled. 基礎フレーム組み立て作業を説明する立面図である。It is an elevation view explaining a basic frame assembly operation. 水平レベル調整作業を説明する立面図である。It is an elevation view for explaining the horizontal level adjustment work. 穴の掘削作業を説明する平面図である。It is a top view explaining the excavation work of a hole. 穴の掘削作業を説明する立面図である。It is an elevation view explaining the excavation work of a hole. 杭の打ち込み作業を説明する立面図である。It is an elevation view explaining the driving operation of the pile. 型枠の取り付け作業を説明する斜視図である。It is a perspective view explaining the attachment work of a formwork. コンクリートの打設作業を説明する斜視図である。It is a perspective view explaining concrete placement work.

[実施形態]
以下、本実施形態に係る基礎構築方法について説明する。
本実施形態に係る基礎構築方法の特徴は、鋼製部材そのものを一から建築現場で組み立てるのではなく、予め工場で組み立てておき建築現場では設計図面に沿ってこれらを配置して相互に連結する点と、杭を打ち込んでから鋼製部材を配置するという順序ではなく、これらの鋼製部材を配置してから杭を打ち込むという点である。鋼製部材そのものを一から建築現場で組み立ててゆく方法では、建築現場における工程が増えて工期が長くなるのに対し、鋼製部材を設計図面に忠実に従って事前に工場で組み立てておくようにすれば、建築現場における工程を簡略化でき、建築現場における工期短縮に寄与する。また、杭を打ち込んでから鋼製部材を配置する方法では、各々の杭を打ち込む位置を逐一正確に測って決めなければならないが、鋼製部材を配置してから杭を打ち込む方法では、その鋼製部材の寸法や形状などが既に設計図面に忠実に従っているものであるから、その鋼製部材を建築現場で設計図面どおりに配置して連結すると、その鋼製部材の位置を基準にして、杭を打ち込む位置が自然と定まることになる。よって、建築現場における工程を簡略化して工期短縮を実現することが可能となる。以下、本実施形態に係る基礎構築方法について詳細に説明する。
[Embodiment]
Hereinafter, the foundation construction method according to the present embodiment will be described.
The feature of the foundation construction method according to this embodiment is that the steel members themselves are not assembled at the construction site from scratch, but are assembled in advance at the factory, and these are arranged and connected to each other along the design drawings at the construction site. The point is not the order of placing the steel members after driving the piles, but the point of driving the piles after placing these steel members. The method of assembling steel members from scratch from the construction site increases the number of processes at the construction site and lengthens the construction period, whereas steel members should be assembled in advance in the factory according to the design drawings. For example, the process at the construction site can be simplified and the construction period at the construction site can be shortened. In addition, in the method of placing steel members after driving piles, the position where each pile is driven must be measured and determined one by one, but in the method of placing piles after placing steel members, the steel Since the dimensions and shape of the steel parts already follow the design drawings, when the steel members are arranged and connected according to the design drawings at the construction site, the piles are based on the position of the steel parts. The position to shoot will be determined naturally. Therefore, it is possible to simplify the process at the construction site and reduce the construction period. Hereinafter, the foundation construction method according to the present embodiment will be described in detail.

(1)墨出し作業
図1に示すように、建築現場において作業員Sは、砕石が撒かれた上に打設された所定の厚さのコンクリート床(定盤Pという)の上に、設計図面に基づいて、基礎の構築に必要な線Lを墨などで描く。これを墨出し作業といい、線Lは、鋼製部材を配置する位置を指定するものである。
(1) Inking work As shown in FIG. 1, a worker S designs on a concrete floor (referred to as a surface plate P) having a predetermined thickness placed on a crushed stone. Based on the drawing, a line L necessary for constructing the foundation is drawn with black or the like. This is called inking work, and the line L designates the position where the steel member is arranged.

(2)基礎フレーム組み立て作業
次に、作業員Sは、墨出し作業において描かれた線Lの位置に、2種類の鋼製部材10a,10bを配置し、これらを相互に連結する。連結された鋼製部材10a,10bによって、基礎フレームと呼ばれる構造体が完成する。図2に示すように、線Lのうち、円形の部分には、中空パイプ状の鋼製部材10aが配置され、直線の部分には、トラス構造の鋼製部材10bが配置される。これらの鋼製部材10a及び鋼製部材10bは、建築現場で一から組み立てられるのではなく、メーカの工場で工場作業員がその縦、横、対角等の寸法を確認しながら、ボルト・ナットや溶接などを利用することで予め組み立てられ、建築現場に運搬される。このため、建築現場における具体的の作業手順は、図3に示すように、作業員Sが操作するクレーン車101によって鋼製部材10aまたは鋼製部材10bを吊り上げてから、線Lによって指定された位置に鋼製部材10a及び鋼製部材10bを配置し、そして、作業員Sの手作業によって図示せぬボルトやナットなどの連結具によってこれらを連結する、という手順になる。これにより、隣り合う鋼製部材10aの間が鋼製部材10bによって接続されることになる。さらに、後述する図5に示すように、隣り合う鋼製部材10bの間を補強部材10cで連結してさらに強度を高めるようにしてもよい(なお、図2,8,9では、図面の内容が煩雑になるため、補強部材10cの図示を省略している)。この結果、建築現場を上方から鉛直方向に見ると、鋼製部材10a及び鋼製部材10bからなる格子状の基礎フレームが構築されることになる。
(2) Foundation frame assembly operation Next, the worker S arranges two types of steel members 10a and 10b at the position of the line L drawn in the marking operation, and connects them together. A structure called a basic frame is completed by the connected steel members 10a and 10b. As shown in FIG. 2, a hollow pipe-shaped steel member 10 a is arranged in a circular portion of the line L, and a truss structure steel member 10 b is arranged in a straight portion. These steel members 10a and steel members 10b are not assembled from the ground up at the construction site, but a factory worker confirms their vertical, horizontal, diagonal, etc. dimensions at the manufacturer's factory. It is pre-assembled by using welding or welding and transported to the construction site. For this reason, as shown in FIG. 3, the specific work procedure at the construction site is specified by the line L after the steel member 10 a or the steel member 10 b is lifted by the crane vehicle 101 operated by the worker S. The steel member 10a and the steel member 10b are arranged at the positions, and these are coupled by a manual operation of the worker S with a coupling tool such as a bolt or a nut (not shown). Thereby, between the adjacent steel members 10a is connected by the steel member 10b. Furthermore, as shown in FIG. 5 to be described later, the strength may be further increased by connecting the adjacent steel members 10b with a reinforcing member 10c (in FIGS. 2, 8, and 9, the contents of the drawings). (The illustration of the reinforcing member 10c is omitted). As a result, when the building site is viewed from above in the vertical direction, a lattice-shaped foundation frame composed of the steel member 10a and the steel member 10b is constructed.

(3)水平レベル調整作業
次に、作業員Sは水平レベル調整作業を行う。より具体的には、作業員は、鋼製部材10bの上端面が水平になっているかどうかと、鋼製部材10bの上端面の高さが設計図面どおりの高さになっているかどうかとを測量器械102などで確認する。そして、作業員は、その確認結果が意図したものでない場合には、鋼製部材10a及び鋼製部材10bを連結しているボルトやナットを緩めたり締めたりして、鋼製部材10bの位置や姿勢を変え、鋼製部材10bの水平度や高さを調整する。
(3) Horizontal level adjustment work Next, the worker S performs horizontal level adjustment work. More specifically, the operator determines whether the upper end surface of the steel member 10b is horizontal and whether the upper end surface of the steel member 10b is as high as the design drawing. Check with surveying instrument 102 or the like. Then, if the confirmation result is not intended, the worker loosens or tightens the bolt or nut connecting the steel member 10a and the steel member 10b, and the position of the steel member 10b The posture is changed to adjust the level and height of the steel member 10b.

