JP2010095941A - Installation method for precast pile - Google Patents
Installation method for precast pile Download PDFInfo
- Publication number
- JP2010095941A JP2010095941A JP2008268924A JP2008268924A JP2010095941A JP 2010095941 A JP2010095941 A JP 2010095941A JP 2008268924 A JP2008268924 A JP 2008268924A JP 2008268924 A JP2008268924 A JP 2008268924A JP 2010095941 A JP2010095941 A JP 2010095941A
- Authority
- JP
- Japan
- Prior art keywords
- layer
- pile
- contaminated
- ground
- excavation hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
Description
本発明は、汚染層とその下方に非透水層とを備えた地盤における既成杭の設置方法に関する。 The present invention relates to a method for installing an existing pile in a ground provided with a contaminated layer and a non-permeable layer below the contaminated layer.
従来より、例えば、図4に示すように、地表から下方に向かって、汚染土11を含んでなる汚染層10と、粘土層などの非透水性の非透水層20と、支持層30と、を備える地盤1において杭を打設する場合には、地盤1を掘削して掘削孔を形成する際に、汚染層10の汚染土11が支持層30に拡散しないように、オールケーシング工法(例えば、非特許文献1参照)を用いて場所打ち杭を構築することが行われている。 Conventionally, for example, as shown in FIG. 4, from the ground surface downward, a contaminated layer 10 including the contaminated soil 11, a non-permeable layer 20 such as a clay layer, a support layer 30, When the pile is driven in the ground 1 provided with the all-casing method (for example, so that the contaminated soil 11 of the contaminated layer 10 does not diffuse into the support layer 30 when excavating the ground 1 to form the excavation hole, A cast-in-place pile is constructed using Non-Patent Document 1).
すなわち、図5Aに示すように、ケーシング210を下端が非透水層20内もしくはそれよりも深い位置まで到達するように地盤1に挿入し、図5Bに示すようにケーシング210内をバケット220で掘削し、下端が支持層に到達するまで掘削孔221を削孔する。次に、図5Cに示すように、掘削孔221内に鉄筋かご222を挿入する。次に、図5Dに示すように、掘削孔221内にトレミー管を挿入し、ケーシング210を引き上げながら掘削孔221内にコンクリート222を打設する。そして、打設したコンクリート222が硬化することで場所打ち杭223を構築することができる。かかる工法によれば、ケーシング210内を掘削するため、汚染層10の汚染土11が掘削孔221内を通じて支持層30に落下することや、汚染土11に含まれる汚染物質が溶け出した汚染水が支持層30まで流れ出ることを防ぐことができ、汚染物質の拡散を防止できる。
ところで、近年、施工コストを削減するため、杭基礎として既成杭を用いることが広く行われており、既成杭を汚染層が含まれる地盤においても用いることが望まれる。既成杭を設置する工法としては、現在、オーガー機を用いたプレボーリング工法が広く用いられており、オールケーシング工法と同様のケーシングを備えたオーガー機も存在する。しかし、このようなオーガー機は、下端が粘土層に到達した状態でケーシングを保持しながら、支持層まで掘削を行うことができない。このため、汚染層を備えた地盤において既成杭を用いることができなかった。 By the way, in recent years, in order to reduce the construction cost, it is widely used to use a built-up pile as a pile foundation, and it is desired that the built-up pile is used also in the ground including a contaminated layer. Currently, the pre-boring method using an auger machine is widely used as a method for installing a prefabricated pile, and there is also an auger machine equipped with a casing similar to the all-casing method. However, such an auger machine cannot perform excavation to the support layer while holding the casing with the lower end reaching the clay layer. For this reason, the existing pile could not be used in the ground with the contaminated layer.
本発明は、上記の問題に鑑みなされたものであり、その目的は、汚染層を有する地盤において既成杭を設置することができるようにすることである。 This invention is made | formed in view of said problem, The objective is to be able to install an existing pile in the ground which has a contaminated layer.
