JP2009052206A JP2007217369A JP2007217369A JP2009052206A JP 2009052206 A JP2009052206 A JP 2009052206A JP 2007217369 A JP2007217369 A JP 2007217369A JP 2007217369 A JP2007217369 A JP 2007217369A JP 2009052206 A JP2009052206 A JP 2009052206A
Authority
JP
Japan
Prior art keywords
block
blocks
suspension
water
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2007217369A
Other languages
Japanese (ja)
Other versions
JP4994153B2 (en
Inventor
Kazuyuki Kojima
和之 児島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUIKO GIKEN KK
Original Assignee
SUIKO GIKEN KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUIKO GIKEN KK filed Critical SUIKO GIKEN KK
Priority to JP2007217369A priority Critical patent/JP4994153B2/en
Publication of JP2009052206A publication Critical patent/JP2009052206A/en
Application granted granted Critical
Publication of JP4994153B2 publication Critical patent/JP4994153B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a block construction method for accurately and safely performing underwater block installation work. <P>SOLUTION: A wire 20 locked to a wire locking part of a support member 11 of a block hanging implement 10 is hooked to a hook 22a of a lifting member 22 of a crane 60 to allow the whole block hanging implement 10 to be lifted and moved. A plurality of blocks 30 are connected one by one to a plurality of hanging members 21 of the block hanging implement 10, and then the lifting member 22 of the crane 60 is lifted to lift the plurality of blocks 30 together with the block hanging implement 10. The crane 60 is then operated to move the plurality of blocks 30 up to the water surface W1 of an installation predetermined face P, and then the lifting member 22 is delivered to lower the block hanging implement 10 gradually into the water. The plurality of blocks 30 can thereby be installed in accurate positions on the installation scheduled face P in the water W. <P>COPYRIGHT: (C)2009,JPO&INPIT

Description

本発明は、河川堤防の護岸工事等において、水中の設置予定面にブロックを設置する技術に関する。   The present invention relates to a technique for installing a block on an underwater installation planned surface in a river bank revetment or the like.

河川堤防の護岸工事等におけるブロック施工法としては、従来、施工区域である護岸前面に仮仕切工を設け、護岸と仮仕切工との間に滞留する水をポンプで仮仕切工の外へ排出し(水替え)、当該施工区域内を陸上と同じ状態に保ちながらブロック設置等の作業を行うというのが一般的である。   As a block construction method for river bank revetment, etc., conventionally, a temporary partition was installed in front of the bank, which is the construction area, and the water remaining between the bank and the temporary partition was pumped out of the temporary partition. However, it is common to perform work such as installing blocks while keeping the construction area in the same state as the land.

一方、河川堤防や海岸等の浸食を防止するため、従来、様々な方式の護岸工事が施工されているが、近年は浸食防止のみを目的とした護岸工事は敬遠され、優れた浸食防止機能を備え、且つ、自然環境との調和性に優れた護岸技術が求められている。このような要請に応えるべく、本出願人は、相互に連結可能な連結部を有する複数のブロックを使用した護岸技術を提案している(例えば、特許文献1,2。)。   On the other hand, in order to prevent erosion of river dikes and coasts, various types of revetment work have been carried out in the past, but in recent years revetment work only for the purpose of erosion prevention has been avoided and has an excellent erosion prevention function. There is a need for revetment technology that is both equipped and excellent in harmony with the natural environment. In order to respond to such a request, the present applicant has proposed a revetment technique using a plurality of blocks having connecting portions that can be connected to each other (for example, Patent Documents 1 and 2).

特許文献1,2に記載された護岸技術を施工することにより、曲がりの多い河川堤防等においても、浸食を有効に防止するとともに自然環境や水辺の生態系との調和性にも優れた護岸構造を構築することができる。   By implementing the revetment technology described in Patent Documents 1 and 2, the revetment structure that effectively prevents erosion and has excellent harmony with the natural environment and waterside ecosystems even in river banks with many bends Can be built.

特開平8−3962号公報JP-A-8-3962 特開平11−315527号公報JP 11-315527 A

従来のブロック施工法の場合、施工現場の地形や水流等の状況により仮仕切工の設置が極めて困難であったり、「水替え」に起因して現場周辺の井戸水が涸れたりすることがある。また、「水替え」が施工現場周辺の地域や水域の生態系へ及ぼす影響も無視できないことがある。さらに、仮仕切工の設置、撤収等には多大な資材と労力が費やされている。このため、「水替え」の不要なブロック施工法の要請が高まっている。   In the case of the conventional block construction method, it may be extremely difficult to install a temporary partition due to the topography and water flow of the construction site, or the well water around the site may drown due to “water change”. In addition, the effect of “water change” on the area around the construction site and the ecosystem in the water area may not be ignored. Furthermore, a great deal of materials and labor are spent on installing and removing temporary partitions. For this reason, there is an increasing demand for block construction methods that do not require “water replacement”.

一方、特許文献1,2に記載されたコンクリートブロックを用いて護岸工事を施工する場合、特許文献1の図4に記載された吊具5を利用してコンクリートブロックの敷設作業が行われている。この吊具5は、I形鋼材等で形成された支持枠41と、支持枠41に所定間隔で設けられた複数のブロック挟着具42と、を備えている。コンクリートブロック2の重心部を複数のブロック挟着具でそれぞれ把持し、ワイヤを介して吊具5全体をクレーン車によって吊り上げて搬送することにより、複数のコンクリートブロック2を施工現場に設置することができる。   On the other hand, when the revetment work is performed using the concrete blocks described in Patent Documents 1 and 2, the concrete block is laid using the lifting tool 5 illustrated in FIG. 4 of Patent Document 1. . The hanger 5 includes a support frame 41 made of I-shaped steel or the like, and a plurality of block clamping tools 42 provided on the support frame 41 at predetermined intervals. It is possible to install the plurality of concrete blocks 2 at the construction site by gripping the center of gravity of the concrete block 2 with a plurality of block sandwiching tools, and lifting and transporting the entire suspension 5 by a crane truck via a wire. it can.

吊具5に設けられた複数のブロック挟着具42はそれぞれコンクリートブロック2を動かないように把持する開閉機構を備えているため、強固な把持機能を有する点において優れている。しかしながら、コンクリートブロック2の設置予定面に凹凸等があって、吊り下げた複数のコンクリートブロック2が略水平に同時接地しないような場合、傾斜姿勢で接地したコンクリートブロック2は重力の作用で低い方へ傾こうとする。このとき、コンクリートブロックに生じた傾動力がブロック挟着具42に作用すると、ブロック挟着具42の開放動作に支障が生じ、接地後のコンクリートブロック2からの挟着具42の離脱が困難となる。   Since the plurality of block sandwiching tools 42 provided on the hanger 5 are each provided with an opening / closing mechanism for gripping the concrete block 2 so as not to move, it is excellent in that it has a strong gripping function. However, if the concrete block 2 is uneven and the surface of the concrete block 2 is to be installed, and the suspended concrete blocks 2 do not touch the ground horizontally at the same time, the concrete block 2 that is grounded in an inclined position is lower due to the action of gravity. Try to lean on. At this time, if the tilting force generated in the concrete block acts on the block clamping tool 42, the opening operation of the block clamping tool 42 is hindered, and it is difficult to remove the clamping tool 42 from the concrete block 2 after grounding. Become.

