JP2006299650A - Launching method - Google Patents

Launching method Download PDF

Info

Publication number
JP2006299650A
JP2006299650A JP2005123168A JP2005123168A JP2006299650A JP 2006299650 A JP2006299650 A JP 2006299650A JP 2005123168 A JP2005123168 A JP 2005123168A JP 2005123168 A JP2005123168 A JP 2005123168A JP 2006299650 A JP2006299650 A JP 2006299650A
Authority
JP
Japan
Prior art keywords
girder
stage
section
straddling
delivery method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP2005123168A
Other languages
Japanese (ja)
Inventor
Shinsuke Kondo
伸介 近藤
Atsushi Isoda
厚志 磯田
Shuji Sato
修二 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MM Bridge Co Ltd
Original Assignee
Mitsubishi Heavy Industries Bridge and Steel Structures Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Heavy Industries Bridge and Steel Structures Engineering Co Ltd filed Critical Mitsubishi Heavy Industries Bridge and Steel Structures Engineering Co Ltd
Priority to JP2005123168A priority Critical patent/JP2006299650A/en
Publication of JP2006299650A publication Critical patent/JP2006299650A/en
Withdrawn legal-status Critical Current

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a launching method without requiring an installation girder. <P>SOLUTION: A method crosses a girder 11 supported by a plurality of piers 12 in grade separation above a straddling object 10. In the sending out method, among the piers 12 for supporting the girder 11, the mutual optional piers 12 except for the mutual piers 12 for sandwiching the straddling object 10 are set as a first section; the mutual piers 12 adjacent to the opposite side of the straddling object 10 side of the first section is set as a second section; a first girder is assembled in the first section; a second girder is assembled in the second section; the first girder is lifted by a lifting means, and is placed on the pier 12 by sending out to the straddling object 10 side; the second girder is lifted by the lifting means, and is placed on the pier 12 by sending out to the straddling object 10 side, and is formed as the launching girder 11 by contacting and joining an end part of the second girder and an end of the first girder, and is sent out to the straddling object 10 side by a launching means while supporting a load by a support means. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本発明は、橋桁等の送り出し方法に関する。   The present invention relates to a feeding method for a bridge girder or the like.

従来、鉄道、道路、河川及び峡谷等の跨対象物上に桁を架設する方法として、送り出し方法が知られている。送り出し方法は、図18に示すように、跨対象物10の際の橋脚12を始めとする橋脚12間にベント51を設置し、その上に架設桁52を設け、桁11及び手延機20を組み立てる(以下、地組立)。組み立て後、台車53により桁11の送り出しを行う。この送り出し方法の一例が下記特許文献1及び特許文献2に開示されている。   Conventionally, a feeding method is known as a method of laying girders on straddling objects such as railways, roads, rivers, and canyons. As shown in FIG. 18, the feeding method is such that a vent 51 is installed between the piers 12 including the pier 12 in the case of the straddling object 10, and a construction girder 52 is provided on the vent 51, and the girder 11 and the spreader 20. Assemble (hereinafter referred to as ground assembly). After the assembly, the beam 11 is sent out by the carriage 53. An example of this delivery method is disclosed in Patent Document 1 and Patent Document 2 below.

特開平9−31915号公報JP-A-9-31915 特開平8−60620号公報JP-A-8-60620

しかしながら、上記特許文献1及び特許文献2に開示されている送り出し方法では、架設桁52は桁11及び手延機20も含めた全長に渡り設置する必要がある。これらは跨対象物10の幅が広い場合、また、橋脚12の高さが高い場合に、ベント51及び架設桁52の設備重量が大きくなり、それにともない工事期間が長期に渡り、工事費用が増大してしまう。   However, in the feeding method disclosed in Patent Document 1 and Patent Document 2, the installation girder 52 needs to be installed over the entire length including the girder 11 and the hand extender 20. In these cases, when the spanning object 10 is wide or the height of the pier 12 is high, the equipment weight of the vent 51 and the erection girder 52 is increased, and accordingly, the construction period is prolonged and the construction cost is increased. Resulting in.

このことから、本発明は、架設桁を必要としない送り出し方法を提供することを目的とする。   Accordingly, an object of the present invention is to provide a delivery method that does not require a construction beam.

上記の課題を解決する第1の発明(請求項1に対応)に係る送り出し方法は、複数の橋脚で支持する桁を跨対象物の上方に立体交差させる方法であって、前記桁を支持する前記橋脚のうち前記跨対象物を挟む前記橋脚間以外の任意の前記橋脚間を第1区間とし、前記第1区間の前記跨対象物側と反対側に隣接する前記橋脚間を第2区間とし、前記第1区間で第1桁を組み立て、前記第2区間で第2桁を組み立て、前記第1桁を上昇手段により上昇し、前記跨対象物側に送り出して前記橋脚上に載置し、前記第2桁を前記上昇手段により上昇し、前記跨対象物側に送り出して前記橋脚上に載置し、さらに前記第2桁を送り出し、前記第2桁の端部と前記第1桁の端部とを接触させて結合して送り出し桁とし、支持手段により前記送り出し桁の荷重を支持しつつ、送り出し手段により前記送り出し桁を前記跨対象物側に送り出すことを特徴とする。   A sending-out method according to a first invention (corresponding to claim 1) that solves the above-mentioned problem is a method in which a girder supported by a plurality of bridge piers is three-dimensionally crossed above a straddling object, and supports the girder. Among the piers, between the piers other than between the piers sandwiching the straddling object is a first section, and between the piers adjacent to the straddling object side of the first section is a second section. Assembling the first girder in the first section, assembling the second girder in the second section, ascending the first girder by the lifting means, sending it to the straddling object side and placing it on the pier, The second girder is raised by the ascending means, sent to the straddling object side, placed on the pier, and further fed out the second girder, the end of the second girder and the end of the first girder The parts are brought into contact with each other to form a feeding girder, and the supporting girder is loaded by the supporting means. While supporting the, characterized in that sending the object side straddle said feeding digits by delivery means.

