JP2005290714A - Check dam raising method for check dam - Google Patents

Check dam raising method for check dam Download PDF

Info

Publication number
JP2005290714A
JP2005290714A JP2004104079A JP2004104079A JP2005290714A JP 2005290714 A JP2005290714 A JP 2005290714A JP 2004104079 A JP2004104079 A JP 2004104079A JP 2004104079 A JP2004104079 A JP 2004104079A JP 2005290714 A JP2005290714 A JP 2005290714A
Authority
JP
Japan
Prior art keywords
check dam
sabo dam
concrete
dam
existing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2004104079A
Other languages
Japanese (ja)
Other versions
JP4204504B2 (en
Inventor
Yoshiki Izumi
佳希 泉
Tetsuo Fukumoto
哲夫 福本
Ryoichi Omiya
良一 大宮
Yoshihito Shibuya
義仁 渋谷
Mitsunori Fujita
光則 藤田
Rei Oyama
玲 尾山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Docon Co Ltd
Original Assignee
Docon Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Docon Co Ltd filed Critical Docon Co Ltd
Priority to JP2004104079A priority Critical patent/JP4204504B2/en
Publication of JP2005290714A publication Critical patent/JP2005290714A/en
Application granted granted Critical
Publication of JP4204504B2 publication Critical patent/JP4204504B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Working Measures On Existing Buildindgs (AREA)
  • Revetment (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a check dam raising method for an existing check dam, which overcomes the problems, associated with constructibility, safety, environment preservation, etc., of a conventional technology. <P>SOLUTION: This check dam raising method comprises: a first step of demolishing a wing section of the existing check dam to be subjected to levee raising; an second step of placing concrete so that a surface can be made vertical, after existing concrete and new concrete are integrated together on an inclined plane on the downstream side of the check dam by using a joint bar etc.; a third step of performing oblique boring toward foundation ground on the upstream side from a top section of the check dam, of inserting a tension member into a bored hole so as to fix it to the foundation ground, and of applying a tensile force, great enough to almost cancel out a tensile force generated by a newly planned silt pressure, to the tension member after that; and a fourth step of placing the concrete to an upper section of the check dam so that a newly planned sedimentation surface can be secured. <P>COPYRIGHT: (C)2006,JPO&NCIPI

Description

本発明は、既設の砂防ダムの嵩上げ方法に関する。   The present invention relates to a method for raising an existing sabo dam.

重力式コンクリート型式の砂防ダムの高さは、施工計画時の堆砂面の高さによって決定される。したがって、施工後に計画堆砂面の高さが上昇した場合には、新たに計画された堆砂面に対処しなければならない。従来、このような場合には、新規に砂防ダムを建設するか、或いは、新計画堆砂面に適合するように既設の砂防ダムを嵩上げしていた。   The height of the gravity concrete type sabo dam is determined by the height of the sedimentation surface at the time of construction planning. Therefore, if the height of the planned sedimentation surface increases after construction, the newly planned sedimentation surface must be dealt with. Conventionally, in such a case, a new sabo dam has been constructed or the existing sabo dam has been raised so as to conform to the newly planned sedimentation surface.

既設の砂防ダムの嵩上げは、嵩上げに要する堤体積に比べて新たに堆積可能な開発容積が大きいため、新規の砂防ダムを建設するよりも効率的な方法であるが、以下のような課題を有している。
(1)既設の砂防ダムの上流側にコンクリート体を施工するには、堆積土砂を除去する必要があるため、施工が困難である。
(2)既設の砂防ダムの下流側にコンクリート体を施工するには、砂防ダムが設けられている個所は一般的に河川が急勾配である場合が多いため、堤体断面が下流下がりな不安定な形状となる場合がある(図3においてAで図示)が、そのような場合は、堤体の体積が大きくなるうえ、施工時(特に直下流の掘削時)の安全性を確保する必要がある。
(3)減勢工長が不足し、減勢工の全面的な改修工事が発生するため、河道内の工事が多くなり、大規模な河流処理や土工を伴い、周囲環境に及ぼす影響が大きい(図3参照)。
(4)既設の砂防ダムにおいて頂部コンクリートを打継ぎして嵩上げすると、上流側に引張応力が発生するため、構造安全上問題がある。
Raising the existing sabo dam is a more efficient method than constructing a new sabo dam because the development volume that can be newly deposited is larger than the volume of the bank required for raising the dam, but the following issues are encountered: Have.
(1) In order to construct a concrete body on the upstream side of an existing sabo dam, it is necessary to remove the sediment, so construction is difficult.
(2) In order to construct a concrete body downstream of an existing sabo dam, the section where the sabo dam is installed generally has a steep river. In some cases, the shape may be stable (shown as A in FIG. 3). In such a case, the volume of the levee body becomes large, and it is necessary to ensure safety during construction (especially during excavation directly downstream). There is.
(3) Since there is a shortage of de-energizing chiefs and full-scale renovation work of de-energizing works occurs, there is a lot of construction in the river channel, which involves large-scale river flow treatment and earthwork, and has a large impact on the surrounding environment. (See FIG. 3).
(4) When the top concrete is cast and raised in an existing sabo dam, tensile stress is generated on the upstream side, which causes structural safety problems.

