JP2008061334A - 配電自動化システムの電力融通方法 - Google Patents
配電自動化システムの電力融通方法 Download PDFInfo
- Publication number
- JP2008061334A JP2008061334A JP2006233498A JP2006233498A JP2008061334A JP 2008061334 A JP2008061334 A JP 2008061334A JP 2006233498 A JP2006233498 A JP 2006233498A JP 2006233498 A JP2006233498 A JP 2006233498A JP 2008061334 A JP2008061334 A JP 2008061334A
- Authority
- JP
- Japan
- Prior art keywords
- power
- supply
- distribution system
- point
- amount
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Remote Monitoring And Control Of Power-Distribution Networks (AREA)
- Supply And Distribution Of Alternating Current (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
【解決手段】融通計算処理部に供給点振分け手段を設け、前記停電発生時に当該停電区間に対する外部区間からの供給点を、仮想の複数供給点に分割して停電復旧したい電力網を木構成とした後に、分割処理手段によって電力の融通演算を実行する。供給点振分け手段による供給点の振分けは、供給点uがk個の需要点に繋がっているとき供給点をk個の仮想供給点に分けてそれぞれの各辺を結び、仮想供給点の供給量を、前記供給点uの供給量と一致するようにした。
【選択図】 図1
Description
この方法は、配電系統をグラフ理論で扱うもので、入力されるグラフを「木」に限定したとき、最適解を効率よく求める。そのためのアルゴリズムは木の持つ特殊な構造を利用することで最適解を求めている。この手法では、配電系統の融通計算問題をグラフ理論で扱うために必要となる構成要素を、供給点、需要点および開閉器の3つとしている。
(1)図15で示すように、部分木の外部から内部へx量だけ電力供給されたとき、その部分木が達成できる最大の充足量yを求め、組(x,y)として候補解にする。ここで、充足量とは電力供給を受けることができる需要量の合計である。
(2)図16で示すように、部分木の内部から外部へx’量だけ電力供給できるとき、その部分木が達成できる最大の充足量y’を求め、組(x’,y’)として候補解にする。
上記(1)(2)で得られる組を候補解として全列挙すれば、木全体に対する最適解を求めることができる。
蒲倉、周、西関:「木の分割問題を解くアルゴリズム」 Technical Report COMP2001-87.IEICE of Japan(2002) p.33〜40 (社)電子情報通信学会
前記融通計算処理部に供給点振分け手段を設け、前記停電発生時に当該停電区間に対する外部区間からの供給点を、仮想の複数供給点に分割して停電復旧したい電力網を木構造とした後に、前記分割処理手段によって電力の融通演算を実行することを特徴としたものである。
前記融通計算処理部に変化点処理手段を設け、電力融通演算時に扱う配電系統の負荷量を配電系統に設置された開閉器単位の区間毎の負荷量として扱い、前記
部分木に対する電力の授受量の最適解を演算処理することを特徴としたものである。
すなわち、候補解の全列挙として図8(b)と図9(b)で示すグラフを求めている。
なお、黒点は電力供給経路が変化した場合であり、白点は変化せず当該白点と同じ高さにある黒点と同じ電力供給経路をしている。
充足量yとしたときの組(x,y)を候補解とする。
2… 演算処理装置
3… 監視制御部
4… 融通計算処理部
5… 記憶装置
Claims (4)
- 電力の融通計算処理部と監視制御部を有する演算処理装置により、
配電系統の停電発生時に記憶装置に格納された停電発生時のデータをもとに電力の融通処理演算を実行するものであって、演算処理装置は、グラフ理論を用いた分割処理手段により配電系統に対しグラフを構成し、部分木に分割して電力の融通演算するものにおいて、
前記融通計算処理部に供給点振分け手段を設け、前記停電発生時に当該停電区間に対する外部区間からの供給点を、仮想の複数供給点に分割して停電復旧したい電力網を木構造とした後に、前記分割処理手段によって電力の融通演算を実行することを特徴とした配電系統の電力融通処理方法。 - 前記供給点振分け手段による供給点の振分けは、供給点uがk個の需要点に繋がっているとき供給点をk個の仮想供給点に分けてそれぞれを辺で結び、仮想供給点の供給量の合計を、前記供給点uの供給量と一致するようにしたことを特徴とした請求項1記載の配電系統の電力融通処理方法。
- 前記融通計算処理部に整数刻み分け手段を設け、この整数刻み分け手段により前記供給点振分け手段によって振分けられた供給量の振分け分を任意の整数毎に分けて処理することを特徴とした請求項1又は2記載の配電系統の電力融通処理方法。
- 電力の融通計算処理部と監視制御部を有する演算処理装置により、
配電系統の停電発生時に記憶装置に格納された停電発生時のデータをもとに電力の融通処理演算を実行するものであって、演算処理装置は、グラフ理論を用いた分割処理手段により配電系統に対しグラフを構成し、部分木に分割して電力の融通演算するものにおいて、
前記融通計算処理部に変化点処理手段を設け、電力融通演算時に扱う配電系統の負荷量を配電系統に設置された開閉器単位の区間毎の負荷量として扱い、前記
部分木に対する電力の授受量の最適解を演算処理することを特徴とした配電系統の電力融通処理方法。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2006233498A JP4622968B2 (ja) | 2006-08-30 | 2006-08-30 | 配電自動化システムの電力融通方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2006233498A JP4622968B2 (ja) | 2006-08-30 | 2006-08-30 | 配電自動化システムの電力融通方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2008061334A true JP2008061334A (ja) | 2008-03-13 |
JP4622968B2 JP4622968B2 (ja) | 2011-02-02 |
Family
ID=39243475
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2006233498A Active JP4622968B2 (ja) | 2006-08-30 | 2006-08-30 | 配電自動化システムの電力融通方法 |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4622968B2 (ja) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010207056A (ja) * | 2009-03-06 | 2010-09-16 | Meidensha Corp | 配電系統の電力融通処理方法 |
JP2010207055A (ja) * | 2009-03-06 | 2010-09-16 | Meidensha Corp | 配電系統の電力融通処理方法 |
CN102324787A (zh) * | 2011-08-26 | 2012-01-18 | 任建福 | 一种配电网自动化实施方法 |
CN102663541A (zh) * | 2012-03-20 | 2012-09-12 | 国电南瑞科技股份有限公司 | 一种配电网故障修复资源调度方法及装置 |
CN103345713A (zh) * | 2013-06-24 | 2013-10-09 | 国家电网公司 | 一种超大规模电力网络同步安全校核系统设计方法 |
CN103778573A (zh) * | 2014-02-26 | 2014-05-07 | 国家电网公司 | 一种配电网供电区域的分类方法 |
CN104485660A (zh) * | 2014-11-11 | 2015-04-01 | 国家电网公司 | 一种基于有向关系图的配电网可靠性评估方法 |
CN104505820A (zh) * | 2014-10-24 | 2015-04-08 | 广东工业大学 | 基于多信息关联利用的配电网智能重构方法 |
CN104700327A (zh) * | 2015-03-30 | 2015-06-10 | 国家电网公司 | 配电自动化方案制定方法及系统 |
WO2015121937A1 (ja) * | 2014-02-13 | 2015-08-20 | 株式会社日立製作所 | 電力融通管理システムおよび電力融通管理方法 |
CN104915787A (zh) * | 2015-06-23 | 2015-09-16 | 广州供电局有限公司 | 设备故障率修正及配电网可靠性评估的方法及系统 |
CN105470949A (zh) * | 2015-12-01 | 2016-04-06 | 江苏省电力公司淮安供电公司 | 考虑复杂转供的配电网可靠性评估方法 |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102354977B (zh) * | 2011-10-20 | 2013-04-03 | 湖南省电力公司科学研究院 | 一种馈线故障处理方法 |
CN103426033B (zh) * | 2013-07-31 | 2017-05-03 | 国家电网公司 | 基于关键路径法的配电网故障恢复优化重构方法 |
CN104091231A (zh) * | 2014-06-30 | 2014-10-08 | 国家电网公司 | 配网故障抢修指挥处理系统及方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06189454A (ja) * | 1992-09-04 | 1994-07-08 | Toshiba Corp | 負荷融通割付方法 |
JPH07203630A (ja) * | 1994-01-07 | 1995-08-04 | Fuji Electric Co Ltd | 負荷融通の決定方法 |
JPH099504A (ja) * | 1995-06-14 | 1997-01-10 | Hitachi Ltd | 配電系統の目標構成決定方法および監視制御システム |
JPH09172737A (ja) * | 1995-12-20 | 1997-06-30 | Hitachi Ltd | 電力系統の復旧方法 |
-
2006
- 2006-08-30 JP JP2006233498A patent/JP4622968B2/ja active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06189454A (ja) * | 1992-09-04 | 1994-07-08 | Toshiba Corp | 負荷融通割付方法 |
JPH07203630A (ja) * | 1994-01-07 | 1995-08-04 | Fuji Electric Co Ltd | 負荷融通の決定方法 |
JPH099504A (ja) * | 1995-06-14 | 1997-01-10 | Hitachi Ltd | 配電系統の目標構成決定方法および監視制御システム |
JPH09172737A (ja) * | 1995-12-20 | 1997-06-30 | Hitachi Ltd | 電力系統の復旧方法 |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2010207056A (ja) * | 2009-03-06 | 2010-09-16 | Meidensha Corp | 配電系統の電力融通処理方法 |
JP2010207055A (ja) * | 2009-03-06 | 2010-09-16 | Meidensha Corp | 配電系統の電力融通処理方法 |
CN102324787A (zh) * | 2011-08-26 | 2012-01-18 | 任建福 | 一种配电网自动化实施方法 |
CN102663541A (zh) * | 2012-03-20 | 2012-09-12 | 国电南瑞科技股份有限公司 | 一种配电网故障修复资源调度方法及装置 |
CN103345713A (zh) * | 2013-06-24 | 2013-10-09 | 国家电网公司 | 一种超大规模电力网络同步安全校核系统设计方法 |
CN103345713B (zh) * | 2013-06-24 | 2019-07-26 | 国家电网公司 | 一种超大规模电力网络同步安全校核系统设计方法 |
WO2015121937A1 (ja) * | 2014-02-13 | 2015-08-20 | 株式会社日立製作所 | 電力融通管理システムおよび電力融通管理方法 |
JPWO2015121937A1 (ja) * | 2014-02-13 | 2017-03-30 | 株式会社日立製作所 | 電力融通管理システムおよび電力融通管理方法 |
US10103575B2 (en) | 2014-02-13 | 2018-10-16 | Hitachi, Ltd. | Power interchange management system and power interchange management method for maintaining a balance between power supply and demand |
CN103778573A (zh) * | 2014-02-26 | 2014-05-07 | 国家电网公司 | 一种配电网供电区域的分类方法 |