上記の課題を解決する第2の発明(請求項2に対応)に係る送り出し方法は、第1の発明に係る送り出し方法において、前記上昇手段として、上下方向に伸張及び収縮可能な大揚程上昇装置と、前記大揚程上昇装置を支持する装置ベントと、前記第1桁及び第2桁を支持する支持ベントを用いることを特徴とする。   A delivery method according to a second invention (corresponding to claim 2) that solves the above-mentioned problems is the delivery method according to the first invention, wherein the lift means is a large lift raising device that can be expanded and contracted vertically as the raising means. And a device vent that supports the large lifting device and a support vent that supports the first and second girders.

上記の課題を解決する第3の発明(請求項3に対応)に係る送り出し方法は、第1の発明又は第2の発明に係る送り出し方法において、前記送り出し手段として、ワイヤと前記ワイヤを牽引するワイヤクランプジャッキを用いることを特徴とする。   A delivery method according to a third invention (corresponding to claim 3) that solves the above-mentioned problem is the delivery method according to the first invention or the second invention, wherein the wire and the wire are pulled as the delivery means. A wire clamp jack is used.

上記の課題を解決する第4の発明(請求項4に対応)に係る送り出し方法は、第1の発明ないし第3の発明のいずれかに係る送り出し方法において、前記支持手段として、前記送り出し桁の端部に設置可能で、伸縮可能な伸縮手延機を用いることを特徴とする。   A delivery method according to a fourth invention (corresponding to claim 4) that solves the above-described problem is the delivery method according to any one of the first to third inventions, wherein the support means includes the delivery girder. It is characterized by using an extendable extender that can be installed at the end.

第1の発明に係る送り出し方法によれば、地上において桁の地組立を行うため、桁の組み立て精度の向上を図ることができる。また、従来の送り出し方法で用いられていた架設桁及びベントを必要としないため、跨対象物の幅が広い場合や橋脚の高さが高い場合であっても設備の省略化及び作業効率の改善を図ることができ、これにより、工事費用を削減することができる。   According to the delivery method according to the first aspect of the present invention, since the girder is assembled on the ground, the assembling accuracy of the girder can be improved. In addition, because the installation girders and vents used in the conventional delivery method are not required, equipment can be omitted and work efficiency can be improved even when the spanning object is wide or the height of the pier is high. As a result, construction costs can be reduced.

第2の発明に係る送り出し方法によれば、上昇手段として、伸張及び収縮が可能な大揚程上昇装置とこの大揚程上昇装置を支持する装置ベントと第1桁及び第2桁を支持する支持ベントを用いることにより、橋梁桁を上昇するためのクレーン車等の重機を必要としないため、作業スペースが狭小な場合や、桁の上空に既に構造物が存在する場所であっても作業を行うことができる。   According to the delivery method according to the second aspect of the present invention, as the lifting means, a large lifting device capable of stretching and contracting, a device vent that supports the large lifting device, and a support vent that supports the first and second girders. Because no heavy machinery such as crane trucks are required to ascend the bridge girder, work can be performed even when the work space is small or where there is already a structure above the girder. Can do.

第3の発明に係る送り出し方法によれば、送り出し手段として、ワイヤとこのワイヤを牽引するワイヤクランプジャッキを用いることにより、結合位置が多少異なってもワイヤが柔軟であるため対応が容易であり、多少の角度が付いてもワイヤをガイドすることにより対応が容易であり、張力によってワイヤ自体が適度に伸縮するため張力管理が容易であり、余分なワイヤは巻き取ることにより処理することが容易である。   According to the delivery method according to the third aspect of the invention, by using a wire and a wire clamp jack that pulls the wire as the delivery means, the wire is flexible even if the coupling position is slightly different. Even if there is a slight angle, it is easy to handle by guiding the wire, and the tension of the wire itself is easily expanded and contracted by the tension, making it easy to manage the tension. is there.

第4の発明に係る送り出し方法によれば、支持手段として、送り出し桁の端部に設置可能で、伸縮可能な伸縮手延機を用いることにより、送り出し桁が片持ちとなることを防ぐことができるため、第1区間及び第2区間の間隔が広く、第1桁及び第2桁の長さが長い場合であっても送り出し桁が自らの重みで崩壊することを防ぐことができる。   According to the delivery method according to the fourth aspect of the invention, it is possible to prevent the delivery girder from being cantilevered by using an extendable telescopic stretcher that can be installed at the end of the delivery girder as the support means. Therefore, even when the interval between the first section and the second section is wide and the lengths of the first and second digits are long, the sending digit can be prevented from collapsing with its own weight.

本発明に係る送り出し方法の実施例について、図1から図16を用いて説明する。図1は実施例1に係る送り出し方法の概要を示す側面図、図2は実施例1に係る送り出し方法の第1段階完了時の側面図、図3は実施例1に係る送り出し方法の第2段階完了時の側面図、図4は実施例1に係る送り出し方法の第3段階完了時の側面図、図5は実施例1に係る送り出し方法の第4段階完了時の側面図、図6は実施例1に係る送り出し方法の第5段階完了時の側面図、図7は実施例1に係る送り出し方法の第6段階完了時の側面図、図8は実施例1に係る送り出し方法の第7段階完了時の側面図、図9は実施例1に係る送り出し方法の第8段階完了時の側面図、図10は実施例1に係る送り出し方法の第9段階完了時の側面図、図11は実施例1に係る送り出し方法の第10段階完了時の側面図、図12は実施例1に係る送り出し方法の第11段階完了時の側面図、図13は実施例1に係る送り出し方法の第12段階完了時の側面図、図14は実施例1に係る送り出し方法の第13段階完了時の側面図、図15は実施例1に係る送り出し方法の第14段階完了時の側面図、図16は実施例1に係る送り出し方法の第15段階完了時の側面図、図17は実施例1に係る送り出し方法の第16段階完了時の側面図である。   An embodiment of a delivery method according to the present invention will be described with reference to FIGS. FIG. 1 is a side view showing an outline of the delivery method according to the first embodiment, FIG. 2 is a side view when the first stage of the delivery method according to the first embodiment is completed, and FIG. 3 is a second view of the delivery method according to the first embodiment. FIG. 4 is a side view when the third stage of the delivery method according to the first embodiment is completed, FIG. 5 is a side view when the fourth stage of the delivery method according to the first embodiment is completed, and FIG. 7 is a side view when the fifth stage of the delivery method according to the first embodiment is completed, FIG. 7 is a side view when the sixth stage of the delivery method according to the first embodiment is completed, and FIG. 8 is a seventh view of the delivery method according to the first embodiment. 9 is a side view when the eighth stage of the delivery method according to the first embodiment is completed, FIG. 10 is a side view when the ninth stage of the delivery method according to the first embodiment is completed, and FIG. FIG. 12 is a side view when the tenth stage of the delivery method according to the first embodiment is completed, and FIG. 12 shows the delivery according to the first embodiment. FIG. 13 is a side view when the twelfth stage of the delivery method according to the first embodiment is completed, and FIG. 14 is a side view when the thirteenth stage of the delivery method according to the first embodiment is completed. 15 is a side view of the delivery method according to the first embodiment at the completion of the fourteenth stage, FIG. 16 is a side view of the delivery method according to the first embodiment at the fifteenth stage, and FIG. 17 is a delivery of the first embodiment. And FIG. 17 is a side view upon completion of the sixteenth stage of the method.

以下、本実施例に係る送り出し方法に用いられる装置の概要について説明する。図1に示すように、高速道路等の跨対象物10の側方の地面27には基礎28の上部に設けた橋脚12がある。この橋脚12は跨対象物10の上方に桁11を立体交差させるためのものである。   Hereinafter, an outline of an apparatus used in the delivery method according to the present embodiment will be described. As shown in FIG. 1, a pier 12 provided on an upper portion of a foundation 28 is provided on a ground 27 on a side of a straddling object 10 such as an expressway. The bridge pier 12 is used for three-dimensionally crossing the girder 11 above the straddling object 10.

この橋脚12の上部に、桁11を跨対象物10の方向に送り出すために必要な送り装置13を設置する。この送り装置13は上下方向での伸張及び収縮が可能であり、また、駆動力を持たせることにより送り装置13自体の力により送り出しを行うことも可能である。   A feeding device 13 necessary for feeding the girder 11 in the direction of the straddling object 10 is installed on the upper part of the pier 12. The feeding device 13 can be extended and contracted in the vertical direction, and can be fed by the force of the feeding device 13 itself by providing a driving force.

桁11の下部には、桁11を上昇させるための大揚程上昇装置16と、桁11を一時的に支持する支持ベント17を設置する。また、大揚程上昇装置16の上部には、桁11を跨対象物10方向に送り出すための縦送り装置18を設置し、下部には装置ベント19を設置する。   At the lower part of the girder 11, a large lift raising device 16 for raising the girder 11 and a support vent 17 for temporarily supporting the girder 11 are installed. Further, a vertical feeding device 18 for sending the beam 11 in the direction of the object 10 is installed at the upper part of the large lift device 16, and a device vent 19 is installed at the lower part.

桁11を跨対象物10側に送り出す際に桁11が片持ち状態になることを防ぐため、桁11の跨対象物10側の端部に手延機20を設置し、反対側の端部に伸縮手延機21を設置する。手延機20は鋼製の構造物により構成して作製する。伸縮手延機21は複数の鋼製の角柱を入れ子状に構成することにより作製し、この構造により伸縮が可能となっている。   In order to prevent the girder 11 from being in a cantilever state when the girder 11 is sent to the straddling object 10 side, the handbill 20 is installed at the end of the straddle object 10 side of the girder 11 and the end on the opposite side The telescopic hand-roller 21 is installed in the door. The hand roll 20 is made of a steel structure. The telescopic handroller 21 is made by nesting a plurality of steel prisms, and this structure enables expansion and contraction.

本実施例では4本の鋼製の角柱を用いることで4段の伸縮手延機21となっているが、それ以外の段数の伸縮手延機21を用いてもよい。また、伸縮手延機21は連結構22を介して桁11の端部に結合する。このため、連結構22を交換することにより、伸縮手延機21はあらゆる工事現場の桁11に取り付けることができる。   In the present embodiment, the four-stage telescopic handrail 21 is formed by using four steel prisms, but the other number of telescopic handrails 21 may be used. Further, the telescopic handrail 21 is coupled to the end portion of the girder 11 through the connecting structure 22. For this reason, by exchanging the connecting structure 22, the telescopic handrail 21 can be attached to the girders 11 at any construction site.

以下、本実施例に係る送り出し方法の作業手順を各段階毎に説明する。
[第1段階]
各橋脚12の間の地上において架台14(図2参照)を設置した上で、この架台14の上部に各ブロック15毎に分かれている桁11を各橋脚12間内に収まる範囲内の長さだけ地組立する。本実施例では図1にAで示す跨対象物10から2つ目の橋脚12と3つ目の橋脚12の間の区間を第1区間とし、Bで示す3つ目と4つ目の橋脚12の間の区間を第2区間とする。第1段階の作業が完了した状態を図2に示す。
Hereinafter, the work procedure of the delivery method according to the present embodiment will be described for each stage.
[First stage]
A length within a range in which the girder 11 divided for each block 15 is placed in the upper part of the gantry 14 after the gantry 14 (see FIG. 2) is installed on the ground between the piers 12. Just assemble the ground. In this embodiment, the section between the second pier 12 and the third pier 12 from the straddling object 10 shown by A in FIG. 1 is a first section, and the third and fourth piers shown by B are shown. A section between 12 is defined as a second section. FIG. 2 shows a state in which the first stage work has been completed.

[第2段階]
第1段階の作業が完了した後、桁11a(第1桁、図3参照)の下部に、桁11aを上昇させるための大揚程上昇装置16(図3参照)と、支持ベント17(図3参照)を設置する。また、大揚程上昇装置16の上部には、縦送り装置18(図3参照)を設置する。そして、桁11aの下面に支持ベント17の上部及び縦送り装置18の上部をボルト締め等により結合する。第2段階の作業が完了した状態を図3に示す。
[Second stage]
After the work of the first stage is completed, a large lift raising device 16 (see FIG. 3) for raising the girder 11a and a support vent 17 (see FIG. 3) are arranged below the girders 11a (first girder, see FIG. 3). Install). In addition, a vertical feed device 18 (see FIG. 3) is installed on the upper portion of the large lift device 16. Then, the upper portion of the support vent 17 and the upper portion of the vertical feeding device 18 are joined to the lower surface of the beam 11a by bolting or the like. FIG. 3 shows a state where the second stage work is completed.

[第3段階]
第2段階の作業が完了した後、大揚程上昇装置16を伸張し、支持ベント17を桁11aごと持ち上げてそれにより生じた隙間に支持ベント17を継ぎ足す。その後、大揚程上昇装置16を収縮し、桁11aに吊るされた状態になった大揚程上昇装置16の下部に生じた隙間に装置ベント19を継ぎ足し再び大揚程上昇装置16を伸張する。これらの作業を繰り返し行うことで、桁11aを送り装置13a上に載置するのに都合のよい高さまで上昇させる。本実施例では、大揚程上昇装置16、支持ベント17及び装置ベント19が上昇手段である。第3段階の作業が完了した状態を図4に示す。
[Stage 3]
After the work of the second stage is completed, the large lift raising device 16 is extended, the support vent 17 is lifted together with the girders 11a, and the support vent 17 is added to the gap formed thereby. Thereafter, the large lift raising device 16 is contracted, and the device vent 19 is added to the gap formed in the lower part of the large lift raising device 16 that is suspended from the beam 11a, and the large lift raising device 16 is extended again. By repeating these operations, the girder 11a is raised to a height convenient for placing it on the feeder 13a. In the present embodiment, the large lift raising device 16, the support vent 17 and the device vent 19 are raising means. FIG. 4 shows a state where the third stage work is completed.

[第4段階]
第3段階の作業が完了した後、桁11aと支持ベント17との結合を解除した後に、大揚程上昇装置16上部の縦送り装置18と橋脚12a上部の送り装置13aを用いて、桁11aを跨対象物10側に送り出し、桁11aの跨対象物10側の端部を送り装置13a上に載置して支持するようにする。このように、跨対象物10に近い方の桁11aから先に送り出しを行う。第4段階の作業が完了した状態を図5に示す。
[Fourth stage]
After the work of the third stage is completed, after the coupling between the beam 11a and the support vent 17 is released, the beam 11a is moved by using the vertical feed device 18 above the large lifting device 16 and the feed device 13a above the pier 12a. It sends out to the straddling target object 10 side, and it is made to mount and support the edge part by the side of the straddling target object 10a on the feeder 13a. In this way, the feeding is performed first from the digit 11a closer to the straddling object 10. FIG. 5 shows a state where the fourth stage work is completed.

[第5段階]
第4段階の作業が完了した後、桁11aの跨対象物10側の端部を支持している橋脚12aから遠い方にある支持ベント17a(図6参照)の上部を桁11aの下部と結合し、この支持ベント17aを残して大揚程上昇装置16、支持ベント17及び装置ベント19を解体して撤去する。第5段階の作業が完了した状態を図6に示す。
[Fifth stage]
After the work of the fourth stage is completed, the upper part of the support vent 17a (see FIG. 6) far from the bridge pier 12a supporting the end of the crossing object 10 side of the girder 11a is joined to the lower part of the girder 11a. Then, leaving the support vent 17a, the large lift raising device 16, the support vent 17 and the device vent 19 are disassembled and removed. FIG. 6 shows a state where the fifth stage work has been completed.

[第6段階]
第5段階の作業が完了した後、第2段階から第5段階の作業を、第2区間B(図2参照)に対しても実施し、桁11b(図7参照)を送り装置13b上に載置するのに都合のよい高さまで上昇させる。大揚程上昇装置16上部の縦送り装置18と、橋脚12b上部の送り装置13bを用いて、桁11bを跨対象物10方向に送り出す。そして、送り出した桁11bと隣接する桁11aとを接合し、これらをボルト締め等により結合する。第6段階の作業が完了した状態を図7に示す。
[6th stage]
After the fifth stage work is completed, the second to fifth stage work is also performed on the second section B (see FIG. 2), and the girder 11b (see FIG. 7) is placed on the feeder 13b. Raise it to a convenient height for placement. The girder 11b is fed in the direction of the straddling object 10 by using the vertical feeding device 18 above the large lifting device 16 and the feeding device 13b above the pier 12b. And the sent-out girder 11b and the adjacent girder 11a are joined, and these are couple | bonded by bolting etc. FIG. 7 shows a state where the sixth stage work is completed.

[第7段階]
第6段階の作業が完了した後、桁11bの跨対象物10側の端部を支持している橋脚12から遠い方にある支持ベント17bを残して大揚程上昇装置16、支持ベント17及び装置ベント19を解体して撤去する。第7段階の作業が完了した状態を図8に示す。
[Step 7]
After the work of the sixth stage is completed, the large lift raising device 16, the support vent 17 and the device are left leaving the support vent 17b farther from the pier 12 supporting the end of the beam 11b on the straddling object 10 side. The vent 19 is dismantled and removed. FIG. 8 shows a state where the seventh stage work has been completed.

[第8段階]
第7段階の作業が完了した後、桁11(送り出し桁)の跨対象物10側の端部に手延機20(図9参照)をクレーン車23(図9参照)により設置し、跨対象物10と反対側の端部に伸縮手延機21(図9参照)をクレーン車23により設置する。本実施例では伸縮手延機21が支持手段である。また、手延機20及び伸縮手延機21はクレーン車23により設置するが、この場合クレーン車23は桁11の幅よりも内側で作業を行うため、工事区域が狭小な場合であっても作業を行うことができる。第8段階の作業が完了した状態を図9に示す。
[Stage 8]
After the work of the seventh stage is completed, the hand extender 20 (see FIG. 9) is installed by the crane vehicle 23 (see FIG. 9) at the end on the straddling object 10 side of the girder 11 (feeding girder), and the straddling target A telescopic handrail 21 (see FIG. 9) is installed by a crane car 23 at the end opposite to the object 10. In the present embodiment, the telescopic handrail 21 is a support means. In addition, the crane 20 and the extendable crane 21 are installed by a crane car 23. In this case, since the crane car 23 works on the inner side of the width of the girder 11, the construction area is narrow. Work can be done. FIG. 9 shows a state where the eighth stage work has been completed.

[第9段階]
第8段階の作業が完了した後、伸縮手延機21の跨対象物10側の端部(以下、後端部21a)にワイヤ24a(図10参照)を結合し、このワイヤ24aを伸縮手延機21よりも跨対象物10側にある橋脚12bに設置したワイヤクランプジャッキ25a(図10参照)で牽引することにより、桁11を跨対象物10側に送り出す。本実施例では、ワイヤ24a及びワイヤクランプジャッキ25aが送り出し手段である。
[9th stage]
After the work of the eighth stage is completed, a wire 24a (see FIG. 10) is coupled to an end portion (hereinafter, rear end portion 21a) on the straddling target object 10 side of the telescopic handbill 21, and the wire 24a is connected to the telescopic hand. By pulling with a wire clamp jack 25a (see FIG. 10) installed on the bridge pier 12b on the straddling object 10 side relative to the stretcher 21, the girder 11 is sent out to the straddling object 10 side. In this embodiment, the wire 24a and the wire clamp jack 25a are the delivery means.

伸縮手延機21の跨対象物10側とは反対側の端部(以下、先端部21b)は橋脚12cの上部で、連結材26c(図10参照)にボルト締め等により結合する。結合の後ワイヤクランプジャッキ25aを作動させることにより桁11及び伸縮手延機21が先端部21bを固定として伸張する。第9段階の作業が完了した状態を図10に示す。   An end portion (hereinafter referred to as a distal end portion 21b) opposite to the straddling object 10 side of the telescopic handrail 21 is an upper portion of the bridge pier 12c and is coupled to the connecting member 26c (see FIG. 10) by bolting or the like. By operating the wire clamp jack 25a after the coupling, the girder 11 and the telescopic handbill 21 extend with the tip 21b fixed. FIG. 10 shows a state where the ninth stage work has been completed.

[第10段階]
第9段階の作業が完了した後、さらに桁11を送り出す。これに伴い伸縮手延機21も伸張する。第10段階の作業が完了した状態を図11に示す。
[10th stage]
After the ninth stage work is completed, the girders 11 are further sent out. Along with this, the telescopic hand-roller 21 also expands. FIG. 11 shows a state where the work of the tenth stage is completed.

[第11段階]
第10段階の作業が完了した後、伸縮手延機21の後端部21aが橋脚12bの上部に到達した時点で、伸縮手延機21の先端部21bと連結材26cとの結合を解除し、伸縮手延機21の先端部21bにワイヤ24b(図12参照)を結合し、このワイヤ24bを伸縮手延機21よりも跨対象物10側にある橋脚12bに設置したワイヤクランプジャッキ25aで牽引することにより、伸縮手延機21を縮小する。第11段階の作業が完了した状態を図12に示す。
[Stage 11]
After the work of the tenth stage is completed, when the rear end portion 21a of the telescopic handrail 21 reaches the upper part of the pier 12b, the connection between the front end portion 21b of the telescopic handwheel 21 and the connecting member 26c is released. The wire 24b (see FIG. 12) is coupled to the distal end portion 21b of the telescopic handbill 21, and the wire 24b is installed by the wire clamp jack 25a installed on the bridge pier 12b on the straddling object 10 side with respect to the telescopic handwheel 21. By pulling, the extender 21 is reduced. FIG. 12 shows a state where the work of the eleventh stage is completed.

[第12段階]
第11段階の作業が完了した後、伸縮手延機21を最小の状態まで収縮する。第12段階の作業が完了した状態を図13に示す。
[Stage 12]
After the work in the eleventh stage is completed, the telescopic handrail 21 is contracted to the minimum state. FIG. 13 shows a state where the work of the twelfth stage is completed.

[第13段階]
第12段階の作業が完了した後、伸縮手延機21の後端部21aにワイヤ24c(図14参照)を結合し、このワイヤ24cを伸縮手延機21よりも跨対象物10側にある橋脚12aに設置したワイヤクランプジャッキ25b(図14参照)で牽引することにより、桁11を跨対象物10側に送り出す。第13段階の作業が完了した状態を図14に示す。
[Stage 13]
After the work of the twelfth stage is completed, a wire 24c (see FIG. 14) is coupled to the rear end portion 21a of the telescopic handbill 21, and the wire 24c is closer to the straddling object 10 side than the telescopic handcuff 21. By pulling with the wire clamp jack 25b (refer FIG. 14) installed in the pier 12a, the girder 11 is sent out to the straddling target object 10 side. FIG. 14 shows a state where the 13th stage work is completed.

[第14段階]
第13段階の作業が完了した後、伸縮手延機21の先端部21bが橋脚12bの上部に到達した時点で、伸縮手延機21の先端部21bを橋脚12bの上部に設置した連結材26b(図15参照)にボルト締め等により結合する。第14段階の作業が完了した状態を図15に示す。
[Stage 14]
After the work of the 13th stage is completed, when the distal end portion 21b of the telescopic handrail 21 reaches the upper portion of the pier 12b, the connecting member 26b in which the distal end portion 21b of the telescopic handrail 21 is installed on the upper portion of the pier 12b. (Refer to FIG. 15). FIG. 15 shows a state where the 14th stage work has been completed.

[第15段階]
第14段階の作業が完了した後、第9段階から第14段階の作業を繰り返し行うことにより、桁11が跨対象物10の上方を跨ぐ。第15段階の作業が完了した状態を図16に示す。
[15th stage]
After the work of the 14th stage is completed, the work of the 14th stage is repeated from the 9th stage, so that the girder 11 straddles the upper side of the straddling object 10. FIG. 16 shows a state where the work of the fifteenth stage is completed.

[第16段階]
第15段階の作業が完了した後、手延機20及び伸縮手延機21を解体し撤去して桁11の送り出しを完了する。第16段階の作業が完了した状態を図17に示す。
[Stage 16]
After the work of the fifteenth stage is completed, the hand-roller 20 and the telescopic hand-roller 21 are disassembled and removed to complete the feeding of the girder 11. FIG. 17 shows a state where the 16th stage work is completed.

本実施例に係る送り出し方法によれば、地上において桁11の地組立を行うため、桁11の組み立て精度の向上を図ることができる。また、従来の送り出し方法(図18参照)で用いられていた架設桁52及びベント51を必要としないため、跨対象物10の幅が広い場合や橋脚12の高さが高い場合であっても、設備の省略化及び作業効率の改善を図ることができ、これにより、コストを削減することができる。   According to the delivery method according to the present embodiment, since the girder 11 is assembled on the ground, the assembly accuracy of the girder 11 can be improved. Moreover, since the installation girder 52 and the vent 51 used in the conventional delivery method (see FIG. 18) are not required, even when the spanning object 10 is wide or the pier 12 is high. Equipment can be omitted and work efficiency can be improved, thereby reducing costs.

また、伸張及び収縮が可能な大揚程上昇装置16と大揚程上昇装置16を支持する装置ベント19と桁11a及び桁11bを支持する支持ベント17を用いることにより、桁11を上昇するためにクレーン車23等の重機を必要としないため、作業スペースが狭小な場合や、桁11の上空に既に構造物が存在する場所であっても作業を行うことができる。   In addition, a crane for ascending the girder 11 by using a large lifting device 16 that can be extended and contracted, a device vent 19 that supports the large lifting device 16, and a support vent 17 that supports the beams 11a and 11b. Since a heavy machine such as the car 23 is not required, the work can be performed even when the work space is small or the place where the structure already exists above the beam 11.

また、ワイヤ24a,24b,24cと、これらを牽引するワイヤクランプジャッキ25a,25bを用いることにより、結合位置が多少異なってもワイヤ24a,24b,24cが柔軟であるため対応が容易であり、多少の角度が付いてもワイヤ24a,24b,24cをガイドすることにより対応が容易であり、張力によってワイヤ24自体が適度に伸縮するため張力管理が容易であり、余分なワイヤ24a,24b,24cは巻き取ることにより処理することが容易である。   In addition, by using the wires 24a, 24b, and 24c and the wire clamp jacks 25a and 25b that pull the wires 24a, 24b, and 24c, the wires 24a, 24b, and 24c are flexible even if the coupling positions are slightly different. Can be easily handled by guiding the wires 24a, 24b, and 24c, and the tension of the wires 24a, 24b, and 24c can be easily controlled because the wires 24 themselves are appropriately expanded and contracted by tension. It is easy to process by winding.

本発明に係る送り出し方法は、跨対象物の幅が広い場合、また、橋脚の高さが高い場合に有効である。   The delivery method according to the present invention is effective when the width of the straddling object is wide and when the height of the pier is high.

実施例1に係る送り出し方法の概要を示す側面図である。It is a side view which shows the outline | summary of the delivery method which concerns on Example 1. FIG. 実施例1に係る送り出し方法の第1段階完了時の側面図である。It is a side view at the time of completion of the first stage of the delivery method according to the first embodiment. 実施例1に係る送り出し方法の第2段階完了時の側面図である。It is a side view at the time of the 2nd step completion of the delivery method concerning Example 1. FIG. 実施例1に係る送り出し方法の第3段階完了時の側面図である。It is a side view at the time of the completion | finish of the 3rd step of the delivery method concerning Example 1. FIG. 実施例1に係る送り出し方法の第4段階完了時の側面図である。It is a side view at the time of the completion | finish of the 4th step of the delivery method which concerns on Example 1. FIG. 実施例1に係る送り出し方法の第5段階完了時の側面図である。It is a side view at the time of completion of the fifth stage of the delivery method according to Embodiment 1. 実施例1に係る送り出し方法の第6段階完了時の側面図である。It is a side view at the time of completion of the 6th stage of the delivery method concerning Example 1. 実施例1に係る送り出し方法の第7段階完了時の側面図である。It is a side view at the time of the completion | finish of the 7th step of the delivery method which concerns on Example 1. FIG. 実施例1に係る送り出し方法の第8段階完了時の側面図である。It is a side view at the time of completion | finish of the 8th step of the delivery method which concerns on Example 1. FIG. 実施例1に係る送り出し方法の第9段階完了時の側面図である。It is a side view at the time of completion | finish of the 9th step of the delivery method concerning Example 1. FIG. 実施例1に係る送り出し方法の第10段階完了時の側面図である。It is a side view at the time of completion | finish of the 10th step of the delivery method which concerns on Example 1. FIG. 実施例1に係る送り出し方法の第11段階完了時の側面図である。It is a side view at the time of the 11th step completion of the delivery method concerning Example 1. 実施例1に係る送り出し方法の第12段階完了時の側面図である。It is a side view at the time of completion of the twelfth stage of the delivery method according to the first embodiment. 実施例1に係る送り出し方法の第13段階完了時の側面図である。It is a side view at the time of completion | finish of the 13th step of the delivery method which concerns on Example 1. FIG. 実施例1に係る送り出し方法の第14段階完了時の側面図である。It is a side view at the time of the 14th step completion of the sending-out method concerning Example 1. 実施例1に係る送り出し方法の第15段階完了時の側面図である。It is a side view at the time of completion | finish of the 15th step of the delivery method concerning Example 1. FIG. 実施例1に係る送り出し方法の第16段階完了時の側面図である。It is a side view at the time of the 16th step completion of the delivery method concerning Example 1. 従来の送り出し方法の側面図である。It is a side view of the conventional sending-out method.

符号の説明Explanation of symbols

10 跨対象物
11,11a,11b 桁
12,12a,12b,12c 橋脚
13 送り装置
14 架台
15 ブロック
16 大揚程上昇装置
17,17a,17b 支持ベント
18 縦送り装置
19 装置ベント
20 手延機
21 伸縮手延機
22 連結構
23 クレーン車
24a,24b,24c ワイヤ
25a,25b ワイヤクランプジャッキ
26b,26c 連結材
27 地面
28 基礎
51 ベント
52 架設桁
53 台車
10 straddling object 11, 11a, 11b girder 12, 12a, 12b, 12c pier 13 feeding device 14 gantry 15 block 16 large lifting device 17, 17a, 17b support vent 18 vertical feeding device 19 device vent 20 extender 21 telescopic Hand extender 22 Connecting structure 23 Crane vehicles 24a, 24b, 24c Wires 25a, 25b Wire clamp jacks 26b, 26c Connecting material 27 Ground 28 Foundation 51 Vent 52 Installation girder 53 Dolly

Claims (4)

複数の橋脚で支持する桁を跨対象物の上方に立体交差させる方法であって、
前記桁を支持する前記橋脚のうち前記跨対象物を挟む前記橋脚間以外の任意の前記橋脚間を第1区間とし、前記第1区間の前記跨対象物側と反対側に隣接する前記橋脚間を第2区間とし、前記第1区間で第1桁を組み立て、前記第2区間で第2桁を組み立て、
前記第1桁を上昇手段により上昇し、前記跨対象物側に送り出して前記橋脚上に載置し、
前記第2桁を前記上昇手段により上昇し、前記跨対象物側に送り出して前記橋脚上に載置し、
さらに前記第2桁を送り出し、前記第2桁の端部と前記第1桁の端部とを接触させて結合して送り出し桁とし、
支持手段により前記送り出し桁の荷重を支持しつつ、送り出し手段により前記送り出し桁を前記跨対象物側に送り出す
ことを特徴とする送り出し方法。
A method of three-dimensionally crossing a girder supported by a plurality of bridge piers above a straddling object,
Between the bridge piers that support the girder, between the bridge piers other than between the bridge piers sandwiching the straddling object is a first section, and between the piers adjacent to the opposite side of the straddling object side of the first section As the second section, the first section is assembled in the first section, the second section is assembled in the second section,
The first digit is raised by the raising means, sent to the straddling object side and placed on the pier,
The second girder is raised by the raising means, sent out to the straddling object side and placed on the pier,
Furthermore, the second girder is sent out, and the end of the second girder and the end of the first girder are brought into contact with each other to form a sending girder,
A delivery method characterized by feeding the delivery girder to the straddling object side by delivery means while supporting the load of the delivery girder by support means.
請求項1に記載する送り出し方法において、
前記上昇手段として、上下方向に伸張及び収縮可能な大揚程上昇装置と、前記大揚程上昇装置を支持する装置ベントと、前記第1桁及び第2桁を支持する支持ベントを用いる
ことを特徴とする送り出し方法。
The delivery method according to claim 1,
As the raising means, a large lifting device capable of extending and contracting in the vertical direction, a device vent for supporting the large lifting device, and a support vent for supporting the first and second girders are used. How to send out.
請求項1又は請求項2に記載する送り出し方法において、
前記送り出し手段として、ワイヤと前記ワイヤを牽引するワイヤクランプジャッキを用いる
ことを特徴とする送り出し方法。
In the delivery method according to claim 1 or 2,
As the delivery means, a wire and a wire clamp jack that pulls the wire are used.
請求項1ないし請求項3のいずれかに記載する送り出し方法において、
前記支持手段として、前記送り出し桁の端部に設置可能で、伸縮可能な伸縮手延機を用いる
ことを特徴とする送り出し方法。
The delivery method according to any one of claims 1 to 3,
A feeding method characterized by using an extendable hand extender that can be installed at the end of the sending beam as the supporting means.
JP2005123168A 2005-04-21 2005-04-21 Launching method Withdrawn JP2006299650A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005123168A JP2006299650A (en) 2005-04-21 2005-04-21 Launching method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005123168A JP2006299650A (en) 2005-04-21 2005-04-21 Launching method

Publications (1)

Publication Number Publication Date
JP2006299650A true JP2006299650A (en) 2006-11-02

Family

ID=37468274

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005123168A Withdrawn JP2006299650A (en) 2005-04-21 2005-04-21 Launching method

Country Status (1)

Country Link
JP (1) JP2006299650A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009133153A (en) * 2007-11-30 2009-06-18 Ihi Corp Viaduct construction method
CN101838968A (en) * 2010-05-19 2010-09-22 中铁二十局集团有限公司 Double track bridge construction process crossing existing railway operational lines
CN102220741A (en) * 2011-04-14 2011-10-19 中铁二十局集团第六工程有限公司 Steel-concrete composite girder construction technology striding current lines and being parallel to existing lines
CN104060548A (en) * 2014-06-17 2014-09-24 河北工业大学 Ultralow conveying frame beam-integrated bridging machine and bridging method thereof
CN104314006A (en) * 2014-10-08 2015-01-28 中铁二十四局集团有限公司 High-performance sliding device oriented to large-tonnage incremental launching engineering
JP2019044453A (en) * 2017-08-31 2019-03-22 西日本旅客鉄道株式会社 Replacement method and erection machine

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009133153A (en) * 2007-11-30 2009-06-18 Ihi Corp Viaduct construction method
CN101838968A (en) * 2010-05-19 2010-09-22 中铁二十局集团有限公司 Double track bridge construction process crossing existing railway operational lines
CN102220741A (en) * 2011-04-14 2011-10-19 中铁二十局集团第六工程有限公司 Steel-concrete composite girder construction technology striding current lines and being parallel to existing lines
CN104060548A (en) * 2014-06-17 2014-09-24 河北工业大学 Ultralow conveying frame beam-integrated bridging machine and bridging method thereof
CN104314006A (en) * 2014-10-08 2015-01-28 中铁二十四局集团有限公司 High-performance sliding device oriented to large-tonnage incremental launching engineering
JP2019044453A (en) * 2017-08-31 2019-03-22 西日本旅客鉄道株式会社 Replacement method and erection machine
JP6991017B2 (en) 2017-08-31 2022-01-12 西日本旅客鉄道株式会社 Replacement method and erection machine

Similar Documents

Publication Publication Date Title
JP4504910B2 (en) Dolly and method of erection of temporary pier using it
JP4581131B2 (en) Bridge erection method and apparatus
JP4377506B2 (en) Bridge erection device and bridge erection method
JP2008088782A (en) Cantilever overhang erection method of corrugated steel plate web bridge
JP2006299650A (en) Launching method
JP2011069164A (en) Bridge girder delivery method
JP2018053496A (en) Bridge girder erection method for multiple span continuous bridge
JP2009035884A (en) Lift-up method for steel tower
JP2003221875A (en) Rail-less slide method
JP5260709B2 (en) Bridge girder delivery method
JP2007218029A (en) Girder lifting erection method and girder erection joint structure
JP4033871B2 (en) How to build a bridge girder
JP4351523B2 (en) Column head construction method
KR100627102B1 (en) Upper bridge structure construcion method with precast segment deck or box using a lifting traveller
JP7136309B2 (en) Superstructure material transportation equipment and superstructure material transportation method
KR200363059Y1 (en) Upper bridge structure construcion system with precast segment deck or box using a lifting traveller
JP6508958B2 (en) Demolition system and demolition method
JP2015212495A (en) Scaffold device, and construction method for concrete skeleton using the same
JP6508959B2 (en) Demolition system and demolition method
JP4349995B2 (en) How to build a bridge
JP2006316409A (en) Compound steel pipe steel tower and construction method therefor
JP6059176B2 (en) Mobile lifting scaffold for assembling temporary elevated jetty
JP6218316B2 (en) Girder block installation device and girder block installation method
JP2008038546A (en) Pyron type overhang construction apparatus, and construction method
JP4103574B2 (en) Construction method of beam-like structure

Legal Events

Date Code Title Description
A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20060809

RD03 Notification of appointment of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7423

Effective date: 20060926

A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20080701