JP2007164519A - Work plan creation device and work plan creation processing program - Google Patents

Work plan creation device and work plan creation processing program Download PDF

Info

Publication number
JP2007164519A
JP2007164519A JP2005360668A JP2005360668A JP2007164519A JP 2007164519 A JP2007164519 A JP 2007164519A JP 2005360668 A JP2005360668 A JP 2005360668A JP 2005360668 A JP2005360668 A JP 2005360668A JP 2007164519 A JP2007164519 A JP 2007164519A
Authority
JP
Japan
Prior art keywords
work
task
date
identification information
scheduled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2005360668A
Other languages
Japanese (ja)
Inventor
Hisashi Watanabe
悠 渡邊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Toshiba Digital Solutions Corp
Original Assignee
Toshiba Corp
Toshiba Solutions Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp, Toshiba Solutions Corp filed Critical Toshiba Corp
Priority to JP2005360668A priority Critical patent/JP2007164519A/en
Publication of JP2007164519A publication Critical patent/JP2007164519A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To create a work plan by which each work process is efficiently feasible. <P>SOLUTION: A control unit 2 sets a period from start of each task to its completion on the basis of a name of a task to be managed by a task management table, a person in charge, and a period of time needed for the work. The control unit 2 changes a content in the task management table so that a scheduled starting date of a task of the highest priority of all tasks nears a scheduled start date of a higher order task. The control unit 2 creates a Gantt chart on the basis of the changed content in the task management table and displays it to a display part 5. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本発明は、生産計画、運用計画、プロジェクト管理などの計画業務の工程管理に用いる作業計画作成装置および作業計画作成処理プログラムに関する。   The present invention relates to a work plan creation apparatus and a work plan creation processing program used for process management of planning work such as production planning, operation planning, and project management.

従来、例えば生産計画、運用計画およびプロジェクト管理などの計画業務の工程管理においてはガントチャートが用いられる。ガントチャートとは横軸に時間を配置し、縦軸にプロジェクトの名称、このプロジェクトに属する各作業項目の項目および担当者名などの項目を配置し、それぞれの作業項目の作業開始予定日、作業完了予定日などの情報を作業項目ごとに帯状に示したものである(例えば特許文献1参照)。
特開2000−254838号公報
Conventionally, Gantt charts are used in process management of planning operations such as production planning, operation planning, and project management. With the Gantt chart, time is placed on the horizontal axis, the project name, items for each work item belonging to this project, and the name of the person in charge are placed on the vertical axis. Information such as the scheduled completion date is shown in a band for each work item (see, for example, Patent Document 1).
JP 2000-254838 A

プロジェクトに属する各作業項目の中には他の作業項目との関連性や作業所要日数などにより他の作業項目に優先して実施を開始すべき項目が存在する。このような場合にはプロジェクト管理者は各作業工程が効率的に実施可能とする様に作業計画を作成するべく各作業項目の重要度をもとに開始順序や開始日などを手作業で入力するが、この管理者の負担が多大となる。   Among the work items belonging to the project, there are items that should be implemented in preference to other work items due to the relevance to other work items and the number of days required for the work. In such a case, the project manager manually inputs the start order and start date based on the importance of each work item in order to create a work plan so that each work process can be carried out efficiently. However, the burden on the administrator becomes great.

そこで、本発明は上記事情に鑑みてなされたものであり、その目的は、各作業工程が効率的に実施可能な作業計画を作成することが可能になる作業計画作成装置および作業計画作成処理プログラムを提供することにある。   Therefore, the present invention has been made in view of the above circumstances, and an object of the present invention is to provide a work plan creation device and a work plan creation processing program that can create a work plan in which each work process can be efficiently performed. Is to provide.

すなわち、本発明に係わる作業計画作成装置は、複数の作業工程でなる作業単位に属する各作業工程の識別情報、前記作業工程の優先度情報およびこの作業工程の着手予定日および完了予定日の情報を作業工程ごとに対応付けて記憶する工程記憶手段を備え、識別情報と関わる作業工程のうち予め定められた条件を満たす優先度情報と対応付けられる作業工程の着手予定日を作業単位の予め定められた着手日に近い日付に設定し、この日付および工程記憶手段に記憶された情報をもとに前記定められた条件を満たす優先度情報と対応付けられて工程記憶手段に記憶される識別情報と関わる作業工程の完了予定日を計算し、工程記憶手段に記憶された作業工程の識別情報、当該作業工程の着手予定日、完了予定日とを対応付けて出力することを特徴とする。   That is, the work plan creation apparatus according to the present invention includes identification information of each work process belonging to a work unit composed of a plurality of work processes, priority information of the work process, and information on a scheduled start date and a scheduled completion date of the work process. Is stored in association with each work process, and the scheduled start date of the work process associated with the priority information satisfying a predetermined condition among the work processes related to the identification information is determined in advance as a work unit. The identification information stored in the process storage means in association with the priority information satisfying the predetermined condition based on the date and the information stored in the process storage means. To calculate the scheduled completion date of the work process related to the process, and output the work process identification information stored in the process storage means, the scheduled start date of the work process, and the planned completion date in association with each other. And butterflies.

また、本発明に係わる作業計画作成処理プログラムは、複数の作業工程でなる作業単位に属する各作業工程の識別情報、前記作業工程の優先度情報およびこの作業工程の着手予定日および完了予定日の情報を作業工程ごとに対応付けて記憶する工程記憶手段を備えるコンピュータを、識別情報と関わる作業工程のうち予め定められた条件を満たす優先度情報と対応付けられる作業工程の着手予定日を作業単位の予め定められた着手日に近い日付に設定し、この日付および工程記憶手段に記憶された情報をもとに前記定められた条件を満たす優先度情報と対応付けられて工程記憶手段に記憶される識別情報と関わる作業工程の完了予定日を計算し、工程記憶手段に記憶された作業工程の識別情報、当該作業工程の着手予定日、完了予定日とを対応付けて出力するように機能させることを特徴とする。   Further, the work plan creation processing program according to the present invention includes identification information of each work process belonging to a work unit composed of a plurality of work processes, priority information of the work process, scheduled start date and scheduled completion date of the work process. A computer having a process storage means for storing information in association with each work process, a work unit indicating a scheduled start date of a work process associated with priority information satisfying a predetermined condition among work processes related to identification information Is set to a date close to a predetermined start date, and stored in the process storage means in association with the priority information satisfying the predetermined condition based on the date and the information stored in the process storage means. The planned completion date of the work process related to the identification information is calculated, and the identification information of the work process stored in the process storage means, the planned start date of the work process, and the planned completion date are compared. Thereby functions to attach the output and said.

本発明に係わる作業計画作成装置によれば、各作業工程を効率的に実施可能にする作業計画を作成することができる。   According to the work plan creation apparatus according to the present invention, it is possible to create a work plan that enables each work process to be efficiently performed.

以下図面により本発明の実施形態について説明する。
図1は、本発明の実施形態に従った作業計画作成装置の構成例を示すブロック図である。
本発明の実施形態に従った作業計画作成装置1は装置全体の動作を司る制御部2、記憶部3、入力部4および表示部5を備え、これらはバス6を介して相互に接続される。
入力部4は例えばキーボードやマウスであり、ガントチャートの各項目の作成および修正にかかる操作を受け付ける。表示部5はガントチャートを表示するための装置である。
Embodiments of the present invention will be described below with reference to the drawings.
FIG. 1 is a block diagram illustrating a configuration example of a work plan creation apparatus according to an embodiment of the present invention.
A work plan creation device 1 according to an embodiment of the present invention includes a control unit 2, a storage unit 3, an input unit 4, and a display unit 5 that control the operation of the entire device, which are connected to each other via a bus 6. .
The input unit 4 is, for example, a keyboard or a mouse, and accepts operations related to creation and correction of each item of the Gantt chart. The display unit 5 is a device for displaying a Gantt chart.

記憶部3は例えばハ−ドディスクドライブや不揮発性メモリ装置などのハードウェアで構成された記憶装置である。記憶部3は制御用のプログラムに加え、各種の管理テーブルを記憶する。記憶部3は制御部2による各種処理のワークメモリとしても機能する。   The storage unit 3 is a storage device configured by hardware such as a hard disk drive or a nonvolatile memory device. The storage unit 3 stores various management tables in addition to the control program. The storage unit 3 also functions as a work memory for various processes performed by the control unit 2.

図2は、本発明の実施形態に従った作業計画作成装置1の記憶部3に記憶されるプロジェクト管理テーブルの構成例を表形式で示す図である。
記憶部3には図2に示したような形式のプロジェクト管理テーブルが記憶される。このプロジェクト管理テーブルは各種プロジェクト番号、客先名、および納期を示す情報が対応付けられて管理される。
プロジェクト番号とは複数の作業工程を含む作業単位に固有の識別番号である。客先名とはプロジェクト管理テーブル上で対応付けられるプロジェクトの発注元である。
FIG. 2 is a diagram showing a configuration example of the project management table stored in the storage unit 3 of the work plan creation apparatus 1 according to the embodiment of the present invention in a table format.
The storage unit 3 stores a project management table in the format shown in FIG. This project management table is managed in association with information indicating various project numbers, customer names, and delivery dates.
The project number is an identification number unique to a work unit including a plurality of work processes. The customer name is a project ordering source associated with the project management table.

