JP2010276449A JP2009128720A JP2009128720A JP2010276449A JP 2010276449 A JP2010276449 A JP 2010276449A JP 2009128720 A JP2009128720 A JP 2009128720A JP 2009128720 A JP2009128720 A JP 2009128720A JP 2010276449 A JP2010276449 A JP 2010276449A
Authority
JP
Japan
Prior art keywords
plant
monitoring
information
monitoring item
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2009128720A
Other languages
Japanese (ja)
Inventor
Isaku Nakura
伊作 名倉
Satoshi Mizuno
諭 水野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP2009128720A priority Critical patent/JP2010276449A/en
Publication of JP2010276449A publication Critical patent/JP2010276449A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Monitoring And Testing Of Nuclear Reactors (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To achieve a plant operation surely observing safety regulations without depending on the experience and skill of an operator by supporting the selection and determination of monitoring items by the operator. <P>SOLUTION: A monitoring item automatic display system 10 includes: an input unit 22 for accepting an input operation by a user; a plant system standby evaluation unit 23 for determining for all the equipments in a plant 11 whether to standby or not, based on the safety regulation information on the plant monitoring, the plant information obtained from the plant 11, the equipment information of all the equipments composing the plant 11 and the process information indicating all the processes to be monitored in the plant 11; a safety regulation compliance evaluation unit 24 for determining whether the monitored process includes the safety regulations, by obtaining the determination by the plant system standby evaluation unit 23, the safety regulation information, the plant equipment information and process information, and the information of the monitored process; and a monitoring item display dial 13 equipped with a monitoring item display unit 25, which, if the safety regulation is complied, collectively displays the monitoring items required for monitoring the process. <P>COPYRIGHT: (C)2011,JPO&INPIT

Description

本発明は、プラントを監視する装置及び方法に係り、特に、プラント監視時の運転員の監視項目確認を支援するプラント監視項目自動表示システムに関する。   The present invention relates to an apparatus and a method for monitoring a plant, and more particularly, to a plant monitoring item automatic display system for assisting an operator to check monitoring items during plant monitoring.

一般に原子力発電設備は、安全性確保のために事業者自ら定めた保安規定があり、この保安規定に則って発電所は運営されている。この保安規定は、発電所運転中はもとより停止中である定期検査時においても発電所運営に関して規定している。原子力発電所を運転管理する中央制御室の運転員は、上記保安規定によって規定された状態を遵守するために多くの監視項目を確認する必要がある。   In general, nuclear power generation facilities have safety regulations established by operators for ensuring safety, and power plants are operated in accordance with these safety regulations. This safety regulation stipulates the operation of the power plant not only during power plant operation but also during periodic inspections that are stopped. The operator of the central control room that manages the operation of the nuclear power plant needs to confirm many monitoring items in order to comply with the conditions stipulated by the above safety regulations.

定期検査時における工事作業状況や機器状態等の入力から作業進捗を総合的に管理監視し、適切な発電所の運用を実現するためのプラント監視装置は、例えば、後述する特許文献1に記載される。   A plant monitoring apparatus for comprehensively managing and monitoring work progress from input of construction work status, equipment status, and the like at the time of periodic inspection and realizing appropriate power plant operation is described in, for example, Patent Document 1 described later. The

特開平9−6428号公報Japanese Patent Laid-Open No. 9-6428

しかしながら、原子力発電所の監視項目確認において、巨大システムである原子力発電所は、安全に運営するために莫大な監視項目があり、目的のための監視パラメータの選定・判定には運転員の経験・スキルが必要であった。また、特許文献1等に記載される従来のプラント監視装置は、中央制御室における運転員の監視項目確認を支援するものではなく、その監視項目は中央制御操作室に分散表示されるため、監視を行う重要な情報が強調されず誤認識、不認識となり得る。   However, in confirming the monitoring items of nuclear power plants, nuclear power plants, which are huge systems, have a huge number of monitoring items for safe operation. Skill was necessary. In addition, the conventional plant monitoring device described in Patent Document 1 does not support the operator's monitoring item confirmation in the central control room, and the monitoring items are distributed and displayed in the central control operation room. Important information that is performed is not emphasized and may be misrecognized or unrecognized.

特に、定期検査中においては、機器・計器等が点検のために使用できない場合があり、代替計器の選定・判定を運転員の経験・スキルに依存しているのが実情であった。更に定期検査中においては、日々発電所の状況が作業進捗等により変わるため、それに応じた監視項目の選定・判定をする必要があり、これについても運転員の経験・スキルに依存しているのが実情であった。これらの状況は、適切な監視におけるヒューマンエラーの要因を内在するとともにプラント安全性の低下が考えられる。   In particular, during regular inspections, equipment and instruments may not be used for inspection, and the actual situation is that the selection and judgment of alternative instruments depends on the experience and skills of the operator. Furthermore, during regular inspections, the status of the power plant changes daily depending on the progress of work, etc., so it is necessary to select and judge monitoring items accordingly, which also depends on the experience and skills of the operator. Was the actual situation. These situations have inherent human error factors in appropriate monitoring and can be considered to reduce plant safety.

本発明は上述した課題を解決するためになされたものであり、運転員の監視項目の選定及び判定を支援し、運転員の経験・スキルに依存することなく、確実に保安規定に則ったプラントの運営を実現するプラント監視項目自動表示システムを提供することを目的とする。   The present invention has been made to solve the above-described problems, supports the selection and determination of monitoring items by the operator, and reliably follows the safety regulations without depending on the experience and skills of the operator. It aims at providing the plant monitoring item automatic display system which realizes management of.

本発明に係るプラント監視項目自動表示システムは、上述した課題を解決するため、監視制御対象となるプラント前記プラントの時々刻々と変化するプラント情報を取得して監視に必要な監視項目を一括表示する監視項目表示盤を具備し、前記監視項目表示盤は、ユーザの入力操作を受け付け入力インターフェイスとしての役割を担う入力部と、予め読み出し可能に格納された前記プラントを監視する上で遵守が求められる保安規定の情報、前記プラントを構成する全機器についての機器情報及び前記プラントの監視すべき全ての工程を示す工程情報に基づいて前記プラントの全ての機器について待機であるか否かを判定するプラント系統待機評価部と、このプラント系統待機評価部が判定した前記プラントの全機器の待機/不待機の判定結果と、前記保安規定情報、前記プラントの機器情報及び前記プラントの工程情報と、前記入力部から前記全工程のうちの何れの工程であるかの情報とを取得し、前記入力部で指定された工程が前記保安規定を遵守しているか否かを判定する保安規定成立評価部と、この保安規定成立評価部が前記入力部で指定された工程が前記保安規定を遵守していると判断した場合、当該工程の監視に必要な監視項目を一括表示する監視項目表示部とを備えることを特徴とする。   In order to solve the above-described problems, the plant monitoring item automatic display system according to the present invention acquires plant information that changes every moment of the plant to be monitored and controlled, and collectively displays monitoring items necessary for monitoring. A monitoring item display panel is provided, and the monitoring item display panel is required to comply with an input unit that receives a user's input operation and plays a role as an input interface, and monitors the plant stored in a readable manner in advance. A plant that judges whether or not all the devices in the plant are in standby based on information on safety regulations, device information on all devices constituting the plant, and process information indicating all processes to be monitored by the plant System standby evaluation unit and standby / non-standby determination result of all the devices of the plant determined by the plant system standby evaluation unit And the safety regulation information, the equipment information of the plant and the process information of the plant, and information on which process of all the processes is obtained from the input unit, specified by the input unit A safety provision establishment evaluation unit that determines whether or not a process complies with the safety provisions, and the safety provision establishment evaluation part determines that the process specified in the input part complies with the safety provisions And a monitoring item display unit that collectively displays monitoring items necessary for monitoring the process.

本発明によれば、監視制御対象となるプラントのプラント情報を取得するとともに、取得したプラント情報、当該プラントを構成する機器、工程及び保安規定等を加味して保安規定を遵守するために必要な監視項目の情報を抽出し、抽出した監視項目を一つの装置内で自動的かつ一括して表示することができるので、運転員の監視項目の選定及び判定を支援することができる。また、一つの装置内で監視すべき全ての監視項目が一括表示されるので、運転員の経験・スキルに依存することなく、確実に保安規定に則ったプラントの運営を実現することができる。   According to the present invention, it is necessary to acquire the plant information of the plant to be monitored and controlled, and to comply with the safety regulations taking into account the acquired plant information, the equipment, the process and the safety regulations constituting the plant. Since information on monitoring items can be extracted and the extracted monitoring items can be displayed automatically and collectively in one apparatus, it is possible to assist the operator in selecting and determining monitoring items. In addition, since all the monitoring items to be monitored in one device are collectively displayed, it is possible to reliably realize the operation of the plant in accordance with the safety regulations without depending on the experience and skill of the operator.

本発明に係るプラント監視項目自動表示システムの概略を示す概略図。Schematic which shows the outline of the plant monitoring item automatic display system which concerns on this invention. 本発明に係るプラント監視項目自動表示システムの概略的な機能構成を示す機能ブロック図。The functional block diagram which shows the schematic functional structure of the plant monitoring item automatic display system which concerns on this invention. 本発明に係るプラント監視項目自動表示システムの処理内容を概略的に示した説明図。Explanatory drawing which showed schematically the processing content of the plant monitoring item automatic display system which concerns on this invention. 本発明に係るプラント監視項目自動表示システムにおける保安規定成立性評価部の処理内容を概略的に示した説明図。Explanatory drawing which showed schematically the processing content of the safety regulation establishment property evaluation part in the plant monitoring item automatic display system which concerns on this invention.

以下、本発明に係るプラント監視項目自動表示システムについて添付の図面を参照して説明する。   Hereinafter, a plant monitoring item automatic display system according to the present invention will be described with reference to the accompanying drawings.

図1は、本発明の実施形態に係るプラント監視項目自動表示システム10の動作概要を示す説明図である。   FIG. 1 is an explanatory diagram showing an outline of operation of the plant monitoring item automatic display system 10 according to the embodiment of the present invention.

図1に示されるプラント監視項目自動表示システム10は、監視制御対象となる例えば原子力等のプラント11において時々刻々と変化するプラント11の状態に応じた監視項目を自動的に一括で表示するディスプレイ12を内蔵した監視項目表示盤13を具備する。この監視項目表示盤13は、運転員の監視項目の選定及び判定を支援する観点から、プラント11を監視し制御する中央制御操作室に設置される。   A plant monitoring item automatic display system 10 shown in FIG. 1 automatically and collectively displays monitoring items corresponding to the state of the plant 11 that changes every moment in a plant 11 such as nuclear power, which is a monitoring control target. Is provided with a monitoring item display board 13. The monitoring item display panel 13 is installed in a central control operation room that monitors and controls the plant 11 from the viewpoint of supporting selection and determination of monitoring items by the operator.

ここで、監視項目表示盤13は、コンピュータ(図において省略)を有しており、例えば、所定のアクセス可能なこのコンピュータ等の記憶装置(記録部)に予め格納されるプラント監視項目自動表示プログラム(以下、プログラムを「PG」と省略する。)15と協働して、監視制御対象となるプラント11の監視項目を抽出する機能(以下、「監視項目抽出機能」と称する。)と、抽出した監視項目に従って取得しているプラント状態情報を抽出して表示する機能(以下、「監視項目表示機能」と称する。)とを実現している。   Here, the monitoring item display board 13 has a computer (not shown in the figure). For example, a plant monitoring item automatic display program stored in advance in a predetermined accessible storage device (recording unit) such as a computer. (Hereinafter, the program is abbreviated as “PG”.) In cooperation with 15, a function for extracting the monitoring items of the plant 11 to be monitored and controlled (hereinafter referred to as “monitoring item extraction function”), and extraction. A function of extracting and displaying plant state information acquired according to the monitored items (hereinafter referred to as “monitored item display function”) is realized.