本発明の既成杭の設置方法は、汚染層と、当該汚染層の下方に位置する非透水層と、前記非透水層の下方に位置する支持層を備えた地盤に既成杭を設置する方法であって、 前記非透水層の上面よりも下方の深さ位置まで前記地盤を掘削し、掘削した部分の土砂を貧配合のセメント系材料に置換する土砂置換ステップと、前記置換したセメント系材料が硬化した後、当該硬化したセメント系材料を貫通し、下端が前記支持層に到達するような掘削孔を形成する削孔ステップと、前記掘削孔内に既成杭を設置する杭設置ステップと、を備えることを特徴とする。 The installation method of the existing pile of this invention is a method of installing an existing pile on the ground provided with the contaminated layer, the non-permeable layer located below the contaminated layer, and the support layer located below the non-permeable layer. And excavating the ground to a position below the upper surface of the non-permeable layer, replacing the excavated portion of earth and sand with poor cementitious material, and the substituted cementitious material comprising: After hardening, a drilling step that forms a drilling hole that penetrates the hardened cementitious material and the lower end reaches the support layer, and a pile installation step that installs a prefabricated pile in the drilling hole, It is characterized by providing.
上記の方法において、前記削孔ステップでは、全旋回掘削機により前記地盤を掘削してもよい。 In the above method, in the drilling step, the ground may be excavated by a full turning excavator.
また、本発明の既成杭の設置方法は、汚染層と、当該汚染層の下方に位置する非透水層と、前記非透水層の下方に位置する支持層を備えた地盤に既成杭を設置する方法であって、 前記汚染層を貫通し、下端が前記非透水層の上面よりも下方まで到達するソイルセメント柱を構築するソイルセメント柱構築ステップと、前記ソイルセメント柱を貫通し、下端が前記支持層に到達するように掘削孔を形成する削孔ステップと、前記掘削孔内に既成杭を設置する杭設置ステップと、を備えることを特徴とする。 Moreover, the installation method of the existing pile of this invention installs an existing pile in the ground provided with the contaminated layer, the non-permeable layer located under the said contaminated layer, and the support layer located under the said non-permeable layer. A soil cement pillar construction step for constructing a soil cement pillar that penetrates through the contaminated layer and has a lower end reaching below the upper surface of the impermeable layer; and passes through the soil cement pillar, the lower end of the soil cement pillar. It comprises a drilling step for forming a drilling hole so as to reach the support layer, and a pile installation step for installing an existing pile in the drilling hole.
本発明によれば、下端が非透水層に到達するように泥土モルタル又はソイルセメントからなる柱体を構築し、この柱体内に掘削孔を形成して、掘削孔内に既成杭を打設することとしたため、汚染層の汚染物質が支持層に落下することを防止でき、汚染物質が拡散するのを防止できる。 According to the present invention, a column body made of mud mortar or soil cement is constructed so that the lower end reaches the non-permeable layer, a drill hole is formed in the column body, and an existing pile is placed in the drill hole. Therefore, it is possible to prevent the contaminants in the contaminated layer from falling on the support layer and to prevent the contaminants from diffusing.
<第一実施形態>
以下、本発明の既成杭の設置方法の第一実施形態を図面を参照しながら詳細に説明する。
図1は、本実施形態の既成杭の設置方法により設置された杭を示す鉛直断面図である。同図に示すように、既成杭の設置される地盤1は、表面から下方に向かって、汚染層10、非透水層20、支持層30を備える。
<First embodiment>
Hereinafter, the first embodiment of the installation method of the existing pile of this invention is described in detail, referring drawings.
FIG. 1 is a vertical cross-sectional view showing a pile installed by the installation method for an existing pile according to this embodiment. As shown in the figure, the ground 1 on which the existing piles are installed includes a contaminated layer 10, a non-permeable layer 20, and a support layer 30 from the surface downward.
汚染層10は、少なくとも一部に汚染物質を含有する汚染土11が含まれた地盤である。また、汚染層10内には、例えば、岩盤や既存杭などの地中障害12が存在している。 The contaminated layer 10 is a ground containing at least a contaminated soil 11 containing a contaminant. In the contaminated layer 10, there are underground faults 12 such as bedrock and existing piles.
非透水層20は、例えば、粘土層などの非透水性を有する地層である。非透水層20が汚染層10と支持層30との間に介在することにより、汚染層10内の汚染物質が地下水に溶け出したとしても、汚染物質が溶け出した地下水は非透水層20により汚染層10内に保持され、支持層30まで到達することがない。 The non-permeable layer 20 is a non-permeable formation such as a clay layer, for example. Since the non-permeable layer 20 is interposed between the contaminated layer 10 and the support layer 30, even if the contaminant in the contaminated layer 10 is dissolved in the ground water, the ground water from which the contaminant is dissolved out is It is held in the contamination layer 10 and does not reach the support layer 30.
本実施形態の既成杭の設置方法は、このように汚染層10を含む地盤において、汚染層10の汚染土11に含まれる汚染物質が支持層30に拡散することなく、下端が支持層30に到達するように既成杭70を設置するための方法である。 In the ground pile including the contaminated layer 10 as described above, the lower end of the prefabricated pile according to the present embodiment is not diffused into the support layer 30 and the lower end is in the support layer 30. This is a method for installing the prefabricated pile 70 to reach.
以下、本実施形態の既成杭の設置方法を図2A〜図2Eを参照しながら説明する。
まず、図2Aに示すように、全旋回掘削機100により下端が非透水層20に到達するまで第1の掘削孔40を削孔し、この部分の土砂を掘削する。この際、汚染層10内に地中障害12が存在するような場合であっても、全旋回掘削機100は地中障害12を切削する性能を有するため、地盤1を掘削して地中障害12を掘り起こすことなく第1の掘削孔40を削孔することができる。
Hereinafter, the installation method of the ready-made pile of this embodiment is demonstrated, referring FIG. 2A-FIG. 2E.
First, as shown in FIG. 2A, the first excavation hole 40 is drilled by the all-turn excavator 100 until the lower end reaches the impermeable layer 20, and the earth and sand in this portion is excavated. At this time, even if the underground fault 12 exists in the contaminated layer 10, the all-turn excavator 100 has the ability to cut the underground fault 12. The first excavation hole 40 can be drilled without digging up 12.
次に、図2Bに示すように、地盤1を削孔することにより第1の掘削孔40内に発生した掘削土を、硬化した状態での圧縮強度5〜10kg/cm2程度である泥土モルタル41と置換する。置換した泥土モルタル41が硬化することにより、汚染層10を貫通し、下端が非透水層20に到達するような、硬化した泥土モルタル41からなる柱体42が構築されることとなる。 Next, as shown in FIG. 2B, mud mortar having a compressive strength of about 5 to 10 kg / cm 2 when the excavated soil generated in the first excavated hole 40 by drilling the ground 1 is hardened. Replace with 41. When the substituted mud mortar 41 is hardened, a pillar body 42 made of the hardened mud mortar 41 is constructed so as to penetrate the contaminated layer 10 and reach the non-permeable layer 20 at the lower end.
泥土モルタル41が硬化した後、プレボーリング工法により既成杭を設置する。すなわち、まず、図2Cに示すように、アースオーガ101により柱体42を貫通し、下端が支持層30に到達するように第2の掘削孔50を掘削する。この際、柱体42は下端が非透水層20内に到達しており、この柱体42を貫通するように第2の掘削孔50を削孔するため、汚染層10内の汚染土11が支持層30に落下するのを防止できる。また、汚染層10の下方に非透水層20が位置し、また、泥土モルタル41が硬化すると遮水性を有し、硬化した泥土モルタル41からなる柱体42の下端が非透水層20内に到達しているため、汚染土11内の汚染物質が溶け出した地下水が第2の掘削孔50内を通じて、支持層30に流れ込むのを防止できる。 After the mud mortar 41 is hardened, a pre-made pile is installed by the pre-boring method. That is, first, as shown in FIG. 2C, the second excavation hole 50 is excavated so that the lower end reaches the support layer 30 through the column 42 by the earth auger 101. At this time, the column body 42 has a lower end reaching the impermeable layer 20, and the second excavation hole 50 is drilled so as to penetrate the column body 42. It can prevent falling to the support layer 30. Further, the impermeable layer 20 is located below the contaminated layer 10, and has a water shielding property when the mud mortar 41 is cured, and the lower end of the column body 42 made of the cured mud mortar 41 reaches the impermeable layer 20. Therefore, it is possible to prevent the groundwater from which the pollutant in the contaminated soil 11 has melted from flowing into the support layer 30 through the second excavation hole 50.
