JP2013136062A - Tapping charge number decision-supporting device of thick plate product - Google Patents

Tapping charge number decision-supporting device of thick plate product Download PDF

Info

Publication number
JP2013136062A
JP2013136062A JP2011287479A JP2011287479A JP2013136062A JP 2013136062 A JP2013136062 A JP 2013136062A JP 2011287479 A JP2011287479 A JP 2011287479A JP 2011287479 A JP2011287479 A JP 2011287479A JP 2013136062 A JP2013136062 A JP 2013136062A
Authority
JP
Japan
Prior art keywords
steel
steel type
output
result
product
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2011287479A
Other languages
Japanese (ja)
Inventor
Hisafumi Maeda
尚史 前田
Norimi Wada
典巳 和田
Hiroshi Nishizaki
西崎  宏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
JFE Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JFE Steel Corp filed Critical JFE Steel Corp
Priority to JP2011287479A priority Critical patent/JP2013136062A/en
Publication of JP2013136062A publication Critical patent/JP2013136062A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Abstract

PROBLEM TO BE SOLVED: To provide a tapping charge number decision-supporting device, in which the product specification and the production specification form a one-to-multiple number of corresponding relationship, and the remainder obtained by dividing the tapping frame, for satisfying the necessary tapping amount of the upper rank steel type related to ordered items, by the steel production tapping unit can be supplemented by the ordered items permitting the alternative of the lower rank steel type by the upper rank steel type to reduce the inventory load.SOLUTION: In order to fill the tapping frame of the upper rank steel type (the steel type in which the alloy component cost is relatively high), the tapping charge number decision-supporting device includes: a temporary production specification determining means 1, in which for the standard and in the order of applying the lower rank steel type (the steel type in which the alloy component cost is relatively low), one that can perform the application of the upper rank steel type is searched and appropriated; and an adjusting means 2 of the necessary tapping amount for each steel type.

Description

本発明は、厚板製品の出鋼チャージ数決定支援装置に関する。   The present invention relates to an apparatus for determining the number of outgoing steel charges for a thick plate product.

鉄鋼厚板製品の製造総コストは、(1)製鋼コスト(合金量、鋼種名、モールド制約、連々鋳)、(2)圧延コスト(圧延能率:ton/hr)、(3)熱処理コスト(¥/ton)はもとより、社会情勢やミル稼動状況、受注状況(製造仕様/納期)に左右されるから、これらを勘案して製造総コストが最小になる最適製造仕様の設定が指向される。
完全受注生産の厚板品種では、上記観点((1)〜(3))からの製造総コストの低減の為、通常、ロット拡大による製鋼コストの低減を最優先し、注文(製品仕様)と一対一の関係にある製造仕様のうち、特に鋼種集約やモールド集約による連々鋳アップにてコスト低減を図っている(例えば特許文献1参照)。その為、汎用鋼種での製造仕様設定が指向されている。
The total production cost of steel plate products is as follows: (1) Steelmaking cost (alloy amount, steel type name, mold restriction, continuous casting), (2) rolling cost (rolling efficiency: ton / hr), (3) heat treatment cost (¥ / ton), as well as the social situation, mill operation status, and order status (manufacturing specifications / delivery date), the optimum manufacturing specifications that minimize the total manufacturing cost are aimed at considering these factors.
In order to reduce the total manufacturing cost from the above viewpoints ((1) to (3)), ordering (product specifications) Among manufacturing specifications having a one-to-one relationship, cost reduction is achieved by continuous casting up by steel type consolidation or mold consolidation (see, for example, Patent Document 1). Therefore, the production specification setting for general-purpose steel grades is directed.

