JP2007204925A - Steel tower rebuilding method and work bench therefor - Google Patents

Steel tower rebuilding method and work bench therefor Download PDF

Info

Publication number
JP2007204925A
JP2007204925A JP2006021788A JP2006021788A JP2007204925A JP 2007204925 A JP2007204925 A JP 2007204925A JP 2006021788 A JP2006021788 A JP 2006021788A JP 2006021788 A JP2006021788 A JP 2006021788A JP 2007204925 A JP2007204925 A JP 2007204925A
Authority
JP
Japan
Prior art keywords
steel tower
tower
work
new
rebuilding
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2006021788A
Other languages
Japanese (ja)
Inventor
Takashi Inoue
隆 井上
Masaki Ogiwara
将樹 荻原
Shunei Iwamoto
俊英 岩本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyo Electric Power Company Holdings Inc
Original Assignee
Tokyo Electric Power Co Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Electric Power Co Inc filed Critical Tokyo Electric Power Co Inc
Priority to JP2006021788A priority Critical patent/JP2007204925A/en
Publication of JP2007204925A publication Critical patent/JP2007204925A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a steel tower rebuilding technology capable of safely and accurately carrying out basic system transmission line steel tower rebuilding work at a low cost within a short power transmission stop period of time. <P>SOLUTION: In the case the existing steel tower 1 is rebuilt, the steel tower rebuilding method constructing a new steel tower A makes good use of a built-up type work bench K installed around the existing steel tower. A plurality of expansible towers 2 are erected at a regular interval around the existing steel tower 1, a supporting member 3 is erected between the expansion/contraction towers, the first process installing the work bench by having a crane device 4 capable of moving along the supporting member, the second process constructing a foundation 5 for the new steel tower by making use of the crane device after the work bench has been installed and the third process assembling a new steel tower lower area of a part near to a charging section 1b of the existing steel tower from the foundation for the new steel tower while expanding/contracting the expansion towers are carried out. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本発明は、既設鉄塔の建て替えに際し、その既設鉄塔の周囲に設置する組み立て式の作業架台を利用して新設鉄塔を施工する鉄塔建て替え技術に関する。   The present invention relates to a steel tower rebuilding technique for constructing a new steel tower using an assembly-type work platform installed around the existing steel tower when rebuilding the existing steel tower.

送電線鉄塔の建て替え工法として、特許文献1に示す2脚1/2面包み込み工法、特許文献2に示すケーブルジャンパー工法、長大ジャンパーによる仮設工事の簡略化工法等が従来から採用されている。これらの工法は、いわゆる、一回線交互停止による鉄塔建て替え工法であるが、次のような問題がある。   As a rebuilding method for a transmission line tower, a two-leg ½-side wrapping method shown in Patent Document 1, a cable jumper method shown in Patent Document 2, a simplified temporary construction method using a long jumper, and the like have been conventionally employed. These construction methods are so-called steel tower rebuilding methods by alternately stopping one line, but have the following problems.

2脚1/2面包み込み工法では、既設鉄塔に強度を負担させているものの、既設鉄塔強度の裕度は少ないという問題がある。したがって、台風、強風が予想される時期は採用できない。この問題は嵩上げ工法でも同様である。   In the two-leg half-plane wrapping method, although the existing steel tower is given strength, there is a problem that the margin of the existing steel tower strength is small. Therefore, the period when typhoons and strong winds are expected cannot be adopted. This problem also applies to the raising method.

ケーブルジャンパー工法は、超高圧送電線には設備容量的に採用できない。長大ジャンパー工法は簡易な支持柱が必要で、超高圧送電線ではジャンパーからのクリアランスが大きく、支持柱が過大となるほか、超超高圧送電線鉄塔のような基幹系送電線鉄塔の建て替え工法には採用し難い場合が多い。
特開2000−345740号公報 特開2000−270454号公報
The cable jumper method cannot be used in terms of equipment capacity for ultra high voltage transmission lines. The long jumper method requires a simple support column. In the ultra high voltage transmission line, the clearance from the jumper is large, the support column becomes excessive, and the rebuilding method for the main transmission line tower such as the ultra ultra high voltage transmission line tower. Are often difficult to adopt.
JP 2000-345740 A JP 2000-270454 A

一方、一回線交互停止による鉄塔建て替え工法に代えて、建て替え対象鉄塔を含む区間の充電停止により既設設備の全撤去後に新設鉄塔を建て替える工法も従来から採用されている。   On the other hand, instead of the steel tower rebuilding method by one-line alternating stop, a method of rebuilding the new steel tower after removing all existing facilities by stopping the charging of the section including the tower to be rebuilt has been adopted.

この工法では、設備規模、周辺環境等により、区間充電停止日数は異なるが、既設設備を全撤去後、新設基礎の施工、鉄塔本体の組立、架線工事を実施する。その際、充電停止日数を可能な限り少なくするために、新設基礎の施工後に、既設鉄塔を撤去する場合もある。   In this construction method, the number of days of section charge stoppage varies depending on the scale of the equipment, the surrounding environment, etc., but after removing all the existing equipment, construction of the new foundation, assembly of the tower body, and overhead construction will be carried out. At that time, the existing steel tower may be removed after the construction of the new foundation in order to minimize the number of days of charge suspension.

しかし、この工法では、次のような課題がある。
(1)第1に、鉄塔建て替え工事に伴い、区間充電停止日数が長期に及ぶことになるが、大型送電線の多くは基幹系送電線であり、供給信頼度維持の観点から、長期停止が得られにくい状況にある。
(2)第2に、大型重機や補助クレーン等の長期使用により、施工コストがかかる問題がある。
(3)第3に、送電線充電中は作業安全上、その作業範囲や重機クレーンの高さ等が大幅に制限される問題がある。
(4)第4に、充電部直下の高い位置に、工事範囲の上限位置を示す目印となるワイヤーや隔離ネット等を張設しておく必要があるが、これらを張設するための仮設工事が必要となる。
However, this method has the following problems.
(1) Firstly, due to the rebuilding of towers, the number of days of section charge stoppage will be extended for a long time, but most of the large transmission lines are backbone transmission lines. It is difficult to obtain.
(2) Secondly, there is a problem that construction costs are increased due to long-term use of large heavy machinery, auxiliary cranes and the like.
(3) Thirdly, there is a problem that the working range, the height of the heavy machinery crane, and the like are greatly limited for work safety during charging of the transmission line.
(4) Fourthly, it is necessary to stretch a wire or an isolation net to mark the upper limit position of the work range at a high position directly under the live part. Temporary work to stretch these Is required.

よって、本発明の課題は、基幹系送電線鉄塔建て替え工事を短い送電停止期間で安全かつ的確に、低コストで実施することができる鉄塔建て替え技術を提供することにある。   Therefore, the subject of this invention is providing the steel tower rebuilding technique which can implement backbone system power transmission line steel tower rebuilding construction safely, exactly, and at low cost in a short power transmission stop period.

前記課題を解決するため、本発明では以下の手段を採用した。
本発明は、既設鉄塔の建て替えに際し、その既設鉄塔の周囲に設置する組み立て式の作業架台を利用して新設鉄塔を施工する鉄塔建て替え工法であって、
既設鉄塔の周囲に間隔をおいて複数の伸縮タワーを立設し、その伸縮タワー間に支持部材を架設し、その支持部材に添って走行移動可能なクレーン装置を装備して作業架台を設置する第1工程と、
作業架台の設置後に、クレーン装置を利用して新設鉄塔用の基礎を施工する第2工程と、
伸縮タワーを伸長させつつ、新設鉄塔用の基礎から既設鉄塔の充電部近くに至る部分の新設鉄塔下部領域を組み立てる第3工程と、
を行うことを特徴としている。
In order to solve the above-mentioned problems, the present invention employs the following means.
The present invention is a tower rebuilding method for constructing a new tower using an assembly-type work platform installed around the existing tower when rebuilding an existing tower,
A plurality of telescopic towers are installed around the existing steel tower at intervals, a support member is installed between the telescopic towers, and a work platform is installed with a crane device that can travel along the support member. The first step;
A second step of constructing a foundation for a new steel tower using a crane device after installation of the work platform;
A third step of assembling the lower part of the new tower from the foundation for the new tower to the vicinity of the charging part of the existing tower while extending the telescopic tower;
It is characterized by performing.

本発明によれば、建て替え対象鉄塔(既設鉄塔)の周囲に設置する作業架台は、伸縮タワーによってクレーン装置の支持部材が上下に昇降移動でき、クレーン装置は支持部材に添って水平方向へ移動できる。従って、伸縮タワーを収縮させた状態にして、この作業架台を既設鉄塔の下部に設置することで、既設鉄塔が充電状態のまま、クレーン装置を利用して新設鉄塔用の基礎工事及び新設鉄塔下部領域の組立工事等を行うことができる。また、伸縮タワーを順次伸長させことで、充電部直下の新設鉄塔下部領域全体について組み立て作業を行うことが可能になる。この際、作業架台の高さ以上は作業範囲とならず、確実に充電部との離隔距離を確保することができ、作業上の安全性を高めることができる。   According to the present invention, the work platform installed around the rebuilding target tower (existing tower) can move the support member of the crane device up and down by the telescopic tower, and the crane device can move along the support member in the horizontal direction. . Therefore, when the telescopic tower is contracted and this work platform is installed at the lower part of the existing tower, the existing tower is charged and the foundation work for the new tower and the lower part of the new tower are maintained using the crane device. The assembly work of the area can be performed. In addition, by sequentially extending the telescopic tower, it is possible to perform assembly work on the entire lower area of the new steel tower directly below the charging unit. At this time, the height of the work platform or more is not within the work range, and the separation distance from the charging unit can be surely ensured, and the work safety can be enhanced.

本発明では、新設鉄塔下部領域の組立後に前記作業架台を撤去する工程と、作業架台撤去後に既設鉄塔の充電部を区間充電停止状態とし、新設鉄塔下部領域に続く上部領域の新設鉄塔組立工程及び既設鉄塔の解体工程を行うことが望ましい。この新設鉄塔下部領域を組み立ててから上部領域に移行することで、送電停止日数(区間充電停止日数)を大幅に少なくすることが可能になる。   In the present invention, the step of removing the work platform after the assembly of the new tower lower region, the charging section of the existing tower after the removal of the work platform, the section charging stop state, the new tower assembly process of the upper region following the new tower lower region, It is desirable to perform the dismantling process of the existing steel tower. By assembling the lower area of the new tower and then moving to the upper area, it is possible to significantly reduce the number of days of power transmission stoppage (number of days of section charge stoppage).

前記作業架台は、平面矩形の四隅に配置される4つの伸縮タワーと、平面矩形の各辺に沿って延びるように配置される4つの支持部材とを備え、各支持部材のうちの少なくとも2つに前記クレーン装置がそれぞれ装備されていることが望ましい。このような作業架台を用いた場合、4つの支持部材のそれぞれにクレー装置を装備することが可能になる。これにより、2つ以上のクレーン装置を利用して、基礎工事や鉄塔組立工事に係る各種作業を同時進行で行うことが可能となり、その分、作業能率を高めて施工期間を短縮することができる。   The work platform includes four telescopic towers arranged at four corners of a planar rectangle and four support members arranged to extend along each side of the planar rectangle, and at least two of the support members It is desirable that each of the crane devices is equipped. When such a work platform is used, each of the four support members can be equipped with a clay device. As a result, it is possible to simultaneously perform various types of work related to foundation work and steel tower assembly work using two or more crane devices, thereby improving work efficiency and shortening the work period. .

前記新設鉄塔用の基礎を施工する第2工程は、杭打ち作業、掘削作業、コンクリート打設作業を含み、それら各作業のうち少なくとも一つの作業において前記クレーン装置を複数用いて行うことが望ましい。例えば、杭打ち作業においては第1のクレーン装置で杭打ち機材の吊り込み作業を行い、第2のクレーン装置で鉄筋篭の建て込み作業を行うことで、異なる作業を併行して、あるいは同種の作業を同時進行で行うことができる。特に、従来必要であった杭打ち工事での補助クレーンを不要にできることにより、これまで、狭隘地では機材配置の関係から1本づつの杭施工であったが、複数杭の併行作業が可能となる。   The second step of constructing the foundation for the new steel tower includes pile driving work, excavation work, and concrete placing work, and it is desirable that at least one of these works be performed using a plurality of the crane devices. For example, in the pile driving work, the first crane device is used to hang the pile driving equipment, and the second crane device is used to build the reinforcing bar. Work can be done simultaneously. In particular, by making it possible to eliminate the need for an auxiliary crane for pile driving work, which has been necessary in the past, it has been the construction of one pile at a time because of the arrangement of equipment in confined areas. Become.

前記新設鉄塔下部領域を組み立てる第3工程では、前記クレーン装置を利用して鉄塔組立に必要な部材搬入作業及び地組作業を行うことが望ましい。この種の作業では、クレーン装置は水平配置となる支持部材に添って走行移動できるので、例えば狭隘地において、搬入出口から遠い位置への鉄塔部材の搬入も容易に可能となる。   In the third step of assembling the lower area of the new steel tower, it is desirable to carry out member carrying-in work and ground work necessary for steel tower assembly using the crane device. In this type of work, the crane device can travel along the horizontally arranged support member, so that it is possible to easily carry in the steel tower member to a position far from the carry-in / out port, for example, in a narrow area.

前記新設鉄塔下部領域を組み立てる第3工程では、前記伸縮タワーを伸長し、既設鉄塔の充電部に対する隔離ネットを前記伸縮タワーに設置して行うことが望ましい。このようにすれば、充電部付近での組立作業を可能にすることができる。また、伸縮タワーは作業時のみ上昇させ、非作業時は収縮させることで安全性並びに安定性を図ることができる。   In the third step of assembling the new steel tower lower region, it is desirable to extend the telescopic tower and install an isolation net for the charging part of the existing steel tower in the telescopic tower. If it does in this way, assembly work near the charge part can be made possible. In addition, the telescopic tower can be raised only during work and can be shrunk during non-work, thereby ensuring safety and stability.

本発明は、既設鉄塔の建て替えに際し、その既設鉄塔の周囲に設置して用いる組み立て式の作業架台であって、既設鉄塔の周囲に間隔をおいて立設される複数の伸縮タワーと、その伸縮タワー間に架設される支持部材と、その支持部材に添って走行移動可能に装備されるクレーン装置とを備える構成とした。   The present invention is an assembly-type work platform that is used around an existing steel tower when rebuilding an existing steel tower, and includes a plurality of telescopic towers installed at intervals around the existing steel tower, and its extension and contraction It was set as the structure provided with the supporting member constructed between towers, and the crane apparatus with which the traveling movement is equipped along the supporting member.

この作業架台によれば、伸縮タワーを収縮状態とすることで作業架台全体の高さを低くすることができ、さらに組み立て式であるので、設置現場での組立も小型クレーンを利用して、あるいはワイヤリングによって比較的簡易に組み立てることができる。また、伸縮タワーを伸長(上昇)させることで、基幹系送電線のように高さ数十メートル程度の充電部直下に至るまで伸長可能にすることも容易であり、しかもこれを簡易な構造で実現することができる。   According to this work platform, the height of the entire work platform can be lowered by making the telescopic tower contracted, and since it is an assembly type, assembly on the installation site can also be performed using a small crane, or It can be assembled relatively easily by wiring. In addition, by extending (raising) the telescopic tower, it is easy to make it extendable to just under the live parts of the tens of meters height like a backbone power transmission line, and with a simple structure. Can be realized.

前記作業架台は、平面矩形の四隅に配置される4つの伸縮タワーと、平面矩形の各辺に沿って延びるように配置される4つの支持部材とを備え、各支持部材のうちの少なくとも2つに前記クレーン装置がそれぞれ装備されている構成とすることが望ましい。このように構成すれば、周囲の複数の方向に機材や資材、鉄塔部材等の搬出入や、土砂の搬出を可能にすることができる。   The work platform includes four telescopic towers arranged at four corners of a planar rectangle and four support members arranged to extend along each side of the planar rectangle, and at least two of the support members It is desirable that the crane apparatus is equipped with each. If comprised in this way, carrying in / out of equipment, materials, a steel tower member, etc., and carrying out of earth and sand can be enabled in several surrounding directions.

前記伸縮タワーは、内部中空な第1支柱と、その第1支柱内に収容されて上下移動可能に設けられた第2支柱とを少なくとも備え、各第1支柱及び第2支柱は、複数段積み重ねて連結されるボックス型の複数の単位部材により構成され、第2支柱と第1支柱との間には第2支柱を上下移動させる駆動装置が装備されていることが望ましい。このような構成の伸縮タワーとした場合、いわゆるクライミングクレーンマスト相当の構成となり、作業架台設置場所での作業架台自体の搬入や組立を容易に行うことができる。   The telescopic tower includes at least a first support column that is hollow inside and a second support column that is accommodated in the first support column and is provided so as to be movable up and down. Each of the first support column and the second support column is stacked in multiple stages. It is desirable that a plurality of box-type unit members connected to each other be provided, and a drive device for moving the second column up and down is provided between the second column and the first column. In the case of the telescopic tower having such a configuration, it becomes a configuration equivalent to a so-called climbing crane mast, and the work platform itself can be easily carried in and assembled at the work platform installation location.

前記支持部材は、前記伸縮タワーの第1支柱により支持され、前記第2支柱の上端は前記支持部材及び第1支柱の上端よりも上方へ伸長可能に構成されていることが望ましい。このように構成すれば、支持部材の高さ、即ち、クレーン装置の高さを一定として作業性を良くすることができる他、第2支柱に加わる荷重は基本的に第2支柱の自重となるので、第2支柱を上下動させる動力機構も簡易にすることができる。   Preferably, the support member is supported by the first support column of the telescopic tower, and the upper end of the second support column is configured to extend upward from the upper end of the support member and the first support column. If comprised in this way, the height of a support member, ie, the height of a crane apparatus, can be made constant, workability | operativity can be improved, and the load added to a 2nd support | pillar becomes a self-weight of a 2nd support | pillar fundamentally. Therefore, the power mechanism for moving the second support up and down can be simplified.

本発明によれば、伸縮タワーやクレーン装置を有する作業架台を用いるので、基幹系送電線鉄塔建て替え工事を短い送電停止期間で安全かつ的確に、低コストで実施することができる。   According to the present invention, because the work platform having the telescopic tower and the crane device is used, the backbone transmission line tower rebuilding work can be safely and accurately performed at a low cost in a short power transmission stop period.

以下、本発明の好適な実施の形態について、図面を参照して説明する。図1及び図2は本発明の実施例に係る建て替え対象鉄塔と作業架台を示す平面図及び側面図である。図3は作業架台の伸縮タワーを伸長させた状態を示す正面図である。図4及び図5は伸縮タワーの伸縮原理図である。図6〜図13は作業手順を示す工程図である。   DESCRIPTION OF EXEMPLARY EMBODIMENTS Hereinafter, preferred embodiments of the invention will be described with reference to the drawings. FIG.1 and FIG.2 is the top view and side view which show the rebuilding object steel tower and work stand based on the Example of this invention. FIG. 3 is a front view showing a state in which the telescopic tower of the work platform is extended. 4 and 5 are diagrams illustrating the expansion and contraction principle of the telescopic tower. 6 to 13 are process diagrams showing work procedures.

この実施例では、建て替え対象鉄塔である既設鉄塔1の一側及び他側に延びる一側既設アーム11及び他側既設アーム12を有し、それら一側既設アーム11及び他側既設アーム12に、懸垂碍子装置を介して一側架空線13及び他側架空線14がそれぞれ多段に架
線された鉄塔の建て替え工法に適用した例を示している。
In this embodiment, it has one side existing arm 11 and the other side existing arm 12 extending to one side and the other side of the existing tower 1 which is a rebuilding target tower, and the one side existing arm 11 and the other side existing arm 12 The example applied to the rebuilding method of the steel tower in which the one side overhead wire 13 and the other side overhead wire 14 are respectively wired in multiple stages via the suspension insulator device is shown.

なお、ここでは、基幹系送電線が架線された既設鉄塔1の建て替えに際し、既設鉄塔1の周囲を囲む形態で新設鉄塔A(図3参照)を建築する建て替え工法例として説明する。その際、通電(充電)されている架空線(送電線)を白丸で示し、断電(停止)されている架空線を黒丸で示す。   Here, a description will be given of an example of a rebuilding method in which the new steel tower A (see FIG. 3) is built in a form surrounding the existing steel tower 1 when the existing steel tower 1 on which the backbone transmission line is installed is rebuilt. At that time, an overhead line (power transmission line) that is energized (charged) is indicated by a white circle, and an overhead line that is disconnected (stopped) is indicated by a black circle.

実施例に係る鉄塔建て替え工法は、既設鉄塔1の建て替えに際し、その既設鉄塔1の周囲に設置する組み立て式の作業架台Kを利用して新設鉄塔Aを施工する工法であって、以下の各工程を実施する。   The steel tower rebuilding method according to the embodiment is a method of constructing the new steel tower A using the assembly-type work platform K installed around the existing steel tower 1 when rebuilding the existing steel tower 1. To implement.

まず、既設鉄塔1の周囲に間隔をおいて複数の伸縮タワー2を立設し、その伸縮タワー2間に支持部材3を架設し、その支持部材3に添って走行移動可能なクレーン装置4を装備して作業架台Kを設置する(第1工程)。   First, a plurality of telescopic towers 2 are erected at intervals around the existing tower 1, a support member 3 is installed between the telescopic towers 2, and a crane apparatus 4 that can travel and move along the support member 3 is provided. Equip and install work platform K (first step).

この第1工程で設置する作業架台Kは、平面矩形の四隅に配置される4つの伸縮タワー2と、平面矩形の各辺に沿って延びるように配置される4つの梁型の支持部材3とを備えている。4つの支持部材3のうちの互いに並行する2つの支持部材3,3は、他の互いに並行する2つの支持部材よりも長く形成されていて、その長い方の2つの支持部材3、3にクレーン装置4、4がそれぞれ装備されている。   The work platform K installed in the first step includes four telescopic towers 2 arranged at the four corners of the plane rectangle, and four beam-type support members 3 arranged to extend along each side of the plane rectangle. It has. Two of the four support members 3 that are parallel to each other are formed longer than the other two support members that are parallel to each other, and the longer two support members 3 and 3 are connected to the crane. Devices 4 and 4 are equipped respectively.

勿論、短い方の支持部材3、3にもクレーン装置4を装備して合計4基備える構成とすることもできる。各支持部材3には、例えばH型鋼等が用いられている。したがって、クレーン装置4は実施例ではテルハ型クレーンとして構成されている。なお、伸縮タワー2を立設する前に、必要に応じて伸縮タワー設置用の基礎2aを施工しておく。伸縮タワー2は基礎2aに対してボルト止め等により固定される。   Of course, the shorter support members 3 and 3 may be equipped with the crane device 4 to have a total of four units. For example, H-shaped steel or the like is used for each support member 3. Therefore, the crane apparatus 4 is configured as a Telha crane in the embodiment. In addition, before installing the expansion tower 2, the foundation 2a for expansion tower installation is constructed as needed. The telescopic tower 2 is fixed to the foundation 2a by bolting or the like.

各伸縮タワー2は、外側に配置される内部中空な第1支柱21と、その第1支柱21内に収容されて上下移動可能に設けられた第2支柱22と、第2支柱22の中に収容されて上下移動可能に設けられた第3支柱23とを備えている。(図3参照)即ち、各伸縮タワー2は3段構造となっている。これら第1支柱21、第2支柱22及び第3支柱23は、複数段積み重ねて連結されるボックス型の複数の単位部材21a、22a、23aによりそれぞれ構成されている。各単位部材には、いわゆるクライミングクレーンマストの単位部材と同種のものが採用されている。各単位部材は軽量化に配慮してアルミ製としている。勿論、他の金属で構成することもできる。   Each telescopic tower 2 includes an inner hollow first support column 21 disposed on the outside, a second support column 22 accommodated in the first support column 21 so as to be movable up and down, and a second support column 22. And a third support column 23 which is accommodated and provided so as to be movable up and down. That is, each telescopic tower 2 has a three-stage structure (see FIG. 3). The first support column 21, the second support column 22, and the third support column 23 are respectively configured by a plurality of box-type unit members 21a, 22a, and 23a that are stacked and connected in a plurality of stages. For each unit member, the same type as the unit member of a so-called climbing crane mast is adopted. Each unit member is made of aluminum in consideration of weight reduction. Of course, it can also be comprised with another metal.

そして、第1支柱21と第2支柱22との間、及び第2支柱22と第3支柱23との間には、第2支柱22及び第3支柱23を上下移動させるための駆動機構が装備されている。この駆動機構は、図4及び図5に示すように、複数のテークル(滑車)24、テークル24に巻回されたワイヤー25、ワイヤー25の巻き取り装置26を備え、巻き取り装置26によるワイヤー25の巻き取り操作あるいは送り出し操作を行うことで、第2支柱22及び第3支柱23を上方へ向けて伸長あるいは下方へ向けて収縮させる構成としている。   A drive mechanism is provided between the first column 21 and the second column 22 and between the second column 22 and the third column 23 to move the second column 22 and the third column 23 up and down. Has been. As shown in FIGS. 4 and 5, the drive mechanism includes a plurality of takers (pulleys) 24, a wire 25 wound around the takel 24, and a take-up device 26 for the wire 25. The second column 22 and the third column 23 are extended upward or contracted downward by performing a winding operation or a feeding operation.

各支持部材3は、図示のように各伸縮タワー2の第1支柱21により支持され、第2支柱22及び第3支柱23の上端は支持部材2及び第1支柱21の上端よりも上方へ伸長できるように構成されている。このように構成したのは、支持部材3の高さ、即ち、クレーン装置4の高さを一定として作業性を良くすると共に、第2支柱22に加わる荷重を基本的に第2支柱22の自重として、第2支柱22を上下動させる動力機構も簡易にするためである。従って、巻き取り装置26の動力源には電動モータや油圧モータ等を利用可能で
あるが、ここでは手動ハンドル操作式としての例を示している。
Each support member 3 is supported by the first support column 21 of each telescopic tower 2 as shown, and the upper ends of the second support column 22 and the third support column 23 extend higher than the upper ends of the support member 2 and the first support column 21. It is configured to be able to. This configuration improves the workability by keeping the height of the support member 3, that is, the height of the crane device 4, and basically applies the load applied to the second support 22 to the own weight of the second support 22. In order to simplify the power mechanism that moves the second support column 22 up and down. Therefore, although an electric motor, a hydraulic motor, or the like can be used as a power source of the winding device 26, an example of a manual handle operation type is shown here.

このように構成される作業架台Kの伸縮タワー2の設置作業としては、設置現場に搬入した小型クレーンを用いて行うこともできる。しかし、小型クレーンの搬入が困難な場合には、図6に示すように、既設鉄塔1の脚部付近に滑車27を取り付け、ワイヤー28の先端を伸縮タワー2の上端に固定し、ワイヤー28の基端側を手動ウインチあるいは電動ウインチなどの巻き取り機29で巻き取る作業によって伸縮タワー2を立ち上げるようにしても良い。   The installation work of the telescopic tower 2 of the work platform K configured as described above can be performed using a small crane carried into the installation site. However, when it is difficult to carry in a small crane, as shown in FIG. 6, a pulley 27 is attached near the leg of the existing tower 1, the tip of the wire 28 is fixed to the upper end of the telescopic tower 2, and the wire 28 The telescopic tower 2 may be raised by the work of winding the base end side by a winder 29 such as a manual winch or an electric winch.

このようにして作業架台Kの設置を終えたら、次いで、図7に示すように、クレーン装置4を有する作業架台Kを十分に活用して新設鉄塔A用の基礎5を施工する(第2工程)。この第2工程では、新設鉄塔A用の基礎5を施工するために必要な、杭打ち作業、掘削作業、コンクリート打設作業等を順次行う。その際、各作業においては2つのクレーン装置4、4を用いて行うことで作業効率を高める。   When the installation of the work platform K is completed in this way, then, as shown in FIG. 7, the work platform K having the crane device 4 is fully utilized to construct the foundation 5 for the new tower A (second process). ). In this second step, pile driving work, excavation work, concrete placing work, and the like necessary for constructing the foundation 5 for the new tower A are sequentially performed. In that case, in each operation | work, work efficiency is improved by performing using the two crane apparatuses 4 and 4. FIG.

例えば、杭打ち作業においては、図14(a)に示すように、第1のクレーン装置4で杭打ち機材51の吊り込み作業を行い、第2のクレーン装置4で鉄筋篭52の建て込み作業を行うことで、異なる作業を併行して、あるいは同種の作業を同時進行で行う。そうすることで、従来必要であった杭打ち工事での補助クレーンを不要にできることにより、これまで、狭隘地では機材配置の関係から1本ずつの杭施工であったが、複数杭の併行作業が可能となる。   For example, in the pile driving work, as shown in FIG. 14A, the first crane device 4 hangs the pile driving equipment 51, and the second crane device 4 lays the reinforcing bar 52. To perform different tasks concurrently or perform the same type of work simultaneously. By doing so, it was possible to eliminate the need for an auxiliary crane for pile driving work, which was necessary in the past, so far, in narrow spaces, one pile was constructed due to the arrangement of equipment. Is possible.

また、掘削作業においては、図14(b)に示すように、掘削土53の搬出をクレーン装置4を用いて運搬車54へ搬送することができる。さらに、コンクリート打設作業においては、図14(c)に示すように、コンクリートポンプ車55のブームを使用せず、クレーン装置4、4により配管56を吊って振り分けることで、地上に据え置く必要が無く、敷地を有効に活用できる。   In excavation work, the excavated soil 53 can be carried out to the transport vehicle 54 using the crane device 4 as shown in FIG. Furthermore, in the concrete placing work, as shown in FIG. 14 (c), it is necessary to suspend the pipe 56 by the crane devices 4 and 4 and distribute it without using the boom of the concrete pump truck 55. The site can be used effectively.

このようにして基礎工事を終えたら、次いで、図8に示すように、各伸縮タワー2を伸長させつつ、新設鉄塔A用の基礎5から既設鉄塔1の充電部1b近くに至る部分の新設鉄塔下部領域を組み立てる(第3工程)。なお、各伸縮タワー2のクライムアップ操作(伸長させる操作)では、巻き取り装置26を人力により操作することで行う。   When the foundation work is completed in this way, then, as shown in FIG. 8, the part of the new tower is extended from the foundation 5 for the new tower A to the vicinity of the charging part 1 b of the existing tower 1 while extending each telescopic tower 2. Assemble the lower region (third step). In addition, the climb-up operation (extension operation) of each telescopic tower 2 is performed by operating the winding device 26 manually.

新設鉄塔Aの下部領域を組み立てる工程では、図15(a)に示すように、クレーン装置4を利用して鉄塔組立に必要な鉄塔部材57の搬入作業、及び同図(b)に示す地組作業を行う。この種の作業では、クレーン装置4は水平配置となる支持部材3に添って走行移動できるので、例えば狭隘地において、搬入出口58から遠い位置への鉄塔部材57の搬入も容易に可能となる。   In the process of assembling the lower area of the new tower A, as shown in FIG. 15A, the crane apparatus 4 is used to carry in the steel tower 57 necessary for the tower assembly, and the ground structure shown in FIG. Do work. In this type of work, the crane device 4 can travel along the horizontal support member 3, so that the steel tower member 57 can be easily carried into a position far from the loading / unloading port 58, for example, in a narrow area.

この新設鉄塔Aの下部領域を組み立てる工程では、図9及び図10に示すように、伸縮タワー2を伸長し、既設鉄塔1の充電部1bに対する隔離ネット6を伸縮タワー2に設置して行う。この隔離ネット6は充電部1b付近に存在すればよいので、伸縮タワーの第3支柱23に取り付けてからその第3支柱23を上昇させる。   In the step of assembling the lower region of the new steel tower A, as shown in FIGS. 9 and 10, the telescopic tower 2 is extended, and the isolation net 6 for the charging part 1 b of the existing steel tower 1 is installed in the telescopic tower 2. Since this isolation net 6 only needs to exist in the vicinity of the charging unit 1b, the third support 23 is raised after being attached to the third support 23 of the telescopic tower.

このようにすることで、充電部1b付近までの鉄塔の組立作業を可能にすることができる。また、伸縮タワー2は、図16(a)、(c)に示すように、例えば昼間の作業時のみ上昇させ、夜間の非作業時は同図(b)に示すように収縮させることで安全性並びに安定性を図ることができる。   By doing in this way, the assembly work of the steel tower to the charging part 1b vicinity can be enabled. Further, as shown in FIGS. 16 (a) and 16 (c), the telescopic tower 2 can be safely raised by, for example, only during daytime work and contracted as shown in FIG. 16 (b) when not working at night. And stability can be achieved.

新設鉄塔下部領域の組立作業において、支持部材3よりも上方の鉄塔部材57を組み立
てる場合には、図9〜図11に示すように、伸縮タワー2を3段まで伸長させた状態で、第3支柱23、23間に上端支持部材31を架設し、その上端支持部材31に上部クレーン装置41を装備した状態で行う。その際の作業は、隔離ネット6の内側で行うことで、作業の安全性を確保することができる。なお、上部クレーン装置41のウインチ43を地上に配置することもできる。
When assembling the tower member 57 above the support member 3 in the assembly work of the lower area of the new tower, as shown in FIGS. 9 to 11, the telescopic tower 2 is extended to three stages, An upper end support member 31 is installed between the columns 23 and 23 and the upper end support member 31 is equipped with an upper crane device 41. The work at that time is performed inside the isolation net 6 so that the safety of the work can be ensured. In addition, the winch 43 of the upper crane apparatus 41 can also be arrange | positioned on the ground.

このようにして新設鉄塔下部領域の組立を終えたら、次いで、図12に示すように、各伸縮タワー2を収縮させ、作業架台Kを撤去する(第4工程)。   When the assembly of the lower area of the new tower is completed in this way, each telescopic tower 2 is then contracted and the work platform K is removed as shown in FIG. 12 (fourth step).

次いで、図13に示すように、既設鉄塔1の充電部1bを区間分断停止状態(断電状態)とした上で、新設鉄塔下部領域に続く上部領域の新設鉄塔組立作業及び既設鉄塔の解体作業を行う。このように新設鉄塔Aの下部領域を組み立ててから上部領域に移行することで、送電停止日数(区間充電停止日数)を大幅に少なくすることが可能になる。なお上部領域の新設鉄塔組立作業及び既設鉄塔の解体作業は、同図に示すように、通常のクレーンやクライミングクレーン7等を用いた既存の工法採用して行うことができる。   Next, as shown in FIG. 13, the charging unit 1 b of the existing tower 1 is set to the section disconnection stop state (disconnection state), and then the new tower assembly work and the existing tower dismantling work in the upper area following the new tower lower area. I do. Thus, by assembling the lower region of the new tower A and then moving to the upper region, it is possible to significantly reduce the number of days of power transmission stoppage (number of days of section charge stoppage). In addition, as shown in the same figure, the new tower assembly work of the upper region and the dismantling work of the existing tower can be performed by using an existing construction method using a normal crane, a climbing crane 7 or the like.

この実施例によれば、伸縮タワー2を収縮状態とすることで作業架台K全体の高さを低くすることができ、さらに組み立て式であるので、設置現場での組立も小型クレーン等を利用して、あるいはワイヤリングによって比較的簡易に組み立てることができる。また、伸縮タワー2を伸長(上昇)させることで、基幹系送電線のように高さ30メートル程度の充電部1b直下に至るまで伸長可能にすることも容易であり、しかもこれを簡易な構造で実現することができる。   According to this embodiment, the height of the work platform K can be lowered by bringing the telescopic tower 2 into a contracted state, and since it is an assembly type, a small crane or the like is used for assembly at the installation site. Or can be assembled relatively easily by wiring. In addition, by extending (raising) the telescopic tower 2, it is easy to make it extendable to just below the charging part 1b having a height of about 30 meters like a main transmission line, and this has a simple structure. Can be realized.

作業架台Kの高さ以上は作業空間とならず、確実に充電部1bとの離隔距離を確保することができる。また、狭隘地において、搬出入口58から遠い位置での掘削で発生した掘削土53を効率的に搬出することができる。また、鉄塔の周囲にて、鉄塔部材57の地組が可能となる。   A work space above the height of the work platform K does not become a work space, and a separation distance from the charging unit 1b can be reliably ensured. Further, the excavated soil 53 generated by excavation at a position far from the carry-in / out entrance 58 can be efficiently carried out in a narrow area. In addition, the steel tower member 57 can be ground around the steel tower.