一方、新規の砂防ダムを建設すると、上述のような経済上の問題の他、ダム建設個所までのアクセス道路が必要になる等、環境保全上の課題も発生する。
このような状況下において、施工性、安全性、環境保全性等の課題を克服した砂防ダムの改修方法が望まれている。
On the other hand, when a new sabo dam is constructed, there are problems in environmental conservation, such as the need for an access road to the dam construction site, in addition to the economic problems described above.
Under such circumstances, a method for repairing a sabo dam that overcomes problems such as workability, safety, and environmental conservation is desired.

したがって、本発明は、従来技術における施工性、安全性、環境保全性等の課題を克服した既設の砂防ダムの嵩上げ方法を提供することを目的としている。   Accordingly, an object of the present invention is to provide a method for raising an existing sabo dam that overcomes problems such as workability, safety, and environmental conservation in the prior art.

本願請求項1に記載の砂防ダムの嵩上げ方法は、嵩上げしようとする既設の砂防ダムの袖部を取り壊す第1工程と、前記砂防ダムの下流側の傾斜面に差し筋など新旧コンクリートの一体化を施した後、面がほぼ垂直になるようにコンクリートを打設する第2工程と、前記砂防ダムの頂部から上流側の基礎地盤に向かって斜めボーリングを行い、ボーリング孔内に緊張部材を挿入して基礎地盤で固定した後、新計画堆砂圧によって生ずる引張力をほぼ打ち消す程の大きさの引張力を緊張部材に加える第3工程と、新計画堆砂面を確保するように前記砂防ダムの上部にコンクリートを打設する第4工程とを含むことを特徴とするものである。   The method for raising a sabo dam according to claim 1 of the present invention is the first step of demolishing the sleeve portion of an existing sabo dam to be raised, and the integration of old and new concrete such as incisors on the inclined surface downstream of the sabo dam. After the second step, the concrete is placed so that the surface is almost vertical, and the boring is performed obliquely from the top of the sabo dam toward the upstream foundation ground, and a tension member is inserted into the borehole. Then, after fixing on the foundation ground, the third step of applying a tensile force to the tension member to a magnitude that almost cancels the tensile force generated by the newly planned sediment pressure, and the sabo to secure the newly planned sediment surface And a fourth step of placing concrete on top of the dam.

本願請求項2に記載の砂防ダムの嵩上げ方法は、前記請求項1の方法において、前記第4工程の後、前記砂防ダムの下流側の底部に水叩き保護部を設ける工程を更に含むことを特徴とするものである。   The method for raising a sabo dam according to claim 2 of the present application further includes a step of providing a water hitting protection part at the bottom of the sabo dam downstream of the fourth step in the method of claim 1. It is a feature.

本発明によれば、既設のダム堤敷内での施工が主体となり、減勢工などダムの下流側への影響が大幅に削減されるため、コスト低減を図ることができるとともに、環境保全上からも有利である。また、頂部コンクリートを打継ぎして嵩上げしても、上流側に引張応力が生じないため、構造上も有利である。   According to the present invention, construction is mainly performed in the existing dam dam, and the influence on the downstream side of the dam, such as de-energization work, is greatly reduced. Is also advantageous. Further, even if the top concrete is cast and raised, no tensile stress is generated on the upstream side, which is advantageous in terms of structure.

