JP2007328434A - Piecework management system - Google Patents

Piecework management system Download PDF

Info

Publication number
JP2007328434A
JP2007328434A JP2006157566A JP2006157566A JP2007328434A JP 2007328434 A JP2007328434 A JP 2007328434A JP 2006157566 A JP2006157566 A JP 2006157566A JP 2006157566 A JP2006157566 A JP 2006157566A JP 2007328434 A JP2007328434 A JP 2007328434A
Authority
JP
Japan
Prior art keywords
cad model
data
construction
work
work process
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2006157566A
Other languages
Japanese (ja)
Inventor
Daisuke Yamawaki
大輔 山脇
Hiroshi Komoto
洋 甲元
Toyohiko Masuda
豊彦 増田
Yoshifumi Kubo
良文 久保
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Ltd
Original Assignee
Hitachi Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Ltd filed Critical Hitachi Ltd
Priority to JP2006157566A priority Critical patent/JP2007328434A/en
Publication of JP2007328434A publication Critical patent/JP2007328434A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a piecework management system capable of obtaining highly objective piecework information for increasing the commonality of the recognition of both a constructor side and a manager side to an output. <P>SOLUTION: In the piecework management system used for managing the progress status of construction to be progressed by the constructor side, a manager side provids a CAD model-including data D3 including a CAD model with respect to the construction of an piecework management object to the constructor side, and the constructor side prepares a CAD model base construction progress status data D17 by overlapping a construction progress status data D16 with respect to the actual progress status of the construction on the CAD model including data, then the constructor side can apply the acceptance of the construction progress status to the manager side by using the CAD model base construction progress status data. <P>COPYRIGHT: (C)2008,JPO&INPIT

Description

本発明は、プラント工事や建設工事あるいは土木工事などの様々な工事における出来高管理で用いられる出来高管理システムに関する。   The present invention relates to a volume management system used in volume management in various works such as plant work, construction work, and civil engineering work.

プラント工事や建設工事あるいは土木工事などの各種工事、特にプラント工事などの大型工事では、発注者側(管理者側)の設計管理の下で工事の施工を請け負う受注者側(施工者側)が所定の工事進行計画に基づいて工事を進め、その工事の進捗に関して出来高管理を行うことが広くなされている。出来高管理では、予定の進捗状態と実際の進捗状態の関係、及び工事の進捗に応じて施工者側で実際に要した費用である実際原価と管理者側で予定した費用である実行予算の関係などが管理される。例えば、施工者側は月単位で工事の進捗実績を検収申請するとともに実際原価による費用を請求し、管理者側はその申請を査定し、工事が予定通りに進捗しており、請求費用が実行予算との関係で問題なしとすれば、査定を確定して費用の支払いをする。こうした出来高管理に関しては、例えば特許文献1や特許文献2に開示の例が知られている。   In various works such as plant work, construction work or civil engineering work, especially large-scale work such as plant work, the contractor side (constructor side) who undertakes construction work under the design management of the orderer side (administrator side) It is widely practiced to proceed with construction based on a predetermined construction progress plan and to manage the volume with respect to the progress of the construction. In volume management, the relationship between the planned progress status and the actual progress status, and the relationship between the actual cost, which is the actual cost required by the contractor according to the progress of the construction, and the execution budget, which is the cost planned by the manager. Etc. are managed. For example, the contractor submits an application for acceptance of the actual progress of construction work on a monthly basis and charges a cost based on the actual cost. The manager assesses the application, and the work is progressing as planned, and the billing cost is executed. If there is no problem in relation to the budget, confirm the assessment and pay the cost. Regarding such volume management, examples disclosed in Patent Document 1 and Patent Document 2, for example, are known.

ここで、上記のような工事においては、工事途中で部分的な設計変更がなされることが少なからずある。そうした設計変更は、それによる実際原価の変動を実行予算の余裕代で吸収できる程度の範囲でなされるのが一般的であるが、管理者側の予想を超えた実際原価の増大を招く場合もある。そのような場合には、実行予算を超えた費用請求が施工者側から管理者側に請求されることになる。そうなると、管理者側では請求費用の妥当性を検討したり、施工者側に請求費用の減額を交渉したりするなどの作業が必要となり、その間は工事が停止するような事態を生じ、そのために工事の遅延を招く結果となったり、さらには管理者側にショートを招く結果になったりすることもある。   Here, in the construction as described above, there are not a few cases in which partial design changes are made during the construction. Such design changes are generally made to the extent that fluctuations in actual costs can be absorbed by the margin of the execution budget. However, there are cases where actual costs increase beyond the expectations of the manager. is there. In such a case, a cost request exceeding the execution budget is charged from the builder side to the manager side. If that happens, the manager will need to consider the appropriateness of the billing costs and negotiate with the contractor to reduce the billing costs. During that time, the construction will be suspended. This may result in a delay in construction, or even a short circuit on the manager side.

特許3262522号公報Japanese Patent No. 3262522 特開平9−26995号公報JP-A-9-26995

本発明の発明者等は、上記のような設計変更などに伴う工事の遅延や資金ショートなどの問題について、出来高管理のありかたを詳細に検討した。その結果、進捗した工事の作業量などの出来高についての施工者側と管理者側双方の認識の共通性に問題のあることが分かった。すなわち設計変更で増加した作業量などについての施工者側と管理者側で認識に食い違いがあり、それが施工者側からの請求費用などに対する管理者側の判断に齟齬をもたらし、そのために施工者側に請求費用の減額を交渉したりするなどの作業が必要となる事態を招くことになっていた、ということである。このことから、施工者側と管理者側双方でより客観性の高い出来高認識をできるようにする出来高情報、つまり工事の出来高について具体的なイメージを管理者側でも容易に得られるような出来高情報を施工者側と管理者側双方で共有できるようにすることができれば、設計変更などに伴う工事の遅延や資金ショートなどの問題を効果的に避けることが可能であるといえる。   The inventors of the present invention have examined in detail how to manage the volume for problems such as delays in construction and shortage of funds associated with the above-described design change. As a result, it was found that there was a problem in the commonality of both the contractor's and manager's perceptions regarding the volume of work that had been done. In other words, there is a discrepancy between the contractor's side and the manager's side regarding the amount of work that has increased due to the design change. It was supposed to lead to a situation that required work such as negotiating a reduction in billing costs to the side. From this, it is possible to recognize the volume information with higher objectivity on both the construction side and the manager side, that is, the volume information that allows the manager side to easily obtain a concrete image of the construction volume. If it can be shared by both the contractor side and the manager side, it can be said that it is possible to effectively avoid problems such as delays in construction and shortage of funds due to design changes.

本発明は、このような知見に基づいてなされたものであり、出来高に対する施工者側と管理者側双方の認識の共通性をより高めるような客観性の高い出来高情報を与えることを可能とする出来高管理システムの構築を課題としている。   The present invention has been made on the basis of such knowledge, and makes it possible to provide highly objective volume information that enhances the commonality of both the construction side and the manager side with respect to the volume. The challenge is to build a volume management system.

本発明では上記課題を解決するために、施工者側が進める工事の進捗状態を管理するのに用いられる出来高管理システムにおいて、出来高管理対象の工事に関するCADモデルを含むCADモデル包含データを管理者側が前記施工者側に提供し、前記施工者側は前記CADモデル包含データに工事の実際の進捗状態に関する工事進捗状態データを重ね合わせてCADモデルベース工事進捗状態データを作成し、このCADモデルベース工事進捗状態データを用いて前記管理者側に対する工事進捗状態の検収申請を行えるようにされていることを特徴としている。   In the present invention, in order to solve the above-mentioned problem, in the yield management system used to manage the progress status of the construction that the contractor proceeds, the administrator side stores the CAD model inclusion data including the CAD model related to the construction of the yield management target. Provided to the construction side, the construction side creates the CAD model base construction progress status data by superimposing the construction progress status data relating to the actual progress status of the construction on the CAD model inclusion data, and the CAD model base construction progress It is characterized in that an application for acceptance of the construction progress status to the manager side can be made using the status data.

このように、出来高管理対象の工事に関するCADモデルをベースにして作成されるCADモデルベース工事進捗状態データを用いて工事進捗状態の検収申請を行えるようにしたことから、管理者側では、工事進捗状態の検収にあたって、工事の内容や進捗状態をイメージ的に把握することができるようになる。そのため、出来高に対する施工者側と管理者側双方の認識の共通性をより高めることができる。   As described above, since the application for acceptance of the construction progress status can be made using the CAD model-based construction progress status data created based on the CAD model related to the volume management target construction, In the inspection of the status, it becomes possible to grasp the contents of the construction and the progress status in an image. Therefore, the commonality of both the construction side and the manager side regarding the volume can be further increased.

また本発明では上記のような出来高管理システムについて、前記CADモデル包含データとして、前記CADモデルに工事の作業単位ごとの進捗計画に関する作業工程をリンクさせて作成されるCADモデル・作業工程リンクデータを用いるようにしている。   Further, in the present invention, the CAD model / work process link data created by linking work processes related to the progress plan for each work unit of work to the CAD model as the CAD model inclusion data for the volume management system as described above. I use it.

このようにCADモデル・作業工程リンクデータを用いるようにすることにより、CADモデルベース工事進捗状態データの作成が容易になり、また工事進捗状態の把握がより容易となる。   By using the CAD model / work process link data in this way, creation of CAD model-based construction progress status data is facilitated, and the construction progress status is more easily grasped.

また本発明では上記のような出来高管理システムについて、前記CADモデルに前記作業工程をリンクさせてCADモデル・作業工程リンクデータを作成するリンク処理部を備えるとともに、前記工事進捗状態データを前記CADモデル・作業工程リンクデータに重ね合わせて前記CADモデルベース工事進捗状態データを作成する工事進捗状態データ作成部を備えた構成とするものとしている。   The present invention also includes a link processing unit for creating a CAD model / work process link data by linking the work process to the CAD model for the volume management system as described above, and the construction progress status data as the CAD model. A construction progress state data creating unit that creates the CAD model base construction progress state data superimposed on the work process link data is provided.

また本発明では上記のような出来高管理システムについて、イメージ的可視化効果をより高めることができるようにするために、CADモデルとして3次元CADモデルを用いるようにしている。   Further, in the present invention, a three-dimensional CAD model is used as the CAD model in order to further enhance the image visualization effect in the volume management system as described above.

以上のような本発明によれば、出来高に対する施工者側と管理者側双方の認識の共通性をより高めるような客観性の高い出来高情報を与えることを可能となる。   According to the present invention as described above, it is possible to provide highly objective volume information that enhances the commonality of both the construction side and the manager side with respect to the volume.

以下、本発明を実施するための形態について説明する。図1に一実施形態による出来高管理システム1の構成を示す。出来高管理システム1は、コンピュータやその周辺機器とコンピュータに組み込まれるコンピュータプログラムで構成され、出来高管理部2、申請部3、及び情報公開部4を備えている。こうした出来高管理システム1の運用は、工事の内容や進捗状態をイメージ的に可視化する情報として出来高管理対象の工事に関するCADモデルを包含して同一ファイル形式で作成される各種電子ファイルの授受を通じて行われる。   Hereinafter, modes for carrying out the present invention will be described. FIG. 1 shows a configuration of a volume management system 1 according to an embodiment. The volume management system 1 includes a computer and its peripheral devices and a computer program incorporated in the computer, and includes a volume management unit 2, an application unit 3, and an information disclosure unit 4. The operation of the volume management system 1 is performed through exchange of various electronic files created in the same file format including a CAD model related to the volume management target construction as information for visualizing the contents and progress of the construction. .

出来高管理部2は、CADモデルデータベース部11、作業工程データベース部12、CADモデル/作業工程リンク処理部13、公開情報データベース部14、検収申請受付/査定登録部15、作業工程シミュレータ部16、及び取引決済処理部17を備えている。   The volume management unit 2 includes a CAD model database unit 11, a work process database unit 12, a CAD model / work process link processing unit 13, a public information database unit 14, an acceptance application acceptance / assessment registration unit 15, a work process simulator unit 16, and A transaction settlement processing unit 17 is provided.

CADモデルデータベース部11は、外部から入力されるCADモデルのデータD1を格納する。CADモデルデータD1は、CADシステムで作成された出来高管理対象工事に関する設計モデルである。CADモデルデータD1には、イメージ的可視化効果をより高めことができるように、3次元の設計モデルつまり3D−CADモデルを用いる。またCADモデルデータD1は、出来高管理対象工事をその種類、例えばプラント工事であれば、建屋工事、装置設置工事、配管工事、配線工事などのような工事種類に基づく作業ブロックを単位とする作業ブロック化CADモデルデータの形態をとる。つまりCADモデルデータD1は、作業ブロック化CADモデルデータとしてCADモデルデータベース部11に入力されるのが通常である。こうしたCADモデルデータD1は、工事の進行中になされることのある設計変更に応じて変更される。   The CAD model database unit 11 stores CAD model data D1 input from the outside. The CAD model data D1 is a design model related to the work volume management target work created by the CAD system. As the CAD model data D1, a three-dimensional design model, that is, a 3D-CAD model is used so that the image visualization effect can be further enhanced. The CAD model data D1 is a work block whose unit is a work management based on the type of work, such as building work, equipment installation work, piping work, wiring work, etc. It takes the form of generalized CAD model data. That is, the CAD model data D1 is normally input to the CAD model database unit 11 as work block CAD model data. Such CAD model data D1 is changed in accordance with a design change that may be made during construction.

作業工程データベース部12は、外部から入力される作業工程のデータD2を格納する。作業工程データD2は、工事施工の上での作業単位にその作業完了予定期日を組み合わせたデータである。ここで、作業単位とは、上記工事の作業ブロックをツリー構造的に階層化して得られる作業の単位で、階層ごとにあり、最下位の階層における作業の単位が最小作業単位となる。そうした工事のツリー構造的階層化は、WBS(Work Breakdown Structure)と呼ばれている。こうした作業工程データD2は、出来高管理対象工事の設計管理を担う管理者により作成される。そして作業工程データD2は、管理者により定期的に見直され、必要ならば変更され、その変更された作業工程データD2が作業工程データベース部12に新たに入力される。作業工程データD2の定期的に見直しは、例えば1ヶ月単位でなされる後述の検収を基準にして行われる。   The work process database unit 12 stores work process data D2 input from the outside. The work process data D2 is data in which the work completion schedule date is combined with the work unit on the construction work. Here, the work unit is a unit of work obtained by hierarchizing the work blocks of the above construction in a tree structure, and is provided for each hierarchy, and the unit of work in the lowest hierarchy is the minimum work unit. Such tree structure hierarchization of construction is called WBS (Work Breakdown Structure). Such work process data D2 is created by an administrator who is responsible for the design management of the work volume management target work. The work process data D2 is periodically reviewed by the administrator, changed if necessary, and the changed work process data D2 is newly input to the work process database unit 12. The work process data D2 is periodically reviewed based on, for example, a later-described inspection performed on a monthly basis.

CADモデル/作業工程リンク処理部13は、CADモデルデータD1に作業工程データD2をリンクさせる処理を行い、CADモデル包含データとしてCADモデル・作業工程リンクデータD3を作成して出力する。またCADモデル/作業工程リンク処理部13は、CADモデル・作業工程リンクデータD3に基づいて工事施工引合ファイルD4や工事発注ファイルD5を作成して出力する。CADモデル・作業工程リンクデータD3は、上述のようにCADモデルデータD1や作業工程データD2が変更された場合にはそれに応じて変更される。こうしたCADモデル/作業工程リンク処理部13の詳細については後述する。ここで、CADモデル・作業工程リンクデータD3は、上述のようにCADモデルデータD1が作業ブロック化CADモデルデータとなるっている場合には、作業ブロック化CADモデル・作業工程リンクデータとなる。   The CAD model / work process link processing unit 13 performs a process of linking the work process data D2 to the CAD model data D1, and creates and outputs CAD model / work process link data D3 as CAD model inclusion data. The CAD model / work process link processing unit 13 creates and outputs a construction work inquiry file D4 and a work order file D5 based on the CAD model / work process link data D3. The CAD model / work process link data D3 is changed accordingly when the CAD model data D1 and the work process data D2 are changed as described above. Details of the CAD model / work process link processing unit 13 will be described later. Here, the CAD model / work process link data D3 becomes work block CAD model / work process link data when the CAD model data D1 is the work block CAD model data as described above.

このようにCADモデルデータD1と作業工程データD2をリンクさせてCADモデル・作業工程リンクデータD3を作成し、これをCADモデル包含データとして用いるようにすることにより、後述のCADモデルベース工事進捗状態データの作成が容易になり、またそのCADモデルベース工事進捗状態データによる工事進捗状態の把握がより容易となる。   In this way, CAD model data D1 and work process data D2 are linked to create CAD model / work process link data D3 and used as CAD model inclusion data, so that the CAD model base construction progress state described later It becomes easy to create data, and it becomes easier to grasp the construction progress status based on the CAD model base construction progress status data.

公開情報データベース部14は、管理者、施工者及び工事の最終顧客などに情報公開部4で公開する情報を格納する。その公開情報としては、出来高管理部2で作成される各種データの内の工事の進捗や検収実績などに関する情報が主なものである。   The public information database unit 14 stores information to be disclosed by the information disclosure unit 4 to the manager, the contractor, the final customer of the construction, and the like. The public information is mainly information on the progress of construction and the inspection results in various data created by the volume management unit 2.

検収申請受付/査定登録部15は、工事施工者が後述のCADモデルベース工事進捗状態データを包含した検収申請ファイル(検収申請データ)D6で行う検収申請を受け付ける申請受付部として機能し、また検収申請ファイルD6による検収申請について工事管理者が行った査定結果を査定ファイル(査定データ)D7として登録して出力する査定登録部としても機能する。   The acceptance application acceptance / assessment registration unit 15 functions as an application acceptance unit that accepts an acceptance application performed by the construction contractor using an acceptance application file (acceptance application data) D6 including CAD model-based construction progress status data described later. It also functions as an assessment registration unit that registers and outputs the assessment results (assessment data) D7, which are made by the construction manager, regarding the acceptance application by the application file D6.

作業工程シミュレータ部16は、作業の進捗に応じた作業工程の見直しのためのシミュレーションを行なう。作業工程見直しシミュレーションは、CADモデル・作業工程リンクデータD3、検収申請データD6、査定データD7及び作業工程の見直しについての条件に関する作業工程見直し条件データD8などを用いて行われる。この作業工程シミュレータ部16からは、作業工程見直しシミュレーションに基づいて、検収/作業工程予測データD9が公開情報データベース部14に出力されるとともに、予測作業工程データD10が外部に出力される。   The work process simulator unit 16 performs a simulation for reviewing the work process according to the progress of the work. The work process review simulation is performed using CAD model / work process link data D3, acceptance application data D6, assessment data D7, work process review condition data D8 regarding conditions for review of the work process, and the like. The work process simulator unit 16 outputs inspection / work process prediction data D9 to the public information database unit 14 and also outputs predicted work process data D10 to the outside based on the work process review simulation.

検収/作業工程予測データD9は、検収申請データD6に含まれる工事進捗実績に基づいた作業工程見直しシミュレーションで得られる作業工程予測を検収実績と関連させたデータであり、公開情報データベース部14に蓄積され、情報公開部4で公開される情報に用いられる。予測作業工程データD10は、検収時以降の作業工程を作業工程見直しシミュレーションで予測して得られるデータであり、外部に出力され、検収がなされる度に管理者が作業工程を見直す際の参考として用いられる。このように予測作業工程データD10を利用できるようにすることにより、管理者は、より効率的に作業工程の見直しを行うことができるようになる。   The acceptance / work process prediction data D9 is data in which the work process prediction obtained by the work process review simulation based on the construction progress results included in the acceptance application data D6 is related to the acceptance results, and is stored in the public information database unit 14. And used for information disclosed by the information disclosure unit 4. Predictive work process data D10 is data obtained by predicting the work process after the acceptance at the work process review simulation, and is output to the outside as a reference when the administrator reviews the work process every time the acceptance is performed. Used. By making the predicted work process data D10 available in this way, the administrator can review the work process more efficiently.

また作業工程シミュレータ部16は、実際の進捗状態と予定進捗状態の関係から作業遅延や納期遅延につながる兆候がある場合にはそれについての警報を出すための作業遅延・納期遅延警報指示D11を出力する。作業遅延・納期遅延警報指示D11が出力されて警報が発せられた場合には、作業遅延などを回避する策を管理者が立て、それが作業工程見直し条件データD8として再入力され、それに基づいて再度の作業工程見直しシミュレーションが行われ、推奨作業工程データD12が出力される。推奨作業工程データD12は、作業遅延などを回避する作業工程見直し条件データD8に基づいてなされた作業工程見直しシミュレーションにより、作業遅延などの回避に推奨できるとされる作業工程を記述するデータであり、外部に出力され、管理者が作業遅延などの回避のために作業工程を見直す際の参考として用いられる。   Further, the work process simulator unit 16 outputs a work delay / delivery delay alarm instruction D11 for issuing an alarm about a sign of work delay or delivery delay from the relationship between the actual progress state and the planned progress state. To do. When the work delay / delivery delay alarm instruction D11 is output and an alarm is issued, the administrator takes measures to avoid the work delay and the like, which is re-input as the work process review condition data D8, and based on that The work process review simulation is performed again, and recommended work process data D12 is output. The recommended work process data D12 is data describing a work process that can be recommended for avoiding work delay or the like by work process review simulation performed based on the work process review condition data D8 that avoids work delay or the like. It is output to the outside and used as a reference when the manager reviews the work process to avoid work delays.

取引決済処理部17は、検収申請された進捗工事分について支払いに関する許可条件D13を生成してそれを外部に出力するとともに、検収実績情報D14を公開情報データベース部14に出力する。支払いは電子決済で行うのが通常で、電子決済の場合、支払い許可条件D13は、電子決済の支払い許可条件となる。取引決済処理部17による支払い許可条件D13や検収実績情報D14の生成は、検収申請データD6、査定データD7及び検収における最終的な査定の確定を指示する査定確定D15の入力を受けて行われる。   The transaction settlement processing unit 17 generates a permission condition D13 related to payment for the progress work for which the application for inspection has been applied, outputs it to the outside, and outputs inspection result information D14 to the public information database unit 14. Payment is usually performed by electronic payment. In the case of electronic payment, the payment permission condition D13 is a payment permission condition for electronic payment. Generation of the payment permission condition D13 and the inspection result information D14 by the transaction settlement processing unit 17 is performed in response to the input of the inspection application data D6, the evaluation data D7, and the assessment confirmation D15 instructing the final assessment in the acceptance.

申請部3は、施工者側が管理者側に提出する各種申請データの作成に機能し、工事進捗状態データ作成部21と申請データ作成部22を備えている。   The application unit 3 functions to create various application data to be submitted by the contractor to the manager, and includes a construction progress state data creation unit 21 and an application data creation unit 22.

工事進捗状態データ作成部21は、工事の実際の進捗状態に関するデータとして施工者により入力される現地工事ステータスデータつまり工事進捗状態データD16をCADモデル・作業工程リンクデータD3に重ね合わせることで、CADモデルをベースにしたCADモデルベース工事進捗状態データD17を作成するのに機能する。工事進捗状態データD16をCADモデル・作業工程リンクデータD3に重ね合わせる処理には、例えばCADモデル・作業工程リンクデータD3を工事進捗状態に応じて色付けするなどの手法を用いることができる。   The construction progress status data creation unit 21 superimposes the local construction status data, that is, the construction progress status data D16, which is input by the contractor as data regarding the actual progress status of the construction, with the CAD model / work process link data D3. It functions to create CAD model-based construction progress status data D17 based on the model. For the process of superimposing the construction progress state data D16 on the CAD model / work process link data D3, for example, a technique of coloring the CAD model / work process link data D3 according to the work progress state can be used.

申請データ作成部22は、工事応札ファイルD18や検収申請ファイルD6を作成するのに機能する。工事応札ファイルD18は、工事施工引合ファイルD4による工事施工の引合いを受け、それに応札する場合に、工事施工引合ファイルD4に対応するファイル形式で作成される。検収申請ファイルD6は、CADモデルベース工事進捗状態データD17を包含する検収申請用データとして所定のファイル形式で作成される。   The application data creation unit 22 functions to create the construction bidding file D18 and the inspection application file D6. The construction bidding file D18 is created in a file format corresponding to the construction construction inquiry file D4 when receiving a construction construction inquiry by the construction construction inquiry file D4 and bidding for it. The acceptance application file D6 is created in a predetermined file format as acceptance application data including the CAD model base construction progress status data D17.

情報公開部4は、出来高管理部2で作成される各種データの内の工事の進捗状態(ステータス)や検収実績などに関する情報を管理者と施工者さらには工事の最終顧客に対して公開する。そのために情報公開部4は、工事進捗状態情報公開部23と検収/作業工程予測/実績情報公開部24を備えている。工事進捗状態情報公開部23は、CADモデルベース工事進捗状態データD17を包含する所定のファイル形式による工事進捗状態情報D19を公開情報データベース部14から得て公開する。一方、検収/作業工程予測/実績情報公開部24は、検収/作業工程予測/実績情報D20を公開情報データベース部14から得て公開する。こうした情報公開部4は、情報公開用のサーバを用いて情報公開を行う。   The information publishing unit 4 publishes information related to the construction progress status (status) and inspection results, etc., among the various data created by the volume management unit 2 to the manager, the installer, and the final customer of the construction. For this purpose, the information disclosure unit 4 includes a construction progress state information disclosure unit 23 and an inspection / work process prediction / result information disclosure unit 24. The construction progress status information disclosure unit 23 obtains the construction progress status information D19 in a predetermined file format including the CAD model base construction progress status data D17 from the public information database unit 14 and publishes it. On the other hand, the inspection / work process prediction / result information disclosure unit 24 obtains the inspection / work process prediction / result information D20 from the public information database unit 14 and publishes it. Such an information disclosure unit 4 performs information disclosure using a server for information disclosure.

以下では、CADモデル/作業工程リンク処理部13の詳細について説明する。図2にCADモデル/作業工程リンク処理部13の構成を示す。CADモデル/作業工程リンク処理部13の基本的な機能は、CADモデルデータD1に作業工程データD2をリンクさせてCADモデル・作業工程リンクデータD3を作成することにある。本実施形態では、この機能に加えて、工事施工引合ファイルD4と工事発注ファイルD5を作成する機能も負わせている。そのために、CADモデル/作業工程リンク処理部13は、前処理部31、リンク処理部32、作業量集計部33、リンク処理部データベース部34、電子ファイル入力部35、及び電子ファイル作成部36を備えている。   Details of the CAD model / work process link processing unit 13 will be described below. FIG. 2 shows the configuration of the CAD model / work process link processing unit 13. The basic function of the CAD model / work process link processing unit 13 is to create CAD model / work process link data D3 by linking work process data D2 to CAD model data D1. In the present embodiment, in addition to this function, a function for creating a construction work inquiry file D4 and a work ordering file D5 is also imposed. Therefore, the CAD model / work process link processing unit 13 includes a preprocessing unit 31, a link processing unit 32, a work amount totaling unit 33, a link processing unit database unit 34, an electronic file input unit 35, and an electronic file creation unit 36. I have.

前処理部31は、CADモデルデータD1にWBS処理を施す。すなわち、工事についてのCADモデルを上述の作業工程データD2における作業単位に対応する作業単位、つまりツリー構造的な階層化による作業単位で区画し、そのツリー構造的階層化作業単位をCADモデルデータD1に重ねてWBS化CADモデルデータD1-wを生成し、これをリンク処理部32に提供する。   The preprocessing unit 31 performs WBS processing on the CAD model data D1. That is, a CAD model for construction is divided into work units corresponding to the work units in the work process data D2 described above, that is, work units based on tree-structured hierarchies, and the tree-structured hierarchical work units are defined as CAD model data D1. The WBS-converted CAD model data D1-w is generated and provided to the link processing unit 32.

リンク処理部32は、前処理部31から提供されるCADモデルデータD1(WBS化CADモデルデータD1-w)と作業工程データベース部12から取り込む作業工程データD2のリンク付けを行ってCADモデル・作業工程リンクデータD3を生成し、これをリンク処理部データベース部34に出力する。リンク処理部32によるリンク付けは、作業工程データD2に含まれている作業単位ごとの作業完了予定期日を適宜な形態でWBS化CADモデルデータD1-wに重ねるなどしてなされる。リンク処理部32は、作業量集計用データD21も生成し、それを作業量集計部33に提供する。作業量集計用データD21は、CADモデルデータD1における上述の最小作業単位のそれぞれに付与されている、例えば溶接点やサポート取り付けなどのような定型作業の属性などについてのデータである。   The link processing unit 32 links the CAD model data D1 (WBS CAD model data D1-w) provided from the preprocessing unit 31 with the work process data D2 fetched from the work process database unit 12 to create a CAD model / work. Process link data D3 is generated and output to the link processing unit database unit 34. Linking by the link processing unit 32 is performed by superimposing the scheduled work completion date for each work unit included in the work process data D2 on the WBS CAD model data D1-w in an appropriate form. The link processing unit 32 also generates work amount totaling data D21 and provides it to the work amount totaling unit 33. The work amount totaling data D21 is data on attributes of routine work such as welding points and support attachments assigned to each of the above-mentioned minimum work units in the CAD model data D1.

作業量集計部33は、工事の施工における作業量、特に定型作業の作業量を作業量集計用データD21に基づいて集計して作業量集計データD22を作成し、それをリンク処理部データベース部34に出力する。   The work amount totaling unit 33 calculates the work amount total data D22 by totaling the work amount in the construction work, in particular, the work amount of the routine work based on the work amount totaling data D21, and generates the work amount totaling data D22. Output to.

リンク処理部データベース部34は、CADモデル・作業工程リンクデータD3や作業量集計データD22などを格納・蓄積し、それらのデータを求めに応じて提供する。   The link processing unit database unit 34 stores and accumulates the CAD model / work process link data D3, work amount totaling data D22, and the like, and provides these data as required.

電子ファイル入力部35は、外部から入力される検収申請ファイルD6や工事応札ファイルD18などの電子ファイルを受け付ける。   The electronic file input unit 35 receives electronic files such as an inspection application file D6 and a construction bid file D18 input from the outside.

電子ファイル作成部36は、CADモデル・作業工程リンクデータD3や作業量集計データD22などを用いて工事施工引合ファイルD4や工事発注ファイルD5を電子ファイルとして作成する。これらの電子ファイルは、出来高管理システム1で扱われる他の各種電子ファイル(検収申請ファイルD6や工事応札ファイルD18など)と共通のファイル形式とされる。   The electronic file creation unit 36 creates the construction work inquiry file D4 and the work order file D5 as electronic files using the CAD model / work process link data D3, work amount totaling data D22, and the like. These electronic files have a common file format with other various electronic files (such as the inspection application file D6 and the construction bid file D18) handled by the volume management system 1.

図3に、出来高管理システム1で扱われる電子ファイル40の構成例を工事施工引合ファイルD4について示す。この電子ファイル40のファイル形式は、他の各種電子ファイルでも基本的に共通であり、ヘッダ41、イメージデータ42、定型作業明細43、非定型作業明細44、施工実務者ステータスデータ45、施工実務者テキストデータ46、現場責任者査定ステータスデータ47、及び現場責任者査定テキストデータ48の各欄を含んでいる。   FIG. 3 shows an example of the configuration of the electronic file 40 handled by the volume management system 1 for the construction work inquiry file D4. The file format of the electronic file 40 is basically common to other various electronic files, and includes a header 41, image data 42, routine work details 43, non-standard work details 44, construction worker status data 45, construction personnel. Each column includes text data 46, field manager assessment status data 47, and field manager assessment text data 48.

ヘッダ41には、CADモデル作業ブロックコード、WBS、工事完了日、発注日、発注番号、発注者コード、受注番号、工事施工者コードなどのフィールがあり、これらのデータが記録される。   The header 41 has fields such as CAD model work block code, WBS, construction completion date, order date, order number, orderer code, order number, construction contractor code, etc., and these data are recorded.

イメージデータ42には、ヘッダ41におけるCADモデル作業ブロックコードに記録された作業ブロックについてのCADモデル・作業工程リンクデータD3やCADモデルベース工事進捗状態データD17が記録される。このイメージデータ42は、図に示す例のように、ツリー構造的階層化による作業単位をツリー構造のノード49として表示し、このノード49を表示画面上でクリックすることにより作業単位レベルでCADモデル・作業工程リンクデータD3やCADモデルベース工事進捗状態データD17を表示させることができるようにされている。   In the image data 42, CAD model / work process link data D3 and CAD model base construction progress status data D17 for the work block recorded in the CAD model work block code in the header 41 are recorded. In the image data 42, as shown in the example shown in the figure, a work unit based on a tree structure hierarchy is displayed as a node 49 of the tree structure, and the CAD model is selected at the work unit level by clicking the node 49 on the display screen. The work process link data D3 and CAD model base construction progress status data D17 can be displayed.

定型作業明細43には、予めCADモデルデータD1に盛り込める定型作業の属性から作業量集計部33で自動集計された作業量集計データD22が明細として記録される。この定型作業明細43は、定型作業項目、物量、標準コストなどのフィールドを含む。   In the routine work description 43, the work amount totaling data D22 automatically counted by the work amount totaling unit 33 based on the attributes of the standard work included in the CAD model data D1 in advance is recorded as details. The standard work details 43 include fields such as standard work items, quantities, and standard costs.

非定型作業明細44には、例えばアライメント調整や防振対策などのような非定型業務についての記録が管理者・施工者双方によるマニュアル操作でなされる。   In the non-standard work details 44, for example, a record of non-standard work such as alignment adjustment and anti-vibration measures is made by manual operation by both the manager and the installer.

施工実務者ステータスデータ45には、工事の施工実務を遂行する施工実務者により工事のステータス(工事進捗状態)が記録される。その記録は、自動的にCADモデル・作業工程リンクデータD3ないしCADモデルベース工事進捗状態データD17に反映される。この施工実務者ステータスデータ45は、見積デビエーション、工事デビエーション、工事着手、工事完了、検査完了、工事トラブル、工程遅延などのフィールを含む。   In the construction practitioner status data 45, the construction status (construction progress state) is recorded by the construction practitioner who performs the construction practice. The record is automatically reflected in the CAD model / work process link data D3 or CAD model base construction progress status data D17. The construction practitioner status data 45 includes fields such as estimated deviation, construction deviation, construction start, construction completion, inspection completion, construction trouble, and process delay.

施工実務者テキストデータ46には、施工実務者が必要に応じてテキストデータを入力する。   In the construction practitioner text data 46, the construction practitioner inputs text data as necessary.

現場責任者査定ステータスデータ47には、施工実務者が遂行する施工実務を監督管理する現場責任者が施工実務者からの進捗状態報告に対して行う査定に関するデータが記録される。その記録は、自動的にCADモデル・作業工程リンクデータD3ないしCADモデルベース工事進捗状態データD17に反映される。この現場責任者査定ステータスデータ47は、検収完了、拒絶査定、工事凍結、支払完了、支払未完などのフィールドを含む。   The field manager assessment status data 47 records data relating to the assessment performed by the site manager who supervises and manages the construction practice performed by the construction practitioner with respect to the progress report from the construction practitioner. The record is automatically reflected in the CAD model / work process link data D3 or CAD model base construction progress status data D17. The field manager assessment status data 47 includes fields such as acceptance completion, rejection assessment, construction freeze, payment completion, and payment incomplete.

現場責任者査定テキストデータ48には、現場責任者が必要に応じてテキストデータを入力する。   The site manager inputs text data to the site manager assessment text data 48 as necessary.

ここで、施工者側には、施工実務者と現場責任者があり、施工実務者からの進捗状態報告を現場責任者が査定し、それを受け入れれば、それに基づいて現場責任者が検収申請ファイルD6を作成して検収申請を管理者に対して行うことになる。   Here, there are construction practitioners and site managers on the contractor side. When the site manager assesses the progress report from the construction practitioner and accepts it, the site manager applies for acceptance based on it. The file D6 is created and an inspection application is made to the administrator.

次に、出来高管理システム1の運用、つまり出来高管理システム1による出来高管理方法について説明する。出来高管理は、その基本として、管理者側と施工者側の関与の下で、工事の内容や進捗状態をイメージ的に可視化する情報として出来高管理対象の工事に関するCADモデルを包含して上述のようなファイル形式を共通に作成される各種電子ファイルの授受を通じて行われる。   Next, the operation of the volume management system 1, that is, the volume management method by the volume management system 1 will be described. Volume management basically includes the CAD model related to the volume management target construction as information that visualizes the contents and progress of construction with the involvement of the manager and the contractor as described above. This is done through the exchange of various electronic files created in common.

また出来高管理で基本的に必要とされる処理は、予定の進捗状態と実際の進捗状態の関係、及び工事の進捗に応じて施工者側で実際に要した費用である実際原価と管理者側で予定した費用である実行予算の関係について処理である。すなわち、施工者側が例えば月単位で工事の進捗実績を検収申請するとともに実際原価による費用を請求し、申請された進捗実績を管理者側が検収し、管理者側がその申請を査定し、工事が予定通りに進捗しており、請求費用が実行予算との関係で問題なしとすれば費用の支払いをする、という処理が出来高管理で基本的に必要とされる処理である。本実施形態の出来高管理システム1では、こうした基本的な出来高管理をなす機能に加えて、それに関連する処理である工事施工引合い、工事応札、工事発注、情報開示、作業工程見直しなどの各処理についても共通ファイル形式の電子ファイルによる処理などを行うための機能も有している。以下では、出来高管理システム1で行われるこれらの各処理について順次説明する。   In addition, the basic processing required for volume management is the relationship between the planned progress and the actual progress, and the actual costs that are actually required by the contractor according to the progress of the construction, and the manager's side. It is a process about the relationship of the execution budget which is the expense which was planned in (4). In other words, for example, the contractor submits an application for acceptance of the actual progress of construction work on a monthly basis, charges for the actual cost, the manager confirms the submitted progress, the manager assesses the application, and the construction is scheduled This is a process that is basically required for volume management, in which the process of paying the cost if the billing cost is related to the execution budget is acceptable. In the volume management system 1 of this embodiment, in addition to such basic volume management functions, each process such as construction work inquiry, construction bidding, construction ordering, information disclosure, work process review, and the like related processes are performed. Also has a function for performing processing using an electronic file in a common file format. Hereinafter, each of these processes performed in the volume management system 1 will be described sequentially.

出来高管理システム1の運用においては、まず工事の施工開始までの処理が進められる。工事施工開始までには、工事施工引合い、工事応札、工事発注の各処理が行われる。これらの処理に先立っては、イメージ的可視化情報の基になるCADモデル・作業工程リンクデータD3を作成する。CADモデル・作業工程リンクデータD3の作成は、CADモデル/作業工程リンク処理部13において上述のようにしてなされる。すなわち、前処理部31により、CADモデルデータベース部11から取り出したCADモデルデータD1にWBS処理を施してWBS化CADモデルデータD1-wを作成し、このWBS化CADモデルデータD1-wにリンク処理部32が作業工程データベース部12からの作業工程データD2のリンク付けを行ってCADモデル・作業工程リンクデータD3を作成する。またCADモデル/作業工程リンク処理部13では、CADモデル・作業工程リンクデータD3の作成と同時に、作業量集計用データD21も作成される。これらのデータの作成は、上述の作業ブロックを単位として行われる。   In the operation of the volume management system 1, processing up to the start of construction is first advanced. Prior to the start of construction, each process of construction inquiries, construction bids, and construction orders is performed. Prior to these processes, CAD model / work process link data D3, which is the basis of the image visualization information, is created. The CAD model / work process link data D3 is created in the CAD model / work process link processing unit 13 as described above. That is, the pre-processing unit 31 performs WBS processing on the CAD model data D1 extracted from the CAD model database unit 11 to create WBS-based CAD model data D1-w, and performs link processing on the WBS-based CAD model data D1-w. The unit 32 links the work process data D2 from the work process database unit 12 to create CAD model / work process link data D3. The CAD model / work process link processing unit 13 creates work amount totaling data D21 simultaneously with the creation of the CAD model / work process link data D3. The creation of these data is performed in units of the above-described work blocks.

CADモデル・作業工程リンクデータD3や作業量集計用データD21が作成されると、これらのデータを取り込んだ工事施工引合ファイルD4がCADモデル/作業工程リンク処理部13により作成される。作成された工事施工引合ファイルD4は、入札参加者(工事施工業者)にインターネットのような通信網などを通じて送られる。   When the CAD model / work process link data D3 and work amount totaling data D21 are created, a construction work inquiry file D4 incorporating these data is created by the CAD model / work process link processing unit 13. The created construction work inquiry file D4 is sent to a bid participant (construction contractor) through a communication network such as the Internet.

工事施工引合ファイルD4を受け取った入札参加者は、工事施工引合ファイルD4のイメージデータ42におけるCADモデル・作業工程リンクデータD3や定型作業明細43における作業量集計用データD21などによって工事のスコープ、つまり当該入札参加者が分担することができる工事ブロックや作業単位を確認し、デビエーションを検討する。ここで、デビエーションとは、発注側が要求する工事内容と受注側が遂行可能な工事内容との偏差のことである。例えば発注側が「10」の内容の工事を要求しているのに対して、受注側で遂行可能な工事内容が「8」であると、「2」の偏差があることになるが、これがデビエーションとなる。スコープの確認とデビエーションの検討を終えて応札するとした場合、入札参加者は、デビエーションがあれば、それについてのデータをテキスト形式などで入力して工事応札ファイルD18を作成し、それを管理者(この時点では発注者)に送る。   The bid participant who has received the construction work inquiry file D4 determines the scope of the work, that is, the work scope by the CAD model / work process link data D3 in the image data 42 of the construction work inquiry file D4 or the work amount totaling data D21 in the fixed work details 43 Confirm the construction blocks and work units that the bid participants can share, and consider deviations. Here, the deviation is a deviation between the construction content requested by the ordering side and the construction content that can be performed by the order receiving side. For example, if the ordering side requests construction with a content of “10”, but the construction content that can be performed by the order receiving side is “8”, there will be a deviation of “2”, which is a deviation. It becomes. In the case of bidding after confirming the scope and consideration of the deviation, the bid participant creates a construction bidding file D18 by inputting the data in a text format etc., if there is a deviation, and creates it as a manager ( At this time, it is sent to the orderer.

工事応札ファイルD18を受け取った管理者は、それの内容を確認し、当該応札希望者を選定するとしたら、工事発注ファイルD5を作成し、それを当該応札希望者に送る。この際、工事応札ファイルD18にデビエーションがあり、それを受け入れる場合、必要であれば、そのデビエーションを反映させてCADモデル・作業工程リンクデータD3や作業量集計用データD21の変更を行う。工事発注ファイルD5は、工事の発注についての契約内容となる。そして、工事発注以後の工事の進捗に伴って管理者と施工者の間で生じる各種交渉などの結果として工事の設計変更とそれに伴うCADモデル・作業工程リンクデータD3の変更などがなされた場合には、その変更履歴が工事発注ファイルD5に反映される。   The manager who has received the construction bidding file D18 confirms the contents thereof, and if the bidding applicant is selected, creates a construction ordering file D5 and sends it to the bidding applicant. At this time, there is a deviation in the construction bidding file D18. If it is accepted, the CAD model / work process link data D3 and the work amount totaling data D21 are changed to reflect the deviation if necessary. The construction order file D5 is a contract for construction ordering. And, as a result of various negotiations, etc. that occur between the manager and the contractor in accordance with the progress of the work after the work order has been placed, when the work design changes and the CAD model / work process link data D3 change accordingly, etc. The change history is reflected in the construction order file D5.

以上のようにして確定した施工者に工事発注がなされて工事の施工が開始されると、以後は、施工者側が例えば月単位で工事の進捗状態を検収申請するとともに実際原価による費用を請求し、管理者側は申請された進捗状態や費用請求を査定し、工事が予定通りに進捗しており、請求費用が実行予算との関係で問題なしとすればその支払いをする、といった出来高管理が工事の完了まで繰り返される。   When a construction order is made to the contractor determined as described above and the construction starts, the contractor then applies for acceptance of the progress status of the construction, for example, on a monthly basis, and charges the actual cost. The management side assesses the submitted progress status and cost claim, and the construction is progressing as planned, and if the billing cost is not related to the execution budget, payment will be made. Repeat until construction is complete.

施工者による工事進捗状態の検収申請は、検収申請ファイルD6を作成して管理者に送ることでなされる。検収申請ファイルD6の作成は、上述のように申請部3を利用して行い、その際には、検収対象CADモデル作業ブロック検索指令D23を入力して検収対象のCADモデル作業ブロックについてのCADモデル・作業工程リンクデータD3を公開情報データベース部14から工事進捗状態データ作成部21に取り込む。そして工事進捗状態データD16を入力し、それをCADモデル・作業工程リンクデータD3に重ね合わせてCADモデルベース工事進捗状態データD17を作成する。   The application for inspection of the construction progress status by the installer is made by creating an inspection application file D6 and sending it to the manager. The acceptance application file D6 is created using the application unit 3 as described above. At this time, the CAD model work block search command D23 is input, and the CAD model for the CAD model work block to be accepted is entered. The work process link data D3 is taken from the public information database unit 14 into the construction progress state data creation unit 21. Then, construction progress status data D16 is input, and this is superimposed on CAD model / work process link data D3 to create CAD model base construction progress status data D17.

検収申請ファイルD6を受け取った管理者は、それを検収のために査定する。その検収においては、検収申請ファイルD6に含まれているCADモデルベース工事進捗状態データD17などで実際の進捗状態を把握してそれを予定の進捗状態と比較し、また施工者からの請求費用(実際原価)を実行予算と比較し、問題なしとすれば査定を確定して査定確定D15を取引決済処理部17入力する。   The manager who has received the acceptance application file D6 assesses it for acceptance. In the acceptance inspection, the actual progress state is grasped by the CAD model base construction progress state data D17 included in the acceptance application file D6 and compared with the planned progress state. The actual cost is compared with the execution budget, and if there is no problem, the assessment is confirmed and the assessment confirmation D15 is input to the transaction settlement processing unit 17.

検収において検収申請ファイルD6でCADモデルベース工事進捗状態データD17を参照するには、検収申請ファイルD6におけるイメージデータ42の欄でノード49をクリックすることにより作業単位レベルでCADモデルベース工事進捗状態データD17を表示させる。CADモデルベース工事進捗状態データD17は、CADモデルをベースにしたデータであり、出来高に対する施工者側と管理者側双方の認識の共通性をより高めるような客観性の高い出来高情報を与え、特に部分的な設計変更などがあった場合に、その設計変更部分の作業量などについて具体的なイメージをもって認識の共通性を高めるような出来高情報を与える。このため管理者側では、設計変更などに伴う工事の遅延や資金ショートなどの問題を効果的に避けることが可能となる。   To refer to the CAD model base construction progress status data D17 in the acceptance application file D6 in the acceptance inspection, click the node 49 in the column of the image data 42 in the acceptance application file D6 to select the CAD model base construction progress status data at the work unit level. D17 is displayed. The CAD model base construction progress status data D17 is data based on the CAD model, and provides highly objective volume information that increases the commonality of both the construction side and the manager side with respect to the volume. When there is a partial design change, yield information that increases the commonality of recognition with a specific image of the amount of work of the design change part is given. For this reason, it is possible for the manager side to effectively avoid problems such as delays in construction and shortage of funds due to design changes.

査定確定D15の入力を受けた取引決済処理部17は、検収申請された進捗工事分について支払いに関する許可条件D13を生成してそれを外部に出力するとともに、検収実績情報D14を公開情報データベース部14に出力する。   Upon receipt of the assessment confirmation D15, the transaction settlement processing unit 17 generates a permission condition D13 related to payment for the progress work for which the acceptance application has been applied, outputs it to the outside, and outputs the inspection result information D14 to the public information database unit 14 Output to.

検収において進捗状態や実際原価に問題があるとした場合には、管理者と施工者の間でその問題についての交渉がなさる。また進捗状態に問題がある場合には、上述のような作業工程シミュレータ部16による作業工程の見直しのシミュレーションが行われる。さらに検収申請された進捗状態から作業遅延や納期遅延につながる兆候があると判断された場合には上述のようにして警報が発せられる。警報が発せられた場合、管理者は作業遅延などを回避するための対策をとる。管理者と施工者の間での交渉が妥結すれば査定確定D15を取引決済処理部17入力する。   If there is a problem with the progress status or actual cost in the acceptance inspection, the manager and the contractor will negotiate the problem. When there is a problem in the progress state, a work process review simulation is performed by the work process simulator 16 as described above. Further, when it is determined that there is a sign of work delay or delivery delay from the progress status of the application for acceptance, an alarm is issued as described above. When an alarm is issued, the administrator takes measures to avoid work delays. If the negotiation between the manager and the contractor is concluded, the assessment settlement D15 is input to the transaction settlement processing unit 17.

以上のような検収申請と検収が定期的に繰り返されながら工事が進行している間には、上述のように、情報公開部4により管理者、施工者、工事の最終顧客に対して工事に関する情報が公開される。公開する情報は、いずれもイメージ的可視化情報の基になるCADモデルを含む工事進捗状態情報D19や検収/作業工程予測/実績情報D20である。このような情報を公開して管理者、施工者、工事の最終顧客の間で工事に関する重要な情報を共有できるようにすることで、出来高管理やそれに伴う交渉などをよりスムースに行えるようになる。   As described above, while the application for inspection and inspection are periodically repeated as described above, the information disclosure section 4 provides information on the work to the manager, the installer, and the final customer of the construction. Information is made public. The information to be disclosed is construction progress status information D19 and inspection / work process prediction / result information D20 including a CAD model that is the basis of the image visualization information. By making such information public and sharing important information about construction among managers, contractors, and end customers of construction, volume management and negotiations associated with it can be performed more smoothly. .

一実施形態による出来高管理システムの構成を示す図である。It is a figure which shows the structure of the volume management system by one Embodiment. CADモデル/作業工程リンク処理部の構成を示す図である。It is a figure which shows the structure of a CAD model / work process link process part. 出来高管理システムで扱われる電子ファイルの構成例を示す図である。It is a figure which shows the structural example of the electronic file handled with a volume management system.

符号の説明Explanation of symbols

1 出来高管理システム
21 工事進捗状態データ作成部
32 リンク処理部
D3 CADモデル・作業工程リンクデータ(CADモデル包含データ)
D6 検収申請ファイル
D16 工事進捗状態データ
D17 CADモデルベース工事進捗状態データ
1 Volume management system 21 Construction progress status data creation unit 32 Link processing unit D3 CAD model / work process link data (CAD model inclusion data)
D6 Inspection application file D16 Construction progress status data D17 CAD model base construction progress status data

Claims (4)

施工者側が進める工事の進捗状態を管理するのに用いられる出来高管理システムにおいて、
出来高管理対象の工事に関するCADモデルを含むCADモデル包含データを管理者側が前記施工者側に提供し、前記施工者側は前記CADモデル包含データに工事の実際の進捗状態に関する工事進捗状態データを重ね合わせてCADモデルベース工事進捗状態データを作成し、このCADモデルベース工事進捗状態データを用いて前記管理者側に対する工事進捗状態の検収申請を行えるようにされていることを特徴とする出来高管理システム。
In the volume management system used to manage the progress status of the construction that the contractor proceeds,
The administrator side provides the CAD model inclusion data including the CAD model relating to the work to be managed in volume management to the builder side, and the builder side superimposes the construction progress state data regarding the actual progress state of the construction on the CAD model inclusion data. In addition, a CAD model-based construction progress status data is created, and the CAD model-based construction progress status data is used to make an application for acceptance of the construction progress status to the manager side. .
前記CADモデル包含データとして、前記CADモデルに工事の作業単位ごとの進捗計画に関する作業工程をリンクさせて作成されるCADモデル・作業工程リンクデータを用いるようにしたことを特徴とする請求項1に記載の出来高管理システム。   2. The CAD model / work process link data created by linking a work process related to a progress plan for each work unit of work to the CAD model is used as the CAD model inclusion data. The volume management system described. 前記CADモデルに前記作業工程をリンクさせてCADモデル・作業工程リンクデータを作成するリンク処理部を備えるとともに、前記工事進捗状態データを前記CADモデル・作業工程リンクデータに重ね合わせて前記CADモデルベース工事進捗状態データを作成する工事進捗状態データ作成部を備えていることを特徴とする請求項2に記載の出来高管理システム。   The CAD model base includes a link processing unit that links the work process to the CAD model to create CAD model / work process link data, and superimposes the construction progress status data on the CAD model / work process link data. The volume management system according to claim 2, further comprising a construction progress status data creation unit that creates construction progress status data. CADモデルとして3次元CADモデルを用いるようにされていることを特徴とする請求項1〜請求項3のいずれか1項に記載の出来高管理システム。   The volume management system according to any one of claims 1 to 3, wherein a three-dimensional CAD model is used as the CAD model.
JP2006157566A 2006-06-06 2006-06-06 Piecework management system Pending JP2007328434A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006157566A JP2007328434A (en) 2006-06-06 2006-06-06 Piecework management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006157566A JP2007328434A (en) 2006-06-06 2006-06-06 Piecework management system

Publications (1)

Publication Number Publication Date
JP2007328434A true JP2007328434A (en) 2007-12-20

Family

ID=38928877

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006157566A Pending JP2007328434A (en) 2006-06-06 2006-06-06 Piecework management system

Country Status (1)

Country Link
JP (1) JP2007328434A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2019168980A (en) * 2018-03-23 2019-10-03 株式会社オービック Progress rate calculation device, progress rate calculation method and progress rate calculation program
CN115878872A (en) * 2023-02-08 2023-03-31 一智科技(成都)有限公司 Construction progress visualization method and system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0926995A (en) * 1995-07-11 1997-01-28 Takenaka Komuten Co Ltd Architectural drawing preparing device with completed amount control function
JP3262522B2 (en) * 1997-11-27 2002-03-04 株式会社ビーイング Civil engineering cost control device
JP2004005237A (en) * 2002-05-31 2004-01-08 Hitachi Plant Eng & Constr Co Ltd Work progress management support method and system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0926995A (en) * 1995-07-11 1997-01-28 Takenaka Komuten Co Ltd Architectural drawing preparing device with completed amount control function
JP3262522B2 (en) * 1997-11-27 2002-03-04 株式会社ビーイング Civil engineering cost control device
JP2004005237A (en) * 2002-05-31 2004-01-08 Hitachi Plant Eng & Constr Co Ltd Work progress management support method and system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2019168980A (en) * 2018-03-23 2019-10-03 株式会社オービック Progress rate calculation device, progress rate calculation method and progress rate calculation program
JP7197989B2 (en) 2018-03-23 2022-12-28 株式会社オービック Progress rate calculation device, progress rate calculation method, and progress rate calculation program
CN115878872A (en) * 2023-02-08 2023-03-31 一智科技(成都)有限公司 Construction progress visualization method and system

Similar Documents

Publication Publication Date Title
Tetik et al. Direct digital construction: Technology-based operations management practice for continuous improvement of construction industry performance
Li et al. A project-based quantification of BIM benefits
Giel et al. Return on investment analysis of using building information modeling in construction
Sloot et al. Assessing usefulness of 4D BIM tools in risk mitigation strategies
KR101760260B1 (en) BIM omitted
KR20070104099A (en) System for network-based development and management of information technology solutions and method thereof
Chelson The effects of building information modeling on construction site productivity
JP2023524043A (en) Model, cost and schedule mapping system for large capital projects
Chen et al. Supplier-contractor coordination approach to managing demand fluctuations of ready-mix concrete
Said et al. Impact of design changes on virtual design and construction performance for electrical contractors
AU2011248728A1 (en) Risk assessment and mitigation planning system and method
Chen et al. Application of project-based change management in construction: a case study
Mohammad et al. Causes and effects of variation orders in the construction of terrace housing projects: A case study in the State of Selangor, Malaysia
Marzouk et al. Applications of building information modeling in cost estimation of infrastructure bridges
JP2012098849A (en) Credibility evaluation method for construction progress level
Moayeri Design change management in construction projects using Building Information Modeling (BIM)
JP2007328434A (en) Piecework management system
US10831944B1 (en) System and method to facilitate the design, manufacturing and construction of structures
Fazeli et al. Automated 4D BIM development: The resource specification and optimization approach
Hassanain et al. Modeling knowledge for MEP coordination in building projects in Saudi Arabia
AU2020102657A4 (en) Systems and Methods for Building and Construction Management and Resource Sharing
Rehman et al. Data-driven integration framework for four-dimensional building information modeling simulation in modular construction: a case study approach
Seo et al. Calculating the cost impact in loss of productivity claims
Schlachter et al. Using Linked Building Data for managing temporary construction items
KR20000054016A (en) Total Engineering &amp; Construction by Internet

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080509

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20101221

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110221

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20110524