図3は、本発明の実施形態に従った作業計画作成装置1の記憶部3に記憶されるタスク管理テーブルの構成例(その1)を表形式で示す図である。
記憶部3には図3に示したような形式のタスク管理テーブルが記憶される。このタスク管理テーブルは図2に示したプロジェクト管理テーブルで管理されるプロジェクトごとに記憶部3に記憶されるテーブルである。図3に示したタスク管理テーブルは図2に示したプロジェクト管理テーブルで管理されるプロジェクト番号「PRO00001」に対応するプロジェクトに属する各作業工程の計画を定義するためのテーブルである。以下、作業工程をタスクと称する。
FIG. 3 is a diagram showing a configuration example (part 1) of the task management table stored in the storage unit 3 of the work plan creation device 1 according to the embodiment of the present invention in a table format.
The storage unit 3 stores a task management table having a format as shown in FIG. This task management table is a table stored in the storage unit 3 for each project managed by the project management table shown in FIG. The task management table shown in FIG. 3 is a table for defining a plan for each work process belonging to the project corresponding to the project number “PRO00001” managed by the project management table shown in FIG. Hereinafter, the work process is referred to as a task.

このタスク管理テーブルはプロジェクト番号、タスク名、タスク階層、担当者、開始予定日、終了予定日、開始日、終了日およびリードタイムが対応付けられて管理される。
タスク管理テーブル中のタスク名とは、プロジェクト番号に対応するプロジェクトに属する上位の作業単位であるサマリタスクおよび当該サマリタスクの下位の作業単位である複数のタスクの名称である。以下、下位の作業単位である複数のタスクを単にタスクと称してサマリタスクと区別する。
This task management table is managed in association with the project number, task name, task hierarchy, person in charge, scheduled start date, scheduled end date, start date, end date, and lead time.
The task name in the task management table is the name of a summary task that is a higher-level work unit belonging to the project corresponding to the project number and a plurality of tasks that are lower-level work units of the summary task. Hereinafter, a plurality of tasks, which are lower work units, are simply referred to as tasks and distinguished from summary tasks.

タスク階層は作業単位の概念の上下関係を数字で示したものである。ここでは階層の数字の少ないサマリタスクが上位概念の作業単位であり、階層の数字の大きいタスクが下位概念の作業単位である。図2で示したプロジェクト管理テーブルで管理されるプロジェクト番号「PRO00001」に対応するプロジェクトに属するサマリタスクは「サマリタスクA」のみであるとする。   The task hierarchy is a numerical representation of the hierarchical relationship of the concept of work units. Here, a summary task with a small number in the hierarchy is an upper concept work unit, and a task with a higher number in the hierarchy is a lower concept work unit. Assume that only the “summary task A” is the summary task belonging to the project corresponding to the project number “PRO00001” managed in the project management table shown in FIG.

タスク管理テーブル上の担当者とは、タスク管理テーブル上で管理されるタスク名と対応するタスクの実施担当者の氏名である。タスク管理テーブル上の開始予定日とは、タスク管理テーブル上で対応付けられるタスク名と対応するタスクの着手予定日である。タスク管理テーブル上の終了予定日とは、タスク管理テーブル上で対応付けられるタスク名と対応するタスクの完了予定日である。   The person in charge on the task management table is the name of the person in charge of executing the task corresponding to the task name managed on the task management table. The scheduled start date on the task management table is the scheduled start date of the task corresponding to the task name associated with the task management table. The scheduled end date on the task management table is the scheduled completion date of the task corresponding to the task name associated with the task management table.

また、開始日はタスク管理テーブル上で対応付けられるタスク名と対応するタスクの実施の着手日である。終了日はタスク管理テーブル上で対応付けられるタスク名と対応するタスクの実施の完了日である。   Also, the start date is the date on which the task corresponding to the task name associated on the task management table is started. The end date is a task completion date corresponding to the task name associated with the task management table.

タスク管理テーブル上のリードタイムはタスク管理テーブル上で対応付けられるタスク名と対応するタスクの着手予定日から終了予定日までの期間である。この期間にはタスクの着手予定日および終了予定日が含まれる。   The lead time on the task management table is a period from the scheduled start date to the scheduled end date of the task corresponding to the task name associated with the task management table. This period includes the scheduled start date and scheduled end date of the task.

図3に示したタスク管理テーブルではタスク「サマリタスクA」に属するタスクがタスク「タスクA−1」、「タスクA−2」、「タスクB−1」、「タスクB−2」、「タスクB−3」、「タスクC−1」、「タスクC−2」にそれぞれ対応するタスクである。   In the task management table shown in FIG. 3, the tasks belonging to the task “summary task A” are tasks “task A-1”, “task A-2”, “task B-1”, “task B-2”, “task B”. −3 ”,“ task C-1 ”, and“ task C-2 ”.

タスク名「サマリタスクA」にはタスク階層「0」、開始予定日「2005年2月12日」および終了予定日「2005年2月26日」が対応付けられる。タスク「タスクA−1」にはタスク階層「1」、担当者「担当者B」、開始予定日「2005年2月12日」、終了予定日「2005年2月14日」、リードタイム「3日」が対応付けられる。タスク「タスクA−2」にはタスク階層「1」、担当者「担当者C」、開始予定日「2005年2月15日」、終了予定日「2005年2月17日」、リードタイム「3日」が対応付けられる。   The task name “summary task A” is associated with the task hierarchy “0”, the scheduled start date “February 12, 2005”, and the scheduled end date “February 26, 2005”. The task “task A-1” includes task hierarchy “1”, person in charge “person B”, scheduled start date “February 12, 2005”, scheduled end date “February 14, 2005”, and lead time “ 3 days "is associated. The task “task A-2” includes task hierarchy “1”, person in charge “person C”, scheduled start date “February 15, 2005”, scheduled end date “February 17, 2005”, and lead time “ 3 days "is associated.

また、タスク「タスクB−1」にはタスク階層「1」、担当者「担当者A」、開始予定日「2005年2月16日」、終了予定日「2005年2月19日」、リードタイム「4日」が対応付けられる。タスク「タスクB−2」にはタスク階層「1」、担当者「担当者C」、開始予定日「2005年2月20日」、終了予定日「2005年2月22日」、リードタイム「3日」が対応付けられる。タスク「タスクB−3」にはタスク階層「1」、担当者「担当者D」、開始予定日「2005年2月23日」、終了予定日「2005年2月26日」、リードタイム「4日」が対応付けられる。   The task “task B-1” has a task hierarchy “1”, a person in charge “person A”, a scheduled start date “February 16, 2005”, a scheduled end date “February 19, 2005”, and a lead. The time “4 days” is associated. The task “task B-2” includes task hierarchy “1”, person in charge “person C”, scheduled start date “February 20, 2005”, scheduled end date “February 22, 2005”, and lead time “ 3 days "is associated. The task “task B-3” includes a task hierarchy “1”, a person in charge “person D”, a scheduled start date “February 23, 2005”, a scheduled end date “February 26, 2005”, and a lead time “ 4 days "is associated.

また、タスク「タスクC−1」にはタスク階層「1」、担当者「担当者E」、開始予定日「2005年2月19日」、終了予定日「2005年2月21日」、リードタイム「3日」が対応付けられる。タスク「タスクC−2」にはタスク階層「1」、担当者「担当者A」、開始予定日「2005年2月22日」、終了予定日「2005年2月26日」、リードタイム「5日」が対応付けられる。   The task “task C-1” includes a task hierarchy “1”, a person in charge “person E”, a scheduled start date “February 19, 2005”, a scheduled end date “February 21, 2005”, and a lead. The time “3 days” is associated. The task “task C-2” includes a task hierarchy “1”, a person in charge “person A”, a scheduled start date “February 22, 2005”, a scheduled end date “February 26, 2005”, and a lead time “ "5 days" is associated.

図4は、本発明の実施形態に従った作業計画作成装置1の記憶部3に記憶される依存関係管理テーブルの構成例を表形式で示す図である。
記憶部3には図4に示したような形式の依存関係管理テーブルが記憶される。このタスク管理テーブルは図3に示したタスク管理テーブルで管理される各タスクの作業順序の前後関係を定義するためのテーブルである。
FIG. 4 is a diagram showing a configuration example of the dependency management table stored in the storage unit 3 of the work plan creation device 1 according to the embodiment of the present invention in a table format.
The storage unit 3 stores a dependency management table in the format shown in FIG. This task management table is a table for defining the context of the work order of each task managed by the task management table shown in FIG.