次に、図2Dに示すように、アースオーガ101の先端より第2の掘削孔50内にセメントミルク60を注入しながら、第2の掘削孔50からアースオーガ101を引き上げる。 Next, as shown in FIG. 2D, the earth auger 101 is pulled up from the second excavation hole 50 while pouring the cement milk 60 into the second excavation hole 50 from the tip of the earth auger 101.
次に、図2Eに示すように、揚重機102により第2の掘削孔50内に既成杭70を挿入する。そして、第2の掘削孔50内のセメントミルク60が硬化することで、既成杭70が地盤1に定着され、既成杭70の設置が完了する。 Next, as shown in FIG. 2E, the pre-made pile 70 is inserted into the second excavation hole 50 by the lifting machine 102. And since the cement milk 60 in the 2nd excavation hole 50 hardens | cures, the existing pile 70 will be fixed to the ground 1, and installation of the existing pile 70 will be completed.
本実施形態によれば、下端が非透水層20に到達するように泥土モルタル41を打設し、この泥土モルタル41が硬化してなる柱体42を貫通するように、第2の掘削孔50を削孔することとしたため、第2の掘削孔50を通じて、汚染土11や、汚染土11から汚染物質が溶け出した地下水が支持層30に到達するのを防止した状態で既成杭70の設置を行うことができる。 According to the present embodiment, the mud mortar 41 is placed so that the lower end reaches the water impermeable layer 20, and the second excavation hole 50 is so penetrated that the mud mortar 41 is cured. Therefore, the prefabricated pile 70 is installed in a state in which the contaminated soil 11 and the groundwater from which the contaminants have dissolved from the contaminated soil 11 are prevented from reaching the support layer 30 through the second excavation hole 50. It can be performed.
また、全旋回掘削機100を用いて第1の掘削孔40を削孔するため、地中に地中障害12があるような場合でも、地中障害12を切削して第1の掘削孔40を削孔することができる。 Further, since the first excavation hole 40 is drilled using the all-round excavator 100, even when there is an underground fault 12 in the ground, the underground excavation 12 is cut and the first excavation hole 40 is cut. Can be drilled.
なお、本実施形態では、硬化した泥土モルタル41により柱体42を構成することとしたが、これに限らず、アースオーガ101により削孔可能な強度(圧縮強度5〜10kg/cm2程度)である貧配合のセメント系材料であれば、泥土モルタル41に代えて用いることができる。 In this embodiment, the pillar body 42 is composed of the hardened mud mortar 41. However, the pillar body 42 is not limited to this, and has a strength capable of drilling with the earth auger 101 (compression strength of about 5 to 10 kg / cm 2 ). Any poor cement-based material can be used in place of the mud mortar 41.
また、本実施形態では、下端が非透水層20に到達するような柱体42を構築するものとしたが、これに限らず、柱体42の下端はさらに深い位置まで延びてもよく、要するに、柱体42の下端が非透水層20の上面よりも深い位置まで到達していればよい。 In the present embodiment, the column body 42 whose bottom end reaches the water impermeable layer 20 is constructed. However, the present invention is not limited to this, and the bottom end of the column body 42 may extend to a deeper position. The lower end of the column body 42 only needs to reach a position deeper than the upper surface of the water impermeable layer 20.
<第二実施形態>
以下、本発明の既成杭の設置方法の第二実施形態を図面を参照しながら説明する。第1実施形態では、下端が非透水層20に到達する第1の掘削孔40を形成し、この第1の掘削孔40内に泥土モルタル41を打設することとしたが、本実施形態では、これに変えて下端が非透水層20に到達するようにソイルセメント柱を構築する。なお、本実施形態における汚染層10の内部に地中障害は存在しないものとする。
<Second embodiment>
Hereinafter, 2nd embodiment of the installation method of the ready-made pile of this invention is described, referring drawings. In the first embodiment, the first excavation hole 40 whose lower end reaches the impermeable layer 20 is formed, and the mud mortar 41 is placed in the first excavation hole 40. In the present embodiment, Instead, the soil cement pillar is constructed so that the lower end reaches the water impermeable layer 20. In the present embodiment, it is assumed that there is no underground fault inside the contaminated layer 10.
図3A〜図3Eは、本実施形態の既成杭の設置方法を説明するための図である。
まず、図3Aに示すように、例えば、3軸オーガー機などの掘削機103により地盤1に下端が非透水層に到達するような第1の掘削孔140を形成するとともに、地盤1を掘削することで第1の掘削孔140内に発生した掘削残土にセメントミルクを注入し、掘削残土とセメントミルクとを混合攪拌して第1の掘削孔140内にソイルセメント141を形成し、下端が非透水層20に到達するようなソイルセメント柱142を構築する。なお、本実施形態のように3軸オーガー機を用いる場合には、図3Aの左右方向に複数列にわたって掘削を行うことで、平面視で略正方形状のソイルセメント柱142を構築することができる。
Drawing 3A-Drawing 3E are figures for explaining the installation method of the existing pile of this embodiment.
First, as shown in FIG. 3A, for example, the excavator 103 such as a three-axis auger machine forms the first excavation hole 140 in the ground 1 so that the lower end reaches the non-permeable layer, and excavates the ground 1. As a result, cement milk is injected into the excavated residual soil generated in the first excavation hole 140, and the excavation residual soil and the cement milk are mixed and stirred to form the soil cement 141 in the first excavation hole 140, and the lower end is not A soil cement pillar 142 that reaches the water permeable layer 20 is constructed. In addition, when using a 3 axis | shaft auger machine like this embodiment, the substantially square-shaped soil cement pillar 142 can be constructed | assembled by digging over several rows in the left-right direction of FIG. 3A. .
次に、図3Bに示すように、アースオーガ101によりソイルセメント柱142を貫通し、下端が支持層30まで到達するような第2の掘削孔50を削孔する。この際、第2の掘削孔50と汚染層10との間にソイルセメント柱142が介在するため、第1実施形態と同様に、汚染層10の汚染土11が第2の掘削孔50を通って支持層30に到達したり、汚染土11から汚染物質が溶け出した地下水が第2の掘削孔50を通って支持層30に流れ込んだりするのを防止できる。 Next, as shown in FIG. 3B, the earth auger 101 penetrates the soil cement pillar 142 and drills the second excavation hole 50 so that the lower end reaches the support layer 30. At this time, since the soil cement pillar 142 is interposed between the second excavation hole 50 and the contaminated layer 10, the contaminated soil 11 of the contaminated layer 10 passes through the second excavation hole 50 as in the first embodiment. Thus, it is possible to prevent the groundwater from reaching the support layer 30 or from the contaminated soil 11 from flowing out the contaminated soil from flowing into the support layer 30 through the second excavation hole 50.
ここで、第2の掘削孔50を削孔する際に、ソイルセメント柱142を削孔することにより発生したソイルセメント141が第2の掘削孔50内に落下してしまう。これらソイルセメント141は、第2の掘削孔50を掘削する際に発生した掘削残土にセメントミルクを混合攪拌して形成してなるため、ソイルセメント141に汚染土11が含まれている。しかしながら、ソイルセメント141が汚染物質を内部に包み込んだ状態でと一体に硬化しているため、汚染物質が支持層30へ流出するのを防止できる。 Here, when the second excavation hole 50 is drilled, the soil cement 141 generated by drilling the soil cement pillar 142 falls into the second excavation hole 50. Since these soil cements 141 are formed by mixing and stirring cement milk with the excavation residual soil generated when the second excavation hole 50 is excavated, the soil cement 141 contains the contaminated soil 11. However, since the soil cement 141 is hardened integrally with the state in which the contaminant is encapsulated therein, it is possible to prevent the contaminant from flowing out to the support layer 30.
次に、図3Cに示すように、アースオーガ101の先端より第2の掘削孔50内にセメントミルク60を注入しながら、第2の掘削孔50からアースオーガ101を引き上げる。 Next, as shown in FIG. 3C, the earth auger 101 is pulled up from the second excavation hole 50 while pouring cement milk 60 into the second excavation hole 50 from the tip of the earth auger 101.
次に、図3Dに示すように、第2の掘削孔50内に既成杭70を挿入する。そして、第2の掘削孔50内のセメントミルク60が硬化することで、図3Eに示すように、既成杭70が地盤1に定着されることとなる。 Next, as shown in FIG. 3D, the ready-made pile 70 is inserted into the second excavation hole 50. And the cement milk 60 in the 2nd excavation hole 50 will harden | cure, and as shown to FIG. 3E, the ready-made pile 70 will be fixed to the ground 1. FIG.
本実施形態によれば、第1実施形態と同様の効果が得られ、さらに、汚染層10の汚染濃度が低い場合には、第2の掘削孔50を削孔する際に発生したソイルセメント141からなる掘削土を産業廃棄物として処分することができる。このため、従来のように掘削土を汚染土として処分する場合に比べて、処分費用を削減することができる。 According to this embodiment, the same effect as that of the first embodiment can be obtained. Furthermore, when the contamination concentration of the contaminated layer 10 is low, the soil cement 141 generated when the second excavation hole 50 is drilled. Can be disposed of as industrial waste. For this reason, compared with the case where excavated soil is disposed as contaminated soil as in the prior art, disposal costs can be reduced.
なお、本実施形態では、下端が非透水層20に到達するようなソイルセメント柱142を構築するものとしたが、これに限らず、下端がさらに深い位置まで到達するようなソイルセメント柱142を掘削してもよく、要するに、ソイルセメント柱142の下端が非透水層20の上面よりも深い位置まで到達していればよい。 In the present embodiment, the soil cement column 142 whose bottom end reaches the water impermeable layer 20 is constructed. However, the present invention is not limited to this, and the soil cement column 142 whose bottom end reaches a deeper position is used. Excavation may be performed. In short, it is only necessary that the lower end of the soil cement column 142 reaches a position deeper than the upper surface of the impermeable layer 20.
また、上記の各実施形態では、非透水層20が汚染層10の直下にある場合について説明したが、これに限らず、汚染層10よりも深い位置に非透水層20が存在する場合であれば、非透水層20に下端が到達するように、泥土モルタル41を打設する又はソイルセメント141を構築すれば、本発明を適用できる。 In each of the above embodiments, the case where the impermeable layer 20 is directly below the contaminated layer 10 has been described. However, the present invention is not limited to this, and the impermeable layer 20 may be present at a position deeper than the contaminated layer 10. For example, the present invention can be applied if the mud mortar 41 is placed or the soil cement 141 is constructed so that the lower end reaches the impermeable layer 20.
また、上記の各実施形態では、汚染層10が地盤1の表面にある場合について説明したが、これに限らず、汚染層10が地中にある場合であっても、本発明を適用することができる。 Moreover, although each said embodiment demonstrated the case where the contaminated layer 10 exists in the surface of the ground 1, it is not restricted to this, Even if it is a case where the contaminated layer 10 exists in the ground, this invention is applied. Can do.
1 地盤
10 汚染層
11 汚染土
12 地中障害
20 非透水層
30 支持層
40 第1の掘削孔
41 泥土モルタル
50 第2の掘削孔
60 セメントミルク
70 既成杭
100 全旋回掘削機
101 アースオーガ
102 揚重機
103 掘削機
140 掘削孔
141 ソイルセメント
142 柱
1 ground 10 contaminated layer 11 contaminated soil 12 underground fault 20 impermeable layer 30 support layer 40 first excavation hole 41 mud mortar 50 second excavation hole 60 cement milk 70 ready-made pile 100 full swirl excavator 101 earth auger 102 lifting Heavy machine 103 Excavator 140 Excavation hole 141 Soil cement 142 Column
Claims (3)
前記非透水層の上面よりも下方の深さ位置まで前記地盤を掘削し、掘削した部分の土砂を貧配合のセメント系材料に置換する土砂置換ステップと、
前記置換したセメント系材料が硬化した後、当該硬化したセメント系材料を貫通し、下端が前記支持層に到達するような掘削孔を形成する削孔ステップと、
前記掘削孔内に既成杭を設置する杭設置ステップと、を備えることを特徴とする既成杭の設置方法。 It is a method of installing a prefabricated pile on a ground having a contaminated layer, a non-permeable layer located below the contaminated layer, and a support layer located below the non-permeable layer,
Excavating the ground to a depth position below the upper surface of the non-permeable layer, and exchanging the earth and sand of the excavated portion with poor cementitious material,
Drilling step of forming a drilling hole that penetrates through the cured cementitious material and the lower end reaches the support layer after the substituted cementitious material is cured;
A pile installation step of installing a pre-made pile in the excavation hole.
前記削孔ステップでは、全旋回掘削機により前記地盤を掘削することを特徴とする既成杭の設置方法。 It is the installation method of the ready-made pile of Claim 1,
In the drilling step, the ground is excavated by a full-spinning excavator, and the method for installing an existing pile is characterized.
前記汚染層を貫通し、下端が前記非透水層の上面よりも下方まで到達するソイルセメント柱を構築するソイルセメント柱構築ステップと、
前記ソイルセメント柱を貫通し、下端が前記支持層に到達するように掘削孔を形成する削孔ステップと、
前記掘削孔内に既成杭を設置する杭設置ステップと、を備えることを特徴とする既成杭の設置方法。 It is a method of installing a prefabricated pile on a ground having a contaminated layer, a non-permeable layer located below the contaminated layer, and a support layer located below the non-permeable layer,
A soil cement pillar construction step for constructing a soil cement pillar that penetrates the contaminated layer and has a lower end reaching below the upper surface of the impermeable layer;
Drilling step that penetrates the soil cement pillar and forms a drilling hole so that the lower end reaches the support layer;
A pile installation step of installing a pre-made pile in the excavation hole.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2008268924A JP5157814B2 (en) | 2008-10-17 | 2008-10-17 | Installation method of ready-made piles |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2008268924A JP5157814B2 (en) | 2008-10-17 | 2008-10-17 | Installation method of ready-made piles |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2010095941A true JP2010095941A (en) | 2010-04-30 |
JP5157814B2 JP5157814B2 (en) | 2013-03-06 |
Family
ID=42257815
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2008268924A Active JP5157814B2 (en) | 2008-10-17 | 2008-10-17 | Installation method of ready-made piles |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP5157814B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014125788A (en) * | 2012-12-26 | 2014-07-07 | Kajima Corp | Foundation pile construction method |
JP2014173337A (en) * | 2013-03-08 | 2014-09-22 | Ohbayashi Corp | Construction method of earth retaining wall |
CN105507321A (en) * | 2015-12-16 | 2016-04-20 | 上海市城市建设设计研究总院 | High-efficiency pile sinking process for existing precast pile |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH03257215A (en) * | 1990-03-07 | 1991-11-15 | Matsuzawa Kiko:Kk | Pile constructing method |
JPH11336060A (en) * | 1998-05-28 | 1999-12-07 | Taisei Corp | Pile construction method |
JP2000045313A (en) * | 1998-07-27 | 2000-02-15 | Kubota Corp | Ground water permeation method making use of soil cement column strip earth retaining wall |
JP2005213804A (en) * | 2004-01-28 | 2005-08-11 | Yahagi Construction Co Ltd | Construction method for countermeasure against spread of contamination |
JP2005290871A (en) * | 2004-03-31 | 2005-10-20 | Yukitake Shioi | Foundation structure |
-
2008
- 2008-10-17 JP JP2008268924A patent/JP5157814B2/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH03257215A (en) * | 1990-03-07 | 1991-11-15 | Matsuzawa Kiko:Kk | Pile constructing method |
JPH11336060A (en) * | 1998-05-28 | 1999-12-07 | Taisei Corp | Pile construction method |
JP2000045313A (en) * | 1998-07-27 | 2000-02-15 | Kubota Corp | Ground water permeation method making use of soil cement column strip earth retaining wall |
JP2005213804A (en) * | 2004-01-28 | 2005-08-11 | Yahagi Construction Co Ltd | Construction method for countermeasure against spread of contamination |
JP2005290871A (en) * | 2004-03-31 | 2005-10-20 | Yukitake Shioi | Foundation structure |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2014125788A (en) * | 2012-12-26 | 2014-07-07 | Kajima Corp | Foundation pile construction method |
JP2014173337A (en) * | 2013-03-08 | 2014-09-22 | Ohbayashi Corp | Construction method of earth retaining wall |
CN105507321A (en) * | 2015-12-16 | 2016-04-20 | 上海市城市建设设计研究总院 | High-efficiency pile sinking process for existing precast pile |
Also Published As
Publication number | Publication date |
---|---|
JP5157814B2 (en) | 2013-03-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100964796B1 (en) | Method for constructing the steel pipe-concrete composite pile structurized of burying and unifying into the bedrock, and a pile construction | |
JP2008231810A (en) | Underground structure construction method | |
KR101045625B1 (en) | Construction method of retaining wall using cast-in-place pile | |
KR101021915B1 (en) | A method for constructing cut-off temporary structure for sheathing work | |
JP5157814B2 (en) | Installation method of ready-made piles | |
KR102223856B1 (en) | Foundation structure of waste landfill site and construction method thereof | |
JP2003147782A (en) | Foundation structure for constructing new building on existing basement and its construction method | |
JP5075090B2 (en) | Cast-in-place pile construction method and cast-in-place pile | |
JP2010101090A (en) | Water-stop structure, construction method therefor, and method of performing water stop of anchor penetration part of seepage control member | |
JP2017521583A (en) | Forming elements in the ground by in situ mixing of geopolymer and soil | |
JP2007308951A (en) | Method of constructing outer peripheral column by inverted construction method | |
JP2007046343A (en) | Liquefaction preventive construction method of ground just under existing building | |
JP2005282043A (en) | Earth retaining wall reinforcing method | |
KR101021913B1 (en) | A method for constructing cut-off temporary structure for sheathing work | |
JP4313070B2 (en) | Sludge treatment method in ready-made pile construction and ground reinforcement structure obtained by the treatment method | |
JP5634036B2 (en) | Method for constructing retaining wall, method for constructing pile, retaining wall, pile | |
JP2012241471A (en) | Pile construction method | |
JPH05106222A (en) | Embedding method for wooden pile | |
KR20030087288A (en) | Executon method of wall for intercepting contamination zone of using steel sheet pile | |
JP2005146756A (en) | Earth retaining impervious wall construction method and earth retaining impervious wall formed by it | |
JP3787536B2 (en) | Foundation construction method | |
JP2874906B2 (en) | Shaft construction method | |
JP2012237159A (en) | Pile construction method | |
JP4336828B2 (en) | Substructure | |
JP2006348637A (en) | Construction method of cast-in-place pile and cast-in-place pile structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20110920 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20120808 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20120821 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20120914 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20121113 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20121126 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 5157814 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20151221 Year of fee payment: 3 |