(4)穴の掘削作業
次に、作業員Sは、図5,6に示すように、作業車103に取り付けられたオーガ14を各々の鋼製部材10aの中空部分に上方から鉛直方向に挿入し、その先端を定盤Pに当てて回転させることで、例えば深さ1mほどの、鉛直方向に延びる穴Hを開ける。
(4) Hole excavation work Next, as shown in FIGS. 5 and 6, the worker S inserts the auger 14 attached to the work vehicle 103 vertically into the hollow portion of each steel member 10a from above. Then, by rotating the tip against the surface plate P, a hole H extending in the vertical direction, for example, having a depth of about 1 m is formed.

(5)杭の打ち込み作業
次に、作業員Sは、図7に示すように、作業車104に取り付けられた、例えば長さ数メートルほどの杭10dを上方から鋼製部材10aの中空部分を介して上記の各穴Hに鉛直方向に挿入し、さらに地中へと打ち込む。つまり、鋼製部材10の中空部分の位置は、鋼製部材10a、10bが設計図面どおりに配置、連結されることで定まるから、鋼製部材10a、10bの位置を基準にして地中に杭10dが打ち込まれることになる。そして、作業員Sは、基礎フレームと杭10dとを固定し、杭10dの余分な部位を切断する。
(5) Pile driving operation Next, as shown in FIG. 7, the worker S attaches the hollow portion of the steel member 10 a to the pile 10 d attached to the work vehicle 104, for example, about several meters long. Through each hole H in the vertical direction and further driven into the ground. That is, since the position of the hollow part of the steel member 10 is determined by arranging and connecting the steel members 10a and 10b according to the design drawing, the pile in the ground is based on the position of the steel members 10a and 10b. 10d will be driven. And worker S fixes a foundation frame and pile 10d, and cuts an extra portion of pile 10d.

(6)型枠の取り付け作業
次に、作業員Sは、図8に示すように、鋼製部材10a,10bのうち、最も外周側にある鋼製部材10a,10bに対して木製の型枠10eを取り付ける。
(6) Work of attaching formwork Next, as shown in FIG. 8, the worker S forms a wooden formwork with respect to the steel members 10a, 10b on the outermost side among the steel members 10a, 10b. 10e is attached.

(7)コンクリートの打設作業
最後に、作業員Sは、図9に示すように、型枠10eによって囲まれた領域に型枠10eの上端部近傍に達するまで作業車105からコンクリートを流し込む。これにより、コンクリートの打設が行われる。
以上のようにして建築現場の基礎が構築される。本実施形態によれば、前述したとおり、建築現場における工程を簡略化して工期短縮を実現することが可能となる。
(7) Concrete Placing Work Finally, as shown in FIG. 9, the worker S pours concrete from the work vehicle 105 into the area surrounded by the mold 10e until it reaches the vicinity of the upper end of the mold 10e. Thereby, concrete placement is performed.
The foundation of the construction site is constructed as described above. According to the present embodiment, as described above, it is possible to simplify the process at the construction site and reduce the work period.

10a,10b 鋼製部材、10c 補強部材、10d 杭、10e 型枠、S 作業員、P 定盤、L 線、H 穴、101 クレーン、102 測量器械、103,104,105 作業車。 10a, 10b Steel member, 10c reinforcement member, 10d pile, 10e formwork, S worker, P surface plate, L wire, H hole, 101 crane, 102 surveying instrument, 103, 104, 105 work vehicle.

Claims (1)

予め組み立てられた複数の鋼製部材を建築現場に配置して相互に連結する工程と、
連結された鋼製部材の位置を基準にして地中に杭を打ち込む工程と、
杭が打ち込まれた後の前記鋼製部材に型枠を取り付ける工程と、
前記型枠によって囲まれた領域にコンクリートを打設する工程と
を備える基礎構築方法。
Arranging a plurality of pre-assembled steel members on the construction site and interconnecting them;
Driving a pile into the ground based on the position of the connected steel members;
Attaching a formwork to the steel member after the pile is driven;
And a step of placing concrete in an area surrounded by the formwork.
JP2012019807A 2012-02-01 2012-02-01 Foundation construction method Pending JP2013159897A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2012019807A JP2013159897A (en) 2012-02-01 2012-02-01 Foundation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2012019807A JP2013159897A (en) 2012-02-01 2012-02-01 Foundation construction method

Publications (1)

Publication Number Publication Date
JP2013159897A true JP2013159897A (en) 2013-08-19

Family

ID=49172401

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012019807A Pending JP2013159897A (en) 2012-02-01 2012-02-01 Foundation construction method

Country Status (1)

Country Link
JP (1) JP2013159897A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4994113A (en) * 1973-01-10 1974-09-06
JPH04297618A (en) * 1991-03-26 1992-10-21 Nippon Concrete Ind Co Ltd Connection of base pile with column member
JP2000257175A (en) * 1999-03-10 2000-09-19 Daiwa House Ind Co Ltd Column base structure of steel structure and its construction method
JP2002309589A (en) * 2001-04-11 2002-10-23 Nippon Steel Corp Structure for joining foundation to footing beam
JP2002309591A (en) * 2001-04-13 2002-10-23 Nippon Steel Corp Structure for joining pile head to steel footing beam
JP2007170076A (en) * 2005-12-22 2007-07-05 Kanematsu Nnk Corp Tool for ground reinforcing work, and ground reinforcing structure and ground reinforcing method using the same

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4994113A (en) * 1973-01-10 1974-09-06
JPH04297618A (en) * 1991-03-26 1992-10-21 Nippon Concrete Ind Co Ltd Connection of base pile with column member
JP2000257175A (en) * 1999-03-10 2000-09-19 Daiwa House Ind Co Ltd Column base structure of steel structure and its construction method
JP2002309589A (en) * 2001-04-11 2002-10-23 Nippon Steel Corp Structure for joining foundation to footing beam
JP2002309591A (en) * 2001-04-13 2002-10-23 Nippon Steel Corp Structure for joining pile head to steel footing beam
JP2007170076A (en) * 2005-12-22 2007-07-05 Kanematsu Nnk Corp Tool for ground reinforcing work, and ground reinforcing structure and ground reinforcing method using the same

Similar Documents

Publication Publication Date Title
JP4957894B2 (en) Reinforcement method for power transmission towers
CN101649678B (en) Structure for strengthening node of beam column by section increase method and construction method thereof
KR101687495B1 (en) Partial top-down construction method for building underground structures
JP2012097458A (en) Foundation construction method for structure on ground, and component of foundation construction
KR100965855B1 (en) Joint structure and method for combining steel member on concrete member
KR101561212B1 (en) Concrete precast wall and the construction method using the same
JP6430271B2 (en) Footing-integrated foundation pile structure and construction method of footing-integrated foundation pile
JP7018682B1 (en) How to build a solid foundation
JP5176786B2 (en) Construction method of column beam frame
JP2016180249A (en) Pile head part joining method and pile head part support structure for precast concrete member
JP2017125322A (en) Base structure
JP6383558B2 (en) Footing basic structure
JP2023029562A (en) pile foundation structure
JP6070118B2 (en) Retaining wall structure, method for constructing retaining wall structure
JP2013159897A (en) Foundation construction method
JP2012057433A (en) Structure and method for connecting pile and steel column
JP2019143354A (en) Method for producing concrete block for mat foundation and construction method for mat foundation
JP2008095362A (en) Steel framed rigid frame structural body construction method and green house for agriculture having foundation constructed by this construction method
JP4722691B2 (en) Repair method for soil concrete in existing structures
KR101707376B1 (en) Structure for constructing underground structure using composite beams and the construction method thereof
KR101206790B1 (en) Pillar Structure and Method for Constructing The Same
JP3181886U (en) Precast pile and composite pile structure
JP2013064264A (en) Support frame for anchor bolt and method of constructing support frame
KR101213553B1 (en) pile cap
KR200362827Y1 (en) concrete structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20121016

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20131129

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20131224

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20140422