尚、図1に示される監視項目表示盤13は、プラントを監視し制御する制御装置(監視制御卓)と独立して構成されているが、一体的に構成されていても良い。また、監視項目表示盤13では、監視項目抽出機能及び監視項目表示機能が実現されていると説明したが、監視項目抽出機能及び監視項目表示機能を外部の他の装置で実現し、外部装置から受け取った情報に従ってディスプレイ12に表示すべき内容を表示する構成であっても構わない。   The monitoring item display panel 13 shown in FIG. 1 is configured independently of a control device (monitoring control console) that monitors and controls the plant, but may be configured integrally. Further, the monitoring item display panel 13 has been described as having the monitoring item extraction function and the monitoring item display function. However, the monitoring item extraction function and the monitoring item display function are realized by other external devices, and the external device can It may be configured to display contents to be displayed on the display 12 according to the received information.

図2は、本発明の実施形態に係るプラント監視項目自動表示システム10の機能的な構成を示す機能ブロック図である。   FIG. 2 is a functional block diagram showing a functional configuration of the plant monitoring item automatic display system 10 according to the embodiment of the present invention.

図2に示されるプラント監視項目自動表示システム10は、図1に示される監視項目表示盤13に内蔵されるコンピュータをプラント監視項目自動表示システム10として機能させたものであり、インターフェイス部(以下、「I/F部」と称する。)21、入力部22、プラント系統待機評価部23、保安規定成立評価部24、監視項目表示部25、記録部26、監視項目表示選択部27、ITV処理部28、警報発報部29及び制御部30を具備する。   A plant monitoring item automatic display system 10 shown in FIG. 2 is obtained by causing a computer built in the monitoring item display board 13 shown in FIG. (Referred to as “I / F unit”) 21, input unit 22, plant system standby evaluation unit 23, safety regulation establishment evaluation unit 24, monitoring item display unit 25, recording unit 26, monitoring item display selection unit 27, ITV processing unit 28, an alarm issuing unit 29 and a control unit 30.

I/F部21は、プラント11側からプラント11の各系統の機器設備の状態やパラメータを含むプラント情報を常時取得する機能を有する。プラント監視項目自動表示システム10は、I/F部21からプラント情報を入手する。   The I / F unit 21 has a function of constantly acquiring plant information including the state of equipment facilities and parameters of each system of the plant 11 from the plant 11 side. The plant monitoring item automatic display system 10 obtains plant information from the I / F unit 21.

入力部22は、ユーザが必要な情報を入力するための入力インターフェイスとしての役割を担う。入力部22はユーザがどの様な入力操作を行ったかを示す情報(以下、「入力操作情報」と称する。)を制御部30へ送る。   The input unit 22 serves as an input interface for a user to input necessary information. The input unit 22 sends information indicating what input operation the user has performed (hereinafter referred to as “input operation information”) to the control unit 30.

プラント系統待機評価部23は、例えば、記録部26等の所定のアクセス可能な記憶領域に格納されるデータベース(以下、データベースを「DB」と省略する。)からプラント機器情報及びプラント機器のアイソレーション・点検情報を取得し、取得した情報に基づきプラント11の各系統が待機か否(不待機)かを判定する。   The plant system standby evaluation unit 23, for example, isolates plant equipment information and plant equipment from a database (hereinafter referred to as “DB”) stored in a predetermined accessible storage area such as the recording unit 26. -Inspection information is acquired and it is determined whether each system | strain of the plant 11 is standby (non-standby) based on the acquired information.

保安規定成立評価部24は、予め読み出し可能に格納され監視上遵守が求められる保安規定の情報と監視する工程とを対応付けた情報を保有しており、任意の工程が指定されると、指定された工程が保安規定に整合しているかを判断する。判断した結果、保安規定に整合している工程については工程成立と判定し、当該工程の監視において必要となる監視機器とこの監視機器が監視する監視項目の情報を抽出し、抽出した監視項目情報を監視項目表示部25へ送る。   The safety regulation establishment evaluation unit 24 stores information that associates safety regulation information that is stored in advance so as to be readable and that is required to be observed for monitoring, and a process to be monitored, and is designated when an arbitrary process is designated. Judge whether the completed process is consistent with the safety regulations. As a result of the determination, it is determined that the process conforms to the safety regulations is established, the monitoring device necessary for monitoring the process and the monitoring item information monitored by the monitoring device are extracted, and the extracted monitoring item information Is sent to the monitoring item display unit 25.

一方、保安規定成立評価部24が、保安規定に整合していない工程については工程不成立と判定し、工程不成立の情報を制御部30へ送る。この時、制御部30は、工程不成立の情報に基づき、警報発報部29が警報音を出力するように制御する。   On the other hand, the safety rule establishment evaluation unit 24 determines that a process that does not conform to the safety rule is a process failure, and sends information on the process failure to the control unit 30. At this time, the control unit 30 performs control so that the alarm issuing unit 29 outputs an alarm sound based on the process failure information.

監視項目表示部25は、保安規定成立評価部24から出力される監視項目情報と監視項目表示選択部27から受け取る監視項目非表示情報とに基づいて、監視項目を表示する機能を有する。監視項目表示部25は、例えば、図1に示されるディスプレイ12等の表示機能を有する要素に出力し、当該要素に表示すべき監視項目を表示させる。   The monitoring item display unit 25 has a function of displaying a monitoring item based on the monitoring item information output from the security rule establishment evaluation unit 24 and the monitoring item non-display information received from the monitoring item display selection unit 27. For example, the monitoring item display unit 25 outputs to an element having a display function such as the display 12 illustrated in FIG. 1 and displays the monitoring item to be displayed on the element.