依存関係とは先のタスクおよび後のタスクの関係を意味する。先のタスクとは後のタスクの開始前に終了することが必要なタスクであり、後のタスクとは先のタスクの終了後に開始することが可能なタスクである。
この依存関係管理テーブルは先のタスクのタスク名および後のタスク名が対応付けられて管理される。
Dependency means the relationship between the previous task and the subsequent task. The previous task is a task that needs to be finished before the start of the later task, and the later task is a task that can be started after the previous task is finished.
This dependency management table is managed by associating the task name of the previous task and the subsequent task name.

図4に示した依存関係管理テーブルでは、先のタスク「タスクA−1」に後のタスク「タスクA−2」が対応付けられ、先のタスク「タスクB−1」に後のタスク「タスクB−2」が対応付けられ、先のタスク「タスクB−2」に後のタスク「タスクB−3」が対応付けられ、先のタスク「タスクC−1」に後のタスク「タスクC−2」が対応付けられる。   In the dependency management table shown in FIG. 4, the subsequent task “task A-1” is associated with the previous task “task A-1”, and the subsequent task “task B-1” is associated with the subsequent task “task A-1”. B-2 "is associated with the previous task" task B-2 ", the subsequent task" task B-3 "is associated with the previous task" task C-1 ", and the subsequent task" task C- " 2 ”is associated.

図5は、本発明の実施形態に従った作業計画作成装置1の記憶部3に記憶される優先度管理テーブルの構成例(その1)を表形式で示す図である。
記憶部3には図5に示したような形式の優先度管理テーブルが記憶される。このタスク管理テーブルは図3に示したタスク管理テーブルで管理される各タスクの優先度を定義するためのテーブルである。優先度は高い優先度である「高」と通常の優先度である「並」に区別される。
FIG. 5 is a diagram showing a configuration example (part 1) of the priority management table stored in the storage unit 3 of the work plan creation apparatus 1 according to the embodiment of the present invention in a table format.
The storage unit 3 stores a priority management table having a format as shown in FIG. This task management table is a table for defining the priority of each task managed by the task management table shown in FIG. The priority is classified into “high” which is a high priority and “normal” which is a normal priority.

この優先度管理テーブルは各タスクの名称および優先度が対応付けられて管理される。図5に示した優先度管理テーブルではタスク「タスクA−1」、「タスクA−2」、「タスクB−2」、「タスクB−3」、「タスクC−1」に優先度「並」が対応付けられ、タスク「タスクB−1」、「タスクC−2」に優先度「高」が対応付けられる。   This priority management table is managed in association with the names and priorities of the tasks. In the priority management table shown in FIG. 5, tasks “task A-1”, “task A-2”, “task B-2”, “task B-3”, and “task C-1” have a priority “parallel”. ”And the tasks“ task B-1 ”and“ task C-2 ”are associated with the priority“ high ”.

次に、図1に示した構成の作業計画作成装置1の動作について説明する。
図6は、本発明の実施形態に従った作業計画作成装置1の処理動作の一例を示すフローチャートである。
Next, the operation of the work plan creation apparatus 1 having the configuration shown in FIG. 1 will be described.
FIG. 6 is a flowchart showing an example of the processing operation of the work plan creation device 1 according to the embodiment of the present invention.

ここで、記憶部3に記憶されるプロジェクト管理テーブル、タスク管理テーブル、依存関係管理テーブルおよび優先度管理テーブルは入力部4に対する予め定められた操作にしたがって図2乃至図5にそれぞれ示した内容に設定されているものと仮定する。また、互いが依存関係にあるタスクのうち後のタスクの開始予定日は先のタスクの終了予定日の翌日であるとする。   Here, the project management table, task management table, dependency management table, and priority management table stored in the storage unit 3 have the contents shown in FIGS. 2 to 5 in accordance with predetermined operations on the input unit 4, respectively. Assume that it is set. Further, it is assumed that the scheduled start date of the later task among the tasks that are dependent on each other is the next day after the scheduled end date of the previous task.

そして、ユーザが入力部4に対する予め定められた操作を行なって、作業計画作成装置1の動作モードを作業計画調整モードに設定する。この状態では、制御部2は記憶部3に記憶された各種テーブルを読み込んだ(ステップS1)上で、この各種テーブルの内容に基づいたガントチャートを作成する。   And a user performs predetermined operation with respect to the input part 4, and sets the operation mode of the work plan preparation apparatus 1 to work plan adjustment mode. In this state, the control unit 2 reads various tables stored in the storage unit 3 (step S1), and creates a Gantt chart based on the contents of the various tables.

図7は、本発明の実施形態に従った作業計画作成装置1が作成したガントチャートの構成例(その1)を示す図である。このガントチャートは作業計画作成装置1の制御部2が図2に示したプロジェクト管理テーブル、図3に示したタスク管理テーブル、図4に示した依存関係管理テーブルおよび図5に示した優先度管理テーブルを元に作成したガントチャートである。   FIG. 7 is a diagram showing a configuration example (part 1) of the Gantt chart created by the work plan creation device 1 according to the embodiment of the present invention. In this Gantt chart, the control unit 2 of the work plan creation apparatus 1 has the project management table shown in FIG. 2, the task management table shown in FIG. 3, the dependency management table shown in FIG. 4, and the priority management shown in FIG. It is a Gantt chart created based on the table.

このガントチャートでは、タスク管理テーブルと同様に、プロジェクト番号、タスク名、開始日および終了日が管理される。また、このガントチャートではプロジェクトの開始日から納期の間における各タスクの作業日程を示すバーがタスクごとに示される。また、記憶部3に記憶された依存関係管理テーブルで互いに依存関係にあるタスクのうち先のタスク日程を示すバーの右端と後のタスクの日程を示すバーの左上にかけて矢印が挿入される。   In this Gantt chart, the project number, task name, start date, and end date are managed as in the task management table. In this Gantt chart, a bar indicating the work schedule of each task between the project start date and the delivery date is shown for each task. In addition, an arrow is inserted from the right end of the bar indicating the previous task schedule and the upper left of the bar indicating the schedule of the subsequent task among the tasks that are dependent on each other in the dependency management table stored in the storage unit 3.

ガントチャート中のサマリタスクの日程を示すバーには「プロジェクト」の文字が挿入され、各タスクの日程を示すバーのうち優先度管理テーブルで優先度が「並」に設定されていたタスクのバーには「タスク」の文字が挿入され、優先度管理テーブルで優先度が「高」に設定されていたタスクのバーには「優先タスク」の文字が挿入される。   The word “Project” is inserted in the bar indicating the schedule of the summary task in the Gantt chart, and the bar of the task whose priority is set to “Normal” in the priority management table among the bars indicating the schedule of each task. The character “task” is inserted, and the character “priority task” is inserted in the bar of the task whose priority is set to “high” in the priority management table.

制御部2は記憶部3に記憶された優先度管理テーブルから優先度が「高」であるタスク名を検索し(ステップS2)、このタスク名と依存関係にあるタスク名を依存関係管理テーブルから検索する。制御部2は依存関係にあるタスクを検索した場合にはこれら2つのタスクのうち先のタスクの開始予定日をタスク管理テーブルから検索する。また、制御部2は依存関係にあるタスクが依存関係管理テーブル中にない場合には前述した優先度が「高」であるタスクの開始予定日をタスク管理テーブルから検索する。   The control unit 2 searches the priority management table stored in the storage unit 3 for a task name having a high priority (step S2), and obtains a task name having a dependency relationship with the task name from the dependency management table. Search for. When the control unit 2 searches for a task having a dependency relationship, the control unit 2 searches the task management table for the scheduled start date of the previous task among these two tasks. In addition, when there is no dependency task in the dependency relationship management table, the control unit 2 searches the task management table for the scheduled start date of the task having the high priority described above.

制御部2は、この検索した開始予定日がこのタスクの上位のサマリタスクの開始予定日の翌日以降である場合(ステップS3のYES)には、前述した先のタスクの開始予定日がサマリタスクの開始予定日に繰り上がるようにタスク管理テーブルの内容を更新する。   The control unit 2 determines that the scheduled start date of the preceding task is the start of the summary task when the searched scheduled start date is after the next day of the scheduled start date of the upper summary task of this task (YES in step S3). Update the contents of the task management table so that it is carried forward on the scheduled date.

これに伴い、制御部2は当該タスクの終了予定日、このタスクと依存関係にあるタスクの開始予定日および終了予定日が前述したように繰り上がった日数分だけ繰り上がるようにタスク管理テーブルの内容を変更する(ステップS4)。ただし、変更後の開始予定日と終了予定日までの日付は上位のサマリタスクの開始予定日から終了予定日までの日付に含まれるものとする。   Accordingly, the control unit 2 sets the task management table so that the scheduled end date of the task, the scheduled start date and the scheduled end date of the task having a dependency relationship with the task are incremented by the number of days incremented as described above. The contents are changed (step S4). However, the dates from the scheduled start date and the scheduled end date after the change are included in the dates from the scheduled start date to the scheduled end date of the upper summary task.