従って、陸上から凹凸の状況などを目視確認できない水中の接地予定面に、吊具5を用いてコンクリートブロック2を設置するのは極めて困難である。また、吊具5で把持した複数のコンクリートブロック2が水中に没すると、それぞれのコンクリートブロック2の正確な位置は陸上から目視確認できなくなるため、設置予定面上の正確な位置にコンクリートブロック2を接地させることは不可能に近い。   Therefore, it is extremely difficult to install the concrete block 2 using the hanging tool 5 on the planned ground contact surface underwater where the unevenness and the like cannot be visually confirmed from the land. In addition, when a plurality of concrete blocks 2 gripped by the hanging tool 5 are submerged in water, the exact position of each concrete block 2 cannot be visually confirmed from the land, so the concrete block 2 is placed at an accurate position on the planned installation surface. It is almost impossible to ground.

本発明が解決しようとする課題は、水中におけるブロックの設置作業を正確かつ安全に行うことのできるブロック施工法を提供することにある。   Problem to be solved by the invention is providing the block construction method which can perform the installation operation | work of the block in water correctly and safely.

本発明のブロック施工法は、クレーンなどの昇降装置で保持して移動可能な支持部材と、複数のブロックを一つずつ着脱可能に吊り下げるため前記支持部材に並列状に設けられた可撓性を有する複数の吊り下げ部材と、を備えたブロック吊り具を使用し、
前記吊り下げ部材に吊り下げられたブロックを水中の設置予定面に設置することを特徴とする。
The block construction method of the present invention includes a support member that can be held and moved by a lifting device such as a crane, and a flexibility that is provided in parallel with the support member so as to detach a plurality of blocks one by one. A plurality of suspension members having a block suspension device comprising:
The block suspended by the suspension member is installed on a planned installation surface in water.

このような構成において、クレーンなどの昇降装置で保持された支持部材に設けられた複数の吊り下げ部材にそれぞれブロックを吊り下げると、可撓性を有する吊り下げ部材はブロックの重さにより鉛直方向に延びた状態に保たれる。このため、吊り下げられた複数のブロックを水没させても、水面から出ている各吊り下げ部材を目視することにより、水中における各ブロックの位置を陸上から把握することができる。従って、各吊り下げ部材の位置を目視確認しながら、クレーンなどの昇降装置を作動させれば、それぞれのブロックを水中の設置予定面に正確に設置することができる。また、作業者は、水中における各ブロックの位置を常に目視確認できるため、作業中の安全性も確保することができる。   In such a configuration, when a block is suspended from each of a plurality of suspension members provided on a support member that is held by a lifting device such as a crane, the flexible suspension member is moved vertically according to the weight of the block. It is kept in the extended state. For this reason, even if a plurality of suspended blocks are submerged, the position of each block in the water can be grasped from the land by observing each hanging member protruding from the water surface. Therefore, if a lifting device such as a crane is operated while visually confirming the position of each suspension member, each block can be accurately installed on the planned installation surface in water. In addition, since the operator can always visually check the position of each block in the water, safety during work can be ensured.

ここで、前記設置予定面と前記ブロックとの間に敷設されるシート材を、前記吊り下げ部材に吊り下げられたブロックに貼着した状態で前記設置予定面に設置することが望ましい。   Here, it is preferable that the sheet material laid between the planned installation surface and the block is installed on the planned installation surface in a state where the sheet material is adhered to the block suspended by the suspension member.

このような構成とすれば、浸食防止などの目的で、設置予定面とブロックとの間に敷設されるシート材を、ブロックの設置作業と同時に敷設することができるため、作業効率が大幅に向上する。   With such a configuration, for the purpose of preventing erosion, the sheet material laid between the planned installation surface and the block can be laid at the same time as the block installation work, which greatly improves work efficiency. To do.

この場合、前記設置予定面に敷設された前記シート材同士を繋ぐための接合手段を当該シート材に設けることが望ましい。このような構成とすれば、シート材同士を繋ぐための接着剤などを塗布する作業を行う手間が省けるため、省力化を図ることができる。   In this case, it is desirable to provide the sheet material with a joining means for connecting the sheet materials laid on the planned installation surface. With such a configuration, it is possible to save labor because the labor of applying an adhesive or the like for connecting the sheet materials can be saved.

本発明により、水中におけるブロックの設置作業を正確かつ安全に行うことのできるブロック施工法を提供することができる。   ADVANTAGE OF THE INVENTION By this invention, the block construction method which can perform the installation operation | work of the block in water correctly and safely can be provided.

以下、本発明の実施の形態を図面に基づいて、説明する。図1は本発明の実施の形態であるブロック施工法におけるブロック吊り具の使用状態を示す斜視図、図2は図1に示すブロック吊り具の使用状態の正面図、図3は本実施形態のブロック施工法で使用するコンクリートブロックの斜視図である。   Hereinafter, embodiments of the present invention will be described with reference to the drawings. 1 is a perspective view showing a use state of a block lifting device in a block construction method according to an embodiment of the present invention, FIG. 2 is a front view of the use state of the block lifting device shown in FIG. 1, and FIG. It is a perspective view of the concrete block used with a block construction method.

図1,図2に示すように、ブロック吊り具10の支持部材11のワイヤ係止部16に係止されたワイヤ20を、クレーン60(図13参照)の昇降部材22のフック22aに引っ掛けて吊り下げれば、ブロック吊り具10全体が昇降及び移動できる状態となる。そして、複数の連接部材12をそれぞれ支持部材11の適切な位置に配置し、固定ボルト15を締め付けて固定する。次に、複数の連接部材12から垂下された吊り下げ部材21下端のブロック連結具25(図4参照)を、図3に示すブロック30のアンカー35の頭部35aにそれぞれ連結する。   As shown in FIGS. 1 and 2, the wire 20 locked to the wire locking portion 16 of the support member 11 of the block lifting device 10 is hooked on the hook 22 a of the lifting member 22 of the crane 60 (see FIG. 13). When suspended, the entire block suspension 10 can be moved up and down and moved. Then, the plurality of connecting members 12 are respectively arranged at appropriate positions on the support member 11, and the fixing bolts 15 are tightened and fixed. Next, the block connector 25 (see FIG. 4) at the lower end of the suspension member 21 suspended from the plurality of connecting members 12 is connected to the head portion 35a of the anchor 35 of the block 30 shown in FIG.