記録部26は、プラント監視項目自動表示PG15、プラント機器DB33及び工程DB34等の情報をPG、DB及びファイル等の所定の形式で、記憶し格納することができる記憶領域である。   The recording unit 26 is a storage area that can store and store information such as the plant monitoring item automatic display PG15, the plant equipment DB 33, and the process DB 34 in a predetermined format such as PG, DB, and file.

監視項目表示選択部27は、表示すべき監視項目について、ユーザの要求があれば、表示しない旨を選択する機能及び表示しない監視項目についての情報を監視項目表示部25に提供する機能を有する。すなわち、監視項目表示選択部27は、入力部22を介して本来表示すべき監視項目であっても表示しない旨のユーザ要求を受け付け、当該要求に基づいて、監視項目表示部25に表示しない監視項目の情報(監視項目非表示情報)を監視項目表示部25へ送る。   The monitoring item display selection unit 27 has a function of selecting not to display a monitoring item to be displayed if there is a user request, and a function of providing the monitoring item display unit 25 with information on a monitoring item not to be displayed. In other words, the monitoring item display selection unit 27 accepts a user request indicating that even a monitoring item that should be originally displayed is not displayed via the input unit 22, and based on the request, monitoring that is not displayed on the monitoring item display unit 25 Item information (monitor item non-display information) is sent to the monitor item display unit 25.

ITV処理部28は、いわゆるITV(Industrial TeleVision:監視モニタ)としての機能を有する。すなわち、ITV処理部28は、監視カメラ(図において省略)を通じて取得した画像を表示する機能を有する。ITV処理部28が取得した監視カメラからの画像は、表示機能を有する構成要素に出力され表示される。例えば、図1に示されるプラント監視項目自動表示システム10では、ITV機能を「入」とした場合、ディスプレイ12に監視カメラからの画像を表示することができる。   The ITV processing unit 28 has a function as a so-called ITV (Industrial TeleVision). That is, the ITV processing unit 28 has a function of displaying an image acquired through a monitoring camera (not shown in the figure). The image from the monitoring camera acquired by the ITV processing unit 28 is output and displayed on a component having a display function. For example, in the plant monitoring item automatic display system 10 shown in FIG. 1, when the ITV function is set to “ON”, an image from the monitoring camera can be displayed on the display 12.

尚、プラント監視項目自動表示システム10において、監視カメラのチャンネル数は一つに限定されるものではなく、二以上であっても良い。監視カメラのチャンネル数が二以上の場合、入力操作によって、ディスプレイ12に表示させる画像出力元の監視カメラを適宜切り替えるように構成することもできる。   In the plant monitoring item automatic display system 10, the number of channels of the monitoring camera is not limited to one, but may be two or more. When the number of channels of the surveillance camera is two or more, the surveillance camera of the image output source to be displayed on the display 12 can be appropriately switched by an input operation.

警報発報部29は、保安規定成立評価部24が保安規定が成立しない(保安規定不成立)と判断した場合に、警報を発報(警報音を出力)する機能を有する。警報発報部29は、保安規定成立評価部24が保安規定不成立と判断した場合、制御部30から警報発令の制御信号を受信し、警報音を出力する。   The alarm notification unit 29 has a function of issuing an alarm (outputting an alarm sound) when the safety rule establishment evaluation unit 24 determines that the safety rule is not established (security rule is not established). When the safety regulation establishment evaluation unit 24 determines that the safety regulation is not established, the alarm reporting unit 29 receives a control signal for issuing a warning from the control unit 30 and outputs an alarm sound.

制御部30は、プラント監視項目自動表示システム10の各処理部、すなわち、I/F部21、入力部22、プラント系統待機評価部23、保安規定成立評価部24、監視項目表示部25、記録部26、監視項目表示選択部27、ITV処理部28及び警報発報部29を制御する機能を有し、制御部30を介して、I/F部21、入力部22、プラント系統待機評価部23、保安規定成立評価部24、監視項目表示部25、記録部26、監視項目表示選択部27、ITV処理部28及び警報発報部29の間を相互に情報を授受できるように構成される。   The control unit 30 includes each processing unit of the plant monitoring item automatic display system 10, that is, an I / F unit 21, an input unit 22, a plant system standby evaluation unit 23, a safety regulation establishment evaluation unit 24, a monitoring item display unit 25, and a record. Unit 26, monitoring item display selection unit 27, ITV processing unit 28, and alarm reporting unit 29. The I / F unit 21, the input unit 22, and the plant system standby evaluation unit are provided via the control unit 30. 23, the safety regulation establishment evaluation unit 24, the monitoring item display unit 25, the recording unit 26, the monitoring item display selection unit 27, the ITV processing unit 28 and the alarm reporting unit 29 are configured to be able to exchange information with each other. .

記録部26に格納されるプラント機器DB33は、プラント11の全ての機器の種別、名称、番号、駆動方式等の機器情報をデータベース化したものである。プラント機器DB33が格納し保有する機器情報は、制御部30を介してプラント系統待機評価部23や保安規定成立評価部24等の他の処理部が参照して利用することができる。   The plant equipment DB 33 stored in the recording unit 26 is a database of equipment information such as types, names, numbers, and drive methods of all equipment in the plant 11. The equipment information stored and held in the plant equipment DB 33 can be used by referring to other processing units such as the plant system standby evaluation unit 23 and the safety regulation establishment evaluation unit 24 via the control unit 30.