次に図面を参照して、本発明の好ましい実施の形態に係る砂防ダムの嵩上げ方法について詳細に説明する。まず、嵩上げしようとする既設の砂防ダム10(長破線で図示)の袖部10aを取り壊す(図1(b)参照)。次いで、既設の砂防ダム10の下流側の下部施工を行う。具体的には、既設の砂防ダム10の下流側の傾斜面に差し筋12など新旧コンクリートの一体化を施した後、傾斜面がほぼ垂直になるようにコンクリート14を打設する(図1(c)参照)。これにより、後述する斜めボーリング作業や緊張作業を行うためのスペース(コンクリート14の上面)が確保される。   Next, a method for raising a sabo dam according to a preferred embodiment of the present invention will be described in detail with reference to the drawings. First, the sleeve part 10a of the existing sabo dam 10 (illustrated by a long broken line) to be raised is demolished (see FIG. 1B). Next, the lower construction on the downstream side of the existing sabo dam 10 is performed. Specifically, after the old and new concrete such as the reinforcing bar 12 is integrated on the inclined surface on the downstream side of the existing sabo dam 10, the concrete 14 is placed so that the inclined surface is substantially vertical (FIG. 1 ( c)). Thereby, the space (upper surface of the concrete 14) for performing the diagonal boring operation | work and tension | tensile_strength operation mentioned later is ensured.

次いで、既設の砂防ダム10の頂部から上流側の基礎地盤に向かって斜めボーリングを行い、ボーリング孔内にPC鋼材などの緊張部材16を挿入し、基礎地盤で固定した後、緊張部材16に引張力を加える(図1(d)参照)。緊張部材16に加える引張力は、新計画堆砂圧によって生ずる引張力をほぼ打ち消す程の大きさとする。   Next, oblique boring is performed from the top of the existing sabo dam 10 toward the upstream foundation ground, and a tension member 16 such as a PC steel material is inserted into the bore hole and fixed on the foundation ground, and then pulled to the tension member 16. Apply force (see FIG. 1 (d)). The tensile force applied to the tension member 16 is set to a magnitude that substantially cancels the tensile force generated by the newly planned sedimentation pressure.

次いで、新計画堆砂面を確保すべく、既設の砂防ダム10の上部にコンクリート18を打設する(図1(e)参照)。   Next, concrete 18 is placed on top of the existing sabo dam 10 in order to secure the newly planned sedimentation surface (see FIG. 1 (e)).

以上のようにして、嵩上げした砂防ダム20が完成する(図1(f)参照)。なお、嵩上げした砂防ダム20の下部は、上流側が既設の勾配のままであり、下流側がほぼ垂直な勾配となる。また、砂防ダム20の上部は、重力式コンクリート型式として所要の安全性を確保できるような形状とする。   The raised sabo dam 20 is completed as described above (see FIG. 1 (f)). In the lower part of the raised sabo dam 20, the upstream side remains the existing slope, and the downstream side has a substantially vertical slope. Moreover, the upper part of the sabo dam 20 is made into the shape which can ensure required safety | security as a gravity type concrete type.

図2は、本発明の嵩上げ方法を施した砂防ダム20の全体図、並びに、砂防ダム20の底面における反力を示した図である。すなわち、図2(b)は、既設の砂防ダムの旧計画堆砂圧による反力図(下流側:圧縮力C1 )、図2(c)は、嵩上げした砂防ダム20の新計画堆砂圧による反力図(下流側:圧縮力C2 、上流側:T1 )、図2(d)は、緊張部材16の引張力による反力図(上流側:圧縮力C3 ≒T1 )、図2(e)は、嵩上げした砂防ダム20の合成反力図(下流側:圧縮力C4 =C1 +C2 )である。図2(e)から分かるように、砂防ダム20の底面においては引張力は生じない。 FIG. 2 is an overall view of the sabo dam 20 subjected to the raising method of the present invention and a diagram showing a reaction force on the bottom surface of the sabo dam 20. That is, FIG. 2B is a reaction force diagram (downstream side: compressive force C 1 ) due to the old planned sedimentation pressure of the existing sabo dam, and FIG. 2C is a new planned sedimentation of the raised sabo dam 20. FIG. 2D is a reaction force diagram (upstream side: compression force C 3 ≈T 1 ) of the tension member 16. FIG. 2D is a reaction force diagram due to pressure (downstream side: compression force C 2 , upstream side: T 1 ). FIG. 2 (e) is a composite reaction diagram (downstream side: compression force C 4 = C 1 + C 2 ) of the raised sabo dam 20. As can be seen from FIG. 2 (e), no tensile force is generated on the bottom surface of the sabo dam 20.

なお、嵩上げした砂防ダム20においては、減勢方式が自由落下に近い形状になるため、砂防ダム20の下流側の底部に、水叩き保護部22を設けるのが好ましい場合がある。水叩き保護部22としては、コンクリート塊、ブロックなどが用いられる。   In addition, in the raised sabo dam 20, since the depressurization method has a shape close to free fall, it may be preferable to provide the water hitting protection part 22 at the bottom of the sabo dam 20 on the downstream side. A concrete lump, a block, or the like is used as the water hitting protection unit 22.

また、管理上、緊張部材16に再緊張作業を伴う場合には、緊張部材16の上部延長上に作業孔を設置することにより作業可能となる。   In addition, for management purposes, when the tension member 16 is accompanied by a re-tensioning operation, the operation can be performed by installing a work hole on the upper extension of the tension member 16.

本発明は、以上の発明の実施の形態に限定されることなく、特許請求の範囲に記載された発明の範囲内で、種々の変更が可能であり、それらも本発明の範囲内に包含されるものであることはいうまでもない。   The present invention is not limited to the above-described embodiments, and various modifications can be made within the scope of the invention described in the claims, and these are also included in the scope of the present invention. Needless to say, it is something.

本発明の好ましい実施の形態に係る砂防ダムの嵩上げ方法についての一連の工程を模式的に示した概略図である。It is the schematic which showed typically a series of processes about the raising method of the sabo dam which concerns on preferable embodiment of this invention. 図2(a)は、図1の嵩上げ方法を施した砂防ダムの全体図、図2(b)〜図2(e)は、嵩上げ方法を施した砂防ダムの底面における各ケースでの反力を示した図である。2A is an overall view of the sabo dam subjected to the raising method of FIG. 1, and FIGS. 2B to 2E are reaction forces in each case on the bottom surface of the sabo dam subjected to the raising method. FIG. 従来の砂防ダムの嵩上げ計画の概念を示した図である。It is the figure which showed the concept of the raising plan of the conventional sabo dam.

符号の説明Explanation of symbols

10 既設の砂防ダム
10a 袖部
12 差し筋
14 下部コンクリート
16 緊張部材
18 上部コンクリート
20 嵩上げされた砂防ダム
22 水叩き保護部
DESCRIPTION OF SYMBOLS 10 Existing sabo dam 10a Sleeve part 12 Reinforcing bar 14 Lower concrete 16 Tension member 18 Upper concrete 20 Raised sabo dam 22 Water hitting protection part

Claims (2)

砂防ダムの嵩上げ方法であって、
嵩上げしようとする既設の砂防ダムの袖部を取り壊す第1工程と、
前記砂防ダムの下流側の傾斜面に差し筋など新旧コンクリートの一体化を施した後、面がほぼ垂直になるようにコンクリートを打設する第2工程と、
前記砂防ダムの頂部から上流側の基礎地盤に向かって斜めボーリングを行い、ボーリング孔内に緊張部材を挿入して基礎地盤で固定した後、新計画堆砂圧によって生ずる引張力をほぼ打ち消す程の大きさの引張力を緊張部材に加える第3工程と、
新計画堆砂面を確保するように前記砂防ダムの上部にコンクリートを打設する第4工程と、
を含むことを特徴とする方法。
A method for raising a sabo dam,
A first step of demolishing a sleeve of an existing sabo dam to be raised;
A second step of placing the concrete so that the surface is substantially vertical after integrating the old and new concrete, such as incisors, on the inclined surface on the downstream side of the sabo dam;
After drilling diagonally from the top of the sabo dam toward the upstream foundation ground, inserting a tension member into the borehole and fixing it with the foundation ground, the tensile force generated by the newly planned sedimentation pressure is almost canceled. A third step of applying a tensile force of magnitude to the tension member;
A fourth step of placing concrete on top of the sabo dam so as to secure the newly planned sand surface;
A method comprising the steps of:
前記第4工程の後、前記砂防ダムの下流側の底部に水叩き保護部を設ける工程を更に含むことを特徴とする請求項1に記載の方法。 The method according to claim 1, further comprising a step of providing a water hitting protection portion at a bottom portion on the downstream side of the sabo dam after the fourth step.
JP2004104079A 2004-03-31 2004-03-31 Raising the sabo dam Expired - Fee Related JP4204504B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004104079A JP4204504B2 (en) 2004-03-31 2004-03-31 Raising the sabo dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004104079A JP4204504B2 (en) 2004-03-31 2004-03-31 Raising the sabo dam

Publications (2)

Publication Number Publication Date
JP2005290714A true JP2005290714A (en) 2005-10-20
JP4204504B2 JP4204504B2 (en) 2009-01-07

Family

ID=35323963

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004104079A Expired - Fee Related JP4204504B2 (en) 2004-03-31 2004-03-31 Raising the sabo dam

Country Status (1)

Country Link
JP (1) JP4204504B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020094377A (en) * 2018-12-12 2020-06-18 一般財団法人砂防フロンティア整備推進機構 Method of making slit in drainage culvert, and erosion control dam having drainage culvert
CN112813931A (en) * 2021-02-05 2021-05-18 中国电建集团华东勘测设计研究院有限公司 Heightening mixed dam structure combined with built earth-rock dam and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020094377A (en) * 2018-12-12 2020-06-18 一般財団法人砂防フロンティア整備推進機構 Method of making slit in drainage culvert, and erosion control dam having drainage culvert
JP7194576B2 (en) 2018-12-12 2022-12-22 一般財団法人砂防フロンティア整備推進機構 Slitting method for drainage culvert and Sabo dam having the drainage culvert
CN112813931A (en) * 2021-02-05 2021-05-18 中国电建集团华东勘测设计研究院有限公司 Heightening mixed dam structure combined with built earth-rock dam and construction method thereof

Also Published As

Publication number Publication date
JP4204504B2 (en) 2009-01-07

Similar Documents

Publication Publication Date Title
CN104405403B (en) A kind of control tunneling greatly across the construction method of subway station surrouding rock deformation
JP6936613B2 (en) Masonry reinforcement structure and reinforcement method
JP5274145B2 (en) Cast-in-place pile and its construction method
CN102162255A (en) Method for reinforcing existing pile foundation in collapsed loess area by slip casting
EA031926B1 (en) Method for forming a pillar part and reinforcing adjacently constructed parallel tunnels with reinforcing rods
CN109235490B (en) Retaining wall and its construction method
CN105862862B (en) A kind of large diameter pile buries hammer Refloatation method
JP2009235809A (en) Construction method for dismantlement and removal of underground structure having foundation pile
KR101109520B1 (en) Construction method of soil barrier using steel pipe pile
CN104775433A (en) Pile extracting construction method
CN106812131B (en) A kind of permanent sheet pile underground structure and its construction method
KR100898969B1 (en) Tunnel excavation method using sheet pile and tunnel structure
JP4373824B2 (en) Joining method of cast-in-place pile and steel pipe column
Shong et al. Design & construction of micropiles
JP4204504B2 (en) Raising the sabo dam
JP2000170149A (en) Forming method for underground pile and equipment therefor
CN116220733B (en) Internal anchoring combined protection technology for lower existing tunnel under top unloading
Porterfield et al. Soil nailing field inspectors manual-soil nail walls
CN100557144C (en) A Method for Removing Construction Obstacles of Bored Pile
CN107747315A (en) A kind of recycling method of shaped steel component for pattern foundation pit supporting structure
KR20130002797A (en) Reinforced concrete pile construction method for which steel pipe casing structure for steel pipe casing recovery this were used
CN104018492A (en) Bamboo reinforced concrete pile
Lajer et al. Deep foundation for high rise in tricky soil conditions and surroundings in Scandinavia–Walkthrough of various high‐rise projects from initial geology to final execution and everything in between
JP2006348690A (en) Retrofitting method for base isolation of existing building
JP2015101880A (en) Structure of retaining wall and construction method for the same

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070207

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080812

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080829

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080908

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20081001

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20081014

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111024

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4204504

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111024

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20141024

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees