JP2008308972A - Nonslip pavement construction method - Google Patents

Nonslip pavement construction method Download PDF

Info

Publication number
JP2008308972A
JP2008308972A JP2007186294A JP2007186294A JP2008308972A JP 2008308972 A JP2008308972 A JP 2008308972A JP 2007186294 A JP2007186294 A JP 2007186294A JP 2007186294 A JP2007186294 A JP 2007186294A JP 2008308972 A JP2008308972 A JP 2008308972A
Authority
JP
Japan
Prior art keywords
pavement
slip
construction method
nonslip
groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2007186294A
Other languages
Japanese (ja)
Inventor
Toshiaki Takeda
俊明 竹田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HOKKAIDO ROAD MAN ENGINEERING
HOKKAIDO ROAD MANAGEMENT ENGINEERING CENTER
Original Assignee
HOKKAIDO ROAD MAN ENGINEERING
HOKKAIDO ROAD MANAGEMENT ENGINEERING CENTER
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HOKKAIDO ROAD MAN ENGINEERING, HOKKAIDO ROAD MANAGEMENT ENGINEERING CENTER filed Critical HOKKAIDO ROAD MAN ENGINEERING
Priority to JP2007186294A priority Critical patent/JP2008308972A/en
Publication of JP2008308972A publication Critical patent/JP2008308972A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Road Paving Structures (AREA)
  • Road Repair (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a nonslip pavement construction method causing neither chipping nor end damage by a blade of a grader used in snow removal work and making no noise by tires at a boundary part between a section in which nonslip pavement is installed and a section in which nonslip pavement is not installed. <P>SOLUTION: The nonslip pavement construction method comprises a first step of forming one or more grooves 10 narrower in width than the blade width 20 of the grader for snow removal in the passing direction of vehicles, and a second step of filling a nonslip pavement material 12 in the grooves so that the upper face of the nonslip pavement material is almost flush with the road surface. <P>COPYRIGHT: (C)2009,JPO&INPIT

Description

本発明は、すべり止め舗装施工方法に関する。より詳細には、積雪寒冷地の除雪作業時に摩耗、破損しにくいすべり止め舗装施工方法に関する。The present invention relates to a slip prevention pavement construction method. More specifically, the present invention relates to a non-slip pavement construction method that is not easily worn or damaged during snow removal work in a snowy cold region.

寒冷地では、交差点手前、急カーブ部,急勾配部などの区間にすべり止め舗装が設置されており、すべり止め舗装材料として、アスファルトや改質アスファルトを使用せず樹脂系すべり止め舗装材が使用されている。樹脂系すべり止め舗装材は、たとえば特許文献1、特許文献2、特許文献3などに公知である。In cold regions, anti-slip pavements are installed in front of intersections, sharp curves, steep slopes, etc., and resin-based anti-slip pavement materials are used as anti-slip pavement materials without using asphalt or modified asphalt. Has been. Resin-based non-slip paving materials are known, for example, in Patent Document 1, Patent Document 2, Patent Document 3, and the like.

前記すべり止め舗装の施工方法は、新設または既設の舗装面上に、すべり止め舗装材料を薄層で塗工する方法や、スプレーによる方法などがあり公知である。
また、舗装道路の路面上に設けられる、センターライン、横断歩道、制限速度表示等のような種々の路面表示の施工方法について、特許文献4では、除雪作業時にグレーダ等を用いる寒冷地においても容易に消失し難い路面表示形成方法として、路面に形成された所定幅の溝内に表示材料を充填する方法が示されている。
As the construction method of the non-slip pavement, there are a method of applying a non-slip pavement material in a thin layer on a new or existing pavement surface, a method using a spray, and the like.
In addition, regarding a method for displaying various road surfaces such as a center line, a pedestrian crossing, a speed limit display, etc. provided on the road surface of a paved road, Patent Document 4 describes that it is easy even in a cold region using a grader or the like during snow removal work. As a method of forming a road surface display that does not easily disappear, a method of filling a display material into a groove having a predetermined width formed on the road surface is shown.

特開平4−100862号公報Japanese Patent Laid-Open No. 4-100862 特開平8−231888号公報JP-A-8-231888 特開平11−21385号公報Japanese Patent Laid-Open No. 11-21385 特開2006−144225号公報JP 2006-144225 A

前記すべり止め舗装の施工方法は、新設または既設の舗装面の上にすべり止め舗装材料の厚さ分突出して塗工やスプレーにより施工されているため、除雪作業時にグレーダのブレードによってすべり止め材料が削り取られることや、すべり止め舗装材料の端部がグレーダのブレードにより破損するという課題がある。The anti-slip pavement is constructed by coating or spraying on the new or existing pavement surface by the thickness of the non-slip pavement material. There is a problem that it is scraped off and an end portion of the non-slip pavement material is damaged by the blade of the grader.

さらに、舗装面からすべり止め舗装材料の厚さ分が突出していることから、すべり止め舗装を設置している区間と設置していない区間の境界部では段差が生じ、タイヤによる騒音が発生するという課題がある。Furthermore, because the thickness of the anti-skid pavement material protrudes from the pavement surface, there is a step at the boundary between the section where the non-slip pavement is installed and the section where it is not installed, and noise due to tires is generated There are challenges.

本発明は、前記課題を解決するためのものであって、舗装路面に溝を形成する第1工程と、前記溝内にすべり止め舗装材料を充填する第2工程とを含むことを特徴とするものである。This invention is for solving the said subject, Comprising: The 1st process of forming a groove | channel in a pavement road surface, and the 2nd process of filling a slip prevention pavement material in the said groove | channel are characterized by the above-mentioned. Is.

前記第1工程が、除雪用グレーダのブレード幅より小さい幅の、単一もしくは複数の溝を、車両通行方向に形成することを特徴とするものである。The first step is characterized in that single or plural grooves having a width smaller than the blade width of the snow removal grader are formed in the vehicle passage direction.

前記第2工程は、前記すべり止め舗装材料の上面が前記路面とほぼ面一となるように行われることを特徴とするものである。The second step is performed such that an upper surface of the anti-skid pavement material is substantially flush with the road surface.

前前記すべり止め舗装材料は、高温で溶融する樹脂製すべり止め舗装材に、硬質骨材を含んでおり、前記硬質骨材の粒径が、前記溝の深さよりも小さくなるように選定されていることを特徴とするものである。The anti-skid pavement material includes a hard aggregate in a resin anti-slip pavement that melts at a high temperature, and the particle size of the hard aggregate is selected to be smaller than the depth of the groove. It is characterized by being.

本発明によれば、すべり止め舗装材料は、除雪用グレーダのブレード幅より小さい幅の溝内にすべり止め舗装材料の上面が前記路面とほぼ面一となるように充填されているので、除雪作業時にグレーダで路面を擦っても、削り取られることや破損することが無く、長期にわたってすべり止め効果があるすべり止め舗装が得られる。また、前記すべり止め舗装材料は、高温で溶融する樹脂製すべり止め舗装材に硬質骨材を含んでおり、前記硬質骨材の粒径が、前記溝の深さよりも小さくなるように選定されており、硬質骨材が前記溝内に留まることから、長期にわたってすべり止め効果が保持できる。According to the present invention, the anti-skid pavement material is filled in the groove having a width smaller than the blade width of the snow removal grader so that the upper surface of the anti-skid pavement material is substantially flush with the road surface. Even if the road surface is sometimes rubbed with a grader, it will not be scraped off or damaged, and a non-slip pavement that has a non-slip effect over a long period of time can be obtained. Further, the anti-slip pavement material includes a hard aggregate in a resin anti-slip pavement that melts at a high temperature, and the particle size of the hard aggregate is selected to be smaller than the depth of the groove. In addition, since the hard aggregate stays in the groove, the anti-slip effect can be maintained for a long time.

さらに、前記溝内にすべり止め舗装材料の上面が路面とほぼ面一となるように充填されているので、すべり止め舗装を設置している区間と設置していない区間の境界部に段差は生じないため、タイヤによる騒音が発生しないという効果がある。Further, since the upper surface of the non-slip pavement material is filled in the groove so as to be substantially flush with the road surface, a step is generated at the boundary between the section where the non-slip pavement is installed and the section where it is not installed. Therefore, there is an effect that no noise is generated by the tire.

次に図面を参照して、本発明の好ましい実施の形態に係るすべり止め舗装施工方法について詳細に説明する。図1は本発明の好ましい実施の形態に係るすべり止め舗装施工方法の工程を示した一連の図である。Next, a slip prevention pavement construction method according to a preferred embodiment of the present invention will be described in detail with reference to the drawings. FIG. 1 is a series of diagrams showing the steps of a slip prevention pavement construction method according to a preferred embodiment of the present invention.

本発明のすべり止め舗装施工方法では、まず、すべり止め舗装を施工する路面に、冬期の除雪作業に使用されるグレーダのブレード幅よりも小さい幅の、単一もしくは複数の溝10を、車両進行方向に形成する(図1(a)参照)。In the slip prevention pavement construction method of the present invention, first, a single or a plurality of grooves 10 having a width smaller than a blade width of a grader used for snow removal work in winter are provided on a road surface on which the slip prevention pavement is constructed. It forms in a direction (refer Fig.1 (a)).

次に、溝10の中に、すべり止め舗装材料12を充填する(図1(b)参照)。すべり止め舗装材料12は、高温で溶融する樹脂製すべり止め舗装材と硬質骨材を含んだものであり、いずれも公知のものを使用して良い。硬質骨材はすべり止め効果があることから、溝10の内に留まり除雪時のグレーダのブレードによる摩耗や損傷を少なくするために、硬質骨材の粒径は、溝10の深さよりも小さくなるように選定する。Next, the anti-skid pavement material 12 is filled in the groove 10 (see FIG. 1B). The anti-slip pavement material 12 includes a resin anti-slip pavement material that melts at a high temperature and a hard aggregate, and any known one may be used. Since the hard aggregate has an anti-slip effect, the particle size of the hard aggregate is smaller than the depth of the groove 10 in order to remain in the groove 10 and reduce wear and damage by the blade of the grader during snow removal. Select as follows.

溝10は、除雪雪作業に使用されるグレーダのブレード幅よりもやや小さい幅の、単一の溝としても良いし、通行車両のタイヤ部分のみとして複数の溝としても良いが、いずれも一つの溝の幅はブレード幅よりも小さくする。(図1(c)および(d)参照)The groove 10 may be a single groove having a width slightly smaller than the blade width of a grader used for snow removal and snow work, or may be a plurality of grooves only as a tire portion of a passing vehicle. The width of the groove is made smaller than the blade width. (See FIGS. 1 (c) and (d))

使用するすべり止め材料は、高温で溶融し常温で固化する型式のものを使用し、使用に際しては加熱し溶融状態となったものを溝10に充填する。充填に際してはすべり止め舗装材料の上面が路面とほぼ面一となるように行う。The anti-slip material to be used is of a type that melts at high temperature and solidifies at room temperature. In use, the material that has been heated and melted is filled into the groove 10. When filling, the top surface of the non-slip pavement material is almost flush with the road surface.

本発明の好ましい実施の形態に係るすべり止め舗装施工方法の工程を示した一連の図である。It is a series of figures showing a process of a slip prevention pavement construction method according to a preferred embodiment of the present invention.

符号の説明Explanation of symbols

10 溝
12 すべり止め舗装材料
20 除雪用グレーダのブレード幅
10 Groove 12 Non-slip pavement material 20 Blade width of snow removing grader

Claims (4)

舗装路面に溝を形成する第1工程と、
前記溝内にすべり止め舗装材料を充填する第2工程と、
を含むことを特徴とするすべり止め舗装施工方法。
A first step of forming grooves on the paved road surface;
A second step of filling the groove with a non-slip paving material;
Non-slip pavement construction method characterized by including.
前記第1工程が、除雪用グレーダのブレード幅より小さい幅の、単一もしくは複数の溝を、車両通行方向に形成することを特徴とする請求項1に記載のすべり止め舗装施工方法。The non-skid pavement construction method according to claim 1, wherein the first step forms a single or a plurality of grooves having a width smaller than a blade width of the snow removal grader in the vehicle passage direction. 前記第2工程が、前記すべり止め舗装材料の上面が前記路面とほぼ面一となるように行われることを特徴とする請求項1または請求項2に記載のすべり止め舗装施工方法。The non-slip pavement construction method according to claim 1 or 2, wherein the second step is performed such that an upper surface of the non-slip pavement material is substantially flush with the road surface. 前記すべり止め舗装材料は、高温で溶融する樹脂製すべり止め舗装材に、硬質骨材を含んでおり、
前記硬質骨材の粒径が、前記溝の深さよりも小さくなるように選定されていることを特徴とする請求項1または請求項2または請求項3に記載のすべり止め舗装施工方法。
The non-slip pavement material includes a hard aggregate in a resin anti-slip pavement material that melts at a high temperature,
The slip prevention pavement construction method according to claim 1, wherein the particle size of the hard aggregate is selected to be smaller than the depth of the groove.
JP2007186294A 2007-06-18 2007-06-18 Nonslip pavement construction method Pending JP2008308972A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007186294A JP2008308972A (en) 2007-06-18 2007-06-18 Nonslip pavement construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007186294A JP2008308972A (en) 2007-06-18 2007-06-18 Nonslip pavement construction method

Publications (1)

Publication Number Publication Date
JP2008308972A true JP2008308972A (en) 2008-12-25

Family

ID=40236810

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007186294A Pending JP2008308972A (en) 2007-06-18 2007-06-18 Nonslip pavement construction method

Country Status (1)

Country Link
JP (1) JP2008308972A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102095399A (en) * 2010-12-15 2011-06-15 中国汽车工程研究院股份有限公司 Road spectrum based method for extracting quantified road characteristic parameters

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102095399A (en) * 2010-12-15 2011-06-15 中国汽车工程研究院股份有限公司 Road spectrum based method for extracting quantified road characteristic parameters

Similar Documents

Publication Publication Date Title
JP3903915B2 (en) Snow removal vehicle
KR101079727B1 (en) Grooving structural body and the spatial-temporal method of asphalt pavement
KR101078600B1 (en) Method for forming a non-slip groove on a road
JP6462355B2 (en) Attention groove forming attachment, warning groove forming device, protective plate material, warning groove pavement construction method and wedge-shaped warning groove
JP3579401B2 (en) Road groove formation method
JP2008308972A (en) Nonslip pavement construction method
JP6856445B2 (en) Manufacturing method of concrete pavement slab and concrete pavement slab
KR101756182B1 (en) Surface treatment method of concrete pavement with multi groove pattern and single groove pattern of asymmetric type
JP2007039944A (en) Antiskid liner for pedestrian crossing
JP3775794B2 (en) Blade assembly and grooving device
CZ290399B6 (en) Road pavement surface treatment
JP2006144225A (en) Road marking forming method
JP2005163511A (en) Embedment of road line
KR101079724B1 (en) Method constructing grooves for non-slip of paved road
JP2004068354A (en) Road-surface antifreezing block and block road-surface using it
KR20110002118A (en) Grooving structural body and the spatial-temporal method of asphalt pavement
KR20150128259A (en) rotor saw for grooving and construction method using rotor saw for grooving
JP7165255B1 (en) Anti-slip road marking
KR100433654B1 (en) Constructing method and structure for sliding prevention section on the road
KR20190010943A (en) Construction for preventing slide of roads
WO2004067847A1 (en) Method of repairing defects of a wearing course of road surface, particularly permanent deformations of its surface and roughness loss
KR100780417B1 (en) Road paving methode for non-skid
JP2004143892A (en) Maintenance-free road surface display paving method
JP3194038B2 (en) Construction method of pavement road with freeze suppression function
JP2898631B1 (en) Structure of road bridge joint and construction method of road bridge joint