工程DB34は、プラント11の各系統及び各機器のアイソレーション時期、点検時期、単体試験時期、試運転時期等を規定した工程情報をデータベース化したものである。工程DB34が格納し保有する工程情報は、制御部30を介してプラント系統待機評価部23や保安規定成立評価部24等の他の処理部が参照して利用することができる。   The process DB 34 is a database of process information defining the isolation time, inspection time, unit test time, trial operation time, etc. of each system and each device of the plant 11. The process information stored and held in the process DB 34 can be used by referring to other processing units such as the plant system standby evaluation unit 23 and the safety regulation establishment evaluation unit 24 via the control unit 30.

図3は、本発明に係るプラント監視項目自動表示システム10の処理内容を概略的に示した説明図である。   FIG. 3 is an explanatory diagram schematically showing the processing contents of the plant monitoring item automatic display system 10 according to the present invention.

プラント監視項目自動表示システム10では、図3に示されるように、まず、取得したプラント情報、プラント11の全ての機器についての機器情報及びプラント11の工程情報に基づいてプラント系統待機評価部23がプラント11の各系統の待機・不待機を判定する。そして、この判定結果、プラント11の全ての機器についての機器情報及びプラント11の工程情報に基づいて保安規定成立評価部24が評価対象の工程が保安規定に従っているかを判定する。続いて、工程が保安規定を遵守している場合、その工程の監視に必要な監視項目を一目でわかるように、監視項目を監視項目表示部25に一括表示する。尚、工程が保安規定を遵守していない場合、警報発報部29は、制御部30を介して保安規定不成立の情報を受け取り、警報音を出力することができる。   In the plant monitoring item automatic display system 10, as shown in FIG. 3, first, the plant system standby evaluation unit 23 is based on the acquired plant information, device information about all devices in the plant 11, and process information of the plant 11. The standby / non-standby of each system of the plant 11 is determined. And based on this determination result, the equipment information about all the equipment of the plant 11, and the process information of the plant 11, the safety regulation establishment evaluation unit 24 judges whether the process to be evaluated complies with the safety regulation. Subsequently, when the process complies with the safety regulations, the monitoring items are collectively displayed on the monitoring item display unit 25 so that the monitoring items necessary for monitoring the process can be seen at a glance. If the process does not comply with the safety regulations, the alarm reporting unit 29 can receive information on the failure to establish the safety regulations via the control unit 30 and output an alarm sound.

さらに、プラント監視項目自動表示システム10の保安規定成立性評価部24の処理内容について、もう少し詳細に説明する。   Furthermore, the processing content of the safety regulation feasibility evaluation unit 24 of the plant monitoring item automatic display system 10 will be described in a little more detail.

図4は、プラント監視項目自動表示システム10における保安規定成立性評価部24の処理内容を概略的に示した説明図である。   FIG. 4 is an explanatory diagram schematically showing the processing contents of the safety regulation feasibility evaluation unit 24 in the plant monitoring item automatic display system 10.

図4に示されるように、保安規定成立性評価部24は、予め監視上遵守が求められる保安規定の情報と監視する工程とを対応付けた情報を保有しており、任意の工程が指定された場合に指定された工程が保安規定に整合しているかを判断する工程条件抽出要素36と、工程条件抽出要素36で指定された工程が保安規定に整合していると判断した場合、当該工程の監視において必要となる監視機器とこの監視機器が監視する監視項目の情報を抽出し、抽出した監視項目情報を制御部30を経由して監視項目表示部25へ送る監視項目情報抽出要素37とを備える。   As shown in FIG. 4, the safety regulation feasibility evaluation unit 24 holds information in which safety regulation information that is required to be observed in advance is associated with monitoring processes, and an arbitrary process is designated. If it is determined that the process specified by the process condition extraction element 36 is consistent with the safety regulations, the process condition extraction element 36 for determining whether the process designated by the process conditions is consistent with the safety regulations. A monitoring item information extraction element 37 that extracts information on a monitoring device necessary for monitoring and monitoring item information to be monitored by the monitoring device, and sends the extracted monitoring item information to the monitoring item display unit 25 via the control unit 30; Is provided.

例えば、図4に示される事例として、定期検査中でプラント11の一例である原子炉の状態が燃料移動前の場合に、「原子炉水位がオーバーフロー水位付近であること」、「原子炉停止時冷却系が運転中であること」等が保安規定で定められている場合を想定する。まず、ユーザから入力部22(図2)を介して図4に示される事例の工程についての情報が入力されると、保安規定成立性評価部24は、工程が定期検査における燃料移動前の状態である旨を受け取り認識する。   For example, as an example shown in FIG. 4, when the state of a nuclear reactor that is an example of the plant 11 is before fuel transfer during periodic inspection, “the reactor water level is near the overflow water level”, “when the reactor is shut down” Assume that the safety regulations stipulate that the cooling system is in operation. First, when information about the process of the case shown in FIG. 4 is input from the user via the input unit 22 (FIG. 2), the safety regulation feasibility evaluation unit 24 checks the state before the fuel movement in the periodic inspection. It is received and recognized.

続いて、保安規定成立性評価部24において、工程条件抽出要素36は、認識した工程と対応付けられている保安規定、すなわち、「原子炉水位がオーバーフロー水位付近であること」、「原子炉停止時冷却系が運転中であること」等を抽出し、これが成立するための条件としては、原子炉水位監視系及び原子炉停止時冷却系がインサービスであることが工程成立条件となる。   Subsequently, in the safety regulation feasibility evaluation unit 24, the process condition extraction element 36 determines the safety regulation associated with the recognized process, that is, “the reactor water level is near the overflow water level”, “reactor shutdown” The conditions for extracting the fact that the time cooling system is in operation and the like and establishing this are the conditions for establishing the process that the reactor water level monitoring system and the reactor shutdown cooling system are in service.

工程条件抽出要素36が原子炉水位監視系及び原子炉停止時冷却系がインサービスであることの工程成立条件を抽出すると、監視項目情報抽出要素37は、工程条件抽出要素36が抽出した条件に基づいて当該工程の監視において必要となる原子炉水位監視系の監視機器及び原子炉停止時冷却系の監視機器と、プラント11の各系統の待機・不待機の判定結果とを取得して、監視すべき監視項目を抽出し、抽出した監視項目情報を監視項目表示部25へ送る。監視項目表示部25では、監視項目情報に基づいて監視項目が一括表示される。   When the process condition extraction element 36 extracts the process establishment condition that the reactor water level monitoring system and the reactor shutdown cooling system are in service, the monitoring item information extraction element 37 sets the conditions extracted by the process condition extraction element 36 to Based on this, the monitoring equipment for the reactor water level monitoring system and the monitoring equipment for the cooling system at the time of shutdown of the reactor and the judgment result of standby / non-standby for each system of the plant 11 are obtained and monitored. The monitoring item to be extracted is extracted, and the extracted monitoring item information is sent to the monitoring item display unit 25. In the monitoring item display unit 25, monitoring items are collectively displayed based on the monitoring item information.

このように構成されるプラント監視項目自動表示システム10によれば、まず、監視制御対象となるプラント11のプラント情報、プラント11の全ての機器についての機器情報、アイソレーション・点検情報及び工程情報を取得し、プラント11の各系統の待機・不待機を判定し、続いて、初期情報として現在の工程が監視すべき工程中の何れの工程であるかの情報、プラント11の各系統の待機・不待機の判定結果、プラント11の全ての機器についての機器情報及びプラント11の工程情報に基づいて評価対象の工程が保安規定に従っているかを判定し、工程が保安規定を遵守している場合、その工程の監視に必要な監視項目を一目でわかるように、監視項目を一つの装置内(図1に示されるプラント監視項目自動表示システム10の場合、監視項目表示盤13)に一括表示することができる。   According to the plant monitoring item automatic display system 10 configured as described above, first, plant information of the plant 11 to be monitored and controlled, device information about all devices of the plant 11, isolation / inspection information, and process information are obtained. Obtaining, determining standby / non-standby of each system of the plant 11, and subsequently, as initial information, information on which process is the current process to be monitored, standby / As a result of non-standby determination, it is determined whether the process to be evaluated complies with the safety regulations based on the equipment information about all equipment in the plant 11 and the process information of the plant 11, and if the process complies with the safety regulations, In order to understand the monitoring items necessary for process monitoring at a glance, the monitoring items are stored in one apparatus (of the plant monitoring item automatic display system 10 shown in FIG. 1). If, it can be collectively displayed on the monitor item display panel 13).

この結果、現在、監視すべき項目が監視項目表示盤13のディスプレイ12(監視項目表示部25)に一括して表示されるので、運転員の監視項目の選定及び判定を支援することができる。また、監視すべき全ての監視項目がディスプレイ12(監視項目表示部25)に一括表示されるので、運転員の経験・スキルに依存することなく、確実に保安規定に則ったプラントの運営を実現することができる。一方、プラント監視項目自動表示システム10において、評価対象の工程が保安規定に従っているかを判定し工程が保安規定を遵守していない場合、保安規定不成立の情報を受け取り、警報音を出力することができる。   As a result, the items to be monitored are collectively displayed on the display 12 (monitoring item display unit 25) of the monitoring item display panel 13, so that the operator can assist in selecting and determining the monitoring items. In addition, since all the monitoring items to be monitored are collectively displayed on the display 12 (monitoring item display unit 25), the operation of the plant is surely performed according to the safety regulations without depending on the experience and skills of the operator. can do. On the other hand, in the plant monitoring item automatic display system 10, if the process to be evaluated complies with the safety regulations and the process does not comply with the safety regulations, the information on the failure of the safety regulations can be received and an alarm sound can be output. .

さらに、プラント系統待機評価部23が、プラント機器情報及びプラント機器のアイソレーション・点検情報を取得し、取得した情報に基づきプラント11の各系統が待機か否(不待機)かを判定することができるので、アイソレーション及び点検実施中の機器を除いたインサービス中の機器に対する監視項目のみを抽出した監視項目情報をディスプレイ12(監視項目表示部25)へ送ることができる。   Furthermore, the plant system standby evaluation unit 23 acquires plant equipment information and plant equipment isolation / inspection information, and determines whether each system of the plant 11 is on standby (non-standby) based on the acquired information. Therefore, it is possible to send the monitoring item information obtained by extracting only the monitoring items for the in-service devices excluding the devices under isolation and inspection to the display 12 (monitoring item display unit 25).

例えば、定期検査工程のある段階(原子炉状態)において、炉水温度を3つの温度計の内、1つ以上の温度計で監視することが保安規定により規定されていて、かつ、3つの温度計の内、1つの温度計がアイソレーション中の場合は、インサービス中の2つの温度計の温度のみが監視項目情報としてディスプレイ12へ送信される。これにより、メンテナンス等でアウトサービス中の計器を運転員が誤って読み取ることを防止できる。   For example, in a certain stage of the periodic inspection process (reactor state), the reactor water temperature is monitored by one or more thermometers among three thermometers, and the three regulations When one of the meters is in isolation, only the temperatures of the two in-service thermometers are transmitted to the display 12 as monitoring item information. As a result, it is possible to prevent the operator from erroneously reading the meter that is out of service due to maintenance or the like.

さらにまた、ユーザの要求に応じて表示すべき監視項目のうち表示させない監視項目については監視項目表示部25に表示させない機能を有する監視項目表示選択部27を具備するので、例えば、監視する工程によっては、表示すべき監視項目が多数あって表示が見にくい等の事情に応じてユーザが適宜に監視項目の表示と非表示とを自由に選択設定することができる。   Furthermore, the monitoring item display selection unit 27 having a function of not displaying the monitoring items to be displayed among the monitoring items to be displayed in response to the user's request on the monitoring item display unit 25 is provided. The user can select and set the display and non-display of monitoring items as appropriate according to circumstances such as there are many monitoring items to be displayed and it is difficult to see the display.