本発明の実施例に係る鉄塔建て替え作業架台を示す平面図。The top view which shows the steel tower rebuilding work platform which concerns on the Example of this invention. 本発明の実施例に係る鉄塔建て替え工法の作業架台を示す側面図。The side view which shows the work platform of the steel tower rebuilding method which concerns on the Example of this invention. 本発明の実施例に係る鉄塔建て替え作業架台を示す正面図。The front view which shows the steel tower rebuilding work platform which concerns on the Example of this invention. 本発明の実施例に係る鉄塔建て替え作業架台の駆動機構の原理図。The principle figure of the drive mechanism of the steel tower rebuilding work stand which concerns on the Example of this invention. 本発明の実施例に係る鉄塔建て替え作業架台の駆動機構の原理図。The principle figure of the drive mechanism of the steel tower rebuilding work stand which concerns on the Example of this invention. 本発明の実施例に係る鉄塔建て替え工法を示す工程図。The process figure which shows the steel tower rebuilding method which concerns on the Example of this invention. 本発明の実施例に係る鉄塔建て替え工法を示す工程図。The process figure which shows the steel tower rebuilding method which concerns on the Example of this invention. 本発明の実施例に係る鉄塔建て替え工法を示す工程図。The process figure which shows the steel tower rebuilding method which concerns on the Example of this invention. 本発明の実施例に係る鉄塔建て替え工法を示す工程図。The process figure which shows the steel tower rebuilding method which concerns on the Example of this invention. 本発明の実施例に係る鉄塔建て替え工法を示す工程図。The process figure which shows the steel tower rebuilding method which concerns on the Example of this invention. 本発明の実施例に係る鉄塔建て替え工法を示す工程図。The process figure which shows the steel tower rebuilding method which concerns on the Example of this invention. 本発明の実施例に係る鉄塔建て替え工法を示す工程図。The process figure which shows the steel tower rebuilding method which concerns on the Example of this invention. 本発明の実施例に係る鉄塔建て替え工法を示す工程図。The process figure which shows the steel tower rebuilding method which concerns on the Example of this invention. 本発明の実施例に係る鉄塔建て替え工法の基礎工事を示す工程図。The process figure which shows the foundation construction of the steel tower rebuilding method which concerns on the Example of this invention. 本発明の実施例に係る鉄塔建て替え工法の鉄塔組立工事例を示す工程図。The process drawing which shows the steel tower assembly example of the steel tower rebuilding method concerning the Example of this invention. 本発明の実施例に係る鉄塔建て替え工法例を示す説明図。Explanatory drawing which shows the example of a steel tower rebuilding method concerning the Example of this invention.

符号の説明Explanation of symbols

1 既設鉄塔
1b 充電部
13、14 架空線
2 伸縮タワー
21 第1支柱
22 第2支柱
23 第3支柱
21a、22a、23a 単位部材
3 支持部材
4 クレーン装置
5 新設基礎
6 隔離ネット
K 作業架台
A 新設鉄塔
DESCRIPTION OF SYMBOLS 1 Existing steel tower 1b Charging part 13,14 Overhead wire 2 Telescopic tower 21 First support column 22 Second support column 23 Third support column 21a, 22a, 23a Unit member 3 Support member 4 Crane device 5 New foundation 6 Isolation net K Work platform A New installation Steel tower

Claims (10)

既設鉄塔の建て替えに際し、その既設鉄塔の周囲に設置する組み立て式の作業架台を利用して新設鉄塔を施工する鉄塔建て替え工法であって、
既設鉄塔の周囲に間隔をおいて複数の伸縮タワーを立設し、その伸縮タワー間に支持部材を架設し、その支持部材に添って走行移動可能なクレーン装置を装備して作業架台を設置する第1工程と、
前記作業架台の設置後に、前記クレーン装置を利用して新設鉄塔用の基礎を施工する第2工程と、
前記伸縮タワーを伸長させつつ、前記新設鉄塔用の基礎から既設鉄塔の充電部近くに至る部分の新設鉄塔下部領域を組み立てる第3工程と、
を行うことを特徴とする鉄塔建て替え工法。
When rebuilding an existing steel tower, it is a steel tower rebuilding method in which a new steel tower is constructed using an assembly-type work platform installed around the existing steel tower.
A plurality of telescopic towers are installed around the existing steel tower at intervals, a support member is installed between the telescopic towers, and a work platform is installed with a crane device that can travel along the support member. The first step;
A second step of constructing a foundation for a new steel tower using the crane device after the installation of the work platform;
A third step of assembling the lower part of the new tower from the foundation for the new tower to the vicinity of the charging part of the existing tower while extending the telescopic tower;
The steel tower rebuilding method characterized by performing.
前記新設鉄塔下部領域の組立後に前記作業架台を撤去する工程と、その作業架台撤去後に、前記既設鉄塔の充電部を区間充電停止状態とし、新設鉄塔下部領域に続く上部領域の新設鉄塔組立工程及び既設鉄塔の解体工程を行うことを特徴とする、請求項1に記載の鉄塔建て替え工法。   A step of removing the work platform after assembly of the lower area of the new tower, and after removing the work platform, the charging section of the existing tower is in a section charge stop state, and a new tower assembly process of the upper area following the new tower lower area; The steel tower rebuilding method according to claim 1, wherein a dismantling process of the existing steel tower is performed. 前記作業架台は、平面矩形の四隅に配置される4つの伸縮タワーと、平面矩形の各辺に沿って延びるように配置される4つの支持部材とを備え、各支持部材のうちの少なくとも2つに前記クレーン装置がそれぞれ装備されている、請求項1又は2に記載の鉄塔建て替え工法。   The work platform includes four telescopic towers arranged at four corners of a planar rectangle and four support members arranged to extend along each side of the planar rectangle, and at least two of the support members The steel tower rebuilding method according to claim 1 or 2, wherein each of the crane devices is equipped. 前記新設鉄塔用の基礎を施工する第2工程は、杭打ち作業、掘削作業、コンクリート打設作業を含み、それら各作業のうち少なくとも一つの作業において前記クレーン装置を複数用いて行うことを特徴とする、請求項1〜3の何れかに記載の鉄塔建て替え工法。   The second step of constructing the foundation for the new steel tower includes pile driving work, excavation work, concrete placing work, and at least one of these works is performed using a plurality of the crane devices. The steel tower rebuilding method according to any one of claims 1 to 3. 前記新設鉄塔下部領域を組み立てる第3工程では、前記クレーン装置を利用して鉄塔組立に必要な部材搬入作業及び地組作業を行うことを特徴とする、請求項1〜4の何れかに記載の鉄塔建て替え工法。   In the 3rd process of assembling the said new steel tower lower area | region, the member carrying-in operation | work required for steel tower assembly and ground work are performed using the said crane apparatus, In any one of Claims 1-4 characterized by the above-mentioned. Steel tower rebuilding method. 前記新設鉄塔下部領域を組み立てる第3工程では、前記伸縮タワーを伸長し、既設鉄塔の充電部に対する隔離ネットを前記伸縮タワーに設置して行うことを特徴とする請求項1〜5の何れかに記載の鉄塔建て替え工法。   The third step of assembling the lower area of the new steel tower is performed by extending the telescopic tower and installing an isolation net for the charging part of the existing steel tower in the telescopic tower. The steel tower rebuilding method described. 既設鉄塔の建て替えに際し、その既設鉄塔の周囲に設置して用いる組み立て式の作業架台であって、
既設鉄塔の周囲に間隔をおいて立設される複数の伸縮タワーと、
その伸縮タワー間に架設される支持部材と、
その支持部材に添って走行移動可能に装備されるクレーン装置と、
を備えている、鉄塔建て替え作業架台。
When rebuilding an existing steel tower, it is an assembly-type work platform that is used around the existing steel tower,
A plurality of telescopic towers standing around the existing steel tower at intervals,
A support member constructed between the telescopic towers;
A crane device that is movably mounted along the support member;
It is equipped with a steel tower rebuilding work platform.
前記作業架台は、平面矩形の四隅に配置される4つの伸縮タワーと、平面矩形の各辺に沿って延びるように配置される4つの支持部材とを備え、各支持部材のうちの少なくとも2つに前記クレーン装置がそれぞれ装備されている、請求項7に記載の鉄塔建て替え作業架台。   The work platform includes four telescopic towers arranged at four corners of a planar rectangle and four support members arranged to extend along each side of the planar rectangle, and at least two of the support members The tower rebuilding work platform according to claim 7, wherein the crane device is equipped with each of the crane towers. 前記伸縮タワーは、内部中空な第1支柱と、その第1支柱内に収容されて上下移動可能に設けられた第2支柱とを少なくとも備え、各第1支柱及び第2支柱は、複数段積み重ねて連結されるボックス型の複数の単位部材により構成され、第1支柱と第2支柱との間に
は、第2支柱を上下移動させる駆動機構が装備されている請求項7又は8に記載の鉄塔建て替え作業架台。
The telescopic tower includes at least a first support column that is hollow inside and a second support column that is accommodated in the first support column and is provided so as to be movable up and down. Each of the first support column and the second support column is stacked in multiple stages. The drive mechanism which moves the 2nd support | pillar up and down is equipped between the 1st support | pillar and the 2nd support | pillar. Steel tower rebuilding work platform.
前記支持部材は、前記伸縮タワーの第1支柱により支持され、前記第2支柱の上端は前記支持部材及び第1支柱の上端よりも上方へ伸長可能である、請求項9に記載の鉄塔建て替え作業架台。   The steel tower rebuilding work according to claim 9, wherein the support member is supported by a first support column of the telescopic tower, and an upper end of the second support column can extend upward from an upper end of the support member and the first support column. Mount.
JP2006021788A 2006-01-31 2006-01-31 Steel tower rebuilding method and work bench therefor Pending JP2007204925A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006021788A JP2007204925A (en) 2006-01-31 2006-01-31 Steel tower rebuilding method and work bench therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006021788A JP2007204925A (en) 2006-01-31 2006-01-31 Steel tower rebuilding method and work bench therefor

Publications (1)

Publication Number Publication Date
JP2007204925A true JP2007204925A (en) 2007-08-16

Family

ID=38484627

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006021788A Pending JP2007204925A (en) 2006-01-31 2006-01-31 Steel tower rebuilding method and work bench therefor

Country Status (1)

Country Link
JP (1) JP2007204925A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101956478A (en) * 2010-09-20 2011-01-26 中国矿业大学(北京) Enhancement-able mining deformation resistance device of high-voltage line tower with externally expanded base
CN108837999A (en) * 2018-08-28 2018-11-20 国网山东省电力公司电力科学研究院 A kind of electric power pylon tower body maintenance device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101956478A (en) * 2010-09-20 2011-01-26 中国矿业大学(北京) Enhancement-able mining deformation resistance device of high-voltage line tower with externally expanded base
CN108837999A (en) * 2018-08-28 2018-11-20 国网山东省电力公司电力科学研究院 A kind of electric power pylon tower body maintenance device
CN108837999B (en) * 2018-08-28 2023-10-10 国网山东省电力公司电力科学研究院 Power transmission tower body maintenance device

Similar Documents

Publication Publication Date Title
US20150308140A1 (en) Modular monopole tower foundation
US8584429B2 (en) Tower erection system and method
KR20110112228A (en) Method of building a hybrid tower for a wind generator
CN215908537U (en) Water supply and drainage pipeline optimizes laying device
CN110185188A (en) Large-span reticulated shell installation method
JP2013234509A (en) Shaft excavation and soil-gathering method and shaft excavation and soil-gathering apparatus
JP7325838B2 (en) Movable modules for lifting telescopic towers and methods for lifting telescopic towers
JP6416474B2 (en) Structure construction method and support device
CN108396749B (en) Installation system and installation method of steel support in foundation pit
JP5921263B2 (en) Reinforcing bar erection device and method
JP2006299650A (en) Launching method
JP2007204925A (en) Steel tower rebuilding method and work bench therefor
JP2007162639A (en) Windmill assembling apparatus and windmill assembling method
JP6059176B2 (en) Mobile lifting scaffold for assembling temporary elevated jetty
KR101317384B1 (en) The hoisting and installing method and apparatus of wind turbines by using the self tower
CN216142044U (en) Variable-rigidity high-adaptability section steel support
JP2017197960A (en) Construction method of suspended steel frame for suspended ceiling
JP4310583B2 (en) Steel tower lifting device
RU2768534C1 (en) Method of mounting a permanent quick-erect lightweight support for emergency recovery works on power transmission lines
CN110127527B (en) Bridge crane hoisting method in limited space
JP4352219B2 (en) Crane equipment
JP2009007129A (en) Climbing crane
JP5941696B2 (en) Storage tank dismantling method and construction method, and dismantling or construction equipment
US20240175277A1 (en) Load dispersion-type indoor lifting apparatus for prefabricated steel structure and method of installing prefabricated steel structure by using same
JP2020125619A (en) Conveyance system and installation method