具体的には、制御部2は図3に示したタスク管理テーブル上のタスク「タスクB−1」の優先度が「高」であり、このタスクより先のタスクとして依存関係管理テーブルで管理されるタスクはなく、このタスクの開始予定日はタスク「サマリタスクA」の開始予定日「2005年2月12日」の翌日以降の「2005年2月16日」であるので、制御部2はタスク管理テーブル中のタスク「タスクB−1」の開始予定日をタスク「サマリタスクA」の開始予定日に変更する。   Specifically, the priority of the task “task B-1” on the task management table shown in FIG. 3 is “high”, and the control unit 2 is managed in the dependency management table as a task ahead of this task. Since the scheduled start date of this task is “February 16, 2005” after the scheduled start date “February 12, 2005” of the task “Summary task A”, the control unit 2 The scheduled start date of task “task B-1” in the management table is changed to the scheduled start date of task “summary task A”.

この変更にかかる繰り上げ日数は4日であるので、制御部2はタスク管理テーブル中のタスク「タスクB−1」の終了予定日、このタスクより後のタスクとして依存関係管理テーブルで管理されるタスク「タスクB−2」の開始予定日、終了予定日、このタスクより後のタスクとして依存関係管理テーブルで管理されるタスク「タスクB−3」の開始予定日、終了予定日を4日ずつ繰り上げた日付にそれぞれ変更する。   Since the number of advance days for this change is four days, the control unit 2 is scheduled to finish the task “task B-1” in the task management table, and is managed in the dependency management table as a task after this task. The scheduled start and end dates of “Task B-2”, and the scheduled start and end dates of task “Task B-3” managed in the dependency management table as tasks after this task are incremented by 4 days. Change the date to

また、図3に示したタスク管理テーブル上のタスク「タスクC−2」の優先度が「高」であり、このタスクより先のタスクとして依存関係管理テーブルで管理されるタスクはタスク「タスクC−1」であり、このタスクの開始予定日はタスク「サマリタスクA」の開始予定日「2005年2月12日」の翌日以降の「2005年2月22日」であるので、制御部2はタスク管理テーブル中のタスク「タスクC−1」の開始予定日「2005年2月19日」を「サマリタスクA」の開始予定日に変更する。   Further, the priority of the task “task C-2” on the task management table shown in FIG. 3 is “high”, and the task managed in the dependency management table as a task ahead of this task is the task “task C”. -1 ”, and the scheduled start date of this task is“ February 22, 2005 ”after the scheduled start date“ February 12, 2005 ”of the task“ Summary Task A ”. The scheduled start date “February 19, 2005” of the task “task C-1” in the task management table is changed to the scheduled start date of “summary task A”.

この変更にかかる繰り上げ日数は7日であるので、制御部2はタスク管理テーブル中のタスク「タスクC−1」の終了予定日、このタスクより後のタスクとして依存関係管理テーブルで管理されるタスク「タスクC−2」の開始予定日、終了予定日を7日ずつ繰り上げた日付にそれぞれ変更する。   Since the number of advance days for this change is 7 days, the control unit 2 is scheduled to finish the task “task C-1” in the task management table, and is managed in the dependency management table as a task after this task. The scheduled start date and the scheduled end date of “task C-2” are respectively changed to a date advanced by 7 days.

図8は、本発明の実施形態に従った作業計画作成装置1の記憶部3に記憶されるタスク管理テーブルの構成例(その2)を表形式で示す図である。このタスク管理テーブルは図3に示したタスク管理テーブルが前述した優先度の高いタスクの開始予定日が繰り上がるように変更されたテーブルである。   FIG. 8 is a diagram showing a configuration example (part 2) of the task management table stored in the storage unit 3 of the work plan creation device 1 according to the embodiment of the present invention in a table format. This task management table is a table in which the task management table shown in FIG. 3 is changed so that the scheduled start date of the above-described high priority task is advanced.

図9は、本発明の実施形態に従った作業計画作成装置1が作成したガントチャートの構成例(その2)を示す図である。このガントチャートは作業計画作成装置1の制御部2が図2に示したプロジェクト管理テーブル、図8に示したタスク管理テーブル、図4に示した依存関係管理テーブルおよび図5に示した優先度管理テーブルを元に作成したガントチャートである。   FIG. 9 is a diagram showing a configuration example (part 2) of the Gantt chart created by the work plan creation device 1 according to the embodiment of the present invention. In this Gantt chart, the control unit 2 of the work plan creation apparatus 1 has the project management table shown in FIG. 2, the task management table shown in FIG. 8, the dependency management table shown in FIG. 4, and the priority management shown in FIG. It is a Gantt chart created based on the table.

次に、制御部2は記憶部3に記憶されるタスク管理テーブルの各担当者のうち一担当者が同一日に複数のタスクの作業担当となっているか否かを判別する(ステップS5,S6)。   Next, the control unit 2 determines whether one person in charge in the task management table stored in the storage unit 3 is in charge of a plurality of tasks on the same day (steps S5 and S6). ).

図9に示したガントチャートによれば「担当者A」は2005年2月15日にタスク「タスクB−1」およびタスク「タスクC−2」の実施担当予定となっている。また、「担当者C」は2005年2月16日から17日にかけてタスク「タスクA−2」とタスク「タスクB−2」の実施担当となっている。   According to the Gantt chart shown in FIG. 9, “Person in charge A” is scheduled to perform the tasks “Task B-1” and “Task C-2” on February 15, 2005. “Person in charge C” is in charge of executing task “task A-2” and task “task B-2” from February 16 to 17, 2005.

この場合、同一担当者による同一日の担当予定のタスクが複数である(ステップS6のYES)ので同一担当者の同一日の担当予定のタスクが1つとなるようにタスク管理テーブルの内容を変更する(ステップS7)。   In this case, since there are a plurality of tasks scheduled to be assigned on the same day by the same person in charge (YES in step S6), the contents of the task management table are changed so that there is one task on the same day for the same person in charge. (Step S7).

ただし、変更後の開始予定日と終了予定日までの日付はタスク「サマリタスクA」の開始予定日から終了予定日までの日付に含まれるものとし、優先度が「高」であるタスクおよびこれと先または後のタスクとして依存関係管理テーブルで管理されるタスクの開始予定日および終了予定日が繰り上げ又は繰り下がる場合にはこの日数が最小限になるようにする。   However, it is assumed that the dates from the scheduled start date and the scheduled end date after the change are included in the dates from the scheduled start date to the scheduled end date of the task “Summary Task A”. When the scheduled start date and the scheduled end date of the task managed in the dependency management table as the previous or subsequent task are moved up or down, the number of days is minimized.

具体的には、図8に示したタスク管理テーブル上の「担当者C」が担当するタスク「タスクA−2」の開始予定日「2005年2月15日」から同タスクの終了予定日「2005年2月17日」までの期間における「2005年2月16日」が「担当者C」の担当予定の別のタスク「タスクB−2」の開始予定日である。   Specifically, from the scheduled start date “February 15, 2005” of the task “task A-2”, which is handled by the “person C” on the task management table shown in FIG. “February 16, 2005” in the period up to “February 17, 2005” is the scheduled start date of another task “task B-2” scheduled to be handled by “person C”.

この場合、制御部2は「担当者C」による同一日の担当予定のタスクが複数あるとみなし、「タスクA−2」の開始予定日から終了予定日までの期間がタスク「タスクB−2」の開始予定日から終了予定日までの期間と重複しないようにタスク「タスクA−2」の開始予定日をタスク「タスクC−2」の終了予定日「2005年2月18日」の翌日である「2005年2月19日」に変更する。   In this case, the control unit 2 considers that there are a plurality of tasks scheduled to be assigned on the same day by “person C”, and the period from the scheduled start date to the scheduled end date of “task A-2” is the task “task B-2”. The scheduled start date of the task “task A-2” is set to the next day of the scheduled end date “February 18, 2005” of the task “task C-2” so that it does not overlap with the period from the scheduled start date to the scheduled end date. To “February 19, 2005”.

この変更にかかる繰り下げ日数は7日であるので、制御部2はタスク管理テーブル中のタスク「タスクA−2」の終了予定日、このタスクより先のタスクとして依存関係管理テーブルで管理されるタスク「タスクA−1」の開始予定日、終了予定日を7日ずつ繰り下げた日付にそれぞれ変更する。   Since the deferred days for this change are 7 days, the control unit 2 is scheduled to finish the task “task A-2” in the task management table, and is managed in the dependency management table as a task ahead of this task. The scheduled start date and the end scheduled date of “task A-1” are respectively changed to dates that are lowered by 7 days.

また、図8に示したタスク管理テーブル上の「担当者A」が担当するタスク「タスクB−1」の開始予定日「2005年2月12日」から同タスクの終了予定日「2005年2月15日」までの期間における「2005年2月15日」が「担当者A」の担当予定の別のタスク「タスクC−2」の開始予定日である。   In addition, from the scheduled start date “February 12, 2005” of the task “task B-1” handled by the “person A” on the task management table shown in FIG. “February 15, 2005” in the period up to “Month 15” is the scheduled start date of another task “Task C-2” scheduled to be handled by “Person A”.

この場合、制御部2は「担当者A」による同一日の担当予定のタスクが複数あるとみなし、「タスクB−1」の開始予定日から終了予定日までの期間が「タスクC−2」の開始予定日から終了予定日までの期間と重複しないようにタスク「タスクC−2」の開始予定日をタスク「タスクB−1」の終了予定日「2005年2月15日」の翌日である「2005年2月16日」に変更する。   In this case, the control unit 2 considers that there are a plurality of tasks scheduled to be handled by the “person A” on the same day, and the period from the scheduled start date to the scheduled end date of “task B-1” is “task C-2”. The scheduled start date of the task “task C-2” is the next day after the scheduled end date “February 15, 2005” of the task “task B-1” so as not to overlap with the period from the scheduled start date to the scheduled end date. It changes to a certain "February 16, 2005".

この変更にかかる繰り下げ日数は1日であるので、制御部2はタスク管理テーブル中のタスク「タスクC−2」の終了予定日、このタスクより先のタスクとして依存関係管理テーブルで管理されるタスク「タスクC−1」の開始予定日、終了予定日を1日ずつ繰り下げた日付にそれぞれ変更する。   Since the deferred number of days for this change is one day, the control unit 2 determines the scheduled end date of the task “task C-2” in the task management table, and the task managed in the dependency management table as a task ahead of this task. The scheduled start date and the scheduled end date of “task C-1” are respectively changed to dates that are lowered by one day.

図10は、本発明の実施形態に従った作業計画作成装置1の記憶部3に記憶されるタスク管理テーブルの構成例(その3)を表形式で示す図である。このタスク管理テーブルは図8に示したタスク管理テーブルが同一担当者による同一日の担当予定のタスクが1つとなるように変更されたテーブルである。   FIG. 10 is a diagram showing a configuration example (part 3) of the task management table stored in the storage unit 3 of the work plan creation device 1 according to the embodiment of the present invention in a table format. This task management table is a table in which the task management table shown in FIG. 8 is changed so that there is one task scheduled to be assigned on the same day by the same person in charge.

図11は、本発明の実施形態に従った作業計画作成装置1が作成したガントチャートの構成例(その3)を示す図である。このガントチャートは作業計画作成装置1の制御部2が図2に示したプロジェクト管理テーブル、図10に示したタスク管理テーブル、図4に示した依存関係管理テーブルおよび図5に示した優先度管理テーブルを元に作成したガントチャートである。   FIG. 11 is a diagram showing a configuration example (No. 3) of the Gantt chart created by the work plan creation device 1 according to the embodiment of the present invention. This Gantt chart is obtained by the control unit 2 of the work plan creation apparatus 1 by the project management table shown in FIG. 2, the task management table shown in FIG. 10, the dependency management table shown in FIG. 4, and the priority management shown in FIG. It is a Gantt chart created based on the table.

次に、制御部2は記憶部3に記憶されるタスク管理テーブルの各タスクのうちいずれかのタスクが納期、つまり上位のタスク「サマリタスクA」の終了予定日に実施予定であるか否かを判別する(ステップS8)。   Next, the control unit 2 determines whether any of the tasks in the task management table stored in the storage unit 3 is scheduled to be delivered, that is, scheduled to be executed on the scheduled end date of the higher-level task “summary task A”. A determination is made (step S8).

図10に示したタスク管理テーブルおよび図11に示したガントチャートによればタスク「サマリタスクA」の終了予定日である「2005年2月26日」に実施予定の下位のタスクはないので、上位タスクの納期に実施予定のタスクがない(ステップS8のYES)とみなし、納期に実施予定の下位のタスクが発生するようタスク管理テーブルの内容を変更する(ステップS9)。   According to the task management table shown in FIG. 10 and the Gantt chart shown in FIG. 11, there is no lower-level task scheduled to be executed on “February 26, 2005” which is the scheduled end date of the task “summary task A”. It is assumed that there is no task scheduled to be executed in the task delivery date (YES in step S8), and the contents of the task management table are changed so that a lower-level task scheduled to be executed occurs in the delivery date (step S9).

ただし、変更後の開始予定日と終了予定日までの日付はタスク「サマリタスクA」の開始予定日から終了予定日までの日付に含まれるものとし、優先度が「高」であるタスクおよびこれと先または後のタスクとして依存関係管理テーブルで管理されるタスクの開始予定日および終了予定日は変更の対象としない。   However, it is assumed that the dates from the scheduled start date and the scheduled end date after the change are included in the dates from the scheduled start date to the scheduled end date of the task “Summary Task A”. The scheduled start date and scheduled end date of the task managed in the dependency management table as the first or subsequent task are not changed.

具体的には、制御部2はタスク「サマリタスクA」の終了予定日である「2005年2月26日」に実施予定の下位のタスクが発生するように、優先度が「並」であり、これより先のタスクとして依存関係管理テーブルで管理されるタスクの優先度も「並」であるタスク「タスクA−1」およびタスク「タスクA−2」を日程変更対象のタスクとする。この場合、制御部2はタスク管理テーブル中のタスク「タスクA−2」の終了予定日をタスク「サマリタスクA」の終了予定日である「2005年2月26日」に変更する。   Specifically, the control unit 2 has a priority “normal” so that a lower-level task scheduled to be executed occurs on “February 26, 2005” which is the scheduled end date of the task “summary task A”. Tasks “task A-1” and “task A-2” whose priorities of tasks managed in the dependency management table are “ordinary” as tasks ahead of this are set as schedule change target tasks. In this case, the control unit 2 changes the scheduled end date of the task “task A-2” in the task management table to “February 26, 2005” that is the scheduled end date of the task “summary task A”.

この変更にかかる繰り下げ日数は5日であるので、制御部2はタスク管理テーブル中のタスク「タスクA−2」の開始予定日およびこれより先のタスクとして依存関係管理テーブルで管理されるタスク「タスクA−1」の開始予定日、終了予定日を5日ずつ繰り下げた日付にそれぞれ変更する。そして制御部2はこの変更後のタスク管理テーブルをもとにガントチャートを作成し、これを表示部5に表示させる(ステップS10)。   Since the number of days to be deferred for this change is five days, the control unit 2 starts the scheduled task “task A-2” in the task management table and the task “ The scheduled start date and the end scheduled date of “task A-1” are respectively changed to dates deferred by 5 days. Then, the control unit 2 creates a Gantt chart based on the changed task management table, and displays it on the display unit 5 (step S10).

図12は、本発明の実施形態に従った作業計画作成装置1の記憶部3に記憶されるタスク管理テーブルの構成例(その4)を表形式で示す図である。このタスク管理テーブルは図10に示したタスク管理テーブルが上位のタスクの終了予定日に実施予定の下位のタスクが発生するように変更されたテーブルである。   FIG. 12 is a diagram showing a configuration example (part 4) of the task management table stored in the storage unit 3 of the work plan creation device 1 according to the embodiment of the present invention in a table format. This task management table is a table in which the task management table shown in FIG. 10 is changed so that a lower task scheduled to be executed occurs on the scheduled end date of the upper task.

図13は、本発明の実施形態に従った作業計画作成装置1が作成したガントチャートの構成例(その4)を示す図である。このガントチャートは作業計画作成装置1の制御部2が図2に示したプロジェクト管理テーブル、図12に示したタスク管理テーブル、図4に示した依存関係管理テーブルおよび図5に示した優先度管理テーブルを元に作成したガントチャートである。   FIG. 13 is a diagram showing a configuration example (part 4) of the Gantt chart created by the work plan creation device 1 according to the embodiment of the present invention. This Gantt chart is generated by the control unit 2 of the work plan creation apparatus 1 by the project management table shown in FIG. 2, the task management table shown in FIG. 12, the dependency management table shown in FIG. 4, and the priority management shown in FIG. It is a Gantt chart created based on the table.

そして、各作業工程の着手後は、オペレータが入力部4に対する予め定められた操作を行なうことで記憶部3に記憶されるタスク管理テーブル上の各タスクの開始日および終了日に日付を書き込むことができる。   Then, after starting each work process, the operator writes a date on the start date and the end date of each task on the task management table stored in the storage unit 3 by performing a predetermined operation on the input unit 4. Can do.

図14は、本発明の実施形態に従った作業計画作成装置1の記憶部3に記憶されるタスク管理テーブルの構成例(その5)を表形式で示す図である。このタスク管理テーブルは図12に示したタスク管理テーブルに対し、タスク「タスクB−1」およびタスク「タスクC−1」の着手時に当該タスクの開始日「2005年2月12日」および「2005年2月13日」がそれぞれ書き込まれ、これらのタスクの終了時に終了日「2005年2月15日」が書き込まれたテーブルである。   FIG. 14 is a diagram showing a configuration example (part 5) of the task management table stored in the storage unit 3 of the work plan creation device 1 according to the embodiment of the present invention in a table format. This task management table is different from the task management table shown in FIG. 12 when the task “task B-1” and the task “task C-1” are started, the start dates “February 12, 2005” and “2005” of the task. "February 13, 2005" is written, and the end date "February 15, 2005" is written at the end of these tasks.

図15は、本発明の実施形態に従った作業計画作成装置1が作成したガントチャートの構成例(その5)を示す図である。このガントチャートは作業計画作成装置1の制御部2が図2に示したプロジェクト管理テーブル、図14に示したタスク管理テーブル、図4に示した依存関係管理テーブルおよび図5に示した優先度管理テーブルを元に作成したガントチャートである。
ここで、オペレータが入力部4に対する予め定められた操作を行なうことで記憶部3に記憶される優先度管理テーブルの内容を変更することができる。
FIG. 15 is a diagram showing a configuration example (No. 5) of the Gantt chart created by the work plan creation device 1 according to the embodiment of the present invention. In this Gantt chart, the control unit 2 of the work plan creation apparatus 1 has the project management table shown in FIG. 2, the task management table shown in FIG. 14, the dependency management table shown in FIG. 4, and the priority management shown in FIG. It is a Gantt chart created based on the table.
Here, the content of the priority management table stored in the storage unit 3 can be changed by the operator performing a predetermined operation on the input unit 4.

図16は、本発明の実施形態に従った作業計画作成装置1の記憶部3に記憶される優先度管理テーブルの構成例(その2)を表形式で示す図である。この優先度管理テーブルは図5に示した優先度管理テーブルで管理される各タスクの優先度のうちタスク「タスクA−1」の優先度が「高」に変更されたテーブルである。   FIG. 16 is a diagram showing a configuration example (part 2) of the priority management table stored in the storage unit 3 of the work plan creation device 1 according to the embodiment of the present invention in a table format. This priority management table is a table in which the priority of the task “task A-1” is changed to “high” among the priorities of the tasks managed by the priority management table shown in FIG.

制御部2は内蔵する図示しない計時回路により現在の日付を認識する。ここでは現在の日付は2005年2月16日であるとする。制御部2は優先度管理テーブル上の優先度が変更された場合(ステップS11のYES)には、変更後の優先度が「高」であるタスクの開始予定日を現在の日付から上位のタスクの終了予定日の間でかつ現在の日付に近い日付に変更する(ステップS12)。   The control unit 2 recognizes the current date by a built-in clock circuit (not shown). Here, it is assumed that the current date is February 16, 2005. When the priority on the priority management table is changed (YES in step S11), the control unit 2 sets the scheduled start date of the task whose priority after the change is “high” to the upper task from the current date. To a date close to the current date (step S12).

具体的には、制御部2は変更後の優先度が「高」であるタスク「タスクA−1」より先のタスクとして依存関係管理テーブルで管理されるタスクがないので、このタスクの開始予定日が現在の日付「2005年2月16日」となるようにタスク管理テーブルの内容を変更する。   Specifically, since there is no task managed in the dependency management table as a task ahead of the task “task A-1” whose priority after change is “high”, the control unit 2 is scheduled to start this task. The contents of the task management table are changed so that the date is the current date “February 16, 2005”.

この変更にかかる繰り上げ日数は5日であるので、制御部2はタスク管理テーブル中のタスク「タスクA−1」の終了予定日およびこのタスクより後のタスクとして依存関係管理テーブルで管理されるタスク「タスクA−2」の開始予定日、終了予定日を5日ずつ繰り上げた日付にそれぞれ変更する。そして制御部2は、この変更後のタスク管理テーブルをもとにガントチャートを作成し、これを表示部5に表示させる。   Since the number of advance days for this change is five days, the control unit 2 manages the scheduled end date of the task “task A-1” in the task management table and the task managed in the dependency management table as a task after this task. The scheduled start date and the scheduled end date of “task A-2” are respectively changed to dates that are advanced by 5 days. The control unit 2 creates a Gantt chart based on the task management table after the change, and displays it on the display unit 5.

図17は、本発明の実施形態に従った作業計画作成装置1の記憶部3に記憶されるタスク管理テーブルの構成例(その6)を表形式で示す図である。このタスク管理テーブルは図14に示したタスク管理テーブルがタスクの優先度の変更にしたがって内容が変更されたテーブルである。   FIG. 17 is a diagram showing a configuration example (No. 6) of the task management table stored in the storage unit 3 of the work plan creation device 1 according to the embodiment of the present invention in a table format. This task management table is a table in which the contents of the task management table shown in FIG. 14 are changed in accordance with the change in task priority.

図18は、本発明の実施形態に従った作業計画作成装置1が作成したガントチャートの構成例(その6)を示す図である。このガントチャートは作業計画作成装置1の制御部2が図2に示したプロジェクト管理テーブル、図17に示したタスク管理テーブル、図4に示した依存関係管理テーブルおよび図16に示した優先度管理テーブルを元に作成したガントチャートである。このガントチャート中の括弧で括られた日付は既に経過した日付を意味する。   FIG. 18 is a diagram showing a configuration example (No. 6) of the Gantt chart created by the work plan creation device 1 according to the embodiment of the present invention. This Gantt chart is generated by the control unit 2 of the work plan creation apparatus 1 by the project management table shown in FIG. 2, the task management table shown in FIG. 17, the dependency management table shown in FIG. 4, and the priority management shown in FIG. It is a Gantt chart created based on the table. The date in parentheses in this Gantt chart means the date that has already passed.

以上のように、本発明の実施形態に従った作業計画作成装置では、各作業工程に設定された優先度を検出し、優先度の高い作業工程の開始予定日が上位の作業工程全体の開始予定日に近い日になるように当該作業工程の開始から終了までの期間を設定するので、機器故障などの予期しない事象が発生した場合でも複数の作業工程全体への影響を最小限にとどめることができる。よって実施効率のよい作業計画を作成することが可能となる。   As described above, in the work plan creation device according to the embodiment of the present invention, the priority set for each work process is detected, and the start date of the work process with a higher priority is the start of the entire work process with higher priority. Since the period from the start to the end of the work process is set so that it is close to the scheduled date, even if an unexpected event such as equipment failure occurs, the effect on the entire work process should be minimized. Can do. Therefore, it is possible to create a work plan with high implementation efficiency.

また、前記実施形態では、各作業工程の作業開始後に優先度管理テーブル上のいずれかの優先度が変更された場合にこの変更された優先度をもとにタスク管理テーブル上の作業期間を変更する構成としたが、これに限らず、例えば各作業工程の作業開始後にタスク管理テーブル上のいずれかの担当者の項目が変更された場合にこの変更された結果、タスク管理テーブル上の同一担当者が同一日に担当するタスクが複数になった場合に、この同一日に担当予定のタスクが単一となるようにタスク管理テーブルの内容を変更する構成としてもよい。   In the embodiment, when any priority on the priority management table is changed after the work of each work process is started, the work period on the task management table is changed based on the changed priority. However, the present invention is not limited to this. For example, when the item of any person in charge in the task management table is changed after the work of each work process is started, this change results in the same person in charge in the task management table. When there are a plurality of tasks that the person is in charge of on the same day, the content of the task management table may be changed so that the task scheduled to be in charge on the same day is single.

なお、この発明は前記実施形態そのままに限定されるものではなく実施段階ではその要旨を逸脱しない範囲で構成要素を変形して具体化できる。また、前記実施形態に開示されている複数の構成要素の適宜な組み合せにより種々の発明を形成できる。例えば、実施形態に示される全構成要素から幾つかの構成要素を省略してもよい。更に、異なる実施形態に亘る構成要素を適宜組み合せてもよい。   The present invention is not limited to the above-described embodiment as it is, and can be embodied by modifying the constituent elements without departing from the scope of the invention in the implementation stage. Moreover, various inventions can be formed by appropriately combining a plurality of constituent elements disclosed in the embodiment. For example, some components may be omitted from all the components shown in the embodiment. Furthermore, you may combine suitably the component covering different embodiment.

本発明の実施形態に従った作業計画作成装置の構成例を示すブロック図。The block diagram which shows the structural example of the work plan preparation apparatus according to embodiment of this invention. 本発明の実施形態に従った作業計画作成装置の記憶部に記憶されるプロジェクト管理テーブルの構成例を表形式で示す図。The figure which shows the structural example of the project management table memorize | stored in the memory | storage part of the work plan preparation apparatus according to embodiment of this invention in a table format. 本発明の実施形態に従った作業計画作成装置の記憶部に記憶されるタスク管理テーブルの構成例(その1)を表形式で示す図。The figure which shows the structural example (the 1) of the task management table memorize | stored in the memory | storage part of the work plan creation apparatus according to embodiment of this invention in a table format. 本発明の実施形態に従った作業計画作成装置の記憶部に記憶される依存関係管理テーブルの構成例を表形式で示す図。The figure which shows the structural example of the dependence relationship management table memorize | stored in the memory | storage part of the work plan creation apparatus according to embodiment of this invention in a table format. 本発明の実施形態に従った作業計画作成装置の記憶部に記憶される優先度管理テーブルの構成例(その1)を表形式で示す図。The figure which shows the structural example (the 1) of a priority management table memorize | stored in the memory | storage part of the work plan creation apparatus according to embodiment of this invention in a table format. 本発明の実施形態に従った作業計画作成装置の処理動作の一例を示すフローチャート。The flowchart which shows an example of the processing operation of the work plan preparation apparatus according to embodiment of this invention. 本発明の実施形態に従った作業計画作成装置が作成したガントチャートの構成例(その1)を示す図。The figure which shows the structural example (the 1) of the Gantt chart which the work plan preparation apparatus according to embodiment of this invention produced. 本発明の実施形態に従った作業計画作成装置の記憶部に記憶されるタスク管理テーブルの構成例(その2)を表形式で示す図。The figure which shows the structural example (the 2) of a task management table memorize | stored in the memory | storage part of the work plan creation apparatus according to embodiment of this invention in a table format. 本発明の実施形態に従った作業計画作成装置が作成したガントチャートの構成例(その2)を示す図。The figure which shows the structural example (the 2) of the Gantt chart which the work plan preparation apparatus according to embodiment of this invention produced. 本発明の実施形態に従った作業計画作成装置の記憶部に記憶されるタスク管理テーブルの構成例(その3)を表形式で示す図。The figure which shows the structural example (the 3) of a task management table memorize | stored in the memory | storage part of the work plan creation apparatus according to embodiment of this invention in a table format. 本発明の実施形態に従った作業計画作成装置が作成したガントチャートの構成例(その3)を示す図。The figure which shows the structural example (the 3) of the Gantt chart which the work plan preparation apparatus according to embodiment of this invention produced. 本発明の実施形態に従った作業計画作成装置の記憶部に記憶されるタスク管理テーブルの構成例(その4)を表形式で示す図。The figure which shows the structural example (the 4) of a task management table memorize | stored in the memory | storage part of the work plan creation apparatus according to embodiment of this invention in a table format. 本発明の実施形態に従った作業計画作成装置が作成したガントチャートの構成例(その4)を示す図。The figure which shows the structural example (the 4) of the Gantt chart which the work plan preparation apparatus according to embodiment of this invention produced. 本発明の実施形態に従った作業計画作成装置の記憶部に記憶されるタスク管理テーブルの構成例(その5)を表形式で示す図。The figure which shows the structural example (the 5) of a task management table memorize | stored in the memory | storage part of the work plan creation apparatus according to embodiment of this invention in a table format. 本発明の実施形態に従った作業計画作成装置が作成したガントチャートの構成例(その5)を示す図。The figure which shows the structural example (the 5) of the Gantt chart which the work plan preparation apparatus according to embodiment of this invention produced. 本発明の実施形態に従った作業計画作成装置の記憶部に記憶される優先度管理テーブルの構成例(その2)を表形式で示す図。The figure which shows the structural example (the 2) of the priority management table memorize | stored in the memory | storage part of the work plan creation apparatus according to embodiment of this invention in a table format. 本発明の実施形態に従った作業計画作成装置の記憶部に記憶されるタスク管理テーブルの構成例(その6)を表形式で示す図。The figure which shows the structural example (the 6) of a task management table memorize | stored in the memory | storage part of the work plan creation apparatus according to embodiment of this invention in a table format. 本発明の実施形態に従った作業計画作成装置が作成したガントチャートの構成例(その6)を示す図。The figure which shows the structural example (the 6) of the Gantt chart which the work plan preparation apparatus according to embodiment of this invention produced.

符号の説明Explanation of symbols

1…作業計画作成装置、2…制御部、3…記憶部、4…入力部、5…表示部、6…バス。   DESCRIPTION OF SYMBOLS 1 ... Work plan preparation apparatus, 2 ... Control part, 3 ... Memory | storage part, 4 ... Input part, 5 ... Display part, 6 ... Bus.

Claims (7)

複数の作業工程でなる作業単位に属する各作業工程の識別情報、前記作業工程の優先度情報およびこの作業工程の着手予定日および完了予定日を示す情報を作業工程ごとに対応付けて記憶する工程記憶手段と、
前記識別情報と関わる作業工程のうち予め定められた条件を満たす優先度情報と対応付けられて前記工程記憶手段に記憶された識別情報と関わる作業工程の着手予定日を前記作業単位の予め定められた着手予定日に近い日付に設定する設定手段と、
前記日付および前記工程記憶手段に記憶された情報をもとに前記定められた条件を満たす優先度情報と対応付けられて前記工程記憶手段に記憶される識別情報と関わる作業工程の完了予定日を計算する計算手段と、
前記工程記憶手段に記憶された作業工程の識別情報と前記設定手段により設定された当該作業工程の着手予定日と前記計算手段により計算された当該作業工程の完了予定日の情報を対応付けて出力する出力手段とを備えたことを特徴とする作業計画作成装置。
A process of storing identification information of each work process belonging to a work unit composed of a plurality of work processes, priority information of the work process, and information indicating a scheduled start date and a completion date of the work process in association with each work process. Storage means;
Among the work processes related to the identification information, the scheduled start date of the work process related to the identification information stored in the process storage means in association with priority information satisfying a predetermined condition is predetermined for the work unit. Setting means for setting a date close to the scheduled start date,
Based on the date and the information stored in the process storage means, the scheduled completion date of the work process related to the identification information stored in the process storage means in association with the priority information satisfying the predetermined condition. A calculation means for calculating;
The work process identification information stored in the process storage means, the scheduled start date of the work process set by the setting means, and information on the scheduled completion date of the work process calculated by the calculation means are output in association with each other. And an output means for performing the work plan.
前記複数の作業工程のうち作業順序の前後関係を有する複数の作業工程の識別情報を対応付けて記憶する作業順序記憶手段と、
前記優先度情報と対応付けられて前記工程記憶手段に記憶される作業工程の識別情報およびこの識別情報と関わる作業工程の着手より前に完了を要する作業工程の識別情報の組合せが前記作業順序記憶手段に記憶されているか否かを判別する判別手段とをさらに備え、
前記設定手段は、前記識別情報の組合せが前記作業順序記憶手段に記憶されていないと前記判別手段が判別した場合に、前記優先度情報と対応付けられて前記工程記憶手段に記憶される識別情報と関わる作業工程の着手予定日を前記複数の作業工程でなる作業単位の予め定められた着手予定日に設定することを特徴とする請求項1記載の作業計画作成装置。
A work order storage means for storing identification information of a plurality of work processes having a context of the work order among the plurality of work processes in association with each other;
A combination of work process identification information associated with the priority information and stored in the process storage means and work process identification information that needs to be completed before the start of the work process related to the identification information is stored in the work order storage. Determining means for determining whether or not the information is stored in the means;
The setting means, when the determination means determines that the combination of the identification information is not stored in the work order storage means, the identification information associated with the priority information and stored in the process storage means 2. The work plan creation device according to claim 1, wherein a scheduled start date of a work process related to the work schedule is set to a predetermined scheduled start date of a work unit composed of the plurality of work processes.
前記工程記憶手段は、前記作業工程の実施担当者の情報を当該作業工程の識別情報と対応付けて記憶し、
各作業工程のうち同一の実施担当者が同日に担当する複数の作業工程の識別情報が前記工程記憶手段に記憶されているか否かを判別する判別手段をさらに備え、
前記設定手段は、同一の実施担当者が同日に担当する複数の作業工程の識別情報が前記工程記憶手段に記憶されていると前記判別手段が判別した場合に、同一の実施担当者が同日に担当する作業工程の識別情報が単一となるように前記設定された着手予定日を変更することを特徴とする請求項1記載の作業計画作成装置。
The process storage means stores information on a person in charge of the work process in association with identification information of the work process,
A discriminating means for discriminating whether or not the identification information of a plurality of work processes in charge of the same execution person in charge of each work process is stored in the process storage means;
The setting means is configured such that when the identification means determines that the identification information of a plurality of work processes handled by the same person in charge on the same day is stored in the process storage means, the same person in charge performs the same day. 2. The work plan creation apparatus according to claim 1, wherein the set start date is changed so that identification information of a work process in charge is single.
前記定められた条件を満たす優先度情報と対応付けられて前記工程記憶手段に記憶された識別情報と異なる識別情報と関わる作業工程の完了予定日が前記複数の作業工程でなる作業単位の予め定められた納期と同一であるか否かを作業工程ごとに判別する判別手段をさらに備え、
前記設定手段は、前記完了予定日が前記複数の作業工程でなる作業単位の予め定められた納期と同一であると前記判別手段が判別した場合に、前記完了予定日を前記納期に近い日付に変更することを特徴とする請求項1記載の作業計画作成装置。
The scheduled completion date of the work process related to the identification information different from the identification information stored in the process storage means in association with the priority information satisfying the predetermined condition is determined in advance as a work unit including the plurality of work processes. Further comprising a discriminating means for discriminating for each work process whether or not it is the same as the delivered delivery date,
The setting means sets the scheduled completion date to a date close to the delivery date when the discrimination means determines that the scheduled completion date is the same as a predetermined delivery date of a work unit composed of the plurality of work steps. The work plan creation device according to claim 1, wherein the work plan creation device is changed.
前記工程記憶手段に記憶された優先度情報の変更入力を受け付ける入力手段をさらに備え、
前記設定手段は、前記入力手段により入力された新たな優先度が前記定められた条件を満たす優先度である場合に、この優先度情報と対応付けられて前記工程記憶手段に記憶された識別情報と関わる作業工程の着手予定日を前記複数の作業工程でなる作業単位の予め定められた着手予定日に近い日付に設定することを特徴とする請求項1記載の作業計画作成装置。
An input unit that receives a change input of priority information stored in the process storage unit;
The setting means, when the new priority inputted by the input means is a priority satisfying the predetermined condition, the identification information associated with the priority information and stored in the process storage means 2. The work plan creation apparatus according to claim 1, wherein the scheduled start date of the work process related to the work schedule is set to a date close to a predetermined scheduled start date of the work unit composed of the plurality of work processes.
前記工程記憶手段に記憶された作業工程の実施担当者の変更入力を受け付ける入力手段をさらに備え、
前記設定手段は、前記入力手段による新たな実施担当者の情報の入力後に同一の実施担当者が同日に担当する複数の作業工程の識別情報が前記工程記憶手段に記憶されていると前記判別手段が判別した場合に、同一の実施担当者が同日に担当する作業工程の識別情報が単一となるように前記設定された着手予定日を変更することを特徴とする請求項3記載の作業計画作成装置。
An input means for receiving a change input of a person in charge of the work process stored in the process storage means;
The setting means is configured to determine that the identification information of a plurality of work processes handled by the same execution person on the same day is stored in the process storage means after the input of the new execution person information by the input means. 4. The work plan according to claim 3, wherein the set scheduled start date is changed so that the identification information of the work process that the same person in charge is in charge of on the same day becomes single when the determination is made. Creation device.
複数の作業工程でなる作業単位に属する各作業工程の識別情報、前記作業工程の優先度情報およびこの作業工程の着手予定日および完了予定日を示す情報を作業工程ごとに対応付けて記憶する工程記憶手段を備えたコンピュータを、
前記識別情報と関わる作業工程のうち予め定められた条件を満たす優先度情報と対応付けられて前記工程記憶手段に記憶された識別情報と関わる作業工程の着手予定日を前記作業単位の予め定められた着手予定日に近い日付に設定する設定手段、
この設定手段により設定された日付および前記工程記憶手段に記憶された情報をもとに前記定められた条件を満たす優先度情報と対応付けられて前記工程記憶手段に記憶される識別情報と関わる作業工程の完了予定日を計算する計算手段、および
前記工程記憶手段に記憶された作業工程の識別情報と前記設定手段により設定された当該作業工程の着手予定日と前記計算手段により計算された当該作業工程の完了予定日の情報を対応付けて出力する出力手段として機能させるようにした、コンピュータ読み取り可能な作業計画作成処理プログラム。
A process of storing identification information of each work process belonging to a work unit composed of a plurality of work processes, priority information of the work process, and information indicating a scheduled start date and a completion date of the work process in association with each work process. A computer equipped with storage means
Among the work processes related to the identification information, the scheduled start date of the work process related to the identification information stored in the process storage means in association with priority information satisfying a predetermined condition is predetermined for the work unit. Setting means to set the date close to the scheduled start date,
Work related to identification information stored in the process storage means in association with priority information satisfying the predetermined condition based on the date set by the setting means and the information stored in the process storage means A calculation means for calculating a scheduled completion date of the process; an identification information of the work process stored in the process storage means; a scheduled start date of the work process set by the setting means; and the work calculated by the calculation means A computer-readable work plan creation processing program which functions as an output means for outputting information on the scheduled completion date of a process in association with each other.
JP2005360668A 2005-12-14 2005-12-14 Work plan creation device and work plan creation processing program Pending JP2007164519A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005360668A JP2007164519A (en) 2005-12-14 2005-12-14 Work plan creation device and work plan creation processing program

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005360668A JP2007164519A (en) 2005-12-14 2005-12-14 Work plan creation device and work plan creation processing program

Publications (1)

Publication Number Publication Date
JP2007164519A true JP2007164519A (en) 2007-06-28

Family

ID=38247332

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005360668A Pending JP2007164519A (en) 2005-12-14 2005-12-14 Work plan creation device and work plan creation processing program

Country Status (1)

Country Link
JP (1) JP2007164519A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012131962A1 (en) * 2011-03-30 2012-10-04 富士通株式会社 Task execution control device, task execution control system, and task execution control method
JP2017004318A (en) * 2015-06-11 2017-01-05 三菱重工業株式会社 Planning assistance system
JP2018106423A (en) * 2016-12-26 2018-07-05 カシオ計算機株式会社 Schedule creation apparatus and program
EP3680830A1 (en) * 2019-01-09 2020-07-15 Subaru Corporation Work planning device

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10244448A (en) * 1997-02-28 1998-09-14 Mitsubishi Electric Corp Production process history management system
JP2002304486A (en) * 2001-04-03 2002-10-18 Mitsubishi Electric Corp Server computer for equipment inspection and updating work management system and client computer for equipment inspection and updating work management system
JP2004139472A (en) * 2002-10-18 2004-05-13 Hitachi East Japan Solutions Ltd Work schedule planning system, work schedule planning method, program, and medium

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10244448A (en) * 1997-02-28 1998-09-14 Mitsubishi Electric Corp Production process history management system
JP2002304486A (en) * 2001-04-03 2002-10-18 Mitsubishi Electric Corp Server computer for equipment inspection and updating work management system and client computer for equipment inspection and updating work management system
JP2004139472A (en) * 2002-10-18 2004-05-13 Hitachi East Japan Solutions Ltd Work schedule planning system, work schedule planning method, program, and medium

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2012131962A1 (en) * 2011-03-30 2012-10-04 富士通株式会社 Task execution control device, task execution control system, and task execution control method
JPWO2012131962A1 (en) * 2011-03-30 2014-07-24 富士通株式会社 Task execution control device, task execution control system, and task execution control method
JP5682705B2 (en) * 2011-03-30 2015-03-11 富士通株式会社 Task execution control device, task execution control system, and task execution control method
US9342356B2 (en) 2011-03-30 2016-05-17 Fujitsu Limited Task execution control for generating context information of a user to locate available services
JP2017004318A (en) * 2015-06-11 2017-01-05 三菱重工業株式会社 Planning assistance system
JP2018106423A (en) * 2016-12-26 2018-07-05 カシオ計算機株式会社 Schedule creation apparatus and program
EP3680830A1 (en) * 2019-01-09 2020-07-15 Subaru Corporation Work planning device

Similar Documents

Publication Publication Date Title
JP5484636B1 (en) Program creation support apparatus, method, and recording medium
JP6121068B2 (en) Information system construction support tool and information system construction support program
US9600792B2 (en) Method and apparatus for generating an engineering workflow
KR20160075667A (en) Device for assisting creation of sequence program
JP2007164519A (en) Work plan creation device and work plan creation processing program
US9811071B2 (en) System construction support apparatus
JP6329038B2 (en) Information processing apparatus, process buffer calculation method, and program
JP2009157690A (en) Manufacturing process management apparatus, manufacturing process management method, program and recording medium for the same
JP2008234552A (en) Project management support device and method therefor
JP6503958B2 (en) Display information control program, method and apparatus
WO2018163421A1 (en) System configuration creation assistance device
JP2008146385A (en) Program generating device, program generation method and program for making computer execute the program
JP2007264973A (en) Commodity name input assist device, commodity name input assist method and program
JP2015111429A (en) Alteration management support apparatus, alteration management support method, and alteration management support program
JP2011044084A (en) Operation state management program and information processing apparatus
US10394943B2 (en) Numerical controller
TWI528267B (en) Programmable display device screen data editing apparatus
JP5682452B2 (en) CHANGE MANAGEMENT SUPPORT DEVICE, CHANGE MANAGEMENT SUPPORT METHOD, AND CHANGE MANAGEMENT SUPPORT PROGRAM
JP5277847B2 (en) Work management device, work management program
JP2018106423A (en) Schedule creation apparatus and program
JP2009301273A (en) Gantt chart display method, data processor and program
JP2008276412A (en) Process progress management system and process progress management method
JPH06332909A (en) Plan managing system
JP2012173983A (en) Task application configuration device
JP2010040016A (en) Screen transition design support device and program

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20081001

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20110215

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110222

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20110913