また、プラント11が例えば原子力発電プラントである場合、その安全管理要領においてITVで確認が規定されていることがある。この様な場合、監視カメラ(図において省略)を通じて取得した画像を表示する機能を有するITV処理部28を具備しているので、ディスプレイ12に監視カメラからの画像を表示することができる。   Moreover, when the plant 11 is a nuclear power plant, for example, confirmation may be prescribed | regulated by ITV in the safety management point. In such a case, since the ITV processing unit 28 having a function of displaying an image acquired through a monitoring camera (not shown in the drawing) is provided, an image from the monitoring camera can be displayed on the display 12.

尚、本発明は上記の各実施形態そのままに限定されるものではなく、実施段階ではその要旨を逸脱しない範囲で構成要素を変形して具体化しても良い。例えば、実施形態に示される全構成要素から幾つかの必須でない構成要素を削除したり、必要に応じて出願時の周知・慣用技術を新たな構成要素として適宜付加したりしても良い。   Note that the present invention is not limited to the above-described embodiments as they are, and may be embodied by modifying constituent elements without departing from the scope of the invention in the implementation stage. For example, some non-essential constituent elements may be deleted from all the constituent elements shown in the embodiment, or the known / conventional techniques at the time of filing may be appropriately added as new constituent elements as necessary.

例えば、図2に示されるプラント監視項目自動表示システム10の監視項目表示選択部27、ITV処理部28及び警報発令部29は、プラント監視項目自動表示システム10の任意的構成要素であって、これらを具備しない構成を採用しても良い。   For example, the monitoring item display selection unit 27, the ITV processing unit 28, and the alarm issuing unit 29 of the plant monitoring item automatic display system 10 shown in FIG. 2 are optional components of the plant monitoring item automatic display system 10, and these You may employ | adopt the structure which does not comprise.

また、図1に示されるプラント監視項目自動表示システム10では、図2に示される処理部21,22,23,24,25,26,27,28,29,30を一の装置(監視項目表示盤)13が有する構成になっているが、このうちの一部の機能を監視項目表示盤13以外の他の装置に持たせても構わない。例えば、監視項目表示部25を監視項目表示盤13のディスプレイ12とは別の設けられる表示装置として構成しても良い。   Moreover, in the plant monitoring item automatic display system 10 shown in FIG. 1, the processing units 21, 22, 23, 24, 25, 26, 27, 28, 29, and 30 shown in FIG. The panel) 13 has a configuration, but a part of these functions may be provided to a device other than the monitoring item display panel 13. For example, the monitoring item display unit 25 may be configured as a display device provided separately from the display 12 of the monitoring item display board 13.

10 プラント監視項目自動表示システム
11 プラント
12 ディスプレイ
13 監視項目表示盤
15 プラント監視項目自動表示プログラム
21 I/F部
22 入力部
23 プラント系統待機評価部
24 保安規定成立性評価部
25 監視項目表示部
26 記録部
27 監視項目表示選択部
28 ITV処理部
29 警報発令部
30 制御部
33 プラント機器DB
34 工程DB
36 工程条件抽出要素
37 監視項目情報抽出要素
DESCRIPTION OF SYMBOLS 10 Plant monitoring item automatic display system 11 Plant 12 Display 13 Monitoring item display board 15 Plant monitoring item automatic display program 21 I / F part 22 Input part 23 Plant system standby evaluation part 24 Security regulation feasibility evaluation part 25 Monitoring item display part 26 Recording unit 27 Monitoring item display selection unit 28 ITV processing unit 29 Alarm issuing unit 30 Control unit 33 Plant equipment DB
34 Process DB
36 Process condition extraction element 37 Monitoring item information extraction element

Claims (6)