図1,図2に示すように、複数のブロック30はそれぞれ透水性、通気性を有するシート材40上に接着剤を用いて接着されている。また、ブロック30が接着された側のシート材40の辺縁部と対向する側の辺縁部のシート材40上面には、後工程において、複数のブロック30とともに敷設されるシート材40を接着するための接着剤層41が設けられている。   As shown in FIGS. 1 and 2, the plurality of blocks 30 are bonded to a sheet material 40 having water permeability and air permeability using an adhesive. In addition, the sheet material 40 laid together with the plurality of blocks 30 is bonded to the upper surface of the sheet material 40 on the side of the side edge facing the side edge of the sheet material 40 on the side to which the block 30 is bonded. An adhesive layer 41 is provided.

図3に示すように、ブロック30は、平面視形状が略T字状のコンクリート製のブロックであり、T字の垂直部分に回転支承用溝部31が形成され、T字の水平部分の左右両端下面にそれぞれ回転支承用突起32が形成されている。また、T字の垂直部分と水平部分との交差部分の上面及び下面にそれぞれ段差部36,33が形成されている。段差部36におけるブロック30の重心上に位置する部分に擂り鉢状の凹部34が形成され、この凹部34の底部にアンカー35が埋設されている。アンカー35は、その軸部35bがブロック30内に起立状に埋設され、その頭部35aが凹部34内に突出した状態にある。図1に示す吊り下げ部材21下端のブロック連結具25(図4参照)を、アンカー35の頭部35aに着脱可能に連結することができる。   As shown in FIG. 3, the block 30 is a concrete block having a substantially T-shape in plan view, and a rotation support groove portion 31 is formed in a vertical portion of the T shape, and left and right ends of the horizontal portion of the T shape. Rotating support protrusions 32 are formed on the lower surfaces. Further, step portions 36 and 33 are formed on the upper surface and the lower surface of the intersecting portion of the T-shaped vertical portion and the horizontal portion, respectively. A bowl-shaped recess 34 is formed in a portion of the step portion 36 located on the center of gravity of the block 30, and an anchor 35 is embedded in the bottom of the recess 34. The shaft 35 b of the anchor 35 is embedded in an upright manner in the block 30, and its head 35 a protrudes into the recess 34. The block connector 25 (see FIG. 4) at the lower end of the suspension member 21 shown in FIG. 1 can be detachably connected to the head portion 35 a of the anchor 35.

ブロック吊り具10の複数の吊り下げ部材21に対して複数のブロック30を一つずつ連結した後、クレーン60(図13参照)を作動させて昇降部材22を上昇させれば、ブロック吊り具10とともに複数のブロック30が持ち上げられる。そして、クレーン60を操作して、複数のブロック30を設置予定面P(図13参照)の上方まで移動させた後、昇降部材22を下降させ、後述する施工手順に沿って、複数のブロック30を水中に降ろせば、設置予定面Pに設置することができる。   After connecting the plurality of blocks 30 to the plurality of suspension members 21 of the block suspension 10 one by one and then operating the crane 60 (see FIG. 13) to raise the elevating member 22, the block suspension 10 At the same time, the plurality of blocks 30 are lifted. And after operating the crane 60 and moving the several block 30 to the upper direction of the installation planned surface P (refer FIG. 13), the raising / lowering member 22 is lowered | hung, and the several block 30 is followed along the construction procedure mentioned later. Can be placed on the planned installation surface P.

ここで、図4〜図10に基づいてブロック吊り具10の構造、機能について説明する。図4(a)は図1に示すブロック吊り具の平面図、同(b)は前記ブロック吊り具の正面図、図5は図4に示すブロック吊り具の一部省略側面図、図6〜図8はそれぞれ図4(b)に示すブロック吊り具の一部省略拡大図、図9は図2に示すブロック吊り具の使用状態を示す一部拡大正面図、図10はブロック吊り具のその他の実施形態を示す一部拡大正面図である。   Here, the structure and function of the block hanger 10 will be described with reference to FIGS. 4A is a plan view of the block suspension shown in FIG. 1, FIG. 4B is a front view of the block suspension, FIG. 5 is a partially omitted side view of the block suspension shown in FIG. 8 is a partially omitted enlarged view of the block suspension shown in FIG. 4 (b), FIG. 9 is a partially enlarged front view showing the use state of the block suspension shown in FIG. 2, and FIG. It is a partially enlarged front view showing the embodiment.

図4に示すように、ブロック吊り具10は、ワイヤ20で吊り下げられ水平保持される直線状の支持部材11と、支持部材11の下面側にその長手方向に沿って隙間を隔てて配列された複数の連接部材12と、連接部材12の下面側に垂下された吊り下げ部材21と、を備えている。支持部材11はI形鋼材等で形成され、その上方のフランジ11fに、ワイヤ係止部16、フォーク係合部17及びフック18がそれぞれ左右一対ずつ設けられている。   As shown in FIG. 4, the block suspension 10 is arranged in a linear support member 11 suspended by a wire 20 and held horizontally, and on the lower surface side of the support member 11 with a gap along the longitudinal direction thereof. A plurality of connecting members 12 and a suspension member 21 suspended from the lower surface side of the connecting member 12 are provided. The support member 11 is formed of an I-shaped steel material or the like, and a pair of left and right wires engaging portions 16, fork engaging portions 17 and hooks 18 are provided on the flange 11f above the supporting member 11, respectively.

支持部材11の下方のフランジ11gには複数の連接部材12が、支持部材11の長手方向に沿ってスライド可能に装着され、これらの連接部材12には、吊り下げ部材21を係止するための係止具13と、連接部材12を支持部材11の所定位置に固定するためのY字状の固定ボルト15と、連接部材12の位置を示すためのカーソル14と、吊り下げ部材21を一時的に引っ掛けるためのJ字状フック26と、が設けられている。ブロック吊り下げ部材21の下端にはブロック連結具25が取り付けられている。連接部材12を支持部材11の長手方向に沿ってスライドさせ、その固定位置を変更することにより、ブロック吊り下げ部材21に吊り下げられたブロック30の間隔を調整することができる。このため、複数のブロック30の間隔を施工条件に適した寸法に設定することができる。   A plurality of connecting members 12 are slidably mounted on the flange 11g below the supporting member 11 along the longitudinal direction of the supporting member 11, and these connecting members 12 are used for locking the suspension member 21. The locking tool 13, the Y-shaped fixing bolt 15 for fixing the connecting member 12 to a predetermined position of the supporting member 11, the cursor 14 for indicating the position of the connecting member 12, and the hanging member 21 are temporarily provided. And a J-shaped hook 26 to be hooked on. A block connector 25 is attached to the lower end of the block suspension member 21. By sliding the connecting member 12 along the longitudinal direction of the support member 11 and changing its fixing position, the interval between the blocks 30 suspended by the block suspension member 21 can be adjusted. For this reason, the space | interval of the some block 30 can be set to the dimension suitable for construction conditions.

図5,図6に示すように、固定ボルト15は連接部材12から支持部材11のウェブ11wに向かって螺合されている。図6中の円弧状の矢線で示す正転・逆転方向に固定ボルト15を回転させると、その先端部15aがウェブ11wに接触、離隔し、連接部材12が支持部材11に係止、解除される。また、連接部材12の下面の係止具13には係止孔13aが設けられ、この係止孔13aに着脱可能な連結具27を介して吊り下げ部材21が垂下状に取り付けられている。本実施形態では吊り下げ部材21としてチェーンを使用しているが、これに限定するものではないので、可撓性を有するワイヤ、線材、紐状体等を使用することもできる。   As shown in FIGS. 5 and 6, the fixing bolt 15 is screwed from the connecting member 12 toward the web 11 w of the support member 11. When the fixing bolt 15 is rotated in the forward / reverse direction indicated by the arcuate arrow in FIG. 6, the tip 15 a contacts and separates from the web 11 w, and the connecting member 12 engages and releases the support member 11. Is done. Further, the locking member 13 on the lower surface of the connecting member 12 is provided with a locking hole 13a, and the suspension member 21 is attached to the locking hole 13a via a detachable connector 27. In the present embodiment, a chain is used as the hanging member 21, but the present invention is not limited to this, and a flexible wire, wire, string, or the like can also be used.

図6に示すように、フォーク係合部17には、フォークリフト(図示せず)の昇降フォークを挿入係合させるための四角筒状の係合孔17aが設けられている。図7に示すように、ワイヤ係止部16にはそれぞれワイヤ20(図1参照)を係止するためのワイヤ係止孔16aが設けられている。図2,図5及び図8に示すように、支持部材11の左右両端の上方のフランジ11fには、ロープ37(図1参照)やワイヤ等を係止するための一対のU字状フック18が起立状に設けられている。   As shown in FIG. 6, the fork engaging portion 17 is provided with a rectangular cylindrical engagement hole 17 a for inserting and engaging a lifting fork of a forklift (not shown). As shown in FIG. 7, the wire locking portions 16 are provided with wire locking holes 16a for locking the wires 20 (see FIG. 1). As shown in FIGS. 2, 5, and 8, a pair of U-shaped hooks 18 for locking a rope 37 (see FIG. 1), a wire, and the like are provided on the flanges 11 f above the left and right ends of the support member 11. Are provided upright.

一方、図9に示すように、吊り下げ部材21で吊り下げられた複数のブロック30に着脱可能に係合する整列部材50を使用することもできる。整列部材50は、円筒状の主軸52と、主軸52の長手方向に沿って移動可能に取り付けられた複数のストッパ51と、で構成されている。ストッパ51は、リング状の係止部51aと、係止部51aの外周にその半径方向に突設されたバー部材51cと、係止部51aを主軸52に係脱させるための係止ボルト51bと、で構成されている。複数のストッパ51の係止部51aに主軸52を挿通させることにより整列部材50が構成されている。   On the other hand, as shown in FIG. 9, it is also possible to use an alignment member 50 that is detachably engaged with the plurality of blocks 30 suspended by the suspension member 21. The alignment member 50 includes a cylindrical main shaft 52 and a plurality of stoppers 51 attached to be movable along the longitudinal direction of the main shaft 52. The stopper 51 includes a ring-shaped locking part 51a, a bar member 51c projecting radially on the outer periphery of the locking part 51a, and a locking bolt 51b for engaging and disengaging the locking part 51a with the main shaft 52. And is composed of. The alignment member 50 is configured by inserting the main shaft 52 through the locking portions 51 a of the plurality of stoppers 51.

図9に示すように、吊り下げ部材21で吊り下げられた複数のブロック30上に、係止ボルト51bを緩めた状態で整列部材50を載置し、複数のバー部材51cをそれぞれ各ブロック30の側面に当接させ、所定間隔に調整した後、各係止ボルト51bを締め付ければ、ストッパ51が主軸52に固定され、複数のブロック30は所定間隔に配列された状態に保持される。この場合、図9に示すように、一つのブロック30の側面を二つのバー部材51cで挟持するようにセットすることが望ましいが、これに限定するものではない。また、係止ボルト51bを緩めれば、ストッパ51の位置を変更したり、整列部材50をブロック30から離脱させたりすることができる。   As shown in FIG. 9, the alignment member 50 is placed on the plurality of blocks 30 suspended by the suspension member 21 with the locking bolts 51 b loosened, and the plurality of bar members 51 c are respectively connected to the respective blocks 30. When the locking bolts 51b are tightened after being brought into contact with the side surfaces and adjusted to a predetermined interval, the stopper 51 is fixed to the main shaft 52, and the plurality of blocks 30 are held in a state of being arranged at a predetermined interval. In this case, as shown in FIG. 9, it is desirable to set the side surface of one block 30 so as to be sandwiched between two bar members 51c, but the present invention is not limited to this. Further, if the locking bolt 51b is loosened, the position of the stopper 51 can be changed or the alignment member 50 can be detached from the block 30.

図9に示すように、整列部材50を使用すれば、吊り下げ部材21で吊り下げられた複数のブロック30に整列部材50を係合させるだけで、複数のブロック30を一定の整列状態に保持することが可能となるため、複数のブロック30を水平な設置面に直列状に設置する場合の作業性が向上する。また、整列部材50を使用することにより、吊り下げ状態にあるブロック30同士が接触するのを回避することもできる。   As shown in FIG. 9, when the alignment member 50 is used, the plurality of blocks 30 can be held in a certain alignment state simply by engaging the alignment member 50 with the plurality of blocks 30 suspended by the suspension member 21. This makes it possible to improve workability when the plurality of blocks 30 are installed in series on a horizontal installation surface. Further, by using the alignment member 50, it is possible to avoid the blocks 30 in a suspended state from contacting each other.

また、図10に示すように、吊り下げ部材21に吊り下げられたブロック30に係脱可能に係合する姿勢保持部材23をブロック吊り具10に装着することもできる。姿勢保持部材23は、連接部材12に支持部材11と平行に設けられた支軸23aと、支軸23aに回動自在に軸支された一対の回動アーム23bと、回動アーム23bの先端に設けられた複数の係止部材23cに挟持された弾性体23dと、を備えている。弾性体23dの先端周縁部はブロック30上面の段差部36に係合する形状となっている。   Further, as shown in FIG. 10, a posture holding member 23 that can be detachably engaged with a block 30 suspended from the suspension member 21 can be attached to the block suspension 10. The posture holding member 23 includes a support shaft 23a provided on the connecting member 12 in parallel with the support member 11, a pair of rotation arms 23b rotatably supported on the support shaft 23a, and a distal end of the rotation arm 23b. And an elastic body 23d sandwiched between a plurality of locking members 23c provided on the surface. The peripheral edge of the distal end of the elastic body 23d is shaped to engage with the stepped portion 36 on the upper surface of the block 30.

図10に示すように、姿勢保持部材23の支軸23aを中心に回動アーム23bを回動させることにより、係止部材23cの弾性体23dをブロック30の段差部36に係合、離脱させることができる。従って、必要に応じて、弾性体23dをブロック30の段差部36に係合させれば、吊り下げ部材21に吊り下げられたブロック30が搬送中に揺動したり、回動したりするのを防止することができる。このため、搬送中の作業性、安全性を高め、ブロック30同士の接触による損傷を防止することができる。また、姿勢保持部材23はブロック30に係脱可能であるため、ブロック30の接地前に姿勢保持部材23をブロック30から離脱させれば、ブロック30は揺動及び傾動可能な状態に復帰する。従って、設置予定面に沿った姿勢で接地でき、設置作業に支障はない。   As shown in FIG. 10, by rotating the rotation arm 23 b around the support shaft 23 a of the posture holding member 23, the elastic body 23 d of the locking member 23 c is engaged with and released from the stepped portion 36 of the block 30. be able to. Therefore, if the elastic body 23d is engaged with the stepped portion 36 of the block 30 as necessary, the block 30 suspended by the suspension member 21 swings or rotates during conveyance. Can be prevented. For this reason, workability | operativity and safety | security during conveyance can be improved and the damage by the contact of blocks 30 can be prevented. Further, since the posture holding member 23 can be engaged with and disengaged from the block 30, if the posture holding member 23 is detached from the block 30 before the block 30 is grounded, the block 30 returns to a state where it can swing and tilt. Therefore, it can be grounded in a posture along the planned installation surface, and there is no hindrance to the installation work.

図10においては、姿勢保持部材23は、一つの連接部材12のみに取り付けられているが、これに限定するものではないので、二つ以上の連接部材12(例えば、両端に位置する連接部材12)にそれぞれ姿勢保持部材23を取り付けることもできる。また、必要に応じて、図9で示した整列部材50と姿勢保持部材23とを併用することもできる。   In FIG. 10, the posture holding member 23 is attached to only one connecting member 12, but is not limited to this, and therefore two or more connecting members 12 (for example, connecting members 12 located at both ends). The posture holding member 23 can also be attached to each of them. Further, the alignment member 50 and the posture maintaining member 23 shown in FIG. 9 can be used together as necessary.

次に、図1,図2及び図11〜図18に基づいて、ブロック施工法について説明する。なお、図11〜図18において図1〜図10に記載された符号と同符号を付した部分は、前述したブロック吊り具10等の構成部分と同じ構造、機能を有する部分であり、説明を省略する。   Next, the block construction method will be described based on FIGS. 1, 2, and 11 to 18. In addition, the part which attached | subjected the code | symbol same as the code | symbol described in FIGS. 11-10 in FIGS. 11-18 is a part which has the same structure and function as structural parts, such as the block hanging tool 10 mentioned above, and demonstrates it. Omitted.

本実施形態のブロック施工法を実施する場合、その前段階として、図11,図12に示すように、施工現場である法面R1の整形が行われる。図11に示すように、バックホウ70のバケット70aを用いて法面R1および川底R2の荒整形が行われる。この場合、水深や法長に応じてロングアームのバックホウ70を使用することがある。また、荒整形作業中に河川の水Wが土砂などで濁るのを防止するため、施工現場を包囲するように汚濁防止フェンス(図示せず)を設けることが望ましい。   When the block construction method of this embodiment is implemented, as shown in FIGS. 11 and 12, the slope R1 that is the construction site is shaped as a previous stage. As shown in FIG. 11, rough shaping of the slope R1 and the riverbed R2 is performed using the bucket 70a of the backhoe 70. In this case, a long arm backhoe 70 may be used depending on the water depth and the length of the law. In order to prevent the river water W from becoming cloudy with earth and sand during rough shaping work, it is desirable to provide a pollution prevention fence (not shown) so as to surround the construction site.

バックホウ70による荒整形が終わったら、施工領域を囲むように立設された複数の支柱71,72と、法面R1および川底R2とに沿って単管丁張73,74が設けられる。そして、水W中の潜水士75が手に持った単管76を単管丁張73,74に沿って移動させながら法面R1の凹凸を探り、潜水士75とバックホウ70との共同作業により、仕上げ整形が行われる。   After the rough shaping by the backhoe 70 is finished, the single pipe tensions 73 and 74 are provided along the plurality of support columns 71 and 72 erected so as to surround the construction area, and the slope R1 and the riverbed R2. Then, the single pipe 76 held by the diver 75 in the water W is moved along the single pipe tensions 73 and 74, and the unevenness of the slope R1 is searched, and by the joint work of the diver 75 and the backhoe 70, Finish shaping is performed.

次に、図1,図2及び図13に示すように、クレーン60に保持されたブロック吊り具10の支持部材11に垂下状に設けられた複数の吊り下げ部材21にそれぞれブロック30を一つずつ吊り下げると、可撓性を有する吊り下げ部材21はブロック30の重さにより鉛直方向に延びた状態に保たれる。従って、図13に示すように、吊り下げられた複数のブロック30を施工現場の水Wの中に没入させても、水面W1から出ている各吊り下げ部材21を目視することにより、水中における各ブロック30の位置を陸上から把握することができる。従って、各吊り下げ部材21の位置を目視確認しながら、クレーン60の昇降部材22を繰り出してブロック吊り具10を徐々に下降させれば、それぞれのブロック30を水W中の設置予定面Pに正確に設置することができる。   Next, as shown in FIGS. 1, 2, and 13, one block 30 is attached to each of a plurality of suspension members 21 provided in a suspended manner on the support member 11 of the block suspension 10 held by the crane 60. When suspended one by one, the flexible suspension member 21 is maintained in a state extending in the vertical direction due to the weight of the block 30. Therefore, as shown in FIG. 13, even if the suspended blocks 30 are immersed in the water W at the construction site, by visually observing each hanging member 21 coming out of the water surface W1, The position of each block 30 can be grasped from the land. Therefore, if the lifting member 22 of the crane 60 is fed out and the block lifting tool 10 is gradually lowered while visually confirming the position of each hanging member 21, each block 30 is placed on the planned installation surface P in the water W. It can be installed accurately.

ブロック吊り具10が水没するまで下降し、図14に示す水面W1が水面W2の位置にきたときは、水面W1から上方へ突出する標示部材19及びその目盛19aを見ることにより、ブロック30の存在位置と深さとを確認しながら、設置予定面Pに設置することができる。   When the block hanging tool 10 descends until it is submerged and the water surface W1 shown in FIG. 14 reaches the position of the water surface W2, the presence of the block 30 can be seen by looking at the marking member 19 projecting upward from the water surface W1 and its scale 19a. It can be installed on the planned installation surface P while checking the position and depth.

複数のブロック30が設置予定面Pに設置されたら、吊り下げ部材21が撓む程度までブロック吊り具10を下降させた後、ブロック連結具25(図4参照)をそれぞれブロック30のアンカー35の頭部35a(図3参照)から離脱させれば設置作業が完了する。このとき、図13に示すように、水Wの中で待機している潜水士Sが、新たに設置したブロック30と既設のブロック30との連結作業等を行う。   When the plurality of blocks 30 are installed on the planned installation surface P, the block suspension 10 is lowered until the suspension member 21 is bent, and then the block connector 25 (see FIG. 4) is attached to the anchor 35 of the block 30. Installation work is completed when the head 35a is detached from the head 35a (see FIG. 3). At this time, as shown in FIG. 13, the diver S waiting in the water W performs a connection operation between the newly installed block 30 and the existing block 30.

ブロック吊り具10の吊り下げ部材21に吊り下げられた複数のブロック30はそれぞれ揺動及び傾動可能な状態に保たれるため、ブロック30の設置予定面Pに傾斜や凹凸等の不陸があっても、吊り下げられた複数のブロック30はそれぞれ設置面に沿った傾斜姿勢で接地させることができる。また、傾斜姿勢で接地したブロック30から吊り下げ部材21に加わる傾動力は、吊り下げ部材21の撓みによって解消されるため、ブロック30から吊り下げ部材21が離脱不能となることもない。従って、ブロック30の設置作業を効率良く、安全に行うことができる。   Since the plurality of blocks 30 suspended by the suspension member 21 of the block suspension 10 are kept in a swingable and tiltable state, there is unevenness or unevenness on the planned installation surface P of the block 30. However, the plurality of suspended blocks 30 can be grounded in an inclined posture along the installation surface. Further, the tilting force applied to the suspension member 21 from the block 30 grounded in the inclined posture is eliminated by the bending of the suspension member 21, so that the suspension member 21 does not become undetachable from the block 30. Therefore, the installation work of the block 30 can be performed efficiently and safely.

ブロック吊り具10においては、支持部材11に沿って連接部材12を移動させることにより、複数の吊り下げ部材21の間隔を変更することができるため、それぞれの吊り下げ部材21に吊り下げられた複数のブロック30の間隔も変更可能である。このため、施工条件に適したブロック間隔に設定することができ、施工現場への適応性に優れている。なお、図1,図2に示すように、本実施形態においてはブロック吊り具10に六個のブロック30を吊り下げているが、これに限定しないので、施工条件に応じて、連接部材12の個数を増減したり、支持部材11の長さを変更したりすることにより、ブロック30の吊り下げ個数を変更することができる。   In the block suspension 10, the interval between the plurality of suspension members 21 can be changed by moving the connecting member 12 along the support member 11, so that the plurality of suspension members 21 suspended by the respective suspension members 21. The interval between the blocks 30 can also be changed. For this reason, it can set to the block space | interval suitable for construction conditions, and is excellent in the adaptability to a construction site. As shown in FIG. 1 and FIG. 2, in the present embodiment, six blocks 30 are suspended from the block lifting tool 10, but the present invention is not limited to this. The number of hanging blocks 30 can be changed by increasing / decreasing the number or changing the length of the support member 11.

また、図1,図2に示すように、ブロック吊り具10には、支持部材11より上方に起立する標示部材19が支持部材11の左右両端に設けられている。従って、図14に示すように、支持部材11が水W中に没しても、これより上方に起立する標示部材19が水面W1から突出するため、水W中における支持部材11の位置を目視確認することにより、複数のブロック30を正確な位置に配置することができる。また、図14に示すように、標示部材19には複数の目盛19aが付設されているため、水W中における支持部材11の深さ方向の位置も目視確認することができる。   As shown in FIGS. 1 and 2, the block suspension 10 is provided with marking members 19 that stand above the support member 11 at both left and right ends of the support member 11. Therefore, as shown in FIG. 14, even if the support member 11 is submerged in the water W, the marking member 19 standing upwards from this protrudes from the water surface W1, so that the position of the support member 11 in the water W is visually observed. By checking, the plurality of blocks 30 can be arranged at accurate positions. Moreover, as shown in FIG. 14, since the marking member 19 is provided with a plurality of scales 19a, the position in the depth direction of the support member 11 in the water W can also be visually confirmed.

一方、図1,図13に示すように、支持部材11両端のフック18に係止されたロープ37を、陸上に居る作業者Tが手で持って操作することにより、水平方向の位置や姿勢の微調整を行うこともできる。このように、クレーンの運転士(図示せず)や陸上に居る作業者Tは、吊り下げ部材21及び標示部材19を目視することにより、水W中における各ブロック30の位置を確認しながら設置作業を行うことができるため、ブロック30を設置予定面P上の正確な位置に設置することができ、作業中の安全性も優れている。   On the other hand, as shown in FIGS. 1 and 13, the operator can be held and operated by the operator T on the land holding the rope 37 locked to the hooks 18 at both ends of the support member 11. It is also possible to make fine adjustments. Thus, the operator (not shown) of the crane or the worker T on the ground installs while checking the position of each block 30 in the water W by visually observing the suspension member 21 and the marking member 19. Since the work can be performed, the block 30 can be installed at an accurate position on the planned installation surface P, and the safety during the work is also excellent.

本実施形態においては、図13,図15に示すように、河川堤防Rの高い位置に設置したブロック30b,30cを止め杭61で地山に係止し、ブロック30cから水W中に向かって順番にブロック30を設置して互いに連結していくことにより、ブロック連結体30Xを形成している。即ち、図15,図16に示す矢線62方向に沿ってブロック30を設置していくことによってブロック連結体30Xが構築されている。   In this embodiment, as shown in FIGS. 13 and 15, the blocks 30 b and 30 c installed at a high position of the river dike R are locked to the natural ground by the stop pile 61, and from the block 30 c toward the water W. The block connection body 30X is formed by installing the blocks 30 in order and connecting them together. That is, the block connection body 30X is constructed by installing the blocks 30 along the direction of the arrow line 62 shown in FIGS.

そして、図15,図16に示すブロック連結体30Xにおいて、河川堤防Rから最も離れた水W中には図17に示すブロック30eを設置し、ブロック連結体30Xの矢線62に沿った側縁部分には図18に示すブロック30s,30tを設置している。これにより、矢線62,63方向の周縁部分の凹凸を少なくすることができる。なお、ブロック30を設置していく方向は前述の方向に限定するものではないので、図19,図20の矢線64の方向に設置していくことによってブロック連結体30Yを構築することもできる。この場合、図20に示すように、ブロック30,30s,30tの配置姿勢は、図14に示す形態から180度回転させた状態となる。   15 and FIG. 16, the block 30e shown in FIG. 17 is installed in the water W farthest from the river embankment R, and the side edge along the arrow line 62 of the block connector 30X. In the portion, blocks 30s and 30t shown in FIG. 18 are installed. Thereby, the unevenness | corrugation of the peripheral part of the arrow lines 62 and 63 direction can be decreased. In addition, since the direction in which the block 30 is installed is not limited to the above-described direction, the block connecting body 30Y can be constructed by installing the block 30 in the direction of the arrow 64 in FIGS. . In this case, as shown in FIG. 20, the arrangement postures of the blocks 30, 30s, and 30t are rotated 180 degrees from the form shown in FIG.

本実施形態においては、図1,図13に示すように、浸食防止の目的で、設置予定面Pとブロック30との間に敷設されるシート材40を、吊り下げ部材21に吊り下げられたブロック30の底面に予め貼着した状態で設置予定面Pに設置している。これにより、シート材40の敷設作業を、ブロック30の設置作業と同時に行うことができるため、作業効率が大幅に向上する。   In the present embodiment, as shown in FIGS. 1 and 13, the sheet material 40 laid between the planned installation surface P and the block 30 is suspended by the suspension member 21 for the purpose of preventing erosion. It is installed on the planned installation surface P in a state where it is attached in advance to the bottom surface of the block 30. Thereby, since the laying operation of the sheet material 40 can be performed simultaneously with the installation operation of the block 30, the work efficiency is greatly improved.

また、図1に示すように、設置予定面Pに敷設されたシート材40同士を繋ぐための接合手段である接着剤層41を当該シート材40の辺縁部に設けているため、シート材40同士を繋ぐための接着剤などの塗布作業が不要となり、省力化を図ることができる。   Moreover, as shown in FIG. 1, since the adhesive layer 41 which is a joining means for connecting the sheet materials 40 laid on the planned installation surface P is provided on the edge portion of the sheet material 40, the sheet material Application work such as an adhesive for connecting the 40 members becomes unnecessary, and labor saving can be achieved.

本発明のブロック施工法は、河川堤防の護岸工事等に伴う水中へのブロック設置作業において広く利用することができる。   The block construction method of the present invention can be widely used in underwater block installation work associated with river bank protection works.

本発明の実施の形態であるブロック施工法におけるブロック吊り具の使用状態を示す斜視図である。It is a perspective view which shows the use condition of the block lifting tool in the block construction method which is embodiment of this invention. 図1に示すブロック吊り具使用状態の正面図である。It is a front view of the block hanging tool use state shown in FIG. 本実施形態のブロック施工法で使用するコンクリートブロックの斜視図である。It is a perspective view of the concrete block used with the block construction method of this embodiment. (a)は図1に示すブロック吊り具の平面図、(b)は前記ブロック吊り具の正面図である。(A) is a top view of the block suspension shown in FIG. 1, (b) is a front view of the block suspension. 図4に示すブロック吊り具の一部省略側面図である。FIG. 5 is a partially omitted side view of the block suspension shown in FIG. 4. 図4(b)に示すブロック吊り具の一部省略拡大図である。FIG. 5 is a partially omitted enlarged view of the block suspension shown in FIG. 図4(b)に示すブロック吊り具の一部省略拡大図である。FIG. 5 is a partially omitted enlarged view of the block suspension shown in FIG. 図4(b)に示すブロック吊り具の一部省略拡大図である。FIG. 5 is a partially omitted enlarged view of the block suspension shown in FIG. 図2に示すブロック吊り具の使用状態を示す一部拡大正面図である。It is a partially expanded front view which shows the use condition of the block hanging tool shown in FIG. ブロック吊り具のその他の実施形態を示す一部拡大正面図である。It is a partially expanded front view which shows other embodiment of a block hanging tool. 本発明の実施の形態であるブロック施工法を実施する前の法面整形工程を示す垂直断面図である。It is a vertical sectional view showing a slope shaping step before carrying out a block construction method according to an embodiment of the present invention. 図11に示す法面整形工程の斜視図である。It is a perspective view of the slope shaping process shown in FIG. 本発明の実施の形態であるブロック施工法を示す模式図である。It is a schematic diagram which shows the block construction method which is embodiment of this invention. 水中における施工状態を示す正面図である。It is a front view which shows the construction state in water. 施工後のブロック配列状態を示す断面図である。It is sectional drawing which shows the block arrangement | sequence state after construction. 施工後のブロック配列状態を示す平面図である。It is a top view which shows the block arrangement | sequence state after construction. 図16に示すエンドブロックの斜視図である。It is a perspective view of the end block shown in FIG. 図16に示すサイドブロックの斜視図である。It is a perspective view of the side block shown in FIG. ブロック施工法のその他の実施形態を示す断面図である。It is sectional drawing which shows other embodiment of the block construction method. 図19に示すブロック配列状態の平面図である。It is a top view of the block arrangement state shown in FIG.

符号の説明Explanation of symbols

10 ブロック吊り具
11 支持部材
11f,11g フランジ
11w ウェブ
12 連接部材
13 係止具
13a 係止孔
14 カーソル
15 固定ボルト
15a 先端部
16 ワイヤ係止部
16a ワイヤ係止孔
17 フォーク係合部
17a 係合孔
18,22a フック
19 標示部材
19a 目盛
20 ワイヤ
21 吊り下げ部材
22 昇降部材
23 姿勢保持部材
23a 支軸
23b 回動アーム
23c 係止部材
23d 弾性体
25 ブロック連結具
26 J字状フック
27 連結具
30,30a,30b,30c,30e,30s,30t ブロック
30X,30Y ブロック連結体
31 回転支承用溝部
32 回転支承用突起
33,36 段差部
34 凹部
35 アンカー
35a 頭部
35b 軸部
37 ロープ
40 シート材
41 接着剤層
50 整列部材
51 ストッパ
51a 係止部
51b 係止ボルト
51c バー部材
52 主軸
60 クレーン
61 止め杭
62,63,64 矢線
70 バックホウ
70a バケット
71,72 支柱
73,74 単管丁張
76 単管
P 設置予定面
R 河川堤防
R1 法面
R2 川底
75,S 潜水士
T 作業者
W 水
W1,W2 水面
DESCRIPTION OF SYMBOLS 10 Block lifting tool 11 Support member 11f, 11g Flange 11w Web 12 Connection member 13 Locking tool 13a Locking hole 14 Cursor 15 Fixing bolt 15a Tip part 16 Wire locking part 16a Wire locking hole 17 Fork engaging part 17a Engagement Hole 18, 22a Hook 19 Marking member 19a Scale 20 Wire 21 Hanging member 22 Lifting member 23 Posture holding member 23a Support shaft 23b Rotating arm 23c Locking member 23d Elastic body 25 Block connector 26 J-shaped hook 27 Connector 30 , 30a, 30b, 30c, 30e, 30s, 30t Block 30X, 30Y Block coupling body 31 Rotating bearing groove 32 Rotating bearing projection 33, 36 Stepped portion 34 Recessed portion 35 Anchor 35a Head portion 35b Shaft portion 37 Rope 40 Sheet material 41 Adhesive layer 50 Alignment Material 51 Stopper 51a Locking part 51b Locking bolt 51c Bar member 52 Spindle 60 Crane 61 Locking pile 62, 63, 64 Arrow 70 Backhoe 70a Bucket 71, 72 Post 73, 74 Single pipe tension 76 Single pipe P Planned installation surface R River dike R1 Slope R2 River bottom 75, S Diver T Worker W Water W1, W2 Water surface

Claims (3)

クレーンなどの昇降装置で保持して移動可能な支持部材と、複数のブロックを一つずつ着脱可能に吊り下げるため前記支持部材に並列状に設けられた可撓性を有する複数の吊り下げ部材と、を備えたブロック吊り具を使用し、
前記吊り下げ部材に吊り下げられたブロックを水中の設置予定面に設置することを特徴とするブロック施工法。
A support member that can be held and moved by an elevating device such as a crane, and a plurality of flexible suspension members provided in parallel to the support member to detachably detach a plurality of blocks one by one; Use a block suspension with
A block construction method characterized in that the block suspended by the suspension member is installed on a surface to be installed in water.
前記設置予定面と前記ブロックとの間に敷設されるシート材を、前記吊り下げ部材に吊り下げられたブロックに貼着した状態で前記設置予定面に設置することを特徴とする請求項1記載のブロック施工法。   The sheet material laid between the planned installation surface and the block is installed on the planned installation surface in a state where the sheet material is stuck to the block suspended by the suspension member. Block construction method. 前記設置予定面に敷設された前記シート材同士を繋ぐための接合手段を当該シート材に設けたことを特徴とする請求項2記載のブロック施工法。   The block construction method according to claim 2, wherein a bonding means for connecting the sheet materials laid on the planned installation surface is provided on the sheet material.
JP2007217369A 2007-08-23 2007-08-23 Block construction method Active JP4994153B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007217369A JP4994153B2 (en) 2007-08-23 2007-08-23 Block construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007217369A JP4994153B2 (en) 2007-08-23 2007-08-23 Block construction method

Publications (2)

Publication Number Publication Date
JP2009052206A true JP2009052206A (en) 2009-03-12
JP4994153B2 JP4994153B2 (en) 2012-08-08

Family

ID=40503513

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007217369A Active JP4994153B2 (en) 2007-08-23 2007-08-23 Block construction method

Country Status (1)

Country Link
JP (1) JP4994153B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011247048A (en) * 2010-05-31 2011-12-08 Toa Harbor Works Co Ltd Installation method of block body and installation jig of block body

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5922288U (en) * 1982-07-30 1984-02-10 日本テトラポツド株式会社 Lifting device for four-legged wave-dissipating block
JPH0158589U (en) * 1987-10-06 1989-04-12
JPH0533320A (en) * 1991-08-05 1993-02-09 Nippon Tetorapotsuto Kk Method and device for installing wave-dissipating foundation-consolidating block
JPH083962A (en) * 1994-06-24 1996-01-09 Suiko Giken Kk Block mat for prevention of erosion
JPH08198579A (en) * 1994-11-21 1996-08-06 Iwata:Kk Hanger for block work execution and work execution method using this hanger
JP2004059207A (en) * 2002-07-26 2004-02-26 Toa Harbor Works Co Ltd Method and device for installing covering block

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5922288U (en) * 1982-07-30 1984-02-10 日本テトラポツド株式会社 Lifting device for four-legged wave-dissipating block
JPH0158589U (en) * 1987-10-06 1989-04-12
JPH0533320A (en) * 1991-08-05 1993-02-09 Nippon Tetorapotsuto Kk Method and device for installing wave-dissipating foundation-consolidating block
JPH083962A (en) * 1994-06-24 1996-01-09 Suiko Giken Kk Block mat for prevention of erosion
JPH08198579A (en) * 1994-11-21 1996-08-06 Iwata:Kk Hanger for block work execution and work execution method using this hanger
JP2004059207A (en) * 2002-07-26 2004-02-26 Toa Harbor Works Co Ltd Method and device for installing covering block

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011247048A (en) * 2010-05-31 2011-12-08 Toa Harbor Works Co Ltd Installation method of block body and installation jig of block body

Also Published As

Publication number Publication date
JP4994153B2 (en) 2012-08-08

Similar Documents

Publication Publication Date Title
CN102720140B (en) Large-span prestress concrete continuous beam deepwater pier construction process
JP2012112191A (en) Landing bridge construction method
JP5825644B2 (en) Pier construction method
JP2019007232A (en) Installation method of timbering
JP4994153B2 (en) Block construction method
JP5089256B2 (en) Block hanger
JP6068774B1 (en) Earth retaining prior construction method using adjustable erection
CN110344440A (en) A kind of method and structure using reinforced concrete supporting beam in-situ conservation pipeline
JP2015169062A (en) Pile press-in device
CN113089654B (en) Construction process of hole digging pile in complex soil layer and steel casing for construction
JP6886356B2 (en) Suspension device and packing method
CN111980014B (en) Pile pouring structure based on informatization technology, pile structure and pile head breaking method
CN110984003B (en) Method for removing pier and bearing platform at lower part of river-crossing bridge
JP6271664B2 (en) Pile press-fitting device
JP2011149183A (en) Hanger and bracket for pile
JP2019183437A (en) Waling installation tool and waling installation structure
JPH0480418A (en) Method of driving steel pipe sheet pile
KR200392153Y1 (en) A reinforcing rod-net perpendicular salvage apparatus for work afloat
JP5241804B2 (en) Vertical shaft construction method
CN111021780B (en) Inclined wall dismantling system and method thereof
KR102571033B1 (en) Concreat block without lifting lug and installation method thereof
CN221097708U (en) Temporary suspension structure for underground shallow pipeline protection construction
JP2003119793A (en) Underwater working method, working can and working device
JP2009137682A (en) Suspending frame device
JP2013023835A (en) Installation device of manhole cover receiving frame

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20100816

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20110707

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110712

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110831

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120207

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120403

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120424

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120508

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150518

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4994153

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250