特開2008−73724号公報JP 2008-73724 A

然し、製品仕様と製造仕様とが一対一に設定されている事で、製鋼での出鋼量の基本単位(標準出鋼単位という)例えば250トンに対し、例えば280トンのオーダ(注文)があったとすると、このオーダに対応する製品仕様の鋼種の出鋼枠は、250トン×2チャージ=500トンとされるが、オーダ分の280トンを除いた残りの220トンは充当先が見つかるまでストックされ、結果的に充当先が見つからなかった分は屑とされる。
つまり、従来では、製品仕様と製造仕様とが一対一に設定されている為に、注文品に係る鋼種である上位鋼種の必要出鋼量を満たす為の出鋼枠を製鋼出鋼単位で割った余りの出鋼品は、注文待ち品となって在庫負担が増すという課題があった。
However, since the product specification and the production specification are set one-to-one, the basic unit of steel output in steelmaking (referred to as standard steel output unit), for example, 250 tons, for example, an order (order) of 280 tons, for example. Assuming that there is a steel frame of the product specification corresponding to this order, 250 tons x 2 charges = 500 tons, but the remaining 220 tons excluding 280 tons for the order will be found until the appropriation destination is found. The part that is stocked and as a result the destination is not found is regarded as scrap.
In other words, in the past, product specifications and production specifications are set on a one-to-one basis, so the steel output frame to satisfy the required steel output of the upper steel grade, which is the steel type related to the ordered product, is divided by the steelmaking steel output unit. There was a problem that excess steel products were waiting for orders and increased the stock burden.

発明者らは前記課題を解決するために検討し、その結果、上位鋼種(合金成分コストが相対的に高い鋼種)の出鋼枠を埋める為に、標準では下位鋼種(合金成分コストが相対的に低い鋼種)を適用するオーダについて上位鋼種の適用が可能であるものを探して引き当てるという手法に想到し、本発明を成した。
即ち本発明は次のとおりである。
(1) 総注文情報データベース(DB1)から総注文情報を読み込む読み込み部(10)と、該読み込みの結果に基き製品仕様データベース(DB2)から各注文品への製品仕様を引き当てる第1の検索部20と、該引き当ての結果に基き製造仕様データベース(DB3)から各製品仕様への標準製造仕様を引き当てて仮製造仕様として決定する第2の検索部(30)とを有する仮製造仕様の決定手段(1)、並びに、
前記決定の結果に基き前記各注文品の仮製造仕様中の鋼種である仮決定鋼種の必要出鋼量合計値を計算する必要出鋼量計算部(40)と、該計算の結果と標準出鋼単位とを用いて出鋼可否を判定する第1の出鋼可否判定部(50)と、該判定の結果に基き、前記各データベース(DB1, DB2, DB3)を参照して、仮決定鋼種よりも下位の鋼種を標準製造仕様としているが仮決定鋼種での代替製造仕様も可とされた注文品である上位鋼種運用候補注文品に係る鋼種である代替鋼種の有無を調べる第3の検索部(60)と、該調べた結果に基き、前記代替鋼種について前記と同様の必要出鋼量合計値の計算乃至出鋼可否の判定を行うか或いは例外処理判断を行う第2の出鋼可否判定部(70)とを有する鋼種毎の必要出鋼量の調整手段(2)、
を有することを特徴とする厚板製品の出鋼チャージ数決定支援装置。
Inventors examined in order to solve the said subject, and, as a result, in order to fill the steel frame of the upper steel grade (steel grade with a relatively high alloy component cost), the lower grade steel grade (alloy component cost is relatively The present invention has been made by conceiving a method of searching for and assigning an order in which a higher steel grade can be applied to an order to which a lower steel grade is applied.
That is, the present invention is as follows.
(1) Reading unit (10) for reading the total order information from the total order information database (DB1), and a first search unit for assigning the product specifications for each ordered item from the product specification database (DB2) based on the result of the reading 20 and a second retrieval unit (30) for assigning a standard production specification to each product specification from the production specification database (DB3) based on the allocation result and determining the provisional production specification (1) and
Based on the result of the determination, the required amount of steel output calculation part (40) for calculating the total required amount of steel output of the provisionally determined steel type, which is the steel type in the provisional production specifications of each ordered product, the result of the calculation and the standard output Based on the result of the judgment, the first steelmaking availability judgment unit (50) that judges whether steelmaking is possible using the steel unit, and each database (DB1, DB2, DB3) The third search for the presence or absence of an alternative steel grade that is a steel grade related to a higher grade grade candidate, which is an order item for which an alternative production specification for a tentatively decided grade is allowed. Based on the result of the investigation and the part (60), the second required steelmaking is performed for the alternative steel type by calculating the required amount of steel output as described above or determining whether or not to produce steel or determining whether to handle the exception. Means for adjusting the required steel output for each steel type having a judgment part (70) (2),
A support for determining the number of steel output charges for a thick plate product.

本発明に係る装置は、コンピュータに実装された装置である。   The apparatus according to the present invention is an apparatus mounted on a computer.

本発明によれば、製品仕様と製造仕様とが一対複数の対応関係となり、注文品に係る上位鋼種の必要出鋼量を満たす為の出鋼枠を製鋼出鋼単位で割った余りを、下位鋼種の上位鋼種による代替を許す注文品で補充することができ、以て、在庫負担を軽減することができる。   According to the present invention, the product specifications and the production specifications have a one-to-multiple correspondence relationship, and the remainder obtained by dividing the steel output frame by the steelmaking unit to satisfy the required steel output amount of the upper steel type related to the ordered product It is possible to replenish with an ordered product that allows replacement by a higher grade of the steel grade, thereby reducing the stock burden.

本発明に係る装置の構成を示すブロック図である。It is a block diagram which shows the structure of the apparatus which concerns on this invention. 本発明に係る装置を用いた出鋼チャージ数の決め方の例を示す流れ図である。It is a flowchart which shows the example of how to determine the number of outgoing steel charges using the apparatus which concerns on this invention.

図1は本発明に係る装置の構成を示すブロック図であり、1は仮製造仕様の決定手段、2は鋼種毎の必要出鋼量調整手段、DB1は、厚板製品の総注文情報データベース、DB2は製品仕様データベース、DB3は製造仕様データベースである。
総注文情報データベースDB1は、厚板製品の全受注情報の中から一定期間内に製造予定となる候補の注文品情報の集合である総注文情報を格納した記憶手段である。全受注情報の中から前記候補を抽出する作業は別途実施されているものとする。製品仕様データベースDB2は、注文品情報に対応して定められている製品仕様(製品のスペック)に関する情報を格納した記憶手段である。該製品仕様は注文品情報に対して通常同様一対一に対応する。製造仕様データベースDB3は、製品仕様を実現する為の製造条件等、例えば、鋼種、必要出鋼量(>注文品の出荷重量)、製造条件(加熱、圧延、冷却、熱処理等の条件)、検査条件、梱包仕様等を要素とする製造仕様の集合を格納した記憶手段である。1つの製品仕様には1つ若しくは複数の製造仕様が対応付けされている。1つの製品仕様に複数の製造仕様が対応する場合、該複数の製造仕様には優先順位が設けられる。最優先の製造仕様が標準製造仕様とされ、他の製造仕様は代替製造仕様とされる。
FIG. 1 is a block diagram showing the configuration of an apparatus according to the present invention, wherein 1 is a means for determining provisional production specifications, 2 is a means for adjusting the required steel output for each steel type, DB1 is a total order information database for thick plate products, DB2 is a product specification database, and DB3 is a manufacturing specification database.
The total order information database DB1 is a storage unit that stores total order information that is a set of candidate order information that is scheduled to be manufactured within a certain period of time from all the order information of thick plate products. It is assumed that the operation of extracting the candidates from all the order information is performed separately. The product specification database DB2 is a storage unit that stores information related to product specifications (product specifications) determined corresponding to the ordered product information. The product specifications correspond one-on-one with the order information as usual. Manufacturing specification database DB3 is manufacturing conditions to realize product specifications, such as steel grade, required steel output (> shipment weight of ordered products), manufacturing conditions (conditions for heating, rolling, cooling, heat treatment, etc.), inspection The storage means stores a set of manufacturing specifications including elements such as conditions and packing specifications. One product specification is associated with one or more manufacturing specifications. When a plurality of manufacturing specifications correspond to one product specification, the plurality of manufacturing specifications are given priority. The highest-priority manufacturing specification is the standard manufacturing specification, and the other manufacturing specifications are the alternative manufacturing specifications.

仮製造仕様の決定手段1は、総注文情報データベースDB1から総注文情報を読み込む読み込み部10と、該読み込みの結果に基き製品仕様データベースDB2から各注文品への製品仕様を引き当てる第1の検索部20と、該引き当ての結果に基き製造仕様データベースDB3から各製品仕様への標準製造仕様を引き当てて仮製造仕様として決定する第2の検索部30とを有する。   The provisional manufacturing specification determination means 1 includes a reading unit 10 that reads total order information from the total order information database DB1, and a first search unit that assigns product specifications to each order item from the product specification database DB2 based on the result of the reading. 20 and a second search unit 30 that assigns standard production specifications to the product specifications from the production specification database DB3 based on the allocation result and determines the provisional production specifications.

又、鋼種毎の必要出鋼量の調整手段2は、前記決定の結果に基き前記各注文品の仮製造仕様中の鋼種である仮決定鋼種の必要出鋼量合計値を計算する必要出鋼量計算部40と、該計算の結果と標準出鋼単位とを用いて出鋼可否を判定する第1の出鋼可否判定部50と、該判定の結果に基き、前記各データベー DB1, DB2, DB3を参照して、仮決定鋼種よりも下位の鋼種を標準製造仕様としているが仮決定鋼種での代替製造仕様も可とされた注文品である上位鋼種運用候補注文品に係る鋼種である代替鋼種の有無を調べる第3の検索部60と、該調べた結果に基き、前記代替鋼種について前記と同様の必要出鋼量合計値の計算乃至出鋼可否の判定を行うか或いは例外処理判断を行う第2の出鋼可否判定部70とを有する。   Further, the required output amount adjusting means 2 for each steel type is a required output steel amount for calculating a total required output amount value of the provisionally determined steel type, which is a steel type in the provisional production specification of each order based on the result of the determination. A quantity calculation unit 40, a first steelmaking availability determination unit 50 that determines whether or not steelmaking is possible using the calculation result and the standard steelmaking unit, and each database DB1, DB2 based on the result of the judgment , With reference to DB3, the steel grades that are lower than the tentatively decided steel grade are standard production specifications, but the alternative grades for the tentatively decided steel grade are also acceptable. Based on the result of the third search unit 60 for checking the presence or absence of the alternative steel type, the same required calculation of the total amount of steel output to the alternative steel type as described above or the determination of whether or not the outgoing steel is possible or the exception processing determination A second steel output availability determination unit 70 that performs

本発明では、上記構成の装置としたから、この装置を用いて例えば図2に示す流れ図に従った処理を実行することで、出鋼チャージ編成の中に含まれる未受注品の出鋼分が最小限に抑えられた出鋼チャージ数を決定することができ、以て、在庫負担を軽減することができる。
図2を参照し、各ステップS10,S20,‥‥における各処理の内容を以下に説明する。尚、前記各処理を行う部を()内に記した。
In this invention, since it was set as the apparatus of the said structure, by executing the process according to the flowchart shown, for example in FIG. It is possible to determine the number of steel charges charged to a minimum, thereby reducing the stock burden.
Referring to FIG. 2, the contents of each process in each step S10, S20,... Will be described below. In addition, the part which performs each said process was described in ().

S10:(読み込み部10) 総注文情報の読み込みを行い、S20へ進む。
S20:(第1の検索部20) 各注文品への製品仕様を引き当てる。次いでS30へ進む。
S30:(第2の検索部30) 各製品仕様への標準製造仕様を引き当てて仮製造仕様として決定する。次いでS40へ進む。破線枠内のS40からS130までのステップは鋼種毎に実行される。
S10: (reading unit 10) The total order information is read, and the process proceeds to S20.
S20: (first search unit 20) Allocate product specifications for each ordered product. Next, the process proceeds to S30.
S30: (second search unit 30) The standard manufacturing specification is assigned to each product specification to determine the provisional manufacturing specification. Next, the process proceeds to S40. The steps from S40 to S130 in the broken line frame are executed for each steel type.

S40:(必要出鋼量計算部40) 各注文品の仮決定鋼種の必要出鋼量を合計して必要出鋼量合計値Mを求める。次いでS50へ進む。
S50:(第1の出鋼可否判定部50) 必要出鋼量合計値Mを標準出鋼単位Mstdで割って、その商と余りMrを求め、商を出鋼チャージ数(仮)とする。次いでS60へ進む。
S60:(第1の出鋼可否判定部50) Mr/Mstdを計算し、該計算値が、予め出鋼可否判定用閾値として定めたα(例えばα=0.95)以上である(Yes)か否(No)かを判定し、YesならばS70へ進み、NoならばS80へ進む。
S40: (Required steel output calculation unit 40) The required steel output amount M is obtained by summing up the required steel output of the provisionally determined steel types of each ordered product. Next, the process proceeds to S50.
S50: (First steelmaking availability determination unit 50) The required steel output total value M is divided by the standard steelmaking unit Mstd to obtain the quotient and the remainder Mr, and the quotient is the number of steel output charges (temporary). Next, the process proceeds to S60.
S60: (first steel output determination unit 50) Mr / Mstd is calculated, and whether or not the calculated value is equal to or greater than α (for example, α = 0.95) set in advance as a threshold value for determining the steel output determination (Yes). (No) is determined. If Yes, the process proceeds to S70, and if No, the process proceeds to S80.

S70:(第2の出鋼可否判定部70) 仮決定鋼種の出鋼チャージ数(仮)に1を加算して、該鋼種の実出鋼時の出鋼チャージ数とする。次いでS130へ進む。
S80:(第3の検索部60) 総注文情報データベースDB1を参照し、仮決定鋼種よりも下位の鋼種を標準製造仕様としているが仮決定鋼種での代替製造仕様も可とされた注文品である上位鋼種運用候補注文品の有無を調べる。有(Yes)ならばS90へ進み、無(No)ならばS120へ進む。
S70: (second steelmaking availability determination unit 70) 1 is added to the number of steelmaking charges of the provisionally determined steel type (temporary) to obtain the number of steeling charges at the time of actual steelmaking of the steel type. Next, the process proceeds to S130.
S80: (Third search unit 60) With reference to the total order information database DB1, the steel grade lower than the tentatively decided steel grade is the standard production specification, but the alternative production specification for the tentatively decided steel grade is also accepted. Examine whether there is an order for an upper steel grade candidate. If yes (Yes), the process proceeds to S90, and if not (No), the process proceeds to S120.

S90:(第3の検索部60) 製品仕様データベースDB2を参照し、上位鋼種運用候補に対する代替製造仕様を引き当てる。次いでS100へ進む。
S100:(第3の検索部60) 製造仕様データベースDB3を参照し、代替製造仕様に対応する鋼種である代替鋼種を引き当てて、仮決定鋼種に代替鋼種を代入する(仮決定鋼種の更新)。次いでS110へ進む。
S90: (Third search unit 60) Refers to the product specification database DB2 and allocates an alternative manufacturing specification for the upper steel grade operation candidate. Next, the process proceeds to S100.
S100: (Third search unit 60) With reference to the production specification database DB3, an alternative steel type that is a steel type corresponding to the alternative production specification is assigned, and the alternative steel type is assigned to the temporarily determined steel type (update of the temporarily determined steel type). Next, the process proceeds to S110.