監視制御対象となるプラント前記プラントの時々刻々と変化するプラント情報を取得して監視に必要な監視項目を一括表示する監視項目表示盤を具備し、前記監視項目表示盤は、
ユーザの入力操作を受け付け入力インターフェイスとしての役割を担う入力部と、
予め読み出し可能に格納された前記プラントを監視する上で遵守が求められる保安規定の情報、前記プラントを構成する全機器についての機器情報及び前記プラントの監視すべき全ての工程を示す工程情報に基づいて前記プラントの全ての機器について待機であるか否かを判定するプラント系統待機評価部と、
このプラント系統待機評価部が判定した前記プラントの全機器の待機/不待機の判定結果と、前記保安規定情報、前記プラントの機器情報及び前記プラントの工程情報と、前記入力部から前記全工程のうちの何れの工程であるかの情報とを取得し、前記入力部で指定された工程が前記保安規定を遵守しているか否かを判定する保安規定成立評価部と、
この保安規定成立評価部が前記入力部で指定された工程が前記保安規定を遵守していると判断した場合、当該工程の監視に必要な監視項目を一括表示する監視項目表示部とを備えることを特徴とする監視項目自動表示システム。
The monitoring item display panel is provided with a monitoring item display panel that obtains plant information that changes every moment of the plant to be monitored and controlled and collectively displays the monitoring items necessary for monitoring,
An input unit that accepts user input operations and serves as an input interface;
Based on safety regulation information required to be observed in monitoring the plant stored in a readable manner, device information about all devices constituting the plant, and process information indicating all processes to be monitored by the plant A plant system standby evaluation unit that determines whether or not all devices in the plant are in standby,
The plant system standby evaluation unit determines the standby / non-standby determination result of all the devices in the plant, the safety regulation information, the plant device information and the plant process information, and the input unit Information on which of these processes is acquired, and a safety rule establishment evaluation unit that determines whether or not the process specified in the input unit complies with the security rule,
A monitoring item display unit that collectively displays monitoring items necessary for monitoring the process when the safety rule establishment evaluation unit determines that the process specified in the input unit complies with the security rule; Monitoring item automatic display system characterized by
前記保安規定成立性評価部は、プラント系統待機評価部が判定した前記プラントの全機器の待機/不待機の判定結果に基づいて、インサービス中の機器に関する監視項目に限定して前記保安規定を遵守しているか否かを判定することを特徴とする請求項1に記載の監視項目自動表示システム。 The safety regulation feasibility evaluation unit limits the security regulation to monitoring items related to in-service devices based on the standby / non-standby determination result of all the devices in the plant determined by the plant system standby evaluation unit. The monitoring item automatic display system according to claim 1, wherein it is determined whether or not compliance is made. 前記保安規定成立性評価部は、前記保安規定の情報と前記監視すべき全工程とを対応付けた情報を保有しており、任意の工程が指定された場合に当該指定された工程が保安規定に整合しているかを判断する工程条件抽出要素と、
前記工程条件抽出要素で指定された工程が保安規定に整合していると判断した場合、当該工程の監視において必要となる監視機器とこの監視機器が監視する監視項目の情報を抽出する監視項目情報抽出要素とを備えることを特徴とする請求項1又は2に記載の監視項目自動表示システム。
The security provision feasibility evaluation unit holds information associating the safety provision information with all the processes to be monitored, and when an arbitrary process is designated, the designated process is designated as a safety provision. A process condition extraction element for judging whether or not
Monitoring item information for extracting information on monitoring devices necessary for monitoring the process and monitoring items monitored by the monitoring device when it is determined that the process specified by the process condition extraction element is consistent with the safety regulations. The monitoring item automatic display system according to claim 1, further comprising an extraction element.
前記入力部からユーザの選択により本来は前記監視項目表示部に表示すべき監視項目を表示させないように選択する機能を提供する監視項目表示選択部をさらに備えたことを特徴とする請求項1乃至3の何れか1項に記載の監視項目自動表示システム。 The monitoring item display selection part which provides the function to select not to display the monitoring item which should be originally displayed on the said monitoring item display part by a user's selection from the said input part is further provided. 4. The monitoring item automatic display system according to any one of 3 above. 前記監視項目表示部及び他の表示装置の少なくとも何れかに、予め設置される監視カメラを通じて取得した画像を表示させる機能を有するITV処理部をさらに備えることを特徴とする請求項1乃至4の何れか1項に記載の監視項目自動表示システム。 5. The ITV processing unit according to claim 1, further comprising an ITV processing unit having a function of displaying an image acquired through a monitoring camera installed in advance on at least one of the monitoring item display unit and another display device. The monitoring item automatic display system according to claim 1. 前記保安規定成立評価部が保安規定が成立しないと判断した場合に、警報を発報するように構成された警報発報部をさらに備えることを特徴とする請求項1乃至5の何れか1項に記載の監視項目自動表示システム。 6. The alarm notification unit configured to issue an alarm when the safety rule establishment evaluation unit determines that the safety rule is not established, 6. Monitoring item automatic display system described in 1.
JP2009128720A 2009-05-28 2009-05-28 Plant monitoring item automatic display system Pending JP2010276449A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009128720A JP2010276449A (en) 2009-05-28 2009-05-28 Plant monitoring item automatic display system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009128720A JP2010276449A (en) 2009-05-28 2009-05-28 Plant monitoring item automatic display system

Publications (1)

Publication Number Publication Date
JP2010276449A true JP2010276449A (en) 2010-12-09

Family

ID=43423551

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009128720A Pending JP2010276449A (en) 2009-05-28 2009-05-28 Plant monitoring item automatic display system

Country Status (1)

Country Link
JP (1) JP2010276449A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020061096A (en) * 2018-10-12 2020-04-16 三菱重工業株式会社 Power-generating plant operation management support device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020061096A (en) * 2018-10-12 2020-04-16 三菱重工業株式会社 Power-generating plant operation management support device
JP7112934B2 (en) 2018-10-12 2022-08-04 三菱重工業株式会社 Power plant operation management support device

Similar Documents

Publication Publication Date Title
KR20160063381A (en) Mobile application interactive user interface for a remote computing device monitoring a test device
JP2012038044A (en) Test device and test method of monitoring control system
US11423494B2 (en) Plant assistance assessment system and plant assistance assessment method
KR102069442B1 (en) The operation support and monitoring system in the nuclear power plant
JP2007042014A (en) System and method for monitoring plant condition
JP2010213770A (en) Individual game machine-monitoring method
KR101594413B1 (en) Real-time monitoring system of station control apparatus and monitoring method thereof
CN102262402A (en) A method and apparatus for providing industrial plant information
JP2010276449A (en) Plant monitoring item automatic display system
JP2021060852A (en) Alarm issuing device and alarm issuing method
JP2008191821A (en) Input test device
JP2010206985A (en) Power system monitoring controller
CN103903311A (en) Intelligent machine room inspection method
JP2008140235A (en) Plant monitoring system and plant monitoring method
JP2016194920A (en) Emergency plant situation display and emergency plant situation display method
JP2010204924A (en) Monitoring control system and monitoring method for maintenance apparatus
KR20200069726A (en) Application method and system of mobile computerized procedural system interface for field operators
JP2018066755A (en) Disassembly method of nuclear plant control system and nuclear plant control system
ITBO20130218A1 (en) AUTOMATED SYSTEM AND METHOD FOR THE MAINTENANCE MANAGEMENT OF FUNCTIONS FOR FUN OR PARTIES PARKS
KR20140060970A (en) System and method for preventing loss of voltage of safety bus in nuclear power plants
JP2005060067A (en) Elevator remote failure monitoring system
JP4945521B2 (en) Automatic hard copy device
JP6264694B2 (en) Nuclear plant control system dismantling method, nuclear plant control system
JP2016025749A (en) Support information provide system, monitoring controller, operation support method and program
JP2016170560A (en) Monitoring control system

Legal Events

Date Code Title Description
RD01 Notification of change of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7421

Effective date: 20111218