CN104505820A (zh) * | 2014-10-24 | 2015-04-08 | 广东工业大学 | 基于多信息关联利用的配电网智能重构方法 |
CN104485660A (zh) * | 2014-11-11 | 2015-04-01 | 国家电网公司 | 一种基于有向关系图的配电网可靠性评估方法 |
CN104700327A (zh) * | 2015-03-30 | 2015-06-10 | 国家电网公司 | 配电自动化方案制定方法及系统 |
CN104915787A (zh) * | 2015-06-23 | 2015-09-16 | 广州供电局有限公司 | 设备故障率修正及配电网可靠性评估的方法及系统 |
CN105470949A (zh) * | 2015-12-01 | 2016-04-06 | 江苏省电力公司淮安供电公司 | 考虑复杂转供的配电网可靠性评估方法 |
Also Published As
Publication number | Publication date |
---|---|
JP4622968B2 (ja) | 2011-02-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP4622968B2 (ja) | 配電自動化システムの電力融通方法 | |
US20230198257A1 (en) | Establishing Communication and Power Sharing Links Between Components of a Distributed Energy System | |
JP5973733B2 (ja) | volt/VAR潮流最適化を加速するためのシステム、方法、および装置 | |
US20160285307A1 (en) | Power Supply Device and Power Supply Method in Data Center | |
WO2014007368A1 (ja) | 電力ネットワークシステム、電力ネットワークシステムの制御方法、及び制御プログラム | |
Ding et al. | A sequential black-start restoration model for resilient active distribution networks | |
Yang et al. | A multiagent system based optimal load restoration strategy in distribution systems | |
CN103809723A (zh) | 机柜与其电源控制方法 | |
Wang et al. | Distributed optimal power flow of DC microgrids: A penalty based ADMM approach | |
US10078316B2 (en) | Pre-configuration and integration of IEDs in substation automation systems | |
Lan et al. | Stochastic optimization for AC optimal transmission switching with generalized benders decomposition | |
JP2016063573A (ja) | 系統安定化システム | |
JP5272809B2 (ja) | 配電系統の電力融通処理方法 | |
Selseleh Jonban et al. | Intelligent fault tolerant energy management system with layered architecture for a photovoltaic power plant | |
Prostejovsky et al. | Demonstration of a multi-agent-based control system for active electric power distribution grids | |
Mazauric et al. | Computational analysis of cascading failures in power networks | |
JP2010207055A (ja) | 配電系統の電力融通処理方法 | |
Shafiee et al. | Need-based communication in fully-distributed secondary control of DC microgrids | |
Eng et al. | Distribution system restoration using spanning tree based on depth first search visual in GUI | |
Bose et al. | Analysis of robustness for shipboard power system with non-radial power flow | |
Liu et al. | Strong controllable siphon basis-based robust deadlock control for manufacturing systems with multiple unreliable resources | |
Kumar et al. | Event Based Robust Action for Fault Restrained Secondary Control of DC Microgrid | |
Grebenyuk et al. | Limit graphs in structural optimization of modes in distribution networks | |
JP2011193586A (ja) | 自家発電システム | |
Yokoyama et al. | Comparison of centralized and decentralized systems in power system restoration |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20090513 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20100713 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20100803 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20100913 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20101005 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20101018 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4622968 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |