JP2008215012A - Building construction method - Google Patents

Building construction method Download PDF

Info

Publication number
JP2008215012A
JP2008215012A JP2007056094A JP2007056094A JP2008215012A JP 2008215012 A JP2008215012 A JP 2008215012A JP 2007056094 A JP2007056094 A JP 2007056094A JP 2007056094 A JP2007056094 A JP 2007056094A JP 2008215012 A JP2008215012 A JP 2008215012A
Authority
JP
Japan
Prior art keywords
building
buildings
aerial
aerial structure
stage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2007056094A
Other languages
Japanese (ja)
Inventor
Yosuke Shiraishi
洋介 白石
Yasushi Nakanishi
康 仲西
Yasushi Shibata
恭伺 柴田
Yoshihiro Ishikawa
善弘 石川
Koji Muranaka
孝司 村中
Akira Nishimura
章 西村
Yoshifumi Kawahara
由史 河原
Sadao Ishibashi
貞雄 石橋
Shigetomo Tateyama
恵朋 立山
Yasuhiko Kimura
康彦 木村
Tsutomu Nohira
勉 野平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP2007056094A priority Critical patent/JP2008215012A/en
Publication of JP2008215012A publication Critical patent/JP2008215012A/en
Pending legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a building construction method, constructing aerial structures of two or more stages at spaces in the direction of height of a building block between two or more blocks of buildings. <P>SOLUTION: Concurrently with the process of performing skeleton construction for two or more building blocks 1, 1, up to a first construction level H<SB>1</SB>of the aerial structure, the principal part 10a of the aerial structure of the first stage is built at the bottom of the building blocks. The principal part 10a is elevated to the first construction level and temporarily fixed to the skeleton of the building block. Concurrently with the process of performing skeleton construction for two or more building blocks 1, 1, up to a second construction level H<SB>2</SB>of the aerial structure, the principal part 20a of the aerial structure of the second stage is built at the bottom between the building blocks, the principal part 10a is elevated up to the second construction level H<SB>2</SB>, temporarily fixed to the skeleton of the building block, and also the principal part 20a is elevated to the first construction level H<SB>1</SB>, and temporarily fixed to the skeleton of the building block. These processes are repeatedly performed according to the number of stages of the aerial structures to be constructed, and the principal parts of the temporarily fixed aerial structures are finally fixed. <P>COPYRIGHT: (C)2008,JPO&INPIT

Description

この発明は、複数の建物棟間に、複数段の空中構造体を、建物棟の高さ方向に間隔をあけて架設して成る建物の構築方法の技術分野に属する。   The present invention belongs to the technical field of a building construction method in which a plurality of stages of aerial structures are installed between a plurality of building ridges at intervals in the height direction of the building wing.

複数の建物棟間に空中構造体を架設して成る建物の構築方法は、例えば、本出願人による下記の特許文献1に開示されており、既に公知である。
この特許文献1に係る建物の構築方法は、同文献1の図1〜図4に示したように、要するに、建物棟1、1を構築する工程と並行して、建物棟1、1間の底部で建物棟1、1間に架設される空中構造体2の主要部を組み立て、建物棟1、1のうち空中構造体2との架設レベルまで躯体構築が完了した後に、前記空中構造体2の主要部を前記架設レベルまで上昇させて建物棟1の躯体へ定着させ、しかる後、建物棟1、1と空中構造体2を完成させる方法である(詳しくは、同文献1の請求項1を参照)。
この構築方法によれば、建物棟1、1の躯体を空中構造体2の架設レベルまで構築した後に、建物棟1、1間に空中構造体2の架設作業を開始する技術と比して、建物棟1、1の躯体構築と並行して空中構造体2の主要部の組み立て作業を行うので作業効率がよく、工期を短縮できる。また、空中構造体2の主要部を地上で組み立てるので、危険な高所作業をなくして、大幅に省力化でき、作業性に優れているし、安全性が高い。さらに、空中構造体2の主要部を建物棟1、1に定着したのち、この空中構造体2を完成させる作業を、当該主要部を足場や作業床として利用できるので、特別な足場や作業床を仮設する必要もないから仮設作業を減じて、合理的、且つ経済的でもある(同文献1の段落[0002]、[0005]、及び[0006]を参照)。
A building construction method in which an aerial structure is constructed between a plurality of building buildings is disclosed in, for example, the following Patent Document 1 by the present applicant, and is already known.
As shown in FIGS. 1 to 4 of the document 1, the building construction method according to Patent Document 1 is basically between the building buildings 1 and 1 in parallel with the process of building the building buildings 1 and 1. After the main part of the aerial structure 2 constructed between the building ridges 1 and 1 is assembled at the bottom, and the building construction is completed up to the construction level with the aerial structure 2 in the building ridges 1 and 1, the aerial structure 2 The main part of the building is raised to the erection level and fixed to the building building 1, and then the building building 1, 1 and the aerial structure 2 are completed (specifically, claim 1 of the document 1). See).
According to this construction method, compared to the technique of starting the construction work of the aerial structure 2 between the building buildings 1 and 1 after the building of the building ridges 1 and 1 is constructed up to the construction level of the aerial structure 2, Since the main part of the aerial structure 2 is assembled in parallel with the building construction of the building buildings 1 and 1, work efficiency is good and the construction period can be shortened. In addition, since the main part of the aerial structure 2 is assembled on the ground, it is possible to eliminate dangerous high-altitude work, greatly reduce labor, and is excellent in workability and high in safety. Furthermore, after fixing the main part of the aerial structure 2 to the buildings 1 and 1, the work to complete the aerial structure 2 can be used as a scaffold or work floor. Therefore, the temporary work is reduced, and it is rational and economical (see paragraphs [0002], [0005], and [0006] of the same document 1).

ところで、特許文献1には、複数の建物棟1、1間に、複数段の空中構造体2…を建物棟1、1の高さ方向に間隔をあけて架設して成る建物の構築方法も、同文献1の段落[0008]に〔別実施例〕として開示されている(同文献1の図5と図6を参照)。
この建物の構築方法は、先ず、建物棟1、1を構築する工程と並行して、建物棟1、1間の底部で建物棟1、1間の上端部に架設される空中構造体2の主要部を組み立て、建物棟1、1のうち空中構造体2との架設レベルまで躯体構築が完了した後に、前記構造物2の主要部を前記架設レベルまで上昇させて建物棟1の躯体へ定着させ、次いで、建物棟1、1間の底部で建物棟1、1間の中間部に架設される空中構造体2を主要部まで組み立て、前記空中構造体2の主要部を建物棟の中間部の架設レベルまで上昇させて建物棟1の中間部の躯体へ定着させることにより、複数の建物棟間に複数段(図示例では2段)の空中構造体を、建物棟の高さ方向に間隔をあけて架設して成る建物を構築する技術である。
By the way, in Patent Document 1, there is also a building construction method in which a plurality of aerial structures 2... Are installed between a plurality of building buildings 1 and 1 at intervals in the height direction of the building buildings 1 and 1. The document [1] is disclosed as [another embodiment] in paragraph [0008] (see FIGS. 5 and 6 of the document 1).
In the building construction method, first, in parallel with the process of constructing the building ridges 1, 1, the aerial structure 2 constructed on the upper end between the building ridges 1, 1 is constructed at the bottom between the building ridges 1, 1. After the main part is assembled and the building construction is completed up to the construction level with the aerial structure 2 of the building buildings 1 and 1, the main part of the structure 2 is raised to the construction level and fixed to the building 1 building Next, the aerial structure 2 constructed in the middle part between the building buildings 1 and 1 is assembled to the main part at the bottom part between the building buildings 1 and 1, and the main part of the aerial structure 2 is assembled to the middle part of the building building. By raising the building level to the middle of the building building 1 and fixing it to the building in the middle of the building building, a plurality of (two in the illustrated example) aerial structures are spaced in the height direction of the building building. This is a technology for constructing a building that is constructed by opening the door.

特許第3115942号公報Japanese Patent No. 3115942

上記特許文献1に係る建物の構築方法によると、一段の空中構造体2を建物棟1、1間へ架設する場合は作業効率良く行える。しかし、2段以上の複数段の空中構造体2を建物棟1、1間へ架設する場合は、上記したように、最上段に架設する空中構造体2から最下段に架設する空中構造体2へ順に定着させる手法で実施するから、作業効率の観点で、下記する点が懸念される。
すなわち、建物棟1、1の躯体構築を、最上段に架設する空中構造体2の架設レベルまで予め構築しておかねばならない。例えば同文献1の図1、図5に示されたように、最上段の空中構造体2を建物棟1、1の頂部に架設する場合は、建物棟1、1の躯体構築を構築予定の高さまでほぼ完成させておかねばならない。
よって、建物棟1、1の躯体構築と並行して組み立て作業を行えるのは、最上段に架設する空中構造体2のみで、以下に架設する他の空中構造体2…は、建物棟1、1の躯体構築がほぼ完了しているにも拘わらず、建物棟1、1間の底部でその主要部を組み立て、架設レベルまで上昇させて建物棟1の躯体へ定着させて当該主要部を空中構造体として完成させる作業を、架設する空中構造体2…の段数に応じて繰り返し行わねばならなかった。
また、これに伴い、当該空中構造体2…を架設レベルへ定着させるまでの一連の作業が完了するまで、建物棟1、1間の底部の施工(例えば、外構仕上げ工事)に着手することができなかった。
以上、要するに、上記特許文献1に係る建物の構築方法によると、2段以上(複数段)の空中構造体2…を建物棟1、1間へ架設する場合は種々の問題があり、作業効率良く行えるとは云えず、改善の余地が残されている。
According to the building construction method according to Patent Document 1 described above, when the one-stage aerial structure 2 is installed between the building ridges 1 and 1, work efficiency can be improved. However, when two or more stages of aerial structures 2 are installed between the building ridges 1 and 1, as described above, the aerial structure 2 is installed from the aerial structure 2 installed at the uppermost stage to the lowermost stage. Therefore, the following points are concerned from the viewpoint of work efficiency.
That is, the building construction of the building buildings 1 and 1 must be constructed in advance up to the construction level of the aerial structure 2 constructed on the uppermost stage. For example, as shown in FIGS. 1 and 5 of the same document 1, when the uppermost aerial structure 2 is installed on the top of the buildings 1 and 1, the building construction of the buildings 1 and 1 is scheduled to be constructed. It must be almost completed to the height.
Therefore, only the aerial structure 2 installed on the uppermost stage can be assembled in parallel with the building construction of the building buildings 1 and 1, and the other aerial structures 2 installed below are the building building 1, In spite of the construction of the main building 1 being almost completed, the main part is assembled at the bottom between the building ridges 1 and 1 and is raised to the erection level to be fixed to the building 1 building. The work to complete as a structure had to be repeated according to the number of steps of the aerial structures 2.
As a result, construction of the bottom part between the building buildings 1 and 1 (for example, exterior finishing work) should be started until a series of operations until the aerial structures 2 are fixed to the construction level is completed. I could not.
In short, according to the building construction method according to Patent Document 1, there are various problems in installing two or more (multiple) aerial structures 2... It can't be done well, but there is room for improvement.

本発明の目的は、複数の建物棟間に、2段以上(複数段)の空中構造体を、建物棟の高さ方向に間隔をあけて架設して成る建物を、複合工程により、作業効率良く合理的に構築することが可能な、経済性に優れた建物の構築方法を提供することにある。   The object of the present invention is to improve the work efficiency of a building comprising two or more (multi-stage) aerial structures between a plurality of building ridges at intervals in the height direction of the building ridge by a complex process. The object is to provide a method for constructing a building that can be constructed reasonably well and that is excellent in economic efficiency.

上記背景技術の課題を解決するための手段として、請求項1に記載した発明に係る建物の構築方法は、
(イ)複数の建物棟の躯体構築を、空中構造体の第1の架設レベルまで行う工程に並行して、その建物棟間の底部で、建物棟間に架設され支持される第1段目の空中構造体の主要部を組立てる工程と、
(ロ)前記複数の建物棟の躯体構築を前記第1の架設レベルまで進めた段階で、前記第1段目の空中構造体の主要部を、前記建物棟に反力をとって前記第1の架設レベルまで上昇させ、建物棟の躯体に仮定着させる工程と、
(ハ)複数の建物棟の躯体構築を、空中構造体の第2の架設レベルまで行う工程に並行して、その建物棟間の底部で、建物棟間に架設され支持される第2段目の空中構造体の主要部を組立てる工程と、
(ニ)前記複数の建物棟の躯体構築を前記第2の架設レベルまで進めた段階で、前記第1段目の空中構造体の主要部を、前記建物棟に反力をとって前記第2の架設レベルまで上昇させ、建物棟の躯体に仮定着させると共に、前記第2段目の空中構造体の主要部を、前記建物棟に反力をとって前記第1の架設レベルまで上昇させ、建物棟の躯体に仮定着させる工程と、
(ホ)以後、上記(ハ)及び(ニ)の工程を、架設する空中構造体の段数に応じて繰り返して行い、仮定着した空中構造体の主要部を本定着させる工程と、から成ることを特徴とする。
As a means for solving the problems of the background art, a building construction method according to the invention described in claim 1 is:
(B) The first stage that is built and supported between the buildings at the bottom between the buildings in parallel with the process of constructing the building of multiple buildings to the first installation level of the aerial structure Assembling the main part of the aerial structure of
(B) At the stage where the building construction of the plurality of building buildings is advanced to the first erection level, the first portion of the first-stage aerial structure is subjected to a reaction force on the building building and the first The process of raising to the construction level of
(C) The second stage that is built and supported between the buildings at the bottom between the buildings in parallel with the process of constructing the buildings of multiple buildings to the second installation level of the aerial structure Assembling the main part of the aerial structure of
(D) When the building construction of the plurality of building buildings is advanced to the second erection level, the second portion of the first-stage aerial structure is subjected to reaction force against the building building To the construction level of the building building, assumed to be attached to the building ridge body, the main part of the second-stage aerial structure is raised to the first construction level by taking a reaction force on the building building, Assuming the process of attaching to the building building
(E) Thereafter, the steps (c) and (d) are repeated according to the number of stages of the aerial structure to be installed, and the main part of the assumed aerial structure is permanently fixed. It is characterized by.

請求項2に記載した発明は、請求項1に記載した建物の構築方法において、
前記空中構造体の主要部は、同主要部に設けた被吊り点にPC鋼線、PC鋼棒等の吊上げ材を取り付け、建物棟間における空中構造体の架設レベルより高い位置にリフトアップ用ジャッキを搭載したリフティングビームを仮設し、前記リフトアップ用ジャッキで前記吊上げ材を吊上げることにより、空中構造体の架設レベルまで上昇させることを特徴とする。
The invention described in claim 2 is the building construction method described in claim 1,
The main part of the aerial structure is lifted to a position higher than the construction level of the aerial structure between building buildings by attaching lifting materials such as PC steel wires and PC steel bars to the suspended points provided in the main part. A lifting beam equipped with a jack is temporarily installed, and the lifting material is lifted by the lift-up jack to raise the aerial structure to a construction level.

請求項3に記載した発明は、請求項1に記載した建物の構築方法において、
前記複数の建物棟は、2棟以上の建物棟を、平面視で、それぞれの建物棟が互いに所定の間隔を隔て、かつ互いに隣接する壁面を、多角形の辺の一部とする多角形配置に構築されており、前記空中構造体は、前記多角形とほぼ同一の平面形状を有することを特徴とする。
The invention described in claim 3 is the building construction method described in claim 1,
The plurality of building ridges are polygonal arrangements in which two or more building ridges are viewed in plan, with the building ridges spaced apart from each other by a predetermined distance, and adjacent wall surfaces being part of the polygon side. The aerial structure has a planar shape substantially the same as the polygon.

請求項4に記載した発明は、請求項1又は3に記載した建物の構築方法において、
前記複数の建物棟は、2棟以上の建物棟を、平面視で、対称配置に構築されていることを特徴とする。
The invention described in claim 4 is the building construction method according to claim 1 or 3,
The plurality of building wings are constructed by symmetrically arranging two or more building ridges in plan view.

請求項1〜請求項4に係る建物の構築方法によれば、建物棟の躯体を空中構造体の架設レベルまで構築した後に、建物棟間に空中構造体の架設作業を開始する技術と比して、下記する効果がある。
1)建物棟1、1の躯体構築と並行して、第1段目〜第3段目の空中構造体10、20、30の各主要部10a、20a、30aの組み立て作業を行うので作業効率が非常によく、工期を大幅に短縮できる。
2)すべての空中構造体10、20、30の主要部10a、20a、30aを地上等の底部で組み立てるので、危険な高所作業を大幅に軽減できる。
3)前記各主要部10a…を建物棟1、1に定着したのち、この空中構造体10…を完成させる作業を、当該各主要部10a…を足場や作業床として利用できるので、特別な足場や作業床を仮設する必要もないから仮設作業を減じて、合理的、且つ経済的である。
According to the building construction method according to claims 1 to 4, compared with the technique of starting the construction work of the aerial structure between the building ridges after constructing the building ridge frame to the construction level of the aerial structure. Have the following effects.
1) Since the assembly of the main parts 10a, 20a, and 30a of the first to third-stage aerial structures 10, 20, and 30 is performed in parallel with the building construction of the buildings 1 and 1, the work efficiency Is very good and can significantly reduce the construction period.
2) Since the main parts 10a, 20a, and 30a of all the aerial structures 10, 20, and 30 are assembled at the bottom such as the ground, dangerous work at a high place can be greatly reduced.
3) Since each main part 10a ... can be used as a scaffold or work floor for the work of completing the aerial structure 10 ... after fixing the main parts 10a ... Since there is no need to install a temporary work floor, the temporary work is reduced, which is rational and economical.

また、請求項1〜請求項4に係る建物の構築方法によれば、上記特許文献1に開示された技術と比して、下記する効果がある。
4)建物棟1、1の躯体構築と並行して、第1段目の空中構造体10の主要部10aのみならず、第2段目、第3段目の空中構造体20、30の各主要部20a、30aの組み立て作業を行い得るので、作業効率が非常に良く、合理的であり、工期を大幅に短縮できる。これに伴い、コスト削減に寄与する。
5)特に、請求項2に係る建物の構築方法によれば、上記効果に加えて、空中構造体10…の主要部10a…をバランス良く吊上げ可能なように、被吊り点、及び吊り点(リフトアップ用ジャッキJ、J)の数を容易に増減できると共に、それらの平面上の位置を自在に調整できるので、当該主要部10a…がより広大で大掛かりな構造となったとしても、安定した状態でリフトアップ作業を行うことができるので、安全性の向上に寄与する。
Moreover, according to the building construction method according to claims 1 to 4, the following effects can be obtained as compared with the technique disclosed in the above-mentioned Patent Document 1.
4) In parallel with the building construction of the buildings 1 and 1, not only the main part 10a of the first-stage aerial structure 10, but also the second- and third-stage aerial structures 20 and 30 Since the main parts 20a and 30a can be assembled, the work efficiency is very good and reasonable, and the construction period can be greatly shortened. This contributes to cost reduction.
5) In particular, according to the building construction method according to claim 2, in addition to the above-described effects, the suspended point and the suspended point ( The number of lift-up jacks J 1 , J 2 ) can be easily increased or decreased, and the position on the plane can be freely adjusted. Therefore, even if the main part 10a is a larger and larger structure, Since the lift-up operation can be performed in a stable state, it contributes to the improvement of safety.

本発明に係る、複数の建物棟間に複数段の空中構造体を建物棟の高さ方向に間隔をあけて架設して成る建物の構築方法は、上述した発明の効果を奏するべく、
(イ)複数の建物棟の躯体構築を、空中構造体の第1の架設レベルまで行う工程に並行して、その建物棟間の底部で、建物棟間に架設され支持される第1段目の空中構造体の主要部を組立てる工程と、
(ロ)前記複数の建物棟の躯体構築を前記第1の架設レベルまで進めた段階で、前記第1段目の空中構造体の主要部を、前記建物棟に反力をとって前記第1の架設レベルまで上昇させ、建物棟の躯体に仮定着させる工程と、
(ハ)複数の建物棟の躯体構築を、空中構造体の第2の架設レベルまで行う工程に並行して、その建物棟間の底部で、建物棟間に架設され支持される第2段目の空中構造体の主要部を組立てる工程と、
(ニ)前記複数の建物棟の躯体構築を前記第2の架設レベルまで進めた段階で、前記第1段目の空中構造体の主要部を、前記建物棟に反力をとって前記第2の架設レベルまで上昇させ、建物棟の躯体に仮定着させると共に、前記第2段目の空中構造体の主要部を、前記建物棟に反力をとって前記第1の架設レベルまで上昇させ、建物棟の躯体に仮定着させる工程と、
(ホ)以後、上記(ハ)及び(ニ)の工程を、架設する空中構造体の段数に応じて繰り返して行い、仮定着した空中構造体の主要部を本定着させる工程をもって実施する。
According to the present invention, a building construction method in which a plurality of stages of aerial structures are installed at intervals in the height direction of a building building between a plurality of building buildings, the effects of the invention described above are achieved.
(B) The first stage that is built and supported between the buildings at the bottom between the buildings in parallel with the process of constructing the building of multiple buildings to the first installation level of the aerial structure Assembling the main part of the aerial structure of
(B) At the stage where the building construction of the plurality of building buildings is advanced to the first erection level, the first portion of the first-stage aerial structure is subjected to a reaction force on the building building and the first The process of raising to the construction level of
(C) The second stage that is built and supported between the buildings at the bottom between the buildings in parallel with the process of constructing the buildings of multiple buildings to the second installation level of the aerial structure Assembling the main part of the aerial structure of
(D) When the building construction of the plurality of building buildings is advanced to the second erection level, the second portion of the first-stage aerial structure is subjected to reaction force against the building building To the construction level of the building building, assumed to be attached to the building ridge body, the main part of the second-stage aerial structure is raised to the first construction level by taking a reaction force on the building building, Assuming the process of attaching to the building building
(E) Thereafter, the steps (c) and (d) are repeated according to the number of stages of the aerial structure to be installed, and the main part of the assumed aerial structure is permanently fixed.

図1A〜Fは、請求項1に記載した建物の構築方法の枢要な工程を段階的に示している。この建物の構築方法は、複数の建物棟1、1間に、複数段の空中構造体10、20、30を建物棟1、1の高さ方向に間隔をあけて順に架設して成る建物の構築方法である。   1A to F show step-by-step steps of a building construction method according to claim 1. In this building construction method, a plurality of aerial structures 10, 20, 30 are erected between a plurality of building ridges 1, 1 in order at intervals in the height direction of the building ridges 1, 1. It is a construction method.

先ず、図1Aに示したように、複数の建物棟1、1の躯体構築を、空中構造体の第1の架設レベルHまで行う工程に並行して、その建物棟1、1間の底部で、建物棟1、1間に架設され支持される第1段目の空中構造体10の主要部10aを組立てる(前記(イ)の工程)。
図1Bに示したように、前記複数の建物棟1、1の躯体構築を前記第1の架設レベルHまで進めた段階で、前記第1段目の空中構造体10の主要部10aを、前記建物棟1、1に反力をとって前記第1の架設レベルHまで上昇させ、建物棟1、1の躯体に仮定着させる(前記(ロ)の工程)。
図1Cに示したように、複数の建物棟1、1の躯体構築を、空中構造体の第2の架設レベルHまで行う工程に並行して、その建物棟1、1間の底部で、建物棟1、1間に架設され支持される第2段目の空中構造体20の主要部20aを組立てる(前記(ハ)の工程)。
図1Dに示したように、前記複数の建物棟1、1の躯体構築を前記第2の架設レベルHまで進めた段階で、前記第1段目の空中構造体10の主要部10aを、前記建物棟1、1に反力をとって前記第2の架設レベルHまで上昇させ、建物棟1、1の躯体に仮定着させると共に、前記第2段目の空中構造体20の主要部20aを、前記建物棟1、1に反力をとって前記第1の架設レベルHまで上昇させ、建物棟1、1の躯体に仮定着させる(前記(ニ)の工程)。
図1Eに示したように、複数の建物棟1、1の躯体構築を、空中構造体の第3の架設レベルHまで行う工程に並行して、その建物棟1、1間の底部で、建物棟1、1間に架設され支持される第3段目の空中構造体30を主要部30aまで組立てる(前記(ホ)に係る(ハ)の工程)。
図1Fに示したように、前記複数の建物棟1、1の躯体構築を前記第3の架設レベルHまで進めた段階で、前記第1段目の空中構造体10の主要部10aを、前記建物棟1、1に反力をとって前記第3の架設レベルHまで上昇させ、建物棟1、1の躯体に仮定着させ、次いで、前記第2段目の空中構造体20の主要部20aを、前記建物棟1、1に反力をとって前記第2の架設レベルHまで上昇させ、建物棟1、1の躯体に仮定着させ、次いで、前記第3段目の空中構造体30の主要部30aを、前記建物棟1、1に反力をとって前記第1の架設レベルHまで上昇させ、建物棟1、1の躯体に仮定着させる工程を、前足(前記主要部10a、20a)が前進した後の位置(前記架設レベルH、H)に、後足(前記主要部20a、30a)が到着する、いわゆる尺取り虫の歩行のように順に行う(前記(ホ)に係る(ニ)の工程)。
仮定着したすべての空中構造体10、20、30の主要部10a、20a、30aを本定着させる(前記(ホ)の工程)。なお、本定着作業は、ほぼ同時に行ってもよいし、前記主要部10a、20a、30aの順に行ってもよく、作業工程上や躯体構築を進める際の構造設計上、不合理とならない限り適宜選択して適用できる。
First, as shown in FIG. 1A, in parallel with the process of constructing the building of a plurality of building buildings 1 and 1 up to the first erection level H1 of the aerial structure, the bottom portion between the building buildings 1 and 1 Thus, the main part 10a of the first-stage aerial structure 10 that is installed and supported between the building ridges 1 and 1 is assembled (step (b)).
As shown in FIG. 1B, when the building construction of the plurality of building buildings 1 and 1 is advanced to the first erection level H1, the main part 10a of the first-stage aerial structure 10 is A reaction force is applied to the building ridges 1 and 1 and is raised to the first erection level H 1 so that the building ridges 1 and 1 are attached to the housing (step (b)).
As shown in FIG. 1C, the precursor construction of multiple buildings buildings 1,1, in parallel with the process carried out until erection level H 2 second aerial structures, at the bottom between the building Building 1,1, The main part 20a of the second-stage aerial structure 20 that is installed and supported between the building buildings 1 and 1 is assembled (step (c)).
As shown in FIG. 1D, at the stage where the building construction of the plurality of building buildings 1 and 1 is advanced to the second erection level H2, the main portion 10a of the first-stage aerial structure 10 is A reaction force is applied to the building ridges 1 and 1 to raise to the second erection level H 2, and is assumed to be attached to the housing of the building ridges 1 and 1, and the main part of the second-stage aerial structure 20. 20a is raised to the first erection level H1 by applying a reaction force to the building ridges 1 and 1 and is assumed to be attached to the housing of the building ridges 1 and 1 (step (d)).
As shown in FIG. 1E, a precursor construction of multiple buildings buildings 1,1, in parallel with the step of performing up to the third erection level H 3 of the aerial structures, at the bottom between the building Building 1,1, The third-stage aerial structure 30 that is installed and supported between the building buildings 1 and 1 is assembled up to the main part 30a (step (c) related to (e)).
As shown in FIG. 1F, at the stage where the building construction of the plurality of building buildings 1 and 1 is advanced to the third erection level H3, the main part 10a of the first-stage aerial structure 10 is The reaction force is applied to the building ridges 1 and 1 and is raised to the third erection level H 3 to be presupposed to the housing of the building ridges 1 and 1, and then the main structure of the second-stage aerial structure 20 The part 20a is raised to the second erection level H2 by taking a reaction force on the building ridges 1 and 1 and is assumed to be attached to the housing of the building ridges 1 and 1, and then the aerial structure of the third stage the main portion 30a of the body 30, by taking the reaction force to the building building 1,1 raised until said first bridging level H 2, the step of temporarily fixing the skeleton of the building building 1,1, forefoot (the main part 10a, the position after the 20a) is advanced (the erection level H 2, H 1), hind paw (the main part 2 a, 30a) arrives, performed in the order as in the walking-called inchworm step (the (E) according to (d)).
The main parts 10a, 20a, 30a of all the assumed aerial structures 10, 20, 30 are permanently fixed (step (e)). The main fixing operation may be performed almost simultaneously, or may be performed in the order of the main parts 10a, 20a, and 30a. As long as it is not unreasonable in terms of the work process and the structural design when proceeding with the building construction, Select and apply.

しかる後、図2A、Bに示したように、複数の建物棟1、1を所要の高さまで構築して完成させると共に、本定着したすべての空中構造体10…の主要部10a…をそれぞれ、空中構造体10…として完成させる。   After that, as shown in FIGS. 2A and 2B, the plurality of building buildings 1 and 1 are constructed and completed to a required height, and the main parts 10a of all the aerial structures 10 are fixed. It is completed as an aerial structure 10.

前記建物棟1は、一例として、柱、梁の躯体が鉄骨造り、或いは鉄筋コンクリート造りで、床がサイト成形のPC版で、外装がカーテンウォールの高層、或いは、超高層の構造体で実施している。ちなみに、本実施例では、建物棟1の幅寸(敷地面積)が20m×20m程度で、高さが140m(42階建て)程度と、アスペクト比が7程度の高層の建物棟1を想定しているが、低層の建物棟でも勿論同様に実施可能である。また、本実施例1では、図2A、Bに示したように、2棟の建物棟1を、平面視で、左右対称な大きさ、及び配置で構築しているがこれに限定されず、後の実施例2で説明するように、3棟以上でも実施できる(図4、図11参照、請求項4記載の発明)。   As an example, the building ridge 1 is constructed with a pillar or beam housing made of steel or reinforced concrete, a floor is a site-molded PC version, and the exterior is a high-rise or super-high-rise structure with curtain walls. Yes. By the way, in this embodiment, the building building 1 is assumed to be a high-rise building building 1 having a width dimension (site area) of about 20 m × 20 m, a height of about 140 m (42 stories), and an aspect ratio of about 7. However, it can of course be similarly applied to low-rise buildings. In the first embodiment, as shown in FIGS. 2A and 2B, the two building ridges 1 are constructed with symmetrical sizes and arrangements in plan view, but not limited thereto. As will be described later in Example 2, the invention can be implemented in three or more buildings (see FIGS. 4 and 11, the invention described in claim 4).

前記第1段目〜第3段目の空中構造体10、20、30はそれぞれ、本実施例ではトラス構造等の鉄骨造りをベースに直方体状に形成しているが、建物棟1、1間に架設され支持されることが可能な大きさ(形状)と剛性を有する構造であれば種々のバリエーションで実施可能である。例えば、本出願人が先に出願した特願2006−254643の段落[0019]、及び特願2006−254677の段落[0018]に開示したような、下弦材の両端部(或いは一端部)に相当する位置にダンパー部材を設けたトラス構造でも実施可能である。勿論、上記特許文献1で開示したような、鉄骨梁、鉄骨柱、及び斜材鉄骨等を組み合わせて成り、中央部に上下に貫通する環状等の孔を形成した構造でも実施可能である。この空中構造体10…は、完成後、通路、或いは居住者の憩いの空間等に供される。
また、図示例に係る前記第1段目〜第3段目の空中構造体10、20、30は、建物棟1、1間の高さ方向に所定の間隔をあけて3段架設して実施しているが、2段でも実施できるし、4段以上でも実施できる。ちなみに、本実施例では、第1段目の空中構造体10を37階部分に架設し、第2段目の空中構造体20を26階部分に架設し、第3段目の空中構造体30を15階部分に架設した場合を想定している。
The aerial structures 10, 20, 30 of the first to third stages are each formed in a rectangular parallelepiped shape based on a steel structure such as a truss structure in this embodiment. As long as the structure has a size (shape) and rigidity capable of being installed and supported on the hood, it can be implemented in various variations. For example, it corresponds to both end portions (or one end portions) of the lower chord material as disclosed in paragraph [0019] of Japanese Patent Application No. 2006-254463 and paragraph [0018] of Japanese Patent Application No. 2006-254677 filed earlier by the present applicant. It is also possible to implement a truss structure in which a damper member is provided at the position. Of course, the present invention can also be implemented by a structure in which a steel beam, a steel column, a diagonal steel frame, and the like are disclosed in Patent Document 1 and an annular hole or the like penetrating vertically is formed in the central portion. The aerial structures 10 are used for a passage or a resident's rest space after completion.
The first to third aerial structures 10, 20, and 30 according to the illustrated example are installed in three stages at predetermined intervals in the height direction between the building buildings 1 and 1. However, it can be implemented in two stages or in four or more stages. Incidentally, in the present embodiment, the first-stage aerial structure 10 is constructed on the 37th floor, the second-stage aerial structure 20 is constructed on the 26th-floor, and the third-stage aerial structure 30 is provided. Is assumed to be installed on the 15th floor.

前記(イ)の工程について、建物棟1、1の躯体構築と並行して、建物棟1、1間の底部の架台2上で組み立てる第1段目の空中構造体10の主要部10aは、本実施例では、図1A等に示したように、H形鋼等の鉄骨部材により、少なくとも建物棟1、1間に架設され支持されることが可能な大きさ(形状)と剛性を有するトラス構造を組み立てて実施している。この時点で、前記第1段目の空中構造体10について、主要部10aのみを組み立ててその全体を完成させない理由は、組立て後のリフトアップ作業を考慮すると、できるだけ軽量化した方が作業上、及び安全上好ましいからである。
なお、本実施例では、空中構造体10…の主要部10aを、地面に設置した架台2上で組み立てているがこれに限定されず、例えば、建物棟1、1間にテナント等の低層建物を予め構築しておいて進める場合には、当該低層建物の屋上部分を作業ステージとして利用し、当該屋上部分に設置した架台2上で空中構造体10の主要部10aの組み立て作業を行う。
About the process (a), in parallel with the building construction of the building buildings 1 and 1, the main part 10a of the first-stage aerial structure 10 assembled on the base 2 at the bottom between the building buildings 1 and 1 is: In this embodiment, as shown in FIG. 1A and the like, a truss having a size (shape) and rigidity capable of being installed and supported at least between the building buildings 1 and 1 by a steel member such as an H-shaped steel. The structure is assembled and implemented. At this point, the reason why the first-stage aerial structure 10 is not assembled only by assembling only the main part 10a is that, in consideration of lift-up work after assembly, it is better to reduce the weight as much as possible. It is also preferable for safety.
In the present embodiment, the main part 10a of the aerial structure 10 is assembled on the gantry 2 installed on the ground, but is not limited to this. For example, a low-rise building such as a tenant between the building buildings 1 and 1 is used. Is constructed in advance, the roof portion of the low-rise building is used as a work stage, and the assembling work of the main portion 10a of the aerial structure 10 is performed on the gantry 2 installed on the roof portion.

前記(ロ)の工程について、前記第1段目の空中構造体10の主要部10aを上昇させる手段は、上記特許文献1で開示した手法とほぼ同様であり、図3に示したように、前記主要部10aの四隅にバランスよく設けた被吊り点3にワイヤ4を取り付け、建物棟1、1の躯体における第1段目の空中構造体10の第1の架設レベルHより高い位置(図示例では上端部)に各々設けた井桁状の架台5に取り付けた滑車装置6に前記ワイヤ4を巻き掛け、地上等に設置したウインチ7で前記ワイヤ4を巻き取ることにより、地上で組み立てた前記第1段目の空中構造体10の主要部10aを前記第1の架設レベルHまで上昇させている(図1B参照)。なお、前記主要部10aの上昇を案内するガイドレールは、図示の便宜上省略している。
前記架台2は勿論、前記滑車装置6、及びこれを支持する井桁状の架台5、並びにガイドレールは事後に撤去する。
ちなみに、前記第1段目の空中構造体10の主要部10aを上昇させる手段はこれに限定されず、後の実施例2で説明するような手段でも実施できるし、所謂プッシュアップ工法(空中構造体10…の主要部10a…を下方から支持した状態にて、当該主要部10a…を下方から上方へ押し上げる手段(例えば、油圧ジャッキ)を用いて、逐次に押し上げる工法)でも実施できる。
また、前記第1段目の空中構造体10の主要部10aを、建物棟1の躯体に仮定着させる手法は、本実施例では、トラス構造の上弦材及び下弦材を構成するH形鋼等の鉄骨部材の端部を、対応する建物棟1の躯体を構成する鉄骨柱、或いは鉄骨梁に、ボルトで仮締めして実施している。以下の工程において、空中構造体10…の主要部10a…を建物棟1の躯体に仮定着する場合も同様に行う。
Regarding the step (b), the means for raising the main portion 10a of the first-stage aerial structure 10 is substantially the same as the method disclosed in Patent Document 1, and as shown in FIG. the main portion 10a at four corners on the mounting well-balanced wire 4 to be suspended point 3 provided in, higher than the first erection level H 1 of the first stage of the airborne structure 10 in the skeleton of a building building 1,1 position ( The wire 4 is wound around a pulley device 6 attached to a cross-girder-shaped mount 5 provided at each of the upper ends in the illustrated example, and the wire 4 is wound up by a winch 7 installed on the ground or the like, and assembled on the ground. The main portion 10a of the first-stage aerial structure 10 is raised to the first erection level H1 (see FIG. 1B). In addition, the guide rail which guides the raise of the said main part 10a is abbreviate | omitted for convenience of illustration.
The pulley 2 as well as the pulley device 6, the cross-girder-like frame 5 that supports the pulley device 6, and the guide rail are removed after the fact.
Incidentally, the means for raising the main part 10a of the first-stage aerial structure 10 is not limited to this, and it can be implemented by means as described in Example 2 later, or a so-called push-up method (aerial structure). It is also possible to implement by a means of pushing up the main parts 10a ... from below to the upper part (for example, a hydraulic jack) while supporting the main parts 10a ... of the bodies 10 ... from below.
In addition, in the present embodiment, the method of presumably attaching the main portion 10a of the first-stage aerial structure 10 to the housing of the building ridge 1 is an H-section steel that constitutes the upper chord member and the lower chord member of the truss structure, etc. The end of the steel member is temporarily tightened to the steel column or the steel beam constituting the housing of the corresponding building 1 with a bolt. In the following steps, the same process is performed when the main parts 10a of the aerial structures 10 are assumed to be attached to the housing of the building 1.

前記(ハ)の工程について、第2段目の空中構造体20の主要部20aを、前記主要部10aと同様に、建物棟1、1間の底部の架台2上で、H形鋼等の鉄骨部材により、少なくとも建物棟1、1間に架設され支持されることが可能な大きさ(形状)と剛性を有するトラス構造を組み立てる。   In the step (c), the main part 20a of the second-stage aerial structure 20 is made of H-section steel or the like on the base 2 at the bottom between the building buildings 1 and 1 in the same manner as the main part 10a. A truss structure having a size (shape) and rigidity capable of being installed and supported at least between the building buildings 1 and 1 is assembled by the steel frame member.

前記(ニ)の工程について、前記空中構造体10、20の主要部10a、20aをそれぞれ、順に第2の架設レベルH、第1の架設レベルHまで上昇させる手段は、上述した第1段目の空中構造体10を上昇させる手段とほぼ同様である。即ち、図示は省略するが、前記主要部10aの四隅にバランスよく設けた被吊り点にワイヤを取り付け、建物棟1、1の躯体における上端部に設けた井桁状の架台に取り付けた滑車装置に前記ワイヤを巻き掛けた後、当該主要部10aの仮定着状態を解除してフリーとし、しかる後、地上等に設置したウインチ7で前記ワイヤ4を巻き取ることにより、前記第1段目の空中構造体10の主要部10aを前記架設レベルHまでリフトアップして建物棟1、1の躯体に仮定着させる。次いで、地上で組み立てた前記主要部20aの四隅にバランスよく設けた被吊り点にワイヤを取り付け、前記滑車装置に前記ワイヤを巻き掛け、前記ウインチで前記ワイヤを巻き取ることにより、前記主要部10aを前記架設レベルHまでリフトアップして建物棟1、1の躯体に仮定着させる(図1D参照)。なお、前記第1段目の空中構造体10の主要部10aを第1の架設レベルHまでリフトアップした場合と同様に、架台2、滑車装置、及びこれを支持する井桁状の架台、並びにガイドレールは事後に撤去する。 In the step (d), the means for raising the main portions 10a and 20a of the aerial structures 10 and 20 to the second erection level H 2 and the first erection level H 1 , respectively, in order This is almost the same as the means for raising the aerial structure 10 at the stage. In other words, although not shown in the drawings, a pulley is attached to a suspended point provided in a well-balanced manner at the four corners of the main part 10a and attached to a cross-girder-like gantry provided at the upper end of the building of the buildings 1 and 1. After the wire is wound, the assumed wearing state of the main part 10a is released to make it free, and then the wire 4 is wound up by the winch 7 installed on the ground or the like, whereby the first-stage air the main portion 10a of the structure 10 lifted up until the erection level H 2 is temporarily fixed to the skeleton of the building building 1,1. Next, wires are attached to suspension points provided in a well-balanced manner at the four corners of the main part 20a assembled on the ground, the wire is wound around the pulley device, and the wire is wound by the winch, thereby the main part 10a. lifted up until the erection level H 1 is temporarily fixed to the skeleton of the building building 1,1 (see FIG. 1D). As in the case where the main portion 10a of the first-stage aerial structure 10 is lifted up to the first erection level H1, the gantry 2, the pulley device, and the cross-girder-like gantry supporting the gantry, The guide rail will be removed after the fact.

前記(ホ)の工程について、図1Eに示したように、建物棟1、1の躯体構築と並行して、第3段目の空中構造体30の主要部30aを、建物棟1、1間の底部の架台2上で、前記主要部10a、20aと同様に、H形鋼等の鉄骨部材により、少なくとも建物棟1、1間に架設され支持されることが可能な大きさ(形状)と剛性を有するトラス構造を組み立てる。   In the step (e), as shown in FIG. 1E, in parallel with the building construction of the buildings 1 and 1, the main part 30a of the third-stage aerial structure 30 is moved between the buildings 1 and 1. The size (shape) that can be laid and supported at least between the building ridges 1 and 1 by a steel frame member such as H-shaped steel, similar to the main portions 10a and 20a. Assemble the truss structure with rigidity.

また、図1Fに示したように、前記空中構造体10、20、30の主要部10a、20a、30aをそれぞれ、順に第3の架設レベルH、第2の架設レベルH、第1の架設レベルHまで上昇させる手段は、上述した第1段目の空中構造体10を第1の架設レベルHまで上昇させる手段とほぼ同様である。
即ち、図示は省略するが、前記空中構造体の10の主要部10aの四隅にバランスよく設けた被吊り点にワイヤを取り付け、建物棟1、1の躯体における上端部に設けた井桁状の架台に取り付けた滑車装置に前記ワイヤを巻き掛けた後、当該主要部10aの仮定着状態を解除してフリーとし、しかる後、地上等に設置したウインチで前記ワイヤを巻き取ることにより、前記第1段目の空中構造体10の主要部10aを前記第3の架設レベルHまで上昇させて建物棟1、1の躯体に仮定着させる。
次いで、前記空中構造体20の主要部20aの四隅にバランスよく設けた被吊り点にワイヤを取り付け、前記滑車装置に前記ワイヤを巻き掛けた後、当該主要部20aの仮定着状態を解除してフリーとし、しかる後、前記ウインチで前記ワイヤを巻き取ることにより、前記第2段目の空中構造体20の主要部20aを前記第2の架設レベルHまで上昇させて建物棟1、1の躯体に仮定着させる。
次いで、地上で組み立てた前記空中構造体30の主要部30aの四隅にバランスよく設けた被吊り点にワイヤを取り付け、前記滑車装置に前記ワイヤを巻き掛け、前記ウインチで前記ワイヤを巻き取ることにより、前記主要部30aを前記第1の架設レベルHまで上昇させて建物棟1、1の躯体に仮定着させる。
Further, as shown in FIG. 1F, the main portions 10a, 20a, 30a of the aerial structures 10, 20, 30 are respectively connected to the third erection level H 3 , the second erection level H 2 , the first erection level, respectively. means for raising up erection level H 1 is substantially similar to the means for raising the first stage aerial structure 10 described above to the first erection level H 1.
In other words, although not shown in the drawing, a wire is attached to the suspended points provided in a well-balanced manner at the four corners of the 10 main parts 10a of the aerial structure, and the cross-girder-like gantry provided at the upper end of the building of the building ridges 1 and 1 After the wire is wound around the pulley device attached to the main body 10a, the assumed wearing state of the main portion 10a is released to make it free, and then the first wire is wound by a winch installed on the ground or the like, thereby The main part 10a of the aerial structure 10 at the stage is raised to the third erection level H3 and is assumed to be attached to the buildings of the building buildings 1 and 1.
Next, wires are attached to suspension points provided in a well-balanced manner at the four corners of the main part 20a of the aerial structure 20, and after the wire is wound around the pulley device, the assumed wearing state of the main part 20a is released. After that, the main part 20a of the second-stage aerial structure 20 is raised to the second erection level H2 by winding the wire with the winch so that the buildings 1 and 1 Assumed to be attached to the body.
Next, by attaching wires to suspension points provided in a well-balanced manner at the four corners of the main part 30a of the aerial structure 30 assembled on the ground, winding the wire around the pulley device, and winding the wire with the winch The main part 30a is raised to the first erection level H1 and is assumed to be attached to the buildings of the building buildings 1 and 1.

そして、前記第3段目の空中構造体30の主要部30aを建物棟1、1間の前記第1の架設レベルHに仮定着させた後、図2A、Bに示したように、建物棟1、1を構築予定の高さまで完成させると共に、仮定着したすべての空中構造体10、20、30の主要部10a、20a、30aを当該部位で本定着させ、当該主要部10a、20a、30aを足場や作業床として利用し、各空中構造体10…の各主要部10a…以外の残りの部分をそれぞれ施工して、すべての空中構造体10、20、30を完成させるのである。
前記各主要部10a…を、建物棟1の躯体に本定着させる手法は、一例として、トラス構造の上弦材及び下弦材を構成するH形鋼等の鉄骨部材の端部を、対応する建物棟1の躯体を構成する鉄骨柱、或いは鉄骨梁に、ボルト又は溶接等の接合手段で強固に剛結して連結する。
After said third stage main portion 30a of the aerial structure 30 is temporarily fixed to the first erection level H 1 between the building Building 1,1, as shown FIG. 2A, the B, building The ridges 1 and 1 are completed to the height to be built, and the main parts 10a, 20a, and 30a of all the aerial structures 10, 20, and 30 that are supposedly attached are permanently fixed at the corresponding parts, and the main parts 10a, 20a, and 30a is used as a scaffold or work floor, and the remaining portions other than the main portions 10a of each aerial structure 10 are respectively constructed to complete all the aerial structures 10, 20, 30.
The method of permanently fixing each of the main parts 10a to the frame of the building ridge 1 is, for example, the end of the steel member such as H-shaped steel constituting the upper chord material and the lower chord material of the truss structure corresponding to the building ridge. It is firmly connected to a steel column or a steel beam constituting one housing by a joining means such as a bolt or welding.

ちなみに、建物棟1、1間に架設する空中構造体の段数が2段の場合は、前記(ホ)に係る(ハ)及び(ニ)の工程は不要であり、前記(イ)〜(ニ)の工程を経た後に、複数の建物棟1、1を完成させると共に、前記空中構造体10、20を完成させるための仕上げ工程(防水工事、植栽工事等を含む。以下同じ。)を行う。また、前記空中構造体の段数が3段以上であれば、前記(イ)〜(ニ)の工程を経て、前記(ホ)の工程を当該空中構造体の段数に応じて繰り返した後に、複数の建物棟1、1を完成させる共に、前記空中構造体10…を完成させるための仕上げ工程を行うのである。   Incidentally, when the number of steps of the aerial structure erected between the building ridges 1 and 2 is two, the steps (c) and (d) relating to the above (e) are not necessary. ), A plurality of building ridges 1 and 1 are completed, and a finishing process (including waterproofing work, planting work, etc.) for completing the aerial structures 10 and 20 is performed. . In addition, if the number of stages of the aerial structure is three or more, after repeating the steps (a) to (d) and repeating the process (e) according to the number of stages of the aerial structure, The building buildings 1 and 1 are completed, and a finishing process for completing the aerial structures 10 is performed.

したがって、上記構成の建物の構築方法によれば、建物棟の躯体を空中構造体の架設レベルまで構築した後に、建物棟間に空中構造体の架設作業を開始する技術と比して、建物棟1、1の躯体構築と並行して、第1段目〜第3段目の空中構造体10、20、30の各主要部10a、20a、30aの組み立て作業を行うので作業効率が非常によく、工期を大幅に短縮できる。また、すべての空中構造体10、20、30の主要部10a、20a、30aを地上等の底部で組み立てるので、危険な高所作業を大幅に軽減できる。さらに、前記各主要部10a…を建物棟1、1に定着したのち、この空中構造体10…を完成させる作業を、当該各主要部10a…を足場や作業床として利用できるので、特別な足場や作業床を仮設する必要もないから仮設作業を減じて、合理的、且つ経済的である。   Therefore, according to the construction method of the building having the above configuration, the building building is compared with the technique of starting the construction work of the aerial structure between the building buildings after the building body is built to the level of the aerial structure. In parallel with the construction of the first and first housings, the main parts 10a, 20a, 30a of the first to third stage aerial structures 10, 20, 30 are assembled so that the work efficiency is very good. The construction period can be greatly shortened. Moreover, since the main parts 10a, 20a, and 30a of all the aerial structures 10, 20, and 30 are assembled at the bottom part such as the ground, dangerous high place work can be greatly reduced. Further, after fixing the main parts 10a to the building ridges 1 and 1, the work to complete the aerial structure 10 can be used as a scaffold or work floor. Since there is no need to install a temporary work floor, the temporary work is reduced, which is rational and economical.

また、上記構成の建物の構築方法によれば、上記特許文献1に開示された技術と比して、建物棟1、1の躯体構築と並行して、第1段目の空中構造体10の主要部10aのみならず、第2、第3段目の空中構造体20、30の各主要部20a、30aの組み立て作業を行い得るので、作業効率が非常に良く、合理的であり、工期を大幅に短縮できる。これに伴い、コスト削減に大きく寄与する。   Moreover, according to the building construction method having the above-described configuration, the first-stage aerial structure 10 is parallel to the building construction of the building buildings 1 and 1 as compared with the technique disclosed in Patent Document 1. Since not only the main part 10a but also the main parts 20a and 30a of the second and third stage aerial structures 20 and 30 can be assembled, the work efficiency is very good, reasonable, and the construction period is long. Can be greatly shortened. This greatly contributes to cost reduction.

図4は、請求項1に記載した建物の構築方法の異なる実施例を示している。この建物の構築方法は、上記実施例1と比して、前記建物棟1と同形・同大の建物棟1を3棟設けて実施していること、及びこれに伴い建物棟1、1、1間に架設する第1段目〜第3段目の
空中構造体10、20、30とその主要部10a、20a、30aの形状を平面視で、ほぼ六角形状に形成していること、並びに前記各主要部10a、20a、30aを上昇させる手段、が主に相違する。
よって、この実施例2に係る建物の構築方法の手順は、上述した実施例1に係る前記(イ)〜(ホ)の工程と同様の工程で行うので、図1A〜Fの工程図を援用すると共に、その説明を適宜割愛する。
FIG. 4 shows a different embodiment of the building construction method described in claim 1. Compared to the first embodiment, this building construction method is implemented by providing three building buildings 1 having the same shape and the same size as the building building 1, and accompanying this, building buildings 1, 1, The first- to third-stage aerial structures 10, 20, 30 and the main parts 10 a, 20 a, 30 a laid between 1 and 2 are formed in a substantially hexagonal shape in plan view; and Means for raising the main parts 10a, 20a, 30a are mainly different.
Therefore, since the procedure of the building construction method according to the second embodiment is performed in the same steps as the above-described steps (a) to (e) according to the first embodiment, the process diagrams of FIGS. The explanation is omitted as appropriate.

この実施例2に係る建物の構築方法は、図4に示したように、3棟の建物棟1、1、1を、平面視で、それぞれの建物棟1、1、1が互いに所定の間隔を隔て、かつ互いに隣接する壁面を、多角形(図示例では六角形)の辺の一部とする多角形配置に構築されており、前記空中構造体は、前記多角形とほぼ同一の平面形状を有している(請求項3記載の発明)。具体的に、図示例に係る複数の建物棟は、3棟の建物棟1、1、1を、平面視で、その中心がほぼ正三角形の各頂点に位置する対称配置にバランス良く構築されており、当該3棟の建物棟1、1、1間に架設される第1段目〜第3段目の空中構造体10、20、30は、平面視で、ほぼ六角形状に形成されている。   In the building construction method according to the second embodiment, as shown in FIG. 4, the three building buildings 1, 1, 1 are viewed in plan, and the building buildings 1, 1, 1 are spaced apart from each other by a predetermined distance. Are constructed in a polygonal arrangement in which the wall surfaces adjacent to each other are part of the sides of a polygon (in the illustrated example, a hexagon), and the aerial structure has substantially the same planar shape as the polygon (Invention of claim 3) Specifically, the plurality of building buildings according to the illustrated example are constructed in a balanced manner in a symmetrical arrangement in which the three building buildings 1, 1, 1 are located at the vertices of substantially equilateral triangles in plan view. The first to third aerial structures 10, 20, and 30 erected between the three building buildings 1, 1, 1 are substantially hexagonal in plan view. .

前記(イ)の工程により地上で組み立てた第1段目の空中構造体10の主要部10aを、前記(ロ)の工程にしたがい、図1Aから図1Bの第1の架設レベルHまで上昇させる手段は、図5〜図7に示したように、当該主要部10aに設けた計6箇所の被吊り点T、Tに、後述するリフトアップ用ジャッキJ、Jから垂れ下がるPC鋼線(又はPC鋼棒)等の吊上げ材13を取り付け、建物棟1、1、1間における第1段目の空中構造体10の架設レベルHより高い位置(建物棟1、1の上端部間)にリフトアップ用ジャッキJ、Jを搭載したリフティングビーム8を仮設し、前記リフトアップ用ジャッキJ、Jで前記吊上げ材13を吊上げることにより、空中構造体10の第1の架設レベルHまでリフトアップしている(請求項3記載の発明)。 Wherein the first stage of the main portion 10a of the aerial structure 10 assembled on the ground by the steps of (i), in accordance with step (b), increases from Figure 1A to the first erection level H 1 of FIG. 1B As shown in FIG. 5 to FIG. 7, as shown in FIG. 5 to FIG. 7, PCs hang from lift-up jacks J 1 and J 2 , which will be described later, at a total of six suspended points T 1 and T 2 provided in the main part 10 a. A lifting material 13 such as a steel wire (or PC steel bar) is attached, and a position higher than the construction level H 1 of the first-stage aerial structure 10 between the building buildings 1, 1, 1 (the upper ends of the building buildings 1, 1 A lifting beam 8 having lift-up jacks J 1 and J 2 mounted between them and temporarily lifting the lifting member 13 with the lift-up jacks J 1 and J 2 . lift until the erection level H 1 of 1 Tsu is up (the invention of claim 3, wherein).

前記主要部10aに被吊り点T、Tを設ける手法として、本実施例では、図5と図7Cに示したように、当該主要部10aの構成要素である、隣接する建物棟1、1間に設けた3体のトラス構造12の上弦材同士を連結する所定の水平材(鉄骨小梁)12a(図7C参照)の中央部を被吊り点T、Tとしている。当該被吊り点T、T部分は、プレートにて加工して形成し、PC鋼線(又はPC鋼棒)の端部と緊結している。また、前記被吊り点T、T部分は、図7Cに示したように、架構の変形を防止するべく、倒立V字形状に形成した補強材14で補強しておくことが好ましい。 As a method of providing the suspended points T 1 and T 2 in the main part 10a, in this embodiment, as shown in FIGS. 5 and 7C, adjacent building ridges 1, which are constituent elements of the main part 10a, The central portions of a predetermined horizontal member (steel beam) 12a (see FIG. 7C) that connects the upper chord members of the three truss structures 12 provided between 1 are defined as suspended points T 1 and T 2 . The suspended points T 1 and T 2 are formed by processing with a plate and are tightly connected to the end of a PC steel wire (or PC steel rod). Further, as shown in FIG. 7C, the suspended points T 1 and T 2 are preferably reinforced with a reinforcing material 14 formed in an inverted V shape so as to prevent deformation of the frame.

建物棟1、1、1間の上端部に仮設するリフティングビーム8は、図6に示したように、長尺と短尺の鋼製プレート(又はH形鋼等の形鋼)を組み合わせて細長い井桁状に形成してなり、平面視で、前記トラス構造12の被吊り点T、Tに対応する配置を通るように載置している。このリフティングビーム8には、前記被吊り点T、Tにそれぞれ対応するべく、平面視でほぼ一致する位置に、リフトアップ用ジャッキJ、Jを搭載している。このリフトアップ用ジャッキJ、Jはそれぞれ、リフティングビーム8の長手方向に沿って位置決め可能な構成で実施されている。
なお、前記建物棟1の上端部における前記リフティングビーム8を載置する部位(例えば、鉄骨梁)は、図示は省略するが、補強材で補強しておくことが好ましい。また、本実施例に係るリフトアップ用ジャッキJ、Jは、所謂ダブルツインジャッキで実施しているがこれに限定されず、センターホールジャッキでも同様に実施可能である。
ちなみに、図6中の符号11は、作業者のための安全通路を示しており、リフティングビーム8に沿って設けている。
As shown in FIG. 6, the lifting beam 8 temporarily installed at the upper end between the building buildings 1, 1, 1 is a long and narrow girder by combining long and short steel plates (or shaped steel such as H-shaped steel). In the plan view, the truss structure 12 is placed so as to pass through the arrangement corresponding to the suspended points T 1 and T 2 . Lifting jacks J 1 and J 2 are mounted on the lifting beam 8 at positions substantially coincident with each other in plan view so as to correspond to the suspended points T 1 and T 2 , respectively. The lift-up jacks J 1 and J 2 are each configured to be positioned along the longitudinal direction of the lifting beam 8.
In addition, although illustration is abbreviate | omitted, the site | part (for example, steel beam) which mounts the said lifting beam 8 in the upper end part of the said building ridge 1 is preferably reinforced with a reinforcing material. Further, the lift-up jacks J 1 and J 2 according to the present embodiment are implemented by so-called double twin jacks, but are not limited thereto, and can also be implemented by a center hole jack.
Incidentally, reference numeral 11 in FIG. 6 indicates a safety passage for the operator, and is provided along the lifting beam 8.

即ち、図5〜図7に係る前記主要部10a(或いは20a、30a)をリフトアップする手法は、先ず、主要部10a全体をバランス良く吊上げることが可能な部位(本実施例では計6箇所)を予め算出し、当該部位近傍に位置するトラス構造12の前記水平材12aの中央部を被吊り点T、Tとする。次いで、前記リフティングビーム8を、当該トラス構造12の配置に対応するように建物棟1、1の上端部間に仮設する。そして、リフティングビーム8に搭載したリフトアップ用ジャッキJ、Jを、所定の部位に位置決めすることにより、平面視で、前記水平材12aに設けた被吊り点T、Tと、リフトアップ用ジャッキJ、J とをそれぞれほぼ一致させるのである。 That is, the method of lifting up the main portion 10a (or 20a, 30a) according to FIGS. 5 to 7 is first a portion where the entire main portion 10a can be lifted in a balanced manner (in this embodiment, a total of six locations). ) Is calculated in advance, and the central part of the horizontal member 12a of the truss structure 12 located in the vicinity of the part is defined as the suspended points T 1 and T 2 . Next, the lifting beam 8 is temporarily installed between the upper ends of the building buildings 1 and 1 so as to correspond to the arrangement of the truss structure 12. Then, the lift-up jacks J 1 and J 2 mounted on the lifting beam 8 are positioned at predetermined portions, so that the suspended points T 1 and T 2 provided on the horizontal member 12a in plan view and the lift The up jacks J 1 and J 2 are substantially matched with each other.

かくして、図7A、Bに示したように、安定した状態で、前記第1段目の空中構造体10の主要部10aを、所定の第1の架設レベルH(図1B参照)、第2の架設レベルH(図1D参照)、或いは第3の架設レベルH(図1F参照)までリフトアップすることができるのである。
同様の手法で、前記第2段目の空中構造体20の主要部20aもまた、安定した状態で、所定の第1の架設レベルH、(図1D参照)、及び第2の架設レベルH(図1F参照)までリフトアップすることができ、前記第3段目の空中構造体30の主要部30aも、安定した状態で、所定の第1の架設レベルH(図1F参照)までリフトアップすることができるのである。
Thus, as shown in FIGS. 7A and 7B, in a stable state, the main portion 10a of the first-stage aerial structure 10 is moved to a predetermined first construction level H 1 (see FIG. 1B), second It is possible to lift up to the installation level H 2 (see FIG. 1D) or the third installation level H 3 (see FIG. 1F).
In the same manner, the main portion 20a of the second-stage aerial structure 20 is also in a stable state with a predetermined first erection level H 1 (see FIG. 1D), and second erection level H. 2 (see FIG. 1F), and the main portion 30a of the third-stage aerial structure 30 is also in a stable state up to a predetermined first construction level H 1 (see FIG. 1F). You can lift up.

なお、本実施例2では、被吊り点を6箇所で実施しているがこれに限定されるものではなく、主要部10aを安定した状態でリフトアップできることを条件に、適宜増減して実施することができ、これに応じて、リフティングビーム8、及びリフトアップ用ジャッキJ、Jの使用数量も適宜増減して実施する。 In addition, in the present Example 2, although the suspended point is implemented in six places, it is not limited to this, It implements by increasing / decreasing suitably on condition that the main part 10a can be lifted up in the stable state. In accordance with this, the amount of the lifting beam 8 and the lift-up jacks J 1 and J 2 used is appropriately increased and decreased.

したがって、上記構成の建物の構築方法によれば、上記実施例1と同様の作用効果を奏することができることに加え、空中構造体10…の主要部10a…をバランス良く吊上げ可能なように、被吊り点T、T、及び吊り点(リフトアップ用ジャッキJ、J)の数を容易に増減できると共に、それらの位置を調整できるので、当該主要部10a…がより広大で大掛かりな構造となったとしても、安定した状態でリフトアップ作業を行うことができるので、安全性の向上に寄与する。 Therefore, according to the building construction method having the above configuration, in addition to being able to achieve the same operational effects as those of the first embodiment, the main parts 10a of the aerial structures 10 can be lifted in a balanced manner. The number of suspension points T 1 and T 2 and the number of suspension points (lift-up jacks J 1 and J 2 ) can be easily increased and decreased, and their positions can be adjusted, so that the main part 10a is larger and larger. Even if it becomes a structure, the lift-up operation can be performed in a stable state, which contributes to an improvement in safety.

なお、このリフトアップ用ジャッキJ、Jを搭載したリフティングビーム8を建物棟1、1、1間の上端部に仮設してリフトアップする手段について、被吊り点T、Tを形成する手段はこれに限定されない。
例えば、図8〜図10に示したように、各トラス構造12の上端部(上弦材)に、その長手方向に直交する方向に所定の間隔をあけて2体の繋ぎ材9を取り付け、同繋ぎ材9上に、被吊り点T(T)を、スライド自在な構成に設けて実施することもできる。この手法によれば、主要部10a全体をバランス良く吊上げることが可能な部位とほぼ一致する位置に、被吊り点T(T)を形成することができる利点がある。
In addition, suspended points T 1 and T 2 are formed as means for temporarily lifting the lifting beam 8 mounted with the lift-up jacks J 1 and J 2 at the upper end between the building ridges 1, 1 , 1 . The means to do is not limited to this.
For example, as shown in FIGS. 8 to 10, two connecting members 9 are attached to the upper end portion (upper chord material) of each truss structure 12 at a predetermined interval in a direction orthogonal to the longitudinal direction. The suspended point T 1 (T 2 ) may be provided on the connecting member 9 in a slidable configuration. According to this method, there is an advantage that the suspended point T 1 (T 2 ) can be formed at a position that substantially coincides with a portion where the entire main portion 10a can be lifted with good balance.

以上に実施形態を図面に基づいて説明したが、本発明は、図示例の実施形態の限りではなく、その技術的思想を逸脱しない範囲において、当業者が通常に行う設計変更、応用のバリエーションの範囲を含むことを念のために言及する。
例えば、本実施例1、2では、2棟又は3棟の建物に空中構造体10…を架設して実施しているが、これに限定されず、4棟以上の建物でも実施可能である(図11参照)。
また、本実施例1、2では、平面視で、シンメトリック状にバランス良く構築して実施しているが、荷重バランスを考慮することにより、対称配置に限らず実施することができる(図11G参照)。これに伴い、本実施例1、2では、建物棟1、1、…を同形・同大で実施しているが、これに限定されるものではなく、空中構造体を架設できる高さと幅を有する建物棟である限り、種々のバリエーションで実施可能である(図11B、G参照)。
The embodiments have been described with reference to the drawings. However, the present invention is not limited to the illustrated embodiments, and design modifications and application variations that are usually made by those skilled in the art are within the scope of the technical idea of the invention. Note that it includes the range.
For example, in the first and second embodiments, the aerial structures 10 are installed in two or three buildings, but the present invention is not limited to this, and can be implemented in four or more buildings ( FIG. 11).
Further, in the first and second embodiments, the balance is constructed in a balanced manner in plan view, but can be implemented not only in a symmetrical arrangement by considering the load balance (FIG. 11G). reference). Accordingly, in the first and second embodiments, the building ridges 1, 1,... Are implemented with the same shape and size. However, the present invention is not limited to this. As long as it is a building wing, it can be implemented in various variations (see FIGS. 11B and 11G).

A〜Fは、本発明に係る建物の構築方法を段階的に示した工程図である。A to F are process diagrams showing the building construction method according to the present invention step by step. Aは、本発明に係る建物の構築方法により施工した建物の平面図であり、Bは、同正面図である。A is a top view of the building constructed by the building construction method according to the present invention, and B is a front view thereof. 実施例1に係る主要部をリフトアップする手法を示した立面図である。It is the elevation which showed the method of lifting up the principal part which concerns on Example 1. FIG. 実施例2に係る建物の構築方法を示した平面図である。It is the top view which showed the construction method of the building which concerns on Example 2. FIG. 実施例2に係る建物の構築方法について、建物間に組み立てた空中構造体の主要部を示した平面図である。It is the top view which showed the principal part of the aerial structure assembled between buildings about the building construction method concerning Example 2. FIG. 実施例2に係る建物の構築方法について、建物間の上端部に仮設したリフティングビームを示した平面図である。It is the top view which showed the lifting beam temporarily installed in the upper end part between buildings about the building construction method concerning Example 2. FIG. Aは、図6に係るリフティングビームの正面図であり、Bは、図5に係る空中構造体の主要部を構成するトラス構造を示した正面図であり、Cは、Bの同側面図である。6A is a front view of the lifting beam according to FIG. 6, B is a front view showing a truss structure that constitutes a main part of the aerial structure according to FIG. 5, and C is a side view of B. FIG. is there. 実施例2のバリエーションに係る建物の構築方法について、建物間に組み立てた空中構造体の主要部を示した平面図である。It is the top view which showed the principal part of the aerial structure assembled between buildings about the building construction method which concerns on the variation of Example 2. FIG. 実施例2のバリエーションに係る建物の構築方法について、建物間の上端部に仮設したリフティングビームを示した平面図である。It is the top view which showed the lifting beam temporarily installed in the upper end part between buildings about the building construction method which concerns on the variation of Example 2. FIG. Aは、図9に係るリフティングビームの正面図であり、Bは、図8に係る空中構造体の主要部を構成するトラス構造を示した正面図であり、Cは、Bの同側面図である。9A is a front view of the lifting beam according to FIG. 9, B is a front view showing a truss structure constituting the main part of the aerial structure according to FIG. 8, and C is a side view of B. FIG. is there. A〜Gはそれぞれ、建物棟と空中構造体の形状のバリエーションを示した平面図である。A to G are plan views showing variations in the shapes of the building ridge and the aerial structure, respectively.

符号の説明Explanation of symbols

1 建物棟
2 架台
3 被吊り点
4 ワイヤ
5 井桁状の架台
6 滑車装置
7 ウインチ
8 リフティングビーム
9 繋ぎ材
10 第1段目の空中構造体
10a 第1段目の空中構造体の主要部
11 通路
12 トラス構造
12a 水平材
13 吊上げ材(PC鋼線、PC鋼棒)
14 補強材
20 第2段目の空中構造体
20a 第2段目の空中構造体の主要部
30 第3段目の空中構造体
30a 第3段目の空中構造体の主要部
、T 被吊り点
、J リフトアップ用ジャッキ
DESCRIPTION OF SYMBOLS 1 Building ridge 2 Base 3 Suspended point 4 Wire 5 Cross-girder base 6 Pulley device 7 Winch 8 Lifting beam 9 Connecting material 10 First stage aerial structure 10a Main part 11 of first stage aerial structure 11 Passage 12 truss structure 12a horizontal material 13 lifting material (PC steel wire, PC steel bar)
14 Reinforcing material 20 Second stage aerial structure 20a Main part 30 of second stage aerial structure Third stage aerial structure 30a Main part of third stage aerial structure T 1 , T 2 Suspended point J 1 , J 2 Lifting jack

Claims (4)

複数の建物棟間に、複数段の空中構造体を建物棟の高さ方向に間隔をあけて架設して成る建物の構築方法であって、
(イ)複数の建物棟の躯体構築を、空中構造体の第1の架設レベルまで行う工程に並行して、その建物棟間の底部で、建物棟間に架設され支持される第1段目の空中構造体の主要部を組立てる工程と、
(ロ)前記複数の建物棟の躯体構築を前記第1の架設レベルまで進めた段階で、前記第1段目の空中構造体の主要部を、前記建物棟に反力をとって前記第1の架設レベルまで上昇させ、建物棟の躯体に仮定着させる工程と、
(ハ)複数の建物棟の躯体構築を、空中構造体の第2の架設レベルまで行う工程に並行して、その建物棟間の底部で、建物棟間に架設され支持される第2段目の空中構造体の主要部を組立てる工程と、
(ニ)前記複数の建物棟の躯体構築を前記第2の架設レベルまで進めた段階で、前記第1段目の空中構造体の主要部を、前記建物棟に反力をとって前記第2の架設レベルまで上昇させ、建物棟の躯体に仮定着させると共に、前記第2段目の空中構造体の主要部を、前記建物棟に反力をとって前記第1の架設レベルまで上昇させ、建物棟の躯体に仮定着させる工程と、
(ホ)以後、上記(ハ)及び(ニ)の工程を、架設する空中構造体の段数に応じて繰り返して行い、仮定着した空中構造体の主要部を本定着させる工程と、から成ることを特徴とする建物の構築方法。
A method for constructing a building comprising a plurality of aerial structures spanned in the height direction of a building building between a plurality of building buildings,
(B) The first stage that is built and supported between the buildings at the bottom between the buildings in parallel with the process of constructing the building of multiple buildings to the first installation level of the aerial structure Assembling the main part of the aerial structure of
(B) At the stage where the building construction of the plurality of building buildings is advanced to the first erection level, the first portion of the first-stage aerial structure is subjected to a reaction force on the building building and the first The process of raising to the construction level of
(C) The second stage that is built and supported between the buildings at the bottom between the buildings in parallel with the process of constructing the buildings of multiple buildings to the second installation level of the aerial structure Assembling the main part of the aerial structure of
(D) When the building construction of the plurality of building buildings is advanced to the second erection level, the second portion of the first-stage aerial structure is subjected to reaction force against the building building To the construction level of the building building, assumed to be attached to the building ridge body, the main part of the second-stage aerial structure is raised to the first construction level by taking a reaction force on the building building, Assuming the process of attaching to the building building
(E) Thereafter, the steps (c) and (d) are repeated according to the number of stages of the aerial structure to be installed, and the main part of the assumed aerial structure is permanently fixed. The building construction method characterized by.
前記空中構造体の主要部は、同主要部に設けた被吊り点にPC鋼線、PC鋼棒等の吊上げ材を取り付け、建物棟間における空中構造体の架設レベルより高い位置にリフトアップ用ジャッキを搭載したリフティングビームを仮設し、前記リフトアップ用ジャッキで前記吊上げ材を吊上げることにより、空中構造体の架設レベルまで上昇させることを特徴とする、請求項1に記載した建物の構築方法。   The main part of the aerial structure is lifted to a position higher than the construction level of the aerial structure between building buildings by attaching lifting materials such as PC steel wires and PC steel bars to the suspended points provided in the main part. The building construction method according to claim 1, wherein a lifting beam equipped with a jack is temporarily installed, and the lifting material is lifted by the lifting-up jack, whereby the building is raised to an aerial structure level. . 前記複数の建物棟は、2棟以上の建物棟を、平面視で、それぞれの建物棟が互いに所定の間隔を隔て、かつ互いに隣接する壁面を、多角形の辺の一部とする多角形配置に構築されており、前記空中構造体は、前記多角形とほぼ同一の平面形状を有することを特徴とする、請求項1に記載した建物の構築方法。   The plurality of building ridges are polygonal arrangements in which two or more building ridges are viewed in plan, with the building ridges spaced apart from each other by a predetermined distance, and adjacent wall surfaces being part of the polygon side. The building construction method according to claim 1, wherein the aerial structure has a planar shape substantially the same as the polygon. 前記複数の建物棟は、2棟以上の建物棟を、平面視で、対称配置に構築されていることを特徴とする、請求項1又は3に記載した建物の構築方法。   The building construction method according to claim 1 or 3, wherein the plurality of building buildings are constructed in a symmetrical arrangement with two or more building buildings in plan view.
JP2007056094A 2007-03-06 2007-03-06 Building construction method Pending JP2008215012A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007056094A JP2008215012A (en) 2007-03-06 2007-03-06 Building construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007056094A JP2008215012A (en) 2007-03-06 2007-03-06 Building construction method

Publications (1)

Publication Number Publication Date
JP2008215012A true JP2008215012A (en) 2008-09-18

Family

ID=39835394

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007056094A Pending JP2008215012A (en) 2007-03-06 2007-03-06 Building construction method

Country Status (1)

Country Link
JP (1) JP2008215012A (en)

Similar Documents

Publication Publication Date Title
JP2010265727A (en) Method for demolishing building using floor climbing type tower crane
JP4691431B2 (en) Roof structure and construction method thereof
JP6474151B2 (en) Dismantling system and dismantling method
JP2010133084A (en) Method of constructing hollow high structure
JP2008214932A (en) Construction method for building
KR20190096187A (en) Prefabricated cage
KR200388758Y1 (en) fixing anchor structure for tower crane
JP5701490B2 (en) Roof repair method and structure
JP6736226B2 (en) Structure and construction method of the structure constructed on the tower-shaped building
JP2012207379A (en) Structure demolition system
JP6646220B2 (en) Construction method of suspended steel frame for suspended ceiling
JP5558757B2 (en) Climbing crane refilling mechanism and floor climbing method
JP6391134B2 (en) Dismantling method and dismantling system
JP2008215012A (en) Building construction method
JP6320242B2 (en) How to install temporary pillars
JP2014047610A (en) Indoor work floor, and method for constructing the same
JP2017066846A (en) Column-beam frame
JP5985263B2 (en) Structure demolition method
JP4027170B2 (en) External scaffold device and construction method of external scaffold device
JP5952098B2 (en) Structure demolition method
JP2008215013A (en) Building construction method
KR200394923Y1 (en) device of fixing tower crane
JP2017031676A (en) Earthquake resistant reinforcement method and reinforcement device of existing building
EP2378021A1 (en) Beam structure suitable for supporting a floor or floor element, floor, construction assembly and method therefor
JP2009001975A (en) Method for constructing aerial structural body between a plurality of building ridges