S110:(第2の出鋼可否判定部70) 仮決定鋼種の必要出鋼量合計値Mを求め、S50に戻る。
S120:(第2の出鋼可否判定部70) 仮決定鋼種の出鋼チャージ数(仮)を、該鋼種の実出鋼時の出鋼チャージ数とする。但し、S60においてMr/Mstdがαよりも大幅に小さかった(例えば、Mr/Mstd<0.5×αである)場合、例外処理として、別途判断を仰ぐメッセージを出力する。次いでS130へ進む。
S110: (Second steel output availability determination unit 70) The required steel output total value M of the temporarily determined steel type is obtained, and the process returns to S50.
S120: (second steelmaking availability determination unit 70) The number of steel output charges (temporary) of the provisionally determined steel type is set as the number of steel output charges at the time of actual steel production of the steel type. However, if Mr / Mstd is significantly smaller than α in S60 (for example, Mr / Mstd <0.5 × α), a message asking for a separate determination is output as exception processing. Next, the process proceeds to S130.

S130:(第2の出鋼可否判定部70) 1つの仮決定鋼種についてのルーチン(実出鋼チャージ数の決定)を終了し、その次の仮決定鋼種について破線枠内のステップを実行し、これを繰り返して総注文情報に対応する全ての仮決定鋼種についてのルーチンが終了したら、S140へ進む。
S140: 全ての仮決定鋼種についてのルーチンの結果であるところの、総注文情報に対応する全鋼種の出鋼チャージ数を出力する。
S130: (second steel generation availability determination unit 70) The routine (determination of the number of actual steel charges) for one temporarily determined steel type is terminated, and the steps in the broken line frame are executed for the next temporarily determined steel type, When this is repeated and the routine for all provisionally determined steel types corresponding to the total order information is completed, the process proceeds to S140.
S140: The number of steel output charges of all steel types corresponding to the total order information, which is the result of the routine for all temporarily determined steel types, is output.

1 仮製造仕様の決定手段
2 鋼種毎の必要出鋼量の調整手段
10 読み込み部
20 第1の検索部
30 第2の検索部
40 必要出鋼量計算部
50 第1の出鋼可否判定部
60 第3の検索部
70 第2の出鋼可否判定部
DB1 総注文情報データベース
DB2 製品仕様データベース
DB3 製造仕様データベース
1 Means for determining provisional manufacturing specifications
2 Adjustment method of required steel output for each steel type
10 Reading section
20 First search part
30 Second search part
40 Required steel output calculator
50 1st steelmaking availability determination part
60 Third search part
70 Second steelmaking availability determination section
DB1 total order information database
DB2 product specification database
DB3 manufacturing specification database

Claims (1)

総注文情報データベース(DB1)から総注文情報を読み込む読み込み部(10)と、該読み込みの結果に基き製品仕様データベース(DB2)から各注文品への製品仕様を引き当てる第1の検索部20と、該引き当ての結果に基き製造仕様データベース(DB3)から各製品仕様への標準製造仕様を引き当てて仮製造仕様として決定する第2の検索部(30)とを有する仮製造仕様の決定手段(1)、並びに、
前記決定の結果に基き前記各注文品の仮製造仕様中の鋼種である仮決定鋼種の必要出鋼量合計値を計算する必要出鋼量計算部(40)と、該計算の結果と標準出鋼単位とを用いて出鋼可否を判定する第1の出鋼可否判定部(50)と、該判定の結果に基き、前記各データベース(DB1, DB2, DB3)を参照して、仮決定鋼種よりも下位の鋼種を標準製造仕様としているが仮決定鋼種での代替製造仕様も可とされた注文品である上位鋼種運用候補注文品に係る鋼種である代替鋼種の有無を調べる第3の検索部(60)と、該調べた結果に基き、前記代替鋼種について前記と同様の必要出鋼量合計値の計算乃至出鋼可否の判定を行うか或いは例外処理判断を行う第2の出鋼可否判定部(70)とを有する鋼種毎の必要出鋼量の調整手段(2)、
を有することを特徴とする厚板製品の出鋼チャージ数決定支援装置。
A reading unit (10) that reads total order information from the total order information database (DB1), a first search unit 20 that assigns product specifications from the product specification database (DB2) to each order based on the result of the reading, Temporary manufacturing specification determination means (1) having a second search unit (30) that allocates standard manufacturing specifications from the manufacturing specification database (DB3) to each product specification based on the allocation result and determines the provisional manufacturing specifications. As well as
Based on the result of the determination, the required amount of steel output calculation part (40) for calculating the total required amount of steel output of the provisionally determined steel type, which is the steel type in the provisional production specifications of each ordered product, the result of the calculation and the standard output Based on the result of the judgment, the first steelmaking availability judgment unit (50) that judges whether steelmaking is possible using the steel unit, and each database (DB1, DB2, DB3) The third search for the presence or absence of an alternative steel grade that is a steel grade related to a higher grade grade candidate, which is an order item for which an alternative production specification for a tentatively decided grade is allowed. Based on the result of the investigation and the part (60), the second required steelmaking is performed for the alternative steel type by calculating the required amount of steel output as described above or determining whether or not to produce steel or determining whether to handle the exception. Means for adjusting the required steel output for each steel type having a judgment part (70) (2),
A support for determining the number of steel output charges for a thick plate product.
JP2011287479A 2011-12-28 2011-12-28 Tapping charge number decision-supporting device of thick plate product Pending JP2013136062A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011287479A JP2013136062A (en) 2011-12-28 2011-12-28 Tapping charge number decision-supporting device of thick plate product

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2011287479A JP2013136062A (en) 2011-12-28 2011-12-28 Tapping charge number decision-supporting device of thick plate product

Publications (1)

Publication Number Publication Date
JP2013136062A true JP2013136062A (en) 2013-07-11

Family

ID=48912270

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011287479A Pending JP2013136062A (en) 2011-12-28 2011-12-28 Tapping charge number decision-supporting device of thick plate product

Country Status (1)

Country Link
JP (1) JP2013136062A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112771461A (en) * 2018-09-26 2021-05-07 安东尼·罗伯特·贝克 Automatic production building wooden product

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112771461A (en) * 2018-09-26 2021-05-07 安东尼·罗伯特·贝克 Automatic production building wooden product

Similar Documents

Publication Publication Date Title
CN104217320B (en) The processing system and processing method of warehouse inventory circulation
US6684117B2 (en) Methods and systems for scheduling work
Xiao et al. A hybrid Lagrangian-simulated annealing-based heuristic for the parallel-machine capacitated lot-sizing and scheduling problem with sequence-dependent setup times
US11714678B2 (en) Smart scheduling method supporting process task volume splitting
JP5134601B2 (en) Production schedule creation device
US20110258087A1 (en) Analytics for setting up strategic inventory systems to handle small lot orders in the steel industry
JP6593080B2 (en) Steelmaking rolling planning device, steelmaking rolling planning method, and program
JP2008080395A (en) Heating furnace charging order determining method and apparatus for the determination
JP2019075016A (en) Inventory management apparatus and inventory management method
JP2014081778A (en) Scheduling method and scheduling program and scheduling device
CN112306661A (en) Task scheduling method and device, electronic equipment and readable storage medium
JP2009082985A (en) Method for deciding heating furnace charging order and rolling order, deciding apparatus therefor, steel plate manufacturing method, and program for deciding heating furnace charging order and rolling order
JP2013136062A (en) Tapping charge number decision-supporting device of thick plate product
JP5652069B2 (en) Optimal charge knitting device and optimal charge knitting method
JP5300708B2 (en) Production management apparatus, production management method and program
JP2002149223A (en) Production management support system
US8670856B2 (en) Algorithmic framework for the integrated optimization of hot strip mill and upstream molten metal operations for a large-scale steel manufacturing plant
CN116882885A (en) Warehouse processing method, device, system, equipment and medium
JP2011227605A (en) Schedule preparation method, schedule preparation program, and schedule preparation device
JP5803318B2 (en) Operation rule creation method and production logistics plan creation method
JP2021127242A (en) Method and device for managing inventory
JP2012221124A (en) Production plan creation system
He Improved Genetic Algorithm in Multi-objective Cargo Logistics Loading and Distribution
KR101839609B1 (en) Apparatus for distributing goods based on assorting box, method thereof, and computer recordable medium storing the method
JP2005259122A (en) Production plan forming method and its device

Legal Events

Date Code Title Description
RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20130716

RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20140326